Vous êtes sur la page 1sur 23

Standard construction document CCDC

22
2002

a guide to construction
surety bonds

Canadian Construction Documents Committee

TABLE OF CONTENTS
INTRODUCTION
1. WHAT IS SURETYSHIP?
1.1 HISTORY
1.2 WHAT IS A SURETY BOND
1.3 TYPES OF CONSTRUCTION SURETY BONDS
1.4 DEFINITIONS
1.5 HOW SURETY BONDS DIFFER FROM OTHER FORMS OF SECURITY?
2. HOW SURETYSHIP WORKS
2.1 THE THREE Cs OF SURETYSHIP
2.2 INDEMNITY AGREEMENTS
2.3 HOW TO GET THE BOND?
2.4 WHAT DOES THE BOND COST?
2.5 VALUE ADDED TAXES
3. BOND FORMS
3.1 CCDC 220 BID BOND
3.2 CCDC 221 PERFORMANCE BOND
3.3 CCDC 222 LABOUR AND MATERIAL PAYMENT BOND

The Canadian Construction Documents Committee is a joint committee composed of owners and
representatives appointed by:
The Association of Consulting Engineers of Canada
The Canadian Construction Association
Construction Specifications Canada
The Royal Architectural Institute of Canada
Committee policy and procedures are directed and approved by the constituent organizations.
This document has been endorsed by each of the above organizations and the Surety Association
of Canada.
Enquiries should be directed to:
The Secretary
Canadian Construction Documents Committee
Suite 400
75 Albert Street
Ottawa, Ontario
K1P 5E7
Tel: (613) 236-9455
Fax: (613) 236-9526
www.ccdc.org
or
The President
Surety Association of Canada
6299 Airport Road
Suite 709
Mississauga, Ontario
L4V 1N3
Tel; (905) 677-1353
Fax; (905) 677-3345
www.surety-canada.com.
CCDC guides are products of a consensus-building process aimed at balancing the interests of all
parties on the construction project. They reflect recommended industry practices. Readers are
cautioned that the guides do not deal with any specific fact situation or circumstance. CCDC
guides do not constitute legal or other professional advice. The CCDC and its constituent
member organizations do not accept any responsibility or liability for loss or damage which may
be suffered as a result of their use and interpretation.
CCDC Copyright 2002
Must not be copied in whole or in part without the written
permission of the CCDC.

Standard Construction Document 2002

INTRODUCTION
The purpose of this guide is to help the construction and business communities in Canada better
understand surety bonds and the suretyship process. This guide was prepared by the Surety SubCommittee of the Canadian Construction Documents Committee (CCDC) and is endorsed by the
constituent organizations of the CCDC and the Surety Association of Canada.
Surety bonds are by far the most common means of securing contractual obligations in the
construction industry today. Bonds are unique in that they are the only contract security
specifically designed to be used with construction contracts. Despite their extensive use,
however, such bonds and the suretyship process are not well understood. Those who use bonds
as an integral part of their business (i.e., contractors, construction purchasers, subcontractors,
suppliers, design professionals and even surety companies themselves) often have divergent
ideas about and expectations of surety bonds and the suretyship process. Too often bonds are
perceived as an obstacle another document to obtain before the bid is submitted or the contract
is signed. This Guide attempts to fill the information gap and assist all sectors of the
construction industry in using surety bonds to their advantage.
The following pages describe the suretyship process and clear up some commonly held
misconceptions. The guide is divided into three parts. Part 1 reviews suretyship, what a bond is
and how it differs from other risk management tools. Part 2 discusses how suretyship works in
practice, how bonds are obtained, the requirements of a surety company, and how the company
proceeds through the prequalification process. Part 3 examines the various forms of bonds with
a view to understanding the purpose of each bond and the claims process.

CCDC 22 2002

1.

WHAT IS SURETYSHIP?

1.1

HISTORY

Although North Americas first corporate surety bond was written in Canada in 1872, it wasnt
until the Post-World War II that suretyship was used extensively by public construction
purchasers and became the preferred method to provide third-party assurance that a contractors
contractual obligations would be met.
More recently, the Canadian surety industrys commercial results have proven to be extremely
volatile. During the 1990s, the industry showed tremendous growth and profitability, but then
came a downturn of unprecedented proportions.
The formation in 1992 of the Surety Association of Canada signalled the industrys
determination to ensure that the product and process keep pace with the business realities of the
construction community and the demands of the construction purchaser.
1.2

WHAT IS A SURETY BOND ?

