Vous êtes sur la page 1sur 90

PJ Enterprises

Customer Service Improvement Plan


By Designing Women, LLC

Designing Women, LLC


Pg. 1

PJ Enterprises Customer Service Improvement Plan

Contents
1.Project Gap Analysis Strategy........................................................................................................................................
Information Needed...........................................................................................................................................................
Team Strategy...................................................................................................................................................................
Analysis Plan.....................................................................................................................................................................
Questions to Ask...............................................................................................................................................................
Roadblocks & Dependencies............................................................................................................................................
Strategies to Mitigate Risks...............................................................................................................................................
2.Performance Analysis Report....................................................................................................................................... 10
Introduction...................................................................................................................................................................... 10
Background..................................................................................................................................................................... 10
Purpose of the Report..................................................................................................................................................... 10
Analysis Methods............................................................................................................................................................ 10
Data Summary: Customer Satisfaction Ratings.............................................................................................................. 11
Data Summary: TO Employee Job Approval Ratings..................................................................................................... 11
Data Summary: PJ Enterprises Catalog Sales History.................................................................................................. 12
Analysis Findings............................................................................................................................................................. 12
Identification of Needs..................................................................................................................................................... 14
Recommended Solutions for PJ Enterprises to Consider................................................................................................14
Proposed Solutions for Consulting Firm to Carry Out...................................................................................................... 15
Evaluation plan................................................................................................................................................................ 16
Request for Proposal....................................................................................................................................................... 16
3.PJ Enterprises Customer Service Improvement Plan.................................................................................................17
Project Information.......................................................................................................................................................... 17
Description of Work......................................................................................................................................................... 19
Project Deliverables......................................................................................................................................................... 20
Project Completion Criteria.............................................................................................................................................. 22
Project Milestones........................................................................................................................................................... 22
Possible Problems / Constraints...................................................................................................................................... 23
Assumptions.................................................................................................................................................................... 25
Vendor Assistance Requirements / External Dependencies............................................................................................25
Budget............................................................................................................................................................................. 26
Terms and Conditions...................................................................................................................................................... 29
4.PJ Enterprises Customer Improvement Project Management Plan..........................................................................32
Project Information.......................................................................................................................................................... 32
Scope Statement............................................................................................................................................................. 33
Deliverables..................................................................................................................................................................... 33
Exclusions/Out-of-scope.................................................................................................................................................. 35
Project Completion Criteria.............................................................................................................................................. 36
External Dependencies................................................................................................................................................... 36
Assumptions.................................................................................................................................................................... 36
Constraints...................................................................................................................................................................... 37
Designing Women, LLC
Pg. 2

PJ Enterprises Customer Service Improvement Plan

Project Milestones Overview........................................................................................................................................... 37


Project Approach and Primary Plans............................................................................................................................... 38
Scheduled Project Team Meetings and Status Reports................................................................................................... 39
Issues Management........................................................................................................................................................ 39
Risk Assessment and Mitigation Plans............................................................................................................................ 40
WBS and Diagram Customer Service Improvement Training.......................................................................................42
In-Classroom Customer Service Training Course Schedule............................................................................................ 44
In-Classroom Customer Service Training Course Gantt Chart........................................................................................ 45
Change Management Plan.............................................................................................................................................. 46
Responsibilities............................................................................................................................................................... 47
Communication Plan....................................................................................................................................................... 48
Project Plan Approvals.................................................................................................................................................... 52
5.Design Document for PJ Enterprises Customer Service Training Course...............................................................53
Document Description..................................................................................................................................................... 53
Purpose of the Course..................................................................................................................................................... 53
Audience Description....................................................................................................................................................... 53
Major Course Objectives................................................................................................................................................. 53
Learning Assessment for Course.................................................................................................................................... 53
Instructional Strategies for Course.................................................................................................................................. 54
Media............................................................................................................................................................................... 54
Development Tools.......................................................................................................................................................... 54
Class/Seat Time of Course.............................................................................................................................................. 54
Course Outline................................................................................................................................................................ 54
Development Time........................................................................................................................................................... 56
Support requirements...................................................................................................................................................... 56
Ownership....................................................................................................................................................................... 56
Project Sign-off................................................................................................................................................................ 56
Appendix A:

Telephone Operators (TOs) Job Task Analysis...................................................................................57

Appendix B:

Detailed In-Classroom Customer Service Course Outline.................................................................58

Designing Women, LLC


Pg. 3

PJ Enterprises Customer Service Improvement Plan

1. Project Gap Analysis Strategy


Information Needed
Designing Women has determined the following information is needed from PJ Enterprises, as grouped
by divisions (or stakeholders), in order to analyze the gap between actual and expected business and
performance results:

1.

Customer Service Representatives (CSSs) and Telephone Operators


demographics (age, gender, ethnicities for language purposes, level of
technical ability, etc.) of CSSs and Operator staff for potential training purposes that
could result from upgraded hardware and equipment to IT/phone systems
level of knowledge of products per catalog / season
level of knowledge of channels available for support via management
obstacles to providing the best quality service
most frequent/difficult customer issues
most frequent/difficult challenges with catalog product information
challenges posed per the work environment (cultural and
technological)

2. Operations (IT/Telephone & Warehouse)


current demographics (age, gender, ethnicities for language
purposes, level of technical ability, etc.) of IT/Phone infrastructure and warehouse
staff for potential training purposes that could result from upgraded hardware,
software, and equipment for IT, phone systems, possible online additions, and
warehouse improvements
current capacity versus future capacity of IT, phone and
warehouse technology
current capacity versus future capacity of supply chain
management
challenges posed per the work environment (cultural and
technological)
current office and warehouse buildings space capacity for
office and warehouse staff/storage versus anticipated future growth of office,
warehouse staff/storage and possible online presence
current infrastructure for online presence or cost for putting
that in place or out-sourcing
cost comparison for updated VoIP phone system vs. the current
phone system
3. Sales and Human Resources Management Directors
validation of target audience (women ages 25 - 55) and their
purchasing motivations/preferences, as well as other potential audiences and their
purchasing motivations/preferences
confirmation of all sales media and vehicles (print catalogs, telephone,
in-person solicitation, web site, television advertising) and total number of sales per
catalog / season and annually
sales figures per most popular/purchased/expensive items the previous
and current years
costs for current year catalog customer lists and print production and
mailing
level of interest/motivation/effect of the current incentives program
provided to customer service and operations (warehouse) staff for error-free work
Designing Women, LLC
Pg. 4

PJ Enterprises Customer Service Improvement Plan

level of interest/motivation among staff for incentivizing monthly


company staff meetings
4. Customer Service Staff Trainers - Catalog Director (Judie Thompson) and
Merchandise Manager (Sheena Perez)

demographics (age, gender, ethnicities for language purposes,


level of technical ability, etc.) of CSSs and Operator staff

challenges or issues the trainers faced delivering the training


via in-person PPT presentation, and any other training options previously
considered

length of time it took staff to retain product line knowledge


that changed quarterly / level of comfort among customer service staff with
changes to the product line

validation of customer service staff (CSSs and Operators)


skills and experience upon hire / difference in job criteria for both positions

validation of all training courses and resources provided other


than the in-person PPT training (e.g. new hire orientation, formal customer service
training, etc.)

target delivery date, estimated length of time to produce new


training(s) and recommended training activities/tactics appropriate to the customer
service staff

gap between average number of calls serviced per hour (3) and
target number of calls per hour (6)

determination of number of calls serviced and number of


operators needed and in order to be profitable

validation of highest selling products and products that receive


the most complaints

Team Strategy
Designing Womens strategy will include using multiple vehicles to obtain research information from
each of the following divisions/employees of PJ Enterprises that will inform the gap between current
and expected performance:
1. CSSs and Operators -- Survey and/or questionnaire delivered via individual interviews
2. Operations Staff (IT/Phone/Warehouse and perhaps the Business Analyst) -- Interview
of upper management in these areas & Business Analyst. Surveys of remaining staff if
necessary.
3. Sales and Human Resources Management -- In-person group interview
4. Training Staff -- In-person individual interviews

Designing Women, LLC


Pg. 5

PJ Enterprises Customer Service Improvement Plan

Analysis Plan
Acti
vity
/Me
tho
d

Purpose or Information
You Hope to Gain

P
e
r
s
o
n
R
e
s
p
o
n
s
i
b
l
e

Survey and/or
questionnaire
delivered via
individual interviews
with CSSs and
Operators

How CSSs and Operators can receive support


to produce better work quality

Cynthia Casillas

Interview with upper


IT/Phone/Warehouse
management with a
possibility of surveys
for the remaining staff
within those areas
depending on the
future sales path
chosen by
management.

Is the current method of taking sales the most


efficient? Could the addition of an online
presence (website) negate the need for highly
trained phone operators and thereby reduce
not only the need for training but also the
number of telephone operators needed?
Would this online presence be more
appealing to the younger targeted audience?
Is the current phone system a traditional
system? Is so, has VoIP vs. tradition system
costs been compared?

Lorraine Ibe

Group or Individual
Interviews with Sales
and HR Management
Team followed up
with a questionnaire if
necessary.

Target and potential audience/customer


purchasing history, motivation and
preferences; validate drivers behind previous
and current year sales; analyze sales
production costs for previous and current
years to forecast costs in terms of future sales
increases.

Leila Rao

Individual Interviews
with Catalog Director
(Judie Thompson) and
Merchandising
Manager (Sheena
Perez)

The problems that they have with the current


PPT training, what kind of training do they
envision for the future, and what tools or
references do they hope for to better assist the
staff and customers.

Erin Skorch

Designing Women, LLC


Pg. 6

PJ Enterprises Customer Service Improvement Plan

Questions to Ask
[CSSs and TOs]

How would you rate the customer service training currently provided?
A. Excellent
B. Very good
C. Good
D. Fair
E. Poor

Number of years in current position?


A. 0-2
B. 3-5
C. 5-10
D. 10+

Does your office use quality communication equipment?

On average, how many calls are responded to within an hour?

On average, how many minutes does 1 call take?


A.
0-2min
B.
3-5min
C.
5-10min
D.
10+

Does your office have a set schedule for breaks?

How do you currently handle customer complaints?


A. Transfer to supervisor
B. Transfer to CSSs

Does your office provide information on most popular items being sold?

Are you familiar with the computer system used for sales?

How do you currently acquire knowledge on an item that a customer requests?

How often do you revisit the catalog when it is updated?

Do you receive incentives from your supervisors when you achieve customer
satisfaction?

How does your office handle safety measures?

[Operations Upper Management (IT/Phone, Warehouse, and perhaps


Business Analyst]

Will the current phone system be able to handle an increase in calls so that the
phone system supports and doesnt detract from the customer service interaction?

Has the current traditional phone system been cost compared to a VoIP system
which could provide PJ Enterprises more affordability, improved functionality, high call
quality, and less maintenance?

Has the idea of an online presence been explored in terms of long term profit
gain? This of course opens up a long list of infrastructure and personnel issues to convert
to, or add additionally, such a sales option. Outside specialty vendors would need to be
consulted.

If a decision to proceed with only the current sales option:

What is the average number of calls coming through the


system per hour if they receive if their target is 6 calls an hour?

How much is shipped now and what is the maximum capacity


for the current supply chain?

Will the current supply chain system handle an increase in


sales so that shipping is handled successfully and doesnt detract from the customer
service interaction?
Designing Women, LLC
Pg. 7

PJ Enterprises Customer Service Improvement Plan


What are the demographics (age, gender, ethnicities for
language purposes, level of technical ability, etc.) of IT/Phone infrastructure and
warehouse staff for potential training purposes that could result from upgraded
hardware and equipment for IT/phone systems and warehouse improvements?

What is the average number of phone calls the current phone


system processes per hour / day as well as the expected number of phone calls with
the projected increase in sales (or average number of phone calls per hour / day that
the new phone system can process)?

What is the average length of a work shift per day, duration of


lunch break (if applicable), and total number of breaks per shift or per hour?

What is the average number of shipments shipped per catalog /


season this year, as well as projected number of shipments shipped per catalog /
season for the next year?

Is there satisfaction with office and warehouse buildings? Is


there adequate space for current office and warehouse staff/storage capacity, as
well as a potential increase in space needs for future growth of office and
warehouse staff/storage capacity?

[Sales and HR Management]

Have you researched other target audiences/customers in addition to


ages women ages 25 - 55?

If so, please define those audiences (or follow-up with information) by


gender, age, location/region, income range if applicable/known, and/or ethnicity if
applicable/known.

Did your research on other target audiences/customers indicate any


motivation trends for purchasing (e.g. personal use versus gifts for special occasions)?

Did your research on other target audiences/customers indicate any


trends in most desired products and why?

What is the total number of individual products PJ Enterprises has


offered each year for the past six years?

What was the total number of individual products offered per each
catalog/season this past year?

What is PJ Enterprises total number of sales per catalog/season and


annually?

What are the top ten highest selling and the top ten most popular items
purchased per catalog/season and annually?

Do you know or have customer feedback on why those products are


the highest selling and/or most popular?

What are the top ten most expensive catalog items and their average
numbers sold per catalog/season?

What are the top ten lowest selling and the top ten least popular items
purchased (including those that receive the most complaints) per catalog/season and
annually?

What was the total annual cost of catalog customer lists purchased the
previous and current years?

What was the total print production cost per catalog the previous and
current years?

What was the total mailing distribution cost per catalog the previous
and current years?

What sales vehicles does PJ Enterprises use besides the telephone (e.g.,
in-person solicitation, web site, etc.)?

What advertising media does PJ Enterprises use (e.g., ads in print, TV,
online, social media, etc.)?

