Académique Documents
Professionnel Documents
Culture Documents
CONTENTS
INTRODUCTION
1. GENERAL APPROACH TO A WORKOVER
2. TYPES OF INTERVENTION
2.1 Internal Tubing Problems
2.2 Tubing Retrieval Problems
3. WORKOVER EQUIPTMENT AND
TECHNIQUES
3.1 Internal Through Tubing Operations
3.2 Tubing Retrieval Equiptment
3.2.1 Concentric Workover Unit
4. SELECTION OF A WORKOVER RIG
5. WORKOVER BENEFIT ANALYSIS
5.1 Evaluation Considerations
5.2 Economic Benefit
5.2.1 Absolute Measures of Profitability
5.2.2 Measures which consider Time Value of Cash
Flow
SUMMARY
EXERCISE
10
1
LEARNING OBJECTIVES:
Having worked through this chapter the Student will be able to:
Introduction to the variable nature of well interventions.
Describe the inherent risks and need for careful diagnostics, planing and
supervision.
Describe the economic implications of a workover in terms of the need to protect
the well production or injection capacity.
List and describe the equipment and operational concepts involved in coiled tubing
and hydraulic workover units.
Well Intervention
10
INTRODUCTION
A production or injection well may be designed for maximum efficiency but will
always be subject to failure or declining performance. These "failures" can be
attributed to either:
(1) Mechanical malfunction or the need for redesign of the complete equipment to
adapt to changing reservoir conditions
(2) Changes in reservoir performance or flow characteristics as a result of reservoir
dynamics and recovery mechanism.
Interventions to address these changes are complex for the following reasons:(1) The completion is a complex mechanical system comprising components
whose operation is inter-dependent
(2) The service environment can be extremely hostile:
High Pressure
High Temperature
Corrosive Fluids
Severe Stresses both hydraulic and mechanical which can be cyclical
1
In addition, it is also crucial that the economic benefits of the operation be fully
appraised and evaluated to make sure that the option selected to correct the problem
will yield the best probable economic benefit to the company.
Well
Well
Data
Data
Problem
Problem
Identification
Identification
Reservoir
Reservoir
Data
Data
Identification
Identification
of
of
Alternative
Alternative
Remedial
Remedial
Measures
Measures
Economic
Economic
Evaluation
Evaluation
Technical
Technical
Evaluation
Evaluation
Planning
Planning
and
and
Implementation
Implimentation
of Workover
of Workover
Workover
Workover
Monitoring
Monitoring
and Evaluation
and Evaluation
2. TYPES OF INTERVENTION
Primarily in this chapter we are concerned with problems associated with the
completion string. Problems associated with the reservoir can be investigated and
evaluated using production logging and well test techniques.
In general, problems associated with the completion string can be classified as
follows:
Problems which arise in the tubing bore and which can be corrected by
concentric through tubing operations
Figure 1
A Logical Approach to
Planning and Conducting a
Workover
Well Intervention
10
2.
The installation operation of, retrieval or equipment within the tubing bore
3.
Concentric tubing
1
1 to 7". In the North Sea for example the large diameter production tubing allows and
physical access to larger diameter coil which is also required to maintain high annular
velocity and hence coil of 2 - 23/4" OD being preferred. The major benefit of the
technique is that it allows concentric operations to be conducted in the tubing. These
operations can include:(a) Mechanical operations whereby devices within the tubing, can be operated
(hydraulically or mechanically), retrieved or inserted.
(b) Circulation operations such as the placement of acid or other treatment
chemicals, or cement to squeeze out at perforated intervals. In addition CT. can
be used as a velocity string to extend the life of a production well where it is
dominated by slippage.
The general configuration of a coiled tubing unit is shown in Figure 2. It consists of:(1) A reel of continuous tubing
(2) A tubing straightener or gooseneck
(3) An injector head which will drive the tubing into the well even if it is under
pressure
(4) The work tools
For offshore applications the system is supplied as a series of fluid mounted modules.
Coiled tubing can assist in conducting the following range of operations: Circulation of fluid placement within the wellbore
Retrieval and installation of wireline or through tubing equipment
Drilling or milling operations
E Mast
A Tractor Pumper
F Injector Head Assembly
B Operators Cab
C Reel (with 1.75'' OD CT wrapped) G Blowout Preventor Stack
from top to bottom:
D Power Sysyem including:
2 blind/shear rams
reel power system
slip rams
hydraulic power system
pipe rams
BOP operating system
C
G
B
A
Figure 2
Schematic of Coiled Tubing
Facility
Well Intervention
10
Coiled tubing is available in a range of sizes and specifications. Some of the smaller
sized coiled tubing is shown in Table 1.
Description
Engine
Reel Capacity
Table 1
Coiled Tubing
Specifications
Service
DNV Cerified
DNV Cerified
Trailer
Truck
Trailer
Truck
Skid/Trailer
Skid/Trailer
Mounted
Mounted
Mounted
Mounted
Mounted
Mounted
1-inch
1-inch
1-inch
1-inch
1 1/4-inch
1 1/2-inch
O.D.TBG.
O.D.TBG.
O.D.TBG.