A surety bond is a contract by which a third party (the Surety) guarantees that one party (the
Principal, usually a contractor or subcontractor), fulfills its obligation to a second party (the
Obligee, usually an owner or general contractor). More simply, a surety bond is a third-party
guarantee of the Principals performance.
All bonds are structurally the same, and share a number of common features. A bond is a
financial instrument. The first paragraph of any bond, including bid, performance and payment
bonds, is identical: it is a promise on the part of the Principal and Surety to pay up to the bond
amount to the Obligee.
Other paragraphs define the conditions that trigger liability under the bond. The conditions of
the various types of surety bonds are different. In a performance bond, for example, the
condition is the performance of the obligations set out in the underlying contract. If the contract
is performed, the obligation of the Surety, as set out in the first paragraph, is no longer an issue.
There is one aspect that sets a surety bond apart from other forms of contract security. Under
surety bonds, the obligation of the bonding company is secondary. The Obligee cannot claim
under a bond until the Principal is in default under the contract. That said, however, the
obligation itself is joint and several in that both the Principal and the Surety are obligated to
perform under the terms of the bond. In other words, if the Principal is unable to perform, the
obligation to perform is owed by the Surety.
The on default nature of a surety bond raises a question often asked of surety companies:
What constitutes a default under a construction contract? That question is not easy to answer and
the existence of default is determined largely by the terms of the contract and the particular
circumstances and problems of the job at hand.

CCDC 22 2002

While there is no one size fits all definition, there may be some guidance that can be given.
Perhaps a good rule of thumb in deciding when to declare default is to look carefully at the issues
raised and assess their effect on the overall performance of the contract. A bonding company
should be called in when the non-performance of a contractual obligation is so significant in its
impact that it becomes difficult or impossible to continue with the work. Some examples would
be:
- Insolvency of the Principal

1.3

Abandonment of the site by the work forces of the Principal (provided this was not the
result of a breach on the part of the Obligee)

Extensive delays and scheduling problems on the part of the Principal.


TYPES OF CONSTRUCTION SURETY BONDS

In response to the needs for contract security in the construction industry, the CCDC endorses
three forms of surety bonds:
Bid Bonds provide financial protection (as described in the bond) to the Obligee in the event that
the Principal fails or refuses to enter into a formal contract after its bid has been accepted in
accordance with the bid documents.
Performance Bonds provide an owner or contractor (the Obligee) with protection (as described
in the bond) ensuring completion of the contract in the event of default of the Principal.
Labour and Material Payment Bonds ensure that the Principals outstanding payables for
labour and materials, supplied under the bonded contract, are paid as described in the bond,
thereby reducing the likelihood of liens and construction schedule delays.
1.4

DEFINITIONS

While terms are defined in each bond, for the purposes of this guide the following general
meanings will be assumed:
Bond Amount the maximum amount for which the Surety will be liable under the bond.
Principal the contractor or subcontractor whose performance is guaranteed by the Surety and
who has entered into a written construction contract with the Obligee.
Obligee the owner or contractor who holds the bond and who has entered into a written
construction contract with the Principal. It is the Obligee alone who is entitled to make a
demand under a bid bond and a performance bond.
Surety the surety company that prequalifies the Principal, and issues and (with the Principal)
executes the bond.
Contract the written agreement between the Principal and the Obligee.

CCDC 22 2002

1.5

HOW SURETY BONDS DIFFER FROM OTHER FORMS OF SECURITY?

In an effort to better understand suretyship, it is instructive to compare bonds to other


instruments and forms of contract security.
Surety vs Insurance
Surety bonds are often confused with insurance policies. This confusion is understandable
because bonds are not only written by major insurance companies, they also share the same
distribution network and, in the marketplace, a common jargon. For example, fees for both
surety bonds and insurance policies are referred to as premiums and payouts are referred to as
claims.
Despite these similarities, surety bonds are distinct from their insurance counterparts. For
example, surety bonds involve three parties, while insurance instruments are two-party
agreements whereby one party (the Insurer) agrees to indemnify another (the Insured) for a
defined loss or set of losses.
Insurance is based on the risk-spreading principle of underwriting. Premiums are collected from
a large population of insureds, and premium levels are determined by actuarial analysis, which
takes into account demographic and other factors. It is accepted that losses will be incurred;
however, under the principle of risk-spreading, the losses of a few are covered by the premiums
of many.
Surety bonds, by contrast, are effectively credit instruments, and are underwritten much like a
banker assesses a loan application. In this case, no losses are anticipated and if the underwriter
believes a contractor may not be able to perform his or her contractual obligations, no bond will
be issued. Premiums for bonds do not pay for losses; rather, they are a service fee for
extending the required credit.
The Surety also has the right to recover any losses from its Principal should it be forced to pay
out under a bond. Principals seeking surety bonds are invariably required to sign an indemnity
agreement under which they specifically agree to those terms.
Surety vs Letters of Credit
Occasionally, an owner will prefer a cash deposit or Letter of Credit to bonds. There are a
number of reasons for this decision. Letters of Credit offer an owner the promise of cash on
demand. They are first demand instruments under which the issuer (usually a bank) must pay
cash to the holder immediately upon a demand. There is no need to prove that the contractor is
in default although a certificate to that effect is usually required.
Additionally, a Letter of Credit or other liquid security allows the owner to fully control the
default rectification process and eliminates the need to deal with the bonding company.