Do your advertising media/vehicles change per catalog and/or per


season?
Designing Women, LLC
Pg. 8

PJ Enterprises Customer Service Improvement Plan


What incentives are currently provided to customer service and
operations (warehouse) staff when they produce error-free work?

Do the incentives change at any time during the year? If so, what are
the reasons they change?

What is the total number of staff who have received incentive rewards
the previous year versus the current year for error-free work?

Was there an increase/decrease/maintenance in the number of staff who


received incentive rewards this current year?

What do you think is the reason or the reasons for this years rise in
customer complaints?

Do you know or have information that you could provide that indicates
the level of interest / motivation customer service and warehouse staff have regarding the
current incentives program?

What was the total number of PJ Enterprises staff per each year over
the past six years?

What is the average number of staff that attend monthly meetings? Do


you know which departments have higher staff attendance rates?

Do you know or have information that you could provide that indicates
the level of interest / motivation PJ Enterprises staff have regarding incentivizing monthly
company staff meetings?

What do you think are the top reasons for employee satisfaction and
dissatisfaction? Do you have additional information you can provide regarding employee
satisfaction and dissatisfaction?

What does PJ Enterprises do that supports a good work environment


for its employees?

What do you think PJ Enterprises can do to improve its current work


environment?

Are there any other internal key stakeholder groups/individuals that


you think we should include regarding this project that have not already been identified?
Please explain.

[Training Staff]

What issues did you have to deal with when it came to the PowerPoint
training?

What other kind of training tool would you consider for this type of content
other than the PowerPoint slides?

Tell me more about how much time it took to train the CSSs and Operators in
order to retain product line knowledge that changed quarterly? How did they adjust to new
products being added to the catalog?

Does PJ Enterprise have any other reference training material on the catalog
products they offer to support their staff when they take customer calls?

What types of skills or experience do you look for when hiring a telephone
operator/supervisor? Any formal customer service training included in the hiring process?

Do you happen to know why operators are only taking 3 calls per hour instead
of the targeted 6 calls? Could it be that they are routed to the CSSs because of lack of
product knowledge?

Do you know of any common complaints that customers have when calling in?
What issues do you want to deal with most?

What is the potential increase in calls have to be in order to be profitable? How


many telephone operators do you need to achieve that?

Do you happen to know some of the reasons why telephone operators leave the
company?

When would be the projected time that you would want this training delivered?
Designing Women, LLC
Pg. 9

PJ Enterprises Customer Service Improvement Plan


Do you have in mind any types of activities that would work well in this
training and fit the general audience of your employees? Also what type of training you
would like to see, such as more classroom training, online, or video, etc?

What level of education does the target audience most likely fall under?

What criteria CSSs have to meet versus telephone operators? How does their
knowledge and experience differ between CSSs and telephone operators?

Do you happen to know which products sell the most, and also which have the
most complaints?

Roadblocks & Dependencies

lack of client/stakeholder groups commitment to the project

client/stakeholder groups are unable to provide all information in a timely


fashion or provides incorrect answers/information

key stakeholder groups are unwilling to participate / information from one or


more of the four identified stakeholder groups is not received, which informs the overall
gap analysis

project team (Designing Women) did not identify key stakeholder groups to
gather information from that could inform the gap analysis

project team did not ask the right questions to receive information that could
correctly or fully inform the gap analysis

Strategies to Mitigate Risks

project team will work to build trust with the client/key stakeholders

project team will meet with sponsor first to request buy-in and support for
conducting gap analysis activities

project team will communicate/inform key stakeholder groups of the goal of


conducting the gap analysis activities first before initiating activities

project team will request additional time to gather needed information if


necessary

project team will review gathered information and determine the need to
follow-up with specific key stakeholder groups or individuals

project team will validate gap analysis findings with sponsor and key
stakeholder groups in order to receive feedback/approval

Designing Women, LLC


Pg. 10

PJ Enterprises Customer Service Improvement Plan

2.

Performance Analysis Report


Introduction
This report is submitted to the owners and managers of PJ Enterprises, as a report of findings and
recommendations on the performance issue analyzed by Designing Women, LLC.

Background
The team of instructional designers, Designing Women, LLC, met with Jane Smith (Project Sponsor),
Judie Thompson (Catalog Director), and Sheena Perez (Merchandising Manager) of PJ Enterprises, to
discuss concerns about reports of poor telephone etiquette and lack of product knowledge by the
telephone operators at this mail-order catalog business. They also performed two surveys given to the
telephone operators (TO) and the Customer Service Supervisors (CSS), as well as interviewed staff of
the IT and Human Resources departments.
At the time, management expressed concerns that poor customer service might be directly related to the
lack of TOs product knowledge and their inability to access the correct product information and
provide it to the customer in a timely manner. They asked Designing Women, LLC to create a training
program for the telephone operators and supervising staff on customer service, product knowledge and
accessibility.
When Designing Women, LLC reviewed some of the data from the Gap Analysis, our first
recommendation was to do a Performance Analysis to determine if training is the correct solution to the
problem, just one of several solutions, or not a solution at all. PJ Enterprises agreed to this study.

Purpose of the Report


The purpose of the Performance Analysis for PJ Enterprises is to determine the causes of and possible
solutions to reports of poor telephone customer service and product knowledge at PJ Enterprises.

Analysis Methods
To determine causes and recommended solutions, Designing Women, LLC performed the following
tasks:

met with the project sponsor, catalog director, and merchandising manager to
obtain additional information, including relevant data, and individual observations

held interviews, work observations, and surveys with the telephone operators
and supervisors to determine service issues and work towards resolution of problems

held a group interview with operators to obtain their perception of problems


and prior training

problem

met with IT and Human Resources staff to obtain their perspective on the

listened to 15 recorded calls and y-jacked with five telephone operators for
three calls each:

time each call took in order to meet the six call hour requirement
time it took for the telephone operator to look up the product

information
Designing Women, LLC
Pg. 11

PJ Enterprises Customer Service Improvement Plan

number of times a customer asked to speak to a supervisor while


waiting for product information

number of times an order was cancelled, and/ or customer dissatisfied

Data Summary: Customer Satisfaction Ratings


PJ Enterprises has experienced their largest dip in customer service ratings since the inception of the
company in 2008. This years figures show a significant drop of 30% in customer satisfaction (based on
complaints with the telephone operators as compared to last year.)

Data Summary: TO Employee Job Approval Ratings


Recent surveys indicate that over 50% of the PJ Enterprises mail order employees are dissatisfied with
their jobs. This dissatisfaction if left unchecked could lead to high employee turnover.

Designing Women, LLC


Pg. 12

PJ Enterprises Customer Service Improvement Plan

Data Summary: PJ Enterprises Catalog Sales History


PJ Enterprises sales have steadily increased with a substantial increase from last year.

Analysis Findings
PJ Enterprises is moving toward increasing their sales for growth in the company. PJ Enterprises
mission is to provide customer satisfaction through excellent and knowledgeable customer service.
After meeting with the managers, focusing on how to improve customer service with the telephone
Designing Women, LLC
Pg. 13

PJ Enterprises Customer Service Improvement Plan

operators (TOs) will help in meeting the goals for increasing sales through improvements in the
customer service department with the TOs. At this time, the customer service complaints are up 30%
from last year. If the customer service complaints decline, PJ Enterprise will meet the desired results of
customer service satisfaction in addition to the benefit of increasing sales. After reviewing data, TOs
currently take in 3 calls per hour. The goal is to increase calls by 3 more per hour by focusing on
delivering customer satisfaction.
The current conditions that affect the TOs performance at PJ Enterprises are:

over 40% increase of sales this past year resulted in


a higher volume of calls that TOs were expected to process and a 30% increase in
customer service complaints

TOs lack of product knowledge

TOs have limited product information


available to them and its provided in a way that doesnt support their needs product guide has the same
information as the customer catalog and does not have customer inquiry
specific information (e.g. product care instructions, shipping costs, etc.), which
doesnt offer the information TOs need to answer customer questions
adequately
product guide does not
provide easily obtainable information; its only offered in a hard copy format
(not integrated into online ordering system for easy search functionality) and
the print layout is confusing/inconsistent causing TOs to spend too much time
flipping through the guide for product information they dont already know in
order to answer customer questions

Training and training resources do not


support product knowledge retention and customer service skills TO training is only provided
on two topics -- the order entry system and new products

Order entry
system training is only provided during new hire orientation for a few
hours and does not allow for hands-on demonstrations to enable employees
to retain procedural information that results in employees taking extra
time at the start of their jobs to relearn the system on the job during
customer calls

Quarterly
new product training is delivered via one format only - one-way
communication (instructor led class) that doesnt account for different
employee learning styles or different delivery tactics that could support
product information retention over time

new product
guide is not available at the time of the quarterly new product training so
TOs cannot take notes during training to help with product information
retention

quarterly new
product training doesnt provide time for TOs to ask specific questions on
products that will help them retain product information or answer specific
customer questions
TOs
do not have any supportive guides for approaches to resolving customer
complaints
Live
over-the-phone customer training support is not provided when TOs experience
customer complaints so TOs are forced to learn through trial and error at the
expense of the customers experience
Designing Women, LLC
Pg. 14

PJ Enterprises Customer Service Improvement Plan

inconsistent definition of service across all

organization levels

management defines service as


knowledgeable/excellent interactions that result in satisfied customers; CSS/TOs
believe service is the act of answering customer questions/complaints only

CSS/TOs do not have up-to-date


standard/consistent phone etiquette or problem resolution guidelines or training to
support positive phone interactions

process of TOs forwarding unresolved


customer questions to CSS isnt time efficient and adds to customer aggravation

lack of standard HR policies/procedures and


inadequate incentives that affect employee retention

specific supervisor/TO job


requirements are only communicated during the hiring process and are not
incorporated into the performance evaluation process

employees are asked to rate their own


performance which can result in biased or misinformed performance results and
lead to low employee morale

current incentive program


goals/rewards are not easily attainable
many TOs cannot reach goal
of 6 or more calls per hour due to not having the information they need to
perform efficiently
only one reward exists for
reaching performance goal of 6 calls per hour -- product discounts for one
week only -- and this results in TOs spending more of their own money, which
is not a reward

TOs are not compensated for trainings


that take place during their work shift hours

monthly employee meetings are used


to motivate employees to sell more and do not offer other constructive instruction
or ideas for achieving higher sales other than to process 6 or more calls per hour

monthly meetings are not scheduled to


accommodate employees schedules and employees are expected to take time away
from their regular work to attend but still be able to achieve the goal of 6 calls per
hour

compensation for attending monthly


meetings is not provided

Outdated Customer Service Equipment/Technology

Slow equipment can add to slower TO


call times (employees can choose to purchase their own out of pocket)

Outdated order entry system software


that will be updated will require TO to learn how to use this new system and could
possibly impact TO call times

new order entry system can eventually


integrate product information but IT division will need to plan for that software
upgrade because its not available at the time of its initial launch

Identification of Needs
As a result of our analyses, Designing Women, LLC have identified PJ Enterprises to have the
following needs in order to meet or exceed their target business goals for the new fiscal year.

TO and CSS need adequate training and product information support aids in order to perform their job at the highest
volume level desired, namely 6 calls per hour, and to minimize the product return rate.
Designing Women, LLC
Pg. 15

PJ Enterprises Customer Service Improvement Plan

Product information support aids need to be consistently organized and provide ease of use thereby providing TOs and
CSSs with necessary product information for customer ordering inquiries.
TOs and CSSs need formal usage training of the product support aids.
TOs and CSSs product knowledge, while using product support materials, needs to be assessed prior to going live with
customers.
Proper phone etiquette needs to be ensured through proper training.
PJ Enterprises incentive program for error-free service needs to be re-evaluated including pay scale increase incentives
and compensation for training time.
Updating of TO equipment and physical features of work space need to be addressed.

Recommended Solutions for PJ Enterprises to Consider


Designing Women recommends the following actions to be taken on the part of PJ Enterprises
management team:

Clarify catalog product information through reference guides

Provide each TO with an organized reformatted product catalog guide for


workstations (with labeled pictures, item number and differentiating categories by tags,
dividers or colors-until the new entry system is available)

Best sellers items

Seasonal items

Year round product guide Summary about new product

The cost of the product

Include/create item number

Include/create style or category number

Consider paid in-service time for TO and CSS staff to practice different
customer scenarios in initial training

How to properly greet customers

Identifying customer wants by using listening techniques

Tips on making and closing the product

Provide customer service tips (job aid)

How to appropriately verbally communicate with customers


over the phone

Different strategies to use when customer satisfaction is


questionable based on the call

Tips on how to create a positive customer experience with PJ


Enterprises

Best practices for phone etiquette

Demonstrate the difference between a positive TO and non-approachable TO

Provide a guideline for tips on how to increase customer satisfaction

Develop Train-the-trainer training for PJ Enterprises training staff to conduct


improved quarterly meetings, consisting of training PJ Enterprises staff on best practices
for meeting preparation (agenda and training activities items), effective on-site meeting
coordination (administration, facilitation/moderation and training instruction), and post
meeting support (analysis and assessment delivery and reporting).

