21st March 12 20th April 12

AL-HASSAN ENGINEERING CO. S.A.O.G


PROJECT: AMAL POWER STATION
PDO CONTRACT NO: C-310987
DOCUMENT NO.
AML-391-AA -6944-0032-000

AL-HASSAN ENGINEERNG CO. SAOG


PROJECT: AMAL POWER STATION
(PDO CONTRACT NO: C-310987)

AML-391-AA-6944-0032000

01

25.04.12

1 to 57

For Approval

A.R.D

K.G.B.

Document No

Rev
No

Date

No. of
`Pages

Description

Prepared
By

Reviewed
by

Approved
by PDO

MONTHLY PROGRESS REPORT


TABLE OF CONTENTS
Page

Section 1

Contract Particulars

1.01

Salient Features of the Contract

1.02

Contract Scope of Work in brief

Section 2

7
8

Project Summary Report

2.01

Project Progress Statistics

2.02

Narrative Summary Report

2.03

Over-all Progress Curve for the Project

2.04

Areas of Concern

Section 3

11
12
12
12

Detailed Report

3.01

Health, Safety and Environment (HSE)

3.02

Engineering & Design Documents

3.03

Procurement

3.04

Manufacturing

3.05

Delivery

3.06

Mobilization

3.07

On plot construction and commissioning

3.08

Off Plot construction and Commissioning

3.09

Equipment Deployment

Doc. No: AML-394-AA-6944-0032-000

14
14
14
14
14
14

Rev. No : 01

15
17
17

Date: 25.04.12

Page 3 of 57

MONTHLY PROGRESS REPORT


3.10

Manpower Deployment

3.11

Quality Assurance

3.12

Plan for Next month

3.13

Contract Financials

Doc. No: AML-394-AA-6944-0032-000

19
20

Rev. No : 01

21
23

Date: 25.04.12

Page 4 of 57

MONTHLY PROGRESS REPORT


Section 4

Appendices

Project Milestone Dates

26

II

Project Schedule (Updated)

31

III

Drawing Control Register

32

IV

Material Tracking Register

33

Critical Project Material List

34

VI

Health & Safety Statistics (Monthly Return)

35

VII

HSE Audit / Inspection Schedule

36

VIII

HSE Training Matrix

38

IX

Quality internal and external audit schedule

39

Summary of progress

40

XI

S-curve for Engineering Progress

42

XII

S-curve for Procurement Progress

43

XIII

S-curve for Construction progress

44

XIV

S-curve for Overall progress

45

XV

S-curve for VOWD

46

XVI

Manpower & Equipment Histogram

47

XVII

Subcontract Details

48

XVIII

Variations Register

50

XIX

Omanisation Requirement

51

XX

SPIR Progress

53

XXI

Progress Photographs

55

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 5 of 57

MONTHLY PROGRESS REPORT

SECTION 1

CONTRACT PARTICULARS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 6 of 57

MONTHLY PROGRESS REPORT


1.01

Salient Features of the Contract


Project Title

: Amal Power Station

Company / Employer

: Petroleum
LLC

Company Contract Holder

: Mr. Harith M Al Amry UIE/5

Company Representative

: Mr. Saud Al Habsi UIE/52

Contractor

: Al-Hassan Engg. Co. S.A.O.G

Contract Value

: Rial Omani 22,950,786/-

Effective Date of Contract

: 24th June 2009

Commencement Date

: 4th July 2009

Contract Duration

: 730 Days

Substantial Completion

: 5th April 2011

Completion Date

: 4th July 2011

Engineering Sub-Contractor

: Mott MacDonald & Company LLC,


Oman

SAP Purchase Order No

: 4500439405

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Development

Date: 25.04.12

Oman

Page 7 of 57

MONTHLY PROGRESS REPORT


1.02: Contract Scope of Work in Brief:
The Amal Power Station will be of modular construction and will comprise initially of
two Frame 9E Gas Turbine Generator (GTG) units.

Construction and commissioning of Amal Power plant comprising two


frame 9E Gas turbine units Installed capacity 252 MW.

Provision will be made for the future addition of Once through Heat
Recovery Generators (OTHRSs) on the back end of the GTG.

Amal Power Station with Frame 9E GTGs will have an ISO rated installed
capacity of 252MW. At a site ambient temperature of 48 deg C,
corresponding to maximum summer temperatures, this will drop to
197.4MW.

