Académique Documents
Professionnel Documents
Culture Documents
BY
1. DWI HANDOYO SAPUTRO
NIP: 780321178 I
2 . BAMBANG SUPRIHANTO
NIP: 7293592 K3
3. BOWO PRAMONO
NIP: 7291007 K3
LETTER OF LEGALIZATION
General Manager
PT. Indonesia Power UBP. Semarang
Page. 2 from 22
ABSTRACT
Keywords : Start-up, CCPP (Combined Cycle Power Plant), Open Cycle, Combine
Cycle, Diverter Damper, HRSG (Heat Recovery Steam Generator)
Start -up design of Tambak Lorok CCPP has a source heat loss. These
losses appear from gas turbine start-up process and diverter damper
opening process. Diverter damper is a steel made plate between gas
turbine stack and HRSG. Modification in start-up mode is a must to
extinguish the losses; we name it as a Direct Combine Cycle Start-Up
mode. This type of start-up is already implemented successfully in GTG
2.2, April 2008. With this modification, we save the heat equal with
13,290,084 liters of No. 2 Oil HSD for 6 gas turbines in a year.
Page. 3 from 22
FOREWORD
Alhamdulillahi Rabbil Alamiin, is the words only for the God who has giving us His
Bless to finish this innovation successfully. Also, we want to say thanks to our
team work in PT. Indonesia Power UBP. Semarang and UBHar Semarang,
especially for the operators and technician of PLTGU Tambak Lorok. Without
them, we cannot finish the job completely.
As a human being, we realize that this innovation is completely not perfect. For
that, your constructive word and advice is what we need. At the end, we hope
this paper can be useful for all of us. Amiin.
W assalam.
Page. 4 from 22
TABLE OF CONTENT
Letter of Legalization
Abstract
Foreword
Table of Content
Table of Figure
2
3
4
5
6
Chapter I PREFACE
1.1
Background
1.2
Problems Identification
1.3
Objective
1.4
Scope
1.5
Methodology
7
7
7
7
7
8
9
10
11
Chapter III
INNOVATION
3.1
Direct Combine Cycle Start-up Mode
3.2
Modification Needed
3.3
Start-up Mode Comparison
12
13
14
Chapter IV
BENEFIT
4.1
Financial Benefits
4.2
Non Financial Benefits
4.3
Risk Analysis
17
18
19
Chapter V
CONCLUSION AND SUGGESTION
5.1
Conclusion
5.2
Suggestion
20
20
REFERENCE LIST
BIODATA
21
22
Page. 5 from 22
Title
Gas Turbines open cycle operating mode
Gas Turbines combine cycle operating mode
Flowchart of Tambak Lorok CCPP design start-up
Dew Point Sulphur Graph.
Flowchart of Tambak Lorok Direct Combine Cycle start-up mode
Graph status of Direct combine cycle Mode start up
Graph status of Design combine cycle Mode start up
Graph of HRSG HP steam temperature in GTG 2.2 April 21th 2008
Page
8
9
9
11
12
14
14
16
Table
1
2
Title
Standard Operating Procedure of Direct Combine Cycle Start-up Mode
Matrix of diverter damper indicationposition signal
Comparisons of 2 different kind of start-up mode, Direct combine
cycle and design start-up mode
Energy Calculation base on design start-up mode (step by step
opening diverter damper)
Diverter damper failure calculation cost
Financial benefits Resume from Direct combine cycle start-up mode
Risk analysis for Direct combine cycle start-up mode with its
mitigation
Page
11
13
3
4
5
6
7
Page. 6 from 22
15
17
18
18
19
CHAPTER I
P R E FAC E
1.1
Background
Tambak Lorok CCPP (Combine Cycle Power Plant) is designed to be
operated in open cycle (combustion gas is release to ambient from gas
turbines stack) or combine cycle (combustion gas is release to HRSG-Heat
Recovery Steam Generator, to produce steam for steam turbine). These
two kinds of operation can be change over (from open to combine cycle) by
opening the diverter damper step by step, which is located between gas
turbine stack and HRSG. This start-up mode operation resulted in a certain
heat loss (when gas turbine operated in open cycle and when opening the
diverter damper).
Beside that, Tambak Lorok CCPP is a start stop operating plant. It happens
since 12 years ago and makes the diverter damper always operated open
close in high temperature and suffers from creep and thermal fatigue
phenomena. Those phenomena are a source of diverter damper failure, at
least once a year with 4 days shutdown time.
Page. 7 from 22
CHAPTER II
THEORITICAL BACKGROUND
2.1
Page. 8 from 22
START
START UP COMMAND
FROM TRANSMISSION
START UP GTG
START UP HRSG
START UP STG
(STEAM TURBINE GEN.)
END
Figure 3. Flowchart of Tambak Lorok CCPP design start-up.
Page. 9 from 22
This heat loss is a potential loss of power. To make it as real as turbines output,
we have to add another factor, machine efficiency (). So the real heat loss is :
W=P.
For combine cycle, the is 40%.
2.4 Sulphur Corrosion Effect On HRSG Tubes
Combustion gas from the gas turbine is a source of sulphur corrosion in HRSG
Tubes. Sulphur content on liquid fuel (No. 2 Oil) is oxidiz ing in combustion
process and change into SOx gas. This gas will condensate into H 2SO4 when the
surrounding temperature comes into its dew point. H2SO4 is corrosive to the steel
metal, especially the upper part of HRSG tubes (eco nomiser tubes). Below is the
reaction that happens in combustion process.
H20 + SO 3 H 2SO4
The sulphur dew po int is a function of sulphur content in the fuel. This relation
can be seen in figure 4 below.
Page. 10 from 22
Page. 11 from 22
CHAPTER III
IN N OVA T ION
3.1
Below is the flowchart of Tambak Lorok CCPP start-up mode that use to avoid
the heat loss, we call it as Direct Combine Cycle Start-up Mode.
START
START -UP COMMAND
FROM TRANSMISSION
OPEN DIVERTER DAMPER
100%
START UP HRSG
START UP GTG
START UP STG
END
Figure 5. Flowchart of Tambak Lorok Direct Combine Cycle start-up mode.
The operating procedure of Direct Com Direct Combine Cycle start-up mode has
been done at gas turbine 2.2 in April 16th 2008 and April 21th 2008. We can see
the detail as below.
Table 1. S tandard Operating Procedure of Direct Combine Cycle Start-up Mode.
No
Item
PIC
Local
2
3
S tart HRSG
Diverter damper switch indication in OFF position.
Oprtr Control R
Local
Page. 12 from 22
No
Item
PIC
Start GTG
Oprtr Control R
5
6
Oprtr Control R
Oprtr Control R
Oprtr Control R
Oprtr Control R
8
9
10
11
12
13
14
3.2
Oprtr Control R
Oprtr Control R
Oprtr Control R
Oprtr Control R
Oprtr Control R
Local
Modification Needed
From the flowchart above, below are the modifications needed for Direct
Combine Cycle Start-up mode.
Adding a switch of indication signal in MCC panel of HRSG (OPEN - CLOSE
OFF position) to make sure that diverter damper signal is on function, as
needed in existing sequence of gas turbine start and HRSG start.
Below is a matrix of diverter damper indication signal and its function.
CONDITION
SWITCH INDICATION
POSITION
REMARKS
START HRSG
CLOSE
START GTG
OFF
GTG ONLINE
OFF
OPEN
COMBINE
Page. 13 from 22
3.3
TTXM
IGV
Damper
Page. 14 from 22
No
Item
Star t
Purging
Gas Turbine Firing stage (gas
turbine speed raise)
Ga Turbine Fsnl (Full spee d
no load)
3
4
5
7
8
9
7*
12
22
15
74
84
138**
72
64
MW/minute
1.094
0.781
oC/m inute
6.258
5.66
Unit
Minute
from
Minute
M inute
from
M inute
from
M inute
from
M inute
from
Minute
Notes :
* Purging time needed in direct combine cycle mode is 4 minutes long than design start-up mode, as
machine design requirement (Mark V sequence control setting).
**This figure is not actually shown, load hold out in 40 MW for 50 m inutes .
From table 3 above, we can see that there is no significant figure between two
kinds of start-up mode. There are 8 minutes differences (point 6), in total time,
start from combustion gas come to HRSG until the HP Steam can rolling up,
These differences can be optimalize by adding the gas turbine ramp rate in direct
combine cycle mode. It happens because of the HP steam temperature raise
average are still under 5 11oC/menit.
Below is the curve of HP steam temperature raise in HRSG when Direct Combine
Cycle start-up mode, April 21st 2008.
Page. 15 from 22
Figure 8. Graph of HRSG HP steam temperature in GTG 2.2 April 21th 2008.
Page. 16 from 22
CHAPTER IV
B E NEFIT
4.1
Financial Benefit
Financial benefits that come from this innovation are:
1. Operational Benefit/Energy benefits from heat recovery
Below is a table of energy calculation from Direct combine cycle
comparing with a normally open diverter damper2.
Table 4. Energy Calculation base on design start-up mode (step by step opening diverter damper)
RPM
LOAD
IGV
FUEL
MW
DEG
KG/S
Amb
Amb
exh
Heat Loss
damper
Exh
Temp.
EXH
temp
FLOW
Exh. Gas
open
degC
kj/kg
DEGC
KG/S
kJ/kg
kW
D=(C-A) x B
6366.0873
50927.357
0
0
1
1.5
A
300
1000
0
0
34
34
1500
2000
2500
2750
TIME
Energy
Loss
minutes
kwh
F = D x E/60
106
0.2
0.3
32
32
305.37
305.37
65
289
194.21
194.35
338.15
567.41
34
32
305.37
449
194.49
737.14
83975.22
1.5
2,099
34
1.4
32
305.37
464
194.63
753.36
87191.398
1.5
2,180
34
1.7
32
305.37
396
194.77
680.23
73011.95
1.5
1,825
52
32
305.37
329
297.89
609.28
90530.269
1.5
2,263
323
319.54
602.98
95097.469
1.5
2,377
3000
56
2.3
32
305.37
3000
10
56
2.6
32
305.37
330
319.82
610.33
97532.435
1.5
2,438
3000
20
56
3.2
32
305.37
370
320.1
652.57
111136.93
3,705
3000
30
56
3.7
32
305.37
412
320.38
697.33
125576.27
4,186
3000
40
56
4.1
32
305.37
451
320.66
739.3
139144.44
20
4.5
8,349
3000
50
56
4.8
32
305.37
492
320.8
783.81
153482.08
30
9,740
3000
60
56
5.4
32
305.37
527
321.08
822.12
165916.29
40
9,209
3000
70
58
5.8
32
305.37
560
321.36
858.51
177757.2
50
7,674
3000
75
58
6.2
32
305.37
560
321.5
858.51
177834.64
60
4,424
3000
80
67
6.4
32
305.37
560
335.4
858.51
185523.29
70
10
8,888
3000
90
83.9
6.8
32
305.37
560
363.2
858.51
200900.59
80
3,557
3000
100
86
7.4
32
305.37
560
391
858.51
216277.9
90
12
3,557
77,851
40
31,140
1,900
Total Energy Loss from design start-up mode for each start-up in 1 gas turbine
59,166,517
From the table above, total energy loss in design start-up mode reach Rp.
59,166,517 for one start -up. If we assume that in one month, Tambak Lorok
CCPP has 22 times start-up (30 days minus 2 x RSH in a week), so the total
energy losses (as energy benefit) in a year are:
firing
1,273
Page. 17 from 22
Gas
turbin
online
Steam
Ok
Item
Unit
Open Cycle
Sfc
liter/kwh
2
3
Output
Days of failure
b
c
4
5
6
7
8
9
Production difference
Equal with liquid fuel HSD
Equal with fuel price
10
11
Combine Cycle
0.35
0.24
Kw
hari
100,000
4
150,000
4
d
e=c*d
f=e*b
jam
jam
Kwh
8
32
3,200,000
8
32
4,800,000
g
h=a*g
i=h*8640
Kwh
liter
Rp.
1,600,000
384,000
3,317,760,000
Rp.
200,000,000
K=i+j
Rp.
3,517,760,000
From the two aspects above we can conclude that Direct combine cycle startup mode can reduce the operation and maintenance cost as below.
Table 6. Financial benefits Resume from Direct combine cycle start-up mode.
No
4.2
Item
Unit
Value
Rp/year
15,619,960,394
Rp/year
3,517,760,000
Rp.
19,137,720,394
Rp.
114,826,322,366
Liter
Liter
2,215,014
13,290,084
Page. 18 from 22
Risk
Risk Level
High
High
Medium
MITIGATION
Tightening SOP of operation and maintenance
Tightening SOP of operation and maintenance
Tightening SOP of operation and maintenance (HP Steam
raise : 5 - 11oC/minutes)
Risk
Risk Level
MITIGATION
Low
Low
Low
Page. 19 from 22
CHAPTER V
CONCLUSION AND SUGGESTION
5.1
Conclusion
Gas turbine MS9001 Tambak Lorok CCPP is possible to do the therm al
improvement by using Direct combine cycle start -up mode.
Direct combine cycle start-up mode will avoid diverter damper failure.
Direct combine cycle start-up mode can minimizing energy loss Rp.
59,166,517 for each start-up in 1 gas turbine, and Rp. 3,241,280,000
for every diverter damper failure. Totally, equal with Rp.
114,826,322,366 in a year for 6 gas turbine (or 13,290,084 liters HSD
liquid fuel).
From the last experience in Direct combine cycle start-up mode (April
16 th, April 21st and May 4 th 2008 ) we found no evidence of negative
side for the machine itself.
Shutdown process with Direct combine cycle mode will do the same
like start-up does but in a small scale aspect.
5.2
Suggestion
We need to socialize this to another unit, so as a corporate we will get
a big number of benefits.
Page. 20 from 22
REFERENCE LIST
1 . Operational data of GTG 2.2 Tambak Lorok CCPP start-up, April 21 st 2008.
2 . Operational data of GTG 2.3 Tambak Lorok CCPP start-up, April 28 th 2008.