Clarify steps on using the order entry system

Provide training for TOs for the new order entry system

How items will be looked up

Shortcuts tips

How new order system will increase calls taken within an hour

Review and update HR job descriptions and skills requirements if necessary

Revise existing customer service incentives program to include monetary


rewards not tied only to product purchases (i.e. discounts) and that are offered during
holidays and/or year-round
Designing Women, LLC
Pg. 16

PJ Enterprises Customer Service Improvement Plan

Proposed Solutions for Consulting Firm to Carry Out


Designing Women, LLC is prepared to assist JP Enterprises with the following solutions:

Customer Service Staff Training and Resources Program Plan - we will


develop a new highly interactive training program plan that will strengthen customer
service/job skills and product knowledge retention, to include:
1. Training on the existing as well as the future new order entry system
2. Support for monthly meeting customer service training topics and activities
3. Quarterly training that incorporates customer scenario role-playing, customer service
best-practices, job aids, guidelines, etc.
4. Assessment strategies and evaluation tactics to measure training program
effectiveness
5. Program management execution timelines/schedules for all plan deliverables

New Product Guide and Reference Materials - we will update and


reorganize the existing product guide to be easy-to-use/understand and include new product
information specific to customer service staff needs (pictures, corresponding item/category
numbers, best-selling/seasonal items identifiers or sections, estimated shipping costs, care
instructions, etc.). We will work with the Training and Customer Service Staff to receive
feedback and input on its redesign.

Customer Service Incentives Program - we will provide specific


incentives recommendations aimed at helping to increase TO staff job satisfaction. The
proposed incentives will be tied to training, performance and salary reviews and can be
delivered during specific seasons, as well as throughout the year. We will work with PJ
Enterprises management, HR and Training staff to finalize and approve appropriate
incentives so they support company policies and procedures.

Integration and communication of new policies and standards - we will


work with PJ Enterprises management and HR to make sure our proposed Customer
Service Staff Training and Resources Program Plan aligns with and supports existing
and/or new changes to job descriptions, policies and company procedures. We will also
work with PJ Enterprises management to create effective change communications and
training as required.

Evaluation plan
Designing Women, LLC recommends that the management of PJ Enterprises evaluates the success of
the proposed solutions (more detailed information will be provided in the Customer Service Staff
Training and Resources Program Plan if requested):

conduct reviews of customer satisfaction surveys, monitor customer


calls, and review data of number of calls processed per hour as well as number of calls
escalated to supervisors on a quarterly basis during the first year.

evaluate sales data at the same intervals as compared to previous years


in order to account for the seasonal nature of the business.
Designing Women, LLC
Pg. 17

PJ Enterprises Customer Service Improvement Plan


administer assessments every six month to evaluate TO customer
service skills, order entry system skills, product knowledge retention, as well as TOs
response to effectiveness/impact of training, communications and incentives on their job
performance. These assessments can serve as a retraining of skills, as well as opportunities
to address changes to policies, standards and procedures at these times.

Request for Proposal


Designing Women, LLC has proven our expertise and value in assisting PJ Enterprises with all phases
of this project. Designing Women is especially skilled at training and communications development,
execution and assessment.
At your request, Designing Women, LLC will submit a proposal to provide the proposed solutions
listed above and to be carried out.

3. PJ Enterprises Customer Service Improvement Plan


Project Information
Client Name
PJ Enterprises

Stakeholders, Roles and Responsibilities

Designing Women, LLC


Pg. 18

PJ Enterprises Customer Service Improvement Plan

Stakeholder

Role

Responsibility

Estimated
Time
Investment

Jan
e
Ma
cKe
nzi
eSmi
th

Pr
oj
ect
Sp
on
sor
,
PJ
En
ter
pri
se
s

oversee all
aspects of project for PJ
Enterprises

She
ena
Per
ez,
Me
rch
and
isin
g
Ma
nag
er

Pr
oj
ect
M
an
ag
er,
PJ
En
ter
pri
se
s

consults
with and manages the Designing
Women, LLC project team

reviews and
provides subject matter expertise
input and final approval of
project deliverables and expenses

2%

Ray
Joh
nso
n

As
sis
ta
nt
M
er
ch
an
dis
in
g
M
an
ag
er,
PJ
En
ter
pri
se

Provide
subject matter expertise and
project insight/feedback

20%

Designing Women, LLC


Pg. 19

25%

review and
provide strategic input and final
approval of project deliverables
and expenses (including tiebreaking decisions)

identify and
designate appropriate team
resources

PJ Enterprises Customer Service Improvement Plan

s
Sar
ah
Co
mm
ons

De
sig
na
te
d
Cu
sto
m
er
Se
rvi
ce
Su
pe
rvi
so
r
(C
SS
),
PJ
En
ter
pri
se
s

Provide
subject matter expertise and
project insight/feedback

Provide
assistance with conducting
training

10%

Ma
ria
Go
me
z

De
sig
na
te
d
Cu
sto
m
er
Se
rvi
ce
Su
pe
rvi
so
r
(C
SS
),
PJ
En
ter
pri

Provide
subject matter expertise and
project insight/feedback

Provide
assistance with conducting
training

10%

Designing Women, LLC


Pg. 20

PJ Enterprises Customer Service Improvement Plan

se
s
Pau
la
Mo
ore

De
sig
na
te
d
Te
le
ph
on
e
O
pe
rat
or(
s)
(T
Os
),
PJ
En
ter
pri
se
s

Provide
subject matter expertise and
project insight/feedback on
training deliverables

5%

Ros
alin
da
San
che
z

De
sig
na
te
d
Te
le
ph
on
e
O
pe
rat
or(
s)
(T
Os
),
PJ
En
ter
pri
se
s

Provide
subject matter expertise and
project insight/feedback on
training deliverables

5%

Designing Women, LLC


Pg. 21

PJ Enterprises Customer Service Improvement Plan

TB
D

De
sig
na
te
d
Di
re
ct
or,
H
u
m
an
Re
so
ur
ce
s,
PJ
En
ter
pri
se
s

Provide
subject matter expertise and
approval of changes to job
descriptions and policies if
applicable

2%

Mi
ke
Me
rrill

Vi
ce
Pr
esi
de
nt,
Sa
les
,
PJ
En
ter
pri
se
s

Provide
additional specific sales
information for assessment
purposes

2%

Di
re
ct
or,
IT
O
pe
rat
io
ns,
PJ
En

Provide
additional specific subject matter
expertise if necessary

2%

TBD

Designing Women, LLC


Pg. 22

PJ Enterprises Customer Service Improvement Plan

ter
pri
se
s
Leil
a
Rao

Pr
oj
ect
M
an
ag
er,
De
sig
ni
ng
W
o
m
en,
L
L
C

Cy
nthi
a
Cas
illa
s

Bu
sin
es
s
A
na
lys
t/
Pr
oj
ect
Co
or
di
na
tor
,
De
sig
ni
ng
W
o
m
en,
L
L

Designing Women, LLC


Pg. 23

consults
with Project Sponsor and
manages the project, resources
and expenses to plan

accountable
for attaining project goals

accountable
for receiving project
acceptance/approvals from
Project Sponsor/Owner

Research,
liaise with client, provide
expertise, coordinate project
activities review/finalize client
deliverables

PJ Enterprises Customer Service Improvement Plan

100%

100%

C
Lor
rain
e
Ibe

Bu
sin
es
s
A
na
lys
t/
Te
ch
ni
cal
W
rit
er,
De
sig
ni
ng
W
o
m
en,
L
L
C

Research,
liaise with client, provide
expertise, coordinate project
activities, review/finalize client
deliverables

100%

Eri
n
Sko
rch

In
str
uc
tio
na
l
De
sig
ne
r/T
rai
ne
r,
De
sig
ni
ng
W
o
m
en,
L
L

Research,
liaise with client, provide
expertise, coordinate project
activities, review/finalize client
deliverables

100%

Designing Women, LLC


Pg. 24

PJ Enterprises Customer Service Improvement Plan

Description of Work
Project Background
PJ Enterprises and Designing Women, LLC met on 23 Jul 2014 to review the Performance
Analysis Report developed by Designing Women, LLC. It was decided and approved that
Designing Women will develop a comprehensive Customer Service / Product Training and
Resources Program, Customer Service Staff Incentives Plan, and Internal Communications
Plan for New Policies and Procedures for PJ Enterprises, a mail-order catalog company.

Business Objectives
1. To provide training, incentives and associated communications that will increase Telephone
Operators (TO) overall job performance within eighteen (18) months

increase TOs overall product knowledge by


70% within eighteen (18) months

increase TOs ability to quickly and easily


find/locate product specific information by 70% within six (6) months

increase TOs accurate use of the telephone


system supporting a quality customer service experience by 70% within twelve (6)
months

train 100% of Customer Service Staff


(CSS/TO) to accurately use the new Customer Order Entry System
2. To improve Telephone Operators (TO) job satisfaction and employee retention rates by 50%
within eighteen (18) months

Project Scope
Designing Women, LLC will develop a series of training, incentives and communications plans
and execute them to support PJ Enterprises performance improvement objectives for its
Telephone Operators (TOs) in delivering improved quality customer service.
The individual plans within this proposal will each include detailed timelines/schedules,
assessment tactics for evaluation purposes and a proposed budget for all deliverables from
initiation, to development, to execution, to transition (or on-going maintenance support) for two
contract years, starting July 29, 2014 and effective through June 30, 2015.

Out of Scope
Designing Women, LLC will not include nor is responsible for:

purchasing/installing technology software and


equipment in CSS/TO offices and workstations

purchasing/installing office furniture or


supplies in CSS/TO offices and workstations

changes to any training course content postclient final approval unless additional expenses for changes to design and
production are approved by the client
Designing Women, LLC
Pg. 25

PJ Enterprises Customer Service Improvement Plan


changes to any training resources and
reference materials, including the Product Catalog Guide, post-client final approval
and production, unless additional expenses for changes to design and production
are approved by the client

changes to any training courses, resources and


reference materials due to changes in phone or IT software or equipment

changes to any HR policies and procedures


that impact any project deliverables post-client final approval and production

meeting space/location, AV/IT requirements


and equipment, administrative tools, food/beverage for monthly staff meetings, inperson classroom trainings and CBTs

compensation (travel/wages) for Customer


Service staff attending monthly staff meetings, in-person classroom trainings and
CBTs.

Project Deliverables
Designing Women, LLC will deliver the following:
A: Customer Service / Product Training and Resources Program Plan
A1: Train-the-Trainer Training to Improve Monthly Customer Service Staff Meetings
Up to forty (40) hours per month / for the first four (4) months of DW train-the-trainer support
consisting of training PJ Enterprises staff on best practices for meeting preparation (agenda and
training activities items), effective on-site meeting coordination (administration,
facilitation/moderation and training instruction), and post meeting support (analysis and assessment
delivery and reporting).
A2: Quarterly In-classroom Training on Catalog Products and Customer Service
Improvement
Two (2) 60-minute courses on seasonal products, one (1) 60-minute course on existing products
(both held Sept. 14 and Mar. 15) and one (1) 90-minute customer service improvement course
(Sept. 14):

Two (2) 60-minute sessions on new seasonal products (held


2x/Sept. 14 and 2x/Mar. 15) added to the existing catalog to include how to utilize the
new catalog product guide and reference materials.

One (1) 60-minute session (held 1x/Sept. 14) and 1x/Mar. 15) on
existing changes to catalog products from the previous quarter to include how to utilize
the new catalog product guide and reference materials

One (1) 90-minute Customer Service Improvement Course (held


Sept. 14):

One (1) 30-minute lesson Phone Technology


How to properly answer, hold, and transfer calls to include a role- playing
scenario and quiz to assess TOs ability to perform the tasks successfully

One (1) 30-minute lesson Professional


Customer Service Etiquette - Learning and performing formal greetings,
responses, etc.

One (1) 30-minute lesson Managing


Customer Conflicts - How to handle customer conflict and response to problems
successfully, including role-play scenarios.

Supporting Print and Online Training Reference Materials for


each of the five (5) courses (e.g. job aids, guidelines, FAQs, etc.)

Revised PJ Enterprises Product Catalog Guide with new, easy-touse/understand catalog product guide to include new product information specific to
Designing Women, LLC
Pg. 26

PJ Enterprises Customer Service Improvement Plan

customer service staff needs (pictures, corresponding item/category numbers, bestselling/seasonal items identifiers or sections, estimated shipping costs, care instructions,
etc.)