O.D.TBG.
O.D.TBG.
O.D.TBG.
140
320
280
280
228
228
17,500
14,000
15,000
15,000
17,500
15,000
5334M
4267 M
4527M
4527M
5334M
4527 M
160
220
160
220
220
220
48,77 MPM
67,05 MPM
48,77 MPM
67,05 MPM
67,05 MPM
67,05 MPM
12,000
12,000
24,000
24,000
24,000
24,000
5488 Kg
5448 Kg
10896 Kg
10896 Kg
10896 Kg
10896 Kg
5,000
5,000
5,000
5,000
5,000
5,000
352 Kg/Cm2
352 Kg/Cm2
352 Kg/Cm2
352 Kg/Cm2
352 Kg/Cm2
352 Kg/Cm2
STD/H2S
STD/H2S
STD/H2S
STD/H2S2
STD/H2S2
STD/H2S2
1
Equipment available to conduct such operations could be either:(a) A full drilling rig with the necessary BOP equipment and the capacity to pull
tubing.
(b) A concentric unit which can be installed over the producing well.
Work
Platform
Control Panel
Hydraulic Bar
Clamp
Travelling
Slips
Power
Rotating
Head
Counter
Balance
Valves
Two or Four
Operating
Cylynders
Counter Balance
Winch
Hydraulic
Bypass
Splined
Telescoping
Guide Tubes
Welded
Pumping
Telescoping
Mast
Stationary
Slips
Window-For
Stripper Bowl
or Annular Bop
Hanger Flange
Blowout
Preventor
Stack
(Variable Designs
available)
Figure 3
Hydraulic Workover Mast
Well Intervention
10
POW.ROT
HEAD
UNIT
Table 2
Hydraulic Workover Unit
Specifications (Halliburton)
BORE SIZE
NO. OF
STROKE
REGULAR
REGEN
SNUB
MAX. TORQUE
HYD.
LENGTH
LIFT
LIFT
IN.
CYLIN.
FT.
LBS.
LBS.
LBS
AT 3000 PSI
120k
4 1/16
200k
7 1/16
120,000
60,000
600,000
235
200,000
100,000
100,000
4800
200k
11 1/8
250k
7 1/16
200,000
100,000
100,000
6400
12
250,000
108,000
100,000
400k
11 1/8
4800
400,000
200,000
200,000
400k
11 1/8
6400
12
400,000
200,000
165,000
600k
11 1/8
6400
600,000
300,000
300,000
6400
FT-LB
5. WORKOVER BENEFITS
In conducting a cost benefit analysis of the proposed workover we must consider the
following factors:
1
(a) Enhancement or restoration of safety
(b) Reduction in operating costs
(c) Accelerate the production revenue
(d) Increase the ultimate recovery
10
Well Intervention
10
+ve
B
Payback
Period
A
Time
-ve
Figure 4
The Payback Period
11
Project 1
Project 2
IRR 1
IRR 2
Discount Rate
NPV Profile for Comparing Projects
(b)
(c)
In terms of benefits we look at the value of the incremental recovery. This technique
allows alternative interest opportunities to be considered and the level of risk to be
incorporated.
The idealised benefit response from a workover is shown in Figure 6.
12
Figure 5
Internal Rate of Return
Figure 6
Idealised Fluid Recovery
Benefit Profile Resulting
from a Workover
Deferred
Production
Minimum
Economic
Flowrate
Workover Period
Well Intervention
10
Cumulative
Incremental
Production
Time (t)
SUMMARY
In this section we have reviewed workover or intervention operations. In general the
following points should be drawn.
(1) Intervention can be conducted through tubing or require tubing retrieval
depending on
the nature of the problem.
(2) A range of optional solutions exist for most problems.
(3) We are dealing with a live well and hence safety and protecting the productivity /
injectivity index are important considerations.
(4) Data is essential to the diagnosis of problems, as well as the collation and
evaluation of options both technically and economically.
13
1
EXERCISE 1.
WELL PROBLEMS AND WORKOVERS
For the attached completions, identify:
(a) The principal potential sources of the problem where a build up in annular
pressure is observed in completion (a) and (c).
(b) Assuming that we wish to pull the tubing from the well how would you service
the well for the completions depicted in figure (b) and (d).
4 1/2" Tubing
2 3/8" Tubing
4 1/2" SSSV
7" Tubing
Packer / tailpipe
9 5/8" Packer (12730' MD)
2.125" Nipple
Perforated joints
1.87" Nipple
Wireline entry guide
14
Figure (a)
Well Intervention
10
BPV Profile
1/
4"Control
line
ft flow coupling
Nipple
Sliding sleeve
ft flow coupling
Top of PBR
Bottom of PBR
Liner packer
Liner hanger
9 5/8" 47 lb/ft
Casing
Perforated intervals
Figure (b)
15
ANNULUS
PRODUCTION
Length (m) Depth (m) Length (m) Depth (m)
0.18
201.50
0.41
201.88
0.48
202.09
23.28
1.80
202.55
225.83
2.85
227.63
4.07
230.48
1.60
0.24
234.55
236.35
2522.43
236.59
24
30
1.82
1.18
1.72
12.87
2759.02
2759.26
2760.56
2762.38
2763.66
2765.26
0.18
201.50
0.41
201.68
0.43
0.30
202.09
203.52
1.55
203.82
0.34
0.38
0.15
205.37
205.71
206.9
206.24
Annulus string
14.17
2778.15
3.64
206.60
2792.32
2796.16
1.76
4
.81
3001.66
3003.76
3003.76
69.86
1.80
0.39
3.08
0.30
1.62
3005.57
3075.43
3077.23
3077.62
3080.70
3081.00
3082.82
Perforations (mBRT)
3106.3 - 3151.0m
16
Figure (c)
Subsea oil producer.