3 . Manual Book GTG and HRSG Tambak Lorok CCPP.
4 . ISO 9001 Document: SOP Start-Up GTG, HRSG and STG Tambak Lorok CCPP.
5 . Yunus A. Cengel, Robert H. Turner, Fundamentals Of Thermal-fluid
Sciences, 2 nd Ed, Mc Graw Hill, NY, 2005.
Page. 21 from 22
BIODATA
NAME
NIPEG
: 780321178 I
TITLE
: ENJINER MESIN
TTL
: JAKARTA, 29-06-1978
NAME
: BAMBANG SUPRIHANTO
NIPEG
: 7293592K3
TITLE
: ENJINER LISTRIK
TTL
NAME
: BOWO PRAMONO
NIPEG
: 7291007k3
TITLE
: SP HMK GU1
TTL
Page. 22 from 22
Muara Tawar
Combined Cycle Power Plant
Prepared for:
HAPUA Working Group No. 1 Generation : Knowledge Sharing Workshop on the
Best Practices in Open Cycle Gas Turbine, Combined Cycle, Non Coal Fired Thermal
& Internal Combustion Diesel Power Plant
Kuala Lumpur, Malaysia. 15th 16th July 2008
Author:
PURWONO JATI AGUNG, ST, MT
Outage Management Supervisor / Engineering Specialist
PT Pembangkitan Jawa Bali
Muara Tawar Combined Cycle Power Plant
Bekasi West Java - Indonesia
purwono@ptpjb.com
jati.agung@yahoo.com
Muara Tawar
Combined Cycle Power Plant
ACRONYM
EAMS
EAF
EFOR
BSC
Balance Scorecard
ERP
FDT
FMEA
FMECA
GCG
GGG
ISO 9001:2000
ISO 14001:2004
KPA
KPI
LCC
MPI
OEE
OH
OHSAS 18001:1999
& Permenaker No.
Overhaul
Safety & Health Management System Standard have implemented in
the PT PJB Muara Tawar Combined Cycle Power Plant
Per.05/Men/1996
PT PJB
RCFA
RO
Recommended Order
SERP
WO
Work Order
WPC
Muara Tawar
Combined Cycle Power Plant
ABSTRACT
PT Pembangkitan Jawa Bali (PT PJB) is one of the subsidiaries of PT PLN (Persero) with
installed capacity are 6500 MW. Muara Tawar Combined Cycle Power Plant is one of the
generation unit of PT PJB, located on Bekasi, West Java and supply of electricity to the
Jakarta as a strategic region. Muara Tawar Combined Cycle Power Plant consists of 1 block
combined cycle (3 gas turbines & 1 steam turbine) and 1 block opened cycle (2 gas turbines)
with HSD (High Speed Diesel) as primary energy and 950 MW installed capacity. For the
continuous improvement of performance, PT PJB Muara Tawar Combined Cycle Power Plant
implemented the Tata Kelola Unit Pembangkitan Terintegrasi (Integrated Best Power Plant
Governance) based on :
1) Generation Plan
2) Asset Management, based on : Reliability Improvement Program, Work Planning and
Control, Supply Chain Management, Efficiency Management, Outage Management, EAMS
(Enterprise Asset Management System) & Energy Management
3) Balanced Scorecard
4) Risk Management
5) Quality Management System (QMS), Environmental Management System (EMS) &
Occupational Health & Safety Management System.
6) Work Culture.
The integrated rule standard of those Best Power Plant Governance are :
1) Asset management (as reference is Reliability Improvement Program) full integrated with
risk management, especially for physical assets.
2) Those integration based on Integrated Management System which have been
implemented at PT PJB Mara Tawar Combined Cycle Power Plant before, pursuant to
Quality Management System (QMS) ISO 9001:2000; Environmental Management System
(EMS) ISO 14001:2004; Occupational Health & Safety
Muara Tawar
Combined Cycle Power Plant
4) All of the reviewed documentation system is integrated in the EAMS (Enterprise Asset
Management System) for becoming standard job. The standard job is a data base for
create the work order (WO), where the work order is a RISK MITIGATION for related
system, subsystem or equipment. Also, this work order integrated with Risk Web Portal of
Risk PT PJB, so that the progress of risk mitigation can be controlled by online.
All of those process must be measure to ascertain successfully stage compared with the
condition before implementation and according to Key Performance Indicator.
For increase of maturity of the implementation, PT PJB Muara Tawar Combined Cycle Power
Plant specifying continuous improvement program based on process business maturity level
assessment to 10 Key Performance Areas (10 KPAs) for several years (long term planning)
with specific KPI (Key Performance Indicator).
Keywords : Integration, Best Power Plant Governance, Asset Management, Risk Management,
Integrated
Management
System,
Reviewed
Documentation
System,
Implementation,
Muara Tawar
Combined Cycle Power Plant
CHAPTER I
PRELIMINARY
1.1. Background
1.1.1.
10.0000
MW
Indonesian
electricity
project.
For
operation
&
system
based
on
Tata
Kelola
Unit
Pembangkitan
1.1.2.
Muara Tawar
Combined Cycle Power Plant
PT PJB assumes that the Integrated Best Power Plant Governance is very
important, because shareholder and investor consider as most important a good
governance than a good financial performance. A good governance will be
brings in sustainable profit and growth.
Those framework must be implemented by every power plant unit in PT
PJB.
So, to reach a Good Corporate Governance (GCG) with the best power plant
performance, the deployment and implementation of Good Corporate
Governance (GGG) have been done uniqueness & special characteristics,
because the alignment to the process conducted by totally integrated, have
never implemented in all of power plant in Indonesia:
1) PT PJB Muara Tawar CCPP have implemented an Integrated Management
System based on Quality Management System (QMS) ISO 9001:2000;
Environment Management System (EMS) ISO 14001:2004; Occupational
Health & Safety Management System (OHSMS) OHSAS 18001:1999 &
Muara Tawar
Combined Cycle Power Plant
1.1.3.
1.2. Target & Goal of Integration of Integrated Best Power Plant Governance.
1.2.1. Target
To reach of Best Practices and Good Corporate Governance (GCG) with the best
performance in the power plant management.
1.2.2. Goal
To create of the best & structured documentation system of Integrated
Management System, consists of Company Policy (document level 1),
Procedure (document level 2), Work Instruction (document level 3) and
Form (document level 4), so will be achieved:
1) Live documented to shows the day to day implementation of business
process.
2) Excellence
business
process
gradually
and
the
best
performance
Muara Tawar
Combined Cycle Power Plant
System
are
Reliability
Improvement,
Supply
Chain
Permenaker No.
Per.05/Men/1996 which
Muara Tawar
Combined Cycle Power Plant
Muara Tawar
Combined Cycle Power Plant
10
Muara Tawar
Combined Cycle Power Plant
CHAPTER II
THE THORY BASIS
2.1. Work Culture
Work culture is a work behavior change program to support sustainability the
management of improvement program as a change management to integrate the program
of Integrated Best Power Plant Governance become a habit behavior. Work culture
must be implemented in the PJB values are integrity, superiority, cooperation, servicing
and environment aware with the implementation area are:
1) Discipline & commitment in the implementation of the determining program.
2) Implemented of daily meeting, weekly meeting and monthly meeting effectively
appropriate the shared good practices.
3) The executor give a feedback for planning improvement.
4) Walk to floor for a top management (manager & deputy manager).
5) Briefing before work execution and debriefing after work execution.
6) Knowledge sharing, safety induction and continuous improvement.
One of the implementation of work culture in the PT PJB Muara Tawar CCPP is
conducted the workshop as a sharing knowledge & capture knowledge in the
development & implementation of the integration concept of Asset Management Risk
Management Integrated Management System, so the recommendation for the
improvement of power plant management have accommodated the experience &
competence from all of personnel in PT PJB Muara Tawar CCPP.
11
Muara Tawar
Combined Cycle Power Plant
compliance of clauses EMS ISO 14001:2004 will be resulted the company target about
corporate social responsibility / CSR and with compliance of clauses OHSAS 18001:1999
will be resulted the company target to guarantee safety work environment. Integrated
Management System which implemented in PT PJB Muara Tawar CCPP as a media to
integrates technical program of the Integrated Best Power Plant Governance become a
structured document, effective document and simple document so will be facilitate the
understanding of implementation of Integrated Best Power Plant Governance.
2.3. Reliability Improvement
Goal of Reliability improvement program which implemented in PT PJB Muara Tawar
CCPP is to change unplanned maintenance become planned maintenance by:
1) Effectiveness of quality control
2) Evaluation of maintenance task (paper work)
3) Elimination of performance gap
4) Ascertain that the system have governance well by system owner.
5) Prioritization of the system
6) Modification equipment / system
12
Muara Tawar
Combined Cycle Power Plant
13
Muara Tawar
Combined Cycle Power Plant
14
Muara Tawar
Combined Cycle Power Plant
CHAPTER III
DISCUSSION
3.1.
3.2.
The Framework of PT PJB Integrated Best Power Plant Governance (Tata Kelola
Unit Pembangkitan Terintegrasi)
The framework of PT PJB Integrated Best Power Plant Governance (Tata Kelola Unit
Pembangkitan Terintegrasi) showed on Attachment 4. Basically, PT PJB Integrated
Best Power Plant Governance (Tata Kelola Unit Pembangkitan) is the implementation
of strategy map (Attachment 1) and grand corporate strategy PT PJB (Attachment
3) in the every management level in power plant unit, where the best integrated
program is very important, because :
1. From the perspective customer, as a one effort to increase of corporate
competitiveness pass through the performance increasing of power plant unit
15
Muara Tawar
Combined Cycle Power Plant
continuously. The Integrated Best Power Plant Governance (Tata Kelola Unit
Pembangkitan Terintegrasi) constitute of superiority competitiveness of PT PJB
that must be understanding by all of employee of PT PJB, together implemented,
evaluated and updated continuously until become a work culture of PT PJB.
2. From the internal perspective and learning & growth perspective, the best
integrated program be needed in order to every function in management level
understand to each role and responsibility to support reach of the goal of power
plant management. Besides that, to directed every function in management level
focus to the its Key Performance Indicator (KPI) and give understanding that
every function in management level owned together goal. Internal process business
and learning & growth perspective well will be more certain that PT PJB, especially
Muara Tawar CCPP had managing with best practices manner.
3. The financial perspective is very important because will be yielding profit & growth
sustainable.
The definition of Integrated Best Power Plant Governance standard shows on Chapter
II, Theory Basis. The characteristic of nine programs is inseparable and codependent.
3.3.
16
Muara Tawar
Combined Cycle Power Plant
of
Asset
Management
Reliability
Improvement
with
Risk
17
Muara Tawar
Combined Cycle Power Plant
Picture 3.1Simple Scheme of Best Integrated Power Plant Governance (Integration of Integrated
Management System Asset Management Risk Management)
18
Muara Tawar
Combined Cycle Power Plant
Safety
Work
Instruction,
Environmental
Work
Instruction,
19
Muara Tawar
Combined Cycle Power Plant
CHAPTER IV
THE SUCCESSFULLY MEASUREMENT OF IMPLEMENTATION OF
INTEGRATED BEST POWER PLANT GOVERNANCE IN
PT PJB MUARA TAWAR POWER PLANT & ITS BENEFIT
The stage of implementation of best integrated power plant governance in PT PJB Muara
Tawar Power Plant shows on Attachment 10. The successfully of implementation of
integration process measured by 3 parameters, where the three of those parameter examined
by Balanced Scorecard (BSC) perspective, are :
1) Business process : Maturity level for every Key Performance Area (KPA)
2) The performance goal / KPI (Key Performance Indicator) :
2.1.
2.2.
2.3.
3) Quantity & quality the document of integrated & reviewed Integrated Management
System.
4.1.
Business process : Maturity level for every Key Performance Area (KPA)
No
1
Before Implementation
After Implementation
Measurement
of
baseline
Area
(KPA)
which
Areas (KPAs) by interview with all of observed remain 10 KPAs, but more
function in PT PJB Muara Tawar CCPP
areas.
The
results
of
20
Muara Tawar
Combined Cycle Power Plant
No
3
Before Implementation
Thought
most
of
all
After Implementation
KPI
showing
improve
when
PT PJB Muara Tawar CCPP not yet compared to baseline. The concept of
implemented
the
business
4.2.
Picture 4.1 Simple Scheme the Influence of Asset Management to Increase of Asset
Contribution.
Asset contribution shows that an asset can be give optimal revenue & optimal cost,
with considered a long term issues related rational optimum lifecycle cost.
Asset contribution for power plant equipment can be optimalized with increase of
Overall Equipment Effectiveness (OEE) and decrease of LCC (Life Cycle Cost) without
big investment, showed on Picture 4.2, Picture 4.3 & Picture 4.4 :
21
Muara Tawar
Combined Cycle Power Plant
Picture 4.2 Simple Scheme of Influence of Best Integrated Power Plant Governance
(Integrated Management System Asset Management Risk Management) to Increase of
Power Plant Asset Contribution
Picture 4.3 Indirect Influence to Increase of EAF (Equivalent Availability Factor) and
Decrease of EFOR (Electric Forced Outage Rate) by Implementation of Best Integrated
Power Plant Governance.
22
Muara Tawar
Combined Cycle Power Plant
Picture 4.4 Cost & Revenue of PT PJB Muara Tawar CC Power Plant that Shows Indirect Successfully
of Implementation of Best Integrated Power Plant Governance)
(Disesuaikan Dengan Skema OEE LCC Gambar 4.2)
4.3.
4.4.
Benefit of Integration
The benefit of concept of Best Integrated Power Plant Governance can be know from
the evaluation Balanced Scorecard (BSC), which affirm that the successful of those
concept will be felt on a long term and influenced by many activities in a managerial
process.
4.4.1. Financial Perspective
Produce the sustainable profit & growth because the business process
developed and implemented truly, always measurable and specified the
continuous improvement program to guarantying reaching of KPI
Increasing of earnings have the character of normative, cause of many
factor, among other the asset management well (sustainable character).
