Académique Documents
Professionnel Documents
Culture Documents
https://www.facebook.com/waleed.naggar
Agenda
Definitions
https://www.facebook.com/waleed.naggar
https://www.facebook.com/waleed.naggar
Definitions (1)
Profit = Revenue Costs
Profit Margin = Profit / Revenue
Cash flow refers to the movement of cash into or
out of the project.
Direct costs are costs that can be directly related
to producing the deliverable of the project:
Salaries, cost of hardware & software purchased
specifically for the project
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
Definitions (2)
Indirect costs are costs that are not directly related
to the deliverable of the project, but are indirectly
https://www.facebook.com/waleed.naggar
Definitions (3)
Sunk cost is money that has been spent in the
past; when deciding what projects to invest in or
continue, you should not include sunk costs
To continue funding a failed project because a
great deal of money has already been spent
https://www.facebook.com/waleed.naggar
Definitions (4)
Variable Costs: change with the amount of
production (cost of material).
Fixed Costs: do not change with production
(rent, setup costs, etc.)
Net present value: the total present value (PV) of
https://www.facebook.com/waleed.naggar
Definitions (5)
Internal Rate of Return: interest rate received for
an investment consisting of payments and
income that occur at regular periods
Opportunity Cost: The cost given up by selecting
one project over another.
https://www.facebook.com/waleed.naggar
Payback Period
Year
Project A Project B
0
1
2
3
4
-1,000
500
400
300
100
-1,000
100
300
400
600
https://www.facebook.com/waleed.naggar
Project A
https://www.facebook.com/waleed.naggar
10
Project B
https://www.facebook.com/waleed.naggar
11
https://www.facebook.com/waleed.naggar
12
Example of PV Calculation
0
100
300
300
-50
10%
90.91
247.93
225.39
-34.15
530.08 = PV
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
13
https://www.facebook.com/waleed.naggar
14
Scope Baseline
Schedule Baseline
Other Information (risks, communication, etc.)
2.Project Charter
3.Enterprise Environmental Factors
4.Organizational Process Assets
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
15
3. Meetings
https://www.facebook.com/waleed.naggar
16
https://www.facebook.com/waleed.naggar
17
https://www.facebook.com/waleed.naggar
18
Scope Statement
WBS
WBS Dictionary
4. Project Schedule
https://www.facebook.com/waleed.naggar
19
Market Conditions
Published Commercial Data
7. Organizational Process Assets
Cost Estimating Policies
Cost Estimating Templates
Historical Information
Lessons Learned
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
20
3. Parametric Estimating
4. Bottom-up estimating
5. Three-point Estimating
https://www.facebook.com/waleed.naggar
21
https://www.facebook.com/waleed.naggar
22
Estimation Assumptions
Constraints
https://www.facebook.com/waleed.naggar
23
Quiz
Analogous estimating:
A. uses bottom-up estimating techniques.
B. is used most frequently during the executing
processes of the project
C. uses top-down estimating techniques.
D. uses actual detailed historical costs.
https://www.facebook.com/waleed.naggar
24
Quiz
The cost of choosing one project and giving up
another is called:
A. fixed cost.
B. sunk cost.
https://www.facebook.com/waleed.naggar
25
https://www.facebook.com/waleed.naggar
26
2. Scope Baseline
3. Activity Costs Estimates
4. Basis of Estimates
5. Project Schedule
6. Resource Calendars
7. Risk Register
8. Agreements
9. Organizational Process Assets
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
27
2. Reserve Analysis
3. Expert Judgment
4. Historical Relationships
5. Funding Limit Reconciliation
https://www.facebook.com/waleed.naggar
28
https://www.facebook.com/waleed.naggar
29
https://www.facebook.com/waleed.naggar
30
Cost Baseline
https://www.facebook.com/waleed.naggar
31
5. Reserve Analysis
6. Project Management Software
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
32
1. Cost Baseline
2. Cost Management Plan
https://www.facebook.com/waleed.naggar
33
https://www.facebook.com/waleed.naggar
34
EVM Terms
https://www.facebook.com/waleed.naggar
35
EVM Formulas
https://www.facebook.com/waleed.naggar
36
https://www.facebook.com/waleed.naggar
37
EVM Example
PV = $42,000
EV = $38,000
AC = $48,000
CV = EV AC
= $38,000 - $48,000 = -$10,000
CV% = CV / EV
= -$10,000 / $38,000 = -26%
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
38
SV = EV PV
= $38,000 - $42,000 = -$4,000
SV% = SV / EV
= -$4,000 / $42,000 = -9.5%
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
39
CPI= EV / AC
= $38,000 / $48,000 = 0.79
For each $1 spent, a work worth $0.79 was
actually performed.
