OCCUPATION: JUNIOR ELECTRICAL TECHNICIAN

01
PERFORM ELECTRICAL SINGLE PHASE WIRING
DUTY NO.
DUTY
01.01
CARRY OUT SINGLE PHASE SURFACE WIRING
TASK NO.
TASK
LEVEL
L1
PERFORMANCE STANDARD:
Carry out single phase surface wiring using electrical hand tools, electrical
equipments, electrical materials etc. so that single phase surface wiring,
installation of accessories, fitting and testing is carried out according to IEE
regulation and specification.
SUB TASK/STEP

ENABLING REQUIREMENT
(Knowledge, Skill, Attitude & Safety)

1. Obtain single phase


Knowledge of:
1.1 Electrical symbol
wiring drawing
1.2 Institute Electrical Engineering (IEE)
regulation
1.3 Wiring connection
Ability to:
1.1 Get drawing from supervisor/superior
2. Inspection on actual
location

Knowledge of:
2.1 Building structure
2.2 Blue print
Ability to:
2.1 Identify the correct location
2.2 Interpreter blue print/wiring drawing

3. Prepare tools,
equipments and
materials

Knowledge of:
3.1 Electrical hand tools
3.2 Electrical equipments
3.3 Electrical materials
Ability to:
3.1 Select electrical hand tools
3.2 Select electrical equipments
3.3 Select electrical materials
Attitude / safety:
3.1 Personal protection equipments

4. Wired single phase


domestic wiring

Knowledge of:
4.1 correct materials
4.2 Tools and equipments
4.3 wiring drawing according to SOP and IEE
regulation
Ability to:
4.1 Select and use correct wiring materials
4.2 Select and use wiring tools and
equipments needed
4.3 Carry out wiring work according to wiring
drawing and IEE regulation
Attitude/safety:
4.1 Personal protection equipment
4.2 General safety

17

TOOLS, EQUIPMENT &


MATERIALS
IEE regulation book
Blue print
Electrical equipment
Electrical hand tools
Electrical power tools
Electrical material such
as:
- Double insulated
cable
- Wiring lead
- Wiring neil
- PVC tape
Single insulated
cable
- Trunking metal/PVC
- Trunking
Accessories
- Trunking tools
- Single insulated
cable
- Metal conduit/PVC
conduit
- Conduit accessories
- Metal/PVC
- Fish wire etc.
- Conduit tools
Personnel protection
equipment
Electrical accessories
Electrical fitting
Testing instrument
Standard Operating
Procedure

18

SUB TASK/STEP

ENABLING REQUIREMENT
(Knowledge, Skill, Attitude & Safety)
4.3 Work shop/environment safety rule and
regulation

5. Fix accessories and


Knowledge of:
5.1 Electrical accessories
fitting
5.2 Electrical fitting
5.3 Wiring drawing
Ability to:
5.1 select and fix electrical accessories
5.2 Select and fix electrical fittings
5.3 Apply IEE regulation to terminate control
cables, accessories and fittings
Attitude/safety:
5.1 Personal protection equipment
5.2 General safety
5.3 Work shop and environment
6. Test electrical
installation.

Knowledge of:
6.1 Testing procedure
6.2 IEE regulation
Ability to:
6.1 Carry out insulation/polarity and continuity test
6.2 Carry out installation inspection
Attitude/safety:
6.1 IEE rule and regulation
6.2 General safety
6.3 Workshop/environment safety rule and
regulation.

18

TOOLS, EQUIPMENT &


MATERIALS

OCCUPATION: JUNIOR ELECTRICAL TECHNICIAN


DUTY NO.
01
DUTY
PERFORM DOMESTIC WIRING
01.02
CARRY OUT SINGLE PHASE TRUNKING WIRING
TASK NO.
TASK
LEVEL
L1
PERFORMANCE STANDARD:
Carry out single phase trunking wiring using electrical hand tools, electrical
equipments, electrical materials etc. so that single phase trunking installation of
accessories, fitting and testing is carried out according to IEE regulation and
specification.
SUB TASK/STEP

ENABLING REQUIREMENT
(Knowledge, Skill, Attitude & Safety)
Knowledge of:
1.1 Electrical symbol
1.2 IEE regulation
1.3 Wiring connection
Ability to:
1.1 Get drawing from Supervisor/superior

1. Wiring single phase


trunking

Knowledge of:
2.1 Building structure
2.2 Blue print
Ability to:
2.1 Identify the correct location
2.2 Interpret blue print and wiring drawing
Knowledge of:
4.1 Electrical hand tools
4.2 Electrical equipments
4.3 Electrical material
Ability to:
3.1 Select electrical hand tools
3.2 Select electrical equipments
4.4 Select electrical material
Attitude/safety:
Personal Protection Equipments
Knowledge of:
4.1 Correct materials
4.2 Tools and equipments
4.3 Wiring drawing according to SOP/IEE
regulation
Ability to:
4.1 Select and use materials
4.2 Select and use wiring tools and
equipments
4.3 Carry out wiring work according to drawing
and IEE regulation
Attitude/safety:
4.1 Personal Protection Equipment
4.2 General safety
4.3 Work shop/environment safety rule and
regulation

19

TOOLS, EQUIPMENT &


MATERIALS

SUB TASK/STEP
5.

