construction work. This Inspection and Testing Plan outline the extent of witness inspection and its
reporting.
CONFLICTING REQUIREMENTS
Should conflicts exist between this specification and other documents, the following order of
precedence shall govern:
1. Scope of Work
2. Data Sheets
3. This Specification
4. Other Company Specification
5. Other Referenced Publications
6. Approved for Construction Drawings
7. Vendors Code
COORDINATION
Quality Control and Inspection by CONTRACTOR
For the items marked with SW and W under column CONTRACTOR, the quality control
and inspection will be conducted by CONTRACTOR at their own responsibility. However,
COMPANY shall have the right to inspect any works done by CONTRACTOR or Vendor at any time
(except for W , a written notification from CONTRACTOR is required).
Inspection Hold Point
For item marked with H under column of COMPANY and CONTRACTOR, CONTRACTOR
shall notify COMPANY in writing of the inspection scheduled date and time. Witnessing shall be
jointly performed by CONTRACTOR and COMPANY. CONTRACTOR can not proceed the next
work step activity until the inspection and measurement or test has been witnessed and approved by
all attending parties.
Notification of Inspection
CONTRACTOR shall give a written notification to COMPANY for attending the inspection/testing.
Document Approval
For item marked with A under column COMPANY, CONTRACTOR shall submit documents,
drawing, etc. to COMPANY. For item marked with A under column CONTRACTOR, Vendor
shall submit documents, drawing, etc. to CONTRACTOR for approval. Inspection shall not be
conducted before COMPANY approves the required documents.
Document Review
For item marked with R under column COMPANY, CONTRACTOR will submit documents,
drawing, etc. to COMPANY for review / comment. For item marked with R under column
CONTRACTOR, Vendor shall submit documents, drawing, etc. to CONTRACTOR for review /
comment.
Document Verification
For item marked with D under column COMPANY, CONTRACTOR shall submit documents,
drawing, etc. to COMPANY for a report and/ or comments (if required). CONTRACTOR shall
accommodate COMPANYs comments (if any). For item marked with D under column
CONTRACTOR, Vendor shall submit documents, drawing, etc. to CONTRACTOR for
verification and review and or report.
4 Responses
1. ASME IX Home Welding & Inspection, on July 15, 2009 at 5:46 am said:
[...] Procedure Qualification Record ( PQR ) Is a record of variables recorded during the
welding of the test coupon , its also contains the test results of the tested specimens.
Contents Actual variables used (of each process) during the welding and shall be certified
by manufacturer Changes Changes to the PQR (content including date) is not permitted
except editorial corrections or addenda Format Any format as long as all variables, type
& number of tests and test results are included Availability Shall be available for
reference & review by the Authorize Inspector Multiple WPSs with one PQR or Single
WPS with multiple PQRs may be used [...]
GENERAL
Inspection & Test Plan shall be submitted to owner for getting approval prior
commences shop fabrication or construction works.
All inspection and Test required shall be in written procedure in accordance with
the owner technical specifications.
The below discussion describes applicable sample of Inspection and Test Plan
applied for construction project.
to particular discipline work activities. All inspection and test reports form shall be
specific to the activity and items inspected.
CONTRACTOR shall also prepare a detailed inspection and test plan indicating
inspection levels (Spot witness, witness, hold point, etc), based on Owner definitions
herein. The test inspection plan shall include witness/attendance requirements by
Owner/Authorized body and/or THIRD PARTY.
Manufacturer/ Subcontractor shall submit their inspection and test plan based on
the CONTRACTORS inspection and test plan document for CONTRACTOR or Owner
review and approval.
CONTRACTOR shall generate, maintain document, and collate the inspection records,
which is done by them or by its Manufacturer. The system employed shall insure full
tractability of records including back up in accordance to Owner requirements.
CONTRACTOR shall submit the originals of all inspection data and other related documents
to Owner, as required by the contract terms