Each GTG unit will be unitised such that any equipment failures
associated with one GTG unit will not cause a trip of an adjacent GTG
unit.

The fuel gas for Amal Power Plant will be supplied from 18 Hubara to
Amal Pipeline and the tie-in point for fuel gas will be provided on 18
bypass line near Amal pie receiver A-2075.

A unitized gas treatment trains will be provided to ensure the gas


delivered to the gas turbine meets the gas turbine Original Equipment
Manufacturers (OEM) requirements at all times.

The Amal Power Station is designed for unmanned operation and under
normal operation will be remotely controlled by SCADA and monitored

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 8 of 57

MONTHLY PROGRESS REPORT


from the Yibal/QA Master Control Room with backup from the
Marmul\Nimr Control Room.

Facilities Service water, DM water, Instrument air system incorporating


screw type compressors and membrane dryers will be provided.

Facilities for transferring Diesel fuel to the Emergency DG set will be


provided.

Gas turbines shall be free issued by PDO. Design, supply of BOP is part
of AHEC scope.

Design and construction of Unit Electrical buildings and Gas treatment


plant building.

Design, supply and construction of OHL from Nimr Central to LILO


location AP05(28 KM) and from LILO location AP05 to Thuleilat ( 70 KM)

HVAC System.

Power Station internal and external communication with provision of


CCTV.

Fire detection and alarm system.

Scope includes interfacing with GTG OEM supplier/ Vendor.

Pre commissioning and commissioning.

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 9 of 57

MONTHLY PROGRESS REPORT

SECTION 2

PROJECT SUMMARY REPORT

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 10 of 57

MONTHLY PROGRESS REPORT


2.01

Project Progress Highlights:


Highlights of April, 2012.

10.1 KM New OHL erection and bolt tightening 34 / 34 nos completed.

10.1 KM New OHL ELM conductor stringing completed except 2 shut


down location.

2.02

10.1 KM OHL OPGW installation works in progress.

Unit # 1 & 2 punch point attending in progress.

Narrative Summary Report


Project progress during the month of March 21st to April 20th
is summarized as follows

Overall project progress for the month has reported 0.05% against the
planned progress 0.10%.

Cumulative overall progress for the month has reported 99.85% against
the planned progress 100%.

Cumulative engineering progress for the month has reported 100%


against the planned progress 100%.

Cumulative Procurement /Manufacturing/ delivery progress is 100%


against the planned progress 100%.

Cumulative construction progress for the month is 99.58% against the


planned progress 100%

2.03

Overall progress curve for the project

2.04

As per section 4, Appendix XII

AREAS OF CONCERN
Receipt of inputs from PDO/BHEL

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 11 of 57

MONTHLY PROGRESS REPORT


1. Unit # 2 - CO2 system connecting Hose. CO2 panel battery back up for
unit # 1 & 2.
2. Unit # 2 - 125V - DCDB - Variable Resistor - 01 set. (3 nos) for DC
Jacking oil pump cubicle.
3. Lube oil NRV, Step down transformer (220V/110V) for the MOV's in U#2
Accessory Base. Shaft for ABOC Fan#7 bearing block
4. Refer critical material list for balance materials.

Other area of concerns


1. Communication between Marks V1 and DCS.
2. MFM SCADA communication.
3. Passing of ESD valve in GTP

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 12 of 57

MONTHLY PROGRESS REPORT

SECTION 3

DETAILED REPORTS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 13 of 57

MONTHLY PROGRESS REPORT

3.01: Health, Safety and Environment (HSE).


Major highlights of the month:

Weekly HSE gate meeting conducting on every Saturday.

Conducting daily tool box for driver and work force before starting of
work.

HSE Monthly meeting conducted.

Vehicle inspection completed 50% along with plant department.

3.02: Engineering & design documents


Major highlights of the month:

3.03: Procurement
Major highlights of the month:

3.04: Manufacturing
Major highlights of the month:

3.05: Delivery
3.06: Mobilization:
Major highlights of the month:

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 14 of 57

MONTHLY PROGRESS REPORT

Mobilization and demobilization of manpower and equipment in progress.

3.07: On plot Construction and commissioning.


Major highlights of the month:
Civil

Unit # 2 - Punch point attending in progress.

Unit # 2 Test pack submission completed.

Mechanical
Unit # 2

Unit # 2 Punch point attending works completed.

