Académique Documents
Professionnel Documents
Culture Documents
SUPREME COURT
Manila
considering that they had not yet filed their Answer. Petitioner, however,
insisted that the joint motion to dismiss is standard operating procedure in
their bank to effect a compromise and to preclude future filing of claims,
counterclaims or suits for damages.
FIRST DIVISION
G.R. No. 141968
After several demand letters and meetings with bank representatives, the
respondents Gueco spouses initiated a civil action for damages before the
Metropolitan Trial Court of Quezon City, Branch 33. The Metropolitan Trial
Court dismissed the complaint for lack of merit. 3
On appeal to the Regional Trial Court, Branch 227 of Quezon City, the
decision of the Metropolitan Trial Court was reversed. In its decision, the
RTC held that there was a meeting of the minds between the parties as to
the reduction of the amount of indebtedness and the release of the car but
said agreement did not include the signing of the joint motion to dismiss as
a condition sine qua non for the effectivity of the compromise. The court
further ordered the bank:
1. to return immediately the subject car to the appellants in good
working condition; Appellee may deposit the Manager's check - the
proceeds of which have long been under the control of the issuing
bank in favor of the appellee since its issuance, whereas the funds
have long been paid by appellants to .secure said Manager's
Check, over which appellants have no control;
2. to pay the appellants the sum of P50,000.00 as moral damages;
P25,000.00 as exemplary damages, and P25,000.00 as attorney's
fees, and
3. to pay the cost of suit.
In other respect, the decision of the Metropolitan Trial Court Branch
33 is hereby AFFIRMED.4
The case was elevated to the Court of Appeals, which on February 17,
2000, issued the assailed decision, the decretal portion of which reads:
WHEREFORE, premises considered, the petition for review on
certiorari is hereby DENIED and the Decision of the Regional Trial
Court of Quezon City, Branch 227, in Civil Case No. Q-97-31176, for
lack of any reversible error, is AFFIRMED in toto. Costs against
petitioner.
SO ORDERED.5
The Court of Appeals essentially relied on the respect accorded to the
finality of the findings of facts by the lower court and on the latter's finding
of the existence of fraud which constitutes the basis for the award of
damages.
The petitioner comes to this Court by way of petition for review
on certiorari under Rule 45 of the Rules of Court, raising the following
assigned errors:
I
THE COURT OF APPEALS ERRED IN HOLDING THAT THERE WAS NO
AGREEMENT WITH RESPECT TO THE EXECUTION OF THE JOINT
MOTION TO DISMISS AS A CONDITION FOR THE COMPROMISE
AGREEMENT.
II
THE COURT OF APPEALS ERRED IN GRANTING MORAL AND
EXEMPLARY DAMAGES AND ATTORNEY'S FEES IN FAVOR OF THE
RESPONDENTS.
III
THE COURT OF APPEALS ERRED IN HOLDING THAT THE PETITIONER
RETURN THE SUBJECT CAR TO THE RESPONDENTS, WITHOUT
MAKING ANY PROVISION FOR THE ISSUANCE OF THE NEW
MANAGER'S/CASHIER'S CHECK BY THE RESPONDENTS IN FAVOR OF
THE PETITIONER IN LIEU OF THE ORIGINAL CASHIER'S CHECK THAT
ALREADY BECAME STALE.6
As to the first issue, we find for the respondents. The issue as to what
constitutes the terms of the oral compromise or any subsequent novation
is a question of fact that was resolved by the Regional Trial Court and the
Court of Appeals in favor of respondents. It is well settled that the findings
of fact of the lower court, especially when affirmed by the Court of
Appeals, are binding upon this Court.7 While there are exceptions to this
rule,8 the present case does not fall under anyone of them, the petitioner's
claim to the contrary, notwithstanding.
The Court has noted, however, that the trial court, in its findings of
facts, clearly indicated that the agreement of the parties on August
28, 1995 was merely for the lowering of the price, hence 'xxx On August 28, 1995, bank representative Jefferson
Rivera and plaintiff entered into an oral compromise
agreement, whereby the original claim of the bank of
P184,985.09 was reduced to P150,000.00 and that upon
payment of which, plaintiff was informed that the subject
motor vehicle would be released to him.' (Rollo, p. 12)
The lower court, on the other hand, expressly made a finding that
petitioner failed to include the aforesaid signing of the Joint Motion
to Dismiss as part of the agreement. In dismissing petitioner's
claim, the lower court declared, thus:
'If it is true, as the appellees allege, that the signing of the
joint motion was a condition sine qua nonfor the reduction
of the appellants' obligation, it is only reasonable and
logical to assume that the joint motion should have been
shown to Dr. Gueco in the August 28, 1995 meeting. Why
Dr. Gueco was not given a copy of the joint motion that day
of August 28, 1995, for his family or legal counsel to see to
be brought signed, together with the P150,000.00 in
manager's check form to be submitted on the following day
on August 29, 1995? (sic) [I]s a question whereby the
answer up to now eludes this Court's comprehension. The
appellees would like this Court to believe that Dr Gueco
was informed by Mr. Rivera Rivera of the bank requirement
of signing the joint motion on August 28, 1995 but he did
not bother to show a copy thereof to his family or legal
counsel that day August 28, 1995. This part of the theory
of appellee is too complicated for any simple oral
agreement. The idea of a Joint Motion to Dismiss being
signed as a condition to the pushing through a deal
surfaced only on August 29, 1995.
'This Court is not convinced by the appellees' posturing.
Such claim rests on too slender a frame, being inconsistent
parties entering into the compromise agreement was in order that Dr.
Gueco would pay his outstanding account and in return petitioner would
return the car and drop the case for money and replevin before the
Metropolitan Trial Court. The joint motion to dismiss was but a natural
consequence of the compromise agreement and simply stated that Dr.
Gueco had fully settled his obligation, hence, the dismissal of the case.
Petitioner's act of requiring Dr. Gueco to sign the joint motion to dismiss
can not be said to be a deliberate attempt on the part of petitioner to
renege on the compromise agreement of the parties. It should, likewise, be
noted that in cases of breach of contract, moral damages may only be
awarded when the breach was attended by fraud or bad faith. 12 The law
presumes good faith. Dr. Gueco failed to present an iota of evidence to
overcome this presumption. In fact, the act of petitioner bank in lowering
the debt of Dr. Gueco from P184,000.00 to P150,000.00 is indicative of its
good faith and sincere desire to settle the case. If respondent did suffer
any damage, as a result of the withholding of his car by petitioner, he has
only himself to blame. Necessarily, the claim for exemplary damages must
fait. In no way, may the conduct of petitioner be characterized as "wanton,
fraudulent, reckless, oppressive or malevolent."13
We, likewise, find for the petitioner with respect to the third assigned error.
In the meeting of August 29, 1995, respondent Dr. Gueco delivered a
manager's check representing the reduced amount of P150,000.00. Said
check was given to Mr. Rivera, a representative of respondent bank.
However, since Dr. Gueco refused to sign the joint motion to dismiss, he
was made to execute a statement to the effect that he was withholding the
payment of the check.14 Subsequently, in a letter addressed to Ms. Desi
Tomas, vice president of the bank, dated September 4, 1995, Dr. Gueco
instructed the bank to disregard the 'hold order" letter and demanded the
immediate release of his car,15 to which the former replied that the
condition of signing the joint motion to dismiss must be satisfied and that
they had kept the check which could be claimed by Dr. Gueco
anytime.16 While there is controversy as to whether the document
evidencing the order to hold payment of the check was formally offered as
evidence by petitioners,17 it appears from the pleadings that said check has
not been encashed.
The decision of the Regional Trial Court, which was affirmed in toto by the
Court of Appeals, orders the petitioner:
1. to return immediately the subject car to the appellants in good
working condition. Appellee may deposit the Manager's Check - the
proceeds of which have long been under the control of the issuing
bank in favor of the appellee since its issuance, whereas the funds
CARPIO-MORALES, J.:
On petition for review is the June 27, 2001 Decision 1 of the Court of
Appeals, as well as its Resolution 2 dated September 28, 2001 denying the
motion for reconsideration, which affirmed that of Branch 21 of the
Regional Trial Court (RTC) of Manila in Civil Case No. 92-631323 holding
petitioner Schmitz Transport Brokerage Corporation (Schmitz Transport),
together with Black Sea Shipping Corporation (Black Sea), represented by
its ship agent Inchcape Shipping Inc. (Inchcape), and Transport Venture
(TVI), solidarily liable for the loss of 37 hot rolled steel sheets in coil that
were washed overboard a barge.
On September 25, 1991, SYTCO Pte Ltd. Singapore shipped from the port of
Ilyichevsk, Russia on board M/V "Alexander Saveliev" (a vessel of Russian
registry and owned by Black Sea) 545 hot rolled steel sheets in coil
weighing 6,992,450 metric tons.
At around 5:30 a.m. of October 27, 1991, due to strong waves, 11 the crew
of the barge abandoned it and transferred to the vessel. The barge pitched
and rolled with the waves and eventually capsized, washing the 37 coils
into the sea.12 At 7:00 a.m., a tugboat finally arrived to pull the already
empty and damaged barge back to the pier.13
Earnest efforts on the part of both the consignee Little Giant and Industrial
Insurance to recover the lost cargoes proved futile.14
Little Giant thus filed a formal claim against Industrial Insurance which paid
it the amount of P5,246,113.11. Little Giant thereupon executed a
subrogation receipt15 in favor of Industrial Insurance.
Industrial Insurance later filed a complaint against Schmitz Transport, TVI,
and Black Sea through its representative Inchcape (the defendants) before
the RTC of Manila, for the recovery of the amount it paid to Little Giant plus
adjustment fees, attorneys fees, and litigation expenses. 16
The vessel arrived at the port of Manila on October 24, 1991 and the
Philippine Ports Authority (PPA) assigned it a place of berth at the outside
breakwater at the Manila South Harbor.6
By Decision of November 24, 1997, Branch 21 of the RTC held all the
defendants negligent for unloading the cargoes outside of the breakwater
notwithstanding the storm signal.18 The dispositive portion of the decision
reads:
(2) If there was negligence, whether liability for the loss may attach to
Black Sea, petitioner and TVI.
When a fortuitous event occurs, Article 1174 of the Civil Code absolves any
party from any and all liability arising therefrom:
ART. 1174. Except in cases expressly specified by the law, or when it is
otherwise declared by stipulation, or when the nature of the obligation
requires the assumption of risk, no person shall be responsible for those
events which could not be foreseen, or which though foreseen, were
inevitable.
In order, to be considered a fortuitous event, however, (1) the cause of the
unforeseen and unexpected occurrence, or the failure of the debtor to
comply with his obligation, must be independent of human will; (2) it must
be impossible to foresee the event which constitute the caso fortuito, or if
it can be foreseen it must be impossible to avoid; (3) the occurrence must
be such as to render it impossible for the debtor to fulfill his obligation in
any manner; and (4) the obligor must be free from any participation in the
aggravation of the injury resulting to the creditor.32
[T]he principle embodied in the act of God doctrine strictly requires that
the act must be occasioned solely by the violence of nature. Human
intervention is to be excluded from creating or entering into the cause of
the mischief. When the effect is found to be in part the result of the
participation of man, whether due to his active intervention or neglect or
failure to act, the whole occurrence is then humanized and removed from
the rules applicable to the acts of God.33
The appellate court, in affirming the finding of the trial court that human
intervention in the form of contributory negligence by all the defendants
resulted to the loss of the cargoes,34 held that unloading outside the
breakwater, instead of inside the breakwater, while a storm signal was up
constitutes negligence.35 It thus concluded that the proximate cause of the
loss was Black Seas negligence in deciding to unload the cargoes at an
unsafe place and while a typhoon was approaching. 36
From a review of the records of the case, there is no indication that there
was greater risk in loading the cargoes outside the breakwater. As the
defendants proffered, the weather on October 26, 1991 remained normal
with moderate sea condition such that port operations continued and
proceeded normally.37
The weather data report,38 furnished and verified by the Chief of the
Climate Data Section of PAG-ASA and marked as a common exhibit of the
parties, states that while typhoon signal No. 1 was hoisted over Metro
Manila on October 23-31, 1991, the sea condition at the port of Manila at
5:00 p.m. - 11:00 p.m. of October 26, 1991 was moderate. It cannot,
therefore, be said that the defendants were negligent in not unloading the
cargoes upon the barge on October 26, 1991 inside the breakwater.
That no tugboat towed back the barge to the pier after the cargoes were
completely loaded by 12:30 in the morning39 is, however, a material fact
which the appellate court failed to properly consider and appreciate40 the
proximate cause of the loss of the cargoes. Had the barge been towed
back promptly to the pier, the deteriorating sea conditions
notwithstanding, the loss could have been avoided. But the barge was left
floating in open sea until big waves set in at 5:30 a.m., causing it to sink
along with the cargoes.41 The loss thus falls outside the "act of God
doctrine."
The proximate cause of the loss having been determined, who among the
parties is/are responsible therefor?
Contrary to petitioners insistence, this Court, as did the appellate court,
finds that petitioner is a common carrier. For it undertook to transport the
cargoes from the shipside of "M/V Alexander Saveliev" to the consignees
warehouse at Cainta, Rizal. As the appellate court put it, "as long as a
person or corporation holds [itself] to the public for the purpose of
transporting goods as [a] business, [it] is already considered a common
carrier regardless if [it] owns the vehicle to be used or has to hire
one."42 That petitioner is a common carrier, the testimony of its own VicePresident and General Manager Noel Aro that part of the services it offers
to its clients as a brokerage firm includes the transportation of cargoes
reflects so.
Atty. Jubay: Will you please tell us what [are you] functions x x x as
Executive Vice-President and General Manager of said Company?
Mr. Aro: Well, I oversee the entire operation of the brokerage and transport
business of the company. I also handle the various division heads of the
company for operation matters, and all other related functions that the
President may assign to me from time to time, Sir.
A: We utilized of (sic) our own trucks and we have some other contracted
trucks, Sir.
As for petitioners argument that being the agent of Little Giant, any
negligence it committed was deemed the negligence of its principal, it
does not persuade.
xxx
ATTY. JUBAY: Will you please explain to us, to the Honorable Court why is it
you have to contract for the barges of Transport Ventures Incorporated in
this particular operation?
A: Firstly, we dont own any barges. That is why we hired the services of
another firm whom we know [al]ready for quite sometime, which is
Transport Ventures, Inc. (Emphasis supplied) 43
It is settled that under a given set of facts, a customs broker may be
regarded as a common carrier. Thus, this Court, in A.F. Sanchez Brokerage,
Inc. v. The Honorable Court of Appeals,44 held:
The appellate court did not err in finding petitioner, a customs broker, to be
also a common carrier, as defined under Article 1732 of the Civil Code, to
wit,
Art. 1732. Common carriers are persons, corporations, firms or associations
engaged in the business of carrying or transporting passengers or goods or
both, by land, water, or air, for compensation, offering their services to the
public.
xxx
Article 1732 does not distinguish between one whose principal business
activity is the carrying of goods and one who does such carrying only as an
ancillary activity. The contention, therefore, of petitioner that it is not a
common carrier but a customs broker whose principal function is to
prepare the correct customs declaration and proper shipping documents as
required by law is bereft of merit. It suffices that petitioner undertakes to
deliver the goods for pecuniary consideration.45
And in Calvo v. UCPB General Insurance Co. Inc.,46 this Court held that as
the transportation of goods is an integral part of a customs broker, the
customs broker is also a common carrier. For to declare otherwise "would
be to deprive those with whom [it] contracts the protection which the law
affords them notwithstanding the fact that the obligation to carry goods for
[its] customers, is part and parcel of petitioners business." 47
True, petitioner was the broker-agent of Little Giant in securing the release
of the cargoes. In effecting the transportation of the cargoes from the
shipside and into Little Giants warehouse, however, petitioner was
discharging its own personal obligation under a contact of carriage.
Petitioner, which did not have any barge or tugboat, engaged the services
of TVI as handler48 to provide the barge and the tugboat. In their Service
Contract,49 while Little Giant was named as the consignee, petitioner did
not disclose that it was acting on commission and was chartering the
vessel for Little Giant.50 Little Giant did not thus automatically become a
party to the Service Contract and was not, therefore, bound by the terms
and conditions therein.
Not being a party to the service contract, Little Giant cannot directly sue
TVI based thereon but it can maintain a cause of action for negligence.51
In the case of TVI, while it acted as a private carrier for which it was under
no duty to observe extraordinary diligence, it was still required to observe
ordinary diligence to ensure the proper and careful handling, care and
discharge of the carried goods.
Thus, Articles 1170 and 1173 of the Civil Code provide:
ART. 1170. Those who in the performance of their obligations are guilty of
fraud, negligence, or delay, and those who in any manner contravene the
tenor thereof, are liable for damages.
ART. 1173. The fault or negligence of the obligor consists in the omission of
that diligence which is required by the nature of the obligation and
corresponds with the circumstances of the persons, of the time and of the
place. When negligence shows bad faith, the provisions of articles 1171
and 2202, paragraph 2, shall apply.
If the law or contract does not state the diligence which is to be observed
in the performance, that which is expected of a good father of a family
shall be required.
Was the reasonable care and caution which an ordinarily prudent person
would have used in the same situation exercised by TVI? 52
same act or omission causes the injury, one resulting in culpa contractual
and the other in culpa aquiliana, Article 2194 of the Civil Code can well
apply. In fine, a liability for tort may arise even under a contract, where tort
is that which breaches the contract. Stated differently, when an act which
constitutes a breach of contract would have itself constituted the source of
a quasi-delictual liability had no contract existed between the parties, the
contract can be said to have been breached by tort, thereby allowing the
rules on tort to apply.57
As for Black Sea, its duty as a common carrier extended only from the time
the goods were surrendered or unconditionally placed in its possession and
received for transportation until they were delivered actually or
constructively to consignee Little Giant.58
Parties to a contract of carriage may, however, agree upon a definition of
delivery that extends the services rendered by the carrier. In the case at
bar, Bill of Lading No. 2 covering the shipment provides that delivery be
made "to the port of discharge or so near thereto as she may safely get,
always afloat."59 The delivery of the goods to the consignee was not from
"pier to pier" but from the shipside of "M/V Alexander Saveliev" and into
barges, for which reason the consignee contracted the services of
petitioner. Since Black Sea had constructively delivered the cargoes to
Little Giant, through petitioner, it had discharged its duty. 60
In fine, no liability may thus attach to Black Sea.
Respecting the award of attorneys fees in an amount over P1,000,000.00
to Industrial Insurance, for lack of factual and legal basis, this Court sets it
aside. While Industrial Insurance was compelled to litigate its rights, such
fact by itself does not justify the award of attorneys fees under Article
2208 of the Civil Code. For no sufficient showing of bad faith would be
reflected in a partys persistence in a case other than an erroneous
conviction of the righteousness of his cause. 61 To award attorneys fees to a
party just because the judgment is rendered in its favor would be
tantamount to imposing a premium on ones right to litigate or seek
judicial redress of legitimate grievances.62
On the award of adjustment fees: The adjustment fees and expense of
divers were incurred by Industrial Insurance in its voluntary but
unsuccessful efforts to locate and retrieve the lost cargo. They do not
constitute actual damages.63
As for the court a quos award of interest on the amount claimed, the same
calls for modification following the ruling in Eastern Shipping Lines, Inc. v.
Court of Appeals64 that when the demand cannot be reasonably
established at the time the demand is made, the interest shall begin to run
not from the time the claim is made judicially or extrajudicially but from
the date the judgment of the court is made (at which the time the
quantification of damages may be deemed to have been reasonably
ascertained).65
WHEREFORE, judgment is hereby rendered ordering petitioner Schmitz
Transport & Brokerage Corporation, and Transport Venture Incorporation
jointly and severally liable for the amount of P5,246,113.11 with the
MODIFICATION that interest at SIX PERCENT per annum of the amount due
should be computed from the promulgation on November 24, 1997 of the
decision of the trial court.
Costs against petitioner.
SO ORDERED.
Decision1 dated February 25, 1998 of the Court of Appeals (CA) in CA-GR
CV No. 52660, affirming, with modification, an earlier decision of the
Regional Trial Court at Makati, Branch 146, in an action for annulment of
deeds of sale thereat instituted by petitioner against the Presidential
Commission for Good
Government (PCGG) and the herein private respondent, Liwayway
Publishing, Inc.
As found by the appellate court in the decision under review, the facts are:
xxx [Petitioner] . . . is a domestic corporation engaged in the publication of
Philippine Free Press Magazine, one of the . . . widely circulated political
magazines in the Philippines. Due to its wide circulation, the publication of
the Free Press magazine enabled [petitioner] to attain considerable
prestige prior to the declaration of Martial Law as well as to achieve a high
profit margin. . . .
On separate occasions in 1973, Locsin, Sr. was approached by the late Atty.
Crispin Baizas with offers from then President Marcos for the acquisition of
the [petitioner]. However, Locsin, Sr. refused the offer stating that
[petitioner] was not for sale (TSN, 2 May 1988, pp. 8-9, 40; 27 May 1993,
pp. 66-67).
the building, the machineries, the office furnishing and the fixtures of the
[petitioner] on a "take-it-or-leave-it" basis (TSN, 2 May 1988, pp.42-43; 27
May 1993, p. 88).
On August 22, 1973, Menzi tendered to Locsin, Sr. a check for One Million
(P1, 000,000.00) Pesos downpayment for the sale, . . . Locsin, Sr. accepted
the check, subject to the condition that he will refund the same in case the
sale will not push through. (Exh. 7).
On August 23, 1973, the Board of Directors of [petitioner] held a meeting
and reluctantly passed a resolution authorizing Locsin, Sr. to sell the assets
of the [petitioner] to Menzi minus the name "Philippine Free Press (Exhs. A1 and 1; TSN, 27 May 1993, pp. 73-76).
Locsin, Sr. thereafter used the proceeds of the sale to pay the separation
pay of [petitioners] employees, buy out the shares of the minority
stockholders as well as to settle all its obligations.
II
xxx IN CONCLUDING THAT THE UNDISPUTED FACTS AND CIRCUMSTANCES
PRECEDING THE EXECUTION OF THE CONTRACTS OF SALE FOR THE
PETITIONER'S PROPERTIES DID NOT ESTABLISH THE FORCE, INTIMIDATION,
DURESS AND UNDUE INFLUENCE WHICH VITIATED PETITIONER'S CONSENT.