CCDC 22 2002

While these liquid security alternatives hold advantages for the construction purchaser, the quick
cash solution is not without problems. Control of the default rectification process can be a
double-edged sword. For example, while the owner may have control of the default rectification
process, he or she must now complete the defaulted job and shoulder all the associated
administrative burden and costs.
More importantly, the requirement to post cash or Letters of Credit can have a negative impact
on a contractors cash reserves and/or borrowing power. It has been suggested that a Letter of
Credit can cause the very problem it seeks to protect against by restricting a contractors access
to cash that may be required to address a problem on a job.
The performance bond is in force for 2 years following Substantial Performance of the Work.
Contractors posting cash or Letters of Credit press hard to have the security returned or
considerably reduced following completion of the project but long before the expiration of the
warranty period. This has caused stress for owners and hardship for contractors cash flow.
Restricted access to cash can also create further problems. Liquid security requires that a
contractors cash reserves or borrowing capacity be the same as the amount posted; therefore, the
available security is limited by the contractors access to cash. Due to this restriction, Letters of
Credit are typically for a smaller percentage (10-15%) of the contract value than performance
bonds (50% or 100%). These smaller amounts have proven inadequate to cover the shortfall in a
majority of defaulted contracts. Finally, Letters of Credit or cash deposits do not address the
problems of unpaid subcontractors and suppliers, who would be protected under a Labour and
Material Payment Bond.
Unlike Letters of Credit, bonds are not liquid security: Letters of Credit provide cash on
demand while surety bonds guarantee performance on default. Bonds do not necessarily
provide the construction purchaser with the funds necessary to rectify the problem; instead they
solve the problem by guaranteeing performance. A bonding company may arrange for the
completion of the defaulted contract.
In addition, a bond is not intrusive in the sense that it does not restrict a contractors cash
resources or borrowing power. By allowing access to all available cash, the potential for cash
flow problems, as discussed above for a Letter of Credit, is reduced. As contractors on
default instruments, performance and payment bonds are available in amounts up to 100% of
the contract price.
Also, unlike Letters of Credit, bonds do not respond on demand. It must first be established that
the Principal is in fact in default of the contractual obligations; simple declaration of default will
not suffice.

CCDC 22 2002

2.

HOW SURETYSHIP WORKS

Construction surety bonds are marketed through the insurance industry, and usually by insurance
brokers and insurance companies which specialize in construction suretyship.
A Principal must establish a surety relationship well in advance of bidding bonded projects.
Surety companies that provide construction surety bonds have varying underwriting guidelines
and often prefer certain types of contractors and sizes of contract. A specialized surety broker
can best match a construction firm with an appropriate surety company. It is important for the
surety company to understand the contractors business plans; the surety brokers role is to
ensure that the surety company underwriter understands and supports the contractors business
objectives.
2.1

THE THREE Cs OF SURETYSHIP

As part of the underwriting process, a surety company will assess a number of factors to
determine whether the contractor is likely to succeed in meeting its contractual obligations. In
other words, a contractor must qualify for a bonding program. If a contractor does not qualify,
no bonds will be available.
Each surety company has its own assessment criteria. However, all companies look at the basic
three Cs of suretyship character, capacity and capital. As a starting point, most surety
companies require the following confidential information:

Background about the company, including ownership, related companies, type and size of
projects previously completed, previous suppliers and subcontractors, and
architects/engineers/general contractors for whom the applicant has previously done
work;

Details about the contractors line of credit including a reference letter from the bank
outlining the amount of the line of credit, the amount currently in use and how it is
secured;

Details about the current work program (work on hand schedule) including the contract
price, billings and costs to date, and estimated costs to complete;

Financial statements of the company (and any related companies) for the last three years
and any interim financial statements prepared since year end; and

Personal financial statements of the company owners.

CCDC 22 2002

Character
The underwriter will assess the individuals who run the firm executives, estimating and office
staff, site superintendents, etc. as to their honesty and approach to business. Generally,
resumes of key personnel will be requested and references checked. The underwriter must
determine the reliability and integrity of the owners of the construction firm. In the event of a
problem, will the owners do the right thing when managing the business under pressure?
Capacity
An underwriter will investigate the capacity of the construction firm to perform its contracts. Is
the equipment in place to perform the work? Do the administrative and construction personnel
have the requisite skills and experience to successfully undertake the current project? Are
qualified people available for the contract? Where a different technique or new equipment is
being employed, are the people and equipment in place to ensure success?
Capital
An underwriter will need assurance that the company has the financial resources to meet not only
its current commitments, but also to withstand the problems inherent in the construction industry
unresolved disputes, unpaid receivables, varying site conditions, holdback provisions, tight
operating margins to name a few. There will be particular attention paid to the working
capital, equity, and ongoing profitability of the business. An underwriter will require regular
updates of financial statements, aged listings of accounts payable and receivable, work on hand
schedules, and details of the contractors bank line of credit. Other financial information may be
requested depending on the surety companys underwriting requirements.
2.2