Training on Catalog Products Course Facilitation Guide -- electronic


copy of the facilitators guide to conduct, the quarterly in-person trainings on catalog
products and their associated reference materials
A3: Computer-Based Training (CBT) for TOs on the Existing and New Customer Order Entry
System
Five (5) 30-minute sessions on using the current and new customer order entry systems to include:

Entering and Removing Customer

Editing/Updating Customer Order

Authorizing Orders for Supervisory

Orders
Entries
Approval

Differences Between the Existing


and New Customer Order Entry Systems - a hands-on demonstration

Assessing Your Customer Order


Entry System Knowledge
A4: Training Program Assessment Strategies and Evaluation Activities/Tactics to measure
effectiveness
The following activities will be performed:

CSS/TO Training Feedback Group - select volunteer


CSSs/TOs will be recruited to participate and provide feedback on all proposed training,
incentives and communications plans as well as pilot training testing to develop key staff
buy-in, create advocates for change and ensure all deliverables are on-point per this key
stakeholder group

Post Training Assessment -- each course will have a


post-training assessment activity (i.e. observances via in-person and on customer calls,
reviews of customer satisfaction surveys, etc.) aligned to all proposed course objectives that
will gauge the quality and efficacy of the training;

Customer Service Staff Meeting Assessment - after


the first initial monthly meeting that Designing Women, LLC supports, a post-meeting
assessment activity (i.e. survey, interviews, etc.) aligned to the proposed meeting objectives
will be delivered to gauge the quality and efficacy of the meeting content; additionally
continued assessment will occur every quarter to track progress against measures
A5: Training Program Management Execution Project Plan
The project plan will include detailed timelines/schedules and roles/responsibilities for all program
deliverables from initiation, to development, to execution, to transition or on-going maintenance
support for two contract years, starting July 2014 and effective through end-of-June 2015. Additional
contract work can be addressed on an as-needed basis, as well as post-contract based on PJ
Enterprises needs.
B: Customer Service Staff Incentives Plan
To support PJ Enterprises goal of increasing TO staff job satisfaction, the following activities will be
performed in coordination with and support of Human Resources and Management:
Designing Women, LLC
Pg. 27

PJ Enterprises Customer Service Improvement Plan


Update Customer Service Staff Job Descriptions to
reflect CSS and TO objectives, roles, responsibilities and performance skills required

Update Annual Performance Review / Evaluation


Process to align to job descriptions and to account for merit increases due to meeting
performance / training objectives

Develop and Execute Employee Performance


Contests and Rewards Recommendations to motivate staff to receive additional monetary
or gift compensation not applied to company catalog purchases

Develop Employee Compensation


Recommendations to address the need to compensate Customer Service staff for required
in-person training and monthly staff meeting attendance.
C: Internal Communications Plan for New Policies and Standards
To assist PJ Enterprises goal of developing integrated training and employee incentives that support
employee performance and satisfaction, the following activities will be performed in coordination
with and support of Human Resources and Management:

Develop an Internal Communications and


Execution Project Plan supporting the change to any new HR/company policies, standards,
performance evaluation and training procedures

Project Completion Criteria


The criteria for project success is the completion of all three (3) plans -- Customer Service / Product
Training and Resources Program, Customer Service Staff Incentives, and Internal Communications on
New Policies and Standards -- in accordance with PJ Enterprises objectives, as well as delivered on
time, achieving 100% customer satisfaction.

Designing Women, LLC


Pg. 28

PJ Enterprises Customer Service Improvement Plan

Project Milestones
PHASE /
TIMELINE

DELIVERABLE(S)
D
E
S
I
G
N
&
D
E
V
E
L
O
P
P
H
A
S
E
I
/
F
Y
1
4
Q
3
(J
ul
y
A
u
g
u
st
2
0
1
4
)

Designing Women, LLC


Pg. 29

MILESTONE(S)

Desig
ning
Wome
n,
LLC
Projec
t
Propos
al for
PJ
Enterp
rises

Submitte
d

Projec
t Kickoff
Meeti
ng

Held/Del
ivered

DUE DATE(S)

Approve
d

PJ Enterprises Customer Service Improvement Plan

7/2
7/2
014
7/2
9/2
014

7/3
1/2
014

A:

Custo
mer
Servic
e/
Produ
ct
Traini
ng
and
Resou
rces
Progr
am
Plan
B:

Custo
mer
Servic
e
Staff
Incent
ives
Plan

E
X
E
C
U
T
E
&
A
Designing Women, LLC
Pg. 30

Submitte
d
Approve
d

Submitte
d
Approve
d

C:
Intern
al
Comm
unicati
ons
Plan
for
New
Policie
s and
Standa
rds

Submitte
d

A:

Submitte
d

Custo
mer
Servic
e/
Produ
ct
Traini
ng

Approve
d

Approve
d

PJ Enterprises Customer Service Improvement Plan

8/7
/20
14
8/1
4/2
014

8/7
/20
14
8/1
4/2
014

8/7
/20
14
8/1
4/2
014

8/2
0/2
014
8/2
7/2
014

S
S
E
S
S
P
H
A
S
E
II
/
F
Y
1
4
Q
3
F
Y
1
5
Q
1
(
A
u
g
u
st
2
0
1
4
M
ar
c
h
2
0
1
5
)

and
Resou
rces
Progr
am
Plan
Deliv
erable
s
Produ
ction

B:

Custo
mer
Servic
e
Staff
Incent
Designing Women, LLC
Pg. 31

Submitte
d
Approve
d

PJ Enterprises Customer Service Improvement Plan

8/2
0/2
014
8/2
7/2
014

ives
Plan
Deliv
erable
s
Produ
ction
C:
Intern
al
Comm
unicati
ons
Plan
Delive
rables
for
New
Policie
s and
Standa
rds
Produ
ction

Submitte
d

A, B,
C
Plans
Execut
ed

Launch/I
mpleme
ntation

A, B,
C Plan
Assess
ments

Submitte
d

Approve
d

Execute

A, B,
C Plan
Assess
ment
Report
s for
PJ
Enterp
rises
Revie
w
I
M
Designing Women, LLC
Pg. 32

A, B,
C

8/2
0/2
014
8/2
7/2
014

Sep
tem
ber
201
4
Jan
uar
y
201
5
Ma
rch
201
5

Submitte

PJ Enterprises Customer Service Improvement Plan

Ap
ril

P
R
O
V
E
&
T
R
A
N
S
I
T
I
O
N
P
H
A
S
E
I
V
/
F
Y
1
5
Q
2
(
A
p
ri
l
J
u
n
e
2
0
1
5
)

Designing Women, LLC


Pg. 33

Projec
t Plans
(Year
2)
Transit
ion
Plans
from
DW to
PJ
Enterp
rises

Approve
d
Execute

Transit
ion
from
DW to
PJ

PJ Enterprises Customer Service Improvement Plan

201
5

Ma
y
201
5
Jun
e
201
5

Possible Problems / Constraints


Problem Area

Change in
project
scope,
schedule
and/or
budget

Likelihood
1 5 scale

Problem
Owner

Project Impact
and Mitigation Plan
Spon
sor /
DW

Impact: could
cause the
project to
delay, become
unfocused or
costly
Mitigation
Plan: regular
planned
communicatio
n with project
sponsor and
owner that
identify risks
and changes
so project
leadership can
address them
immediately
through an
identified/agre
ed upon
course of
action.

Change in
assigned
project
resources /
level of
effort
(LOE)

Designing Women, LLC


Pg. 34

Spon
sor /
DW

Impact: could
cause the
project to
delay, become
unfocused or
costly
Mitigation
Plan: work
with project
sponsor and
owner to
identify
potential client
or consultant
resources
available to
fill any gaps
and invest
time to orient
them on

PJ Enterprises Customer Service Improvement Plan

project
history/objecti
ves and the
newly
assigned team
members
role/responsibi
lities.
Customer
Service
Staff time
capacity /
level of
effort
(LOE)

Spon

Impact: could
result in
customer
service staff
not taking
advantage of
the program
resources
available to
them, and no
improvement
to their job
performance
or staff
retention rates.
Mitigation
Plan:
determine
prior to
program
launch with
project
sponsor if
program
training and
specific
performance
evaluation
processes can
be required
and
strategically
align
incentives to
motivate
participation
at its highest
levels.

Technical
operations

Designing Women, LLC


Pg. 35

Spon
sor /
Oper
ations

Impact: delay
in installing
new customer
order entry

PJ Enterprises Customer Service Improvement Plan

/ IT /
DW

system, phone
system is
incapable of
handling
increased call
volumes, as
well as server
issues can
delay DWs
delivery.
Mitigation
Plan: set up
regular
meetings with
Operations
and IT
stakeholders
to discuss both
DW and
infrastructure
projects
timelines and
upcoming
activities, in
order to
anticipate and
mitigate
potential risks
on both sides.

Change in
leadership/
strategic
direction

Spon
sor /
DW

Impact:
project time
and resources
could be
wasted
Mitigation
Plan: work
with sponsor
to determine if
project should
continue as is
or if there is a
need to
redefine any
project
objectives/pla
ns to support
the companys
shifting
strategic goals.

Designing Women, LLC


Pg. 36

PJ Enterprises Customer Service Improvement Plan

Current
client
corporate
culture
doesnt
intrinsicall
y value its
employees

Spon
sor /
HR /
DW

Impact:
results in low
staff morale,
job
dissatisfaction
and no desire
to improve
performance
because there
are no real
rewards.
Mitigation
Plan:
leadership will
need to
embrace and
support the
belief and core
company
value that its
employees are
the most
important
single attribute
that directly
impacts the
bottom line
and
everyones
success.
Performance
evaluation and
incentives will
need to
support this
core value
through means
that empower
employees by
providing
skills, growth
opportunities,
and monetary
rewards/benefi
ts.

Assumptions
Designing Women is responsible for:
Designing Women, LLC
Pg. 37

PJ Enterprises Customer Service Improvement Plan

design and development of all deliverables in a timely manner

adherence to the agreed upon budget and timeline for the

as indicated in this charter


project
notifying PJ Enterprises of any significant changes that may
impact the project as agreed upon in this charter
providing the Project Sponsor and Owner with scheduled
status reports as generated with our project management software
providing electronic copies in the appropriate format for any
project document or training deliverable
providing training course facilitation guides where applicable
conducting all in-person classroom product training sessions
providing significant and applicable follow-up documentation
of project effectiveness
PJ Enterprises is responsible for:
providing to DW all data already gathered from stakeholders
(i.e. surveys, interview responses, sales performance reports, employee job descriptions,
employee performance criteria/evaluations, etc.) or a compilation report if available
providing subject matter experts (SMEs) / points of contact
(POCs) for all designated positions/divisions
notifying DW of any significant changes (i.e., personnel
changes) that may impact the project as agreed upon in this proposal
reviewing all materials in a timely manner to ensure agreed
upon timeline
working with DW to develop a suitable rotational in-person
classroom training schedule so as to accommodate the 24/7 TO work schedules
printing and binding of all specified designed training or
project materials
providing adequate and comfortable meeting facility and
necessary AV supplies for employee classroom training sessions and light refreshments for
training sessions
recording all classroom training sessions
compensating employees for training time as stated in agreed
upon incentive and pay scale program
providing incentives for error-free customer service as stated
in agreed upon incentive and pay scale program

Vendor Assistance Requirements / External Dependencies


Designing Women, LLC (DW) may require timely, and if applicable, affordable assistance from
product vendors in order to obtain precise and accurate product information and/or product photos for
the design, development and production of PJ Enterprises Product Catalog Guide and associated
training resources.
Additionally, DW may require timely assistance from the PJ Enterprises IT and Customer Order Entry
software vendor/provider subject matter experts (SMEs) prior to PJ Enterprises company-wide launch
of the system, in order for DW to work with and develop associated training materials.

Budget
A: Customer Service / Product Training and Resources Program Plan
A1: Training Support for Monthly Customer Service Staff Meetings

Designing Women, LLC


Pg. 38

PJ Enterprises Customer Service Improvement Plan

Up to forty (40) hours total per month / twelve (12) months total of
meeting preparation, real-time on-site coordination, and post meeting support.
Ho
urs
/
Co
st

Labor Category / Hourly Rate

Project Manager / $150

120
/
$18
,00
0

Senior Instructional Designer / $150

120
/
$18
,00
0

Business Analyst & Project Coordinator / $125

120
/
$15
,00
0

Business Analyst & Technical Writer / $125

120
/
$15
,00
0

Total Hours / Cost

~48
0/
$66
,00
0

A2: Quarterly In-classroom Training on Catalog Products and Customer Service


Five (5) Courses Total: two (2) sixty-minute courses on seasonal products and one (1) sixty-minute
course on existing products (both Sept. 14 and Mar. 15) and one (1) ninety-minute customer service
improvement course (Sept. 14), to include all associated reference materials.
Labor Category / Hourly Rate

Designing Women, LLC


Pg. 39

D
e
s
i
g
n

PJ Enterprises Customer Service Improvement Plan

Cos

/
A
d
m
i
n
H
o
u
r
s
O
v
e
r
6
M
o
n
t
h
s
Project Manager / $150

1
0
0

$15,
000

Senior Instructional Designer /


$150

1
5
0

$22,
500

Business Analyst & Project


Coordinator / $125

1
0
0

$12,
500

Business Analyst & Technical


Writer / $125

1
0
0

$12,
500

T
o
t
a
l

$62,
500

Designing Women, LLC


Pg. 40

PJ Enterprises Customer Service Improvement Plan

A3: Computer-Based Training for TOs on the Existing and New Customer Order Entry System
Five (5) 30-minute sessions on using the current and new customer order entry systems
D
e
s
i
g
n
/
A
d
m
i
n

Labor Category / Hourly Rate

H
o
u
r
s
O
v
e
r
4
M
o
n
t
h
s

Designing Women, LLC


Pg. 41

PJ Enterprises Customer Service Improvement Plan

Cos

Project Manager / $150

8
0

$12,
000

Senior Instructional Designer /


$150

3
0
0

$45,
000

Business Analyst & Project


Coordinator / $125

1
0
0

$12,
500

Business Analyst & Technical


Writer / $125

1
0
0

$12,
500

T
o
t
a
l

$82,
000

A4: Training Program Assessment Strategies and Evaluation Activities/Tactics to measure


Effectiveness
Labor Category / Hourly Rate

D
e
s
i
g
n
/
A
d
m
i
n
H
o
u
r
s
O

Designing Women, LLC


Pg. 42

PJ Enterprises Customer Service Improvement Plan

Cos

v
e
r
1
2
M
o
n
t
h
s
Project Manager / $150

4
0

$6,0
00

Senior Instructional Designer /


$150

100

$15,
000

Business Analyst & Project


Coordinator / $125

75

$9,3
75

Business Analyst & Technical


Writer / $125

75

$9,3
75
T
o
t
a
l

$39,
750

B: Customer Service Staff Incentives Plan


To support PJ Enterprises goal of increasing TO staff job satisfaction, the following activities will be
performed: update Customer Service Staff job descriptions, update annual Performance Review /
Evaluation Process, develop and execute employee performance contests and rewards
recommendations, develop employee compensation recommendations.
Labor Category / Hourly Rate
Designing Women, LLC
Pg. 43