Well Intervention
10
Figure (d)
Large bore oil producer.
17
1
EXERCISE 2.
PROBLEM WELL DESIGN
1. A well having been on production for several years starts to show signs of declining
production rate. There are no real signs of a change in water cut. List some of the
probable causes and what other indicators would assist in your analysis of the
problem.
2. A well starts to cut water at very high rates, what would you expect to see happening
progressively in the future in terms of flowrates? Any other changes that you may
wish to watch for?
3. After workover in which the well was killed, the well only flowed at 50% of its preworkover rate. What questions would you ask regarding the kill procedure, fluids
used and the leak off history?
4. For the following damage scenarios, how would you expect the well to respond in
terms of oil production rate to clean up post-workover:
(a) Sensitive sandstone completed with a low salinity workover fluid.
(b) Loss of large volume of water based fluid to a clean oil bearing sandstone.
(c) Use of calcium carbonate kill slurry.
(d) Leak off of fluid into the reservoir and creating an emulsion with the crude oil.
18
Well Intervention
10
SOLUTION TO EXERCISE 1
4 1/2" Tubing
2 3/8" Tubing
4 1/2" SSSV
Leak at side pocket mandrel
3 1/2" Side pocket mandrel
2.75" Nipple
7" Tubing
Seal assembly
3 1/2" Tubing plus
4 x 2 7/8" Side pocket mandrels
2.25" Nipple, c/w orifice valve (12560'MD)
Seal or packer leak coupled
Perforated joint with 7" liner hanger leak
5 1/2 " Seal assembly
Figure (a)
Solution
Packer / tailpipe
9 5/8" Packer (12730' MD)
2.125" Nipple
Perforated joints
1.87" Nipple
Wireline entry guide
19
1
ANNULUS
PRODUCTION
Length (m) Depth (m) Length (m) Depth (m)
0.18
201.50
0.41
201.88
0.48
202.09
23.28
1.80
202.55
225.83
2.85
227.63
4.07
230.48
1.60
0.24
234.55
236.35
2522.43
236.59
24
30
1.82
1.18
1.72
12.87
2759.02
2759.26
2760.56
2762.38
2763.66
2765.26
0.18
201.50
0.41
201.68
0.43
0.30
202.09
203.52
1.55
203.82
Flow coupling
0.34
0.38
0.15
205.37
205.71
206.9
206.24
Annulus string
Flow coupling
SSSV Control
line failure
Flow coupling
x/o coupling 4 1/2" VAM
x 6 1/2" VAM
Tubing joint /
coupling failure
S.S.D leak
ELTSR leak
14.17
2778.15
3.64
206.60
2792.32
2796.16
1.76
4
.81
3001.66
3003.76
3003.76
69.86
1.80
0.39
3.08
0.30
1.62
3005.57
3075.43
3077.23
3077.62
3080.70
3081.00
3082.82
Packer leak
Flow coupling
Nipple 3.888"R
Flow coupling
Perforations (mBRT)
3106.3 - 3151.0m
20
Figure (c)
Solution
Well Intervention
10
Length
Max. I.D.
Min. I.D.
BPV Profile
1/
4"Control
line
ft flow coupling
Nipple
Sliding sleeve
ft flow coupling
Top of PBR
Bottom of PBR
Liner packer
Liner hanger
9 5/8" 47 lb/ft
Casing
Perforated intervals
Figure (b)
Solution
Open SSD and reverse circulate tubing holding PBH > PRES.
Run and set threw tubing bridge plug.
Observe well and set BPV in tubing hanger.
Remove Xmas tree and nipple up BOP.
Commence pulling tubing.
21
1
Dual encapsulated 1/4" monel
control lines
7", 32#, SEU C75 Tubing
7" WLR Dual line SSSV (OTIS
"DB" ball) at C.2000' BDF.
I.D. 3.34".
5 1/2", 23#, SEU tubing
Figure (d)
Solution
Well Intervention
5.
6.
7.
8.
9.
10
SOLUTION TO EXERCISE 2
1. Pressure depletion
Fines migration
Asphaltine / wax deposition
Scaling in perforations and tubing.
Indications
Solids production in fluid
Chemical analysis of oil.
2.
Tubing will load up with water - high hydrostatic head pressure drop / reduced
flowrate.
Production of fines from connate water film.
Possible destabilisation of sand / dissolution of calcite cement yielding sand
production with possible decrease in slurry factors and higher liquid production
rates.
(b)
(c)
(d)
23