Vous êtes sur la page 1sur 12

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST

SAIC NUMBER

Pre-Application Inspection of Castable & Brick Refractory


PROJECT TITLE

SAIC-N-2024
WBS / BI / JO NUMBER

EQUIPMENT ID NUMBER(S)

EQUIPMENT DESCRIPTION

LAYOUT DRAWING NUMBER

REV. NO.

SCHEDULED INSPECTION DATE & TIME

ACTUAL INSPECTION DATE & TIME

REFERENCE

General Requirements (Both SAES-N-110 & SAES-N-120 Applications, See Note 1)


Refractory systems for specific equipment meet requirements
specified in SAES-N-100 Table 3 "Mandatory Refractory Systems" :
A) Refractory Anchor (Material, Sizes & Types) selection is correct
B) Refractory Material (Type, Weight % of Needles,
Application Method) selection is correct. See Note 3 (Make Field Copy).

SAES-N-100,
Para. 9.1

A2

Checklist SAIC-N-2022 is completed & accepted. Anchorage, supports


& hexsteel installations are welded. All inspection & testing is complete.

as referenced

A3

Checklist SAIC-N-2023 has been completed & accepted & both


applicators & application techniques are fully qualified.

as referenced

A4

Post-weld Heat treatment (PWHT) & hardness testing after welding is


completed & accepted.
See Note 2

SAES-N-110,
Para. 6.2.2

A5

Materials have been stored off the ground & properly covered with tarps
to protect against damage from water or moisture.
See Note 2.

SAES-N-110,
Para. 7.2

B.

Pre-Application Requirements for Castable Refractories (SAES-N-110 Procedure)

B1

All surfaces are clean, dry & free from oil, grease, weld slag & mill scale
prior to installation of refractory.

SAES-N-110,
Para. 8.1

B2

Prior to application of refractory, all metallic surfaces have been grit


blasted in accordance with SSPC SP 6, "Commercial Blast Clean".

SAES-N-110,
Para. 8.2

B3

Surfaces previously coated with a vapor barrier or that are heavily


corroded (such as tie-ins to existing equipment or repairs) are brush
blasted in accordance with SSPC SP 7, "Brush Blasting".

SAES-N-110,
Para. 8.3

B4

Application of hydraulic-setting refractory is by gunning, casting, or


vibration casting (as previously qualified by test sample).

SAES-N-110,
Para. 9.1.1

B5

Testing procedures (test panel & production sample) were performed


per SAES-N-110, Section 11.2 requirements with all testing conducted
by a fully qualified & Company approved independent lab. (Note 4)

SAES-N-110,
Para. 9.1.2

B6

Surfaces to be lined were inspected prior to refractory installation & SA


authorized Refractory Inspector has given approval for lining application.

SAES-N-110,
Para. 9.1.3

B7

Linings backing surface temperatures are monitored & do not exceed


32C for application.

SAES-N-110,
Para. 9.1.4

B8

Protective Steps are taken are maintain a maximum temperature of


32C for a minimum of 24 hours after installation. Linings are protected
from heat-induced accelerated setting by protective measures. Note 5.

SAES-N-110,
Para. 9.1.5

Page 1 of 12

PLANT NO.

EC / PMCC / MCC NO.


MH's SPENT

TRAVEL TIME

SAUDI ARAMCO USE ONLY

CONTRACTOR INSPECTION LEVEL

A1

MECH-

SYSTEM ID.

QUANTITY INSP.

SAUDI ARAMCO INSPECTION LEVEL

ACCEPTANCE CRITERIA

QR NUMBER

CONTRACTOR / SUBCONTRACTOR

PURCHASE ORDER NUMBER

SAUDI ARAMCO ACTIVITY NUMBER

A.

15-Dec-09

EQPT CODE

SAUDI ARAMCO TIP NUMBER

ITEM
No.

30-Jun-08
DATE APPROVED

WORK PERMIT REQUIRED?

PASS

FAIL

N/A

RE-INSP DATE

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST


Pre-Application Inspection of Castable & Brick Refractory
PROJECT TITLE

ITEM
No.

SAIC NUMBER

SAIC-N-2024
WBS / BI / JO NUMBER

ACCEPTANCE CRITERIA

REFERENCE

B9

Linings & lining materials are kept above 10C during the lining
application and for a period 24 hours after the lining application.