Unit # 2 Test pack submission completed.

ELECTRICAL
Unit -1

Punch point attending in progress.

Test pack submission completed except 1 package.

Unit -2

Punch point attending in progress.

Test pack submission in progress for 6 packages.

Instrumentation

Unit # 1 & 2 Punch point attending works 95% completed.

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 15 of 57

MONTHLY PROGRESS REPORT

Unit # 1 & 2 Test pack preparation and submission in progress for 10


packages.

Testing

Pre Commissioning and Commissioning


Unit-1 & 2

Unit # 1 & 2 - DCS punch point attending in progress

DCS SAT 84% completed.

Alarm rationalization 45% completed.

3.08: Off plot Construction and commissioning.


Major highlights of the month:
AP07 to Nimr Central OHL

Tower assembly 34/ 34 completed. Tower erection 34 /34 completed.

Stringing for 9 section completed out of 10 sections.

FOC stringing works in progress.

Spacer damper installation works completed.

3.09: Plant And Equipment Deployed At Site:


1.

Station wagon

2.

Pickup

3.

Potable water tanker 5000 Gallon

4.

Tipper

5.

Diesel Tanker

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 16 of 57

MONTHLY PROGRESS REPORT


6.

Shovel/Loader

7.

Grader

8.

Bucket truck

9.

62 Seat Big bus

10.

Crew cab

11.

7 Ton Truck

12.

Box Tailor

13

7 Ton Hiab

14

Brackish water tanker

15

Excavator

16

1 T Roller

17

JCB

18

10 T Roller

19

Concrete Mixture machine

20

Power generator portable

21

Plate compactor

22

Jumping compactor

23

Welding machine

24

Air compressor

25

24 Seater Bus

26

Crane 140 T

27

Crane 50/25 T

28

Generator 225 KV

29

Ambulance

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 17 of 57

MONTHLY PROGRESS REPORT


30

Folk lift

31

Transit Mixer

32

Cement Bulker

33

Batching plant

34

Waste Disposal Truck

35

60 Seated Big Bus

36

Bobcat

37

Vibrator

38

Generator 350 KVA

39

Hydra

40

Truck Gas

3.10: Manpower Deployment:


Project Office at Muscat
1.

Project Manager

2.

Interface Manager

3.

Planning Manager

4.

Procurement Manager

5.

Design Manager

6.

Design Electrical Engineer

7.

Design Civil Engineer

8.

Project Coordinator

9.

Cost Accountant

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 18 of 57

MONTHLY PROGRESS REPORT


10.

Draughts man

11

Secretary

12

Drivers (Omani)

MMC (Engg. Consultant) Office at Muscat


1.

Project Manager

2.

Civil Discipline

3.

Electrical Discipline

4.

Mechanical Discipline

5.

Process Discipline

6.

C & I Discipline

7.

Piping Discipline

Manpower Deployed at Site


1.

Staff ( Expat)

30

2.

Staff (Omani)

10

3.

JE (Expat)

92

4.

JE (Omani)

59

Sub contract

35

3.11: Quality Assurance:


Major Highlights of the Month:

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 19 of 57

MONTHLY PROGRESS REPORT

Unit # 2 - Tests pack preparation and submission for Electrical and


instrumentation in progress.

Mark up drawings preparation and submission works in progress.

3.12, Plan for Next Month:


Health, Safety and Environment.

Inspection of plant and equipments.

Conducting monthly HSE Meeting.

Gate meeting on every Saturday

Tool box talk for driver and work force

Drivers forum.

Mobilization:

Manpower and equipment mobilization and demobilization.

On Plot Construction / Commissioning:


Civil

Punch point attending works to complete.

Mechanical

Punch point close out.

Electrical

UEB # 1 & 2

De energizing of temporary transformer. Termination of cables for SUAT.

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 20 of 57

MONTHLY PROGRESS REPORT

Punch point attending

Commissioning

Unit # 1 Reliability run to start

Unit # 2 DLN tuning.

Unit # 1 & 2 Marks V1 e and DCS communication establishment through


Matrikon.

Instrumentation

Punch point close out.

Off Plot Construction:


AP07 to NIMR CENTRAL(TWIN ELM)

Shut down jobs at Tower location 2 & 3 and 34 & 35 to complete.

OPGW stringing works to complete.

Aviation light and sphere installation works to complete.

QUALITY ASSURANCE

Unit # 1 Balance test pack submission for CO2, EDG and CEMS.

