Académique Documents
Professionnel Documents
Culture Documents
WAPDA PRACTICES
WAPDA have to analyses whether fault lies in prescribing the standards, their implementation,
the management or the resources.
There is no doubt that performance of any utility is measured from the quality of service it
provides to its consumers. Evidently our proficiency cannot be compared with any developed
nations due to lack of financial resources. However in WAPDA system there is a lot of margin
for improvement due to lack of proper planning and maintenance and Poor workmanship. Let us
have a look at some photographs, which represents our system.
WPDA identified that most of the systems here run on either Gas or Coal i-e
they are thermal systems. Both Gas and Coal are considered as scarce and
expensive commodities for electricity producers.
Lack of Capacity of Transmission of Electricity:
Management identified that most electricity transmission lines here in
Pakistan are incapable of transmitting electric voltages of more than two
phases. This makes them in-compatible to carry higher voltages.
Type
Causes
HI TECH Faults
(Difficult to
Identify)
1) Switching Surges
2) Lightning discharge
3) Power frequency synchronisation
problems
4) Harmonies
5) Corona
6) Capacitances & inductance of
Transmission Line
7) Air pollution
1) Equipment failures/mal operations
2) Relay malfunctions
3) Indiscriminate trappings
4) Lack of proper protection
5) Insulation Co-ordination
1) Non compliance to standards
a) Construction
b) Materials
- Loose Jumpers & Connections
- Improper conductor clearances
- Loose binding of conductor with
insulators
- No or Poor earthling
- Improper line sag
- Unequal or excessive tension on
conductors (poles out of
alignment)
- Broken or cracked insulators
- Improper protection to equipment
- Imbalance of three phase loads
1) External interferences
2) Lightening, Wind storm, Kites, Traffic
Accidents
Bridge
Medium TECH
(Simpler to
identify)
Low Tech Faults
(Common Fault,
Most of them
Apparent &
Visible)
Percentage
5%
15%
70%
10%
Cost
1KM
408,000
1408,000
2 Nos.
185,000
370,000
30 Nos.
9400
282,000
1KM
225,000
225,000
1,285,000
Cost
1KM
272,000
272,000
2 Nos.
140,000
280,000
1KM
200,000
200,000
30 Nos.
4500
135,000
TOTAL COST
887,000
Cost of single phase system is at least 33% cheaper compared with three
single phase system .We can have still more savings up to 40% of total cost
by designing lighter poles for single conductor. In addition single phase
system will drastically reduce cost of maintenance and improve power supply
as there will be no problem of phase to phase short circuits.
7. ACTION:
After the cost comparison WAPDA has decide that introduce single
phase system. Because this technology is cheaper as compare to
than three single phases.
8. Data gathering after implementation:
After changing the technology we reached at these result.
The advantages of single-phase system over three-phase system are
elaborated below:
Single-phase system is 30% to 40% cheaper compared to
three-phase system.
It is simpler and easier to maintain as Single-phase will carry
only one conductor for 11 kV and two conductors for LT
feeders.
11 kV single-phase systems can be laid down in narrow streets
as cross-arms are eliminated.
30% larger span can be used with the same height of
structures.
There will be no phase to phase short circuits due to improper
sags, unequal or loose tension on conductor, broken or tilted
cross-arms.
Over hanging branches of trees will not cause any short circuit
as in case of three-phase system.
There will be no short circuits on 11 kV feeders due to kite
strings.
There will be no problem due to imbalance of loads on singlephase transformers as in case of three-phase system.
Three-phase transformers are more vulnerable to short circuits
compared to Single-phase transformer.
Damage to grid station equipment will be reduced
proportionate to reduction in faults on 11 kV systems.
Balancing of load on 11 kV feeders will be easy.