SAES-N-110,
Para. 9.1.7

B10

Linings shall be applied in a manner that will ensure minimal shrinkage.


Manufacturer specific instruction's to minimize shrinkage are followed.

SAES-N-110,
Para. 9.1.8

B11

Water used to mix refractory (certificate) complies with the following:


A) The pH is within a range of 5.8-8.6.
B) Water quality (All Impurities < 1000 ppm, Iron < 500 ppm,
Calcium & Magnesium, both < 300 ppm, Chlorine & Sulfur, both < 200
ppm).

SAES-N-110,
Para. 9.1.9

B12

Admixtures are not used during refractory mixing operations.

SAES-N-110,
Para. 9.1.10

B13

Water ratios specified by Refractory Manufacturer are available & mixing


containers used have accurate level markings to assure mix accuracy.

SAES-N-110,
Para. 9.1.11

B14

Temperature Controls (water & refractory) exist to keep mixed refractory


between 10C and 32C.

SAES-N-110,
Para. 9.1.12

B15

Additives to linings have been approved by Saudi Aramco Engineer


(Supervisor, Piping & Valves Unit, Consulting Services Dept, Dhahran).

SAES-N-110,
Para. 9.1.13

B16

Piping & equipment is supported to prevent distortion during lining.

SAES-N-110,
Para. 9.1.14

B17

Threaded attachments on equipment are protected from lining during


application & Protection does not interfere with the application of lining.

SAES-N-110,
Para. 9.1.15

B18

Equipment nozzle extensions were properly coated with grease to


prevent refractory from bonding to them.

SAES-N-110,
Para. 9.1.16

B19

All openings in equipment are closed & tapered hardwood plugs & sheet
metal sleeves extend beyond the final thickness of the lining.

SAES-N-110,
Para. 9.1.17

B20

These plugs or sleeves are coated with grease, fit snugly into openings,
& shall remain in place until the refractory has set.

SAES-N-110,
Para. 9.1.17

B21

Refractory Manufacturer's recommended time limits (for lining


settlement) are available. The application is well-planned to ensure use
within specified time limits.

SAES-N-110,
Para. 9.1.18

B22

A minimum gap (Cut Back) of 100 mm is provided at the ends of each


section for refractory installed in piping or vessel sections to be
connected by welding.

SAES-N-110,
Para. 9.1.19

B23

The second layer in Double-layer linings is applied after the first layer
has cured for 24 hour minimum and the first layer is thoroughly wetted
just before 2nd layer application.

SAES-N-110,
Para. 9.1.20

B24

Linings of each type of refractory are installed to full thickness in a single


application & are not built up in layers.

SAES-N-110,
Para. 9.1.21

B25

When necessary to apply lining in sections to achieve full thickness in a


single application, edge forms are beveled 10 for keying of adjoining
sections. Construction Joint provisions exist. (Detailed Drawings).

SAES-N-110,
Para. 9.1.21

B26

Anchors were installed per SASD AC-036397.


See Attachment 1.

SAES-N-110,
Para. 9.2.1

Page 2 of 12

30-Jun-08
DATE APPROVED

15-Dec-09

QR NUMBER

MECH-

CONTRACTOR / SUBCONTRACTOR

PASS

FAIL

N/A

RE-INSP DATE

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST


Pre-Application Inspection of Castable & Brick Refractory
PROJECT TITLE

ITEM
No.

SAIC NUMBER

SAIC-N-2024
WBS / BI / JO NUMBER

ACCEPTANCE CRITERIA

REFERENCE

30-Jun-08
DATE APPROVED

15-Dec-09

PASS

FAIL

Nozzle & manway opening details in refractory lined pressure vessels


& piping were installed per SASD AB-036914.
See Attachment 2.

SAES-N-110,
Para. 9.2.2

B28

Hexsteel was installed per SASD AB-036396.


See Attachment 3.

SAES-N-110,
Para. 9.2.3

B29

Inspector reviews the following procedure before production work:


"Mixing Refractory for Pneumatic Applications" .
See Note 6.

SAES-N-110,
Section 9.3

B30

Inspector reviews the following procedure before production work:


"Application of Pneumatically Applied Refractory". See Note 6.