A. xxx IN CONSIDERING AS HEARSAY THE TESTIMONIAL EVIDENCE WHICH
CLEARLY ESTABLISHED THE THREATS MADE UPON PETITIONER AND THAT
RESPONDENT LIWAYWAY WILL BE USED AS THE CORPORATE VEHICLE FOR
THE FORCED ACQUISITION OF PETITIONER'S PROPERTIES.
B. xxx IN CONCLUDING THAT THE ACTS OF THEN PRESIDENT MARCOS
DURING MARTIAL LAW DID NOT CONSTITUTE THE FORCE, INTIMIDATION,
DURESS AND UNDUE INFLUENCE WHICH VITIATED PETITIONER'S CONSENT.
[DBP] vs. Pundogar4, the 4-year prescriptive period for the annulment of
the aforesaid deeds ended "in late 1977", doubtless suggesting that
petitioners right to seek such annulment accrued four (4) years earlier, a
starting time-point corresponding, more or less, to the date of the
conveying deed, i.e., October 23, 1973. Petitioner contends, however, that
the 4-year prescriptive period could not have commenced to run on
October 23, 1973, martial law being then in full swing. Plodding on,
petitioner avers that the continuing threats on the life of Mr. Teodoro
Locsin, Sr. and his family and other menacing effects of martial law which
should be considered as force majeure - ceased only after the February 25,
1986 People Power uprising.
Petitioner instituted its complaint for annulment of contracts on February
26, 1987. The question that now comes to the fore is: Did the 4-year
prescriptive period start to run in late October 1973, as postulated in the
decision subject of review, or on February 25, 1986, as petitioner argues,
on the theory that martial law has the effects of aforce majeure5, which, in
turn, works to suspend the running of the prescriptive period for the main
case filed with the trial court.
Petitioner presently faults the Court of Appeals for its misapplication of the
doctrinal rule laid down in DBP vs. Pundogar6 where this Court, citing and
quoting excerpts from the ruling in Tan vs. Court of Appeals 7, as reiterated
in National Development Company vs. Court of Appeals, 8 wrote
We can not accept the petitioners contention that the period during which
authoritarian rule was in force had interrupted prescription and that the
same began to run only on February 25, 1986, when the Aquino
government took power. It is true that under Article 1154 [of the Civil
Code] xxx fortuitous events have the effect of tolling the period of
prescription. However, we can not say, as a universal rule, that the period
from September 21, 1972 through February 25, 1986 involves a force
majeure. Plainly, we can not box in the "dictatorial" period within the term
without distinction, and without, by necessity, suspending all liabilities,
however demandable, incurred during that period, including perhaps those
ordered by this Court to be paid. While this Court is cognizant of acts of the
last regime, especially political acts, that might have indeed precluded the
enforcement of liability against that regime and/or its minions, the Court is
not inclined to make quite a sweeping pronouncement, . . . . It is our
opinion that claims should be taken on a case-to-case basis. This selective
rule is compelled, among others, by the fact that not all those imprisoned
or detained by the past dictatorship were true political oppositionists, or,
for that matter, innocent of any crime or wrongdoing. Indeed, not a few of
Given the foregoing perspective, the Court is not prepared to disturb the
ensuing ruling of the appellate court on the effects of martial law on
petitioners right of action:
In their testimonies before the trial court, both Locsin, Sr. and Locsin, Jr.
claimed that they had not filed suit to recover the properties until 1987 as
they could not expect justice to be done because according to them,
Marcos controlled every part of the government, including the courts, (TSN,
2 May 1988, pp. 23-24; 27 May 1993, p. 121). While that situation may
have obtained during the early years of the martial law administration, We
could not agree with the proposition that it remained consistently
unchanged until 1986, a span of fourteen (14) years. The unfolding of
subsequent events would show that while dissent was momentarily stifled,
it was not totally silenced. On the contrary, it steadily simmered and
smoldered beneath the political surface and culminated in that groundswell
of popular protest which swept the dictatorship from power. 13
The judiciary too, as an institution, was no ivory tower so detached from
the ever changing political climate. While it was not totally impervious to
the influence of the dictatorships political power, it was not hamstrung as
to render it inutile to perform its functions normally. To say that the
Judiciary was not able to render justice to the persons who sought redress
before it . . . during the Martial Law years is a sweeping and unwarranted
generalization as well as an unfounded indictment. The Judiciary, . . . did
not lack in gallant jurists and magistrates who refused to be cowed into
silence by the Marcos administration. Be that as it may, the Locsins
mistrust of the courts and of judicial processes is no excuse for their nonobservance of the prescriptive period set down by law.
Corollary to the presented issue of prescription of action for annulment of
contract voidable on account of defect of consent14 is the question of
whether or not duress, intimidation or undue influence vitiated the
petitioners consent to the subject contracts of sale. Petitioner delves at
length on the vitiation issue and, relative thereto, ascribes the following
errors to the appellate court: first, in considering as hearsay the
testimonial evidence that may prove the element of "threat" against
petitioner or Mr. Locsin, Sr., and the dictatorial regime's use of private
respondent as a corporate vehicle for forcibly acquiring petitioners
properties; second, in concluding that the acts of then President Marcos
during the martial law years did not have a consent-vitiating effect on
petitioner; andthird, in resolving the case on the basis of mere surmises
and speculations.
Article 1470. Gross inadequacy of price does not affect a contract of sale,
except as it may indicate a defect in the consent, or that the parties really
intended a donation or some other act or contract.
Following the aforequoted codal provision, it behooves petitioner to first
prove "a defect in the consent", failing which its case for annulment
contract of sale on ground gross inadequacy of price must fall. The
categorical conclusion of the Court of Appeals, confirmatory of that of the
trial court, is that the price paid for the Free Pressoffice building, and other
physical assets is not unreasonable to justify the nullification of the sale.
This factual determination, predicated as it were on offered evidence,
notably petitioners Balance Sheet as of November 30, 1972 (Exh. 13),
must be accorded great weight if not finality.32
In the light of the foregoing disquisition, the question of whether or not
petitioners undisputed utilization of the proceeds of the sale constitutes,
within the purview of Article 1393 of the Civil Code, 33 implied ratification of
the contracts of sale need not detain us long. Suffice it to state in this
regard that the ruling of the Court of Appeals on the matter is well-taken.
Wrote the appellate court: 34
In the case at bench, Free Presss own witnesses admitted that the
proceeds of the 1973 sale were used to settle the claims of its employees,
redeem the shares of its stockholders and finance the companys entry into
money-market shareholdings and fishpond business activities (TSN, 2 May
1988, pp. 16, 42-45). It need not be overemphasized that by using the
proceeds in this manner, Free Press only too clearly confirmed the
voluntaries of its consent and ratified the sale. Needless to state, such
ratification cleanses the assailed contract from any alleged defects from
the moment it was constituted (Art. 1396, Civil Code).
Petitioners posture that its use of the proceeds of the sale does not
translate to tacit ratification of what it viewed as voidable contracts of sale,
such use being a "matter of [its financial] survival",35 is untenable. As
couched, Article 1393 of the Civil Code is concerned only with the act
which passes for ratification of contract, not the reason which actuated the
ratifying person to act the way he did. "Ubi lex non distinguit nec nos
distinguere debemus. When the law does not distinguish, neither should
we". 36
Finally, petitioner would fault the Court of Appeals for excluding Exhibits
"X-6" to "X-7" and "Y-3" (proffer). These excluded documents which were
apparently found in the presidential palace or turned over by the US
Government to the PCGG, consist of, among others, what appears to be
Under the terms of the Loan Agreement, the proceeds of the loan were to
be released on staggered basis. Interest on the loan was pegged at sixteen
(16%) percent per annum based on the diminishing balance. The loan was
payable in thirty-six (36) equal and consecutive monthly amortizations to
commence at the beginning of the thirteenth month from the date of the
first release in accordance with the Schedule of Amortization. 5 In case of
default, an acceleration clause was, among others, provided and the
amount due was made subject to a twenty (20%) percent one-time penalty
on the amount due and such amount shall bear interest at the highest rate
permitted by law from the date of default until full payment thereof plus
liquidated damages at the rate of two (2%) percent per month
compounded quarterly on the unpaid balance and accrued interests
together with all the penalties, fees, expenses or charges thereon until the
unpaid balance is fully paid, plus attorney's fees equivalent to twenty-five
(25%) percent of the sum sought to be recovered, which in no case shall be
less than Twenty Thousand Pesos (P20,000.00) if the services of a lawyer
were hired.6
In accordance with the terms of the Loan Agreement, respondent Este del
Sol executed several documents7 as security for payment, among them, (a)
a Real Estate Mortgage dated January 31, 1978 over two (2) parcels of land
being utilized as the site of its development project with an area of
approximately One Million Twenty-Eight Thousand and Twenty-Nine
PARTICULARS
AMO
P7,999,63
327,09
Balance
8,326,72
1,665,34
1,481,87
1,200,71
4,96
P12,679,63
the publication of the Sheriff's Notice of Sale, Four Thousand Nine Hundred
Sixty-Four Pesos (P4,964.00); for Sheriff's fees for conducting the
foreclosure proceedings, Fifteen Thousand Pesos (P15,000.00); and for
Attorney's fees, Three Million One Hundred Sixty-Eight Thousand Six
Hundred Sixty-Six Pesos and Seventy-Five Centavos (P3,168,666.75). The
remaining balance of Five Million Eight Hundred Eleven Thousand Three
Hundred Sixty-Nine Pesos and Twenty-Five Centavos (P5,811,369.25) was
applied to interests and penalty charges and partly against the principal,
due as of June 23, 1980, thereby leaving a balance of Six Million Eight
Hundred Sixty-Three Thousand Two Hundred Ninety-Seven Pesos and
Seventy-Three Centavos (P6,863,297.73) on the principal amount of the
loan as of June 23, 1980.13
Failing to secure from the individual respondents, as sureties of the loan of
respondent Este del Sol by virtue of their continuing surety agreements,
the payment of the alleged deficiency balance, despite individual demands
sent to each of them,14 petitioner instituted on November 11, 1980 the
instant collection suit15 against the respondents to collect the alleged
deficiency balance of Six Million Eight Hundred Sixty-Three Thousand Two
Hundred Ninety-Seven Pesos and Seventy-Three Centavos (P6,863,297.73)
plus interest thereon at twenty-one (21%) percent per annum from June
24, 1980 until fully paid, and twenty-five (25%) percent thereof as and for
attorney's fees and costs.
In their Answer, the respondents sought the dismissal of the case and set
up several special and affirmative defenses, foremost of which is that the
Underwriting and Consultancy Agreements executed simultaneously with
and as integral parts of the Loan Agreement and which provided for the
payment of Underwriting, Consultancy and Supervision fees were in reality
subterfuges resorted to by petitioner FMIC and imposed upon respondent
Este del Sol to camouflage the usurious interest being charged by
petitioner FMIC.16
The petitioner FMIC presented as its witnesses during the trial: Cesar
Valenzuela, its former Senior Vice-President, Felipe Neri, its Vice-President
for Marketing, and Dennis Aragon, an Account Manager of its Account
Management Group, as well as documentary evidence. On the other hand,
co-respondents Vicente M. De Vera, Jr. and Valentin S. Daez, Jr., and
Perfecto Doroja, former Senior Manager and Assistant Vice-President of
FMIC, testified for the respondents.
After the trial, the trial court rendered its decision in favor of petitioner
FMIC, the dispositive portion of which reads:
WHEREFORE, judgment is hereby rendered in favor of plaintiff and
against defendants, ordering defendants jointly and severally to
pay to plaintiff the amount of P6,863,297.73 plus 21% interest per
annum, from June 24, 1980, until the entire amount is fully paid,
Principal of Loan
Deficiency
P7,382,500.00
1,476,500.00
900,000.00 P9,759,000.00
9,000,000.00
P759,000.00
P 200,000.00
200,000.00
1,330,000.00
P1,730,000.00
After a careful and thorough review of the record including the evidence
adduced, we find no reason to depart from the findings of the appellate
court.
exception.24 The form of the contract is not conclusive for the law will not
permit a usurious loan to hide itself behind a legal form. Parol evidence is
admissible to show that a written document though legal in form was in
fact a device to cover usury. If from a construction of the whole transaction
it becomes apparent that there exists a corrupt intention to violate the
Usury Law, the courts should and will permit no scheme, however
ingenious, to becloud the crime of usury.25
In the instant case, several facts and circumstances taken altogether show
that the Underwriting and Consultancy Agreements were simply cloaks or
devices to cover an illegal scheme employed by petitioner FMIC to conceal
and collect excessively usurious interest, and these are:
f) Petitioner FMIC failed to comply with its obligation under the Consultancy
Agreement,40 aside from the fact that there was no need for a Consultancy
Agreement, since respondent Este del Sol's officers appeared to be more
competent to be consultants in the development of the projected
sports/resort complex.41
All the foregoing established facts and circumstances clearly belie the
contention of petitioner FMIC that the Loan, Underwriting and Consultancy
Agreements are separate and independent transactions. The Underwriting
and Consultancy Agreements which were executed and delivered
contemporaneously with the Loan Agreement on January 31, 1978 were
exacted by petitioner FMIC as essential conditions for the grant of the loan.
An apparently lawful loan is usurious when it is intended that additional
compensation for the loan be disguised by an ostensibly unrelated contract
providing for payment by the borrower for the lender's services which are
of little value or which are not in fact to be rendered, such as in the instant
case.42 In this connection, Article 1957 of the New Civil Code clearly
provides that:
Art. 1957. Contracts and stipulations, under any cloak or device
whatever, intended to circumvent the laws against usury shall be
void. The borrower may recover in accordance with the laws on
usury.
In usurious loans, the entire obligation does not become void because of
an agreement for usurious interest; the unpaid principal debt still stands
and remains valid but the stipulation as to the usurious interest is void,
consequently, the debt is to be considered without stipulation as to the
interest.43 The reason for this rule was adequately explained in the case
of Angel Jose Warehousing Co., Inc. v. Chelda Enterprises 44 where this Court
held:
In simple loan with stipulation of usurious interest, the prestation of
the debtor to pay the principal debt, which is the cause of the
contract (Article 1350, Civil Code), is not illegal. The illegality lies
only as to the prestation to pay the stipulated interest; hence,
being separable, the latter only should be deemed void, since it is
the only one that is illegal.
Thus, the nullity of the stipulation on the usurious interest does not affect
the lender's right to receive back the principal amount of the loan. With
respondents. Whether the exact amount of the relief was not expressly
prayed for is of no moment for the reason that the relief was plainly
warranted by the allegations of the respondents as well as by the facts as
found by the appellate court. A party is entitled to as much relief as the
facts may warrant 47
In view of all the foregoing, the Court is convinced that the appellate court
committed no reversible error in its challenged Decision.
WHEREFORE, the instant petition is hereby DENIED, and the assailed
Decision of the Court of Appeals is AFFIRMED. Costs against petitioner.
SO ORDERED.
As Josephine and her husband Ferdinand Aguilar (the Aguilars) were being
made to sign by the two representatives a promissory note, chattel
mortgage, disclosures and other documents the dates of which were left
blank and which showed that they would still be obliged to pay on
installment in 12 months for the car even if checks in full payment thereof
in 90 days were to be issued, the two replied that it was only for formality,
for in case the checks were not cleared, the documents would take effect,
otherwise they would be cancelled.2
The Aguilars did sign the promissory note3 binding them to be jointly and
severally liable to World Cars in the amount of P301,992.00, payable in 12
months, with a monthly amortization of P25,166.00 and a late payment
charge of 5% per month on each unpaid installment from due date until
fully paid.
By Josephines claim, at the time she and her husband signed the
promissory note, its date, May 30, 1992, and the due date of the monthly
amortization which was agreed to be every 3rd day of each month starting
July 1992 were not reflected therein.4
The Aguilars did execute too a chattel mortgage5 in favor of World Cars
which embodied a deed of assignment6 in favor of Citytrust Finance
Corporation (Citytrust).7 Again by Josephines claim, the date May 30, 1992
appearing in the chattel mortgage cum deed of assignment was not yet
filled up at the time she and her husband signed it. 8
After the Aguilars signing of the documents, Perez asked Josephine to
make the check payments payable to him, prompting her to call up Perezs
boss, a certain Lily Paloma, to inquire whether Perez could collect payment
to which Lily replied in the affirmative, the latter advising her to just secure
a receipt.9
Josephine thus issued four Far East Bank and Trust Company (FEBTC)
checks, the details of which are indicated below:
Check No.
Payable to
Amount
Dated
11270310
Joselito Perez
P148,000.00
11270411
World Cars
P16,000.00
11270512
Joselito Perez
P111,000.00
112706
Joselito Perez
P111,000.00
For Check Nos. 112703, 112705, and 112706 which were made payable to
Perez in the total amount ofP370,000.00, Perez issued Josephine World
Cars Provisional Receipt No. 5965.13 Check No. 112704 which was made
payable to World Cars represented payment of the premium on the car
insurance, secured from Dominion Insurance which issued a policy in the
name of Josephine.14
Josephine at once informed Ana Marie that she had fully paid the car to
which Ana Marie replied that "maybe not all of the papers have been
processed yet," hence, she advised Josephine not to worry about it. 29
xxx
Josephine again called Ana Marie inquiring what was going on and the
latter replied that no payment for the car had been received. Josephine
also called up World Cars and spoke to its Vice-President, a certain
Domondon, who informed her that based on company records, the last
payment had not been received.31
The spouses Aguilar thus filed a complaint32 for "annulment of chattel
mortgage plus damages" against Citytrust and World Cars before the
Regional Trial Court (RTC) of Quezon City.
In its Answer with Counterclaims and Crossclaim against World
Cars,33 Citytrust disclaimed knowledge of the alleged prior arrangement
and the alleged subsequent payments made by the Aguilars to World Cars.
And it claimed that it accepted the endorsement and assignment of the
promissory note and chattel mortgage in good faith, relying on the terms
and conditions thereof; and that assuming that the Aguilars claim were
true, World Cars appeared to have violated the terms and conditions of the
Receivables Financing Agreement (RFA) it executed with it, the pertinent
portions of which read:34
Citytrust prayed in its Crossclaim against World Cars that "in the remote
event that the complaint is not dismissed . . . [World Cars] be ordered to
pay all and whatever unpaid obligation due to [it] arising from [the]
promissory note . . ."35
In its Answer with Counterclaim,36 World Cars claimed that, among other
things, it received only the check in the amount of P148,000.00 (Check No.
112703 payable to Perez) as downpayment for the car; and that the
Aguilars defaulted in the payment of their monthly amortizations to
Citytrust, and it should not be held accountable for the personal and
unilateral obligations of the Aguilars to Citytrust.
At the pre-trial conference, only the counsels for the Aguilars and Citytrust
appeared. World Cars was thus declared as in default.
As defined in the Pre-trial Order37 dated November 11, 1994, the issues of
the case were:
1. Whether or not [the Aguilars] have duly paid the purchase price of the
car, and if so, whether or not [they] can still be held liable to pay under the
promissory note and the chattel mortgage.
2. Whether or not [Citytrust and World Cars] are liable to [the Aguilars] for
damages and if so, how much.
3. Whether or not [the Aguilars] have fully paid the balance installment
price of the [car] which was purchased from [World Cars].
4. Whether or not [the Aguilars] are entitled to the damages prayed for in
the complaint.
The trial court further found that Perez was authorized to receive payment
for the car, hence, all payments made to him for the purchase of the car
were payments made to his principal, World Cars; that the Aguilars had
paid a total amount of P386,000.00 including their final payment on July
30, 2002, which date World Cars admitted to be the deadline therefor; and
that the Aguilars had no intention to be bound by the promissory note
which they signed in favor of World Cars or its assignee nor by the terms of
the Chattel Mortgage, the conforme in the undated Letter (Notice of
Assignment) of World Cars and the Disclosure Statement of Loan/Credit
Transaction having been predicated on the validity of the promissory note.
Moreover, the trial court held that the fact that on May 30, 1992, the same
date of the promissory note, Josephine issued three checks to fully cover
the purchase price of the car (the fourth represented payment of insurance
premium), the last of which was still to mature on July 30, 1992, proves
that the Aguilars signed the promissory note without intending to be bound
by its terms.
In fine, the trial court held that the Aguilars had paid World Cars the full
purchase price of the car, and Citytrust as the assignee of World Cars had
no right to collect from them the amount stated in the Chattel
Mortgage cum Deed of Assignment which is simulated and, therefore, void,
following Art. 1346 of the Civil Code which provides:
Art. 1346. An absolutely simulated or fictitious contract is void. A relative
simulation, when it does not prejudice a third person and is not intended
for any purpose contrary to law, morals, good customs, public order or
public policy binds the parties to their real agreement.
The trial court thus disposed:
I.
THE COURT A QUO COMMITTED SERIOUS ERRORS OF FACT AND OF LAW IN
NOT HOLDING THAT [SPOUSES AGUILAR] ARE LIABLE TO [CITYTRUST] FOR
THE PAYMENT OF THE PROMISSORY NOTE (PN) (EXH. "I") AND ARE BOUND
BY THE TERMS AND CONDITIONS OF SAID PN AND CHATTEL MORTGAGE
(EXH. "2").
II.
THAT ASSUMING, THAT SPOUSES AGUILAR ARE NOT LIABLE ON THE
PROMISSORY NOTE, THE COURT A QUO COMMITTED SERIOUS ERRORS OF
FACT AND OF LAW IN NOT HOLDING THAT WORLD CARS IS LIABLE TO
CITYTRUST AS GENERAL ENDORSER OF THE PROMISSORY NOTE AND FOR
VIOLATION OF ITS WARRANTY UNDER THE RECEIVABLES FINANCING
AGREEMENT (RFA).
III.
THE COURT A QUO, COMMITTED SERIOUS ERRORS IN FACT AND IN
LAW WHEN IT ADJUDGED CITYTRUST JOINTLY AND SEVERALLY LIABLE TO
[SPOUSES AGUILAR].39 (Emphasis supplied)
World Cars appealed too, contending that the trial court erred in:
I.
. . . HOLDING WORLD CARS, INC., LIABLE FOR THE PERSONAL ACTIONS OR
ACTIONS BEYOND THE SCOPE OF AUTHORITY OF ITS SALES AGENT
JOSELITO PEREZ.
II.
. . . HOLDING THAT THE SALE IS A CASH SALE AND NOT AN INSTALLMENT
SALE AS EVIDENCED BY THE PROMISSORY NOTE AND CHATTEL MORTGAGE
EXECUTED BY [SPOUSES AGUILAR] IN FAVOR OF [WORLD CARS] AND
ASSIGNED TO [CITYTRUST].
III.
C.
. . . RULING [SPOUSES AGUILAR] LIABLE ON THE PN CONTRARY TO
EVIDENCE ON RECORD.
