INSTRUCTION: Select the correct answer for each of the following questions. Mark
only one answer for each item by shading the box corresponding to the letter of
your choice on the answer sheet provided.
STRICTLY NO ERASURES ALLOWED. Use pencil no. 2 only.
1. Employees get a bonus if the firms costs are reduced due to increased work efficiency.
A. Bonus
C. Loan
B. Merit Pay
D. Gain Sharing Program*
2. What is defined as critical viewing or investigation or a careful, complete and
systematic examination of some electronic items, installation and project question?
A. Investigation
C. Inspection*
B. Autopsy
D. Observation
3. This skill involves the ability to see the enterprise as a whole.
A. Technical Skill
C. Human Skill
B. Managerial Skill
D. Conceptual Skill*
4. What refers to the act of conceptualizing, planning and projecting scheme, system and
facility using the arts and science of electronics along with social, economic,
financial and technical consideration?
A. Planning Service
C. Design Service*
B. Concept Service
D. Project Service
5. What style of leadership should the engineer manager use when his unit is manned by
professionals?
A. free rein leadership*
C. professional leadership
B. functional authority
D. all of these
6. It is used when product are made singly or in small batches. It happens when a small
number of products are processed at each storage before going on to the next stage.
A. Batch Production
C. Job Production*
B. Flow Production
D. Production Design
7. What type of training is where the trainee is placed in a situation almost exactly the
same as the workplace where machines, materials, time constraints are present with the
trainer working full time?
A. Training School
C. Vestibule School*
B. Job School
D. Foyer School
8. What refers to the method of determining the early start and finish times for each
activity in the project network?
A. Forward Pass*
C. Upward Pass
B. Backward Pass
D. Downward Pass
9. It is a method of managing all the activities that affect the quality of goods or
services in order to prevent faults.
A. Quality Assurance *
C. Quality Circle
B. Quality Control
D. Quality Standard
10. It is the name given to any activity undertaken by the organization with the express
purpose of gaining information about potential customer
A. Market Analysis
C. Market Intelligence
B. Market Research*
D. Market System

Page 1 of 2

UIC, DAVAO CITY


ENGINEERING MANAGEMENT
Engr. Melvin John Habla Banzuelo

COLLEGE DEPT.
MIDTERM EXAM.
Oct. 15-17, 2014

NAME:______________________________

SCORE:_________

11. This process can be used to measure achievement in Total Quality Management (TQM)
system. Also it provides the essential control and measure feedback loop necessary for
quality improvement
A. Benchmarking*
C. Continuous Improvement
B. Quality chain
D. Quality circle
12. The process of successfully influencing the activities of a group towards the
achievement of a common goal.
A. Background skills
C. Human skills
B. Interpersonal skills*
D. Technical skills
13. When the decision-maker is able to assign probabilities to the various events, the use
of probabilistic decision rule called ___ become possible?
A. Bay Criterion
C. Monte Carlo Criterion
B. Bayes Criterion*
D. Hayate Criterion
14. It is the rational way to ensure that our limited time is always used effectively.
A. Management Commitment
C. Management Responsibility
B. Time Management *
D. Time Conflict
15. It is the process of attracting potential employees to the company so that the
selection process can be carried out.
A. Advertising
C. Benchmarking
B. Selection
D. Recruitment*
16. What refers to a fundamental obligation under the contract which goes to the root of
the contract?
A. Warranty
B. Injuction
C. Condition*
D. Innominate terms
17. What is sometimes referred to as the heart of all the management functions?
A. Decision Making*
C. Recruitment
B. Risk Assessment
D. Promotion
18. What is the keystone of professional conduct?
A. Justice
B. Honesty
C. Integrity*

D. Loyalty

19. What refers to the method used to compute the late start and and finish time of each
activity in the project network.
A. Forward Pass
B. Backward Pass*
C. Upward Pass
D. Downward Pass