PJ Enterprises Customer Service Improvement Plan

Cos

e
s
i
g
n
/
A
d
m
i
n
H
o
u
r
s
O
v
e
r
1
2
M
o
n
t
h
s
Project Manager / $150

7
5

$11,
250

Senior Instructional Designer /


$150

5
0

$7,5
00

Business Analyst & Project


Coordinator / $125

2
0
0

$25,
000

Business Analyst & Technical


Writer / $125

2
0
0

$25,
000

Designing Women, LLC


Pg. 44

PJ Enterprises Customer Service Improvement Plan

T
o
t
a
l

$68,
750

C: Develop and Execute an Internal Communications Plan for New Policies and Standards
To assist PJ Enterprises goal of developing integrated training and employee incentives that support
employee performance and job satisfaction.
D
e
s
i
g
n
/
A
d
m
i
n

Labor Category / Hourly Rate

H
o
u
r
s
O
v
e
r
1
2
M
o
n
t
h
s

Designing Women, LLC


Pg. 45

PJ Enterprises Customer Service Improvement Plan

Cos

Project Manager / $150

5
0

$7,5
00

Senior Instructional Designer /


$150

2
5

$3,7
50

Business Analyst & Project


Coordinator / $125

1
0
0

$12,
500

Business Analyst & Technical


Writer / $125

1
0
0

$12,
500

T
o
t
a
l

$36,
250

TOTAL PROPOSAL PROJECT COSTS


Project

Cos

A1: Training Support for Monthly Customer Service


Staff Meetings

$66,
000

A2: Quarterly In-classroom Training on Catalog Products and Customer


Service

$62,
500

A3: Computer-Based Training for TOs on the Existing


and New Customer Order Entry System

$82,
000

A4: Training Program Assessment Strategies and


Evaluation Activities/Tactics to measure effectiveness

$39,
750

B: Customer Service Staff Incentives Plan

$68,
750

C: Develop and Execute an Internal Communications

$36,

Designing Women, LLC


Pg. 46

PJ Enterprises Customer Service Improvement Plan

Plan

250

for New Policies and Standards


TOTAL PROJECT COST / 1-YEAR CONTRACT

$35
5,25

Terms and Conditions


Applicability of These Terms and Conditions
These terms and conditions are part of the agreement between Designing Women, LLC (hereinafter
DW) and the client and normally will accompany a proposal letter. If there are any inconsistencies
between this form and the proposal letter, the letter will control.
Hourly Fees and Expenses
Overtime work (billing of more than 40 hours per week, more than 8 hours per day, or weekend work)
incurs an extra charge of 25% over the regular hourly rates per DW project team member. The client is
responsible for out-of pocket
expenses incurred in connection with the project.
Billings
DW will submit invoices on the 30th of the month. All invoices are payable within 30 days of the date
on the invoice. Amounts past-due will bear interest at the rate of 1.5% per month until paid. Work on
the project may be suspended if payments are overdue. Work will not begin until any required advance
payment has been received by DW.
Change in Scope of the Project
Any expansion or modification of the project will require written approval of the client and DW.
Written approval for DW can only come from Jane MacKenzie-Smith of PJ Enterprises. Pending
receipt of written approval, DW may, at DWs discretion, take reasonable action and expend reasonable
amounts of time and money based on oral approval of an expansion or modification from the
designated representative of the client. The client will be responsible for payment for such action, time,
and expenses. Fee quotes, fee estimates, and schedules are based on the project as originally approved.
Cancellation, Rescheduling, and Project Delays
If the client cancels or reschedules the project or this contract before completion, the client will pay for
all time and expenses incurred to date, plus an additional 15% of the portion of the initial estimate
which has not yet been earned. The cancellation/rescheduling fee is not for services to be performed
after the postponement or cancellation, but are to compensate DW for maintaining availability for the
project. The schedule for any rescheduled project will be subject to other obligations of DW. Delays of
more than 20 days render the project agreement and this contract null and void with no further penalties
to either party. Either DW or the client may end this contract by giving two weeks notice in writing via
certified mail at the following addresses:
Designing Women, LLC
123 Contact Rd.
New York, NY 10001
PJ Enterprises
Jane MacKenzie-Smith
65 Mingus Mountain Rd.
Designing Women, LLC
Pg. 47

PJ Enterprises Customer Service Improvement Plan

Sedona, AZ 86336
Completion Dates
Except where deadlines are expressly stated to be firm, completion dates are estimates based on the
information available to DW. Final schedule with firm dates will be delivered on August 15, 2014.
Staffing
DW will restrict its commitments to other clients to the extent necessary to complete the project in a
timely manner. All services will be done as an independent consultant contractor. Neither DW nor any
of DWs staff shall be deemed to be an employee of the client on account of the work done on the
project.
Access to the Clients Staff
The client will provide DW with reasonable access to the clients staff and resources as needed to
perform the services needed to timely complete the project.
Proprietary materials
DW warrants that its work product will not violate any existing copyright or trademark. The client
warrants that material provided by the client for the project will not violate any existing copyright or
trademark. Prior to payment in full, JP Enterprises will own the copyright on all materials developed by
DW in the course of the project. DW will have a perpetual, irrevocable, royalty-free license to use such
materials not specific to the clients product in its business.
The client will provide DW with two copies of the final [deliverable], if applicable
Confidential Information
DW will take reasonable steps to maintain the confidentiality of any confidential information relating to
the client received by DW in the course of the project.
Arbitration
Any dispute arising out of the project Agreement shall be submitted to binding arbitration before a
single arbitrator selected by the client and DW. If an arbitrator is not selected within 10 days of written
demand for arbitration, the dispute shall be decided by a single arbitrator under the then current
Commercial Arbitration rules of the American
Arbitration Association. All arbitration proceedings shall be conducted within 25 miles of New York,
NY. DW and the client understand that any award the Arbitrator issues may be converted into a
judgment pursuant to New York law.
Damage Exclusion and Limits
The client is responsible (and DW is not responsible) for the accuracy of the content of a completed
project. Designing Women, LLC shall not be liable, under any circumstances, for consequential,
special, or incidental damages, even if it has been advised that such damages may occur. DWs liability
arising out of this Agreement, whether in contract, tort, or otherwise, shall not exceed the total of the
amounts which the client has paid to DW under this Agreement.
Attorney Fees
In the unlikely event that a dispute between the client and DW leads to arbitration or a lawsuit, the
prevailing party may recover from the other party all legal expenses, including reasonable attorney and
expert client fees.
Warranty of Authority
Each individual signing in a representative capacity warrants that he or she has the power and authority
to sign on behalf of the party in whose behalf he or she is signing, that such signature alone is binding
on such party, and that the execution of this document has been duly authorized by such party.
Entire Agreement
Designing Women, LLC
Pg. 48

PJ Enterprises Customer Service Improvement Plan

This Agreement contains the entire understanding of the parties with respect to the subject matter
hereof, and all agreements entered into prior hereto with respect to the subject matter hereof are
revoked and superseded by this Agreement, and no representations, warranties, inducements or oral
agreements have been made by any of the parties
except as expressly set forth herein.
Binding Effect
This agreement shall be binding upon and inure to the benefit of the parties, their heirs, successors,
assigns and personal representatives.
Time of the Essence
Time is of the essence as to each and every provision of this Agreement.
Amendment to Agreement
This agreement may be amended, modified, or supplemented only by written agreement of DW and the
client. Written agreement from JP Enterprises can only come from Jane MacKenzie-Smith.

Signed

Signed

______________________________

____________________________

Date: July 27, 2014

Date: July 27, 2014

for Designing Women, LLC

for PJ Enterprises

4. PJ Enterprises Customer Improvement Project


Management Plan
Project Name
Customer Service Improvement Plan

Prepared by
Designing Women, LLC

Date
August 3, 2014

Version Control

Designing Women, LLC


Pg. 49

PJ Enterprises Customer Service Improvement Plan

Version

Purpose/

Author

Change

Date

Comments

1.0

Designing Women,
LLC

Consultation
Draft to JP
Enterprises

08/03/14

Initial draft

2.0

Jane MacKenzieSmith, PJ Enterprises

Project
Sponsor
Review

8/04/14

Edits /
Feedback

3.0

Designing Women,
LLC

Feedback
incorporated

8/24/14

FINAL

Project Information
Project Description/Overview
Designing Women, LLC (DW) met with Jane Smith (Project Sponsor), Judie Thompson
(Catalog Director), and Sheena Perez (Merchandising Manager) of PJ Enterprises, to discuss
concerns about reports of poor telephone etiquette and lack of product knowledge by the
telephone operators at this mail-order catalog business. Designing Women also performed two
surveys given to the telephone operators (TO) and the Customer Service Supervisors (CSS), as
well as interviewed staff of the IT and Human Resources departments.
At the time, management expressed concerns that poor customer service might be directly
related to the lack of TOs product knowledge and provide it to customers in a timely manner.
PJ Enterprises asked DW to create a training program for the telephone operators and
supervising staff on customer service, product knowledge and accessibility.
In response, DW performed a Gap Analysis and a Performance Analysis to determine if training
is the correct solution to the problem, one of several solutions, or not a solution at all. Based on
the Performance Analysis Report findings and recommendations, PJ Enterprises approved DW
to develop a comprehensive Customer Service / Product Training and Resources Program,
Customer Service Staff Incentives Plan, and Internal Communications Plan for New
Policies and Procedures.

Business Objectives
DWs comprehensive project plan addresses the following PJ Enterprises business objectives:
1. To provide training, incentives and associated communications that will increase Telephone
Operators (TO) overall job performance within twelve (12) months, including:

increase TOs overall product knowledge by 70% within twelve (12) months
increase TOs ability to quickly and easily find/locate product
specific information by 70% within six (6) months
increase TOs accurate use of the telephone system supporting a
quality customer service experience by 70% within twelve (12) months
train 100% of Customer Service Staff (CSS/TO) to accurately
use the new Customer Order Entry System

Designing Women, LLC


Pg. 50

PJ Enterprises Customer Service Improvement Plan

2. To improve Telephone Operators (TO) job satisfaction and employee retention rates by 50%
within twelve (12).

Scope Statement
DW has developed a series of training, incentives and communications plans and will execute them to
support PJ Enterprises performance improvement objectives for its Telephone Operators (TOs) in
delivering improved quality customer service.
The individual plans within this proposal will each include detailed timelines/schedules, assessment
tactics for evaluation purposes and a proposed budget for all deliverables from initiation, to
development, to execution, to transition (or on-going maintenance support) for two contract years,
starting July 31, 2014 and effective through June 30, 2015.

Deliverables
DW will deliver the following:
A: Customer Service / Product Training and Resources Program Plan
A1: Training Support for Monthly Customer Service Staff Meetings
Up to forty (40) hours per month for the first four (4) months of DW train-the-trainer support
consisting of training PJ Enterprises staff on best practices for meeting preparation (agenda and
training activities items), effective on-site meeting coordination (administration,
facilitation/moderation and training instruction), and post meeting support (analysis and
assessment delivery and reporting).
A2: Quarterly In-classroom Training on Catalog Products and Customer Service
Improvement
Two (2) 60-minute courses on seasonal products, one (1) 60-minute course on existing products
(both held Sept. 14 and Mar. 15) and one (1) 90-minute customer service improvement course
(Sept. 14):
Two (2) 60-minute sessions on new seasonal products (held
2x/Sept. 14 and 2x/Mar. 15) added to the existing catalog to include how to utilize
the new catalog product guide and reference materials.
One (1) 60-minute session (held 1x/Sept. 14) and 1x/Mar. 15) on
existing changes to catalog products from the previous quarter to include how to
utilize the new catalog product guide and reference materials
One (1) 90-minute Customer Service Improvement Course (held
Sept. 14):
One (1) 30-minute lesson Phone Technology
How to properly answer, hold, and transfer calls to include a role- playing
scenario and quiz to assess TOs ability to perform the tasks successfully
One (1) 30-minute lesson Professional
Customer Service Etiquette - Learning and performing formal greetings,
responses, etc.
One (1) 30-minute lesson Managing
Customer Conflicts - How to handle customer conflict and response to
problems successfully, including role-play scenarios.
Supporting Print and Online Training Reference Materials for
each of the five (5) courses (e.g. job aids, guidelines, FAQs, etc.)
Designing Women, LLC
Pg. 51

PJ Enterprises Customer Service Improvement Plan

Revised PJ Enterprises Product Catalog Guide with new, easy-touse/understand catalog product guide to include new product information specific to
customer service staff needs (pictures, corresponding item/category numbers, bestselling/seasonal items identifiers or sections, estimated shipping costs, care
instructions, etc.)
Training on Catalog Products Course Facilitation Guide -- electronic
copy of the facilitators guide to conduct, the quarterly in-person trainings on catalog
products and their associated reference materials
A3: Computer-Based Training (CBT) for TOs on the Existing and New Customer Order
Entry System
Five (5) 30-minute sessions on using the current and new customer order entry systems to
include:

Entering and

Editing/Upda

Authorizing

Removing Customer Orders


ting Customer Order Entries
Orders for Supervisory Approval
Differences
Between the Existing and New Customer Order Entry Systems - a hands-on
demonstration
Assessing
Your Customer Order Entry System Knowledge
A4: Training Program Assessment Strategies and Evaluation Activities/Tactics to measure
effectiveness
The following activities will be performed:
CSS/TO Training Feedback Group select volunteer CSSs/TOs will be recruited to participate and provide feedback on all
proposed training, incentives and communications plans as well as pilot training testing
to develop key staff buy-in, create advocates for change and ensure all deliverables
are on-point per this key stakeholder group
Post Training Assessment -- each
course will have a post-training assessment activity (i.e. survey, observances, etc.)
aligned to all proposed course objectives that will gauge the quality and efficacy of the
training;
Customer Service Staff Meeting
Assessment - after the first initial monthly meeting that Designing Women, LLC
supports, a post-meeting assessment activity (i.e. survey, interviews, etc.) aligned to the
proposed meeting objectives will be delivered to gauge the quality and efficacy of the
meeting content; additionally continued assessment will occur every quarter to track
progress against measures.