D.
. . . RULING [CITYTRUST NOT JOINTLY AND SEVERALLY LIABLE WITH WORLD
CARS FOR DAMAGES AND ATTORNEYS FEES CONTRARY TO EVIDENCE ON
RECORD.42 (Underscoring supplied)
On the other hand, World Cars contend that:
A. THE ASSAILED DECISIONS OF THE HONORABLE COURT OF APPEALS
ARE CONTRARY TO LAW AND PREVAILING JURISPRUDENCE.
B. CONSIDERING THAT THE ASSAILED DECISIONS OF THE HONORABLE
COURT OF APPEALS ARE CONTRARY TO LAW AND PREVAILING
JURISPRUDENCE THE AWARDS OF MORAL DAMAGES AGAINST WORLD
CARS, INC. ARE ALSO CONTRARY TO LAW.
C. LIKEWISE, THE AWARDS OF EXEMPLARY DAMAGES, ATTORNEYS FEES
AND APPEARANCE FEES, LITIGATION EXPENSES AND THE COST OF SUIT
AGAINST [WORLD CARS] ARE ALSO CONTRARY TO LAW.43(Underscoring
supplied)
Clearly, Perez was the agent of World Cars and was duly authorized to
accept payment for the car. Josephines testimony that before issuing the
checks in the name of Perez, she verified from his supervisor and the latter
confirmed Perez authority to receive payment remains unrefuted by World
Cars. In fact, World Cars admitted in its Answer with Counterclaim that
"[w]hat was actually paid [by the Aguilars] and received by [it] was
[Josephines] check in the amount of P148,000.00 as downpayment for
the said car."44 Parenthetically, as earlier stated, when Josephine spoke to
World Cars Vice President Domondon, the latter informed her that
the last payment had not been received.45 This information of Domondon
does not jibe with the claim of World Cars that it received only Josephines
first check in the amount of P148,000.00 as downpayment.
As the above table of checks issued by Josephine shows, the check in the
amount of P148,000.00, Check No. 112703 dated May 30, 1992,
was payable to Perez.
Since the Aguilars payment to Perez is deemed payment to World Cars,
the promissory note, chattel mortgage and other accessory documents
they executed which were to take effect only in the event the checks would
be dishonored were deemed nullified, all the checks having been cleared.
Since the condition for the instruments to become effective was fulfilled,
the obligation on the part of the Aguilars to be bound thereby did not arise
and World Cars did not thus acquire rights thereunder following Art. 1181
of the Civil Code which provides:
ARTICLE 1181. In conditional obligations, the acquisition of
rights, as well as the extinguishment or loss of those already
acquired, shall depend upon the happening of the event which
constitutes the condition.(Emphasis supplied)
As no right against the Aguilars was acquired by World Cars under the
promissory note and chattel mortgage, it had nothing to assign to
Citytrust. Consequently, Citytrust cannot enforce the instruments against
the Aguilars, for an assignee cannot acquire greater rights than those
pertaining to the assignor.46
At all events, the Aguilars having fully paid the car before they became
aware of the assignment of the instruments to Citytrust when they
received notice thereof by Citytrust, they were released of their obligation
thereunder. The Civil Code so provides:
ARTICLE 1626. The debtor who, before having knowledge of the
assignment, pays his creditor, shall be released from the obligation.
While Citytrust cannot enforce the instruments against the Aguilars, since
under the RFA, specifically paragraph 5(a) thereof, World Cars guaranteed
as follows:
5. As further warranties, [World Cars] hereby agrees and shall be bound by
the following:
a. World Cars guarantees to [Citytrust] its successors, and
assigns, that it has full right and legal authority to make the
assignment or discounting; that the installment papers so
discounted by virtue of this agreement, are subsisting, valid,
enforceable and in all respects what they purport to be; that the
papers contain the entire agreement between the customers and
[World Cars]; x x x that it has absolute and good title to such
contracts and the personalties covered thereby and the right to
sell and transfer the same in favor of [Citytrust]; x x x (Emphasis
and underscoring supplied),
Citytrusts allegations in its Crossclaim against World Cars Inc., to wit:
xxx
6. That under the terms and conditions of the RFA, upon violation of
the dealers warranties and undertakings, defendant Citytrust Finance
(1) whatever unpaid obligation due to it arising from the assignment of the
promissory note;
Moreover, if it is proven that said plaintiffs have already paid the amount
on said promissory note, then defendant World Cars Inc. would appear to
have received twice the considerations thereof because it likewise received
the proceeds of discounting thereof, from defendant Citytrust at the time
said note was endorsed and assigned thus, unjustly enriching itself;
xxx
9. Assuming that plaintiffs claims are proven to be true and that defendant
World Cars, Inc. violated its warranties and undertakings to the defendant
Citytrust, defendant World Cars, Inc. should likewise be made liable to
herein defendant Citytrust for all the unpaid obligations arising from said
promissory note above alleged, plus damages and attorneys fees as
maybe proven during the trial.47 (Emphasis and underscoring supplied),
are well-taken.
Respecting the award of moral and exemplary damages, attorneys fees
and other litigation expenses to the Aguilars which World Cars assails, the
same is in order. For by Josephines testimony, 48 she was "annoyed, upset
and angry"; and her husband became hypertensive on account of, and the
credit line of their business was affected by World Cars fraudulent breach
of its agreement with them.49
As for the award to Citytrust of attorneys fees, appearance fees, litigation
expenses and costs of suit against World Cars, the same is in order too,
World Cars violation of the RFA having compelled Citytrust to incur
expenses to protect its interest.50
WHEREFORE, the Court of Appeals decision is REVERSED and SET
ASIDE and another rendered:
1. ANNULLING the promissory note, chattel mortgage and its accessory
contracts;
2. ORDERING World Cars to PAY:
(a) Citytrust
xxx
xxx
Public for Makati, _____, as Doc. No. ______, Page No. _____,
Book No. ___, Series of 1986 of his Notarial Register.
'That as part of the consideration of this sale, the VENDEE
hereby assumes to pay the mortgage obligations on the
property herein sold in the amount of ONE MILLION EIGHT
HUNDRED THOUSAND PESOS (P1,800,000.00), Philippine
currency, in favor of Bank of Philippine Islands, in the name
of the VENDOR, and further agrees to strictly and faithfully
comply with all the terms and conditions appearing in the
Real Estate Mortgage signed and executed by the VENDOR
in favor of BPI, including interests and other charges for
late payment levied by the Bank, as if the same were
originally signed and executed by the VENDEE.
'It is further agreed and understood by the parties herein
that the capital gains tax and documentary stamps on the
sale shall be for the account of the VENDOR; whereas, the
registration fees and transfer tax thereon shall be the
account of the VENDEE.' (Exh. 'A', pp. 11-12, Record).'
"On the same date, and as part of the above-document, plaintiff
Avelina Velarde, with the consent of her husband, Mariano,
executed an Undertaking (Exh. 'C', pp. 13-14, Record).'
'x x x
xxx
xxx
act (Article 1592, Civil Code). In the case at bar, Raymundo sent
Velarde notarial notice dated January 8, 1987 of
cancellation/rescission of the contract due to the latter's failure to
comply with their obligation. The rescission was justified in view of
Velarde's failure to pay the price (balance) which is substantial and
fundamental as to defeat the object of the parties in making the
agreement. As adverted to above, the agreement of the parties
involved a reciprocal obligation wherein the obligation of one is a
resolutory condition of the obligation of the other, the nonfulfillment of which entitles the other party to rescind the contract
(Songcuan vs. IAC, 191 SCRA 28). Thus, the non-payment of the
mortgage obligation by appellees Velarde would create a right to
demand payment or to rescind the contract, or to criminal
prosecution (Edca Publishing & Distribution Corporation vs. Santos,
184 SCRA 614). Upon appellee's failure, therefore, to pay the
balance, the contract was properly rescinded (Ruiz vs. IAC, 184
SCRA 720). Consequently, appellees Velarde having violated the
contract, they have lost their right to its enforcement and hence,
cannot avail of the action for specific performance (Voysaw vs.
Interphil Promotions, Inc., 148 SCRA 635)."10
Hence, this appeal.
11
The Issues
Petitioners, in their Memorandum,12 interpose the following assignment of
errors:
"I.
The Court of Appeals erred in holding that the non-payment of the
mortgage obligation resulted in a breach of the contract.
"II
The Court of Appeals erred in holding that the rescission
(resolution) of the contract by private respondents was justified.
"III
The Court of Appeals erred in holding that petitioners' January 7,
1987 letter gave three 'new conditions' constituting mere offers or
an attempt to novate necessitating a new agreement between the
parties."
The Court's Ruling
been agreed upon in the original contract. Thus, it cannot be said that the
breach committed by petitioners was merely slight or casual as would
preclude the exercise of the right to rescind.
Misplaced is petitioners' reliance on the cases 19 they cited, because the
factual circumstances in those cases are not analogous to those in the
present one. In Song Fo there was, on the part of the buyer, only a delay of
twenty (20) days to pay for the goods delivered. Moreover, the buyer's
offer to pay was unconditional and was accepted by the seller.
Third Issue
Attempt to Novate
In view of the foregoing discussion, the Court finds it no longer necessary
to discuss the third issue raised by petitioners. Suffice it to say that the
three conditions appearing on the January 7, 1987 letter of petitioners to
private respondents were not part of the original contract. By that time, it
was already incumbent upon the former to pay the balance of the sale
price. They had no right to demand preconditions to the fulfillment of their
obligation, which had become due.
WHEREFORE, the assailed Decision is hereby AFFIRMED with
the MODIFICATION that private respondents are ordered to return to
petitioners the amount of P874,150, which the latter paid as a
consequence of the rescinded contract, with legal interest thereon from
January 8, 1987, the date of rescission. No pronouncement as to costs. SO
ORDERED.
Republic of the Philippines
SUPREME COURT
Manila
Required in Rescission
As discussed earlier, the breach committed by petitioners was the
nonperformance of a reciprocal obligation, not a violation of the terms and
conditions of the mortgage contract. Therefore, the automatic rescission
and forfeiture of payment clauses stipulated in the contract does not apply.
Instead, Civil Code provisions shall govern and regulate the resolution of
this controversy.
Considering that the rescission of the contract is based on Article 1191 of
the Civil Code, mutual restitution is required to bring back the parties to
their original situation prior to the inception of the contract. Accordingly,
the initial payment of P800,000 and the corresponding mortgage payments
in the amounts of P27,225, P23,000 and P23,925 (totaling P874,150.00)
advanced by petitioners should be returned by private respondents, lest
the latter unjustly enrich themselves at the expense of the former.
Rescission creates the obligation to return the object of the contract. It can
be carried out only when the one who demands rescission can return
SECOND DIVISION
G.R. No. 129598
resolution dated June 19, 1997 in CA-G.R. CV No. 49693, affirming the
order of the Regional Trial Court of Manila, Branch 38, dated August 21,
1995 in Civil Case No. 95-72685. In said order, the RTC directed the
garnishment of the credits and receivables of Pantranco North Express, Inc.
(PNEI), also known as Philippine National Express, Inc., in the possession of
PNB MADECOR, and if these were insufficient to cover the debt of PNB
MADECOR to PNEI, to levy upon the assets of PNB MADECOR.
The facts of this case, culled from the decision of the CA, 1 are as follows:
Guillermo Uy, doing business under the name G.U. Enterprises, assigned to
respondent Gerardo Uy his receivables due from Pantranco North Express
Inc. (PNEI) amounting to P4,660,558.00. The deed of assignment included
sales invoices containing stipulations regarding payment of interest and
attorney's fees.
On January 23, 1995, Gerardo Uy filed with the RTC a collection suit with an
application for the issuance of a writ of preliminary attachment against
PNEI. He sought to collect from PNEI the amount of P8,397,440.00. He
alleged that PNEI was guilty of fraud in contracting the obligation sued
upon, hence his prayer for a writ of preliminary attachment.
A writ of preliminary attachment was issued on January 26, 1995,
commanding the sheriff "to attach the properties of the defendant, real or
personal, and/or (of) any person representing the defendant" 2 in such
amount as to cover Gerardo Uy's demand.
On January 27, 1995, the sheriff issued a notice of garnishment addressed
to the Philippine National Bank (PNB) attaching the "goods, effects, credits,
monies and all other personal properties"3 of PNEI in the possession of the
bank, and requesting a reply within five days. PNB MADECOR received a
similar notice.
On March 1995, the RTC, through the application of Gerardo Uy, issued a
subpoena duces tecum for the production of certain documents in the
possession of PNB and PNB MADECOR: (1) from PNB, books of account of
PNEI regarding trust account nos. T-8461-I, 8461-II, and T-8565; and (2)
from PNB MADECOR, contracts showing PNEI's receivables from the
National Real Estate Development Corporation (NAREDECO), now PNB
MADECOR, from 1981 up to the period when the documents were
requested.
the Civil Code. Petitioner assails the CA's ratiocination that compensation
could not have taken place because the receivables in question were the
subject of attachment proceedings commenced by a third party
(respondent). This reasoning is contrary to law, according to petitioner.
II
THE [COURT OF APPEALS] COMMITTED A CLEAR ERROR IN
INTERPRETING THE PROVISIONS OF SECTION 45, RULE 39 OF THE
RULES OF COURT, NOW SECTION 43, RULE 39 OF THE REVISED
RULES OF COURT, AS AMENDED ON 1 JULY 1997, BY RULING THAT
PETITIONER PNB-MADECOR, UPON BEING CITED FOR AND SERVED
WITH A NOTICE OF GARNISHMENT BECAME A FORCED
INTERVENOR, HENCE, DENYING THE RIGHT OF HEREIN PETITIONER
TO VENTILATE ITS POSITION IN A FULL-BLOWN TRIAL AS PROVIDED
FOR UNDER SEC. 10, RULE 57, WHICH REMAINS THE SAME RULE
UNDER THE REVISED RULES OF COURT AS AMENDED ON 1 JULY
1997.
III
THE [COURT OF APPEALS] COMMITTED AN ERROR IN FINDING THAT
A DEMAND WAS MADE BY PANTRANCO NORTH EXPRESS, INC. TO
PNB MADECOR FOR THE PAYMENT OF THE PROMISSORY NOTE
DATED 31 OCTOBER 1982.7
After considering these assigned errors carefully insofar as they raise
issues of law, we find that the petition lacks merit. We shall now discuss
the reasons for our conclusion.
Petitioner admits its indebtedness to PNEI, in the principal sum of
P7,884,921.10, per a promissory note dated October 31, 1982 executed by
its precursor NAREDECO in favor of PNEI. It also admits that the principal
amount should earn an interest of 18 percent per annum under the
promissory note, in case NAREDECO fails to pay the principal amount after
notice. Petitioner adds that the receivables of PNEI were thereafter
conveyed to PNB in payment of PNEI's loan obligation to the latter, in
accordance with a dacion en pago agreement executed between PNEI and
PNB.
Petitioner, however, maintains that there is nothing now that could be
subject of attachment or execution in favor of respondent since
compensation had already taken place as between its debt to PNEI and the
latter's obligation to it, consistent with Articles 1278, 1279, and 1290 of
Petitioner insists that even the Asset Privatization Trust (APT), which now
has control over PNEI, recognized the set-off between the subject
receivables as indicated in its reply to petitioner's demand for payment of
PNEI's unpaid rentals.8 The APT stated in its letter:
"xxx
xxx
xxx
xxx
xxx"
Petitioner argues that PNEI's letter dated September 28, 1984 did not
contain a demand for payment but only notice of the implementation of
thedacion en pago agreement between PNB and PNEI.
Petitioner contends that the CA's statement that PNEI's obligation to
petitioner had either been settled or was not yet demandable is highly
speculative and conjectural. On the contrary, petitioner asserts that its
failure to institute a judicial action against PNEI proved that the receivables
of petitioner and PNEI had already been subject to legal compensation.
Petitioner submits that Rule 39, Section 43 of the Revised Rules of Court
applies to the present case. It asserts that it stands to lose more than P7
million if not given the opportunity to present its side in a formal
proceeding such as that provided under the cited rule. According to
petitioner, it was not an original party to this case but only became
involved when it was issued a subpoenaduces tecum by the trial court.
For his part, respondent claims that the requisites for legal compensation
are not present in this case, contrary to petitioner's assertion. He argues
that the better rule should be that compensation cannot take place where
"x x x It has been stipulated that the promissory note shall earn an
interest of 18% per annum in case NAREDECO, after notice, fails to
pay the amount stated therein."15
Petitioner's obligation to PNEI appears to be payable on demand, following
the above observation made by the CA and the assertion made by
petitioner. Petitioner is obligated to pay the amount stated in the
promissory note upon receipt of a notice to pay from PNEI. If petitioner fails
to pay after such notice, the obligation will earn an interest of 18 percent
per annum.
Respondent alleges that PNEI had already demanded payment. The alleged
demand letter reads in part:
"We wish to inform you that as of August 31, 1984 your
outstanding accounts amounted to P10,376,078.67, inclusive of
interest.
In accordance with our previous arrangement, we have conveyed
in favor of the Philippine National Bank P7,884,921.10 of said
receivables from you. With this conveyance, the unpaid balance of
your account will be P2,491,157.57.16
To forestall further accrual of interest, we request that you take up
with PNB the implementation of said arrangement. x x x." 17
We agree with petitioner that this letter was not one demanding payment,
but one that merely informed petitioner of (1) the conveyance of a certain
portion of its obligation to PNEI per adacion en pago arrangement between
PNEI and PNB, and (2) the unpaid balance of its obligation after deducting
the amount conveyed to PNB. The import of this letter is not that PNEI was
demanding payment, but that PNEI was advising petitioner to settle the
matter of implementing the earlier arrangement with PNB.
Apart from the aforecited letter, no other demand letter appears on record,
nor has any of the parties adverted to another demand letter.
Since petitioner's obligation to PNEI is payable on demand, and there being
no demand made, it follows that the obligation is not yet due. Therefore,
this obligation may not be subject to compensation for lack of a requisite
under the law. Without compensation having taken place, petitioner
remains obligated to PNEI to the extent stated in the promissory note. This
law requires only is that the obligations be due and demandable at the
same time.
Coming now to the second assigned error, which we reserved as the last
for our discussion, petitioner contends that it did not become a forced
intervenor in the present case even after being served with a notice of
garnishment. Petitioner argues that the correct procedure would have been
for respondent to file a separate action against PNB MADECOR, per Section
43 of Rule 39 of the Rules of Court.21 Petitioner insists it was denied its
right to ventilate its claims in a separate, full-blown trial when the courtsa
quo ruled that the abovementioned rule was inapplicable to the present
case.
On this score, we had occasion to rule as early as 1921 inTayabas Land Co.
v. Sharruf ,22 as follows:
". . . garnishment . . . consists in the citation of some stranger to
the litigation, who is debtor to one of the parties to the action. By
this means such debtor stranger becomes a forced intervenor; and
the court, having acquired jurisdiction over his person by means of
the citation, requires him to pay his debt, not to his former creditor,
but to the new creditor, who is creditor in the main litigation. It is
merely a case of involuntary novation by the substitution of one
creditor for another. Upon principle the remedy is a species of
attachment or execution for reaching any property pertaining to a
judgment debtor which may be found owing to such debtor by a
third person."
Again, inPerla Compania de Seguros, Inc. v. Ramolete,23 we declared:
"Through service of the writ of garnishment, the garnishee
becomes a "virtual party" to, or a "forced intervenor" in, the case
and the trial court thereby acquires jurisdiction to bind him to
compliance with all orders and processes of the trial court with a
view to the complete satisfaction of the judgment of the court."
Petitioner here became a forced intervenor by virtue of the notice of
garnishment served upon him. It could have presented evidence on its
behalf. The CA, in fact, noted that petitioner presented a statement of
account purportedly showing that PNEI had not yet settled its obligation to
petitioner.24 That petitioner failed to present any more proof of its claim, as
observed by the CA, is no longer the fault of the courts.
There is no need for the institution of a separate action under Rule 39,
Section 43, contrary to petitioner's claim. This provision contemplates a
situation where the person allegedly holding property of (or indebted to)
the judgment debtor claims an adverse interest in the property (or denies
the debt). In this case, petitioner expressly admits its obligation to PNEI. 25
WHEREFORE, the petition is DENIED. The assailed decision and resolution
of the Court of Appeals are AFFIRMED. Costs against petitioner.
SO ORDERED.
May 9, 2001
this action, plus interest thereon at the rate of 12% per annum
counted from October 1979 until fully paid;
"2. Ordering the defendant to pay the plaintiff the sum equivalent
to 25% of the total amount due and collectible; and
"3. Ordering the defendant to pay the costs of the suit."5
The Facts
The factual and procedural antecedents of the case are summarized by the
Court of Appeals as follows:
PANGANIBAN, J.:
When both parties to a transaction are mutually negligent in the
performance of their obligations, the fault of one cancels the negligence of
the other. Thus, their rights and obligations may be determined equitably.
No one shall enrich oneself at the expense of another.1wphi1.nt
The Case
Before us is a Petition for Review on Certiorari 1 under Rule 45 of the Rules
of Court, assailing the January 21, 1993 Decision 2 of the Court of
Appeals3 (CA) in CA-GR CV No. 26045. The challenged Decision affirmed
with modification the ruling of the Regional Trial Court of Bacolod City in
Civil Case No. 2296. The CA ruled as follows:
"WHEREFORE, the decision under appeal should be, as it is hereby
affirmed in all its aspects, except for the deletion of paragraph 2 of
its dispositive portion, which paragraph shall be replaced by a new
paragraph which shall read as follows:
'2. ordering the defendant to pay the plaintiff the sum
equivalent to 10% of the total amount due and collectible,
as attorney's fees; and'
"No pronouncement as to costs."4
On the other hand, the trial court had rendered this judgment:
"1. Ordering the defendant to pay the plaintiff the sum of
P76,000.00, representing the principal amount being claimed in
Issues
Petitioner presents the following issues for resolution:
"1. Whether or not it is proper for a banking institution to pay a
letter of credit which has long expired or been cancelled.
"2. Whether or not respondent courts were correct in their
conclusion that there was a consummated sale between petitioner
and Ekman Co.
"3. Whether or not Respondent Court of Appeals was correct in
evading the issues raised in the appeal that under the trust receipt,
petitioner was merely the depositary of private respondent with
respect to the goods covered by the trust receipt." 8
The Court's Ruling
We affirm the Court of Appeals, but lower the interest rate to only 6
percent and delete the award of attorney's fees.
