Académique Documents
Professionnel Documents
Culture Documents
DRSR - 001
Project:
Job No.:
Design Task Element:
Bob Hajjar
Originator / 3/4/2009
Revision No.:
John Smith
Reviewer / 3/7/2009
Objective
The purpose of this task is to design the superstructure elements of the replacement
bridge which carries Interstate 91 (I-91) over the Deerfield River and Stillwater Road.
The project consists of replacing the existing 6-span Northbound and Southbound bridges
with new 5-span steel plate-girder bridges.
This work includes, but is not limited to:
o Superstructure design of steel plate girders, diaphragms, utility supports, splices,
bearing stiffeners, shear connectors, and the calculation of cambers and top of
form elevations.
o Deck Design selection of reinforcement and concrete deck thickness as well as
selection of additional reinforcement in deck overhangs.
o Substructure design of the abutment, reinforcement and geometry; calculation
of beam seat elevations at abutments and piers; pier wall design including
reinforcing in the wall and pile cap, selection of pipe piles at the piers, and design
of the cofferdam and tremie seal at the piers.
Prerequisites (Input)
Required Formats:
o All calculations and drawings will be in English units.
o Two independent sets of calculations will be performed for the design, with the
exception of the steel plate girder design, which will be designed using MerlinDash and independently verifying the input. All detailing work computed using
Merlin-Dash shall be verified by equivalent hand calculations.
o Computations should be performed in accordance with current Design Control
Procedures for the Preparation and Review of Calculations.
DTP: DF-S-001
PAGE 1 OF 5
Design
Design Criteria: All design is in accordance with the 5th Edition of AASHTO LRFD
Bridge Design Specifications 2010, the 1st Edition of AASHTO Guide Specifications for
LRFD Seismic Bridge Design 2009, and the Massachusetts Department of Transportation
(MassDOT) LRFD Bridge Manual (2009) Part I and II. All steel design shall be designed
by the Load and Resistance Factor Design Method (LRFD).
Design Manuals:
o MassDOT Highway Division LRFD Bridge Manual (2009)
Design Loads: This structure will be designed for AASHTO group loadings, including:
dead load, live load, wind, seismic, and all other loads as directed by the Codes and
Standards above, with minimum values as specified below:
o Dead Load
Soil
Concrete
Steel
Water
Pavement
120 pcf
150 pcf
490 pcf
62.4 pcf
150 pcf a 3 HMA wearing surface shall
be taken into account
250 plf (B.M. section 3.5.4.2)
Utility loads
o Live Load
Each bridge shall be designed for HL93 truck loading. Appropriate
distribution factors will be calculated by AASHTO and dynamic load
allowance shall be included. Two 12 lanes, one 10-0 shoulder, and one
8-0 shoulder will be carried over each bridge (D-06-044). Staged
construction need not be considered in the superstructure design as a
temporary bridge will be provided.
o Wind Load
DTP: DF-S-001
PAGE 2 OF 5
A wind load of 50 psf shall be applied horizontally and at right angles for
groups II and V. Groups III and VI loadings shall comprise the loads used
in group II and V reduced by 70%.
o Seismic Load
25 percent of tributary dead load is considered for seismic design of
substructure. Per Section 3.10.8 of AASHTO LRFD Bridge Design
Specifications 2010, 100 percent of the absolute value of the force effects
in one of the perpendicular directions will be combined with 30 percent of
the absolute value of the force effects in the second perpendicular
direction and vice versa.
Materials:
o Superstructure
o Concrete: 4000 psi, 585 HP Cement Concrete for deck,
o Reinforcement: AASHTO M31, GRADE 60 Stainless Steel
o Structural Steel: Uncoated weathering steel, AASHTO M270, Grade 50W
o High Strength Bolts:
All field connections shall be made with AASHTO M164 (A325)
o Anchor Rods: ASTM F1554 Grade 50
o Substructure
o Concrete:
4000 psi, 1 565 Cement Concrete for pier footing, lower half of
abutment, and approach slab
4000 psi, , 610 Cement Concrete for pier wall, pier diaphragms, keeper
blocks, and the upper half of abutment
4000 psi, 3/8, 705 Cement Concrete for pier pipe piles
5000 psi, , 685 HP Cement Concrete for retaining wall barriers
o Reinforcement: AASHTO M31, GRADE 60, epoxy coated
o Structural Steel: Uncoated weathering steel, AASHTO M270, Grade 50W
o High Strength Bolts:
All field connections shall be made with AASHTO M164 (A325)
o Anchor Rods: ASTM F1554 Grade 36
Preferred analysis methods and design approaches: All analysis and design will be
completed using the software listed below following guidelines from AASHTO. Load
and Resistance Factor Design shall be used for all superstructure, deck, and substructure
elements. The following elements have specific design criteria:
o Steel Plate-girder Design
Plate-girders will be designed using Merlin-Dash software.
Plate-girders shall be designed considering composite design, following
the steps outlined in the MassDOT Bridge Manual Chapter 3.
Load Distribution
Distribution of loads will be per MassDOT Bridge Manual
Section 3.5.3
Shear connectors
DTP: DF-S-001
PAGE 3 OF 5
PAGE 4 OF 5
Assumptions:
o See those stated above
Appropriate Validated Software: Merlin-Dash, STAAD, LEAP Bridge Suite RC Pier, LPile Group, MathCad, validated Microsoft Excel spreadsheets.
Construction Specifications: Designer should review Construction Specifications to
ensure consistency of material properties specified and construction methods to be used.
Interdisciplinary Coordination
Significant coordination with the Civil Department is required for geometry, utilities,
obstructions, and construction phasing.
END OF PROTOCOL
DTP: DF-S-001
PAGE 5 OF 5