Académique Documents
Professionnel Documents
Culture Documents
AML-391-AA-6944-0032000
01
25.04.12
1 to 57
For Approval
A.R.D
K.G.B.
Document No
Rev
No
Date
No. of
`Pages
Description
Prepared
By
Reviewed
by
Approved
by PDO
Section 1
Contract Particulars
1.01
1.02
Section 2
7
8
2.01
2.02
2.03
2.04
Areas of Concern
Section 3
11
12
12
12
Detailed Report
3.01
3.02
3.03
Procurement
3.04
Manufacturing
3.05
Delivery
3.06
Mobilization
3.07
3.08
3.09
Equipment Deployment
14
14
14
14
14
14
Rev. No : 01
15
17
17
Date: 25.04.12
Page 3 of 57
Manpower Deployment
3.11
Quality Assurance
3.12
3.13
Contract Financials
19
20
Rev. No : 01
21
23
Date: 25.04.12
Page 4 of 57
Appendices
26
II
31
III
32
IV
33
34
VI
35
VII
36
VIII
38
IX
39
Summary of progress
40
XI
42
XII
43
XIII
44
XIV
45
XV
46
XVI
47
XVII
Subcontract Details
48
XVIII
Variations Register
50
XIX
Omanisation Requirement
51
XX
SPIR Progress
53
XXI
Progress Photographs
55
Rev. No : 01
Date: 25.04.12
Page 5 of 57
SECTION 1
CONTRACT PARTICULARS
Rev. No : 01
Date: 25.04.12
Page 6 of 57
Company / Employer
: Petroleum
LLC
Company Representative
Contractor
Contract Value
Commencement Date
Contract Duration
: 730 Days
Substantial Completion
Completion Date
Engineering Sub-Contractor
: 4500439405
Rev. No : 01
Development
Date: 25.04.12
Oman
Page 7 of 57
Provision will be made for the future addition of Once through Heat
Recovery Generators (OTHRSs) on the back end of the GTG.
Amal Power Station with Frame 9E GTGs will have an ISO rated installed
capacity of 252MW. At a site ambient temperature of 48 deg C,
corresponding to maximum summer temperatures, this will drop to
197.4MW.
Each GTG unit will be unitised such that any equipment failures
associated with one GTG unit will not cause a trip of an adjacent GTG
unit.
The fuel gas for Amal Power Plant will be supplied from 18 Hubara to
Amal Pipeline and the tie-in point for fuel gas will be provided on 18
bypass line near Amal pie receiver A-2075.
The Amal Power Station is designed for unmanned operation and under
normal operation will be remotely controlled by SCADA and monitored
Rev. No : 01
Date: 25.04.12
Page 8 of 57
Gas turbines shall be free issued by PDO. Design, supply of BOP is part
of AHEC scope.
HVAC System.
Rev. No : 01
Date: 25.04.12
Page 9 of 57
SECTION 2
Rev. No : 01
Date: 25.04.12
Page 10 of 57
2.02
Overall project progress for the month has reported 0.05% against the
planned progress 0.10%.
Cumulative overall progress for the month has reported 99.85% against
the planned progress 100%.
2.03
2.04
AREAS OF CONCERN
Receipt of inputs from PDO/BHEL
Rev. No : 01
Date: 25.04.12
Page 11 of 57
Rev. No : 01
Date: 25.04.12
Page 12 of 57
SECTION 3
DETAILED REPORTS
Rev. No : 01
Date: 25.04.12
Page 13 of 57
Conducting daily tool box for driver and work force before starting of
work.
3.03: Procurement
Major highlights of the month:
3.04: Manufacturing
Major highlights of the month:
3.05: Delivery
3.06: Mobilization:
Major highlights of the month:
Rev. No : 01
Date: 25.04.12
Page 14 of 57
Mechanical
Unit # 2
ELECTRICAL
Unit -1
Unit -2
Instrumentation
Rev. No : 01
Date: 25.04.12
Page 15 of 57
Testing
Station wagon
2.
Pickup
3.
4.
Tipper
5.
Diesel Tanker
Rev. No : 01
Date: 25.04.12
Page 16 of 57
Shovel/Loader
7.
Grader
8.
Bucket truck
9.
10.
Crew cab
11.
7 Ton Truck
12.
Box Tailor
13
7 Ton Hiab
14
15
Excavator
16
1 T Roller
17
JCB
18
10 T Roller
19
20
21
Plate compactor
22
Jumping compactor
23
Welding machine
24
Air compressor
25
24 Seater Bus
26
Crane 140 T
27
Crane 50/25 T
28
Generator 225 KV
29
Ambulance
Rev. No : 01
Date: 25.04.12
Page 17 of 57
Folk lift
31
Transit Mixer
32
Cement Bulker
33
Batching plant
34
35
36
Bobcat
37
Vibrator
38
39
Hydra
40
Truck Gas
Project Manager
2.
Interface Manager
3.
Planning Manager
4.
Procurement Manager
5.
Design Manager
6.
7.
8.
Project Coordinator
9.