First Issue:
Efficacy of Letter of Credit
Petitioner asserts that respondent bank was negligent in paying for the two
hydraulic loaders, when it no longer had any obligation to do so in view of
the expiration and cancellation of the Letter of Credit.
Petitioner Rodzssen Supply Inc. applied for and obtained an irrevocable 30day domestic Letter of Credit from Far East Bank and Trust Company Inc.
on January 15, 1979, in favor of Ekman and Company Inc., in order to
finance the purchase of five units of hydraulic loaders in the amount
of P190,000. Originally set to expire on February 15, 1979, the subject
Letter of Credit was amended several times to extend its validity until
October 16, 1979.
The Letter of Credit expressly restricted the negotiation to respondent bank
and specifically instructed Ekman and Company Inc. to tender the following
documents: (1) delivery receipt duly acknowledged by the buyer, (2)
accepted draft, and (3) duly signed commercial invoices. Likewise, the
instrument contained a provision with regard to its expiration date. 8
For the first three hydraulic loaders that were delivered, the bank paid the
amount specified in the letter of credit. The present dispute pertains only
to the last two hydraulic loaders.
Petitioner claims that it accepted the late delivery of the equipment, only
because it was bound to accept it under the company's trust receipt
arrangement with respondent bank.
Clearly, the bank paid Ekman when the former was no longer bound to do
so under the subject Letter of Credit. The records show that respondent
paid the latter P76,000 for the last two hydraulic loaders on March 14,
1980,10five months after the expiration of the Letter of Credit on October
16, 1979.11 In fact, on December 27, 1979, the bank had informed
Rodzssen of the cancellation of the commercial paper and credited P22,800
to the account of the latter. The amount represented the marginal deposit,
which petitioner had been required to put up for the unnegotiated portion
of the Letter of Credit -- P76,000 for the two hydraulic loaders.12
Granting that petitioner was bound under such arrangement to accept the
late delivery of the equipment, we note its unexplained inaction for almost
four years with regard to the status of the ownership or possession of the
loaders. Bewildering was its lack of action to validate the ownership and
possession of the loaders, as well as its stolidity over the purported failed
sales transaction. Significant too is the fact that it formalized its offer to
return the two pieces of equipment only after respondent's demand for
payment, which came more than three years after it accepted delivery.
The subject Letter of Credit had become invalid upon the lapse of the
period fixed therein.13 Thus, respondent should not have paid Ekman; it
was not obliged to do so. In the same vein, of no moment was Ekman's
presentation, within the prescribed period, of all the documents necessary
for collection, as the Letter of Credit had already expired and had in fact
been cancelled.
Second Issue:
Was Petitioner Liable to Respondent?
Be that as it may, we agree with the CA that petitioner should pay
respondent bank the amount the latter expended for the equipment
belatedly delivered by Ekman and voluntarily received and kept by
petitioner.
Respondent bank's right to seek recovery from petitioner is anchored, not
upon the inefficacious Letter of Credit, but on Article 2142 of the Civil Code
which reads as follows:
"Certain lawful, voluntary and unilateral acts give rise to the
juridical relation of quasi-contract to the end that no one shall be
unjustly enriched or benefited at the expense of another."
Indeed, equitable considerations behoove us to allow recovery by
respondent. True, it erred in paying Ekman, but petitioner itself was not
without fault in the transaction. It must be noted that the latter had
voluntarily received and kept the loaders since October 1979.
xxx
xxx
"Plaintiffs and defendant Iloilo Traders Finance, Inc., are directed to clarify
whether the words herein defendants include defendants Bernadette
Castellano and the provincial sheriff of Iloilo.
"If the plaintiffs desire to dismiss the complaint against defendants
Castellano and the provincial sheriff of Iloilo, they should state it
categorically and in writing.
"Furthermore, the Court wants to know from the plaintiffs and defendant
Iloilo Traders Finance, Inc., if the writ of preliminary injunction issued on
January 6, 1982 should be lifted as to all three defendants.
"The clarification herein sought after by the Court shall be made in writing
and signed by the parties concerned, assisted by their respective
attorneys.
"This Order shall be complied with within a period of ten (10) days from
notice hereof."1
The parties failed to comply with the court order. Resultantly, the trial court
disapproved the amicable settlement and set the case for pre-trial. Nothing
much could be gleaned from the records about what might have transpired
next not until seven years later when the Soriano couple filed a motion to
submit anew the amicable settlement. The motion was opposed by ITF on
the ground that the amount expressed in the settlement would no longer
be accurate considering the lapse of seven years, implying in a way that it
could be amendable thereto if the computation were to be revised. The
trial court denied the Soriano motion. Significantly, while the order of
denial was made on the thesis that the debtor spouses, without the
consent of ITF, could not unilaterally resurrect the amicable settlement, the
trial court, nevertheless, made the following observations "x x x (T)hat in relation to the disapproved Amicable Settlement, the
intention of ITF to agree and abide by the provisions thereof, as evidenced
by the signatures thereto of its President and counsels, cannot be ignored.
That intention pervades to the present time since the disapproval by the
court pertains only to a technicality which in no way intruded into the
substance of the agreement reached by the parties. Such being the case,
the Amicable Settlement had novated the original agreement of that
parties as embodied in the promissory note. The rights and obligations of
the parties, therefore, at this time should be based on the provisions of the
amicable settlement, these should pertain to the principal amount as of
that date which the parties pegged at P431,200.00 and the legal rate of
interest thereon.
"The foregoing should however be a good issue in another forum, not in
the present case."2
Taking cue from the court order, the Sorianos withdrew their complaint
and, on 16 October 1991, filed a case for novation and specific
performance, docketed Civil Case No. 20047, before the Regional Trial
Court, Branch 37, of Iloilo City. The case ultimately concluded with a finding
made by the trial court in favor of herein respondents. On appeal to it, the
Court of Appeals affirmed the judgment of the court a quo.
The parties have submitted that the issue focuses on whether or not the
amicable settlement entered into between the parties has novated the
original obligation and also, as they would correctly suggest in their
argument, on whether the proposed terms of the amicable settlement were
carried out or have been rendered inefficacious.
The "amicable settlement" read "COME NOW plaintiffs and defendant Iloilo Traders Finance, Inc., assisted
by their respective undersigned counsels and to this Honorable Court most
respectfully submit the following Amicable Settlement, thus:
"1. That the total of the two (2) accounts of plaintiff to herein
defendant as of June 30, 1983 is Two Hundred Ninety Thousand Six
Hundred Ninety One Pesos (P290,691.00) of which amount
P10,691.00 shall be paid by plaintiffs to herein defendant at the
time of the signing of this Amicable Settlement;
"2. That to this amount of P290,691.00 shall be added P151,200.00
by way of interest for 36 months thus making a total of Four
Hundred Thirty One Thousand Two Hundred Pesos (P431,200.00);
"3. That this amount of P431,200.00 shall be paid by plaintiffs to
herein defendant in 36 monthly installments as follows, the first
installment at P12,005.00 shall be paid on or before August 16,
1983 and the 2nd to 36th installments at P11,977.00 shall be paid
on the 15th day of each month thereafter until fully paid;
"4. That the plaintiffs waive any claims, counterclaims, attorneys
fees or damages that they may have against herein defendants;
"5. That should plaintiffs fail to comply with the terms of this
Amicable Settlement the preliminary injunction issued in the case
shall be immediately dissolved and the foreclosure and public
auction sale of the properties of the plaintiffs subject of the
mortgage to defendant shall immediately take place and the
corresponding writ of execution shall issue from this Court;
It would appear that the arrangement reached by the Soriano spouses and
ITF would have the original obligation of respondent spouses on two
promissory notes for the sums of P150,000.00 and P80,000.00, both
secured by real estate mortgages, impliedly modified. The amicable
settlement contained modificatory changes. Thus, (1) it increased the
indebtedness of the Soriano spouses, merely due to accruing interest, from
P290,691.00 to P431,200.00; (2) it extended the period of payment and
provided for new terms of payment; and (3) it provided for a waiver of
claims, counterclaims, attorneys fees or damages that the debtor-spouses
might have against their creditor, but the settlement neither cancelled, nor
materially altered the usual clauses in, the real estate mortgages, e.g., the
foreclosure of the mortgaged property in case of default.
Verily, the parties entered into the agreement basically to put an end to
Civil Case No. 14007 then pending before the Regional Trial
Court.11 Concededly, the provisions of the settlement were beneficial to the
respondent couple. The compromise extended the terms of payment and
implicitly deferred the extrajudicial foreclosure of the mortgaged property.
It was well to the interest of respondent spouses to ensure its judicial
approval; instead, they went to ignore the order of the trial court and
virtually failed to make any further appearance in court. This conduct on
the part of respondent spouses gave petitioner the correct impression that
the Sorianos did not intend to be bound by the compromise settlement,
and its non-materialization negated the very purpose for which it was
executed.
An extinctive novation would thus have the twin effects of, first,
extinguishing an existing obligation and, second, creating a new one in its
stead. This kind of novation presupposes a confluence of four essential
requisites: (1) a previous valid obligation, (2) an agreement of all parties
concerned to a new contract, (3) the extinguishment of the old obligation,
and (4) the birth of a valid new obligation.6 Novation is merely modificatory
where the change brought about by any subsequent agreement is merely
incidental to the main obligation (e.g., a change in interest rates 7 or an
extension of time to pay8); in this instance, the new agreement will not
have the effect of extinguishing the first but would merely supplement it or
supplant some but not all of its provisions.1wphi1
Given the circumstances, the provisions of Article 2041 of the Civil Code
come in point -
"If one of the parties fails or refuses to abide by the compromise, the other
party may either enforce the compromise or regard it as rescinded and
insist upon his original demand."
As so well put in Diongzon vs. Court of Appeals,12 a "supposed new
agreement is deemed not to have taken effect where a debtor never
complied with his undertaking." In such a case, the other party is given the
option to enforce the provisions of the amicable settlement or to rescind
it13 and may insist upon the original demand without the necessity for a
prior judicial declaration of rescission.14
WHEREFORE, the decision of the Court of Appeals in C.A. G.R. CV No.
46910, affirming that of the court a quo, is REVERSED and SET ASIDE, and
another is entered dismissing the complaint in Civil Case No. 20047 before
the Regional Trial Court, Branch 37, of Iloilo City. No costs. SO ORDERED.
a Real Estate Mortgage dated October 13, 1977 in favor of PSBank over the
same aforementioned 8 real properties.
On March 5, 1979, Maalac and spouses Igmidio and Dolores Galicia, with
the prior consent of PSBank,5 entered into a Deed of Sale with Assumption
of Mortgage involving 3 of the mortgaged properties covered by TCT Nos.
N-6162 (now N-36192), N-8552 (now TCT No. N-36193), and 469843 (now
TCT No. N-36194). The Deed of Sale with Assumption of Mortgage
contained the following stipulations:
1. The VENDEES shall assume as they hereby assume as part of the
purchase price, the amount of P550,000.00, representing the portion of the
mortgaged obligation of the VENDORS in favor of the Philippine Savings
Bank, which is secured by that Real Estate Mortgage contract mentioned in
the Second Whereas Clause hereof covering among others the abovedescribed parcels of land under the same terms and conditions as
originally constituted.
2. The VENDORS hereby warrant valid title to, and peaceful possession of
the property herein sold subject to the encumbrance hereinbefore
mentioned.
3. This instrument shall be subject to the Consent of the Philippine Savings
Bank.
4. All expenses relative to this instrument including documentary stamps,
registration fees, transfer taxes and other charges shall be for the account
of the VENDEES.6
Thereafter, the 3 parcels of land purchased by the Galicias, together with
another property, were in turn mortgaged by them to secure a
P2,600,000.00 loan which they obtained from PSBank. Specifically, the
mortgaged properties include TCT Nos. N-36192, N-36193, N-36194,
(formerly TCT Nos. N-6162, N-8552 and 469843, respectively) and
75584.7 This loan is evidenced by Promissory Note LC-79-36. 8
On March 12, 1979, Maalac paid PSBank P919,698.11 which corresponds
to the value of the parcels of land covered by TCT Nos. N-36192, N-36193,
and N-36194, now registered in the name of the spouses Galicia.
Accordingly, PSBank executed a partial release of the real estate mortgage
covered by the aforesaid properties.9
On August 25, 1981, the spouses Galicia obtained a second loan from
PSBank in the amount of P3,250,000.00 for which they executed
Promissory Note LC No. 81-108. They also executed a Real Estate Mortgage
in favor of the bank covering TCT Nos. N-36192, N-36193, N-36194, 75584
and 87690.10
Since Maalac defaulted again in the payment of their loan installments
and despite repeated demands still failed to pay their past due obligation
which now amounted to P1,804,241.76, PSBank filed with the Office of the
Provincial Sheriff of Rizal a petition for extrajudicial foreclosure of their 5
remaining mortgaged properties, specifically those covered by TCT Nos.
417012, N-1347, N-1348, N-3267, and 343593.
Despite several postponements of the public auction sale, Maalac still
failed to pay their mortgage obligation. Thus, on May 3, 1982, the
foreclosure sale of the subject real properties proceeded with PSBank as
the highest bidder in the amount of P2,185,225.76. 11 On the same date,
the Certificate of Sale was issued by the Acting Ex-Oficio Provincial Sheriff
for Rizal province.12
Maalac failed to redeem the properties hence titles thereto were
consolidated in the name of PSBank and new certificates of title were
issued in favor of the bank, namely, TCT No. N-79995 in lieu of TCT No.
343593; TCT No. 79996 in lieu of TCT No. 417012; TCT No. 79997 in lieu of
TCT No. N-3267; TCT No. N-79998 in lieu of TCT No. N-1347; and TCT No. N79999 in lieu of TCT No. N-1348.
On December 16, 1983, Maalac wrote the Chairman of the Board of
PSBank asking information on their request for the partial release of the
mortgage covered by TCT Nos. N-36192, N-36193, N-36194, and 417012
(now TCT No. 79996). TCT Nos. 36192, 36193, and 36194 were registered
in the name of the Galicias, and mortgaged to partially secure their
outstanding loan from the bank. Enclosed in the same letter is a Cashiers
Check for P1,200,000.00 with a notation which reads:
Re: Payment to effect release of TCT Nos. N-36192, 36193, and 36194
under loan account of Spouses Igmedio and Dolores Galicia; and TCT No.
417012 under Loan Account of Spouses Rodolfo and Rosita Maalac.
Upon receipt of the check, PSBanks Acting Manager Lino L. Macasaet
issued a typewritten receipt with the inscription:13
Received from Sps. Rodolfo and Rosita Maalac and Sps. Igmidio and
Dolores Galicia PCIB Check No. 002133 in the amount of One Million Two
Hundred Thousand Pesos Only (P1,200,000.00).
It is understood however, that receipt of said check is not a commitment
on the part of the Bank to release the Four (4) TCTs requested to be
released on your letter dated 19 December 1983.
On December 19, 1983, the bank applied P1,000,000.00 of the
P1,200,000.00 to the loan account of the Galicias as payment for the
arrearages in interest and the remaining P200,000.00 thereof was applied
to the expenses relative to the account of Maalac.14
On May 23, 1985, the bank sold the property covered by TCT No. 79996
(previously TCT No. 343593) to Ester Villanueva who thereafter sold it to
Maalac. On October 30, 1985, the land covered by TCT No. 79995 was
sold by the bank to Teresita Jalbuena.
Thereafter, or on October 20, 1986, Maalac instituted an action for
damages, docketed as Civil Case No. 53967, before the Regional Trial Court
of Pasig, Branch 161, against PSBank and its officers namely Cezar
Valenzuela, Alfredo Barretto and Antonio Viray, and spouses Alejandro and
Teresita Jalbuena.
The bank also filed a petition, docketed as LRC Case No. R-3951, before the
Regional Trial Court of Pasig, Branch 159, for the issuance of a writ of
possession against the properties covered by TCT Nos. N-79997, N-79998,
and N-79999 (formerly TCT Nos. N-3267, N-1347, and N-1348) and the
ejectment of the respondents.
In an order dated January 2, 1989, the trial court consolidated LRC Case
No. R-3951 with Civil Case No. 53967. On April 27, 1993, a judgment was
rendered the dispositive portion of which reads:
WHEREFORE, judgment is hereby rendered ordering:
For Civil Case No. 53967
1. The annulment of the Certificate of Sale issued by the acting Ex-Oficio
Provincial Sheriff of Rizal on May 3, 1982 involving Transfer Certificate of
Title Nos. N-1347-Rizal, N-1348-Rizal and N-3267-Rizal and the Contract to
Sell executed by defendant PSB in favor of defendants spouses Alejandro
HAD BECOME NULL AND VOID AS THE SAME HAD BEEN FORECLOSED BY
PETITIONER;
Petitioner claims that the Court of Appeals erred in sustaining the trial
courts order consolidating Civil Case No. 53967 with LRC Case No. R-3951,
arguing that consolidation is proper only when it involves actions, which
means an ordinary suit in a court of justice by which one party prosecutes
another for the enforcement or protection of a right, or a prevention of a
wrong. Citing A.G. Development Corp. v. Court of Appeals,18 petitioner
posits that LRC Case No. R-3951, being summary in nature and not being
an action within the contemplation of the Rules of Court, should not have
been consolidated with Civil Case No. 53967.
In the same case, the Court likewise rejected the contention that under the
Rules of Court only actions can be consolidated. The Court held that the
technical difference between an action and a proceeding, which involve the
same parties and subject matter, becomes insignificant and consolidation
becomes a logical conclusion in order to avoid confusion and unnecessary
expenses with the multiplicity of suits.
In the instant case, the consolidation of Civil Case No. 53967 with LRC Case
No. R-3951 is more in consonance with the rationale behind the
consolidation of cases which is to promote a more expeditious and less
expensive resolution of the controversy than if they were heard
independently by separate branches of the trial court. Hence, the technical
difference between Civil Case No. 53967 and LRC Case No. R-3951 must be
disregarded in order to promote the ends of justice.
Petitioner also contends that the Court of Appeals committed reversible
error in applying the doctrine laid down inBarican v. Intermediate Appellate
The elements of novation are patently lacking in the instant case. Maalac
tendered a check for P1,200,000.00 to PSBank for the release of 4 parcels
of land covered by TCT Nos. N-36192, 36193, and 36194, under the loan
account of the Galicias and 417012 (now TCT No. 79996) under the loan
account of Maalac. However, while the bank applied the tendered amount
to the accounts as specified by Maalac, it nevertheless refused to release
the subject properties. Instead, it issued a receipt with a notation that the
acceptance of the check is not a commitment on the part of the bank to
release the 4 TCTs as requested by Maalac.
From the foregoing, it is obvious that there was no agreement to form a
new contract by novating the mortgage contracts of the Maalacs and the
Galicias. In accepting the check, the bank only acceded to Maalacs
instruction on whose loan accounts the proceeds shall be applied but
rejected the other condition that the 4 parcels of land be released from
mortgage. Clearly, there is no mutual consent to replace the old mortgage
contract with a new obligation. The conflicting intention and acts of the
parties underscore the absence of any express disclosure or circumstances
with which to deduce a clear and unequivocal intent by the parties to
novate the old agreement.
Novation is never presumed, and the animus novandi, whether totally or
partially, must appear by express agreement of the parties, or by their acts
that are too clear and unmistakable. The extinguishment of the old
obligation by the new one is a necessary element of novation, which may
be effected either expressly or impliedly. The term "expressly" means that
the contracting parties incontrovertibly disclose that their object in
executing the new contract is to extinguish the old one. Upon the other
hand, no specific form is required for an implied novation, and all that is
prescribed by law would be an incompatibility between the two contracts.
While there is really no hard and fast rule to determine what might
constitute to be a sufficient change that can bring about novation, the
touchstone for contrariety, however, would be an irreconcilable
incompatibility between the old and the new obligations. 27
A fortiori, 3 of the 4 properties sought to be released from mortgage,
namely, TCT Nos. N-36192, N-36193, and N-36194, have already been sold
by Maalac to Galicia and are now registered in the name of the latter who
thereafter mortgaged the same as security to a separate loan they
obtained from the bank. Thus, without the consent of PSBank as the
mortgagee bank, Maalac, not being a party to the mortgage contract
between the Galicias and the bank, cannot demand much less impose
upon the bank the release of the subject properties. Unless there is a
stipulation to the contrary, the release of the mortgaged property can only
be made upon the full satisfaction of the loan obligation upon which the
mortgage attaches. Unfortunately, Maalac has not shown that the
P1,000,000.00 was sufficient to cover not only the accrued interests but
also the entire indebtedness of the Galicias to the bank.
Neither can Maalac be deemed substitute debtor within the
contemplation of Article 1293 of the Civil Code, which states that:
Art. 1293. Novation which consists in substituting a new debtor in the place
of the original one, may be made without the knowledge or against the will
of the latter, but not without the consent of the creditor. Payment by the
new debtor gives him the rights mentioned in articles 1236 and 1237. 28
In order to change the person of the debtor, the old one must be expressly
released from the obligation, and the third person or new debtor must
assume the formers place in the relation. Novation is never presumed.
Consequently, that which arises from a purported change in the person of
the debtor must be clear and express. It is thus incumbent on Maalac to
show clearly and unequivocally that novation has indeed taken
place.29 InMagdalena Estates Inc. v. Rodriguez,30 we held that "the mere
fact that the creditor receives a guaranty or accepts payments from a third
person who has agreed to assume the obligation, when there is no
agreement that the first debtor shall be released from responsibility, does
not constitute a novation, and the creditor can still enforce the obligation
against the original debtor."
Maalac has not shown by competent evidence that they were expressly
taking the place of Galicia as debtor, or that the latter were being released
from their solidary obligation. Nor was it shown that the obligation of the
Galicias was being extinguished and replaced by a new one. The existence
of novation must be shown in clear and unmistakable terms.
Likewise, we hold that Maalac cannot demand to repurchase the
foreclosed piece of land covered by TCT No. 417012 (now TCT No. 79996)
from the bank. Its foreclosure and the consolidation of ownership in favor
of the bank and the resultant cancellation of mortgage effectively
cancelled the mortgage contract between Maalac and the bank. Insofar as
TCT No. 417012 is concerned, there is no more existing mortgage to speak
of. As the absolute owner of the foreclosed property, the petitioner has the
discretion to reject or accept any offer to repurchase.
