Académique Documents
Professionnel Documents
Culture Documents
Rev 3
SAIC NUMBER
SAIC-N-2035
PROJECT TITLE
WBS / BI / JO NUMBER
EQUIPMENT ID NUMBER(S)
EQUIPMENT DESCRIPTION
REV. NO.
SYSTEM ID.
MH's SPENT
TRAVEL TIME
REFERENCE
PASS
FAIL
General Requirements (Note: This Checklist applies to Fireclay Brick Refractories Only per SAES-N-130)
A1
Sch Q,
Section 3.1
A2
Sch Q,
Section 3.1
A3
Sch Q,
Section 3.1
A4
Procedure Scope covers fireclay bricks used for bridges and dividing
walls in boilers, sulfur recovery unit equipment and process heaters.
SAES-N-130,
Para. 1.1
A5
SAES-N-100,
Sec. 3
A6
SAES-N-100,
Section 3 & 4
A7
SAES-N-100,
Para. 3.2
A8
SAES-N-130,
Para. 5.2
A9
SAES-N-130,
Section 5
A10
Procedure states that "Refractory Installation" work will not begin until
Refractory work procedures have been approved by Company.
Page 1 of 9
PLANT NO.
A.
MECH-
CONTRACTOR / SUBCONTRACTOR
ACCEPTANCE CRITERIA
QR NUMBER
15-Dec-09
EQPT CODE
ITEM
No.
30-Jun-08
DATE APPROVED
N/A
RE-INSP DATE
Rev 3
SAIC NUMBER
SAIC-N-2035
WBS / BI / JO NUMBER
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
B.
Materials Section (Procedure lists material requirements, storage & handling controls)
B1
SAES-N-130,
Para. 7.1
B2
SAES-N-130,
Para. 7.2
B3
SAES-N-130,
Para. 1.1
B4
SAES-N-130,
Para. 6.4
B5
SAES-N-130,
Para. 6.2
C.
C1
Types of materials supplied are checked upon receipt including the data
sheets & specific mixing instructions for materials (mortars, bricks).
C2
C3
C4
D.
D1
SAES-N-130,
Para. 8.3
SAES-N-130,
Para. 8.3
SAES-N-130,
Para. 8.3
SAES-N-130,
Para. 8.3
SAES-N-100,
Para. 9.1
See Note 2.
D2
Fired Process Heater refractory is installed per the API 560, Section 11
specific requirements, unless otherwise specified.
See Note 3.
Page 2 of 9
SAES-N-100,
Para. 3.2
30-Jun-08
DATE APPROVED
15-Dec-09
QR NUMBER
MECH-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
Rev 3
ITEM
No.
SAIC NUMBER
SAIC-N-2035
WBS / BI / JO NUMBER
ACCEPTANCE CRITERIA
REFERENCE
SAES-N-130,
Para. 8.3
(SA
Checklist)
E.
E1
SAES-N-130,
Para. 6.1
E2
Walls, arches & floors allow for proper expansion of parts & multilayer
bricks have staggered joints that are not continuous through the lining.
(API 560, Para. 11.1.3)
SAES-N-130,
Para. 1.1
E3
Target walls with flame impingement on both sides (Bricks are laid dry or
mortared joints) have expansion joint gaps packed with ceramic fiber
strips having a service temp rating equal to brick. (API 560, Para. 11.1.7)
SAES-N-130,
Para. 1.1
E4
Floor bricks are not mortared & have a 13 mm expansion gap on a 1.8
meter interval (gaps are packed with fibrous strip refractory material).
SAES-N-130,
Para. 6.2
F.
F1
Brick lining on vertical flat casing is tied back (minimum 15% of bricks) &
supported by structural steel framing members with tie members
constructed of austenitic alloy material.
SAES-N-130,
Para. 6.3
F2
Tie backs are not required when the radius of the curvature of cylindrical
casing keys the bricks.
SAES-N-130,
Para. 6.3
F3
SAES-N-130,
Para. 6.4
G.