SAES-N-110,
Section 9.4

B31

Inspector reviews the following procedure before production work:


"Mixing Refractory for Casting Applications" .
See Note 6.

SAES-N-110,
Section 9.5

B32

Inspector reviews the following procedure before production work:


"Application of Cast Refractory".
See Note 6.

SAES-N-110,
Section 9.6

B33

Inspector reviews the following procedure before production work:


"Application of Vibration Casting".
See Note 6.

SAES-N-110,
Section 9.7

C.

SAES-N-110 Procedure Figure 1 Checklist for Castable Refractory (Section A, Prior to Installation)

C1

MATERIALS are checked as follows:


A) Types of materials supplied are correct
B) Data sheets & mixing instructions are available
C) MSDS sheets are available

SAES-N-110,
Figure 1, Sect. A

C2

DOCUMENTS include approved detail drawings

SAES-N-110,
Figure 1, Sect. A

C3

INSPECTION includes the following:


A) Inspect surface preparation
B) Inspect anchor layout and welding

C4

C5

C6

C7

C) Review
welding procedures
WEATHER PROTECTION exists as follows:
A) Materials are properly stored
B) Equipment to be lined is prepared for inclement
weather
EQUIPMENT - MIXERS is checked as follows:
A) Number and type are adequate
B) Back up mixer is
available
C) Location relative to work
D) Cleanliness
GUNNITE RIGS are checked as follows:
A) Number & Type of Rigs is adequate
B) Operating Condition &
Cleanliness is adequate
C) Hose is sufficient
F) Nozzle type is
correct
VIBRATORS are checked as follows:
A) Number & Type of vibrators is adequate
B) Attachment method
C) Operating condition
D) Backup

Page 3 of 12

SAES-N-110,
Figure 1, Sect. A

SAES-N-110,
Figure 1, Sect. A

SAES-N-110,
Figure 1, Sect. A

SAES-N-110,
Figure 1, Sect. A

MECH-

CONTRACTOR / SUBCONTRACTOR

B27

SAES-N-110,
Figure 1, Sect. A

QR NUMBER

N/A

RE-INSP DATE

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST


Pre-Application Inspection of Castable & Brick Refractory
PROJECT TITLE

ITEM
No.

C8

SAIC-N-2024
WBS / BI / JO NUMBER

ACCEPTANCE CRITERIA

REFERENCE

CURING COMPOUND APPLICATORS are checked as follows:


A) Type and size
B) Cleanliness
C) Number
D) Working
conditions
AIR COMPRESSORS are checked as follows:
A) Size

C9

C10

SAIC NUMBER

B) Operating Condition
C) Contingencies
SAMPLE MOLDS are checked as follows:
A) Cubes are adequate
B) Gunnited molds are
adequate

30-Jun-08
DATE APPROVED

15-Dec-09

PASS

SAES-N-110,
Figure 1, Sect. A

SAES-N-110,
Figure 1, Sect. A

D.

Pre-Application Requirements for Extreme Erosion-Resistant Refractory (SAES-N-120 Procedure)

D1

Material is unopened & within expiry date (Or material is rejected).

SAES-N-120,
Para. 10.1.1

D2

Water used to mix refractory (certificate) complies with the following:


A) The pH is within a range of 5.8-8.6.
B) Water quality (All Impurities < 1000 ppm, Iron < 500 ppm,
Calcium & Magnesium, both < 300 ppm, Chlorine & Sulfur, both < 200
ppm).

SAES-N-120,
Para. 10.1.3

D3

Admixtures are not used unless approved by Saudi Aramco Engineer.

SAES-N-120,
Para. 10.1.4

D4

Linings will be installed indoors except for in-situ patching & repairs.

SAES-N-120,
Para. 10.1.5

D5

Lining backing surface temperatures will not exceed 32C on application

SAES-N-120,
Para. 10.1.6

D6

Protective Steps are taken are maintain a maximum temperature of


32C for a minimum of 24 hours after installation. Linings are protected
from heat-induced accelerated setting by protective measures. Note 5.

SAES-N-120,
Para. 10.1.7

D7

Linings & lining materials will be kept above 10C during the lining
application and for a period 48 hours after the lining application.

SAES-N-120,
Para. 10.1.9

D8

Surfaces shall be kept dry before, during and after installation.