A5: Training Program Management Execution Project Plan


The project plan will include detailed timelines/schedules and roles/responsibilities for all
program deliverables from initiation, to development, to execution, to transition or on-going
maintenance support for two contract years, starting July 2014 and effective through the endDesigning Women, LLC
Pg. 52

PJ Enterprises Customer Service Improvement Plan

of-June 2015. Additional contract work can be addressed on an as-needed basis, as well as postcontract based on PJ Enterprises needs.
B: Customer Service Staff Incentives Plan
To support PJ Enterprises goal of increasing TO staff job satisfaction, the following activities will be
performed in coordination with and support of Human Resources and Management:

Update Customer Service Staff Job


Descriptions to reflect CSS and TO objectives, roles, responsibilities and performance
skills required

Update Annual Performance


Review / Evaluation Process to align to job descriptions and to account for merit increases
due to meeting performance / training objectives

Develop and Execute Employee


Performance Contests and Rewards Recommendations to motivate staff to receive
additional monetary or gift compensation not applied to company catalog purchases

Develop Employee Compensation


Recommendations to address the need to compensate Customer Service staff for required
in-person training and monthly staff meeting attendance.
C: Internal Communications Plan for New Policies and Standards
To assist PJ Enterprises goal of developing integrated training and employee incentives that support
employee performance and satisfaction, the following activities will be performed in coordination with
and support of Human Resources and Management:

Develop an Internal
Communications and Execution Project Plan supporting the change to any new
HR/company policies, standards, performance evaluation and training procedures

Exclusions/Out-of-scope
DW will not include nor is responsible for:

purchasing/installing technology software and equipment in CSS/TO offices and workstations


purchasing/installing office furniture or supplies in CSS/TO offices and workstations
changes to any training course content post-client final approval and production, unless client
approves costs for additional changes
changes to any training resources and reference materials, including the Product Catalog Guide,
post-client final approval and production, unless client approves costs for additional changes
changes to any training courses, resources and reference materials due to changes in phone or IT
software or equipment, unless client approves costs for additional changes
changes to any HR policies and procedures that impact any project deliverables post-client final
approval and production, unless client approves costs for additional changes
meeting space/location, AV/IT requirements and equipment, administrative tools, food/beverage for
monthly staff meetings, in-person classroom trainings and CBTs
compensation (travel/wages) for Customer Service staff attending monthly staff meetings, in-person
classroom trainings and CBTs

Designing Women, LLC


Pg. 53

PJ Enterprises Customer Service Improvement Plan

Project Completion Criteria


The criteria for project success is the completion of all three (3) plans -- Customer Service / Product
Training and Resources Program, Customer Service Staff Incentives, and Internal Communications on
New Policies and Standards -- in accordance with PJ Enterprises objectives, as well as delivered on
time, achieving 100% customer satisfaction.

External Dependencies
DW may require timely, and if applicable, affordable assistance from product vendors in order to obtain
precise and accurate product information and/or product photos for the design, development and
production of PJ Enterprises Product Catalog Guide and associated training resources.
Additionally, DW may require timely assistance from the Customer Order Entry software
vendor/provider subject matter experts (SMEs) prior to PJ Enterprises company-wide launch of the
system, in order for DW to work with and develop associated training materials.

Assumptions
DW is responsible for:

design and development of all deliverables in a timely manner

adherence to the agreed upon budget and timeline for the

as indicated in this charter


project
notifying PJ Enterprises of any significant changes that may
impact the project as agreed upon in this charter
providing the Project Sponsor and Owner with scheduled
status reports as generated with our project management software
providing electronic copies in the appropriate format for any
project document or training deliverable
providing training course facilitation guides where applicable
conducting all in-person classroom product training sessions
providing significant and applicable follow-up documentation
of project effectiveness
PJ Enterprises is responsible for:

providing to DW all data already gathered from stakeholders (i.e. surveys, interview responses,
sales performance reports, employee job descriptions, employee performance criteria/evaluations,
etc.) or a compilation report if available
providing subject matter experts (SMEs) / points of contact (POCs) for all designated
positions/divisions
notifying DW of any significant changes (i.e., personnel changes) that may impact the project as
agreed upon in this proposal
reviewing all materials in a timely manner to ensure agreed upon timeline
working with DW to develop a suitable rotational in-person classroom training schedule so as to
accommodate the 24/7 TO work schedules
printing and binding of all specified designed training or project materials
providing adequate and comfortable meeting facility and necessary AV supplies for employee
classroom training sessions and light refreshments for training sessions
recording all classroom training sessions
compensating employees for training time as stated in agreed upon incentive and pay scale program
providing incentives for error-free customer service as stated in agreed upon incentive and pay
scale program
Designing Women, LLC
Pg. 54

PJ Enterprises Customer Service Improvement Plan

Constraints
The following are known project constraints:

PJ Enterprises has indicated a project budget of $400,000 for the fiscal year.
Classroom training must coincide with PJ Enterprises quarterly catalog business approach.
Therefore the first quarterly training must be completed by September 15, 2014.
In-classroom training must be scheduled to accommodate TOs 24/7 work schedule.
PJ Enterprises has the following personnel constraints:
Sheena Perezs schedule and work load allows little time availability to DW
Maria Gomez (CSS and SME) is on evening shift
New SMEs will need time to learn the project and get up to speed
In-class training room capacity may not accommodate all TOs for one training session and
additional sessions may need to be scheduled.
Initial training will be done on current out-dated equipment which PJ Enterprises plans to update
but the time frame is unknown.
Forthcoming training may be done on new workstations, which though their speed may be
improved, the ease of use due to unfamiliarity may prove to be a deterrent for some.

Project Milestones Overview


PHASE /
TIMELINE

DELIVERABLE(S)
D
E
S
I
G
N
&
D
E
V
E
L
O
P
P
H
A
S
E
I
/
F
Y
1
4
Q
3
(J
ul
y

Designing Women, LLC


Pg. 55

Desig
ning
Wome
n,
LLC
Projec
t
Propos
al for
PJ
Enterp
rises

MILESTONE(S)

DUE DATE(S)

Submitte
d
Approve
d

PJ Enterprises Customer Service Improvement Plan

7/
27
/2
01
4
7/
29
/2
01
4

A
u
g
u
st
2
0
1
4)
Projec
t Kickoff
Meeti
ng

Held/Del
ivered

7/
31
/2
01
4

A:

Submitte
d

8/
4/
20
14

Custo
mer
Servic
e/
Produ
ct
Traini
ng
and
Resou
rces
Progr
am
Plan
B:

Custo
mer
Servic
e
Staff
Incent
ives
Plan
C:
Intern
al
Comm
unicati
ons
Plan
Designing Women, LLC
Pg. 56

Approve
d

8/
12
/2
01
4

Submitte
d
Approve
d

8/
4/
20
14
8/
12
/2
01
4

Submitte
d
Approve
d

PJ Enterprises Customer Service Improvement Plan

8/
4/
20
14
8/
12

for
New
Policie
s and
Standa
rds
E
X
E
C
U
T
E
&
A
S
S
E
S
S
P
H
A
S
E
II
/
F
Y
1
4
Q
3
F
Y
1
5
Q
1
(
A
u
g
u
st
2
0
1
4
M
ar
Designing Women, LLC
Pg. 57

A:

Custo
mer
Servic
e/
Produ
ct
Traini
ng
and
Resou
rces
Progr
am
Plan
Deliv
erable
s
Produ
ction

/2
01
4

Started
Submitte
d
Approve
d
Delivere
d

PJ Enterprises Customer Service Improvement Plan

8/
13
/2
01
4
8/
27
/2
01
4
9/
1/
20
14
9/
15
/2
01
4

c
h
2
0
1
5)
B:

Custo
mer
Servic
e
Staff
Incent
ives
Plan
Deliv
erable
s
Produ
ction

Started
Submitte
d
Approve
d
Delivere
d

8/
13
/2
01
4
8/
27
/2
01
4
9/
1/
20
14
9/
15
/2
01
4

C:
Intern
al
Comm
unicati
ons
Plan
Delive
rables
for
New
Policie
s and
Standa
rds
Produ
ction

Designing Women, LLC


Pg. 58

Started
Submitte
d
Approve
d
Delivere
d

PJ Enterprises Customer Service Improvement Plan

8/
13
/2
01
4
8/
27
/2
01
4
9/
1/
20
14
9/
15
/2
01
4

I
M
P
R
O
V
E
&
T
R
A
N
S
I
T
I
O
N
P
H
A
S
E
II
I
/
F
Y
1
5
Q
2
(
A
Designing Women, LLC
Pg. 59

A, B,
C Plan
Assess
ments

Execute
d

Ja
nu
ar
y
20
15

A, B,
C Plan
Assess
ment
Report
s for
PJ
Enterp
rises
Revie
w

Submitte
d

M
arc
h
20
15

A, B,
C
Projec
t Plans
(Year
2)

Submitte
d

Ap
ril
20
15

Transit
ion
Plans
from
DW to
PJ
Enterp
rises

Approve
d

Execute

Transit
ion
from
DW to
PJ

PJ Enterprises Customer Service Improvement Plan

M
ay
20
15

Ju
ne
20
15

pr
il
J
u
n
e
2
0
1
5)

Project Approach and Primary Plans


DW will use the ADDIE model for design and development and the primary plan consists of a threephase approach for rolling out the Customer Service / Product Training and Resources Program,
Customer Service Staff Incentives, and Internal Communications on New Policies and Standards.
Phase I:

Design and Develop all Plans

Phase II:

Execute Plans and Assess Outcomes

Phase III:

Provide Improvement Recommendations and Transition Program Management

Each project plans implementation is scheduled to accommodate PJ Enterprises most critical


stakeholders (TO/CSS) and their schedules, learning abilities, and the need to mitigate cognitive
overload during the busiest sales season.
DWs project plans will include: project schedules based on milestones, individual project budgets, and
associated risks and mitigation plans.

Scheduled Project Team Meetings and Status Reports


Status reports will be submitted to Jane Smith, Project Sponsor and Sheena Perez, Merchandising
Manager prior to the scheduled status meeting that will be held during each project phase (see below).
Meeting Location
PJ Enterprises
Jane MacKenzie-Smith
65 Mingus Mountain Rd.
Sedona, AZ 86336

Data and Time

Purpose

7/31/2014, 10:00 AM

Project Kick-Off
Meeting

8/7/2014, 10:00 AM
8/14/2014, 10:00 AM
8/21/2014, 10:00 AM
8/28/2014, 10:00 AM

Phase I Project Status


Meetings (Every
Thursday)
PJ Enterprises - DW
Project Team

Designing Women, LLC


Pg. 60

PJ Enterprises Customer Service Improvement Plan

9/4/2014, 10:00 AM
9/11/2014, 10:00 AM
9/18/2014, 10:00 AM
9/25/2014, 10:00 AM
10/2/2014, 10:00 AM
10/9/2014, 10:00 AM
10/16/2014, 10:00 AM
10/23/2014, 10:00 AM
10/30/2014, 10:00 AM
11/13/2014, 10:00 AM
11/25/2014, 10:00 AM
12/4/2014, 10:00 AM
12/18/2014, 10:00 AM
Every other Thursday,
January - March 2015

Phase II Project Status


Meetings (Weekly to
Bi-weekly)
PJ Enterprises - DW
Project Team

Every other Thursday,


April - June 2015

Phase III Project


Status Meetings (Biweekly)
PJ Enterprises - DW
Project Team

Issues Management
1.0 Issue Identification
1.1 Email notification will be sent by project manager, project sponsor and project coordinator
stating the details of the issue and priorities assigned. The project coordinator will keep track of
all issues and email notifications.
2.0 Issue Analysis
2.1 The appropriate team member will work on the issue and email notification will be sent to
coordinator, and manager with any concerns.
3.0 Issue Evaluation
3.1 A resolution on the issue will be submitted to project coordinator, who will evaluate the
solution and contact all other team members involved.
4.0 Action Implementation
4.1 The assignee accepts the assignment, email notification will automatically be sent upon
accepting and the issue will be worked on.
5.0 Monitoring & Review
5.1 The project coordinator will oversee all issues and record them in the Master Change Log,
also contact via email appropriate team members. She will track the progress in the log and
close all issues that have been opened by the team.

Designing Women, LLC


Pg. 61

PJ Enterprises Customer Service Improvement Plan

Risk Assessment and Mitigation Plans


Ris
k

Ris
k
Le
vel
Lo
w/
Me
diu
m/
Hig
h

Likeli
hood
of
Event
(1-5
scale)

Mitigat
ion
Plan

Ch
ang
e in
pro
ject
sco
pe,
sch
edu
le
and
/or
bud
get

Hig
h

Regular
planned
commu
nication
with
project
sponsor
and
owner
that
identify
risks
and
changes
so
project
leaders
hip can
address
them
immedi
ately
through
an
identifi
ed/agre
ed upon
course
of
action.