Granting arguendo that a new obligation was established with the
acceptance by the bank of the PCIB Check and its application to the loan
The Case
Before us is a Petition for Review1 under Rule 45 of the Rules of Court,
assailing the August 31, 2001 Decision 2 of the Court of Appeals (CA) in CAGR CV No. 50095, which disposed as follows:
"WHEREFORE, the instant appeal is DISMISSED for lack of merit. The
decision dated January 19, 1995 of the Regional Trial Court, Branch 145,
Makati City is AFFIRMEDin toto."3
The Facts
On February 21, 1991, Spouses Jonas Ramos and Myrna Ramos executed a
contract over their conjugal house and lot in favor of Susana S. Sarao for
and in consideration of P1,310,430.4 Entitled "DEED OF SALE UNDER PACTO
DE RETRO," the contract, inter alia, granted the Ramos spouses the option
to repurchase the property within six months from February 21, 1991,
for P1,310,430 plus an interest of 4.5 percent a month. 5 It was further
agreed that should the spouses fail to pay the monthly interest or to
exercise the right to repurchase within the stipulated period, the
conveyance would be deemed an absolute sale.6
On July 30, 1991, Myrna Ramos tendered to Sarao the amount
of P1,633,034.20 in the form of two managers checks, which the latter
refused to accept for being allegedly insufficient.7 On August 8, 1991,
Myrna filed a Complaint for the redemption of the property and moral
damages plus attorneys fees.8 The suit was docketed as Civil Case No. 912188 and raffled to Branch 145 of the Regional Trial Court (RTC) of Makati
City. On August 13, 1991, she deposited with the RTC two checks that
Sarao refused to accept.9
On December 21, 1991, Sarao filed against the Ramos spouses a Petition
"for consolidation of ownership in pacto de retro sale" docketed as Civil
Case No. 91-3434 and raffled to Branch 61 of the RTC of Makati City. 10 Civil
Case Nos. 91-2188 and 91-3434 were later consolidated and jointly tried
before Branch 145 of the said Makati RTC.11
The two lower courts narrated the trial in this manner:
"x x x Myrna [Ramos] testified as follows: On February 21, 1991, she and
her husband borrowed from Sarao the amount of P1,234,000.00, payable
within six (6) months, with an interest thereon at 4.5% compounded
monthly from said date until August 21, 1991, in order for them to pay
[the] mortgage on their house. For and in consideration of the said amount,
they executed a deed of sale under a [pacto de retro] in favor of Sarao
over their conjugal house and lot registered under TCT No. 151784 of the
Registry of Deeds of Makati (Exhibit A). She further claimed that Sarao will
keep the torrens title until the lapse of the 6-month period, in which case
she will redeem [the] subject property and the torrens title covering it.
When asked why it was the amount of P1,310,430 instead of the
aforestated amount which appeared in the deed, she explained that upon
signing of the deed in question, the sum of P20,000.00 representing
attorneys fees was added, and its total amount was multiplied with 4.5%
interest rate, so that they could pay in advance the compounded interest.
She also stated that although the market value of the subject property as
of February 1991 [was] calculated to [be] more or less P10 million, it was
offered [for] only P1,310,430.00 for the reason that they intended nothing
but to redeem the same. In May 1991, she wrote a letter to Atty. Mario
Aguinaldo requesting him to give a computation of the loan obligation, and
[expressed] her intention to redeem the subject property, but she received
no reply to her letter. Instead, she, through her husband, secured directly
from Sarao a handwritten computation of their loan obligation, the total of
which amount[ed] to P1,562,712.14. Later, she sent several letters to
Sarao, [furnishing] Atty. Aguinaldo with copies, asking them for the
updated computation of their loan obligation as of July 1991, but [no reply
was again received]. During the hearing of February 17, 1992, she
admitted receiving a letter dated July 23, 1991 from Atty. Aguinaldo which
show[ed] the computation of their loan obligation [totaling]
to P2,911,579.22 (Exhs. 6, 6-A). On July 30, 1991, she claimed that she
offered the redemption price in the form of two (2) managers checks
amounting to P1,633,034.20 (Exhs. H-1 & H-2) to Atty. Aguinaldo, but the
latter refused to accept them because they [were] not enough to pay the
loan obligation. Having refused acceptance of the said checks covering the
redemption price, on August 13, 1991 she came to Court to consign the
checks (Exhs. L-4 and L-5). Subsequently, she proceeded to the Register of
Deeds to cause the annotation of lis pendens on TCT No. 151784 (Exh. B-1A). Hence, she filed the x x x civil case against Sarao.
"On the other hand, Sarao testified as follows: On February 21, 1991,
spouses Ramos together with a certain Linda Tolentino and her husband,
Nestor Tolentino approached her and offered transaction involv[ing a] sale
of property[. S]he consulted her lawyer, Atty. Aguinaldo, and on the same
date a corresponding deed of sale underpacto de retro was executed and
signed (Exh. 1 ). Later on, she sent, through her lawyer, a demand letter
dated June 10, 1991 (Exh. 6) in view of Myrnas failure to pay the monthly
interest of 4.5% as agreed upon under the deed[. O]n June 14, 1991 Jonas
replied to said demand letter (Exh. 8); in the reply Jonas admitted that he
no longer ha[d] the capacity to redeem the property and to pay the
interest. In view of the said reply of Jonas, [Sarao] filed the corresponding
consolidation proceedings. She [further claimed] that before filing said
action she incurred expenses including payment of real estate taxes in
arrears, x x x transfer tax and capital [gains] tax, and [expenses] for [the]
consolidated proceedings, for which these expenses were accordingly
receipted (Exhs. 6, 6-1 to 6-0). She also presented a modified computation
of the expenses she had incurred in connection with the execution of the
subject deed (Exh. 9). She also testified that Myrna did not tender payment
of the correct and sufficient price for said real property within the 6-month
period as stipulated in the contract, despite her having been shown the
computation of the loan obligation, inclusive of capital gains tax, real
estate tax, transfer tax and other expenses. She admitted though that
Myrna has tendered payment amounting to P1,633,034.20 in the form of
two managers checks, but these were refused acceptance for being
insufficient. She also claimed that several letters (Exhs. 2, 4 and 5) were
sent to Myrna and her lawyer, informing them of the computation of the
loan obligation inclusive of said expenses. Finally, she denied the
allegations made in the complaint that she allied herself with Jonas, and
claimed that she ha[d] no knowledge about said allegation." 12
After trial, the RTC dismissed the Complaint and granted the prayer of
Sarao to consolidate the title of the property in her favor. 13 Aggrieved,
Myrna elevated the case to the CA.
Ruling of the Court of Appeals
The appellate court sustained the RTCs finding that the disputed contract
was a bonafide pacto de retro sale, not a mortgage to secure a loan.14 It
ruled that Myrna Ramos had failed to exercise the right of repurchase, as
the consignation of the two managers checks was deemed invalid. She
allegedly failed (1) to deposit the correct repurchase price and (2) to
comply with the required notice of consignation.15
Hence, this Petition.16
The Issues
Petitioner raises the following issues for our consideration:
"1. Whether or not the honorable appellate court erred in ruling the subject
Deed of Sale under Pacto de Retro was, and is in reality and under the law
an equitable mortgage;
"2. Whether or not the honorable appellate court erred in affirming the
ruling of the court a quo that there was no valid tender of payment of the
redemption price neither [sic] a valid consignation in the instant case; and
"3. Whether or not [the] honorable appellate court erred in affirming the
ruling of the court a quo denying the claim of petitioner for damages and
attorneys fees."17
The Courts Ruling
The Petition is meritorious in regard to Issues 1 and 2.
First Issue:
A Pacto de Retro Sale
or an Equitable Mortgage?
Respondent Sarao avers that the herein Petition should have been
dismissed outright, because petitioner (1) failed to show proof that she had
served a copy of it to the Court of Appeals and (2) raised questions of fact
that were not proper issues in a petition under Rule 45 of the Rules of
Court.18 This Court, however, disregarded the first ground; otherwise,
substantial injustice would have been inflicted on petitioner. Since the
Court of Appeals is not a party here, failure to serve it a copy of the Petition
would not violate any right of respondent. Service to the CA is indeed
mentioned in the Rules, but only to inform it of the pendency of the appeal
before this Court.
As regards Item 2, there are exceptions to the general rule barring a review
of questions of fact.19 The Court reviewed the factual findings in the
present case, because the CA had manifestly overlooked certain relevant
and undisputed facts which, after being considered, justified a different
conclusion.20
Pacto de Retro Sale Distinguished
from Equitable Mortgage
The pivotal issue in the instant case is whether the parties intended the
contract to be a bona fide pacto de retrosale or an equitable mortgage.
remained as her address for the service of court orders and copies of
Respondent Saraos pleadings.40
(3) When upon or after the expiration of the right to repurchase another
instrument extending the period of redemption or granting a new period is
executed;
(4) When the purchaser retains for himself a part of the purchase price;
(5) When the vendor binds himself to pay the taxes on the thing sold;
(6) In any other case where it may be fairly inferred that the real intention
of the parties is that the transaction shall secure the payment of a debt or
the performance of any other obligation.
In any of the foregoing cases, any money, fruits, or other benefit to be
received by the vendee as rent or otherwise shall be considered as interest
which shall be subject to the usury laws.33
Furthermore, a contract purporting to be a pacto de retro is construed as
an equitable mortgage when the terms of the document and the
surrounding circumstances so require. 34 The law discourages the use of
a pacto de retro, because this scheme is frequently used to circumvent a
contract known as a pactum commissorium. The Court has frequently
noted that a pacto de retro is used to conceal a contract of loan secured by
a mortgage.35Such construction is consistent with the doctrine that the law
favors the least transmission of rights.36
Equitable Mortgage Presumed
to be Favored by Law
Jurisprudence has consistently declared that the presence of even just one
of the circumstances set forth in the forgoing Civil Code provision suffices
to convert a contract to an equitable mortgage.37 Article 1602 specifically
states that the equitable presumption applies to any of the cases therein
enumerated.
In the present factual milieu, the vendor retained possession of the
property allegedly sold.38 Petitioner and her children continued to use it as
their residence, even after Jonas Ramos had abandoned them. 39 In fact, it
the spouses had entered into the alleged pacto de retro sale to secure a
loan obligation, not to transfer ownership of the property.
Sarao contends that Jonas Ramos admitted in his June 14, 1991 letter to
her lawyer that the contract was a pacto de retro.46 That letter, however,
cannot override the finding that the pacto de retro was executed merely as
security for a loan obligation. Moreover, on May 17, 1991, prior to the
transmittal of the letter, petitioner had already sent a letter to Saraos
lawyer expressing the formers desire to settle the mortgage on the
property.47Considering that she had already denominated the transaction
with Sarao as a mortgage, petitioner cannot be prejudiced by her
husbands alleged admission, especially at a time when they were already
estranged.48
Inasmuch as the contract between the parties was an equitable mortgage,
Respondent Saraos remedy was to recover the loan amount from
petitioner by filing an action for the amount due or by foreclosing the
property.49
Second Issue:
Propriety of Tender of
Payment and Consignation
Tender of payment is the manifestation by debtors of their desire to comply
with or to pay their obligation.50 If the creditor refuses the tender of
payment without just cause, the debtors are discharged from the obligation
by the consignation of the sum due. 51 Consignation is made by depositing
the proper amount to the judicial authority, before whom the tender of
payment and the announcement of the consignation shall be proved. 52 All
interested parties are to be notified of the consignation. 53 Compliance with
these requisites is mandatory.54
The trial and the appellate courts held that there was no valid
consignation, because petitioner had failed to offer the correct amount and
to provide ample consignation notice to Sarao.55 This conclusion is
incorrect.
Note that the principal loan was P1,310,430 plus 4.5 per cent monthly
interest compounded for six months. Expressing her desire to pay in the
fifth month, petitioner averred that the total amount due
was P1,633,034.19, based on the computation of Sarao herself. 56 The
amount of P2,911,579.22 that the latter demanded from her to settle the
loan obligation was plainly exorbitant, since this sum included other items
not covered by the agreement. The property had been used solely as
secure ty for the P1,310,430 loan; it was therefore improper to include in
that amount payments for gasoline and miscellaneous expenses, taxes,
attorneys fees, and other alleged loans. When Sarao unjustly refused the
tender of payment in the amount of P1,633,034.20, petitioner correctly
filed suit and consigned the amount in order to be released from the
latters obligation.
The two lower courts cited Article 1257 of the Civil Code to justify their
ruling that petitioner had failed to notify Respondent Sarao of the
consignation. This provision of law states that the obligor may be released,
provided the consignation is first announced to the parties interested in the
fulfillment of the obligation.
The facts show that the notice requirement was complied with. In her
August 1, 1991 letter, petitioner said that should the respondent fail to
accept payment, the former would consign the amount.57 This statement
was an unequivocal announcement of consignation. Concededly, sending
to the creditor a tender of payment and notice of consignation -- which was
precisely what petitioner did -- may be done in the same act. 58
Because petitioners consignation of the amount of P1,633,034.20 was
valid, it produced the effect of payment.59"The consignation, however, has
a retroactive effect, and the payment is deemed to have been made at the
time of the deposit of the thing in court or when it was placed at the
disposal of the judicial authority."60 "The rationale for consignation is to
avoid making the performance of an obligation more onerous to the debtor
by reason of causes not imputable to him."61
Third Issue:
Moral Damages and Attorneys Fees
Petitioner seeks moral damages in the amount of P500,000 for alleged
sleepless nights and anxiety over being homeless. 62 Her bare assertions
are insufficient to prove the legal basis for granting any award under
Article 2219 of the Civil Code.63 Verily, an award of moral damages is
uncalled for, considering that it was Respondent Saraos accommodation
that settled the earlier obligation of the spouses with the commercial bank
and allowed them to retain ownership of the property.
Other Matters
(4) DIRECTING the Register of Deeds of Makati City to cancel Entry No.
24057, the annotation appearing on TCT No. 151784
No pronouncement as to costs.
SO ORDERED.
completing the work has relieved the latter from the obligation of
completing the same.
On the other hand, Philamgen contends that the various amendments
made on the principal contract and the deviations in the implementation
thereof which were resorted to by plaintiff and co-defendant Pacific without
its (defendant Philamgens) written consent thereto, have automatically
released the latter from any or all liability within the purview and
contemplation of the coverage of the surety bonds it has issued. Upon
agreement of the parties to appoint a commissioner to assist the court in
resolving the issues confronting the parties, on 7 July 1981, an order was
issued by then Presiding Judge Segundo M. Zosa naming Architect Antonio
Dimalanta as Court Commissioner from among the nominees submitted by
the parties to conduct an ocular inspection and to determine the amount of
work accomplished by the defendant Pacific and the amount of work done
by plaintiff to complete the project.
On 28 November 1984, the Court received the findings made by the Court
Commissioner. In arriving at his findings, the Commissioner used the
construction documents pertaining to the project as basis. According to
him, no better basis in the work done or undone could be made other than
the contract billings and payments made by both parties as there was no
proper procedure followed in terminating the contract, lack of inventory of
work accomplished, absence of appropriate record of work progress
(logbook) and inadequate documentation and system of construction
management.
Based on the billings of defendant Pacific and the payments made by
plaintiff, the work accomplished by the former amounted
to P11,788,282.40 with the exception of the last billing (which was not
acted upon or processed by plaintiff) in the amount of P844,396.42. The
total amount of work left to be accomplished by plaintiff was based on the
original contract amount less value of work accomplished by defendant
Pacific in the amount ofP681,717.58 (12,470,000-11,788,282.42).
As regards the alleged repairs made by plaintiff on the construction
deficiencies, the Court Commissioner found no sufficient basis to justify the
same. On the other hand, he found the additional work done by defendant
Pacific in the amount of P477,000.00 to be in order.
considering that: (a) time is of the essence of the contract; (b) the
liquidated damages was fixed by the parties to serve not only as penalty in
case Pecorp fails to fulfill its obligation on time, but also as indemnity for
actual and anticipated damages which Filinvest may suffer by reason of
such failure; and (c) the total liquidated damages sought is only 32% of the
total contract price, and the same was freely and voluntarily agreed upon
by the parties.
At the outset, it should be stressed that as only the issue of liquidated
damages has been elevated to this Court, petitioner Filinvest is deemed to
have acquiesced to the other matters taken up by the courts below.
Section 1, Rule 45 of the 1997 Rules of Court states in no uncertain terms
that this Courts jurisdiction in petitions for review on certiorari is limited to
"questions of law which must be distinctly set forth."5 By assigning only
one legal issue, Filinvest has effectively cordoned off any discussion into
the factual issue raised before the Court of Appeals. 6 In effect, Filinvest has
yielded to the decision of the Court of Appeals, affirming that of the trial
court, in deferring to the factual findings of the commissioner assigned to
the parties case. Besides, as a general rule, factual matters cannot be
raised in a petition for review on certiorari. This Court at this stage is
limited to reviewing errors of law that may have been committed by the
lower courts.7 We do not perceive here any of the exceptions to this rule;
hence, we are restrained from conducting further scrutiny of the findings of
fact made by the trial court which have been affirmed by the Court of
Appeals. Verily, factual findings of the trial court, especially when affirmed
by the Court of Appeals, are binding and conclusive on the Supreme
Court.8 Thus, it is settled that:
(a) Based on Pecorps billings and the payments made by Filinvest, the
balance of work to be accomplished by Pecorp amounts to P681,717.58
representing 5.47% of the contract work. This means to say that Pecorp, at
the time of the termination of its contract, accomplished 94.53% of the
contract work;
No Costs.4
(d) The cost to repair deficiency or defect, which is for the account of
Pecorp, is P532,324.02; and
Hence, the instant petition grounded solely on the issue of whether or not
the liquidated damages agreed upon by the parties should be reduced
Coming now to the main matter, Filinvest argues that the penalty in its
entirety should be respected as it was a product of mutual agreement and
it represents only 32% of the P12,470,000.00 contract price, thus, not
shocking and unconscionable under the circumstances. Moreover, the
penalty was fixed to provide for actual or anticipated liquidated damages
and not simply to ensure compliance with the terms of the contract; hence,
pursuant toLaureano v. Kilayco,9 courts should be slow in exercising the
authority conferred by Art. 1229 of the Civil Code.
In herein case, the trial court ruled that the penalty charge for delay
pegged at P15,000.00 per day of delay in the aggregate amount
of P3,990,000.00 -- was excessive and accordingly reduced it
to P1,881,867.66 "considering the amount of work already performed and
the fact that [Filinvest] consented to three (3) prior extensions." The Court
of Appeals affirmed the ruling but added as well that the penalty was
unconscionable "as the construction was already not far from completion."
Said the Court of Appeals:
Turning now to plaintiffs appeal, We likewise agree with the trial court that
a penalty interest of P15,000.00 per day of delay as liquidated damages
or P3,990,000.00 (representing 32% penalty of the P12,470,000.00
contract price) is unconscionable considering that the construction was
already not far from completion. Penalty interests are in the nature of
liquidated damages and may be equitably reduced by the courts if they are
iniquitous or unconscionable (Garcia v. Court of Appeals, 167 SCRA 815,
Lambert v. Fox, 26 Phil. 588). The judge shall equitably reduce the penalty
when the principal obligation has been partly or irregularly complied with
by the debtor. Even if there has been no performance, the penalty may
also be reduced by the courts if it is iniquitous or unconscionable (Art.
1229, New Civil Code). Moreover, plaintiffs right to indemnity due to
defendants delay has been cancelled by its obligations to the latter
consisting of unpaid works.
There is no question that the penalty of P15,000.00 per day of delay was
mutually agreed upon by the parties and that the same is sanctioned by
law. A penal clause is an accessory undertaking to assume greater liability
in case of breach.10 It is attached to an obligation in order to insure
performance11 and has a double function: (1) to provide for liquidated
damages, and (2) to strengthen the coercive force of the obligation by the
threat of greater responsibility in the event of breach.12 Article 1226 of the
Civil Code states:
Art. 1226. In obligations with a penal clause, the penalty shall substitute
the indemnity for damages and the payment of interests in case of
noncompliance, if there is no stipulation to the contrary. Nevertheless,
damages shall be paid if the obligor refuses to pay the penalty or is guilty
of fraud in the fulfillment of the obligation.
The penalty may be enforced only when it is demandable in accordance
with the provisions of this Code.
As a general rule, courts are not at liberty to ignore the freedom of the
parties to agree on such terms and conditions as they see fit as long as
they are not contrary to law, morals, good customs, public order or public
policy.13 Nevertheless, courts may equitably reduce a stipulated penalty in
the contract in two instances: (1) if the principal obligation has been partly
or irregularly complied; and (2) even if there has been no compliance if the
penalty is iniquitous or unconscionable in accordance with Article 1229 of
the Civil Code which provides:
Art. 1229. The judge shall equitably reduce the penalty when the principal
obligation has been partly or irregularly complied with by the debtor. Even
if there has been no performance, the penalty may also be reduced by the
courts if it is iniquitous or unconscionable.
Art. 2226. Liquidated damages are those agreed upon by the parties to a
contract to be paid in case of breach thereof.
Art. 2227. Liquidated damages, whether intended as an indemnity or a
penalty, shall be equitably reduced if they are iniquitous or
unconscionable.
Thus, we lamented in one case that "(t)here is no justification for the Civil
Code to make an apparent distinction between a penalty and liquidated
damages because the settled rule is that there is no difference between
penalty and liquidated damages insofar as legal results are concerned and
that either may be recovered without the necessity of proving actual
damages and both may be reduced when proper."19
Finally, Filinvest advances the argument that while it may be true that
courts may mitigate the amount of liquidated damages agreed upon by the
parties on the basis of the extent of the work done, this contemplates a
situation where the full amount of damages is payable in case of total
breach of contract. In the instant case, as the penalty clause was agreed
upon to answer for delay in the completion of the project considering that
time is of the essence, "the parties thus clearly contemplated the payment
of accumulated liquidated damages despite, and precisely because of,
partial performance."20 In effect, it is Filinvests position that the first part
of Article 1229 on partial performance should not apply precisely because,
in all likelihood, the penalty clause would kick in in situations where Pecorp
had already begun work but could not finish it on time, thus, it is being
penalized for delay in its completion.
The above argument, albeit sound,21 is insufficient to reverse the ruling of
the Court of Appeals. It must be remembered that the Court of Appeals not
only held that the penalty should be reduced because there was partial
compliance but categorically stated as well that the penalty was
unconscionable. Otherwise stated, the Court of Appeals affirmed the
reduction of the penalty not simply because there was partial
compliance per se on the part of Pecorp with what was incumbent upon it
but, more fundamentally, because it deemed the penalty unconscionable
in the light of Pecorps 94.53% completion rate.