INDEMNITY AGREEMENTS

When a surety company completes its investigation and agrees to a surety program, the
contractor must execute (i.e., sign and seal) an indemnity agreement. In the event of a loss, the
Obligee looks to the Surety to make it whole in accordance with the terms and conditions of the
bond. The surety company, in turn, looks to the parties who executed the indemnity agreement
to make it whole. The criteria for indemnity vary from one surety company to another; however,
most will ask for the indemnity of the construction firm, its owners and their spouses, and any
related companies (including holding companies).
Once the indemnity agreement is in place, the contractor can request bonds from the surety
company. The contractor must continue to inform the surety company about any changes within
the firm, and also any changes in the financial position and ongoing work of the firm. This
information is usually relayed through the contractors surety broker.

CCDC 22 2002

2.3

SECURING THE BOND

When bidding or commencing a project that requires a bond, the contractor contacts its surety
broker with the project details. While the information required varies by surety company,
contractor, and type of work, the following basic information is usually required:
-

Full legal name of the Obligee;

Description of the work, including type of work and location;

Estimated contract value should the Principal seek to submit a bid and require a bid bond;

The actual contract price (and other bidders and their prices, if known) if the Principal is
seeking a Performance and/or Labour and Material Payment Bond;

Confirmation that there is an engineer and/or architect on the job;

Bid or contract date;

Payment terms;

Maintenance or warranty period;

Penalties for delay;

Estimated or actual completion time;

Amount and type of work to be sublet (the surety company may request that some of the
subcontractors provide bonds); and

Amounts and types of bonds required.

A fourth C of surety, Conditions, is often discussed at this stage. The Surety may request
specific details about the project (including the terms and conditions of the contract) prior to
giving the surety broker approval to issue the bond.
Some surety companies give specialty surety brokers Powers of Attorney enabling them to issue
bonds in their offices. All bonds are executed under corporate seal by the attorney-in-fact of the
surety company and must also be similarly executed by the Principal (i.e., the contractor). Bonds
are legal documents and must be issued accurately with the proper legal names of the parties to
the bond, as well as a clear description of the work to be undertaken. Bonds must be signed,
sealed and delivered to the Obligee to be operative.

CCDC 22 2002

2.4

BOND COSTS

Surety companies generally do not charge clients for the bonds necessary to bid on a project;
however, most companies charge an annual administration fee to cover some of the costs of
issuing these documents. Surety companies receive remuneration when a contractor is awarded a
project and a Performance Bond (and perhaps a Labour and Material Payment Bond) is issued.
The surety companys fee is calculated per $1,000 of the contract price. Standard rates are
charged annually. Long-term rates may be available for projects where the construction schedule
exceeds 24 months. Both standard and long-term rates include warranty protection for up to one
year. Rates vary by surety company and are based on the financial position of the construction
firm.
In addition to the requirement of a Bid Bond, a contractor is occasionally asked to provide what
may be referred to as an Agreement to Bond, Consent of Surety, Bid Letter, etc. These can be in
the form of a letter or an undertaking signed by the Surety under which the Surety agrees to
provide a Performance Bond and, if required, a Labour and Material Payment Bond on behalf of
the contractor. When the project is awarded to that contractor, the Obligee may choose to waive
the requirement for performance and payment bonds. Although the owner has used the services
of the surety industry to prequalify the contractor, the surety company receives no remuneration
for its prequalification efforts. In these circumstances, most surety companies will charge a
prequalification fee.
2.5

VALUE ADDED TAXES

Surety companies do not receive the benefit of input tax credits and therefore may be exposed to
Value Added Taxes (e.g. the Goods and Services Tax, the Quebec Sales Tax and the Harmonized
Sales Tax) costs in the event of a claim. As a result, they may include the Value Added Taxes in
the bond amount and compute the premium on a Value Added Taxes inclusive basis.
Clarification on the effect of Value Added Taxes on surety bonds may be required for individual
circumstances.

CCDC 22 2002

3.

BOND FORMS

Contract surety bonds are distinctive among methods of contract security they are the only
instruments designed to respond to the unique needs of the construction industry. CCDC
endorses three forms of contract surety bonds: CCDC 220, Bid Bond; CCDC 221, Performance
Bond; and CCDC 222, Labour and Material Payment Bond.
3.1