ENABLING REQUIREMENT
(Knowledge, Skill, Attitude & Safety)
Knowledge of:
5.1 Electrical accessories
5.2 Electrical fittings
5.3 Wiring drawing
Ability to:
5.1 Select and fix electrical accessories
5.2 Select and fix electrical fittings
5.3 Apply IEE regulation to terminate control
cables, accessories and fittings
Attitude/safety:
5.1 Personal Protection Equipment
5.2 General safety
5.3 Work shop/environment
Knowledge of:
6.1 Testing procedure
6.2 IEE regulation
6.4 Standard Operating Procedure
Ability to:
6.1 Carry out insulation, polarity and continuity
test
6.2 Carry out installation inspection
Attitude/safety:
6.1 Safety regulation
6.2 Personal Protection Equipment
6.3 IEE rule and regulation

20

TOOLS, EQUIPMENT &


MATERIALS

OCCUPATION: JUNIOR ELECTRICAL TECHNICIAN


DUTY NO.
01
DUTY
PERFORM DOMESTIC WIRING
01.03
CARRY OUT SINGLE PHASE CONDUIT WIRING
TASK NO.
TASK
LEVEL
L1
PERFORMANCE STANDARD:
Carry out Single Phase conduit wiring using electrical hand tools, electrical
equipments, electrical materials etc. so that single phase conduit wiring,
installation of accessories, fittings and testing are carried out to IEE regulation
and specification.
SUB TASK/STEP

ENABLING REQUIREMENT
(Knowledge, Skill, Attitude & Safety)
Knowledge of:
1.1 Electrical symbol
1.2 Institute of Electrical Engineering
regulation
1.3 Wiring connection
Ability to:
1.1 Get drawing from Supervisor/superior

1. Wiring single phase


conduit wiring

Knowledge of:
2.1 Building structure
2.2 Blue print/layout
Ability to:
2.1 Identify the correct location
2.2 Interpreter blue print and wiring drawing
Knowledge of
4.1 Electrical hand tools
4.2 Electrical equipments
4.3 Electrical materials
Ability to:
3.1 Select electrical hand tools
3.2 Select electrical equipments
3.3 Select electrical materials such as cable,
fittings, conduit junction box and accessories
Attitude/safety:
3.1 Personal Protection Equipments
Knowledge of;
4.1 Correct materials
4.2 Tools and equipments
4.3 Wiring drawing according to SOP/IEE
Ability to:
4.1 Select and use electrical conduit materials
4.2 Select tools and equipments
4.3 Carry out wiring work according to wiring
drawing and IEE regulation
Attitude/safety:
4.1 Personal Protection Equipment
4.2 General safety
4.4 Work shop/environment safety rule and
regulation

21

TOOLS, EQUIPMENT &


MATERIALS

SUB TASK/STEP

ENABLING REQUIREMENT
(Knowledge, Skill, Attitude & Safety)
Knowledge of:
5.1 Electrical accessories
5.2 Electrical fittings
5.3 Wiring drawing
Ability to:
5.1 Select and fix electrical accessories
5.2 Select and fix electrical fittings
5.3 Apply IEE regulation to terminate cables to
electrical accessories and fittings
5.4 Type of installation and testing
Attitude/safety:
5.1 Personal Protection Equipment
5.2 General safety
5.3 Work shop and environment
Knowledge of:
6.1 Testing procedure
6.2 IEE regulation
6.1 Standard operating procedure
Ability to:
6.1 Carry out insulation, polarity and continuity
test
6.2 Carry out installation inspection
Attitude/safety:
6.1 Safety regulation
6.2 Personal protection Equipment
6.3 IEE rule and regulation

22

TOOLS, EQUIPMENT &


MATERIALS

OCCUPATION: JUNIOR ELECTRICAL TECHNICIAN


DUTY NO.
02
DUTY
PERFORM DOMESTIC WIRING
01.04
INSTALL DISTRIBUTION BOARD AND TERMINATION
TASK NO.
TASK
LEVEL
L1
PERFORMANCE STANDARD:
Install distribution board using Electrical hand tools, Electrical equipments, cables,
blue print, testing instruments and fitting materials so that distribution board is
installed and terminated according to specification.
ENABLING REQUIREMENT
(Knowledge, Skill, Attitude & Safety)

SUB TASK/STEP
1. Identify actual location
through blue print

Knowledge of:
1.1 Blue print
Ability to:
1.1 Interpret blue print

2. Confirm number of
circuit/load

Knowledge of:
2.1 Type of circuit/connection
2.3 Type of load/connection
Ability to:
2.1 Identify type of circuit/controls
2.2 Calculate electrical load/circuit

3. Confirm the actual


location

Knowledge of:
3.1 Building structure
3.1 Blue print
Ability to:
3.1 Identify correct location
3.2 Interpret blue print/wiring drawing

4. Select the tools and


accessories

Knowledge of:
6.1 Accessories, fittings and tools
6.2 Accessories connection and function of tools
Ability to:
4.1 Identify accessories and fitting
4.2 Identify connection terminal

Fix distribution board

Knowledge of:
5.1 Operation of hand tools and equipment
5.2 Blue print
Ability to:
5.1 Identify type of hand tools and equipment
5.2 Interpret blue print
Attitude/safety:
5.1 Personal protection equipment
5.2 General safety
5.3 Work shop and environment safety rules and
regulation

6. Terminate and inspect


final sub circuit and
incoming circuit

Knowledge of:
6.1 Cable color code
6.2 IEE regulation
6.3 Standard operating procedure

23

TOOLS, EQUIPMENT &


MATERIALS
Cables
Blue print
- Test instruments
fixing material
Electrical power tools
IEE regulation
Distribution Board

SUB TASK/STEP

ENABLING REQUIREMENT
(Knowledge, Skill, Attitude & Safety)
Ability to:
6.1 Identify cable color code
6.2 Interpret wiring drawing
6.4 Inspect cable termination and installation
Attitude/safety:
6.1 Safety regulation
6.2 Personal Protection Equipment
6.3 IEE rule and regulation

24

TOOLS, EQUIPMENT &


MATERIALS

25

Vous aimerez peut-être aussi