Cost Accountant
Rev. No : 01
Date: 25.04.12
Page 18 of 57
Draughts man
11
Secretary
12
Drivers (Omani)
Project Manager
2.
Civil Discipline
3.
Electrical Discipline
4.
Mechanical Discipline
5.
Process Discipline
6.
C & I Discipline
7.
Piping Discipline
Staff ( Expat)
30
2.
Staff (Omani)
10
3.
JE (Expat)
92
4.
JE (Omani)
59
Sub contract
35
Rev. No : 01
Date: 25.04.12
Page 19 of 57
Drivers forum.
Mobilization:
Mechanical
Electrical
UEB # 1 & 2
Rev. No : 01
Date: 25.04.12
Page 20 of 57
Commissioning
Instrumentation
QUALITY ASSURANCE
Unit # 1 Balance test pack submission for CO2, EDG and CEMS.
CONTRACT FINANCIALS:
Rev. No : 01
Date: 25.04.12
Page 21 of 57
Rev. No : 01
Date: 25.04.12
Page 22 of 57
Mile stone 09 completion certificate for 50% received. Invoice submitted for
payment.
Rev. No : 01
Date: 25.04.12
Page 23 of 57
SECTION 4
APPENDICES
Rev. No : 01
Date: 25.04.12
Page 24 of 57
APPENDICES-I
Rev. No : 01
Date: 25.04.12
Page 25 of 57
MS-1
MS-2a
MS-2b
MS-2c
MS-2d
MS-3
MS-4a
MS-4b
Description
Weight
-age
Amount
in
Million
R.O
6%
Mobilization
PO for 3 critical
items (
Generator
transformer,GCB
,6.6KV
switchgear
PO issue for
wooden poles
and steel towers
of OHL
Upon completion
of issue of PO
for remaining
engineered item
purchase order
for electrical ,C &
Upon the
completion of
issue of PO for
remaining
engineered item
purchase orders
for mechanical
Site
Establishment
Upon
Completion of
Engineering
activities for
Design review,
IPF/HAZOP,SAF
OP
Upon
Completion of
Remaining
Engineering
activities
Sch.
Comple
tion
Act
Completi
on date
Payment
Receive
d
1.377
15-Aug09
15-Aug09
05-Oct09
6%
1.377
18-Aug09
18-Aug09
4%
0.918
17-Nov09
17-Nov09
26-Dec09
4%
0.918
15-Feb10
02-May10
14-Jun10
5%
1.147
13-Jan10
25-Mar10
28-May10
5%
1.147
11-Dec09
02-Mar10
09-Apr10
2%
0.459
31-Mar10
19-Aug10
30
Sep-10
4%
0.918
Rev. No : 01
29-Jul10
16-Mar11
Date: 25.04.12
Remarks
05-Oct09
30-Apr11
Page 26 of 57
Ms-5a
Ms-5b
Ms-5c
Ms-6a
MS-6b
Description
Upon
Completion of
following Civil
work Amal power
station site
leveling &
grading
Upon
Completion of
following Civil
work UEB, GTP,
GTG and Off
base foundation.
Upon
Completion of
following Civil
work balance
foundation,
fencing on plot
and off plot,
Road works.
Upon receipt at
Site of following
Equipment
(including
documentation)
materials for
OHL (wooden
poles, steel
towers, FOC)
Upon receipt at
Site of following
Equipment
(including
documentation) (
Generator
transformers,15/
6.6KV
transformer,
Control &
automation
cable, bus duct )
Weight
-age
Amount
in
Million
R.O
Sch.
Act
complet Completi
ion
on date
Payment
Receive
d
2%
0.459
24-Feb10
15-Apr10
28-May10
10%
2.295
27-Sep10
27-Sep10
3%
0.688
11-Mar11
10-Nov11
4%
0.918
19-Jun10
16-Jul-10
16-Nov10
25-Jun11
10%
2.295
Rev. No : 01
Date: 25.04.12
Remarks
26-Dec10
09-Jan12
6-Sep-10
13-Sep11
Page 27 of 57
Ms-6c
Ms-6d
Ms-6e
Ms-7a
Ms-7b
Description
Weight
-age
Amount
in
Million
R.O
4%
0.918
3-Oct-10
3%
0.688
22-Jul10
4%
0.918
03-Sep10
2%
0.459
03-Nov10
2%
0.459
23-Oct10
Upon receipt at
Site of following
Equipment
(including
documentation)(
GCB,6.6KV
switchgear,415V
switchgear,6.6K
V cables &
termination)
Upon receipt at
Site of following
Equipment
(including
documentation)(
vent system
,drain system)
Upon receipt at
Site of following
Equipment
(including
documentation)(
DC and AC UPS,
EDG, Instrument
air compressor,
DCS)
Upon completion
of 132kv
switchyard works
at Nimr West
132kv Substation
including
Upon completion
of 132kv OHLS
Sch.