SAES-N-120,
Para. 10.1.10

D9

Refractory Manufacturer's mixing instructions, installation instructions, &


precautions are available (to be strictly followed during applications).

SAES-N-120,
Para. 10.2.1

D10

A) Hobart, Model #D-33 commercial mixer (or approved equal).


B) Two, 30-quart mixing bowls
C) A beater and a wire whip

SAES-N-120,
Para. 10.2.2

Applicators understand the following mandatory requirements:

D11

A) The Mixed quantity is only what can be applied within 15 mins after
the addition of water.
B) Any mixed refractory not used within 15 minutes is
discarded.
C) Mixing does not continue
after the plastic stage occurs.
D) All
equipment, mixing bowls & tools must be kept clean & free of foreign
material & must be cleaned thoroughly after each mix.

Page 4 of 12

SAES-N-120,
Para. 10.2.3
&
Para. 10.2.4

MECH-

CONTRACTOR / SUBCONTRACTOR

SAES-N-110,
Figure 1, Sect. A

Mandatory mixing equipment (all Stainless Steel) is available as follows:

QR NUMBER

FAIL

N/A

RE-INSP DATE

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST


Pre-Application Inspection of Castable & Brick Refractory
PROJECT TITLE

ITEM
No.

D12

D13

D14

SAIC NUMBER

SAIC-N-2024
WBS / BI / JO NUMBER

ACCEPTANCE CRITERIA

REFERENCE

SAMPLE TESTING PROCEDURE (9 Steps) has been completed.


(1) Select three packages at random from each batch or lot, then take 5
lbs of dry and damp material from each batch or lot.
(2) Reseal the packages that the samples were taken from and mark
them "Package Opened for Sampling".
(3) Mix the three samples of the dry material together to give a uniform
mixture. Repeat this procedure with the damp material.
(4) Take enough of the sample mix to prepare five 50 mm cubes for the
cold crushing strength tests.
(5) Seal the remainder for possible re-test.
(6) Mix the two materials together & add required amount of water (refer
to mixing instructions in paragraph 10.2.3 above) & cast five cubes.
(7) Air cure and dryout the samples in accordance with Chapter 11.
(8) Perform cold-crushing strength and bulk density tests in accordance
with ASTM C133 and ASTM C134. The cold-crushing strength and bulk
density values are the average result obtained for the five test cubes.
(9) Any sample that does not meet the minimum published strength or
density will be cause for rejection of the complete batch.

Hand packing tools (Plastic or wooden mallets) are available to


hammer refractory into hexsteel to eliminate voids or air pockets &
increase the installed density of the material.

Extreme care prevents overlaying of lining material over hexsteel. Form


for screeding is checked for levelness (screed board, line, straightedge)
& securement. No hexsteel protrusions or depressions exist.

30-Jun-08
DATE APPROVED

15-Dec-09

QR NUMBER

MECH-

CONTRACTOR / SUBCONTRACTOR

PASS

FAIL

N/A

RE-INSP DATE

SAES-N-120,
Section 10.3

SAES-N-120,
Para. 10.4.1

SAES-N-120,
Para. 10.4.2

Smooth screeding is flush to the face of the hexsteel & hexsteel


pattern must be visibly distinguishable after screeding of lining.

D15

Air curing & Dryout equipment (Ventilation equipment, furnace,


auxilliary burners, temperature measuring devices, etc) is available.

SAES-N-120,
Section 11.1

Preparations for Sample Testing before Application are as follows:


A) Enough (64-80) sample forms of 50 mm cube size exist on jobsite.
D16

B) A chart is available (Sample number, date & time taken, location).


C) Sketch & log exists to show each batch location &
samples location.
D) Approved test laboratory has been determined for sample testing.

SAES-N-120,
Section 10.5

D17

A 1-pound hammer (head weight as stamped) is available for testing


the lining.

SAES-N-120,
Section 12.2.6

E.

SAES-N-120 Procedure Figure 1 Checklist for Extreme Erosion-Resistant Refractory (Section A, Prior to Installation)

E1

MATERIALS are checked as follows:


A) Types of materials supplied are correct
B) Data sheets & mixing instructions
C) MSDS sheets are available

SAES-N-120,
Para 12.5
Check List
Sec. A

Page 5 of 12

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST


Pre-Application Inspection of Castable & Brick Refractory
PROJECT TITLE

ITEM
No.