4.4.2. Customer Perspective
23
Muara Tawar
Combined Cycle Power Plant
24
Muara Tawar
Combined Cycle Power Plant
CHAPTER V
CONTINUOUS IMPROVEMENT PROGRAM
Integrated Best Power Plant Governance which implemented fully integrated based on
Integrated Management System Asset Management Risk Management and conducted
consistently expected will be produced sustainable gain & growth. So, must be create of
continuous improvement program in a long term, as a shape of clear performance goal which
cover of performance continuous potential, improvement of intern business process capability
and cycle of Plan Do Check Act.
Continuous improvement program related to Integrated Best Power Plant Governance are :
1. Determining of a long term performance goal for Integrated Best Power Plant Governance
based on measurement of maturity level for 10 pillars asset management. The assessment
do every month and increasing of determined target based on consensus between auditee
and assessment auditor (become framework maturity level with agreed target.
Based on this measurement will be know existing position and improvement direction. The
measurement based on assessment model which become guidance for improvement of
business process maturity in the integration process of Integrated Best Power Plant
Governance. With the good maturity level will be produced the best target level / Key
Performance Indicator (KPI) gradually can be increasing continuously (Best Practices
Concept), shows on Picture 5.1 :
25
Muara Tawar
Combined Cycle Power Plant
The measurement to performance target of Integrated Best Power Plant Governance based
on integration of Integrated Management System Asset Management Risk Management,
PT PJB Muara Tawar CCPP have determined the maturity level until year of 2011 with the
work program as a continuous improvement.
The measured results for :
1. Knowing the work maturity (enabling area) of physical assets management appropriate
framework of Integrated Best Power Plant Governance based on integration of
Integrated Management System Asset Management Risk Management.
2. Guidance for understanding
26
Muara Tawar
Combined Cycle Power Plant
CHAPTER V
CONCLUSION & SUGGESTION
5.1.
Conclusion
1) The program of Integrated Best Power Plant Governance determined by PT PJB is a
framework for implemented of strategy map & grand corporate strategy until to
every management level in power plant unit and this is a PT PJB competitive
program.
2) The implemented of Integration of Asset Management and Risk Management in the
system of Integrated Best Power Plant Governance produced the sharp engineering
recommendation related to improvement of physical asset management. The
choice factor analyzed in the FMECA (Failure Mode & Effect Analysis) is very
important to determine of the sharpening of recommendation. In this case, the
recorded asset history become the basis needed.
3) Implementation of Integrated Management System (based on Quality Management
System / QMS ISO 9001:2000; Environment Management System / EMS ISO
14001:2004; Occupational Health & Safety Management System / OHSMS OHSAS
18001:1999 & Permenaker No. Per.06/Men/1996) is a very important & valuable
based modal to integration process of Integrated Best Power Plant Governance
(asset Management & Risk Management).
4) To know the successful level of implementation of Integrated Best Power Plant
Governance must be conducted the measurement with the precise method. To
improve
of
implemented
maturity,
must
be
determined
the
continuous
improvement program.
5.2.
Suggestion
1. The successfully of implementation of integration of Integrated Best Power Plant
Governance need a strong commitment management and must be support by all of
personnel related to power plant operation & maintenance business process.
2. The method of integration based on Integrated Management System Asset
Management Risk Management developed by PT PJB Muara Tawar CCPP can be the
modeled for ideal power plant organization.
27
Muara Tawar
Combined Cycle Power Plant
REFFERENCE
1.
2.
3.
4.
Ruly Firmansyah; Laporan On The Job Training (OJT) di PT Pembangkitan Jawa Bali
Unit pembangkitan Muara Tawar 15 January - 15 Mei 2007; International Plant
Manager Training And Development Program 2007.
5.
6.
Materi - Materi Presentasi untuk Raker (Rapat Kerja) PT PJB, Forum Komunikasi Teknik,
Presentasi Manajemen aset dan Manajemen Risiko.
7.
Direktur SDM & Organisasi PT PLN (Persero); Knowledge Management Untuk Mengatasi
Knowledge Drain Menuju Learning Organization, Round Table Knowledge Management
Indnesia XII 2007
8.
Robert S Kaplan, David P Norton, Strategy Maps : Converting Intangible assets into
Tangible Outcomes, Harvard Bussiness School Publishing Corporations, USA, 2004.
9.
John Mobry, Reliability Centered Maintenance RCM II, Industrial Press USA, Second
Edition, 1997.
11. John Dixon Campbell, Uptime : Strategies for Excellence in Maintenance Management,
Productivity Press, New York, 1995.
12. Edward H Frazelle Ph.D, Supply Chain Management, Mc Graw Hill USA, 2002.
28
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 1
STRATEGY MAP of PT PEMBANGKITAN JAWA BALI
(Reference : Corporate Strategy Map PT PJB)
29
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 2
ASSET MANAGEMENT of PT PEMBANGKITAN JAWA BALI (PT PJB)
(Reference: Corporate Strategy Map PT PJB)
30
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 3
Corporate Strategy Map of PT PJB
(Reference: Corporate Strategy Map PT PJB)
31
Muara Tawar
Combined Cycle Power Plant
32
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 4
Tata Kelola Unit Pembangkitan Terintegrasi
(Integrated Best Power Plant Governance)
PT PEMBANGKITAN JAWA BALI
Tata Kelola Unit Pembangkitan (Integrated Best Power Plant Governance) is
implemented of corporate strategy map of PT PJB for every management level in
power plant unit.
33
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 5
BASIC CONCEPT of INTEGRATION of
ASSET MANAGEMENT / RELIABILITY IMPROVEMENT
with RISK MANAGEMENT AT PT PJB MUARA TAWAR CCPP
(Developed by Engineering Team of PT PJB Muara Tawar CCPP)
34
Muara Tawar
Combined Cycle Power Plant
2. Grand Planning
35
Muara Tawar
Combined Cycle Power Plant
36
Muara Tawar
Combined Cycle Power Plant
37
Muara Tawar
Combined Cycle Power Plant
7. Check, Action & Continuous Improvement : Application at PT PJB Muara Tawar CCPP
38
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 6
INTEGRATION of BUSSNIESS PROCESS of PJB MUARA TAWAR CCPP
BASED ON INTEGRATED MANAGEMENT SYSTEM
ASSET MANAGEMENT RISK MANAGEMENT
(Developed by Engineering Team of PT PJB Muara Tawar CCPP)
39
Muara Tawar
Combined Cycle Power Plant
40
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 7A
STAGE OF INTEGRATION CONCEPT OF
INTEGRATED MANAGEMENT SYSTEM ASSET MANAGEMENT RISK
MANAGEMENT
41
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 7B
THE INFRASTUCTURE OF INTEGRATION CONCEPT OF
INTEGRATED MANAGEMENT SYSTEM ASSET MANAGEMENT RISK
MANAGEMENT
42
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 8
RISK MITIGATION OF HOT GAS PATH PARTS OF GAS TURBINE
(CASE STUDY OF RISK MANAGEMENT)
43
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 9
UPLOAD THE REVIEWED INTEGRATED MANAGEMENT SYSTEM DOCUMENT
INTEGRATED TO EAMS & RISK MANAGEMENT PORTAL WEB PT PJB
1. Standard Job
44
Muara Tawar
Combined Cycle Power Plant
45
Muara Tawar
Combined Cycle Power Plant
46
Muara Tawar
Combined Cycle Power Plant
7. LINK www.mr.pjb2.com
47
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 10
Stage of Implementation of
Integrated Best Power Plant Governance
48
Muara Tawar
Combined Cycle Power Plant
49
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 11
RESULTS OF BUSINESS PROCESS ASSESSMENT
PT PEMBANGKITAN JAWA BALI
BEFORE IMPLEMENTATION OF INTEGRATED BEST POWER PLANT GOVERNANCE
(January 2006)
Maturity Matrix
Business Processes / KPI
PT PJB UP Muara Tawar, January 2006
Condition of business process of
PT PJB Muara Tawar CCPP (16th
January 2006). Not yet
implemented business process
properly
Expected condition for next 1218 months at the position of 44 (World Class)
50
Muara Tawar
Combined Cycle Power Plant
Assessment conducted in period November 2005 January 2006 to 10 Key Performance Areas
(KPA), are :
1. Management Strategy
This is a new activity at Muara Tawar, where the strategy map has been successfully
completed.
Outstanding actions are to :
Finalise the map
Communicate content & intent through the plant
Complete designation of owners
Owners to complete action tables & KPIs
Strategy execution needs at least weekly review by owners and monthly review by the
management team. In this review progress needs to be reviewed, KPIs analysed &
performance barriers identified & removed. Strategy execution progress also needs to
be reported back to Head Office monthly.
Suggest running strategy execution skills workshop at Muara Tawar; or attend next
course.
Communication and visibility actions across the organisation should follow these review
sessions.
51
Muara Tawar
Combined Cycle Power Plant
An owner for MOP (and WP & C) needs to be clearly identified and appointed. Owner
for MOP needs deputy manager authority.
MT needs to become more KPI orientated in its management style. This will involve:
Defining local required KPIs (and goals)
Develop a management culture which uses KPIs as an accountability methodology
and tool.
2. Reliability Management
52
Muara Tawar
Combined Cycle Power Plant
There is the great opportunity to progress from level 2 to level 4 in WP& C in the short
term (breakthrough) this will however take a very carefully managed execution of the
new business processes.
In order to accelerate implementation of the business processes it is recommended
that MT receives some coaching and support from a MOP technical expert.
The WP&C Business Process needs to be formally announced as the main business
process for PJB. This will avoid confusion and help improve the implementation.
(performance barrier)
The planners have never received formal planning or scheduling training. This needs to
be arranged. (performance barrier)
There is emerging visibility in the planning office. However, to support the needs,
more effort is required to be focussed on visibility management. Visibility requires a
strategy and an owner and KPIs.
53
Muara Tawar
Combined Cycle Power Plant
4. Performance Management
54
Muara Tawar
Combined Cycle Power Plant
5. Organisational Alignment
The engineering department has not been formally constituted due to Head Office
issues (performance barrier)
The individual functions within the organisational structure need to be aligned with the
new responsibilities associated with MOP this is again an issue which requires
coordination and support with head office. (performance barrier)
MT should review ways of recognising and rewarding performance.
MOP requires a new range of skills and competencies. There needs to be a plan to put
these in place. (performance barrier)
Planning & scheduling
MOP Level 1 & 2 etc
This needs a supporting set of KPIs to measure the required competencies are being
achieved.
This training will not occur from a head office level, it is recommended that Gresik
develop its own training strategy in support of these goals.
55
Muara Tawar
Combined Cycle Power Plant
6. Materials Management
Materials management does not impose the issues experienced at the other plant.
(serious delays stock outs etc.)
There are problems with the inflexibility of the PJB purchasing process, but MT has
worked around these in many ways.
Materials management at MT can be considered as an internal best practise.
56
Muara Tawar
Combined Cycle Power Plant
57
Muara Tawar
Combined Cycle Power Plant
8. Continuous Improvement
58
Muara Tawar
Combined Cycle Power Plant
Muara Tawar has a enabling work culture which leads to a positive attitude to work and
challenges.
There were some comfort factors that should be brought to managements' attention.
These include:
No real recognition of Muara Tawars achievements from head office
Transportation issues
Muara Tawar have an empowered work culture which needs to be recognised and
looked after it is an asset.
59
Muara Tawar
Combined Cycle Power Plant
60
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 12
RESULTS OF ASSESSMENT MATURITY LEVEL
BEFORE IMPLEMENTATION OF INTEGRATED BEST POWER PLANT GOVERNANANCE
BASELINE (APRIL 2007) AND TARGET 2007
61
Muara Tawar
Combined Cycle Power Plant
62
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 13
EXAMPLE of MANAGEMENT PERFORMANCE CONTRACT
63
Muara Tawar
Combined Cycle Power Plant
ATTACHMENT 14
EXAMPLE of CONTINUOUS IMPROVEMENT
64
Muara Tawar
Combined Cycle Power Plant
65
Abstract
This paper will discuss on the productivity that we have gained through the use our LifeCycle
Asset Information Management System. The system is up and running in two of our power
plants in Malaysia. Common to any information/knowledge management solution, it is not easy
to properly measure the impact of such system. So we have decided to run some benchmark so
that a clearer measure of gained productivity can be obtained. We have decided the best way to
do this is by conducting a time study0 on normal working process against working process with
the help of EALIS. The result from this study will be shown here alongside the analysis.
Introduction
We at Teknik Janakuasa Sdn. Bhd. TJSB have invested in a system to manage all of our
engineering information on most of our Power Plants. This is where the initiative for Life Cycle
Asset Information Management LCAIM started and three years later here we are.
During the initial phase of development, the idea was to use LCAIM internally within TJSB. But
in the later stage of development we realized that the system has a lot of commercial potential
and decided that it best if we can share this new tool with the whole industry. We then decided to
package the whole idea behind LCAIM into a single product. The resulting product goes by the
name of EALIS. Throughout this paper the name LCAIM and EALIS will be used
interchangeably, but both are referring to the same thing.
Our main motivation behind EALIS is the realization that there are no solutions out there that
could really help us in providing with accurate plant information at a given time. There is also
the problem on managing the information changes throughout the plant lifecycle. We knew the
technology was out there, but it would take some effort from us to actually mold it to fit that
standards and specifications that we were hoping for.
To relate yourself to this problem, consider this scenario. Original documentations that ware
handed by the EPC will always be slightly inaccurate. Despite this fact it will end up being the
reference. This slightly crooked reference will then be used thoroughly though out the plant
lifecycle. Engineering changes will be made but not all of these changes were properly
documented nor properly reflected on the reference drawing. Time will slowly rot these papers.
Just five years into operation, some of the original reference material will be missing or just
turned into dust. The other possibility is that the same reference might be kept by different
department with their own notes on the engineering changes. But often enough these changes are
only known by the person in charge of the changes. Over time these information will just decays
even further and at the same time the some of the team senior member has left team. The new
team will then have trouble to do work as most of the documents are broken while their only
salvation has left the company. This is exactly what EALIS is trying to prevent, total information
management throughout the plant lifecycle; nothing is left behind.