Unit # 2 Test pack submission for Electrical and instrumentation


packages.

Unit # 1 & 2 As built drawings submission and approval.

CONTRACT FINANCIALS:

Milestone 1 payment invoice submitted on 26.08.09 payment received on


05.10.09.

Milestone 2a payment invoice submitted on 26.08.09 payment received on


05.10.09.

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 21 of 57

MONTHLY PROGRESS REPORT

Milestone 02B payment invoice submitted on 18.11.09, payment received


on 26.12.09.

Milestone 03 invoice submitted on 05.03.10, payment received on


09.04.10.

Milestone 02D payment invoice submitted on 10.04.10, payment received


on 28.05.2010.

Milestone 02C payment invoice submitted on 15.05.10, Payment received


on 14.06.10.

Milestone 05A payment invoice submitted on 24.04.10, payment received


on 28.05.10.

Mile stone 06A payment invoice submitted on 16.07.2010, payment


received on 06th September 2010.

Mile stone 04 A documents submitted and approved, Invoice submitted on


19th August 2010, payment received on 30th September 2010.

Mile stone 05 B documents submitted for approval, payment received on


26th December 2010.

Mile stone MS 04B completion certificate received. Payment received on


30th April 2011.

Mile stone MS 06 C completion certificate received. Payment received on


30th April 2011.

Mile stone MS 06 D completion certificate received. Payment received on


27th August 2011.

Mile stone MS 06 E completion certificate received. Payment received on


27th August 2011.

Mile stone MS 06 B completion certificate received. Payment received on


13th September 2011.

Mile stone MS 07 B completion certificate received. Payment received on


23rd October 2011.

Mile stone MS 05 C completion certificate received. Payment due on 12 th


December 2011.

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 22 of 57

MONTHLY PROGRESS REPORT

Mile Stone 07 A and 08 completion certificate received 50%. Payment


received on 9th January 2012.

Mile Stone 07 A and 08 completion certificate for balance 50% received.


Invoice submitted for payment.

Mile stone 09 completion certificate for 50% received. Invoice submitted for
payment.

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 23 of 57

MONTHLY PROGRESS REPORT

SECTION 4

APPENDICES

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 24 of 57

MONTHLY PROGRESS REPORT

APPENDICES-I

PROJECT MILESTONE DATES

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 25 of 57

MONTHLY PROGRESS REPORT


Project Milestone Schedule / Dates
Milesto
ne

MS-1

MS-2a

MS-2b

MS-2c

MS-2d

MS-3

MS-4a

MS-4b

Description

Weight
-age

Amount
in
Million
R.O

6%

Mobilization
PO for 3 critical
items (
Generator
transformer,GCB
,6.6KV
switchgear
PO issue for
wooden poles
and steel towers
of OHL
Upon completion
of issue of PO
for remaining
engineered item
purchase order
for electrical ,C &
Upon the
completion of
issue of PO for
remaining
engineered item
purchase orders
for mechanical
Site
Establishment
Upon
Completion of
Engineering
activities for
Design review,
IPF/HAZOP,SAF
OP
Upon
Completion of
Remaining
Engineering
activities

Doc. No: AML-394-AA-6944-0032-000

Sch.
Comple
tion

Act
Completi
on date

Payment
Receive
d

1.377

15-Aug09

15-Aug09

05-Oct09

6%

1.377

18-Aug09

18-Aug09

4%

0.918

17-Nov09

17-Nov09

26-Dec09

4%

0.918

15-Feb10

02-May10

14-Jun10

5%

1.147

13-Jan10

25-Mar10

28-May10

5%

1.147

11-Dec09

02-Mar10

09-Apr10

2%

0.459

31-Mar10

19-Aug10

30
Sep-10

4%

0.918

Rev. No : 01

29-Jul10

16-Mar11

Date: 25.04.12

Remarks

05-Oct09

30-Apr11

Page 26 of 57

MONTHLY PROGRESS REPORT


Milesto
ne

Ms-5a

Ms-5b

Ms-5c

Ms-6a

MS-6b

Description

Upon
Completion of
following Civil
work Amal power
station site
leveling &
grading
Upon
Completion of
following Civil
work UEB, GTP,
GTG and Off
base foundation.
Upon
Completion of
following Civil
work balance
foundation,
fencing on plot
and off plot,
Road works.
Upon receipt at
Site of following
Equipment
(including
documentation)
materials for
OHL (wooden
poles, steel
towers, FOC)
Upon receipt at
Site of following
Equipment
(including
documentation) (
Generator
transformers,15/
6.6KV
transformer,
Control &
automation
cable, bus duct )