In Ligutan v. Court of Appeals,22 we pointed out that the question of
whether a penalty is reasonable or iniquitous can be partly subjective and
partly objective as its "resolution would depend on such factors as, but not
necessarily confined to, the type, extent and purpose of the penalty, the
nature of the obligation, the mode of breach and its consequences, the
supervening realities, the standing and relationship of the parties, and the
SECOND DIVISION
G.R. No. 121940
December 4, 2001
"D").4 This deed was notarized but was not registered immediately upon its
execution in 1974 because GSIS prohibited him from registering the same
in view of the five-year prohibition to sell during the period ending in 1979.
Sometime in 1979, for being suspected as a subversive, an Arrest, Search
and Seizure Order (ASSO) was issued against private respondent. Military
men ransacked his house in Cainta, Rizal. Upon learning that he was
wanted by the military, he voluntarily surrendered and was detained for
two (2) years. When released, another order for his re-arrest was issued so
he hid in Mindanao for another four (4) years or until March 1984. In
December of 1990, he discovered that the subject TCT was missing. He
consulted a lawyer but the latter did not act immediately on the matter.
Upon consulting a new counsel, an Affidavit of Loss5 was filed with the
Register of Deeds of Pasig and a certified copy6 of TCT No. 436465 was
issued. Private respondent also declared the property for tax purposes and
obtained a certification thereof from the Assessor's Office. 7
Private respondent sent notices to the registered owner at her address
appearing in the title and in the Deed of Sale. And, with his counsel, he
searched for the ,registered owner in Metro Manila and Rizal and as far as
Samar, Leyte, Calbayog City, Tacloban City, and in Eastern and Northern
Samar. However, their search proved futile.
On July 8, 1992 private respondent filed a petition docketed as LRC Case
No. R-4659 with the RTC, Branch 154, Pasig, Metro Manila for the issuance
of owner's duplicate copy of TCT No. 436465 to replace the lost one. To
show he was the owner of the contested lot, he showed the Deed of
Absolute Sale, Exhibit "D". The petition was set for hearing and the court's
order dated July 10, 1992 was published once in Malaya, a nationally
circulated newspaper in the Philippines.8
During the hearing on September 3, 1992, only Menez and his counsel
appeared. The Register of Deeds who was not served notice, and the Office
of the Solicitor General and the Provincial Prosecutor who were notified did
not attend.
On September 18, 1992, there being no opposition, Menez presented his
evidence ex-parte. The trial court granted his petition in its decision 9 dated
September 30, 1992, the dispositive portion of which reads:
WHEREFORE, the petition is hereby GRANTED and the Registry of
Deeds of Pasig, Metro Manila, is hereby directed to issue a new
Owner's Duplicate Copy of Transfer Certificate of Title No. 436465
based on the original thereon filed in his office which shall contain
the memorandum of encumbrance and an additional memorandum
of the fact that it was issued in place of the lost duplicate and
which shall, in all respect, be entitled to like faith and credit as the
original duplicate, for all legal intents and purposes.
Issuance of new owner's duplicate copy shall be made only after
this decision shall have become final and executory. The said lost
owner's duplicate is hereby declared null and void.
Petitioner shall pay all legal fees in connection with the issuance of
the new owner's copy.
Let copies of this Order be furnished the petitioner, the registered
owner of his given address in the title, in the deed of sale, and in
the tax declaration; the Registry of Deeds of Pasig, the Office of the
Solicitor General; and the Provincial Fiscal of Pasig, Metro Manila.
SO ORDERED.10
On October 13, 1992, herein petitioner, Jesus San Agustin, received a copy
of the abovecited decision. He-claimed this was the first time he became
aware of the case of her aunt, Macaria Vda. de Caiquep who, according to
him, died sometime in 1974. Claiming that he was the present occupant of
the property and the heir of Macaria, he filed his "Motion to Reopen
Reconstitution Proceedings''11 on October 27, 1992. On December 3, 1992,
RTC issued an order denying said motion.12
Petitioner filed an appeal with the Court of Appeals, which, as earlier
stated, was denied in its decision of May 19, 1995. Petitioner moved for a
reconsideration, but it was denied in a resolution dated September 11,
1995.13
Thus, the present petition, attributing the following errors to the court
a quo:
A.
THE RESPONDENT COURT GRAVELY ERRED IN HOLDING THAT LRC CASE NO.
R-4659 BEING ONLY A PETITION FOR THE ISSUANCE OF A NEW OWNER'S
DUPLICATE OF TITLE, THERE IS NO NEED OF PERSONAL NOTICE TO THE
PETITIONER, THE ACTUAL POSSESSOR [WHO HAS] AND ACTUALLY BEEN
PAYING THE REAL ESTATE TAX, DESPITE PRIVATE RESPONDENT'S
Destroyed," while the present case is based on Section 109 of P.D. 1529 as
above explained.
the condition and treat the sale as good, in which event, the sale
can not be assailed for breach of the condition aforestated. 19
Under Republic Act No. 26, reconstitution is validly made only in case
the original copy of the certificate of title with the Register of Deeds is lost
or destroyed. And if no notice of the date of hearing of a reconstitution
case is served on a possessor or one having interest in the property
involved, he is deprived of his day in court and the order of reconstitution
is null and void.16 The case at bar is not for reconstitution, but merely for
replacement of lost duplicate certificate.
In this case, the GSIS has not filed any action for the annulment of Exhibit
"D", nor for the forfeiture of the lot in question. In our view, the contract of
sale remains valid between the parties, unless and until annulled in the
proper suit filed by the rightful party, the GSIS. For now, the said contract
of sale is binding upon the heirs of Macaria Vda. de Caiquep, including
petitioner who alleges to be one of her heirs, in line with the rule that heirs
are bound by contracts entered into by their predecessors-in-interest. 20
On the second assigned error, petitioner contends that Exhibit "D" is null
and void under Article 1409 of the Civil Code, specifically paragraph
(7),17 because the deed of sale was executed within the five-year
prohibitory period under Commonwealth Act No. 141, as amended,
otherwise known as "The Public Land Act."18
We are not unmindful of the social justice policy of R.A. 8291 otherwise
known as "Government Service Insurance Act of 1997" in granting housing
assistance to the less-privileged GSIS members and their dependents
payable at an affordable payment scheme.21 This is the same policy which
the 5-year restrictive clause in the contract seeks to implement by stating
in the encumbrance itself annotated at the back of TCT No. 436465 that,
"The purpose of the sale is to aid the vendee in acquiring a lot for
himself/themselves and not to provide him/them with a means for
speculation or profit by a future assignment of his/their right herein
acquired or the resale of the lot through rent, lease or subletting to others
of the lot and subject of this deed, . . . within five (5) years from the date
final and absolute ownership thereof becomes vested in the vendee,
except in cases of hereditary succession or resale in favor of the
vendor."22 However, absent the proper action taken by the GSIS as the
original vendor referred to, the contract between petitioner's predecessorin-interest and private respondent deserves to be upheld. For as pointed
out by said private respondent, it is protected by the Constitution under
Section 10, Article III, of the Bill of Rights stating that, "No law impairing
the obligation of contracts shall be passed." Much as we would like to see a
salutary policy triumph, that provision of the Constitution duly calls for
compliance.
benefited from it, said parties should be held in estoppel to assail and
annul their own deliberate acts."
WHEREFORE, the appeal is DENIED, and the decision of the respondent
court is AFFIRMED.
SO ORDERED.
that it was impossible for him and his wife to be upgraded without his two
friends who were traveling with them. Because of Dr. Vazquezs outburst,
Ms. Chiu thought of upgrading the traveling companions of the Vazquezes.
But when she checked the computer, she learned that the Vazquezes
companions did not have priority for upgrading. She then tried to book the
Vazquezes again to their original seats. However, since the Business Class
Section was already fully booked, she politely informed Dr. Vazquez of such
fact and explained that the upgrading was in recognition of their status as
Cathays valued passengers. Finally, after talking to their guests, the
Vazquezes eventually decided to take the First Class accommodation.
Cathay also asserted that its employees at the Hong Kong airport acted in
good faith in dealing with the Vazquezes; none of them shouted,
humiliated, embarrassed, or committed any act of disrespect against them
(the Vazquezes). Assuming that there was indeed a breach of contractual
obligation, Cathay acted in good faith, which negates any basis for their
claim for temperate, moral, and exemplary damages and attorneys fees.
Hence, it prayed for the dismissal of the complaint and for payment of
P100,000 for exemplary damages and P300,000 as attorneys fees and
litigation expenses.
During the trial, Dr. Vazquez testified to support the allegations in the
complaint. His testimony was corroborated by his two friends who were
with him at the time of the incident, namely, Pacita G. Cruz and Josefina
Vergel de Dios.
For its part, Cathay presented documentary evidence and the testimonies
of Mr. Yuen; Ms. Chiu; Norma Barrientos, Comptroller of its retained
counsel; and Mr. Robson. Yuen and Robson testified on Cathays policy of
upgrading the seat accommodation of its Marco Polo Club members when
an opportunity arises. The upgrading of the Vazquezes to First Class was
done in good faith; in fact, the First Class Section is definitely much better
than the Business Class in terms of comfort, quality of food, and service
from the cabin crew. They also testified that overbooking is a widely
accepted practice in the airline industry and is in accordance with the
International Air Transport Association (IATA) regulations. Airlines overbook
because a lot of passengers do not show up for their flight. With respect to
Flight CX-905, there was no overall overbooking to a degree that a
passenger was bumped off or downgraded. Yuen and Robson also stated
that the demand letter of the Vazquezes was immediately acted upon.
Reports were gathered from their office in Hong Kong and immediately
forwarded to their counsel Atty. Remollo for legal advice. However, Atty.
Remollo begged off because his services were likewise retained by the
Vazquezes; nonetheless, he undertook to solve the problem in behalf of
In its decision1 of 19 October 1998, the trial court found for the Vazquezes
and decreed as follows:
However, the Court of Appeals was not convinced that Ms. Chiu shouted at,
or meant to be discourteous to, Dr. Vazquez, although it might seemed that
way to the latter, who was a member of the elite in Philippine society and
was not therefore used to being harangued by anybody. Ms. Chiu was a
Hong Kong Chinese whose fractured Chinese was difficult to understand
and whose manner of speaking might sound harsh or shrill to Filipinos
because of cultural differences. But the Court of Appeals did not find her to
have acted with deliberate malice, deceit, gross negligence, or bad faith. If
at all, she was negligent in not offering the First Class accommodations to
other passengers. Neither can the flight stewardess in the First Class Cabin
be said to have been in bad faith when she failed to assist Dr. Vazquez in
lifting his baggage into the overhead storage bin. There is no proof that he
asked for help and was refused even after saying that he was suffering
from "bilateral carpal tunnel syndrome." Anent the delay of Yuen in
responding to the demand letter of the Vazquezes, the Court of Appeals
found it to have been sufficiently explained.
The Vazquezes and Cathay separately filed motions for a reconsideration of
the decision, both of which were denied by the Court of Appeals.
Cathay seasonably filed with us this petition in this case. Cathay maintains
that the award for moral damages has no basis, since the Court of Appeals
found that there was no "wanton, fraudulent, reckless and oppressive"
display of manners on the part of its personnel; and that the breach of
contract was not attended by fraud, malice, or bad faith. If any damage
had been suffered by the Vazquezes, it was damnum absque injuria, which
is damage without injury, damage or injury inflicted without injustice, loss
or damage without violation of a legal right, or a wrong done to a man for
which the law provides no remedy. Cathay also invokes our decision
in United Airlines, Inc. v. Court of Appeals3 where we recognized that, in
accordance with the Civil Aeronautics Boards Economic Regulation No. 7,
as amended, an overbooking that does not exceed ten percent cannot be
considered deliberate and done in bad faith. We thus deleted in that case
the awards for moral and exemplary damages, as well as attorneys fees,
for lack of proof of overbooking exceeding ten percent or of bad faith on
the part of the airline carrier.
On the other hand, the Vazquezes assert that the Court of Appeals was
correct in granting awards for moral and nominal damages and attorneys
fees in view of the breach of contract committed by Cathay for transferring
them from the Business Class to First Class Section without prior notice or
consent and over their vigorous objection. They likewise argue that the
issuance of passenger tickets more than the seating capacity of each
section of the plane is in itself fraudulent, malicious and tainted with bad
faith.
The key issues for our consideration are whether (1) by upgrading the seat
accommodation of the Vazquezes from Business Class to First Class Cathay
breached its contract of carriage with the Vazquezes; (2) the upgrading
was tainted with fraud or bad faith; and (3) the Vazquezes are entitled to
damages.
We resolve the first issue in the affirmative.
A contract is a meeting of minds between two persons whereby one agrees
to give something or render some service to another for a consideration.
There is no contract unless the following requisites concur: (1) consent of
the contracting parties; (2) an object certain which is the subject of the
contract; and (3) the cause of the obligation which is
established.4 Undoubtedly, a contract of carriage existed between Cathay
and the Vazquezes. They voluntarily and freely gave their consent to an
agreement whose object was the transportation of the Vazquezes from
Manila to Hong Kong and back to Manila, with seats in the Business Class
Section of the aircraft, and whose cause or consideration was the fare paid
by the Vazquezes to Cathay.
The only problem is the legal effect of the upgrading of the seat
accommodation of the Vazquezes. Did it constitute a breach of contract?
Breach of contract is defined as the "failure without legal reason to comply
with the terms of a contract."5 It is also defined as the "[f]ailure, without
legal excuse, to perform any promise which forms the whole or part of the
contract."6
parties had foreseen or could have reasonably foreseen. In such a case the
liability does not include moral and exemplary damages. 14
In this case, we have ruled that the breach of contract of carriage, which
consisted in the involuntary upgrading of the Vazquezes seat
accommodation, was not attended by fraud or bad faith. The Court of
Appeals award of moral damages has, therefore, no leg to stand on.
The deletion of the award for exemplary damages by the Court of Appeals
is correct. It is a requisite in the grant of exemplary damages that the act
of the offender must be accompanied by bad faith or done in wanton,
fraudulent or malevolent manner.15 Such requisite is absent in this case.
Moreover, to be entitled thereto the claimant must first establish his right
to moral, temperate, or compensatory damages.16 Since the Vazquezes are
not entitled to any of these damages, the award for exemplary damages
has no legal basis. And where the awards for moral and exemplary
damages are eliminated, so must the award for attorneys fees. 17
The most that can be adjudged in favor of the Vazquezes for Cathays
breach of contract is an award for nominal damages under Article 2221 of
the Civil Code, which reads as follows:
Article 2221 of the Civil Code provides:
Article 2221. Nominal damages are adjudicated in order that a
right of the plaintiff, which has been violated or invaded by the
defendant, may be vindicated or recognized, and not for the
purpose of indemnifying the plaintiff for any loss suffered by him.
Worth noting is the fact that in Cathays Memorandum filed with this Court,
it prayed only for the deletion of the award for moral damages. It deferred
to the Court of Appeals discretion in awarding nominal damages; thus:
As far as the award of nominal damages is concerned, petitioner
respectfully defers to the Honorable Court of Appeals discretion.
Aware as it is that somehow, due to the resistance of respondentsspouses to the normally-appreciated gesture of petitioner to
upgrade their accommodations, petitioner may have disturbed the
respondents-spouses wish to be with their companions (who
traveled to Hong Kong with them) at the Business Class on their
flight to Manila. Petitioner regrets that in its desire to provide the
respondents-spouses with additional amenities for the one and
one-half (1 1/2) hour flight to Manila, unintended tension ensued. 18
DANILO D. MENDOZA, also doing business under the name and style of
ATLANTIC EXCHANGE PHILIPPINES, petitioner,
vs.
COURT OF APPEALS, PHILIPPINE NATIONAL BANK, FERNANDO
MARAMAG, JR., RICARDO G. DECEPIDA and BAYANI A.
BAUTISTA, respondents.
DE LEON, JR., J.:
Before us is a petition for review on certiorari of the Decision1 dated August
8, 1994 of the respondent Court of Appeals (Tenth Division) in CA-G.R. CV
No. 38036 reversing the judgment2 of the Regional Trial Court (RTC) and
dismissing the complaint therein.
Petitioner Danilo D. Mendoza is engaged in the domestic and international
trading of raw materials and chemicals. He operates under the business
name Atlantic Exchange Philippines (Atlantic), a single proprietorship
registered with the Department of Trade and Industry (DTI). Sometime in
1978 he was granted by respondent Philippine National Bank (PNB) a Five
Hundred Thousand Pesos (P500,000.00) credit line and a One Million Pesos
(P1,000,000.00) Letter of Credit/Trust Receipt (LC/TR) line.
As security for the credit accommodations and for those which may
thereinafter be granted, petitioner mortgaged to respondent PNB the
following: 1) three (3) parcels of land3 with improvements in F. Pasco
Avenue, Santolan, Pasig; 2) his house and lot in Quezon City; and 3)
several pieces of machinery and equipment in his Pasig coco-chemical
plant.
The real estate mortgage4 provided the following escalation clause:
(P40,000.00); and the last dated September 27, 1979 for One Hundred Fifty
Thousand Pesos (P150,000.00). The said 1979 promissory notes uniformly
stipulated: "with interest thereon at the rate of 12% per annum, until paid,
which interest rate the Bank may, at any time, without notice, raise within
the limits allowed by law xxx."5
Petitioner made use of his LC/TR line to purchase raw materials from
foreign importers. He signed a total of eleven (11) documents
denominated as "Application and Agreement for Commercial Letter of
Credit,"6 on various dates from February 8 to September 11, 1979, which
uniformly contained the following clause: "Interest shall be at the rate of
9% per annum from the date(s) of the draft(s) to the date(s) of arrival of
payment therefor in New York. The Bank, however, reserves the right to
raise the interest charges at any time depending on whatever policy it may
follow in the future."7
In a letter dated January 3, 1980 and signed by Branch Manager Fil S.
Carreon Jr., respondent PNB advised petitioner Mendoza that effective
December 1, 1979, the bank raised its interest rates to 14% per annum, in
line with Central Bank's Monetary Board Resolution No. 2126 dated
November 29, 1979.
On March 9, 1981, he wrote a letter to respondent PNB requesting for the
restructuring of his past due accounts into a five-year term loan and for an
additional LC/TR line of Two Million Pesos (P2,000,000.00).8 According to
the letter, because of the shut-down of his end-user companies and the
huge amount spent for the expansion of his business, petitioner failed to
pay to respondent bank his LC/TR accounts as they became due and
demandable.
Ceferino D. Cura, Branch Manager of PNB Mandaluyong replied on behalf of
the respondent bank and required petitioner to submit the following
documents before the bank would act on his request: 1) Audited Financial
Statements for 1979 and 1980; 2) Projected cash flow (cash in - cash out)
for five (5) years detailed yearly; and 3) List of additional machinery and
equipment and proof of ownership thereof. Cura also suggested that
petitioner reduce his total loan obligations to Three Million Pesos
(P3,000,000.00) "to give us more justification in recommending a plan of
payment or restructuring of your accounts to higher authorities of the
Bank."9
On September 25, 1981, petitioner sent another letter addressed to PNB
Vice-President Jose Salvador, regarding his request for restructuring of his
loans. He offered respondent PNB the following proposals: 1) the disposal
of some of the mortgaged properties, more particularly, his house and lot
and a vacant lot in order to pay the overdue trust receipts; 2) capitalization
and conversion of the balance into a 5-year term loan payable semiannually or on annual installments; 3) a new Two Million Pesos
(P2,000,000.00) LC/TR line in order to enable Atlantic Exchange Philippines
to operate at full capacity; 4) assignment of all his receivables to PNB from
all domestic and export sales generated by the LC/TR line; and 5)
maintenance of the existing Five Hundred Thousand Pesos (P500,000.00)
credit line.
The petitioner testified that respondent PNB Mandaluyong Branch found his
proposal favorable and recommended the implementation of the
agreement. However, Fernando Maramag, PNB Executive Vice-President,
disapproved the proposed release of the mortgaged properties and
reduced the proposed new LC/TR line to One Million Pesos
(P1,000,000.00).10 Petitioner claimed he was forced to agree to these
changes and that he was required to submit a new formal proposal and to
sign two (2) blank promissory notes.
In a letter dated July 2, 1982, petitioner offered the following revised
proposals to respondent bank: 1) the restructuring of past due accounts
including interests and penalties into a 5-year term loan, payable semiannually with one year grace period on the principal; 2) payment of Four
Hundred Thousand Pesos (P400,000.00) upon the approval of the proposal;
3) reduction of penalty from 3% to 1%; 4) capitalization of the interest
component with interest rate at 16% per annum; 5) establishment of a One
Million Pesos (P1,000,000.00) LC/TR line against the mortgaged properties;
6) assignment of all his export proceeds to respondent bank to guarantee
payment of his loans.
According to petitioner, respondent PNB approved his proposal. He further
claimed that he and his wife were asked to sign two (2) blank promissory
note forms. According to petitioner, they were made to believe that the
blank promissory notes were to be filled out by respondent PNB to conform
with the 5-year restructuring plan allegedly agreed upon. The first
Promissory Note,11 No. 127/82, covered the principal while the second
Promissory Note,12 No. 128/82, represented the accrued interest.
Petitioner testified that respondent PNB allegedly contravened their verbal
agreement by 1) affixing dates on the two (2) subject promissory notes to
make them mature in two (2) years instead of five (5) years as supposedly
agreed upon; 2) inserting in the first Promissory Note No. 127/82 an
interest rate of 21% instead of 18%; 3) inserting in the second Promissory
Note No. 128/82, the amount stated therein representing the accrued
interest as One Million Five Hundred Thirty Six Thousand Four Hundred
Ninety Eight Pesos and Seventy Three Centavos (P1,536,498.73) when it
should only be Seven Hundred Sixty Thousand Three Hundred Ninety Eight
Pesos and Twenty Three Centavos (P760,398.23) and pegging the interest
rate thereon at 18% instead of 12%.