CCDC 220 BID BOND

Bid bonds provide construction purchasers with assurance that the contractor submitting the bid
has been examined by the surety company and has been found qualified to perform the work.
Specifically, this bond offers an Obligee financial protection should a successful bidder not enter
into a formal written contract, or not provide the specified security. This protection is limited to
the lesser of the bond amount (usually 10% of the bid) and the difference in price between the
Principals bid and the next lowest compliant bid. This is the primary prequalification
instrument issued by a surety company to ensure that construction purchasers receive a bid from
a qualified contractor.
Condition of the Bond
The bidding process, which defines the obligation under a Bid Bond, is usually described in the
Invitation to Bid.
Provided a bid is submitted in accordance with the Invitation to Bid and is capable of acceptance,
the proper acceptance of the bid creates an obligation on the part of the Principal to enter into a
formal contract as specified in the Invitation and, often, to provide contract security (usually a
Performance Bond and a Labour and Material Payment Bond).
The condition of the form 220 Bid Bond is that if the Principal satisfies the obligation to enter
into a formal contract and, if required, provides the specified contract security, the bond is then
null and void. If the Principal defaults in this obligation, the bond remains enforceable, subject
to its conditions.
The Claims Process
Surety Investigation
When a demand is made by the Obligee under a Bid Bond, the Surety will investigate the
circumstances surrounding the demand. The investigation will focus on several questions:

10

Has the bidding process created an obligation for the Principal to enter into a formal
contract and to provide certain contract security?

If such an obligation has been created, is the Principal in default of the obligation?

If the Surety is liable under the bid bond, what amount should be paid under the bond?

CCDC 22 2002

Making a Demand
A demand should be made promptly in writing to the Surety. The form of a demand is not
specified in the bond, but it will assist the Surety investigation and response if the demand
includes:
-

notice that the Principal has an obligation to enter into the formal contract and/or provide
security, and a brief description of the circumstances giving rise to the obligation (i.e.,
the submission and acceptance of a bid, and the proper award and delivery for execution
of a formal written contract in accordance with the bid);

notice that the Principal has defaulted on the obligation, and that demand is being made
on the Surety under the Bid Bond; and

confirmation that a written notice of the default has been provided to the Principal and
that no satisfactory response has been received.

Copies of the following documents, provided with or shortly after the demand; will also assist
the Suretys investigation:
-

Invitation to Bid (or similar document to which the bid responded);

Principals bid as submitted;

documented proof of the acceptance and contract award in accordance with the Invitation
to Bid;

the formal written contract as presented to the Principal for execution;

any documents showing evidence that the Principal has refused or failed to honour the
obligation;

the list of bid results;

any formal or written bid analysis on the basis of which the Principals bid was accepted;

the next lowest compliant bid ; and

- the signed contract that the Obligee has entered into with another party to perform the
work.
Common Problems to Avoid
-

Accepting an informal or non-compliant bid;

Accepting a mistaken bid;

CCDC 22 2002

11

Failing to follow the prescribed bid process, or failing to properly accept or award the
contract;

Presenting for execution by the Principal a contract that is materially different from the
submitted bid;

Postponing acceptance beyond the period stipulated in the Invitation to Bid, or beyond
the period specified in the bond;

Failing to institute legal action to enforce the bond within seven (7) months of the date of
the bond (not from the date of the bid closing, award, or Principals default);

Entering with another party into a contract that is in a different form or that includes an
obligation(s) that differs from the original contract;

Failing to mitigate damages.

The Bidding Process: An Obligees Bid Bond Checklist


Pre-bid
-

Include specific reference in the bid documents to the CCDC 220 Bid Bond as there are
many non-standard forms in the marketplace.

Ensure the bid documents clearly define the bidding process, including time limits for
review and acceptance of bids, the document or act that constitutes acceptance of a bid,
when a formal contract must be signed, and what constitutes entering into a formal
contract, including the form of the contract (e.g. CCDC 2, 3 or 4).

Before extending the acceptance period of a bid, keep in mind the Bid Bond is not enforceable
after seven months from the date of the bond.
After Bid Closing

12

Ensure that the bid bond received was accurately drawn and executed.

The formal contract presented by the Obligee to the Principal must be essentially the
same contract that was bid in order for the Obligee to rely on the Bid Bond. The
Principal and the Surety are not bound to pay under the Bid Bond if the formal contract,
which the Principal fails or refuses to enter into, is materially different from the
contractual terms and conditions set out in the bid documents.

Payment under the Bid Bond requires that the Obligee actually enters into a contract with
another contractor.

CCDC 22 2002

3.2

CCDC 221 PERFORMANCE BOND

The Performance Bond guarantees that the Principal will perform the contract in accordance with
its terms and conditions. This bond protects the Obligee financially from the excess costs of
completion of a bonded contract should the Principal fail to perform. Usually the Surety will
participate actively in arranging for completion of the defaulted contract and in resolving any
resultant issues. For example, instead of simply funding a cost over-run, the Surety may remedy
a default, complete the contract, or re-bid the remaining work under a new contract.
Without a Performance Bond, the construction purchaser would have to finance the additional
costs to complete a defaulted contract, and bear the risk and expense of recovering the costs from
the defaulted Principal. Under the Performance Bond, the Surety essentially finances the
additional cost of completing a defaulted contract up the bond amount, and assumes the risk and
expense of recovery.
The Bond Condition
The condition that the Principal must be in default is the fundamental characteristic of a surety
bond, one that clearly distinguishes it from other forms of contract security. If the Principal
performs, the bond is null and void. If the Principal defaults, the undertaking to pay the bond
amount or elect one of the alternative settlements described in the bond remains in full force and
effect.
The construction contract between the Principal and the Obligee establishes the obligations of
the Principal. Assuming the performance bond is properly drawn, and has been signed, sealed,
and delivered to the Obligee and is, therefore, operative, the Surety will be liable if:
-

the Principal has been declared to be in default pursuant to the terms of the contract;

the Principal is, in fact, in default under the contract (i.e., the declaration of default is
justified and proper given the circumstances); and

the Obligee has honoured its obligations under the contract.