A presentation1 on LCAIM/EALIS has been made on the last HAPUA Conference and a few
other conferences so it will not be covered here. The aim of this paper is just to discuss our
finding on the time study conducted and the benefits from using EALIS for the Operation &
Maintenance team.
For two of the plants operated by TJSB, we manage to install and have EALIS serving the end
users. These two plants are GB3 and Tanjung Bin Power. GB3 is a Combined Cycle power plant
running on an Alstom GT13E2 machine while Tanjung Bin Power is a Coal-Fired Plant. But for
the purpose if this paper, the plant in context is the GB3 plant.
information in relation to the pending work, with 2000 pages in that single file this will take
some time. But the trouble does not ends the, some of these documents has to be carried to site,
and 2000 pages is not light. So we can now see why this method is unacceptable anymore.
With EALIS in place the workflow still remains the same, the only difference here is the method.
With EALIS in place any one can retrieve data from their workstations, since the system uses a
centralized database, anyone with access to a computer and the network can gather information
easily. Gone from the old way is the need of physical files as all of the actual documents have
been stored into EALIS digitally. With these files made accessible through the network, any
document can be accessed from site through a laptop or a tablet pc (given the availability of a
network).
4. The repair works are normally carried out by maintenance technicians or contractors supervised
by appointed personnel from Maintenance section. (This is the crucial part where the
troubleshooting will be carried out. EALIS will definitely assist Maintenance Section with the
structured data and information on the work execution).
5. On completion of the job the competent personnel will sign-off the permit and return it to
Operations for cancellation (again, EALIS will be used by Operation section to identify, ensure
and carry out de-isolation point on the corrected Equipment Failure and back the mentioned
equipment into operational (Buy-off))
6. The Completion Remarks, Cause and Damage information from the Job Card are entered into
Maintenance Notification by maintenance personnel and reviewed by the engineers or section
head. The maintenance personnel will then proceed to perform Task Completion on Notification
and Completion Confirmation in SAP R/3. Then the planner will then close the Notification and
set the status of Maintenance Order to Technical Completion (TECO). After all costs have been
collected from purchase orders etc., the Order will be settled and financially completed by
Accounts Department (where EALIS is mostly not applicable in this stage).
Result
The result shown here is the average times calculated for all of three given test situations. Each
graph will compare the time taken to by using ELIS and without using EALIS. A graph
representing the total average time for the 3 task is also given to show the significant difference
in total time spent between these two methods of gathering information.
Mechanical Department
Average time of all 3 tasks / stage
Case 1 - (31MBV21AP001) Main Lube Oil Pump 1 - Temperature high
Case 2 - (31MBU32AP001) NOx Water Pump - Pump leaking
Case 3 - (31MBA33AP001) Fuel Pump - pump failure
90
30
80
25
70
60
20
With EALIS
50
Without EALIS
15
40
30
10
20
5
10
From the chart on the right we can clearly see that the time taken by using EALIS is quite
short compared to the old method of file and papers. That is 70 minutes saving in total time
required for information gathering.
Electrical Department
Average time of all 3 tasks
Case 1 - (31MBA81AA011) Blow off Valve - failed to get actuator status
Case 2 - (31MBP31AA002) Fuel Gas Relief Valve - failed to get actuator status.
Case 3 - (31MBV40CT002) Lube oil temperature The reading fluctuates.
120
30
100
25
80
20
With EALIS
60
Without EALIS
15
10
40
20
The same trend from the Mechanical Department seems to be showing here as well, but with 90
minutes of time saved.
Control & Instrumentation Department
Average time of all 3 tasks
Case 1 - (31MBX21AP001) Power Oil Pump 1 Pump MCC tripped.
Case 2 - (31MBV10AN100) Exhaust Fan - Alarm triggered.
Case 3 - (31MBN35AP001) Sump Pump 1 Pump motor failed to start.
100
30
90
25
80
70
20
60
50
15
With EALIS
40
Without EALIS
30
10
20
10
These final graphs has basically confirms what we have been hoping for all this while. By
including EALIS in our workflow, the time spent in information gathering has been cut by
around 80%. This is a very significant improvement.
Analysis of Result
From the result obtained we can clearly see that through the help of EALIS, the time consumed
for information retrieval has been cut dramatically. To get a better understanding on the
advantages gained from these results, the data can be used to obtain the increase in productivity
and the cost savings behind it.
Productivity increment (in view of information gathering)
The average time for all 9 test situations;
With using EALIS
: 11.13
Without using EALIS
: 91.45
The time difference
Productivity gained
: 80.32
: around 700%
Cost savings
Its hard to give actual numbers on the actual cost savings. But with the productivity
increase given, it safe to say that there is money to be saved somewhere.
But for a rough estimation, let us assume the model2 below to represent the overall
process of doing any particular tasks;
50%
Preparation time (includes info gathering)
60%
Other
15%
Others
35%
Wrench time
40%
Information Gathering
Out of the whole model 20% of the time is spent on finding information. If we assume
the 700% productivity gained to this information gathering process this will cut down the
information gathering by a factor of 8 which brings us to 2.5% of the total time which
essentially cuts 17.5% from the total time.
We can then assume the saved time is directly proportional to saved cost of man hour.
17.5% is quite a significant when we are talking about tens of million of dollar spent in
O&M budget.
The other way to look at it is that the extra time gained can increase the wrench time.
With more time spent on doing the job with higher quality documents in hand, one can
rest assure that any work done is a guaranteed success.
Conclusion
With the result shown in this paper, one can see the clear the advantage of having EALIS for the
management of information within any organization. The clear increase in productivity through
the reduction of time consumed to gather information result in cost saving opportunities and
higher work quality. We can proudly say that we have beginning to see the result that we are
hoping for when we started the whole LCAIM initiative.
Still EALIS have a lot to offer. What we have shown here is just the tip of the iceberg, there is a
lot of other possibilities to explore. So from time to time we are planning to do similar
benchmark to prove and access the effectiveness of having such system within an organization.
At the same time we will keep on continuing in the development of EALIS to even further its
potential. But we will not stop there, as the next push will be stepping up our marketing effort to
make sure EALIS become relevant to the industry as something that is more prominent like SAP
or Maximo.
References
0. Industrial Timestudy Institute Inc, Time Study and Methods Engineering (website at
http://www.industrialtimestudy.com/tsandmethods.html )
1. Ir. Rosli Hamid, LifeCycle Asset Information Management Presentation slides
(available from www.ealis.net)
2. Doc Richard D. Palmer, Maintenance Planning and Scheduling Handbook - Book.
3. EALIS, . . . . more information on EALIS (website at www.ealis.net)
4. Gregory P. Sullivan, Federal Energy Management Program (FEMP): Operations and
Maintenance Best Practices Guide (O&M BPG) Book.
5. U.S. EPA and U.S. DOE, Fifteen O&M Best Practices Published report.
! "##$
Abstract
Plan outages affect plants availability. The unexpected problems
found during the plan outage will extend the working days which reduces
plants availability.
During Bangpakong Gas Turbine Combustion Inspection, damage in
the segment seal of turbine stationary blade stage 4 was found. The
traditional method of solving this problem is to lift the upper half casing and
change the segment seal, which resulted in extending the plan outage.
By analyzing the segment seal, changing method was modified
resulting in work scope reduction and maintaining the plants availability.
Introduction
2.1
Inspection
Material Properties
2.3
Correcting Problem
TSB#4
3.
From this solution, we did not find any suspicious output while the unit
was in operation. And we can save the plants availability for 15 days [5],
which can be amounted to 5,525,000 Bath according to the PPA availability
credit. In addition, we can save labor and resource cost which can be
amounted to 699,872 Baht [6]. All save will be 6,224,872 Baht in total.
4.
Conclusion
The solution was proved success as the unit has been in operation for
more than 8 years. Since last inspection (3 July 2007), we did not find any
cracks on the welding line. This solution can keep plants availability, and
manage efficient used of asset.
5.
Bibliography
[1]
[2]
[3]
[4]
[5]
[6]
Abstract
Gas turbine generator 2.3 Tanjung Priok Combined Cycle Power Plant was fault. There was a short circuit on
stator winding bar phase R. Short circuit was caused by insulation failed. End winding junction of bar number 15
was melted. The result of this phenomenon is decreasing of some bars volume. Decision had already made;
eliminating the broken bars because it has lower risk than bar welding/ connecting. Two turns (4 bars) of
winding phase R was cut and so did another phase (S & T) for voltage balancing. The new bypass connection
was made to connect the normal winding. The result, 12 of 120 bars had already eliminated. Elimination of
these bars consequence at 10% drops of generator output voltage. Overcome this consequence; ratio changing
was made at Main Transformers tap changer to compensate the lower generator output voltage. The Main
Transformers output voltage became equal with transmission voltage. Tap changer ratio in Auxiliary
Transformer was also changed for gain an auxiliary voltage same as before. Resetting generator protection
relay and excitation system was done in order to match between old and new generator value and made
generator and gas turbine operation safer. Control and evaluation of generator operation after elimination
process have been made. Generator has been operating normal and safely although it was not in maximum
rate until now (5 months). We hope this paper can give inspiration to face the generator problem in other power
plants.
1. Introduction
Gas turbine generator GT 2.3 Tj. Priok CCPP was
fault. There was short circuited on phase R. It was
caused by insulation failed. End winding junction
on bar number 15 was melted. It resulted
decreasing of bar volume in some bars especially
in bar number 15. The circle of winding in DE side
got the carbon dust from the arching process in bar
number 15.
Rated current
Rated frequency
Rated speed
Poles
Phases
Stator connection
Excitation voltage
Excitation current
Cooling media
: 7698 A
: 50 hz
: 3000 rpm
:2
:3
: star
: 310 V
: 1437 A
: air
2. Objective
To recover the generator condition as soon as
possible
To decide what the optimal way to recover
generator
To anticipate the operation character after
recovery
3. Generator GT 2.3 Priok CCPP
Specification of generator GT 2.3 Tanjung Priok
Rated apparent power
: 210 MVA
Rated active power
: 168 MW
Rated power factor
: 0.8
Rated voltage
: 15.750 kV (+/- 7.5%)
HAPUA Workshop, 15-16 July 2008
4. Problem
End winding junction of bar number 15 was melted
and it caused decreasing volume of some bars.
Generator must operate in normal and safe
condition as soon as possible.
5. Solution
It was decided to eliminate bar number 15 in one
turn (2 bars) because it had lower risk than bar
welding. We could account the effect of bar
elimination but it couldnt for bar welding. The
1
B
d
l
n
k
k =
wk
kd
2
wk
k ' = 0 .9
kd
2
S ' = 0 .9 k A B d
l n
'
S = 0 . 9 210 MVA
S ' = 189 MVA
Rated current before elimination :
S = 3 V I
I=
S
3 V
210MVA
3 15.75kV
= 7698 A
I=
U ph = 2 f w f w
Uph
f
w
fw
/l
l
= phase voltage
= frequency (hz)
= number of turns (turn)
= winding factor
= magnetic flux per unit length of rotor (Tesla)
= rotor length (m)
S
3 V
189 MVA
3 14.175kV
= 7698 A
7. Elimination Process
Elimination process need 34 time working days
(some of days use double shift). Two turns (4 bars)
of winding phase R was cut also another phases
for voltage balancing. Generator winding bars
totally 12 bars were cut. Hipot testing was done
before elimination process to ensure the condition
of winding bar in every phase. The broken bar was
separated to ensure the condition of normal bars.
Eliminated bars were isolated but still in existing
slot. Special bypass connection was made to
connect the normal bar.
For Y connection :
Vt = 3U ph
Vt
Vt =
2 f w fw
Vt ' =
2 f 0 .9 w f w
l = 15 . 75
V t ' = 0 . 9 V t = 0 . 9 15 . 75
V t ' = 14 . 175 kV
The elimination process change
Apparent Power of generator :
the
Rated
S = k A B d 2 l n
S
A
Setting
Before
1.00 UN
1.40 IN
4.0 s
0.08 IN
0.08 I2/IB
1.40 UN
0.2 s
1.20 UN
3.0 s
HV
LV
Ratio
Position
162750
15750
10.33
X (new)
158875
15750
10.09
155000
15750
9.84
151125
15750
9.60
147250
15750
9.35
X (existing)
After
0.90 UN
1.10 IN
4.0 s
0.05 IN
0.05 I2/IB
1.10 UN
0.1 s
1.076 UN
6.0 s
Setting
Original
New
100%
107.5%
92.5%
90%
95%
85%
115%
97%
5%
0%
105%
100%
130%
105%
100%
100%
Tap
HV
LV
Ratio
16537.50
400
41.34
RTD
90 MW
100 MW
Position
( C)
( C)
Slot 2
95.28
99.26
3.98
4.18
Slot 10
96.49
100.66
4.17
4.32
Slot 18
96.07
100.27
4.2
4.37
Slot 26
95.87
99.92
4.05
4.22
Slot 34
95.71
99.58
3.87
4.04
Slot 42
94.99
99.04
4.05
4.26
16143.75
400
40.36
15750
400
39.38
15356.25
400
38.39
14962.5
400
37.41
Posisi
X (existing)
X (new)
Phase R = 0.78 nC
Phase S = 0.80 nC
Phase T = 0.69 nC
Fig 6. Partial discharge value
Rp
24 180 100 MW
kWh
= Rp 138 ,870 , 720 , 000 ,
= USD 15 , 094 , 695
= 321 . 46
12. Suggestion
Elimination process of stator winding bars is
applicable for other power plant if the
compensation factor for it process are feasible.
13. References
1. Power Plant Training Manual, Generator Vol. 1,
Tanjung Priok CCPP, ABB-Marubeni.
2. Generator Transformer For Gas & Steam
Turbine Generator (177 & 235 MVA),
Maintenance Manual, Marubeni-Hitachi Ltd.
3. Electrical Insulation for Rotating Machines
(Design, Evaluation, Aging & Testing), Greg C.
Stone, Hussein Dhirani, Ian Culbert, Edward A
Boulter, IEEE Press.