Weight
-age

Amount
in
Million
R.O

Sch.
Act
complet Completi
ion
on date

Payment
Receive
d

2%

0.459

24-Feb10

15-Apr10

28-May10

10%

2.295

27-Sep10

27-Sep10

3%

0.688

11-Mar11

10-Nov11

4%

0.918

19-Jun10

16-Jul-10

16-Nov10

25-Jun11

10%

Doc. No: AML-394-AA-6944-0032-000

2.295

Rev. No : 01

Date: 25.04.12

Remarks

26-Dec10

09-Jan12

6-Sep-10

13-Sep11

Page 27 of 57

MONTHLY PROGRESS REPORT


Milesto
ne

Ms-6c

Ms-6d

Ms-6e

Ms-7a

Ms-7b

Description

Weight
-age

Amount
in
Million
R.O

4%

0.918

3-Oct-10

3%

0.688

22-Jul10

4%

0.918

03-Sep10

2%

0.459

03-Nov10

2%

0.459

23-Oct10

Upon receipt at
Site of following
Equipment
(including
documentation)(
GCB,6.6KV
switchgear,415V
switchgear,6.6K
V cables &
termination)

Upon receipt at
Site of following
Equipment
(including
documentation)(
vent system
,drain system)

Upon receipt at
Site of following
Equipment
(including
documentation)(
DC and AC UPS,
EDG, Instrument
air compressor,
DCS)
Upon completion
of 132kv
switchyard works
at Nimr West
132kv Substation
including
Upon completion
of 132kv OHLS

Doc. No: AML-394-AA-6944-0032-000

Sch.
Act
complet Completi
ion
on date

Rev. No : 01

20-Mar11

25-Jun11

23-Jun11

15-Jul 11

Date: 25.04.12

Payment
Receive
d

Remarks

30-Apr11

27-Aug11

27-Aug11

23-Oct11

Page 28 of 57

MONTHLY PROGRESS REPORT


Milesto
ne

Ms-8

Ms-9

Ms-10

Description

Weight
-age

Amount
in
Million
R.O

5%

1.147

16-Jan11

9%

2.065

05-Apr11

Upon completion
of precommissioning
of GTG package
including all
auxiliaries (precommissioning
completed, ready
for introduction
of hydrocarbons)
Upon Substantial
Completion of
the Work for
GTG Package
Upon
Completion of
the Work
(Demobilization)

Doc. No: AML-394-AA-6944-0032-000

6%

Sch.
Act
complet Completi
ion
on date

1.377

Rev. No : 01

Payment
Receive
d

Remarks

30-Jan12

04-Jul11

Date: 25.04.12

Page 29 of 57

MONTHLY PROGRESS REPORT

APPENDICES II

INTERGRATED OVERALL PROJECT SCHEDULE

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 30 of 57

MONTHLY PROGRESS REPORT

APPENDICES-III

DRAWING CONTROL REGISTER

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 31 of 57

MONTHLY PROGRESS REPORT

APPENDICES-IV

MATERIAL TRACKING REGISTER

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 32 of 57

MONTHLY PROGRESS REPORT

APPENDICES-V

CRITICAL PROJECT MATERIAL LIST

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 33 of 57

MONTHLY PROGRESS REPORT

APPENDICES-VI

HEALTH & SAFETY STATISTICS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 34 of 57