Ch
ang
e in
assi
gne
d
pro
ject
res
our
ces

Me
diu
m

Work
with
project
sponsor
and
owner
to
identify
potentia
l client
or

Designing Women, LLC


Pg. 62

PJ Enterprises Customer Service Improvement Plan

Ris
k

Ris
k
Le
vel
Lo
w/
Me
diu
m/
Hig
h

Likeli
hood
of
Event
(1-5
scale)

/
lev
el
of
eff
ort
(L
OE
)

Cus
tom
er
Ser
vic
e
Sta
ff
tim
e
cap
acit
y/
lev
el
of
Designing Women, LLC
Pg. 63

Mitigat
ion
Plan

consult
ant
resourc
es
availabl
e to fill
any
gaps
and
invest
time to
orient
them
on
project
history/
objectiv
es and
the
newly
assigne
d team
membe
rs
role/res
ponsibil
ities.
Hig
h

Determ
ine
prior to
progra
m
launch
with
project
sponsor
if
progra
m
training
and
specific
perform

PJ Enterprises Customer Service Improvement Plan

Ris
k

Ris
k
Le
vel
Lo
w/
Me
diu
m/
Hig
h

Likeli
hood
of
Event
(1-5
scale)

eff
ort
(L
OE
)

Tec
hni
cal
ope
rati
ons
(ph
one
/co
mp
uter
syst
em
s
for
trai
nin
g
des
ign
and
dev
elo
Designing Women, LLC
Pg. 64

Mitigat
ion
Plan

ance
evaluati
on
process
es can
be
require
d and
strategi
cally
align
incentiv
es to
motivat
e
particip
ation at
its
highest
levels.
Me
diu
m

Schedul
e
regular
meeting
s with
Operati
ons and
IT
stakeho
lders to
discuss
both
DW
and
infrastr
ucture
projects

timelin
es and
upcomi
ng
activitie

PJ Enterprises Customer Service Improvement Plan

Ris
k

Ris
k
Le
vel
Lo
w/
Me
diu
m/
Hig
h

Likeli
hood
of
Event
(1-5
scale)

pm
ent
pur
pos
es)

Mitigat
ion
Plan

s, in
order to
anticipa
te and
mitigat
e
potentia
l risks
on both
sides.

Ch
ang
e in
lea
der
shi
p/
stra
tegi
c
dire
ctio
n

Lo
w

Work
with
sponsor
to
determi
ne if
project
should
continu
e as is
or if
there is
a need
to
redefin
e any
project
objectiv
es/plans
to
support
the
compan
ys
shifting
strategi
c goals.

Cur
rent
clie
nt
cor

Hig
h

Leaders
hip will
need to
embrac
e and

Designing Women, LLC


Pg. 65

PJ Enterprises Customer Service Improvement Plan

Ris
k

por
ate
cult
ure
doe
snt
intr
insi
call
y
val
ue
its
em
plo
yee
s

Designing Women, LLC


Pg. 66

Ris
k
Le
vel
Lo
w/
Me
diu
m/
Hig
h

Likeli
hood
of
Event
(1-5
scale)

Mitigat
ion
Plan

support
the
belief
and
core
compan
y value
that its
employ
ees are
the
most
importa
nt
single
attribut
e that
directly
impacts
the
bottom
line and
everyon
es
success
.
Perfor
mance
evaluati
on and
incentiv
es will
need to
support
this
core
value
through
means
that
empow
er
employ
ees by
PJ Enterprises Customer Service Improvement Plan

Ris
k

Ris
k
Le
vel
Lo
w/
Me
diu
m/
Hig
h

Likeli
hood
of
Event
(1-5
scale)

Mitigat
ion
Plan

providi
ng
skills,
growth
opportu
nities,
and
moneta
ry
rewards
/benefit
s.
Ch
ang
es
in
role
s
and
res
pon
sibi
litie
s
wit
hin
the
cor
por
atio
n

Designing Women, LLC


Pg. 67

Me
diu
m

Talk
with
project
leaders
hip and
ask if a
replace
ment
point of
contact/
SME
could
be
conside
red and
when
that
could
happen,
grant
direct
access
to PJ
Enterpr
ises.

PJ Enterprises Customer Service Improvement Plan

WBS and Diagram Customer Service Improvement Training


Lesson 3: Managing Customer Conflicts
1.0

2.0

Project Management
1.1

Develop project plan

1.2

Monitor and control project

Steps to Customer Dissatisfaction Resolution Guide (Job Aid)


2.1

Research best practice steps for managing customer dissatisfaction resolution


job aid

2.2

Create page layout


2.2.1

Draft appropriate content and captions

2.2.2

Proof-read for final draft

2.2.3

Submit final draft to stakeholders for approval

2.2.4

Deliver completed final draft in appropriate format to publisher for


printing / laminating

3.0

Managing Customer Conflicts Course


3.1

Develop course design document

3.2

Create presentation slides and videos

3.3

3.4

3.2.1

Design presentation slides and videos

3.2.2

Develop presentation

3.2.3

Proof presentation aids for finalization

Create trainee materials


3.3.1

Design trainee materials

3.3.2

Develop trainee materials

3.3.3

Proof-read trainee materials for finalization

3.3.4

Deliver completed final draft in appropriate format to publisher for


printing / binding

Create Facilitators Guide


3.4.1

Create page layout


3.4.1.1 Secure illustrations, charts, images etc. as needed
3.4.1.2 Draft appropriate content and captions
3.4.1.3 Proof-read for final draft
3.4.1.4 Submit final draft to stakeholders for approval

Designing Women, LLC


Pg. 68

PJ Enterprises Customer Service Improvement Plan

3.4.1.5 Deliver completed final draft in appropriate format to


publisher for printing / binding
3.5

Implement training course to pilot group


3.5.1

3.6

Make revisions as necessary based on pilot group feedback

Course Delivery
3.6.1

Designing Women, LLC


Pg. 69

Record training session

PJ Enterprises Customer Service Improvement Plan

In-Classroom
Customer
Service
Training
Course
Schedule
Lesson 3:
Managing
Customer
Conflicts
The following is a
detailed schedule of
specific tasks for the
design and
development of the
30-minute Quarterly
In-Classroom
Customer Service
Course Lesson3:
Managing Customer
Conflicts session that
includes the design
and development of
the Steps to
Customer
Dissatisfaction
Resolution Guide Job Aid and its
accompanying
Facilitators Guide.

In-Classroom
Customer
Service
Training Course Gantt Chart
Lesson 3: Managing Customer Conflicts
The following is a detailed Gantt chart that includes specific milestones and tasks for the design and
development of the 30-minute -Classroom Customer Service Course Lesson3: Managing Customer Conflicts
Designing Women, LLC
Pg. 70

PJ Enterprises Customer Service Improvement Plan

session that includes the design and development of the Steps to Customer Dissatisfaction Resolution Guide Job Aid and its accompanying Facilitators Guide.

Change Management Plan


Purpose
The purpose of the Change Management Plan is to:
1. Manage and control scope change during project completion.
2. Ensure that the project is completed on time.
Designing Women, LLC
Pg. 71

PJ Enterprises Customer Service Improvement Plan

3. Ensure that the project stays within approved budget and scope.
4. Evaluate all changes necessary for project implementation.
5. Deliver a standard process for change within the project.

Goals
The goals of the Change Management Plan are to:
1. Manage the process of any changes and gaps between PJ Enterprises and
Designing Women covering procedures and processes being implemented.
2. Limit modifications in implementing project plan.
3. Align resources to meet PJ Enterprises needs.
4. Stay within spending cost approved by PJ Enterprises and Designing
Women.
5. Encourage process and project changes before any modifications are
determined.
6. Encourage project communication between PJ Enterprises and Designing
Women of project changes as appropriate.

Change Control Process


Designing Women will handle changes that may be presented by following the steps listed
below:
1. Project Coordinator will initiate the Change Request by completing the
Change Request Form and submitting form to the Project Manager.
2. Project Manager and Project Coordinator will review with the
Designing Women Team and identify: (a) needed information (b) next steps to
complete changes (c) document into change log.
3. Project Manager will communicate and coordinate (as needed) with
appropriate personal (SMEs, Project Sponsor, and Project Coordinator) to gather
needed information.
4. Project Coordinator will review and prepare changes needed and
complete the Changes Request Form to submit to the Change Management Team.
5. Designing Women Team will receive weekly updates through email
notification of any pending request for changes within the project with PJ Enterprises
and will provide input as needed via email.
6. Change is approved/denied by Project Manager and provides final
recommendation on the Change Request Form with notifying Project Coordinator
which will then notify team members.
7. The Project Manager communicates the decision to (a) Designing
Women Team making the request of the Change review team decision (b) Any other
active participants involved in the project development (c) Documenting appropriate
entries via email notifications to/by Project Coordinator.
8. Once all steps have been completed, modifications can be processed in
implementation plan based on approved changes from all parties delivered via email
notification.

Designing Women, LLC


Pg. 72

PJ Enterprises Customer Service Improvement Plan

9. All email submissions will be tracked by the Project Coordinator and


will then contact appropriate team members and clients with notifying Project Manager
of project updates.

Responsibilities
Person Responsible

Responsibilities

Leila (Project Manager)

Facilitate the completion of change request and


gather information. Work directly with PJ
Enterprises and vendors (if any applied), work with
appropriate personnel (Project Coordinator,
Business Analyst, Instructional Designers, Graphics
Team, TOs, CSS and Technical Writers to complete
and collect information needed to process request.
Evaluates, allows/disallows change request based
on submitted information. Collects updated
information based on change request.

Erin (Instructional
Designer/Business Analyst)

Receive updates of completed change request.


Provide input as needed/requested. Communicate
via email for information needed to
complete/process updated changes to project.
Provide information based on information gathered.
Produce new plan/strategies developed for new
approved changes.

Lorraine (Technical
Writer/Business Analyst)

Receive updates of completed change request.


Provide input as needed/requested. Communicate
via email for information needed to
complete/process updated changes to project.
Provide information based on information gathered.
Produce new plan/strategies developed for new
approved changes. Review/Edit/Revise all approved
changes for project.

Cynthia (Project Coordinator)

Completes/submits process of change request based


on information needed, approved forms and
communication procedures. Keeps accountability
and documentation of email updates from any
change request submissions and additional
information for the change request. Maintains
updates of completed change request pending
approval. Notifies team members and Project
Manager of any information needed/requested for
revision/completion of project.

Designing Women, LLC


Pg. 73

PJ Enterprises Customer Service Improvement Plan

Communication Plan
Communication Objectives
The Communication Objectives specify what will be achieved within the communication plan.
1. To communicate the changes that the Customer Service Improvement plan will have on all affected
audiences, including any new HR policies and procedures, such as new job descriptions and
performance reviews/incentives, etc.
2. Gain buy-in from all audiences in order to support the changes

Communication Principles
Communication will be:
1. Delivered via the appropriate medium [written/electronic, verbal communication] per the
appropriate channels [email, company or department newsletters, monthly staff meetings/training,
one-on-one supervisor/team member meetings]
2. Discussed and developed based on the specifics of the information needed.
3. Reviewed and approved by the assigned stakeholders before dissemination.

Target Audiences
Audiences that will be affected by the project are:
1.
2.
3.
4.
5.

Telephone Operators (TO)


Customer Service Supervisors (CSS)
Project Sponsor/Management
Human Resources Staff
IT/Operations Staff

6. All PJ Enterprises Staff (encompasses all the above audiences and other staff not already identified)

Key Messages
1. As PJ Enterprises continues to grow and increase our sales, we
also want to make sure we are staying true to our core value of providing excellent customer
satisfaction. Therefore in anticipation of our upcoming busy sales season, we will be rolling out
a new program called the Customer Service Improvement Plan -- several projects aimed at
supporting our customer service staff with new and improved training, as well as revised
employee incentives that will help them be as successful in their jobs as possible, and enable
them to deliver on our promise to our customers.
2. Training provided will include information on new seasonal
and existing products, accompanying reference resources and customer service best practices.
3. Benefits to the customers will include accurate quality
customer service.
4. Benefits for PJ Enterprises after training include supporting
our mission for customer satisfaction, knowledgeable TOs and a potential increase in sales.

Designing Women, LLC


Pg. 74

PJ Enterprises Customer Service Improvement Plan

5. PJ Enterprises will be supported in making these changes by


frequently communicating and being involved with the Designing Women team Project
Manager to develop and design trainings for TOs.
6. Projected start date: 7/31/2014 Projected end date 6/30/2015.
7. PJ Enterprises will know when training was successful after a
collective amount of information has been gathered and reviewed/compared with previous
training data.
8. Customer Service and HR staff will be impacted the most by
the plan and management is here to support them every step of the way through the changes,
because leadership greatly values their contributions and every employees contribution to our
success.

Change Implications
1. PJ Enterprises TOs currently do not have the resources or training to provide quality customer
satisfaction. With the new methods provided by Designing Women, TOs will have the appropriate
procedures, best practices and resources available, including reference guides that will assist with
product information for customer inquiries.
2.