4. Electrical Machinery Fundamentals, Stephen J.
Chapman, McGraw Hill International Edition.
5. ABB Generator and Transformer Protection :
Lecture, ABB Network Partner AG.
6. GT 13E Setting Data for the Gen. Protection
Functions, No. GKW E 094 407, Tanjung
Priok CCPP, ABB-Marubeni.
7. Static Excitation System for Gas Turbine
Type : DDS-0/ 431. Tanjung Priok CCPP,
ABB-Marubeni.
14. Biographies
Tri Tjahjonoputro, Buyung Arianto, and Wasis
Jati Waskitho are employed by Indonesia Power,
Tanjung Priok Generating Business Unit,
Maintenance Department, based in Tj. Priok
Jakarta
Email address :
tri.tjahjonoputro@indonesiapower.co.id
buyung.arianto@indonesiapower.co.id
wasis.jw@indonesiapower.co.id
11. Conclusion
Decreasing volume of stator bars generator in
GT 2.3 Tanjung Priok CCPP occurred
because of end winding junction melting
Stator bar elimination was done in generator
winding GT 2.3 to recovery its generator
HAPUA Workshop, 15-16 July 2008
INNOVATION PAPER
Title
by:
IIM IBRAHIM
NIP: 5983068KIII
RULY HUSNIE RIDWAN
NIP: 820721003I
AGUS WITARSA
NIP: 5579201KIII
ABSTRACTION
Relatively short of fan blade life cycle, high probability loss in KWh, and high risk of
safety & environment on blade failure make the innovation and lengthening fan life cycle as
worth thing to be done.
Conclusion of blade failure analysis, the root cause of failure is the erosion on blade.
Based on that conclusion, the innovation is aimed to new method for lengthen the blade life
cycle. The method submitted by manufacture is mechanical coating, but this method does not
give optimal result. Then it is reasonable to implement cladding method using stainless steel
SUS 304 material and riveting for joint. The implementation on this method gives extension
on life cycle from 13.000 to 40.000 hours operation times. Last condition at hour 40.000 of
operation time, the blade is still operating properly.
Financial benefit on the implementation this method is 1.8 billion rupiah
(192.612. USD) saving in the five years implementation. Risk analysis shows the low risk of
cladding method and good reliability on this implementation, it is reasonable that these
method become as a references for fan blade at other plant.
Key words : life extension, cladding, fan blade of cooling tower
AUTHENTICATION PAGE
Innovation on title :
LENGHTHENING LIFE CYCLE FOR FAN BLADE OF COOLING TOWER
Submitted by :
1.
IIM IBRAHIM
2.
3.
AGUS WITARSA
PREFACE
Thank unlimited to God the great, because God gave the ease for finishing these innovations
report titled LIFE EXTENSION OF COOLING TOWER FAN BLADE. But the obstacles
we met is a learning to us for the future.
Thanks is submitted to the people helped us in finishing these report.
1. Mr. Ahsin Sidqi as General Manager of PT.Indonesia Power UBP KAMOJANG.
2. Mr. Agoes Danarto as Maintenance manager of PT.Indonesia Power UBP
KAMOJANG
3. Mr. Pelita Baru Pakpahan as Engineering manager of PT.Indonesia Power UBP
KAMOJANG
4. Mr. Gregoryus Y.L as Operation manager of PT.Indonesia Power UBP KAMOJANG
that always give the challenges for innovation activities.
5. Management Team of PT.Indonesia Power UBP KAMOJANG.
6. Collegues and unmentioned name that helped us in finishing this report
We hope that this report is usable as reference. We know that these report is far away from
perfection, so we have a good will for critical and suggestion for these innovation. Our hope,
this report is much usable for other plant, especially for PT. Indonesia Power.
Author
CHAPTER I
INTRODUCTION
1.1
Background
Geothermal plant is a plant with low cost production compared to other power plant. Though
its infestations cost is high, but so many positive side, any of them:
High robustness operation (based on NERC standard, geothermal plant is higher
performance compared to other plant)
Operation & transportation is not conditioned by weather
Reduce the fuel consumption and the bad effect of its use.
In terms of energy and electricity crisis, geothermal plant robustness is a crucial thing.
Based on best practice, about 40% geothermal plant failure is caused by its part
failure. The failure root is that the steam is not pure H2O steam, but contains any corrosive
fluid and abrasive solid particle. It shortens the parts life cycle, not exception for blade of
cooling tower. Appropriately the life cycle of the blade is only 13.000 hours because on the
factor mentioned above.
This innovation is aimed for explanation for blade life cycle extension on PLTP
Kamojang as innovation from mechanical coating proposed by manufacture.
1.2
Purpose
1.3
Innovation scopes
1.4
Method
The innovation is focused on method for extending the life cycle of blade of cooling tower. It
is done through some analysis stage:
a. Do a technical study for failure case of fan blade
b. Collect the design data, operation data, and historical maintenance for finding the root
of the failure.
c. Do a technical study and risks study for life extension as alternative solution for the
root failure prevention.
d. Do a financial and non financial study and determine the step for application for the
method.
CHAPTER II
APPLYING THE INNOVATION
II.1 Preface
Cooling tower at PLTP Kamojang is the main heat exchanger on main cooling
circulation system. In other side, it spreads the Non Condensable Gas so there is no high
concentration and stacking. If the cooling tower fails performing its job, acid rain will occur
in the plant area because of CO2 and H2S contain on the Non Condensable Gas exhausted
by the plant.
Fan blades, as the main part of cooling tower, often fails perform its job. These failure
had the looses for KWh production. In the other hand, it enlarges the risk on the environment
and social aspect on the plant area. (Picture on appendix 7 & 8 shows the fan blade failure)
extensively in designing the blade that made of fiberglass composite. At the reality, the
material is not endurance enough holding the erosion on the leading edge. The erosion is
caused by impact of the mist grain. The erosion gains outspread porous face on the blade
surface, the mist infiltrates to the pore and continually makes the holes on the surface. It
increases the unbalance load and increase of SIFs (stress intensification factor). If it is
neglected, the SIF will intensify and generate the crack. Crack propagation will occur and
blade failure happens.
Fan blade mainly affects the cooling tower performance. Main effect of one blade failure is
power plant derated about 10 MW, shutdown should be done if the amount of failure blade
three or more. Time duration of one cell fan cooling tower is about 10 to 48 hour (depend on
the level of failure and availability of spare part), it is about 9 months indent time for OEM
(Original Equipment Manufacturer) replacement. Picture 4 shows the failure blade.
From historical data for maintenance the blade, this method only lengthen the life cycle about
13.000 hour operation time. Next table performs the data from field monitoring.
Table 1. Blade replacement using mechanical coating method on PLTP Kamojang.
No
1
Equipment
Date of
Date of next
/ failure type
replacement
replacement
16 January 2001
21 June 2002
Note
Mechanical coating method
erosion
Thickness
: 0.4
Length
: 2,000 mm
Width
: 200
mm
mm
At this time, the cladding operation is considered successfully done. It is proved by the blade
of 3rd unit cooling tower is still operate properly. Table 3 present the historical maintenance
data of fan blade of 2nd and 3rd unit cooling tower.
Table 2. Blade replacement using cladding method on PLTP Kamojang.
No
1
Equipment
Date of
/ failure type
replacement
21 June 2002
/ erosion
Note
Cladding method
replacement
In addition, from parameter operation monitoring and maintenance, before and after cladding,
no significant change of the operation data, the change is still in the scope of tolerances, any
of them:
For the next step, cladding is done for 10 set of fan blade on 2nd and 3rd cooling tower unit on
PLTP Kamojang. Table 3 presents the operation & maintenance data of 2nd and 3rd cooling
tower unit.
Table.3. Operation & maintenance data of 2nd and 3rd cooling tower unit.
Fan
Cell
No.
Damage
Details
Replacement
/ Repairmen
Repairmen / Replacement
Date
Life time
(hours)
09/10/2004
Erosion
09/10/2004
Cladding
27,696
07/12/2007
Erosion
07/12/2007
Cladding
4,584
18/05/2004
Erosion
18/05/2004
Mechanical coating
31,152
07/12/2007
Erosion
07/12/2007
Cladding
4,584
18/05/2004
Erosion
18/05/2004
Mechanical coating
9,216
06/06/2005
Erosion
06/06/2005
Cladding
26,520
17/04/2008
Erosion
17/04/2008
Cladding
1,416
24/10/2005
Erosion
24/10/2005
Cladding
23,160
Erosion
21/06/2002
Cladding
52,464
10/02/2004
Erosion
10/02/2004
Cladding
38,088
09/05/2004
Erosion
09/05/2004
Cladding
35,952
27/08/2004
Erosion
27/08/2004
Mechanical coating
14,832
07/05/2006
Erosion
07/05/2006
Cladding
18,480
09/05/2004
Erosion
09/05/2004
Mechanical coating
17,520
09/05/2006
Erosion
09/05/2006
Mechanical coating
1,680
18/07/2006
Erosion
18/07/2006
Mechanical coating
7,464
25/05/2007
Erosion
25/05/2007
Cladding
9,288
CHAPTER III
INNOVATION ADVANTAGES
3 times
3 x 10 MW x 8 hours
240 MWh
Rp 756,37 / KWh
Rp 181.528.800
3 x Rp 32.000.000
Rp 96.000.000
Total cost
Rp 277.528.800
1 x 10 MW x 8 hours
1 time
80 MWh
Rp 756,37 / KWh
80 MWh x Rp 756,37
Rp 60.509.600
1 x Rp 34.037.630
Rp 34.037.630
Total cost
Rp 94.547.230
Rp 182.981.570
@ 5 cell
10 cell
Rp 1.829.815.700
= 192.612. USD
In this innovation, cost benefit from innovation implementation to cooling tower at PLTP
Kamojang reached Rp 1,8 billion in five years time innovate realization.
There was fan blade failure at cooling tower frequently when fan was operating. Beside that,
direction fan blade falling couldnt be predicted. This is risk to employee safety (k3) at PLTP
Kamojang area. Then, the decrease fan ability to drain causes NCG (Non-Condensable Gas,
consist of CO2 and H2S) flow out doesnt optimal. It would make sour rain surrounding
system. It affected environmental. Actually, PLTP Kamojang closes to people agriculture.
Therefore, it would give social effect to surrounding people:
This innovation has succeed generate life extension, where could be increasing autonomy unit
to OEM part. Time OEM fan blade order is minimize 9 months.
The heavier fan blade weight because water bulbs enter erosion located, certainly increasing
pumps power consume. This can be seen from increasing parameter at current motor.
Innovation has succeed prevent erosion so motor power hasnt significant increase. This is
pointed to generator efficiency from self consumption.
: PT IP UBP Kamojang
Project
Status
1.
Risk Rating
Cause
Result
Result
Posibility
Level
Level
Choosen option
Category
Failure
Erotion,
Derating
of Fan
stress,
unit 10
cladding method to
Cooling
material,
MW/ cell
tower
Fatigue.
High
Blade
Risk analysis after inovation
: PT IP UBP Kamojang
Project
Status
1.
Caus
Risk Rating
Result
Failure
Erotion,
Cladding
of Fan
stress,
method to
Cooling
material,
fan blade,
tower
Fatigue.
so
Blade
Cause
Possibility
Level
Level
Category
Low
Choosen option
Increasing PM and
PdM
increase
reliability
That table shown that there is decreasing risk level of fan blade when system was operating.
Risk analysis result in innovation which has been done (appendix 13) shown that risk to
strategic aspect, financial aspect, and cooling tower operational have lower category. Thats
mean that the innovation deserves to be executed.
Table.5. Risk Identification if innovation would be executed
No
Target
Strategic
PS Efficiency
2
B
Risk
Sources
Risk
Internal
Internal
KWh Production
Decreased
Internal
Internal
Damage at low
transmission system
KWh
Production
Financial
Cost
effectiveness
Operasional
Performance of
cooling tower
Cause
Performance of
cooling tower
Internal
Difficulty to
maintenance/operation
Performance of
cooling tower
Internal
High Vibration
Performance of
cooling tower
Internal
Material corotion
Possibility
rating
Not
significant
Minor
Effect
Increasing current
with plate addition
Plate cladding
released
Increasing
KWh PS
Decreasing
KWh
Material
Procurement cost
for cladding
Increasing
HAR cost
overload because
over material
addition
The long time to fan
blade plate
procurement
Heavier Fan blade
weight because
unbalance cladding
cladding material
Oxidation
Medium
Major
Decreasing
cooling tower
work
Decreasing
cooling tower
work
Decreasing
cooling tower
work
Decreasing
cooling tower
work
Fatal
Very big
Big
Medium
1
Small
Very small
3
5
CHAPTER IV
CONCLUSION AND SUGGESTION
IV.1.
Conclusion
V.2.
Suggestion
Life extension method of fan blade cooling tower can be able to be applied at the application
of fan blade in other power plant unit with similar problems. This implementation is done by
considering several technical aspects, i.e.: equipments design, material, operating condition,
etc.
BIBLIOGRAPHY
1. Design, Operation & Maintenance Manual PLTP Kamojang Unit 2 dan 3, 1987.
2. Physical and chemical process of geothermal fluid impact on metal of geothermal
power plant equipment, O.A. Povarov, G.V. Tomarov, V.N. Semenov), 2005.
3. Prevention of scale adhesion using surface treatment of coating with organic
compound at geothermal power station, Shimizu, Eiichi Suzuki, Yuko Mitobe, Hidetosi
Hiraha, Hiroshi Nakazawa, Tokumi Saito, Kazuo Oyama, Rokunosuke Hirata, 2005.
4. Upgrading and life extension technology for geothermal steam turbines, Sakuma T.
Takahashi O. Watanabe M. Fukuda, 2005.
5. Exposure test of turbine materials in geothermal steam from a deep production well,
Hideo Kato, Koji Furuya and Mitsuo Yamashita, 2005.