SAIC NUMBER

SAIC-N-2024
WBS / BI / JO NUMBER

ACCEPTANCE CRITERIA

REFERENCE
SAES-N-120,
Para 12.5
Check List
Sec. A

E2

DOCUMENTS include approved detail assembly drawings

E3

SURFACE PREPARATION & HEXSTEEL is checked as follows:


A) Surface preparation meets specifications
B) Welding procedures

E4

WEATHER PROTECTION exists as follows:


A) Materials are properly stored
B) Equipment to be lined is prepared for inclement weather conditions

E5

EQUIPMENT - MIXERS are checked as follows:


A) Number and types are adequate
B) Back up mixer is available
C) Location relative to work & Cleanliness

SAES-N-120,
Para 12.5
Check List
Sec. A

SAMPLE MOLDS are checked as follows:


A) Cubes

SAES-N-120,
Para 12.5
Check List
Sec. A
SAES-N-120,
Para 12.5
Check List
Sec. A

E6

B) Plate for erosion testing

SAES-N-120,
Para 12.5
Check List
Sec. A
SAES-N-120,
Para 12.5
Check List
Sec. A

E7

PNEUMATIC RAMMERS are checked as follows:


A) Number of rammers is adequate
B) Operating condition

F.

Pre-Application Requirements for Fireclay Brick Refractory . (SAES-N-130 Procedures)

F1

The Refractory installation procedure incorporates the requirements of


the Refractory Manufacturer, the Equipment Manufacturer, and this
standard and is approved by the Saudi Aramco Engineer prior to
installation.

SAES-N-130
Para. 5.2

F2

Detailed engineering drawings of the refractory system are available


showing anchorage design including spacing and orientation, refractory
thicknesses, all materials, surface preparation, and welding details.

SAES-N-130
Para. 5.3

F3

Structural steel framing members and tie back are provided for
supporting the brick lining on vertical flat sections.
Note:
A) All tie members shall be austenitic alloy material.
B) A minimum of 15% of the bricks shall be tied back.
C) Tie backs are not required when the radius of the curvature of
cylindrical casing keys the brick

SAES-N-130
Para. 6.3

F4

Metal support shelves welded to the casing and centered a minimum of


8 meters vertically to support the Brick lining Note: Shelves shall be
slotted to provide for differential thermal expansion.

SAES-N-130
Para. 6.3

F5

Fireclay bricks are free from mechanical damage prior to placement.

SAES-N-130
Para. 7.1

G.

SAES-N-130 - Checklist for Fire Clay Brick Refractory Installation. (Prior to Installation)

G1

MATERIALS are checked as follows:


A) Types of materials supplied are correct
B) Data sheets & mixing instructions are available
C) MSDS sheets are available

G2

DOCUMENTS include approved detail assembly drawings

Page 6 of 12

SAES-N-130
Para 8.3
Check List
SAES-N-120,
Para 12.5
Check List
Sec. A

30-Jun-08
DATE APPROVED

15-Dec-09

QR NUMBER

MECH-

CONTRACTOR / SUBCONTRACTOR

PASS

FAIL

N/A

RE-INSP DATE

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST


Pre-Application Inspection of Castable & Brick Refractory
PROJECT TITLE

ITEM
No.

G3

SAIC NUMBER

SAIC-N-2024
WBS / BI / JO NUMBER

ACCEPTANCE CRITERIA

REFERENCE

EQUIPMENT - MIXERS are checked as follows:


A) Number and types are adequate
B) Back up mixer is available
C) Brick saw is available.
D) Location relative to work & Cleanliness

SAES-N-120,
Para 12.5
Check List
Sec. A

Page 7 of 12

30-Jun-08
DATE APPROVED

15-Dec-09

QR NUMBER

MECH-

CONTRACTOR / SUBCONTRACTOR

PASS

FAIL

N/A

RE-INSP DATE

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST

SAIC NUMBER

Pre-Application Inspection of Castable & Brick Refractory


PROJECT TITLE

SAIC-N-2024
WBS / BI / JO NUMBER

ITEM
No.