Installation of Firebricks & Tiles (API 560 Fired Process Heaters Specific Requirements)
G1
SAES-N-130,
Para. 1.1
G2
SAES-N-130,
Para. 1.1
Page 3 of 9
30-Jun-08
DATE APPROVED
15-Dec-09
QR NUMBER
MECH-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
Rev 3
SAIC NUMBER
SAIC-N-2035
PROJECT TITLE
WBS / BI / JO NUMBER
ITEM
No.
ACCEPTANCE CRITERIA
30-Jun-08
DATE APPROVED
REFERENCE
G3
Vertical expansion joints are provided at gravity wall ends and required
intermediate locations. All expansion joints are kept open & free to
move.
If the expansion joint is formed with lapped brick, no mortar is used. it
shall be, a dry joints.
(API 560, Para.11.2.4)
SAES-N-130,
Para. 1.1
G4
Expansion joint gaps are packed with ceramic fiber strips with a service
temperature rating equal to or greater than brick. (API 560, Para. 7.1.7)
SAES-N-130,
Para. 1.1
H.
H1
SAES-N-130,
Para. 8.1
H2
ASTM C134 production testing (Size and Bulk Density, Squareness and
Warpage of Firebricks) was performed per SA Insp. Form 175-328110
Line 23 with certificates available.
SAES-N-100
Sec. 3.2
H3
SAES-N-130,
Para. 8.2
QR NUMBER
15-Dec-09
MECH-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
REMARKS:
REFERENCE DOCUMENTS:
1.
2.
3.
4.
5. API RP 936 -- Refractory Installation Quality Control Guidelines - Inspection & Testing Monolithic Refractory Lining & Materials (Nov 2008 Edition)
ATTACHMENTS:
1. Attachment 1, API RP 936 Table 1
2. Attachment 2, SA Inspection Requirement Form 175-328110 (Refractories)
NOTES: 1. Contractor's refractory installation procedure must follow the SA mandatory specific installation procedure SAES-N-130. Contractor can
copy & paste much of the SA refractory procedure into his own procedure. However, Refractory & Equipment Manufacturer requirements must also
be incorporated into the procedure (per SAES-N-130, Para. 5.2 for procedure section)
2. Use Table 3 Mandatory Refractory Systems of SAES-N-100 (Not Attached) for Receipt & Pre-installation inspection checks of firebricks.
3. Incorporate API 560 general/specific requirements & utilize API 560 Section 7 as a checklist during Heater construction. (This is Not Attached).
Process Heater refractory procedures may be submitted separately from other equipment refractory procedures with a heater installation package.
Ensure SAES-N-100, Table 3 & Notes (Not attached) are incorporated in procedure to check Process Heater Refractory materials on installation.
Contractor / Third-Party
Saudi Aramco
Construction Representative*
PMT Representative
QC Inspector
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
PID Representative
Performed Inspection
QC Supervisor
T&I Witnessed
Name, Initials and Date:
Name, Organization,
Initials and Date:
Page 4 of 9
Rev 3
SAIC NUMBER
SAIC-N-2035
PROJECT TITLE
ITEM
No.
WBS / BI / JO NUMBER
ACCEPTANCE CRITERIA
Quality Record Approved:
REFERENCE
30-Jun-08
DATE APPROVED
15-Dec-09
QR NUMBER
MECH-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
Y = YES
N = NO F = FAILED
Name, Organization,
Initials and Date:
Page 5 of 9
Rev 3
SAIC NUMBER
SAIC-N-2035
30-Jun-08
DATE APPROVED
15-Dec-09
Page 6 of 9
QR NUMBER
MECH-
Rev 3
SAIC NUMBER
SAIC-N2035
30-Jun-08
DATE APPROVED
15-Dec-09
Page 7 of 9
Rev 3
SAIC NUMBER
Page 8 of 9
SAIC-N2035
30-Jun-08
DATE APPROVED
15-Dec-09
Rev 3
SAIC NUMBER
Page 9 of 9
SAIC-N2035
30-Jun-08
DATE APPROVED
15-Dec-09