ATTACHMENT
DAMAGE MECHANISM
COMPONENT
INSPECTION TECHNIQUES
Creep Fatigue Erosion Corrosion HTT VT UTG UTF PT MT ET HT REP FOT DT CA SPL
BOILER & AUXILIARIES
1. Drums
2. Steam Headers
3. Water Headers
4. Steam Piping
5. Superheater &
Reheater Tubes
7. Ductings
8. Precipitator
6. Waterwall tubes
9. Structures
TURBINE
1. Rotor
2. Shell
3. Steam Chest
4. Casing
5. Blades
6. HT Bolts
GENERATOR
1. Rotor
2. Retaining rings
Table 1: Damage mechanisms and inspection techniques for Power Plant components
LEGEND : X - APPLICABLE; HTT - High Temperature Tensile Failure; VT - Visual Inspection & Dimensional Check; UTG Ultrasonic Thickness Gauging; UTF - Ultrasonic Flaw Detection; PT - Penetrant Testing; MT - Magnetic Particle Inspection; ET Eddy Current Testing; HT - Hardness Measurement; REP - In-situ Replica Metallography; FOT Fiber optic Examination; DT Destructive Tests on Samples; CA - Chemical Analysis In-situ; SPL - Special Test Methods; a - Oxide scale measurement by
special Ultrasonic technique; b - Hydrogen damage assessment by special Ultrasonic technique; c - Boresonic Inspection; d Special Eddy Current Test of Roots
Attachment .3. Thermal Fatigue Cracking on connection between Ferritic and Austenitic
d
b
a
c
e
where :
a. Root
b. Span
c. Trailing Edge
d. Leading Edge
e. Chord
Attachment .10. picture of fan blade after cladding plat SUS 304
No
Target
Risk
source
Strategic
PS effeciency
Internal
KWh production
Internal
Finance
Cost
effectiveness
Operasional
Cooling tower
performance
Risk
High
electric
power
KWh
Productio
n
decrease
HAR cost
increase
Internal
Internal
Failure on
power
transmissi
on system
on cooling
tower fan
Maintenan
ce/
operation
difficulty
Internal
Internal
High
Vibration
Internal
Material
Corrosion
10
Cause
effect
Possibility
Rating
Effect
Rating
Risk
Level
Current increase
as addition of
plate
Kwh PS
increase
Small
Not
significant
Low
Plate cladding
moved so need
repair time.
KWh
decrease
Very small
not
significant
Low
Cost of material
procurement for
cladding
HAR cost
increase
Small
Minor
Low
Overload because
of plate adding
excess.
cooling
tower
performanc
e decrease
Very small
Minor
Low
Very small
Minor
Low
Very small
Minor
Low
Very small
Minor
Low
Immediaty part
fan blade need
long time for
procurement.
Addition of fan
blade weight
because of
unevenly
cladding
Oxidation process
on cladding
material
cooling
tower
performanc
e decrease
cooling
tower
performanc
e decrease
cooling
tower
performanc
e decrease
BIODATA
INNOVATION TEAM KAMOJANG
Name
Iim Ibrahim
Agus Witarsa
Education
STMN GARUT
ST Negeri
Bandung
Institut Teknologi
Bandung
Position
Mech. Maintenance
Technisian
Maintenance staff
supervisor
Corporate
address
PO BOX 125
GARUT, 44101
Residance
Perum.Bumi Tarogong
Komp.PLTP Kamojang
Garut
Garut
address
Bandung
! "##$
*13,%4
Interval Optimization
for Off-Line Gas Turbine Compressor Washing
Author : Suwat Wongthebbabudth
Co-Author : Pongsak Vithayakornvanich
Abstract
South Bangkok Combined Cycle Plant Block No 2, which is located at Samutprakarn
province, Thailand, has installed capacity of 618 MW. The block consists of two Gas Turbines Model
GE-PG 9311 FA. In the past, short term gas turbine efficiency improvement by Off Line Compressor
Washing had been performed every three months according to manufacturer recommendation.
Nowadays, the appropriate interval to perform this work has been adjusted. By optimizing the
benefit, power station will lose business opportunity for producing electricity by doing more frequent
washing or the power station will lose in term of compressibility because of compressor fouling, the
power stations should find their appropriate interval. In case of South Bangkok Combined Cycle
Plant Block No 2, the answer has been found and is different from the original interval
recommended by manufacturer.
1. INTRODUCTION
Gas turbine and combined cycle performance
loss during extended operational period is
largely due to compressor fouling. The rates of
both compressor fouling and performance loss
are a result of the variation in environment
conditions, fuel used, machine operating
scenario and maintenance practices. The
performance
degradation
attributed
to
compressor fouling is mainly due to deposits
formed on the compressor blades by particles
carried in by the air that are not large enough
(typically a few microns in diameter) to be
blocked by the inlet filter. These deposits result
in a reduction of compressor mass flow rate,
efficiency and pressure ratio which in turn
causes a drop in gas turbines power output
while increasing its heat rate. Performance
recovery from compressor fouling is a
recoverable degradation in that it can be
alleviated by periodic on-line and/or off-line
compressor washing. In case of on-line
compressor washing, distilled water is injected
into the compressor while the gas turbine is
running such that water droplets impact the
blades at high speed to loosen and partially
remove
deposits.
However,
complete
performance recovery can only be achieved by
an off-line compressor washing where distilled
water mixed with a special detergent is
sprayed into the gas turbine while being
rotated by the starter at the crank speed. The
performance degradation associated with hot
gas path components is influenced by several
factors such as fuel quality, number of starts,
operating scenario etc. and it is commonly
referred to as non-recoverable. The only
remedy for non-recoverable degradation is an
engine overhaul.
=1{
and
Px =
Pa
200
195
Average curve of unit A with online wash one time a week after
off-line wash 22/02/2000
190
Average curve of unit A with no online wash after off-line wash
14/09/2001
185
180
0
1000
2000
3000
4000
5000
Fired Hours
SB-CC2 may only be undertaken during offpeak periods at times to be mutually agreed.
Applicable Days
All
All
Sundays and
Declared Holidays
Monday to
Saturday exclude
Declared Holidays
Applicable
Periods
00:00 08:00
Aggregate
Hours
(Wu)
Weight
0.5
22:00 24:00
08:00 22:00
2
14
0.5
0.5
08:00 22:00
14
1.6
Minimum
cost
100
80
60
Lost cost of power
dropping
40
Deduction
20
200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000
I. Objective
This paper is written to share experience dealing with maintenance of
open cycle gas turbine frame V. Since 1976 until now, these plants still
operate well.
Gresik Power Plant has 4 open cycle gas turbines frame V, consist of:
? 2 units of open cycle gas turbine Alstom Atlantique, operated since
1976, installed capacity 20 MW,
? 2 units of open cycle gas turbine GE, operated since 1976 (became
belong to gresik power plant since 1995), installed capacity 20 MW
All gas turbines have dual fuel firing facility, HSD and Natural Gas. Because
of gas supply less, HSD is used as fuel.
II. Introduction
Open cycle gas turbines in Gresik Power Plant are very old, we cold not
do an ordinary maintenance for them, which means it is entering that period
where equipment problems will become more prevalent. (The plant is starting
to proceed to the back-end of the probability of failure bathtub curve), see
figure 1
Failure Rate
Shorten Life
Initial Failure
Random Failure
Life Prolongation
Wear-out
Failure
5%
60
%
10%
On Failure
50%
P r ed i ct i v e
Maintain Based Upon
known Condition
Fix it when it
fails
Maintenance Plan
30
%
Planned /
Preventive
30%
Desi gn
Out
Identify & design
Out root cause
of
Maintain Based
upon
Calendar
Old Method
Serious incidents/catastrophic
accident which involve multiple
equipment failures are usually the
result of bad luckor acts of God,
and are hence unmanageable
10%
2%
New Method
To a considerable extent, the likelihood of a
multiple failure is a manageable variable,
especially in protected systems
Figure 2
? On failure maintenance:
Consciously allowing equipment to run to failure. No intervention is planned
prior to failure.
? Preventive Maintenance
Preventative maintenance is defined as regularly scheduled repair of
components and equipment. It may consist of scheduled inspection, cleaning,
lubrication, parts replacement, and repair of components. Preventative
maintenance is time based intervention according to a prescribed schedule
? Predictive Maintenance
A process which requires technologies and people skills which combines and
uses all available diagnostic and performance data, maintenance histories,
operations data and design data to make timely decisions about maintenance
requirements of major / critical equipment.
? Design Out
Elimination of conditional failures through the identification of the root cause
condition that initiates the failure cycle.
By combining kind of maintenance types above, we decide the reliability
improvement sequence
Continuous Improvement
Baseline
FMEA
RCFA
Task
Identification
FDT
PM/PdM
Proactive
Plan
Schedule
Implement
Task
Measurement
Overhaul
Task Execution
Figure 3
according to the load dispatcher (PT. PLN), they are used as peak load
condition and for black start if there were black out condition in Java-Bali
power grid.
We use Computerized Maintenance Management System (CMMS,
Ellipse), condition monitoring tools and other resources to implement the
maintenance tactics, Figure 4 shows how CMMS can help PT. PJB Gresik
manages Preventive Maintenance, comparison available hour of man power
and schedule hour can be used as a resource smoothing method. Besides, it
can help us to know when maintenance of Gas turbine equipments will be
done.
Figure 4
Vibration data is taken on new and/or rebuilt machinery to ensure that the
machinery is operating within acceptable vibration tolerance. If excessive
vibration is discovered, the cause can be remedied before the equipment is
put in service
? Infrared Thermograph
Infrared surveys have a great deal of value in that production is not
compromised because, in most cases, machinery does not have to be
stopped in order to conduct a survey. In fact, when scanning electrical
components, machinery needs to be in service, and under at least 50% load
in order to detect abnormal thermal profiles. The temperature associated with
heat generation or loss can be an indication of change in the condition of an
object or machine. Faults are usually found very quickly because the data is
live
? Tribology (oil analysis)
Oil analysis is often the first technology to alert maintenance to an impending
problem. It is the only technology that can detect root causes of problems in
bearings before irrevocable damage shortens life. Used oil analysis is a
proven means of determining lubricating oil condition and monitoring machine
health. Information about oil condition is used to determine when and if the oil
should be changed. Tests measuring wear debris concentrations, types and
size distributions provide insight into machinery maintenance needs
Indicators),
here
show
comparison
between
Planned
Planned Maintenance
Unplanned Maintenace
40%
20%
0%
2001 2002 2003 2004 2005 2006 2007
Figure 5
Maintenace Cost
100%
80%
60%
Planned Maintenance
Unplanned Maintenace
40%
20%
0%
2001 2002 2003 2004 2005 2006 2007
Figure 6
Efficienc
(%
Capacity
(%)
New
Technology
Improve
100
Restore
3
C
HG
HG
Annual
Inspection
75
Rehabilitation
Recondition
50
25
2
3
4
5
6
7
Decreasing of Capacity & Efficiency of Power Plant
(Typical)
Age
Figure 7
The main things have to considered in gas turbines are hot parts, because of
operation in high temperature, more than 1000o C, and of course high cost
material. Good planning and scheduling of hot parts, when they should be
repair (recondition) or have to be replaced is very important. Both the duration
and frequency of outages are being changed to minimize this costly activity.
Outage management has two aspects: 1) reducing outage duration through
better planning and progress tracking during the outage, and 2) redistributing
maintenance tasks to non-outage times or performing those tasks less often.
Here are some equipments should be inspected carefully during outages.
Figure 9 Nozzle,
V. Conclusion
? Open cycle gas turbine in Gresik power Plant need more pay attention,
because of aging, which means it is entering that period where
equipment problems will become more prevalent.
? By optimizing the maintenance, reliability of Open cycle gas turbine can
be increased, maintenance cost can be reduced as well.
References
? Asset Management, S. Iwan Santoso, Pembangkitan Jawa Bali, 2005
? Reliability Improvement, Graham Fogel, Maintenance Total Solution, 2005
? Maintenance Optimizing Program, Pembangkitan Jawa Bali, 2004
Biographical of author
Name
Born
Education
Nationality
: Indonesia
Company
staff
of
maintenance
planning
and
controlling
? Specialist of maintenance planning and controlling
? Supervisor
of
maintenance
planning
and
controlling (2007-now)
? Electrical Engineer at annual inspection of Rabigh
Power Plant (Saudi Arabia), with PT.PJB Services
(January-March 2008)
Title of Paper : Gas Turbine Exhaust Duct Reliability Improvement; Sultan Ismail Power
Station Pakas Experience
by
Abidin Bin Sarjo (abidins@tnb.com.my)
Reliability and Engineering Department
Sultan Ismail Power Station, TNB Generation Division,
23100 Paka, Terengganu. Malaysia.
1.0 Abstract
Exhaust Duct System is an important component in combined cycle plant to divert the
exhaust from Gas Turbine either to atmosphere or into Waste Heat Boiler. Maintaining the
exhaust system structural components is rather challenging because of its exposure to a very high
temperature.
The system has been in operation for more than 20 years. The exhaust duct structure and
its surrounding components are constantly exposed to high temperature (450C 460C) and
harsh coastal environment. Over the years, this condition has affected the integrity of thermal
insulation and damaging the steel plate. Once the crack occurs on the plate, the exhaust gas will
escape into nearby field service devices and cause plant tripping. Failure of the system is one of
the major contributors to station forced outages and loss of efficiency.
Based on site observations, findings and technical evaluations using available nondestructive testing, CAD and infrared thermography, station task force had managed to come up
with ingenious modification solutions.
Currently the exhaust duct systems on all our 6 gas turbines have been reengineered and
are now performing well without any single tripping. The heat transfer efficiency has improved
tremendously with no exhaust gas leakages and failure of field service devices has been
minimized.
2.0 Background
Sultan Ismail Power Station, Paka is located in the State of Terengganu approximately
100km to the south of the state capital, Kuala Terengganu. The four combined cycle blocks, is the
first and still remains as one the largest plants of this combined-cycle type in Tenaga Nasional
were built in two phases. Phase 1 consists of 6 units of GE Fr9E Gas Turbines (GT) coupled with
6 units Waste Heat Boilers (WHB) from Stein Industrie, France and 3 units Steam Turbines (ST)
from Toshiba, Japan while Phase 2 consists of 2 units ALSTOM 13DM GT coupled with 2 unit
WHB and 1 unit ST from Ansaldo, Italy.