Surety Options
If the Principal has defaulted in the performance of the contract, and if the Surety is liable under
the bond, the Surety can satisfy its obligation in a number of ways as described below. The
Surety has the discretion to select the settlement option, but will often consult with the Obligee
and consider the unique circumstances of the default when making its decision. It is in the best
interest of the Surety and the Obligee to act expeditiously to mitigate the cost of completing the
contract.

CCDC 22 2002

13

Remedy the Default


The Surety may elect to remedy the default by providing assistance to the defaulted Principal.
This may involve financing a cash-strapped Principal through to the completion of the bonded
project.
Complete the Contract
The Surety may elect to complete the contract. Although under this option it may appear that the
Surety has simply replaced the defaulted Principal and is acting as the contractor or
subcontractor under the contract, it is important to note that the Surety is not a party to the
contract and will be acting in its capacity as Surety under the bond. The Surety will complete the
defaulted contract using the unpaid balance of the contract price, which it is entitled to receive
from the Obligee, and seek recovery from the Principal any additional costs or expenses arising
from the default.
There are several ways by which the Surety can complete the contract. For example, the Surety
can hire one or more general or subcontractors, project or construction managers, or suppliers to
provide the required services. Under this option the Surety makes financial and payment
commitments directly to the parties retained. The Obligee must be informed of the arrangements
and commitment for the unpaid contract balance to be made available to the Surety, subject to
any statutory requirements or obligations imposed upon the Obligee (e.g., lien holdback).
Re-bid
Under this option, the Surety may seek bid(s) for completion of the contract and arrange for a
new contract between the successful bidder and the Obligee. Usually, the terms of the
completion contract, including scope of work, payment terms and bonding requirements, are the
same as in the defaulted contract. However, agreement about the scope of the remaining work,
as well as provision for approved and pending changes to the work, will be required.
The Obligee administers the new completion contract and makes payments directly to the new
contractor. If the amount payable to the completion contractor exceeds the amount the Obligee
would have otherwise been required to pay to the defaulted Principal had there been no default,
the Surety pays this additional amount to the Obligee under the bond as the work progresses,
subject to the bond amount.
Pay the Bond Amount
The Surety, when it accepts liability under the bond, is entitled to pay the bond amount to the
Obligee in full satisfaction of its obligation under the bond. A Surety would consider this option,
for example, when satisfied that the Obligees completion costs, which the Surety would be
liable for under the bond, exceeded the bond amount. Where the completion costs for which the
Surety is liable are less than the bond amount, the Surety may satisfy its obligation under the
bond by tendering payment of the lesser amount to the Obligee.

14

CCDC 22 2002

Disputed Default
Occasionally, when presented with a demand under a Performance Bond and following its
investigation, the Surety will be unable to determine whether there has been a default. The
contract between the Obligee and the Principal sometimes gives rise to genuine disputes which
cannot be resolved or determined by the Surety, and which require resolution by some alternative
means or, ultimately, by the courts.
In this situation, the Performance Bond continues to provide the same degree of financial
protection to the Obligee. If a determination is ultimately made in favour of the Obligee, and
assuming the Obligee has given proper notice to the Surety and preserved its rights under the
bond, the Surety will be liable to the same extent as if the default had been clear at the outset.
In a disputed default, the parties often agree to put aside the dispute in the interests of
completing the job as expeditiously and economically as possible. In these circumstances, a
Surety might propose or accept an arrangement whereby the work is completed and funded by
the parties while preserving their respective rights under the contract and the bond. This
approach focuses the parties energies on promptly completing the work, mitigating the costs,
and avoiding additional disputes about the costs of completion.
The Construction Process - An Obligees Performance Bond Checklist
Pre-construction
-

Include specific reference in the bid documents to CCDC 221 as there are many nonstandard bond forms in the marketplace.

- Ensure that the fully executed bond is accurately drawn and in the possession of the
Obligee. In the event the bond is not delivered to the Obligee, it cannot become
operative.
During Construction
-

Notify the Surety of material changes in the contract, and obtain the Suretys consent to
remain bound under the bond. Since the performance of the contract referred to by the
Principal in the bond is the condition of the bond, a material change in the contract
without the Suretys consent releases the Surety.