The subject Promissory Notes Nos. 127/82 and 128/82 both dated
December 29, 1982 in the principal amounts of Two Million Six Hundred
Fifty One Thousand One Hundred Eighteen Pesos and Eighty Six Centavos
(P2,651,118.86) and One Million Five Hundred Thirty Six Thousand Seven
Hundred Ninety Eight and Seventy Three Centavos (P1,536,798.73)
respectively and marked Exhibits "BB" and "CC" respectively, were payable
on equal semi-annual amortization and contained the following escalation
clause:
x x x which interest rate the BANK may increase within the limits
allowed by law at any time depending on whatever policy it may
adopt in the future; Provided, that, the interest rate on this note
shall be correspondingly decreased in the event that the applicable
maximum interest rate is reduced by law or by the Monetary
Board. In either case, the adjustment in the interest rate agreed
upon shall take effect on the effectivity date of the increase or
decrease in the maximum interest rate. x x x
The petitioner filed in the RTC in Pasig, Rizal a complaint for specific
performance, nullification of the extra-judicial foreclosure and damages
against respondents PNB, Fernando Maramag Jr., Ricardo C. Decepida,
Vice-President for Metropolitan Branches, and Bayani A. Bautista. He
alleged that the Extrajudicial Foreclosure Sale of the mortgaged properties
was null and void since his loans were restructured to a five-year term
loan; hence, it was not yet due and demandable; that the escalation
clauses in the subject two (2) Promissory Notes Nos. 127/82 and 128/82
were null and void, that the total amount presented by PNB as basis of the
foreclosure sale did not reflect the actual loan obligations of the plaintiff to
PNB; that Bautista purposely delayed payments on his exports and caused
delays in the shipment of materials; that PNB withheld certain personal
properties not covered by the chattel mortgage; and that the foreclosure of
his mortgages was premature so that he was unable to service his foreign
clients, resulting in actual damages amounting to Two Million Four
Thousand Four Hundred Sixty One Pesos (P 2,004,461.00).
On March 16, 1992, the trial court rendered judgment in favor of the
petitioner and ordered the nullification of the extrajudicial foreclosure of
the real estate mortgage, the Sheriffs sale of the mortgaged real
properties by virtue of consolidation thereof and the cancellation of the
new titles issued to PNB; that PNB vacate the subject premises in Pasig and
turn the same over to the petitioner; and also the nullification of the
extrajudicial foreclosure and sheriff's sale of the mortgaged chattels, and
that the chattels be returned to petitioner Mendoza if they were removed
It appears from the record that the subject Promissory Notes Nos. 127/82
and 128/82 superseded and novated the three (3) 1979 promissory notes
and the eleven (11) 1979 "Application and Agreement for Commercial
Letter of Credit" which the petitioner executed in favor of respondent PNB.
from his Pasig premises or be paid for if they were lost or rendered
unserviceable.
The trial court also ordered respondent PNB to restructure to five-years
petitioner's principal loan of Two Million Six Hundred Fifty One Thousand
One Hundred Eighteen Pesos and Eighty Six Centavos (P2,651,118.86) and
the accumulated capitalized interest on the same in the amount of Seven
Hundred Sixty Thousand Three Hundred Eighty Nine Pesos and Twenty
Three Centavos (P760,389.23) as of December 1982, and that respondent
PNB should compute the additional interest from January 1983 up to
October 15, 1984 only when respondent PNB took possession of the said
properties, at the rate of 12% and 9% respectively.
The trial court also ordered respondent PNB to grant petitioner Mendoza an
additional Two Million Pesos (P2,000,000.00) loan in order for him to have
the necessary capital to resume operation. It also ordered respondents
PNB, Bayani A. Bautista and Ricardo C. Decepida to pay to petitioner actual
damages in the amount of Two Million One Hundred Thirteen Thousand
Nine Hundred Sixty One Pesos (P2,113,961.00) and the peso equivalent of
Six Thousand Two Hundred Fifteen Dollars ($6,215.00) at the prevailing
foreign exchange rate on October 11, 1983; and exemplary damages in the
amount of Two Hundred Thousand Pesos (P200,000.00).
Respondent PNB appealed this decision of the trial court to the Court of
Appeals. And the Court of Appeals reversed the decision of the trial court
and dismissed the complaint. Hence, this petition.
It is the petitioners contention that the PNB management restructured his
existing loan obligations to a five-year term loan and granted him another
Two Million Pesos (P2,000,000.00) LC/TR line; that the Promissory Notes
Nos. 127/82 and 128/82 evidencing a 2-year restructuring period or with
the due maturity date "December 29, 1984" were filled out fraudulently by
respondent PNB, and contrary to his verbal agreement with respondent
PNB; hence, his indebtedness to respondent PNB was not yet due and the
extrajudicial foreclosure of his real estate and chattel mortgages was
premature. On the other hand, respondent PNB denies that petitioner's
loan obligations were restructured to five (5) years and maintains that the
subject two (2) Promissory Notes Nos. 127/82 and 128/82 were filled out
regularly and became due as of December 29, 1984 as shown on the face
thereof.
Respondent Court of Appeals held that there is no evidence of a promise
from respondent PNB, admittedly a banking corporation, that it had
accepted the proposals of the petitioner to have a five-year restructuring of
his overdue loan obligations. It found and held, on the basis of the
evidence adduced, that "appellee's (Mendoza) communications were mere
proposals while the bank's responses were not categorical that the
appellee's request had been favorably accepted by the bank."
Contending that respondent PNB had allegedly approved his proposed fiveyear restructuring plan, petitioner presented three (3) documents executed
by respondent PNB officials. The first document is a letter dated March 16,
1981 addressed to the petitioner and signed by Ceferino D. Cura, Branch
Manager of PNB Mandaluyong, which states:
x x x In order to study intelligently the feasibility of your above
request, please submit the following documents/papers within
thirty (30) days from the date thereof, viz:
1. Audited Financial Statements for 1979 and 1980;
2. Projected cash flow (cash in - cash out) for five years
detailed yearly; and
3. List of additional machinery and equipment and proof of
ownership thereof.
We would strongly suggest, however, that you reduce your total
obligations to at least P3 million (principal and interest and other
charges) to give us more justification in recommending a plan of
payment or restructuring of your accounts to higher authorities of
this bank.
The second document is a letter dated May 11, 1981 addressed to Mr. S. Pe
Benito, Jr., Managing Director of the Technological Resources Center and
signed by said PNB Branch Manager, Ceferino D. Cura. According to
petitioner, this letter showed that respondent PNB seriously considered the
restructuring of his loan obligations to a five-year term loan, to wit:
xxx
At the request of our client, we would like to furnish you with the
following information pertinent to his accounts with us:
xxx
We are currently evaluating the proposal of the client to restructure his accounts with us into a five-year plan.
We hope that the above information will guide you in evaluating
the proposals of Mr. Danilo Mendoza.
xxx
Petitioner argues that he submitted the requirements according to the
instructions given to him and that upon submission thereof, his proposed
five-year restructuring plan was deemed automatically approved by
respondent PNB.
xxx
We disagree.
The third document is a letter dated July 8, 1981 addressed to petitioner
and signed by PNB Assistant Vice-President Apolonio B. Francisco.
xxx
Considering that your accounts/accommodations were granted and
carried in the books of our Mandaluyong Branch, we would suggest
that your requests and proposals be directed to Ceferino Cura,
Manager of our said Branch.
We feel certain that Mr. Cura will be pleased to discuss matters of
mutual interest with you.
xxx
Petitioner also presented a letter which he addressed to Mr. Jose Salvador,
Vice-President of the Metropolitan Branches of PNB, dated September 24,
1981, which reads:
Re: Restructuring of our Account into a 5-year Term Loan and
Request for the Establishment of a P2.0 Million LC/TR Line
Dear Sir:
In compliance with our discussion last September 17, we would like
to formalize our proposal to support our above requested
assistance from the Philippine National Bank.
xxx
Again we wish to express our sincere appreciation for your openminded approach towards the solution of this problem which we
know and will be beneficial and to the best interest of the bank and
mutually advantageous to your client.
proof as to when he acquired the subject movables and hence, we are not
disposed to believe that the same were "after-acquired" chattels not
covered by the chattel and real estate mortgages.
In asserting its rights over the subject movables, respondent PNB relies on
a common provision in the two (2) subject Promissory Notes Nos. 127/82
and 128/82 which states:
In the event that this note is not paid at maturity or when the same
becomes due under any of the provisions hereof, we hereby
authorized the BANK at its option and without notice, to apply to
the payment of this note, any and all moneys, securities and things
of value which may be in its hands on deposit or otherwise
belonging to me/us and for this purpose. We hereby, jointly and
severally, irrevocably constitute and appoint the BANK to be our
true Attorney-in-Fact with full power and authority for us in our
name and behalf and without prior notice to negotiate, sell and
transfer any moneys securities and things of value which it may
hold, by public or private sale and apply the proceeds thereof to
the payment of this note.
It is clear, however, from the above-quoted provision of the said
promissory notes that respondent bank is authorized, in case of default, to
sell "things of value" belonging to the mortgagor "which may be on its
hands for deposit or otherwise belonging to me/us and for this purpose."
Besides the petitioner executed not only a chattel mortgage but also a real
estate mortgage to secure his loan obligations to respondent bank.
A stipulation in the mortgage, extending its scope and effect to afteracquired property is valid and binding where the after-acquired property is
in renewal of, or in substitution for, goods on hand when the mortgage was
executed, or is purchased with the proceeds of the sale of such goods. 30 As
earlier pointed out, the petitioner did not present any proof as to when the
subject movables were acquired.
More importantly, respondent bank makes a valid argument for the
retention of the subject movables. Respondent PNB asserts that those
movables were in fact "immovables by destination" under Art. 415 (5) of
the Civil Code.31 It is an established rule that a mortgage constituted on an
immovable includes not only the land but also the buildings, machinery
and accessories installed at the time the mortgage was constituted as well
as the buildings, machinery and accessories belonging to the mortgagor,
installed after the constitution thereof.32
Petitioner also contends that respondent PNBs bid prices for this
foreclosed properties in the total amount of Three Million Seven Hundred
Ninety Eight Thousand Seven Hundred Nineteen Pesos and Fifty Centavos
(P3,798,719.50), were allegedly "unconscionable and shocking to the
conscience of men". He claims that the fair market appraisal of his
foreclosed plant site together with the improvements thereon located in
Pasig, Metro Manila amounted to Five Million Four Hundred Forty One
Thousand Six Hundred Fifty Pesos (P5,441,650.00) while that of his house
and lot in Quezon City amounted to Seven Hundred Twenty Two Thousand
Pesos (P722,000.00) per the appraisal report dated September 20, 1990 of
Cuervo Appraisers, Inc.33 That contention is not well taken considering that:
This petition for review seeks to annul the decision1 of the Court of Appeals
in CA-G.R. CV No. 49618, reversing the order2 of the Regional Trial Court,
Branch 145, of Makati City which held Eddie C. Olalia liable to BPI Express
Card Corporation (BECC) in the amount of P136,290.97. The CA found only
the amount of P13,883.27 to be due and owing to BECC. Petitioners
motion for reconsideration was denied through a resolution, 3 also before us
on review.
The factual antecedents of this case are as follows:
Petitioner operates a credit card system under the name of BPI Express
Card Corporation (BECC) through which it extends credit accommodations
to its cardholders for the purchase of goods and other services from
member establishments of petitioner to be reimbursed later on by the
cardholder upon proper billing.
Respondent Eddie C. Olalia applied4 for and was granted membership and
credit accommodation with BECC. BECC Card No. 020100-3-00-0281667
was issued in his name with a credit limit of P5,000.
In January 1991, Olalias card expired and a renewal card was issued. BECC
also issued Card No. 020100-2-01-0281667 in the name of Cristina G.
Olalia, respondents ex-wife. This second card was an extension of Olalias
credit card. BECC alleges that the extension card was delivered and
received by Olalia at the same time as the renewal card. However, Olalia
denies ever having applied for, much less receiving, the extension card.
As evidenced by charge slips presented and identified in court, it was
found that the extension card in the name of Cristina G. Olalia was used for
purchases made from March to April 1991, particularly in the province of
Iloilo and the City of Bacolod. Total unpaid charges from the use of this card
amounted to P101,844.54.1wphi1.nt
BECC sent a demand letter to Olalia, to which the latter denied liability
saying that said purchases were not made under his own credit card and
that he did not apply for nor receive the extension card in the name of his
wife. He has likewise not used or allowed anybody in his family to receive
or use the extension card. Moreover, his wife, from whom he was already
divorced, left for the States in 1986 and has since resided there. In
addition, neither he nor Cristina was in Bacolod or Iloilo at the time the
questioned purchases were made. She was dropped as defendant by the
trial court, in an Order dated September 29, 1995.5
A case for collection was filed by BECC before the RTC but Olalia only
admits responsibility for the amount of P13,883.27, representing purchases
made under his own credit card. After trial on the merits, a decision was
rendered as follows:
WHEREFORE, judgment is rendered ordering defendant Eddie C.
Olalia to pay plaintiff the sum of Thirteen Thousand Eight Hundred
Eighty-Three Pesos and Twenty-seven Centavos (P13,883.27),
Philippine Currency with interest thereon at the legal rate from June
18, 1991, until fully paid; and to pay the costs.
SO ORDERED.6
From the aforesaid decision, a Motion for Reconsideration was filed,
alleging that Olalia should also be held liable for the purchases arising from
the use of the extension card since he allegedly received the same, as
evidenced by his signature appearing in the Renewal Card
Acknowledgement Receipt7 and by the express provision of paragraph 2 of
the terms and conditions governing the use and issuance of a BPI Express
Card, making the cardholder and his extension jointly and severally liable
for all purchases and availments made through the use of the card.
On April 28, 1995, the Motion for Reconsideration was granted and an
Order was issued, stating:
Defendant Eddie C. Olalia has not filed any reaction paper up to
the present relative to plaintiffs MOTION FOR RECONSIDERATION
dated December 20, 1994.
Finding the allegations in said motion to be meritorious, the same
is hereby granted.
WHEREFORE, the dispositive portion of the decision dated
November 25, 1994, is reconsidered and accordingly
amended/corrected to read as follows:
WHEREFORE, judgment is rendered ordering defendant
Eddie C. Olalia to pay plaintiff the sum of One Hundred
Thirty Six Thousand Two Hundred Ninety Pesos and Ninetyseven Centavos (P136,290.97) Philippine Currency, as of
October 27, 1991.
SO ORDERED.8
SO ORDERED.
Herein petitioners, Spouses Domingo Paguyo and Lourdes Paguyo, were
the owners of a small five-storey building known as the Paguyo Building
located at Makati Avenue, corner Valdez Street, Makati City. With one (1)
unit per floor, the building has an average area of 100 square meters per
floor and is constructed on a land belonging to the Armas family. 5
This lot on which the Paguyo Building stands was the subject of Civil Case
No. 5715 entitled, Armas, et al., v. Paguyo, et al., wherein the RTC of Makati
City, Branch 57, rendered a decision on 20 January 1988 approving a
Compromise Agreement made between the Armases and the petitioners.
The compromise agreement provided that in consideration of the total sum
of One Million Seven Hundred Thousand Pesos (P1,700,000.00), the
Armases committed to execute in favor of petitioners a deed of sale and/or
conveyance assigning and transferring unto said petitioners all their rights
and interests over the parcel of land containing an area of 299 square
meters.6
In order for the petitioners to complete their title and ownership over the
lot in question, there was an urgent need to make complete payment to
the Armases, which at that time stood at P917,470.00 considering that
petitioners had previously made partial payments to the Armases.
On 29 November 1988, in order to raise the much needed amount,
petitioner Lourdes Paguyo entered into an agreement captioned
as Receipt of Earnest Money with respondent Pierre Astorga, for the
sale of the formers property consisting of the lot which was to be
purchased from the Armases, together with the improvements thereon,
particularly, the existing building known as the Paguyo Building, under the
following terms and conditions as stated in the document, to wit:
RECEIVED from MR. PIERRE M. ASTORGA the sum of FIFTY THOUSAND
(P50,000.00) PESOS (U.C.P.B. Managers Check No. 013085 dated
November 29, 1988) as earnest money for the sale of our property
consisting of a parcel of land designated as Lot 12 located at Makati
Avenue, Makati, Metro Manila, covered by and described in T.C.T. No.
154806 together with the improvements thereon particularly the existing
building known as the Paguyo Bldg. under the following terms and
conditions:
1. The earnest money (Exh. "D") shall be good for fifteen (15) days from
date of this document during which period the owner is bound to sell the
property to the buyer;
2. Should the buyer decide not to buy the subject property within the
earnest/option period, the seller has the right to forfeit Fifteen Thousand
(P15,000.00) pesos, and return the difference to the buyer;
3. The agreed total purchase price is seven million (P7,000,000.00) pesos
Philippine Currency;
4. Within fifteen (15) days from execution of this document, the buyer shall
pay Fifty (50%) percent of the total purchase price less the aforesaid
earnest money, upon payment of which the following documents shall be
executed or caused to be executed as the case may be, namely:
a. Deed of Absolute Sale of the Paguyo Bldg., in favor of the buyer.
b. Deed of Absolute Sale to be executed by the Armases who still appear
as the registered owners of the lot in favor of the buyer.
c. Deed of Real Estate Mortgage of the same subject lot and Bldg. to
secure the 50% balance of the total purchase price to be executed by the
buyer in favor of the herein seller.
5. The Deed of Real Estate Mortgage shall contain the following provisions,
namely:
a. payment of the 50% balance of the purchase price shall be payable
within fifteen (15) days from actual vacating of the Armases from the
subject lot.
b. During the period commencing from the execution of the documents
mentioned under paragraph 4 (which should be done simultaneously) the
buyer is entitled to one-half (1/2) of the rental due and actually received
from the tenants of the Paguyo Bldg. plus the use of the penthouse while
the seller shall retain possession and use of the basement free of rent until
the balance of the purchase price is fully paid in accordance with the
herein terms and conditions. The one-half (1/2) of the tenants deposits
shall be credited in favor of the buyer. 7
However, contrary to their express representation with respect to the
subject lot, petitioners failed to comply with their obligation to acquire the
lot from the Armas family despite the full financial support of respondents.
Nevertheless, the parties maintained their business relationship under the
terms and conditions of the above-mentioned Receipt of Earnest Money. 8
Avenue, the particulars and description of which are indicated on TCT No.
154806 which, for reasons we perceive to be not legitimate, was cancelled.
...
(SGD.) HECTOR B. ALMEYDA
For the Firm21
(Emphasis supplied.)
3. P100,00.00 for attorneys fees and litigation expenses and pay the cost
of suit.24
Q: There was statement here by Mrs. Paguyo that this document entitled
the deed of absolute sale of a building marked Exhibit "9" was not
expressive of the intention of the parties meaning to say that she did not
intend to sell the said building and one of the reasons she tried to raise
was the fact that the building was only sold for P500,000.00, what can you
say to that?
A: Well, the P500,000.00 amount that she would want to impress to be an
inadequate amount is what we in St. Andrews end believed as value for
money for the reason that the building stands on the lot she does
not own and there were separate owners and apparent conflict
between them even the seeming impossibility of getting the lot
Q: By the way, before the plaintiffs decided to dispose the building or sell
the building by virtue of this deed of sale marked Exhibit "98" was your
company ever interested in acquiring the said building?
A: The building alone, no. In fact, on December 21 when we had the
problem as to acquiring the lot, we did not part with any payment to Mrs.
Paguyo demonstrating that we had really and truly intended a
simultaneous buy of the building and the lot to acquire the property
simultaneously the building and as well as the lot.
Q: Now, you mentioned that you are a realtor, I will ask you the same
question, which Atty. Almeyda asked me when I was on the witness stand,
as a realtor will you please tell the court what would be your appraisal of
the value of the building?
A: Okay, appraisal can take many forms if its appraised value based on the
construction cost it could be different from appraising per se the building.
That is now existing in that address also appraisal will depend on where
the building is and there is only one owner of the building and the lot. As
the case here is, the building in a manner of speaking stands on thin air.
That is so including depreciation and timing that we were doing in this
transaction which was 1989, my appraisal will be in the range of a Million
may be.
Q: You made mentioned the word timing in 1989, why did you mention
that?
A: Well, 89 was not the best real estate year. In fact, we have a boom in
1988 but prices were already deep during this year such that it is in 1988
when it could have been another price. But this transaction happened or
entered into in 1989, there were no interested buyers during that time, sir.
Q: Why?
A: coup de etat was one, and many other issue on hand that causes value
to take deep.
Q: You mentioned that word depreciation, will you please explain to us
what that depreciation has got to do with that building?
ATTY. COLOMA
Q: Before you went into this agreement with the plaintiff Paguyo have you
inspected the building?
COURT
Q: Will you please explain to the court the size of the building and the
description of the building?
WITNESS
ATTY. JOSE
A: That building is five (5) storey it has only one (1) unit per floor, sir. There
is a narrow stairway that leads up to the penthouse. It is, I would say, in an
advance deteriorating stage, it needed some renovations here and
there.29(Emphasis supplied.)
WITNESS
executed the receipt of the earnest money with me. Now, during the
transaction of this subject matter, you will also recall that at times you
were represented in dealing with me as counsel for defendant corporation
by Atty. Lalin and Atty. Carino?
A Yes, sir.32
Neither does the fact that the subject contracts have been prepared by
respondents ipso facto entail that their validity and legality be strictly
interpreted against them. Petitioner Lourdes Paguyos insinuation that she
was disadvantaged will not hold. True, Article 24 of the New Civil Code
provides that "(i)n all contractual, property or other relations, when one of
the parties is at a disadvantage on account of his moral dependence,
ignorance, indigence, mental weakness, tender age or other handicap, the
courts must be vigilant for his protection."33 Thus, the validity and/or
enforceability of the impugned contracts will have to be determined by the
peculiar circumstances obtaining in each case and the situation of the
parties concerned.
Here, petitioner Lourdes Paguyo, being not only cultured but a person with
great business acumen as well, cannot claim to be the weaker or
disadvantaged party in the subject contract so as to call for a strict
interpretation against respondents. More importantly, the parties herein
went through a series of negotiations before the documents were signed
and executed.34
Further, we find the stipulations in the subject documents plain and
unambiguous. For instance, the Deed of Sale provides in no uncertain
termsWHEREAS, the VENDOR is the true and absolute owner, free from any lien
or encumbrance, of a concrete building presently known as the Paguyo
Building, constructed on Lot 12, Blk. 4 (described in T.C.T No. 154806Makati) located at No. 7856 Makati Ave. corner Valdez St., Makati, Metro
Manila, covered by and described in Tax Declaration No. 93762 for the year
1984, and more particularly described as follows:
Thus, the amount of moral damages should be set at only P30,000.00, and
the award of exemplary damages at only P20,000.00. The award of
attorneys fees should also be reduced to P20,000.00 which, under the
circumstances of this case, appears justified and reasonable.
All told, we find no reason to reverse the assailed decision of respondent
court. The factual findings of the appellate court are conclusive on the
parties and carry greater weight when they coincide with the factual
findings of the trial court.43 This Court will not weigh the evidence anew
lest there is a showing that the findings of the lower court are totally
devoid of support or are clearly erroneous so as to constitute serious abuse
of discretion. In the instant case, the trial court found that the documents,
which petitioners seek to rescind, were entered into as a result of an armslength transaction. These are factual findings that are now conclusive upon
us.44
WHEREFORE, the Decision and the Resolution dated 30 April 1997 and 12
September 1997, respectively, of the Court of Appeals in CA-G.R. CV No.