Changes in practices include:


New training topics, delivery and effectiveness evaluation
New customer order entry system procedures
New customer service best practices and procedures
New customer service staff incentives / rewards based on updated performance evaluation
standards
3. Changes in behavior include:

improved communication and trust among all staff


improved sense of job ownership
increased morale/job satisfaction

4. Changes in expectations include:

TOs improved quality of customer service


TOs number of calls processed per hour
TOs job responsibilities
Accountability to participate in staff trainings and meetings
Improved Performance due to new evaluation and incentives
Improved morale and staff retention
5. Employees can participate and contribute to the change by:

attending or completing all required trainings


attending and/or participating in staff meetings
sharing information learned with other staff as appropriate
responding to requests for feedback for evaluation and improvement purposes
communicating questions, concerns and/or challenges with supervisors and management
Designing Women, LLC
Pg. 75

PJ Enterprises Customer Service Improvement Plan

Challenges and Opportunities

Audience
Telephone
Operators

Challenge
Telephone
Operators feel
frustrated with
lack of resources,
training and
product
knowledge
information, and
lack of time for
meetings/trainings

Designing Women, LLC


Pg. 76

Messaging

Channel(s)

Responsible

Ne

w
training/meetin
gs will provide
new skills to
help you on the
job

ne
w incentives
will be
provided to
support you

mail /
written
communicati
on

m
onthly staff
meetings

C
SS and TO
meetings

A
nnual HR
Performance
Evaluation
communicati
ons

PJ - DW Team

PJ Enterprises Customer Service Improvement Plan

Audience
Customer Service
Supervisors (CSS)

PJ Enterprises
Management

Challenge

Messaging

CSS limited
availability to
support TOs
because of
talking to
customers that
are frustrated
with TOs lack
of product
knowledge
or/and timely
manner to
complete order
effectively, and
lack of time for
meetings/trainin
gs

TO
s will complete
Computer
Based training
on phone
etiquette/custo
mer service
skills and inclassroom
products
training

Thi
s should help
improve TOs
performance,
alleviate CSS
from having to
deal with some
customer issues
directly, and
free up CSSs to
provide
improved
managerial
direction to
TOs

ne
w incentives
will be
provided for all
Customer
Service staff
including CSSs

Time and
budget
constraints for
replacing TOs
due to high
turnover, and
the need for
CSSs to be
accountable for
providing
training to new
TOs

Set
ting budgeting
aside for extra
hours for TOs
and CSS to
attend
compensated
trainings
should result in
improved TO
performance
and job
satisfaction/staf
f retention

cus

Designing Women, LLC


Pg. 77

Channel(s)

Em

Responsible
PJ - DW
Team

ail / written
communication

mo
nthly meetings

CS
S and TO
meetings

An
nual HR
Performance
Evaluation
communication
s

Pro
ject status and
program
assessment
reports
delivered via
email and/or
regularly
scheduled
management
meetings

Project
Sponsor

PJ Enterprises Customer Service Improvement Plan

tomer
satisfaction
should improve
and positively
impact sales
PJ Enterprises
Management

Qu
ality two-way
communication
improves
working
relationships,
department
operations and
company
morale by
modeling a
culture of
openness and
trust

Opportunity to
improve
company
culture to one
of trust/value
that will attract
and retain
qualified and
skilled
employees

Pro
ject status
talking points
for leadership
and
management
delivered via
email and/or
regularly
scheduled
management
meetings

all
staff Q&A
sessions during
monthly
meetings

Project
Sponsor /
PJ - DW
Team

Project Plan Approvals


Name

Role

Signature

Jane Smith

Project Sponsor, PJ
Enterprises

Sheena Perez

Merchandising Manager,
PJ Enterprises

Leila Rao

Designing Women, LLC,


Project Manager

Designing Women, LLC


Pg. 78

Date

PJ Enterprises Customer Service Improvement Plan

5. Design Document for PJ Enterprises


Customer Service Training Course
Document Description
Designing Women, LLC (DW) is presenting this Design Document to PJ Enterprises for the
development and design plan regarding the Customer Service Improvement Plans, Customer Service
Training course, for PJ Enterprises Telephone Operators (TOs), who are responsible for over-the-phone
customer orders. This design document outlines the 2-hour Customer Service Training course.

Purpose of the Course


The purpose for the customer service training for PJ Enterprises Telephone Operators is designed to
provide satisfactory customer service skills. The Customer Service Training course will provide
strategies on proper phone etiquette, managing customer challenges, and decreasing customer wait
times. Participants will role play customer service phone call scenarios to improve customer service
skills.

Audience Description
The primary audience for the Customer Service Training course consists of current and new Telephone
Operators (TO) and Customer Service Supervisors (CSS) at PJ Enterprises customer service/order
taking department. Some may have experience in customer service and order taking tasks; however, to
improve PJ Enterprises customer satisfaction mission/goals, all TOs and CSSs will benefit from the
course.

Major Course Objectives


Upon completion of this training, the learner will:

learn the six steps of handling/managing customer complaints and actively apply them on the job
greet 100% of customers with a company standard greeting on all phone calls
end 100% of customer calls with a formal company closure
place customer calls on hold or transfer them by performing the essential steps, without incident at
least 90%
increase calls processed from 3 to 4 - 6 calls per hour by using the provided time management
techniques
resolve customer dissatisfaction issues without supervisor assistance in at least 90% of calls
transfer any unresolved customer dissatisfaction issues to supervisor as needed using proper
guidelines and etiquette techniques, with 70% of transferred calls resulting in customer satisfaction
ratings of above average
perform essential steps to accurately place all customer phone orders, with a margin of error less
than 2%

use
the provided sales tips to introduce customers to a minimum of 1 other product per phone
order
Designing Women, LLC
Pg. 79

PJ Enterprises Customer Service Improvement Plan

Learning Assessment for Course


Learners will engage in role playing activities with real-life customer service scenarios that will
practice, test, and hone skills taught and thereby instill comfort and confidence within the learners
toward job success. Training assessment will consist of the following:

Inclassroom post-role play Question and Answer sessions to discuss types of complaint
scenarios, difficulty/ease of certain steps taken and best practices / lessons learned
quarterly customer service phone call monitoring to assess the degree of implementation/use of the
training techniques, as outlined per the training course objectives

and
mid-quarter review of customer satisfaction surveys, monitoring of customer calls and inperson TO observances with resulting evaluation/recommendation reports to PJ Enterprises
by the end of the quarter to anticipate implementing upcoming quarterly adjustments if
applicable.

Instructional Strategies for Course


The course will follow a combination teaching strategy of Near and Far Transfer performance.
The Near Transfer performance strategy will be incorporated as learners are trained in using a company
specific phone greeting and closure statement, guidelines for hold and/or transferring unresolved
customer dissatisfaction calls to supervisors, and essential steps to follow when placing all orders.
The Far Transfer performance strategy will be used as learners learn and practice selling techniques via
instruction and real-life role play scenarios.

Media
This course will utilize the following media:

TO phone etiquette

Instructor
Slide presentation
Student handouts
Job reference guide

reference guide

Development Tools
The following tools will be used in the design and development of the course:
Microsoft Word
Microsoft PowerPoint
Adobe Photoshop

Adobe InDesign

Class/Seat Time of Course


This Customer Service training course on Conflict Resolution for PJ Enterprises will take 30 hours of
seat time to complete.

Course Outline
Introduction
a) Welcome
Designing Women, LLC
Pg. 80

PJ Enterprises Customer Service Improvement Plan

b) Purpose of Training

Designing Women, LLC


Pg. 81

PJ Enterprises Customer Service Improvement Plan

c) Overview of the Course


d) Course Objectives
e) Brief Summary on Job Aid
Lesson 1: Proper Greetings and Closures for Customer Calls
a) Steps for formal greetings when answering calls
b) Steps for formal closures when ending calls
c) Role Play Scenario
d) Course Summary
Lesson 2: Guidelines for Successfully Holding and Transferring Phone Calls
a) Guidelines for placing a call on hold
b) How to know when to transfer to a supervisor for specific issues
c) Role Play Scenario
d) Course Summary
Lesson 2: Guidelines for Successfully Holding and Transferring Phone Calls
a) Guidelines for placing a call on hold
b) How to know when to transfer to a supervisor for specific issues
c) Role Play Scenario
d) Course Summary
Lesson 3: Handling Customer Conflicts
a) Six Steps to Dissolve Customer Dissatisfaction
b) Video Demonstration on Six Steps
c) Two Role Play Scenarios
d) Course Summary
Lesson 4: Managing Your Time Effectively During calls
a) Etiquette for minimizing talk time with a customer
b) How to avoid distractions, and to focus on your call
c) Role Play Scenario
d) Course Summary
Lesson 5: Proper Etiquette for Taking a Customers Product Order
a) Product accuracy, etiquette for repeating customer information
b) Confirming the order
c) Role Play Scenario
d) Course Summary
Lesson 6: Maximizing Product Orders
a) Guidelines and best-practice techniques for offering product add-ons
b) Role Play Scenario
c) Course Summary
Class Activity: Final Role-Playing Scenario
Designing Women, LLC
Pg. 82

PJ Enterprises Customer Service Improvement Plan

Development Time
The course will be developed in 106 hours. This includes the design and development of learner
handouts, presentation slides, job reference guide, facilitator guide, and course delivery to pilot group
with follow-up revisions. Project management hours that drive the completion of the project are also
included in the total development time.

Support requirements
PJ Enterprises will provide the following support:

SMEs availability for review/editing of all training materials prior to development


SMEs to partner and assist with in-classroom training/instruction
training/meeting room space where the training course will take place
overhead projector and screen
video recorder if role-playing scenarios are to be recorded for future review or CBT use
telephones
current Catalog Product Guides
additional room resources as requested (flip charts, paper pads and writing utensils for the total
number of staff in attendance, etc.)

light refreshments and


beverages

Ownership
Sarah Commons and Maria Gomez, Customer Service Supervisors (CSS), PJ Enterprises will own the
PJ Enterprises Customer Service Training course after completion and will make any future
modifications to the curriculum and delivery as needed.

Project Sign-off
Please sign below indicating agreement with the proposed course plan and approving start-up of the
development phases.

Name

Role

Jane Smith

Project Sponsor, PJ
Enterprises

Erin Skorch

Instructional Designer,
Designing Women, LLC

Designing Women, LLC


Pg. 83

Signature

Date

PJ Enterprises Customer Service Improvement Plan

Appendix A:
Analysis

Designing Women, LLC


Pg. 84

Telephone Operators (TOs) Job Task

PJ Enterprises Customer Service Improvement Plan

Designing Women, LLC


Pg. 85

PJ Enterprises Customer Service Improvement Plan

Appendix B:
Detailed In-Classroom Customer Service Course Outline
Lessons 1, 2, 3
Task
/
Topic
/ Key
Conc
ept

1.

5
mins

Int
ro
du
cti
on

Objec
tive

All course
objectives

Met
hod

Absorb Activity
Presentation
slides

Ass
ess
me
nt

N/A

Visu
als /
Medi
a
Sup
port

Job aid
Slide presentation

a)
We
lco
me
b)
Pur
pos
e of
Tra
inin
g
c)
Ov
ervi
ew
of
the
Co
urs
e
d)
Co
Designing Women, LLC

PJ Enterprises Customer Service Improvement Plan

Pg. 86

Task
/
Topic
/ Key
Conc
ept

Objec
tive

Met
hod

Ass
ess
me
nt

Visu
als /
Medi
a
Sup
port

urs
e
Obj
ecti
ves
e)
Bri
ef
Su
mm
ary
on
Job
Aid
2. 30
mins

Le
ss
on
1:
Pr
op
er
Gr
ee
tin
gs
an
d
Cl
os
ur
Designing Women, LLC

Apply/demonstrate
learned techniques
for proper greetings
and closures of
customer calls

Absorb Activity
- refer to job aid
during
presentation
Connect Activity
Greeting and
Closing Customer
Calls Role Play

PJ Enterprises Customer Service Improvement Plan

R
ol
e
Pl
a
y
S
c
e
n
ar
io

Job aid
Slide presentation

Pg. 87

Task
/
Topic
/ Key
Conc
ept

Objec
tive

Met
hod

Ass
ess
me
nt

Visu
als /
Medi
a
Sup
port

es
for
Cu
sto
m
er
Ca
lls
a)
Ste
ps
for
for
mal
gre
etin
gs
wh
en
ans
wer
ing
call
s
b)
Ste
ps
for
for
mal
clo
Designing Women, LLC

PJ Enterprises Customer Service Improvement Plan

Pg. 88

Task
/
Topic
/ Key
Conc
ept

Objec
tive

Met
hod

Ass
ess
me
nt

Visu
als /
Medi
a
Sup
port

sur
es
wh
en
end
ing
call
s

3. 30
mins

Lesson 2:
Guidelines for
Successfully
Holding and
Transferring
Phone Calls
a) Guidelines for
placing a call on hold

Apply/demonstrate
proper steps for
holding and
transferring calls
using professional
etiquette

Connect
Activity - TOs
pair off and take
turns role playing
TO/Customer calls
using learned
etiquette rules

b) How to know when


to transfer to a
supervisor for specific
issues

Designing Women, LLC

PJ Enterprises Customer Service Improvement Plan

R
ol
e
Pl
a
y
S
c
e
n
ar
io

Job aid
Slide presentation

Pg. 89

Task
/
Topic
/ Key
Conc
ept

4.

30
mins

Lesson 3:
Handling
Customer
Conflicts

Objec
tive

a) Six Steps to
Dissolve Customer
Dissatisfaction

Apply/demonstrate
the six steps to
handling customer
complaints during a
role play scenario

b) Video
Demonstration on Six
Steps

5.

5
mins

Designing Women, LLC

Briefly recap all


three lesson
objectives

Refer to all Job


Aids/materials as
take-aways

Refer to follow-up
training information
if applicable

Met
hod

Ass
ess
me
nt

Absorb Activity
- Presentation

Video
Demonstration on
customer conflict

Connect Activity
Role play
scenarios #1 and
#2

Absorb Activity
Presentation
slides

T
w
o
R
ol
e
Pl
a
y
S
c
e
n
ar
io
s

PJ Enterprises Customer Service Improvement Plan

N/A

Visu
als /
Medi
a
Sup
port

Job aid
Slide presentation

Presentation
Slides

Pg. 90

Vous aimerez peut-être aussi