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
40
https://www.facebook.com/waleed.naggar
41
Estimate at Completion
https://www.facebook.com/waleed.naggar
42
Variance at Completion
VAC = BAC - EAC
(BAC=$80,000)
= $80,000 - $101,265 = -$21,265
Based on past performance, project will
exceed planned budget by $21,265
ETC= EAC - AC
(BAC=$80,000)
= $101,265 $48,000 = $53,265
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
43
https://www.facebook.com/waleed.naggar
44
Case 1
PV = $ 1,860
EV = $ 1,860
AC = $ 1,860
https://www.facebook.com/waleed.naggar
45
Case 2
PV = $ 1,900
EV = $ 1,500
AC = $ 1,700
Spending Variance
= EV AC = - $ 200
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
46
Case 2
PV = $ 1,900
EV = $ 1,500
AC = $ 1,700
SV
= EV PV = - $ 400
SV % = SV / PV x 100 = - 21 %
https://www.facebook.com/waleed.naggar
47
Case 2
PV = $ 1,900
EV = $ 1,500
AC = $ 1,700
CV
= EV AC = - $ 200
CV % = CV / EV x 100 = -13 %
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
48
Case 2
PV = $ 1,900
EV = $ 1,500
AC = $ 1,700
SPI = EV / PV = $ 0.79
CPI = EV / AC = $ 0.88
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
49
Case 2
PV = $ 1,900
EV = $ 1,500
AC = $ 1,700
https://www.facebook.com/waleed.naggar
50
Case 3
PV = $ 2,600
EV = $ 2,400
AC = $ 2,200
https://www.facebook.com/waleed.naggar
51
Case 3
PV = $ 2,600
EV = $ 2,400
AC = $ 2,200
SPI = 0.92
SV = - $ 200; SV % = - 8 %
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
52
Case 3
PV = $ 2,600
EV = $ 2,400
AC = $ 2,200
CV = $ 200; CV % = 8 %
CPI = 1.09
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
53
Case 4
PV = $ 1,700
EV = $ 1,500
AC = $ 1,500
SV = - $ 200; SV % = - 12 %
SPI = 0.88
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
54
Case 4
PV = $ 1,700
EV = $ 1,500
AC = $ 1,500
CV = $ 0.00
CPI = 1.00
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
55
Case 5
A positive scenario;
right? But is it
because we are outperforming our
learning-curve
standards or because
we planned too
pessimistically?
PV = $ 1,400
EV = $ 1,600
AC = $ 1,400
https://www.facebook.com/waleed.naggar
56
Case 5
PV = $ 1,400
EV = $ 1,600
AC = $ 1,400
SPI = 1.14
CPI = 1.14
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
57
Case 5
...work is ahead of
schedule by 14
percent and
under-running cost
by 12.5%.
PV = $ 1,400
EV = $ 1,600
AC = $ 1,400
SV = $ 200; SV % = 14 %
CV = $ 200; CV % = 12.5 %
PMP - Project Cost Management
https://www.facebook.com/waleed.naggar
58
Text
Text
Text
https://www.facebook.com/waleed.naggar
59
Text
Text
Text
https://www.facebook.com/waleed.naggar
60