Act
complet Completi
ion
on date
Rev. No : 01
20-Mar11
25-Jun11
23-Jun11
15-Jul 11
Date: 25.04.12
Payment
Receive
d
Remarks
30-Apr11
27-Aug11
27-Aug11
23-Oct11
Page 28 of 57
Ms-8
Ms-9
Ms-10
Description
Weight
-age
Amount
in
Million
R.O
5%
1.147
16-Jan11
9%
2.065
05-Apr11
Upon completion
of precommissioning
of GTG package
including all
auxiliaries (precommissioning
completed, ready
for introduction
of hydrocarbons)
Upon Substantial
Completion of
the Work for
GTG Package
Upon
Completion of
the Work
(Demobilization)
6%
Sch.
Act
complet Completi
ion
on date
1.377
Rev. No : 01
Payment
Receive
d
Remarks
30-Jan12
04-Jul11
Date: 25.04.12
Page 29 of 57
APPENDICES II
Rev. No : 01
Date: 25.04.12
Page 30 of 57
APPENDICES-III
Rev. No : 01
Date: 25.04.12
Page 31 of 57
APPENDICES-IV
Rev. No : 01
Date: 25.04.12
Page 32 of 57
APPENDICES-V
Rev. No : 01
Date: 25.04.12
Page 33 of 57
APPENDICES-VI
Rev. No : 01
Date: 25.04.12
Page 34 of 57
APPENDICES-VII
Rev. No : 01
Date: 25.04.12
Page 35 of 57
Subject
Auditor
Schedule
Month
Journey
management
Road
safety
November
09
November
09
November
09
December
09
April 2010
Catering
February
2010
March
2010
Welding
March
2010
April 2010
May 2010
May 2010
June 2010
Nov 2010
Radiography
Scaffolding
July 2010
July 2010
10
Waste Disposal
Aug 2010
Oct 2010
Rev. No : 01
Remarks
October 09
October 09
transport HSE
Advisor
+
Manager
HSE+
Construction
Manager
August 09
Actual
Month
Date: 25.04.12
Page 36 of 57
APPENDICES-VIII
Rev. No : 01
Date: 25.04.12
Page 37 of 57
APPENDICES-IX
Rev. No : 01
Date: 25.04.12
Page 38 of 57
APPENDICES-X
SUMMARY OF PROGRESS
Rev. No : 01
Date: 25.04.12
Page 39 of 57
CUMULATIVE
PLANNED
CUMULATIVE
ACTUAL
ENGINEERING
100.00%
100%
PROCUREMENT
100.00%
100%
DESCRIPTION
PLANNED
MONTHLY
ACTUAL
CONSTRUCTION
0.24%
0.12%
100%
99.58%
OVERALL
0.10%
0.05%
100%
99.85%
Rev. No : 01
Date: 25.04.12
Page 40 of 57
APPENDICES-XI
Rev. No : 01
Date: 25.04.12
Page 41 of 57
APPENDICES-XII
Rev. No : 01
Date: 25.04.12
Page 42 of 57
APPENDICES-XIII
Rev. No : 01
Date: 25.04.12
Page 43 of 57
APPENDICES-XIV
Rev. No : 01
Date: 25.04.12
Page 44 of 57
APPENDICES-XV
Rev. No : 01
Date: 25.04.12
Page 45 of 57
APPENDICES-XVI
Rev. No : 01
Date: 25.04.12
Page 46 of 57
APPENDICES-XVII
SUBCONTRACT DETAILS
Rev. No : 01
Date: 25.04.12
Page 47 of 57
Description of subcontract
Subcontractor
Design consultant
Topographical survey
Soil investigation
Sayouh
Mahwees
Trading
and
Catering
Block works & slope protection, Cable Al Badea National trading & Cont.
trench works
Est
Block works
10
11
Rock Anchoring and Grouting for tower IBN Salim Al Hadi trading
foundation
12
NDT
13
14
15
Reaming works
16
On plot Telecommunication
17
18
19
Rev. No : 01
Date: 25.04.12
Page 48 of 57
APPENDICES-XVIII
VARIATION REGISTER
Rev. No : 01
Date: 25.04.12
Page 49 of 57
APPENDICES-XIX
OMANISATION REQUIREMENTS
Rev. No : 01
Date: 25.04.12
Page 50 of 57
Rev. No : 01
Date: 25.04.12
Page 51 of 57
APPENDICES-XX
SPIR PROGRESS
Rev. No : 01
Date: 25.04.12
Page 52 of 57
125 V DC UPS
I P Bus Duct
14 MVA M V UAT
1.6 MV LV Transformer
2.25 MV LV Transformer
240 V AC UPS
MAC system
HVAC system
6.6 KV MVUAS
415 V LVMCC
GTP skids
Rev. No : 01
Date: 25.04.12
Page 53 of 57
APPENDICES-XXI
PROGRESS PHOTOGRAPHS
Rev. No : 01
Date: 25.04.12
Page 54 of 57
Rev. No : 01
Date: 25.04.12
Page 55 of 57
Rev. No : 01
Date: 25.04.12
Page 56 of 57
Rev. No : 01
Date: 25.04.12
Page 57 of 57