With a total capacity of 1,004MW (TAAC), this least-cost combined cycle power plant
operate on base load with the average capacity factor exceeding 80%.
Exhaust gas
temperatures in excess of 568 C for base load or 604 C for peak load trip the gas turbine. The detail
drawing is as follow;
Exhaust
Plenum
Transition
Duct
Low Freq.
Silencer
High Freq.
Silencer
Exhaust
Elbow
Exhaust Duct
Guillotine
Damper
Exhaust
Stack
Acess Door
Expansi
on Join
t P1
Exhau
Expan
sion Jo
st Du
ct
Acces
Door
int P2
Expan
sion Jo
To
int P3
e
Th
r
ile
Bo
Year
No of tripping
2000
2001
2002
2003
2004
2005
17
21
22
25
31
14
Station carried out regular corrective and preventive maintenance on this system
to mitigate the above tripping risk. At any GT minor inspections (Combustion and Hot Gas
Inspections), the maintenance teams will do the patching work on insulations, rewelding on the
cracking plate, repair on the silencers and any accessible damaged areas. However, the duration
of work was insufficient due to the maximum allowable time of 5 days during CI and 14 days
during HGPI were inadequate to perform comprehensive repairwork, it is just a matter of time
before cracking and leakages will recur at the other areas.
Based on stations WHY TREE analysis, it was concluded that the root cause of the
above tripping is the structural and insulation failure which lead to exhaust gas leakages. The
table below describes the conclusion of the analysis;
The leakage exhaust gas will seep through the cracking steel plate and thermal insulation
causing the above system to fail. It was one of the major contributors to station forced outages,
ST deration, heat and thermal efficiency loss. All the proposals given by various parties were
evaluated by stations task force in order to find the most suitable solution. Finally, we had
managed to come up with our own ingenious modification solutions to solve these issues.
taking thermographic imaging and heat mapping during operation. Based on that, the task force
was able to focus at the main areas as listed below;
Most cracking happened on the high stress area i.e. at all four corners, it adjacent area
and on the silencers perforated sheet. Detail inspection revealed that 80% of the steel
plates were in plastic behavior, as per the stress-strain curve in figure 6.1
The thermal insulation thickness on the power cylinder area were thinner compared to
other area
Most of the Inconnel sealing plate at flip flap damper were damaged
The ducting design of hot air blower is facing towards P2 compensator and exhaust
stack area, so most of the time these area were exposed to the hot air causing premature
failure of P2
Improvement of thermal insulations material, using more bonded type instead of normal
loose type packing
mandatory weekly progress meeting were done to manage and ensure that this project would be
completed successfully.
With high teamwork spirit, well coordinated and executed, the works were completed 2
days ahead of schedule. In order to verify the effectiveness of the repair work, thermographic
imaging was done during the commissioning of the units. Since then, our thermographic
condition monitoring team is doing regular heat mapping and will report to relevant section if any
abnormalities found. This has become part of our condition monitoring activities.
The following is sample of thermographic image taken before and after the repair work.
Fig 8.1 : Thermographic imaging on inspection door before and after repair
Gain in ST output, less heat loss since no leakages on the exhaust system. More water can
be converted to steam and flip flap dampers can be closed at all time due to improved
reliability of the power cylinder after the relocation process
Less tripping due to exhaust duct system since 2006 as per table below;
Year
No of tripping
2006
10
2007
2008 to date
Reengineering knowledge
We can develop our local vendor if we can work hand in hand with them, any problem
arise should be solved as early as possible via open minded discussion. Once contract is
sign, the owner and vendor have to work as a team, if vendor fails means the owner also
fails.
The OEM design is not perfect. If we study how the system works, we can change the
OEM design to suit our requirement. It also enhances our reengineering knowledge and
self confidence.
Managing the project with time as a major determinant, the need of full coordination is
essential. Discussion on parallel work and contingency plans with vendor is vital to
ensure project is completed within allocated time.
Total involvement of all technical staffs in the project has improved their morale and self
belonging.
11.0 Conclusions
It can be concluded that the project which were carried out in November 2004 - May
2006 was successful in term of bringing the reliability of exhaust duct system to the position
higher than what it has been intended for. The target external average temperature of 55C was
achieved by thermal insulation and structure improvements while the relocation of auxiliary
equipment, cabling and field service devices prolonged the life of the parts and avoids premature
failure. Zero tripping caused by this system since the completion of the modification and
improvement works serves as a measure of the projects success.
______________________________________________________________________________
Author Biography:
The author is an Engineer (Reliability & Engineering Gas Turbine) at Sultan Ismail
Power Station, Paka. He has been working with this combined cycle power plant since 1999.
Prior to that, he worked at conventional thermal power plant as assistance Shift Charge Engineer
at Tuanku Jaafar Power Station in Port Dickson and Technical Assistant at Sultan Salahuddin
Abdul Aziz Power Station in Kapar.
His current job involves managing day to day gas turbines reliability and engineering
issues, efficiency and heat rate improvement project, spares management, parts planning and
refurbishment works. He holds a Bachelor of Science in Mechanical Engineering from Purdue
University, USA..
References:
1. Exhaust duct work completion report for GT1A, 1B, 2A, 2B, 3A and 3B - By Vital
Equity Sdn. Bhd.
2. SDOP GT Systems, Sultan Ismail Power Station.
3. Monthly Performance Report (2000 - 2008), Sultan Ismail Power Station.
4. Tender document for exhaust duct repair work
5. XRF certification of test by TNB Research Sdn. Bhd.
6. Thermography imaging record, Sultan Ismail Power Station.
7. WHY TREE analysis document, Sultan Ismail Power Station.
8. http://www.shodor.org/~jingersoll/weave/tutorial/node4.html ; Stress strain curve
I. Objective
In this paper, we want to share our experience in the implementation of power plant
performance monitoring in Gresik Power Station. In addition, we want to share our experience
in creating a database system for operational data of power plant and implementing a
computerized model for power plant performance calculation.
II. Introduction
PJB has applied Generation Management System, a corporate integrated management system,
to manage the corporate asset and achieve the companys excellent performance. PJB believes
that implementation of the system, as described in Figure 1, will support the company to
compete in the electricity market.
The corporate performance is measured in two aspects, financial and operational aspect. The
financial aspects includes revenue and production cost, while the operational aspect includes
availability, outage and efficiency. At the end, the corporate goal is to achieve greater revenue
with lowest production cost in a low outage, high availability and efficiency. The Generation
Plan consists of some leading key performance indicators for PJB programs. Based on the
culture, experience and past management system, PJB has identified and established seven
strategic programs as the main business process. Nevertheless, these programs should be
monitored and measured to ensure that they are in alignment with the corporate goal.
The efficiency management is one of PJB strategic programs to manage, maintain and improve
the efficiency of power station. It can be carried out by implementing power plant performance
monitoring. Another program is to achieving higher power plant efficiency but it would be more
difficult and complex to be implemented. The implementation of Power Plant Performance
Monitoring in Gresik Power Station that has started since 2005 will be discussed further.
In the past, the PJB operators monitored and wrote all equipment operational data in standard
forms. Normally, they monitored data or trend on the display of data acquisition system
provided in central control room.
CCR
Monitor
New connection
to capture the
operational data
Database System
Performance Monitoring
Gresik Power Station attempted to improve its data collection by creating a database system
connected to the data acquisition system of power plant that enables the automatic acquisition
of operational data from power plant equipments. As described in Figure 3, all data displayed in
the monitor of central control room can be stored in database and processed further. Currently
there have been 14 of 20 power plants which are successfully captured, the twelve units are
combined cycled and the others are steam power plants.
Some benefits of capturing the operational data automatically are:
a. making data processing easier in the next step of performance monitoring such as daily
monitoring and heat balance calculation,
b. replacing the previous manual activity,
c. and saving some resources such as time, human, and cost.
Figure 4. An example of computerized heat balance model of Gresik Steam Power Plant
The power plant and equipments performance can be identified in a relative short time by using
the computerized models. The models were built by an external consultant that has a lot of
experiences in thermal power plant modeling. This project was a part of PJB program,
Maintenance Optimization Program, which was implemented in 2005. The implementation steps
are shown in Figure 5.
Figure 5. The implementation steps of a computerized heat balance and performance model
Later, we analyze equipments condition whether they are still in an increasing, reasonable, or
decreasing condition. The examples of performance chart as the result of computerized heat
balance model is shown in Figure 6.
LP Exhaust Dryness
1.05
1.00
0.95
0.90
0.85
100%
HPST
0.80
0.75
25Aug07
IPST
90%
25Sep07
25Oct07
25Nov07
25Dec07
25Jan08
25Feb08
25Mar08
25Apr08
25May08
25Jun08
80%
70%
60%
25Aug
25Sep
25Oct
25Nov
25Dec
25Jan
25Feb
25Mar
25Apr
25May
25Jun
Economizer
Air Heater
0.9
0.8
0.7
0.6
0.5
0.4
25Aug07
25Sep07
25Oct07
25Nov07
25Dec07
25Jan08
25Feb08
25Mar08
25Apr08
25May08
GT Compressor Efficiency
25Jun08
85.0%
84.5%
84.0%
83.5%
83.0%
82.5%
82.0%
81.5%
01Jan08
31Jan08
01Mar08
31Mar08
30Apr08
30May08
3.3. Recommendation
Based on the analysis of power plant performance, our efficiency engineers identify whether the
equipment operated efficiently or experienced degradation. Later on, some recommendations of
maintenance or operation task are commended so that the equipment can perform better or
return to its best performance. The recommendation can be in the form of a minor or major task.
A minor action can be a revised Standard Operation Procedure and/or maintenance task which
can be applied easily and soon by operator or maintenance technician. A major task requires
redesigning, detail calculation, and cost benefit analysis by a specific team.
can be solved by giving the employees conversion energy and power plant modeling training.
Moreover, the sufficient experiences to maintain and modify the computerized models are also
needed.
Apart from performance and competency, the plant performance monitoring in Gresik Power
Station also needs to be supported by good work culture such as consistency, self knowledge
improvement and vision of efficiency improvement.
V. Conclusion
The implementation of power plant performance monitoring helps plant operator or efficiency
engineer to monitor and analyze power plant performance. The execution of appropriate
recommendation in power plant performance yields high efficiency of power plant. In
conclusion, the implementation of power plant performance monitoring in Gresik Power Station
supports the corporate goal to achieve high reliability and efficiency.
References :
1. Maintenance Optimization Program, PJB, 2004
2. The Generation Management System, PJB, 2006.
3. Gate Cycle, General Electric Enter Software.
Author Biography
Name
: Teguh Handoyo
Date of Birth
: 10 February 1976
Education
Company
Gaining the Lost MW through Steam Turbine Cooling Water Intake System Improvement at Sultan
Ismail Power Station
by
Md. Yusof A. Rahman (yusofar@tnb.com.my)
Reliability and Engineering Department
Sultan Ismail Power Station, TNB Generation Division,
23100 Paka, Terengganu. Malaysia.
ABSTRACT
The steam turbine at TNB Generation Division, Sultan Ismail Power Station (SIPS), Paka,
Terengganu is a 2- Pressure Stage design and receives steam at two different pressures from the waste
heat boiler (WHB). The used steam is exhausted into condenser and then cooled by sea water
(through two underground culverts). Over the years, gradual flow restriction in the culvert (due to
marine growth) and changes to the seabed contour cause insufficient cooling water during low tide
(<0.3 meter), and subsequently leading to stations failure to meet the base load demand. In June
2006, after detailed engineering analysis and rectification works carried out, station managed to
recover the lost MW. This paper describes the rectification and improvement works undertaken by the
station in order to maintain and improve the reliability, availability and efficiency of the station.
Keywords: flow restriction, insufficient cooling water, reliability, availability and efficiency.
1.0: INTRODUCTION
Sultan Ismail Power Station (SISP), fully commissioned in 1987 is one of the TNB combined cycle
plants with 2x2x1 configuration and total plant rated capacity of 1150MW (Phase 1: 3 Blocks~900MW,
Phase 2~ 1 Block~300MW). The Phase 1 steam turbine is 2-Pressure Stage design and receives steam
at two different pressures from the waste heat boiler (WHB). The used steam is exhausted into
condenser and then cooled by sea water (through two underground culverts). Any interruption to the
main component such as the water intake, culvert and pumps will have direct impacts on plant
reliability, availability and efficiency.
Prior to 2005, the steam turbines load could not be raised to base load during low tide due to insufficient
cooling water flow (Good tide level: > 1.5m, Bad tide level < 0.3m). When this happened, the
following actions were taken by the station:
1.
Throttling the Condenser outlet valve which led to higher outfall temperature.
2.
Reducing the Steam Turbine output or even shutting one Waste Heat Boiler (Steam Turbine
running on half load) during critical situation. ( very low tide level < 0.1m)
3.
Running with only 4 cooling water pumps for 3 Steam Turbines parallel operation (normal
operation requires 5 pumps). This will result in the reduction in the vacuum and lower power
output and efficiency of the steam turbine.
In June 2006, after detailed engineering analysis and rectification works carried out, station managed
to recover the lost in steam turbine performance. This paper describes the rectification and
improvement works undertaken by the station in order to maintain and improve the reliability,
availability and efficiency of the station. The whole work scopes dealt with time factor and safety
issues which had to be managed properly in order to ensure the project was successful.
2.0:
ENGINEERING ANALYSIS
VERIFICATION
Flow restriction due to barnacle Chlorine Injection Pipe dislodged To carry out
grow up in the culvert
although Residual Chlorine reading inspection
at forebay area found normal (0.2
ppm)
Table 2.1: Extract from WHY THREE ANALYSIS (SISP Analysis Report 2005)
culvert
Inspection in January 2006 revealed the chlorine injection line in Culvert A (refer to Fig. 2.1) had
dislocated and leaked at 40 m point from the forebay. Marine growth was evident from this point on.