ACCEPTANCE CRITERIA

30-Jun-08
DATE APPROVED

REFERENCE

QR NUMBER

15-Dec-09

MECH-

CONTRACTOR / SUBCONTRACTOR

PASS

FAIL

N/A

RE-INSP DATE

REMARKS:
REFERENCE DOCUMENTS:
1.
2.
3.
3.

SAES-N-100 -- Refractory Systems (30 Jan 2007)


SAES-N-110 -- Installation Requirements-Castable Refractories (30 Jan 2007)
SAES-N-120 -- Installation Requirements-Extreme Erosion Resistant Refractories (30 Jan 2007)
SAES-N-130 Installation Requirements Fireclay Bricks. (30 January 2007)

ATTACHMENTS:
Attachment 1 -- SASD AC-036397 (Anchoring Details for Castable Refractories)
Attachment 2 -- SASD AB-036914 (Support Details at Nozzles & Manways for Castable Refractory)
Attachment 3 -- SASD AB-036396 (Hexsteel Details)
NOTES:
1. This checklist applies to Pre-Application inspection for castable refractory systems detailed in procedures SAES-N-110 & SAES-N-120.
2. This is a requirement for both SAES-N-110 & SAES-N-120.
3. Use Table 3 Mandatory Refractory Systems of SAES-N-100 (Not Attached) for Pre-installation inspection checks of materials.
4. The standard refers to Paragraph 11. This is an error. Testing requirements are in Section 11. This will be revised upon the next standard review.
5. To achieve temperature limitations specified (Maximum 32C for 24 hours minimum), the backing surface may be shaded from direct sunlight,
the refractory lining may be applied indoors, or apply refractory lining at night with proper illumination. Cooling by water spraying is prohibited.
6. Inspector reviews a Field Copy of SAES-N-110, Section 9, Installation. (This is not attached to this checklist & a field copy will be needed). The
Inspector uses the procedure as a checklist for equipment (mixing, application), consumables (air, water, materials), & set-up (formwork) checks.

Contractor / Third-Party

Saudi Aramco

Construction Representative*

PMT Representative

Work is Complete and Ready for Inspection:


Name, Initials and Date:

T&I Witnessed

QC Record Reviewed

Work Verified

T&I Witnessed

QC Record Reviewed

Work Verified

T&I Witnessed

QC Record Reviewed

Work Verified

Name, Initials and Date:

QC Inspector

PID Representative
Performed Inspection

Work / Rework May Proceed

Name, Initials and Date:

Name, Initials and Date:

QC Supervisor

Proponent and Others


Quality Record Approved:

Name, Sign and Date:

Name, Organization,
Initials and Date:

*Person Responsible for Completion of Quality Work / Test

Y = YES

Page 8 of 12

N = NO F = FAILED

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST


Pre-Application Inspection of Castable & Brick Refractory

SAIC NUMBER

SAIC-N-2024

30-Jun-08
DATE APPROVED

QR NUMBER

15-Dec-09

MECH-

Attachment 1 -- SASD AC-036397


(Anchoring Details for Castable Refractories)
Note: Use this Attachment on Layout (Pre-Welding) & Final Inspections

Page 9 of 12

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST


Pre-Application Inspection of Castable & Brick Refractory

SAIC NUMBER

SAIC-N-2024

30-Jun-08
DATE APPROVED

15-Dec-09

QR NUMBER

MECH-

Attachment 2 -- SASD AB-036914


(Support Details @ Nozzles & Manways for
Castable Refractory)

Note: Use this Attachment on Layout (Pre-Welding) & Final Inspections

Page 10 of 12

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST


Pre-Application Inspection of Castable & Brick Refractory

Page 11 of 12

SAIC NUMBER

SAIC-N-2024

30-Jun-08
DATE APPROVED

15-Dec-09

QR NUMBER

MECH-

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3
SAIC NUMBER

SAUDI ARAMCO INSPECTION CHECKLIST


Pre-Application Inspection of Castable & Brick Refractory

SAIC-N-2024

30-Jun-08
DATE APPROVED

15-Dec-09

QR NUMBER

MECH-

Attachment 3 -- SASD AB-036396 (Hexsteel Details)


Note: Use this Attachment on Layout (Pre-Welding) & Final Inspections

Page 12 of 12

Vous aimerez peut-être aussi