Understandably there is often confusion among Obligees, Principals and consultants as to when a
change to a contract is material. Regrettably, there are no absolute criteria to define material
change and indeed a change which may be material in one contract can be insignificant in
another.

CCDC 22 2002

15

Some owners have attempted to address this issue by establishing a percentage change threshold
(e.g. 25%) in the contract and/or bond. They deal with this issue by defining a material change
as any change which increases the contract price by an amount greater than that percentage.
Unfortunately a material change may not have any effect on the contract value and this approach,
however well intentioned is probably misguided.
The good news is that even though there are no hard and fast rules there are some indicators.
Significant extensions of time or increases or decreases in the contract price, changes in the
payment terms (e.g., advance payments), major changes in the scope or nature of the work (e.g.,
the addition of design responsibility) are examples of changes which, in specific circumstances,
can be material to the Suretys risk. Probably the best advice to an Obligee is to take the cautious
approach. If you think theres a chance that a change to a contract may be material it is best to
inform the bonding company as described above.
Default
If a default occurs for which the Obligee intends to look to the Surety, the Obligee or its
consultant should ensure that the default is first properly declared to the Principal in accordance
with the terms of the contract.
The Surety should be provided with a clear and unequivocal written demand under the bond,
advising that the Principal is in default under the contract (naming the specific provision(s) of the
contract that may have been breached), and that the Obligee requires the Surety to meet its
obligations under the bond. Keep in mind that the Surety will not likely take any action until the
time allowed under the contract for the Principal to remedy the default has expired. Notice must
be given to the Surety so that it has an opportunity to consider its options under the bond. If
notice is not given, the Surety is discharged.
Investigation by the Surety
The Surety will investigate the circumstances surrounding the declaration of a default and the
demand on the bond, and will attempt to answer the following questions: Is the Surety liable
under the bond and, in the event of liability, what arrangements should be made to complete the
contract and settle the Suretys financial obligation to the Obligee?
Keep in mind that it may take some time and, indeed, may not be possible to determine whether
the Surety is liable under the bond. Contractual disputes are often complex because they have
evolved over a period of time.
The Obligee should assist the Surety in its investigation by providing:
-

16

copies of contract documents, including general, special, and supplementary conditions,


specifications, drawings, latest approved schedule, approved and pending change orders,
minutes of meetings and other correspondence or documents relevant to the default;

CCDC 22 2002

a full accounting of the contract price, including reconciliation of the price or unit values
specified in the contract at the time of award with the current contract value, including a
record of all payments, credits or backcharges, holdback or other amounts retained, and
copies of payment certificates;

reasonable access to the work-site and assistance in determining the status and condition
of the work;

information about any special or urgent circumstances necessary to the Suretys


investigation.

Should it be necessary to preserve or protect the work while the Surety is investigating, seek the
Suretys agreement that the Obligee undertake reasonable and economical action, with the
resultant expenses treated as costs to complete the contract.
Verify that project insurance remains in force and, if necessary, notify the Surety of any pending
lapse and seek agreement that the Obligee pay any premium for interim coverage, which should
be treated as a cost to complete the contract.
Completion and Settlement
When considering a Suretys proposal to complete the contract and satisfy its financial
obligation, it is important to keep the following in mind:
-

The settlement option proposed by the Surety often involves arranging for or even
directly performing some of the work called for under the contract. However, the Surety
does not replace the Principal. In fact, after having satisfied its obligations under the
bond, the Surety will usually attempt to recover from the Principal the excess cost to
complete the job, just as the Obligee would have had there been no bond. Additional
costs of completing the bonded contract are, in essence, financed by the Surety, but
ultimately paid by the Principal.

When electing to remedy the default or complete the contract, the Surety may ask the
Obligee to acknowledge that the Surety is acting in its capacity as Surety under the bond,
and is subject, therefore, to the terms and limitations of the bond. This acknowledgement
can avoid confusion and expense where it appears that the Surety is acting as the
Principal contractor.

If the Surety proposes to complete the contract, it will require a clear commitment by the
Obligee to pay to the Surety the contract balance as defined in the bond, subject to any
statutory requirements or obligations imposed on the Obligee (e.g., lien holdback). It is
typically part of the completion agreement between Obligee and Surety that the Obligee
will pay these amounts as the work progresses, in the same manner as they would have
had the original contractor not defaulted.

The Suretys financial responsibility is limited to the bond amount.