Inside Culvert B, the diffuser ring, which was supposed to be anchored at the bellmouth side (800 m
from the forebay), was found just 4 m from the forebay. The dislocation of this diffuser ring (chlorine
outlet) was attributed to the damages on the anchoring bolts (due to corrosion). Thus insufficient
chlorine injection into the seawater intake lines led to the uncontrolled marine growth, which reduced
the inside diameter and thus restricted the seawater flow. (refer to Fig. 2.2)
Based on the finding, the project team recommended the station to consider the following actions:
1.
To clean and remove the marine growth in the culverts and clean up the forebay.
2.
To install dedicated external chlorine injection pipe to ensure the reliability of the
chlorine injection even if the internal pipe impaired.
Figure 2.1: Cross section of Culvert A and B with existing and proposed Chlorine injection pipe
Figure 2.2: Marine Growth (Barnacles) found attached to the culverts wall.
Time and personnel safety were 2 key factors taken in consideration during project execution. To ensure
timely completion, we divided our manpower and equipment into 2 teams (on-shore and off-shore). We
started with excavating the beach for the external chlorine injection pipes installation. The pipes were
weld jointed, hydrostatic tested and secured with concrete sinker to the sea bed.
At the same time, divers started removing the barnacles in side the culvert from both ends (forebay and
bell mouth entrance) by using high pressure water jet. The debris were flushed to forebay area at the
end of the project (with Cooling Water pumps running) and collected by air lift method to the ground.
Live CCTV was made available all the time to monitor the cleaning work in the culvert by the divers
and for safety purposes.
The other activities carried out to improve cooling water supply were as follows;
After the completion of rectification and improvement works, the following improvements have been
observed: (refer to Table 2.2)
1.
The Steam Turbine can still achieve the full load capacity at low tide level and no
requirement to shutdown one unit of Waste heat Boiler during extreme low tide level.
2.
Five (5) Circulating Water pumps can be put in operation, which mean better vacuum and
steam turbine output.
3.
Out fall temperature meeting regulatory requirement of < 400C (37.40C with 5 CW pumps
running)
4.
Parameters
Average Block Load
Before cleaning
After cleaning
200 MW
254 MW
(Both GTs at minimum load ~ 62 MW, ST ~ 76
MW)
Vacuum
Start up ejector required to maintain 0.92 bar vacuum Only
main
air
(another 2 MW lost)
ejector in operation
Outfall temperature
40 deg C
38 deg C
Table 2.2: Improvement gained before and after culvert cleaning. - At the same tide level (0.3m)
4.0:
CONCLUSIONS
Cooling water system is one of the critical systems in the power plant, therefore rectification and
improvement works of the Cooling Water Intake System at SJSI, Paka is very crucial in order to
maintain and improve the efficiency, reliability and availability of the Combine Cycle operation.
Ensuring the reliability of the Electrochlorination plant, chlorine injection pipe and carrying out
scheduled internal culvert under water inspection are crucial in order to ensure no marine growth
inside the culvert. By doing so, it will certainly reduce station Unplanned Outage Rate, maintenance
cost and improve plant efficiency.
As for the way forward, Station plans to carry out sea bed contour mapping to monitor changes to
sea bed profile at the bell mouth, in order to verify the effect of break water installation by Kerteh
Port in 1995 to our Cooling Water intake system.
'
,
'
'
( #
!
"#
$%
)**+$
&'
)**) '
& - )*./ )**.$%
'
'
1
(
(
'
# $%
'
&
(
'
# #
(
$
'
'(
References:
1. Completion Report of Steam Turbine Cooling Water Intake System Improvement at Sultan
Ismail Power Station - By TNB Engineering Cooperation Sdn Bhd.
2. OJT Manual Vol. 8 (SD 13 OP 13 Circulating Water Pump), Sultan Ismail Power Station.
3. Daily Actual Station Availability: Sultan Ismail Power Station.
4. Daily Production Log sheet: Sultan Ismail Power Station.
5. Tide Tables Malaysia 2006/2007/2008 Vol. 1
Abstract
Majority performance of combustion engine including gas turbine engine are affected by combustion
process inside of the combustion chamber. Effective process of combustion, positively resulting also to
the engine performance. It is will be bring the positive implication, for the example is life time machine
become longer, economical of using material, generating power steadily, etc.
The basic problem is when the operator cannot know surely combustion status inside the chamber.
Flame monitoring which usually use the flame scanner, sometimes still has a mistake in measurement.
One of simple method in evaluating combustion process is by doing projection visualization flame to
screen (paper, etc) from sight glass at the bottom of the combustion chamber.
Approach of this method is joining the concept of fluids mechanics of combustion and heat intensity
which has been produced. Both of the things will be generate various pattern of the light in the
combustion chamber is depended from the combustion condition. This pattern will be shown at the
screen. The pattern of this light is becoming of the pre-evaluation deformation of gun burner.
Result from the calculation and experiment, making a simple method to analyze projection of
combustion light. Good combustion process light pattern will be shown in clear circle light projection
with same amount according to used amount of burner. And if that happened is contrary, it will be
shown with the hazy circle light projection. A number of circle from each burner can becoming into one
big circle, even if all gun burner has deformation, light projection only become one disguised big circle.
Inferential that the projection of combustion light through the sight glass at screen, can be used as preevaluation deformation of gun burner. The damage of the gun burner like hole deformation and others,
causing change of light combustion pattern.
Keyword : projection, combustion, pattern, deformation, gun burner
Introduction
Gas turbine is one of machine that used in
power plant. One of the positive point of this
power plant is able to generate electric power
more simple than steam turbine. It doesnt
need convert energy into another form of
energy, its only use flue gas from combustion
chamber to turn shaft turbine.
And with its compact size, usually gas turbine
does not need a larger place to install. It makes
that the gas turbine is the favorite ones.
But gas turbine also has the weakness like
another combustion engine. It is require
specifically of fuel oil and air mass flow, also its
where
= density of liquid
A2
position 1 and 2
= shear stress at the air/liquid interface
We =
AU R2 D0
L
Where
We 0.5
Z=
Re
Figure 2. Burner Layout
MMD
1
b
= a (We ) 1 +
D0
AFR
+d
We
Re 2
1+
1
AFR
Where
MMD
D0
= characteristic dimension of
AFR
2
L2
2
L1
LU A2 LU A1 = PA + Aside
a, b, c, d , e, f = empirical
constants,
And the sight glass position is above of the
combustion chamber
determined by experimental
data
In substitution,
b
L
MMD
=a
D0
AU R2 D0
MMD = a
L
AU R2
1+
1
AFR
+d
L2
1
1+
L L D0
AFR
1+
L2
1
1
b+1
D0 + d
1+
AFR
L L
AFR
In differential form
MMD
L
=a
D0
AU R2
1+
1
AFR
[b + 1]D0b
MMD
b
= kD0
D0
Combustion Chamber
Combustion chamber represents the all
important element in the gas turbine engine.
Because in combustion chamber the
combustion that produce the gas will happen to
rotate turbine shaft.
Gun burner no 1
Gun burner no 2
Gun burner no 3
...
Gun burner no 1
Gun burner no 2
Gun burner no 3
...
References
Meherwan P.Boyce Ph.D,P.E; Gas Turbine
Engineering Hand Book, Third Edition, Gulf
Professional Publishing; USA 2006
T.U. Yu, S.W. Kang and J.M. Bear; Secondary
Atomization of Coal Water Fuels For Gas
Turbine Application; MIT 1988
www.wikipedia.com
! "##$
&
Abstract
The work scope for the 5th Major Overhaul of gas turbines at Bangpakong
Power Plant Block I & II, which due to be decommissioned in May 2009, has been
drastically changed. In order to conform to the situation, maintenance work scope
needs to be tailored so that cost benefit would be achieved for the rest of power plant
operating time. Factors affecting the decision-making to determine new framework are
design data, history record of turbine blades and engine, process parameters and
special inspection. Finally, the reduction of work scope, time, expense, spare parts
help increase availability of gas turbine engine and reduce maintenance cost.
Introduction
According to the EGAT Power Development Plan (PDP 2007), all 8 units
(GT11, GT12, GT13, GT14, GT21, GT22, GT23, GT24) of the 60 MW Siemens gas
turbine model V93.2 at Bangpakong power plant are scheduled to be
decommissioned in May 2009. During April - June 2006, unit 22 was on the plan for
the fifth major overhaul and there is around 9,000 equivalent operating hours[1] left
before the unit is decommissioned. Therefore, the new framework of fifth major
overhaul had to be properly set up because of an extremely expensive hot gas parts
comparing to the others especially turbine blades considering on their complex
maintenance strategies. Reducing maintenance is time and expense saving.
From these reasons, it is necessary to take into consideration the history record
of all 8 units on turbine blades performance, design data, climate data, advanced
materials and coating and non destructive testing (NDT) for making-decision on new
framework in comply with optimized asset management methodology.
2.1
By checking the turbine blades equivalent operating hours of unit 22 since the
fourth major overhaul up to the fifth major overhaul, the equivalent operating hours is
around 23,204 hours [2] and the equivalent hours forecast is shown in Table 1 ( Red
means scrap , Yellow means continue service without refurbishment )
Table 1 shows the turbine blades equivalent hours of unit 22 from 4th M O - 5th M O
and at the time unit being decommissioned.
Table 1 shows that the equivalent operating hours of turbine blades (TMB#4,
TSB#1, TSB#3 and TSB#4) are over 100,000 hours (according to design data) [3] at
the time the units are decommissioned from the grid. General design procedures
already include safety factors, but it was necessary to consider turbine blades history
records of the above four stages.
By checking turbine blades equivalent operating hours that are over 100,000
hours, it was found that the TMB#4 of unit 24 has been brought back in continuous
service 4 times and has gained equivalent operating hours more than 140,455 hours
without refurbishment [4]. Also, the TSB#4 has been brought back in service at least
2 times without refurbishment and has gained equivalent operating hours more than
122,404 hours.[2] ( TMB means Turbine Moving Blade, TSB means Turbine Stator
Blade )
From the above information comparing to Table 1 shows that the TMB#4 and
TSB#4 have gained longer equivalent operating hours and they can be continued in
operation but they have to be inspected by NDT methods. As the TSB#1 and TSB#3
have never had the equivalent operating hours over 100,000 hours [2], they have to
be replaced.
The TMB#1-3 are new sets. Their equivalent operating hours ( from 4th major
overhaul up to decommission ) are 32,164 hours, therefore all turbine blades of 8
units have to be checked the equivalent operating hours and start-stop numbers.
Table 2 shows the operating conditions that the turbine blades equivalent operating
hours are over 32,164 hours [2] and start-stop numbers are over 323 times.
Table 2 shows the turbine blades equivalent operating hours over 32,164
hours in each major overhaul
In the past, some turbine blades have gained equivalent operating hour more
than two times. So they have opportunity to be brought back in service again.
2.2
Design Data
The general damage of hot gas parts especially turbine blades are creep, hot
corrosion and high temperature oxidation and fatigue.
2.2.1 Creep
The long term service of hot gas parts at high temperature causes
degradation of material, so they have to be refurbished before catastrophic failures
occur. But they can be in service for a while before getting serious failure as shown
in Figure 1.
Figure 1 shows operation hours at high temperature of turbine blades before failure
From the turbine blades design data at 100,000 hours reveals that the safety
factors of the TMB#1, TMB#4 and TSB#4 are quite high (>2 times) as shown in
Figure 2-4 and Table 3. [3]
2.2.3 Fatigue
Generally, the fatigue damage of turbine blades, especially stationary blades
that are frequently started and stopped, will occur from low cycle fatigue (LCF)
cracking. Table 2 shows the comparison of the start-stop numbers of unit 22 before
each major overhaul and until the unit is decommissioned from grid. The fatigue
strength safety factor of the TMB#1-4 is larger than double as shown in Figure 6.
2.3
Climate Benefit
The gas turbines are designed at an ambient temperature of 15C but the
average ambient temperature at Bangpakong power plant is around 30C. The
difference between designed and average ambient temperature is around 15C that
causes air density decreases by 5%.[5] That means the gas turbine output
decreases by 5% and this is the benefit of turbine blades especially stationary blades
which will be less damaged by downstream deflection (creep) during the unit is in
services.
2.4
2.5
Process Parameters
At present operating condition, checking on April 01, 2008 (equivalent
operating hours = 4,060 hrs, start-stop numbers = 44 times), there was no abnormal
sign during operation.[8]
2.6
After a lot of consideration and data analyzing, TMB#1-4 and TSB#4 were
brought back in service again. The remaining stages (TSB#1-3) were replaced by
new sets. Resulting in spare parts saving, work scope reduction and the availability
can be increased for 2 days.[9] This helps saving 28,733,739 baht. [10, 11]
4.
Conclusion
Bibliography
SIEMENS (V93.2) gas turbine operating data history record of unit 22 for
EGAT, Bangpakong, Thailand in June 2006.
SIEMENS (V93.2) gas turbine equivalent hours history record of all 8 units
(11,12,13,14,21,22,23,24) for EGAT, Bangpakong, Thailand in 2006.
SIEMENS (V93.2). Brief information on the gas turbine V93.2. Material of the
turbine blades and of the hot gas parts. Bangkok October 1978.
SIEMENS (V93.2) gas turbine first to fourth major overhaul maintenance report
for EGAT, Bangpakong, Thailand unit 24.
www.denysschen.com
SIEMENS (V93.2). Gas turbine maintenance seminar. Bangpakong October
1997.
SIEMENS (V93.2) gas turbine fourth major overhaul maintenance report for
EGAT, Bangpakong, Thailand unit 22.
SIEMENS (V93.2) gas turbine log sheet of operating data of unit 22 for EGAT,
Bangpakong, Thailand April 2008.
SIEMENS (V93.2) gas turbine fifth major overhaul maintenance report for
EGAT, Bangpakong, Thailand unit 22.
OEM quotation of price of TMB#1, 2005.
Non OEM quotation of price of refurbishment of TMB#2-4 and TSB#4, 2005.
AUTHORS BACKGROUND