MONTHLY PROGRESS REPORT

APPENDICES-VII

HSE AUDIT/INSPECTION SCHEDULE

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 35 of 57

MONTHLY PROGRESS REPORT


#

Subject

Auditor

Schedule
Month

Journey
management

HSE Advisor + Site


Manager

Road
safety

November
09

Lifting equipment Site HSE Advisor +


and lifting gears
Project Manager

November
09

November
09

Welding and gas Site HSE Advisor +


cutting
Corp. HSE Manager

December
09

April 2010

Catering

Site HSE Advisor

February
2010

March
2010

Welding

Site HSE Manager

March
2010

April 2010

Transportation of Site HSE Manager +


compressed gas Project Manager
cylinder

May 2010

May 2010

Site HSE Manager +


Construction
Manager

June 2010

Nov 2010

Radiography

Scaffolding

Site HSE Manager

July 2010

July 2010

10

Waste Disposal

Site HSE Manager

Aug 2010

Oct 2010

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Remarks

October 09

October 09

transport HSE
Advisor
+
Manager
HSE+
Construction
Manager

August 09

Actual
Month

Date: 25.04.12

Page 36 of 57

MONTHLY PROGRESS REPORT

APPENDICES-VIII

HSE TRAINING MATRIX

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 37 of 57

MONTHLY PROGRESS REPORT

APPENDICES-IX

QUALITY INTERNAL AND EXTERNAL AUDIT


SCHEDULE

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 38 of 57

MONTHLY PROGRESS REPORT

APPENDICES-X

SUMMARY OF PROGRESS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 39 of 57

MONTHLY PROGRESS REPORT


MONTHLY

CUMULATIVE
PLANNED

CUMULATIVE
ACTUAL

ENGINEERING

100.00%

100%

PROCUREMENT

100.00%

100%

DESCRIPTION

PLANNED

MONTHLY
ACTUAL

CONSTRUCTION

0.24%

0.12%

100%

99.58%

OVERALL

0.10%

0.05%

100%

99.85%

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 40 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XI

S-CURVE FOR ENGINEERING PROGRESS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 41 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XII

S-CURVE FOR PROCUREMENT PROGRESS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 42 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XIII

S-CURVE FOR CONSTRUCTION PROGRESS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 43 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XIV

S-CURVE FOR OVERALL PROGRESS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 44 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XV

S-CURVE FOR VOWD PROGRESS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 45 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XVI

MANPOWER & EQUIPMENT HISTOGRAM

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 46 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XVII

SUBCONTRACT DETAILS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 47 of 57

MONTHLY PROGRESS REPORT


Sl no

Description of subcontract

Subcontractor

Design consultant

Mott Macdonald & co LLC

Topographical survey

AZD land survey LLC

Soil investigation

Fugro middle east & Partners LLC

Lab Technician for soil testing

Fugro middle east & Partners LLC

Grading and backfilling

Sayouh

Mahwees

Trading

and

contracting company LCC


6

Catering

Socat universal sodexho

Pole hole drilling

Ray Oman LLC

Block works & slope protection, Cable Al Badea National trading & Cont.
trench works

Est

Block works

Durat Al Ghubra trading

10

Pole Hole drilling

Powertech Engineering LLC

11

Rock Anchoring and Grouting for tower IBN Salim Al Hadi trading
foundation

12

NDT

Hi Tech Inspections services LLC

13

Back filling works & Cable trench works

Harweel International LLC

14

Wadi protection works

Al Badea National trading & Cont.


Est

15

Reaming works

Singh Tool industries India

16

On plot Telecommunication

M/s Bhawan projects and telecom

17

Off Plot Telecommunication

ORB communications network LLC

18

Excavation and backfilling of tower United International LLC


foundation

19

Tower Foundation concreting

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Global Design trading LLC

Date: 25.04.12

Page 48 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XVIII

VARIATION REGISTER

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 49 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XIX

OMANISATION REQUIREMENTS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 50 of 57

MONTHLY PROGRESS REPORT

OPAL CVC certificate submitted to PDO.

All drivers shall be Omani nationals.

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 51 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XX

SPIR PROGRESS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 52 of 57

MONTHLY PROGRESS REPORT


SPIR FORMS ATTACHED FOR FOLLOWING MATERIALS

125 V DC UPS

I P Bus Duct

142 MVA Generator Transformer

14 MVA M V UAT

1.6 MV LV Transformer

2.25 MV LV Transformer

240 V AC UPS

Generator circuit breaker

MAC system

HVAC system

Instrument air compressor

415 V GTP UAS

415 V GTP UAS Sub DB

6.6 KV MVUAS

415 V LVMCC

Emergency Diesel Generator

GTP skids

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 53 of 57

MONTHLY PROGRESS REPORT

APPENDICES-XXI

PROGRESS PHOTOGRAPHS

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 54 of 57

MONTHLY PROGRESS REPORT

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 55 of 57

MONTHLY PROGRESS REPORT

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 56 of 57

MONTHLY PROGRESS REPORT

Doc. No: AML-394-AA-6944-0032-000

Rev. No : 01

Date: 25.04.12

Page 57 of 57