CCDC 22 2002

17

It is important to record the date on which the Principals default or abandonment occurred.
Should completion of the contract or financial settlement with the Surety extend over a long
period, steps should be taken to preserve the right to recover under the bond. It is a good
practice to evaluate the status of the work immediately after the default in order to have an
accurate record of the work performed and any deficiencies observed. Any suit against the
Surety under the bond must commence within two years from the earlier of:
1) the date of substantial performance of the contract as defined in the lien legislation
where the work is taking place or, if no such definition exists, the date when the
work is ready for use or is being used for its intended purpose; or
2) the date on which the Principal is declared in default by the Obligee.
3.3

CCDC 222 LABOUR AND MATERIAL PAYMENT BOND

This bond provides financial protection to subcontractors who have a direct subcontract with the
defaulted Principal to provide labour and materials for the project covered by the bond. Labour
and Material Payment Bonds are usually available only together with Performance Bonds.
Under the bond provisions, should the Principal pay the claimants for all labour and material
used in the performance of the contract, the obligation of the Surety would then be null and void.
That is, if the Principal fulfills its obligations to the claimants, the Surety has no liability under
the bond.
While some non-standard or Government of Canada Labour and Material Payment Bonds
provide limited coverage to secondtier subcontractors and suppliers, this is not the case with
CCDC 222.
It is important for claimants to realize that coverage under this bond is limited to labour and/or
material supplied to the specific project described in the bond. While it is not uncommon for a
supplier to maintain a running account with the general contractor, and to simply apply payments
to the oldest outstanding invoices, this can pose problems for both general contractors and
subcontractors in relation to this bond. Potential claimants should, during the performance of
their agreement with the Principal, identify the project for which they are supplying materials,
general contractors should identify which invoices are being paid at any one time. Where a
supplier sells materials in bulk, it maybe unable to recover unpaid debt under a labour and
material payment bond because it is not possible to prove the ultimate destination of the supplies.
Bond Conditions
Potential claimants should understand the terms and conditions of the Labour and Material
Payment Bond, especially the following:
-

18

Claimants cannot sue under the bond until 90 days after the date on which they last
supplied labour and/or materials to a project.

CCDC 22 2002

Under their contract with the Principal, claimants must provide notice of their claim
(other than for holdbacks), indicating the exact amount or their claim, within 120 days
after the date on which the claimant did or performed the last of the work or labour, or
last furnished materials for which the claim is being made.

With respect to statutory or other holdbacks (e.g., maintenance holdback), claims must be
submitted within 120 days after the claimant should have been paid in full under the
claimants contract with the Principal.

No suit or action shall be commenced by any claimant under this bond after one year
following the date on which the Principal ceased work on the contract, including work
performed under the guarantees provided in the contract and provided the claimant has
complied with the conditions of the bond. This condition simply limits a suit and does not
serve to extend the notification period within which a claim must be made.

Claimants should note that written notice of their claim must be sent to each of the
Principal, Surety, and Obligee by registered mail.

Proving the Claim


While the requirements for proving the claim may vary, the following documentation is normally
required:
-

Copy of the complete contract or purchase order with the Principal;

Copies of all change orders and change directives concerning the contract;

Copies of all invoices and/or progress billings submitted to the Principal;

Copies of all statements of account rendered to the Principal;

A summary of all payments, including the date and amount of each payment;

Evidence of the last date upon which labour and/or material was supplied to the project;

Signed delivery tickets and/or time sheets;

Evidence and documentation to support other amounts being claimed and which may not
have been agreed to or authorized in writing under the contract or within a change order
or change directive; and

Proof of acceptance of the work by the owner or consultant.

CCDC 22 2002

19

Benefits of Labour and Material Payment Bonds


While Labour and Material Payment Bonds clearly benefit subcontractors and suppliers, they
also benefit Obligees who may appear to be nothing more than trustees for the claimants and not
direct beneficiaries. The benefits to Obligees include the following:

20

In the event of a default by a Principal, construction purchasers and/or their


representatives will have to deal with subcontractors and suppliers who, in turn, may feel
that the construction purchaser has a direct obligation to them. This can become a
significant administrative burden to an owner who is deluged with phone calls from
angry, frustrated and confused subtrades and suppliers. Furthermore, an owner has a
statutory obligation to retain and properly distribute any holdback monies for those
parties who may have registered liens against the property in question. With a Labour
and Material Payment Bond in place, the surety company deals with these claimants and,
upon payment, will be subrogated to their claims.

Owners who do not require Labour and Material Payment Bonds, may do so to their own
detriment. Many subcontractors and suppliers are reluctant to enter into a contract on a
project where there is no Labour and Material Payment Bond, because of the inherent
credit risk, and may, consequently, increase their prices to reflect the additional risk.

A Suretys obligation under a Performance Bond is limited to the balance of the work to
be completed under the contract. There is no obligation on the part of the Surety to deal
with unpaid labour or material suppliers to the Principal. These unpaid parties typically
refuse to return to a project until paid for the work already completed; since the Surety
has no obligation towards them, the Surety would likely contract with replacement
contractors for the balance of the work. This would then require additional time to
complete the contract in that replacement contractors must familiarize themselves with
the work in place. With a Labour and Material Payment Bond in place, the Surety is in a
position to bring the sub-trades up-to-date financially, to obtain their co-operation to
complete the contract, and to maintain the integrity of the warranties. Obviously, any
unpaid sub-trade has no obligation to maintain or honour a warranty.

CCDC 22 2002

Vous aimerez peut-être aussi