47034, are hereby AFFIRMED with MODIFICATION as to the amount of
damages and attorneys fees recoverable, as follows: (1) moral
damages is reduced to P30,000.00, (2) exemplary damages is reduced
to P20,000.00, and (3) attorneys fees is reduced to P20,000.00. Costs
against petitioners.
SO ORDERED.
We have held that moral damages may be recovered in cases where one
willfully causes injury to property, or in cases of breach of contract where
the other party acts fraudulently or in bad faith.37 There is no hard and fast
rule in the determination of what would be a fair amount of moral
damages, since each case must be governed by its own peculiar
circumstances.38 Exemplary damages, on the other hand, are imposed by
way of example or correction for the public good, when the party to a
contract acts in a wanton, fraudulent, oppressive or malevolent
manner.39 Attorneys fees are allowed when exemplary damages are
awarded and when the party to a suit is compelled to incur expenses to
protect his interest.40
While it has been sufficiently proven that the respondents are entitled to
damages, the actual amounts awarded by the lower court must be reduced
because damages are not intended for a litigants enrichment, at the
expense of the petitioners.41 Judicial discretion granted to the courts in the
assessment of damages must always be exercised with balanced restraint
and measured objectivity.42
The respondent corporation denied all these, claiming that upon the
petitioners retirement, he received the amount of P6,902,387.19
representing all the benefits due him. Despite this, the petitioner again
demandedP7,080,546.00, which demand was without factual and legal
basis. The respondent corporation asserted that the chairman of its board
of directors and its president/vice-president had unlimited discretion in the
use of their time, and had never been required to file applications for
vacation and sick leaves; as such, the said officers were not entitled to
vacation and sick leave benefits. The respondent corporation, likewise,
pointed out that even if the petitioner was entitled to the said additional
benefits, his claim had already prescribed. It further averred that it had no
policy to grant vacation and sick leave credits to the petitioner. 6
In his Affidavit7 dated May 19, 1998, Lim denied making any such verbal
promise to his son-in-law on the grant of unlimited vacation and sick leave
credits and the cash conversion thereof. Lim averred that the petitioner
had received vacation and sick leave benefits from 1994 to 1996.
Moreover, assuming that he did make such promise to the petitioner, the
same had not been confirmed or approved via resolution of the respondent
corporations board of directors.
It was further pointed out that as per the Memorandum dated November 6,
1981, only regular employees and managerial and confidential employees
falling under Category I were entitled to vacation and sick leave credits.
The petitioner, whose position did not fall under Category I, was, thus, not
entitled to the benefits under the said memorandum. The respondent
corporation alleged that this was admitted by the petitioner himself and
affirmed by Raoul Rodrigo, its incumbent executive vice-president and
general manager.
In a Decision8 dated November 27, 1998, the Labor Arbiter ruled in favor of
the petitioner. The fallo of the decision reads:
WHEREFORE, all the foregoing premises being considered, judgment is
hereby rendered ordering the respondent company to pay complainant the
sum of P7,080,546.00, plus ten percent (10%) thereof as and for attorneys
fees.
SO ORDERED.9
Undaunted, the respondent corporation appealed the decision to the NLRC,
alleging that:
Aggrieved, the petitioner filed a petition for review with the CA, on the
following grounds:
I
the same, especially considering that such privileges are not inherent to
the positions occupied by the petitioner in the respondent corporation, sonin-law of its president or not.
Under Rule 45 of the Rules of Court, only questions of law may be raised
under a petition for review on certiorari. The Court, not being a trier of
facts, is not wont to reexamine and reevaluate the evidence of the parties,
whether testimonial or documentary. Moreover, the findings of facts of the
CA on appeal from the NLRC are, more often than not, given conclusive
effect by the Court. The Court may delve into and resolve factual issues
only in exceptional circumstances, such as when the findings of facts of the
Labor Arbiter, on one hand, and those of the NLRC and the CA, on the
other, are capricious and arbitrary; or when the CA has reached an
erroneous conclusion based on arbitrary findings of fact; and when
substantial justice so requires. In this case, however, the petitioner failed
to convince the Court that the factual findings of the CA which affirmed the
findings of the NLRC on appeal, as well as its conclusions based on the said
findings, are capricious and arbitrary.
Except for his bare assertions, petitioner has not adduced sufficient
evidence to support his claim that he was, indeed, promised the cash
conversion of his unused vacation and sick leaves upon retirement.
Petitioner harps on what he calls the prevalent practice in PCMC of giving
him benefits, such as the use of golf and country club facilities, salary
increases, the use of the company vehicle and driver, and sharing in
PCMCs annual net income, without either a written contract or a Board
resolution to back it up. Respondent PCMC denies all these, however.
According to respondent, petitioners share in the income of the company
is actually part of the consultancy fee which PCMC pays DK Management
Services, Inc., a firm owned by petitioners company. PCMC adds that the
yearly salary increases of corporate officers were always with the prior
approval of the Board.
Nevertheless, assuming that petitioner was, indeed, given the benefits
which he so claimed, it does not necessarily follow that among those is the
cash conversion of his accumulated leaves. It is a basic rule in evidence
that each party must prove his affirmative allegation. Since the burden of
proof lies with the party who asserts an affirmative allegation, the plaintiff
or complainant has to prove his affirmative allegations in the complaint
and the defendant or respondent has to prove the affirmative allegations in
his affirmative defenses and counterclaim. Petitioner, in the case at bar,
has failed to discharge this burden.26
The CA made short shift of the claim of the petitioner that per
Memorandum dated November 6, 1981, he was not entitled to the benefits
of the company policy of commutation of leave credits. Indeed, the
company policy of conversion into equivalent cash of unused vacation and
sick leave credits applied only to its regular employees. The petitioner
failed to offer evidence to rebut the testimony of Nel Gopez, Chief
Accountant of the respondent, that the petitioner was not among the
regular employees covered by the policy for the simple reason that he had
And would you know, Mr. Witness, why he is (sic) not given the conversion
of the vacation leave benefits at the time category one employees sectors
(sic) are given?
ATTY. PIMENTEL
WITNESS
And, so you mention[ed] earlier that the policy on vacation leave
benefits apply for category one employee(s) and rank-and-file
employee(s)?
Yes.
ATTY. PIMENTEL
ATTY. PIMENTEL
ATTY. PIMENTEL
ATTY. PIMENTEL
How about the complainant, Mr. Kwok, does he falling (sic) to the category
one?
WITNESS
WITNESS
Yes, right.
ATTY. PIMENTEL
ATTY. PIMENTEL
WITNESS
WITNESS
Yes, Maam.
ATTY. PIMENTEL
granting PCMC employees the conversion of their unused vacation and sick
leaves into cash.27
We have reviewed the records and found no evidence to controvert the
following findings of the CA and its ratiocinations on its resolution of the
petitioners submissions:
Second, even assuming that petitioner is included among the "regular
employees" of PCMC referred to in said memorandum, there is no evidence
that he complied with the cut-off dates for the filing of the cash conversion
of vacation and sick leaves. This being so, we find merit in respondents
argument that petitioners money claims have already been barred by the
three-year prescriptive period under Article 291 of the Labor Code, as
amended.
Third, and this is of primordial importance, there is no proof that petitioner
has filed vacation and sick leaves with PCMCs personnel department.
Without a record of petitioners absences, there is no way to determine the
actual number of leave credits he is entitled to. The P7,080,546.00 figure
arrived at by petitioner supposedly representing the cash equivalent of his
earned sick and vacation leaves is thus totally baseless.
And, fourth, even assuming that PCMC President Patricio Lim did promise
petitioner the cash conversion of his leaves, we agree with respondent that
this cannot bind the company in the absence of any Board resolution to
that effect. We must stress that the personal act of the company president
cannot bind the corporation. As explicitly stated by the Supreme Court
in Peoples Aircargo and Warehousing Co., Inc. v. Court of Appeals:
"The general rule is that, in the absence of authority from the board of
directors, no person, not even its officers, can validly bind a corporation. A
corporation is a juridical person, separate and distinct from its stockholders
and members, having xxx powers, attributes and properties expressly
authorized by law or incident to its existence.
" the power and the responsibility to decide whether the corporation
should enter into a contract that will bind the corporation is lodged in the
board, subject to the articles of incorporation, by-laws, or relevant
provisions of law."
Anent the third assigned error, petitioner maintains that the PCMC Board of
Directors has granted its President, Patricio Lim, awesome powers to grant
benefits to its employees, adding that the Board has always given its
consent to the way Lim ran the affairs of the company especially on
matters relating to the benefits that its corporate officers enjoyed.
True, jurisprudence holds that the president of a corporation possesses the
power to enter into a contract for the corporation when "the conduct on
the part of both the president and corporation [shows] that he had been in
the habit of acting in similar matters on behalf of the company and that
the company had authorized him so to act and had recognized, approved
and ratified his former and similar actions."
In the case at bar, however, there is no showing that PCMC had either
recognized, approved or ratified the cash conversion of petitioners leave
credits as purportedly promised to him by Lim. On the contrary, PCMC has
steadfastly maintained that "the Company, through the Board, has long
adopted the policy of granting its earlier mentioned corporate officers
unlimited leave benefits denying them the privilege of converting their
unused vacation or sick leave benefits into their cash equivalent."
As to the last assigned error, petitioner faults the NLRC for holding as
applicable to petitioner, the April 26, 1997 Memorandum issued by PCMC
to Raoul Rodrigo, Donald Kwoks successor as company executive vicepresident. The said memo granted Rodrigo unlimited sick and vacation
leave credits but disallowed the cash conversion thereof. Before he
became executive vice-president, Rodrigo was senior vice-president and
enjoyed the commutation of his unused vacation and sick leaves.
We note that the April 26, 1997 memo was issued to Rodrigo when
petitioner was already retired from PCMC. While said memorandum was
particularly directed to Rodrigo, however, this does not necessarily mean
that petitioner, as former executive vice-president, was then not prohibited
from converting his earned vacation and sick leaves into cash since he was
not issued a similar memo. On the contrary, the memo simply affirms the
long-standing company practice of excluding PCMCs top two positions,
that of president and executive vice-president, from the commutation of
leaves. As heretofore discussed, among the perks of those occupying these
posts is the privilege of having unlimited leaves, which is totally
incompatible with the concept of converting unused leave credits into their
cash equivalents.28
We are not convinced by the petitioners claim that Lim capriciously
deprived him of his entitlement to the cash conversion of his accumulated
vacation and sick leave credits simply because of his estrangement from
his wife, who happens to be Lims daughter. The petitioner did not adduce
any evidence to show that he appealed to the respondent corporations
board of directors for the implementation of the said privilege which was
allegedly granted to him. Even if Lim was the president and chairman of
the respondent corporations board of directors, the rest of the
membership of the board could have overruled him and granted to the
petitioner his claim if, indeed, the latter was entitled thereto. Indeed, even
the petitioner admitted that, after his retirement, the board of directors
granted to him salary increase for two years prior to his retirement. If the
claim of the petitioner had been approved by the board of directors, for
sure, it would have approved the same despite his falling out with the
daughter of Lim.
IN LIGHT OF ALL THE FOREGOING, the petition is DENIED for lack of
merit. Costs against the petitioner. SO ORDERED.
There is grave abuse of discretion (1) when an act is done contrary to the
Constitution, the law or jurisprudence;1or (2) when it is executed
whimsically, capriciously or arbitrarily out of malice, ill will or personal
bias.2 In the present case, the Commission on Elections approved the
assailed Resolution and awarded the subject Contract not only in clear
violation of law and jurisprudence, but also in reckless disregard of its own
bidding rules and procedure. For the automation of the counting and
canvassing of the ballots in the 2004 elections, Comelec awarded the
Contract to "Mega Pacific Consortium" an entity that had not participated
in the bidding. Despite this grant, the poll body signed the actual
automation Contract with "Mega Pacific eSolutions, Inc.," a company that
joined the bidding but had not met the eligibility requirements.
Comelec awarded this billion-peso undertaking with inexplicable haste,
without adequately checking and observing mandatory financial, technical
and legal requirements. It also accepted the proferred computer hardware
and software even if, at the time of the award, they had undeniably failed
to pass eight critical requirements designed to safeguard the integrity of
elections, especially the following three items:
They failed to achieve the accuracy rating criteria of 99.9995
percent set-up by the Comelec itself
second envelope would be the Bid Envelope itself. The RFP outlines the
bidding procedures as follows:
"25. Determination of Eligibility of Prospective Bidders
"25.1 The eligibility envelopes of prospective Bidders shall
be opened first to determine their eligibility. In case any of
the requirements specified in Clause 20 is missing from the
first bid envelope, the BAC shall declare said prospective
Bidder as ineligible to bid. Bid envelopes of ineligible
Bidders shall be immediately returned unopened.
"25.2 The eligibility of prospective Bidders shall be
determined using simple pass/fail criteria and shall be
determined as either eligible or ineligible. If the
prospective Bidder is rated passed for all the legal,
technical and financial requirements, he shall be
considered eligible. If the prospective Bidder is rated
failed in any of the requirements, he shall be considered
ineligible.
"26. Bid Examination/Evaluation
"26.1 The BAC will examine the Bids to determine whether
they are complete, whether any computational errors have
been made, whether required securities have been
furnished, whether the documents have been properly
signed, and whether the Bids are generally in order.
We can imagine that anyone else standing in the shoes of the Honorable
Commissioners would have been extremely conscious of the overarching
need for utter transparency. They would have scrupulously avoided the
slightest hint of impropriety, preferring to maintain an exacting regularity
in the performance of their duties, instead of trying to break a speed
record in the award of multi-billion-peso contracts. After all, between April
15 and April 21 were a mere six (6) days. Could Comelec not have waited
out six more days for the written report of the BAC, instead of rushing pellmell into the arms of MPC? Certainly, respondents never cared to explain
the nature of the Commissions dire need to act immediately without
awaiting the formal, written BAC Report.
In short, the Court finds it difficult to reconcile the uncommon dispatch
with which Comelec acted to approve the multi-billion-peso deal, with its
claim of having been impelled by only the purest and most noble of
motives.
At any rate, as will be discussed later on, several other factors combine to
lend negative credence to Comelecs tale.
Second, without necessarily ascribing any premature malice or
premeditation on the part of the Comelec officials involved, it should
nevertheless be conceded that this cart-before-the-horse maneuver
(awarding of the Contract ahead of the BACs written report) would
definitely serve as a clever and effective way of averting and frustrating
any impending protest under Section 55.
Having made the foregoing observations, we now go back to the question
of exhausting administrative remedies. Respondents may not have realized
it, but the letter addressed to Chairman Benjamin Abalos Sr. dated May 29,
200328 serves to eliminate the prematurity issue as it was an actual written
protest against the decision of the poll body to award the Contract. The
letter was signed by/for, inter alia, two of herein petitioners: the
The only logical conclusion is that no such agreement was ever submitted
to the Comelec for its consideration, as part of the bidding process.
Two-Envelope,
Two-Stage System
As stated earlier in our factual presentation, the public bidding system
designed by Comelec under its RFP (Request for Proposal for the
Automation of the 2004 Election) mandated the use of a two-envelope,
two-stage system. A bidders first envelope (Eligibility Envelope) was
meant to establish its eligibility to bid and its qualifications and capacity to
perform the contract if its bid was accepted, while the second envelope
would be the Bid Envelope itself.
The Eligibility Envelope was to contain legal documents such as articles of
incorporation, business registrations, licenses and permits, mayors permit,
VAT certification, and so forth; technical documents containing
documentary evidence to establish the track record of the bidder and its
technical and production capabilities to perform the contract; and financial
documents, including audited financial statements for the last three years,
to establish the bidders financial capacity.
In the case of a consortium or joint venture desirous of participating in the
bidding, it goes without saying that the Eligibility Envelope would
necessarily have to include a copy of the joint venture agreement, the
consortium agreement or memorandum of agreement -- or a business plan
or some other instrument of similar import -- establishing the due
existence, composition and scope of such aggrupation. Otherwise, how
would Comelec know who it was dealing with, and whether these parties
are qualified and capable of delivering the products and services being
offered for bidding?32
In the instant case, no such instrument was submitted to Comelec during
the bidding process. This fact can be conclusively ascertained by
scrutinizing the two-inch thick "Eligibility Requirements" file submitted by
Comelec last October 9, 2003, in partial compliance with this Courts
instructions given during the Oral Argument. This file purports to replicate
the eligibility documents originally submitted to Comelec by MPEI allegedly
on behalf of MPC, in connection with the bidding conducted in March 2003.
Included in the file are the incorporation papers and financial statements of
the members of the supposed consortium and certain certificates, licenses
and permits issued to them.
However, there is no sign whatsoever of any joint venture agreement,
consortium agreement, memorandum of agreement, or business plan
executed among the members of the purported consortium.
It thus follows that, prior the award of the Contract, there was no
documentary or other basis for Comelec to conclude that a consortium had
actually been formed amongst MPEI, SK C&C and WeSolv, along with
Election.com and ePLDT.33 Neither was there anything to indicate the exact
relationships between and among these firms; their diverse roles,
undertakings and prestations, if any, relative to the prosecution of the
project, the extent of their respective investments (if any) in the supposed
consortium or in the project; and the precise nature and extent of their
respective liabilities with respect to the contract being offered for bidding.
And apart from the self-serving letter of March 7, 2003, there was not even
any indication that MPEI was the lead company duly authorized to act on
behalf of the others.
So, it necessarily follows that, during the bidding process, Comelec had no
basis at all for determining that the alleged consortium really existed and
was eligible and qualified; and that the arrangements among the members
were satisfactory and sufficient to ensure delivery on the Contract and to
protect the governments interest.
Notwithstanding such deficiencies, Comelec still deemed the "consortium"
eligible to participate in the bidding, proceeded to open its Second
Envelope, and eventually awarded the bid to it, even though -- per the
Comelecs own RFP -- the BAC should have declared the MPC ineligible to
bid and returned the Second (Bid) Envelope unopened.
Inasmuch as Comelec should not have considered MPEI et al. as comprising
a consortium or joint venture, it should not have allowed them to avail
themselves of the provision in Section 5.4 (b) (i) of the IRR for RA 6957 (the
Build-Operate-Transfer Law), as amended by RA 7718. This provision states
in part that a joint venture/consortium proponent shall be evaluated based
on the individual or collective experience of the member-firms of the joint
venture or consortium and of the contractor(s) that it has engaged for the
project. Parenthetically, respondents have uniformly argued that the said
IRR of RA 6957, as amended, have suppletory application to the instant
case.
Hence, had the proponent MPEI been evaluated based solely on its own
experience, financial and operational track record or lack thereof, it would
surely not have qualified and would have been immediately considered
ineligible to bid, as respondents readily admit.
At any rate, it is clear that Comelec gravely abused its discretion in
arbitrarily failing to observe its own rules, policies and guidelines with
respect to the bidding process, thereby negating a fair, honest and
competitive bidding.
Section 1.4 to shore up the MOAs and the Teaming Agreements is simply
unwarranted.
Third and last, we fail to see how respondents can arrive at the conclusion
that, from the above-quoted provisions, it can be immediately established
that each of the members of MPC assumes the same joint and several
liability as the other members. Earlier, respondents claimed exactly the
opposite -- that the two MOAs (between MPEI and SK C&C, and between
MPEI and WeSolv) had set forth the joint and several undertakings among
the parties; whereas the two Teaming Agreements clarified the parties
respective roles with regard to the Project, with MPEI being the
independent contractor and Election.com and ePLDT the subcontractors.
Obviously, given the differences in their relationships, their respective
liabilities cannot be the same. Precisely, the very clear terms and
stipulations contained in the MOAs and the Teaming Agreements -- entered
into by MPEI with SK C&C, WeSolv, Election.com and ePLDT -- negate the
idea that these "members" are on a par with one another and are, as such,
assuming the same joint and several liability.
Moreover, respondents have earlier seized upon the use of the term
"particular contract" in the Comelecs Request for Proposal (RFP), in order
to argue that all the members of the joint venture did not need to be
solidarily liable for the entire project or joint venture. It was sufficient that
the lead company and the member in charge of a particular contract or
aspect of the joint venture would agree to be solidarily liable. The glaring
lack of consistency leaves us at a loss. Are respondents trying to establish
the same joint and solidary liability among all the "members" or not?
Enforcement of Liabilities Problematic
Next, it is also maintained that the automation Contract between Comelec
and the MPEI confirms the solidary undertaking of the lead company and
the consortium member concerned for each particular Contract, inasmuch
as the position of MPEI and anyone else performing the services
contemplated under the Contract is described therein as that of an
independent contractor.
complications that it would produce. Hence, the Article states that the role
or position of MPEI, or anyone else performing on its behalf, is that of an
independent contractor. It is obvious to the Court that respondents are
stretching matters too far when they claim that, because of this provision,
the Contract in effect confirms the solidary undertaking of the lead
company and the consortium member concerned for the particular phase
of the project. This assertion is an absolute non sequitur.
Enforcement of Liabilities Under the Civil Code Not Possible
In any event, it is claimed that Comelec may still enforce the liability of the
"consortium" members under the Civil Code provisions on partnership,
reasoning that MPEI et al. represented themselves as partners and
members of MPC for purposes of bidding for the Project. They are,
therefore, liable to the Comelec to the extent that the latter relied upon
such representation. Their liability as partners is solidary with respect to
everything chargeable to the partnership under certain conditions.
The Court has two points to make with respect to this argument. First, it
must be recalled that SK C&C, WeSolv, Election.com and ePLDT never
represented themselves as partners and members of MPC, whether for
purposes of bidding or for something else. It was MPEI alone that
represented them to be members of a "consortium" it supposedly headed.
Thus, its acts may not necessarily be held against the other "members."
Second, this argument of the OSG in its Memorandum 44 might possibly
apply in the absence of a joint venture agreement or some other writing
that discloses the relationship of the "members" with one another. But
precisely, this case does not deal with a situation in which there is nothing
in writing to serve as reference, leaving Comelec to rely on mere
representations and therefore justifying a falling back on the rules on
partnership. For, again, the terms and stipulations of the MOAs entered
into by MPEI with SK C&C and WeSolv, as well as the Teaming Agreements
of MPEI with Election.com and ePLDT (copies of which have been furnished
the Comelec) are very clear with respect to the extent and the limitations
of the firms respective liabilities.
The Court does not see, however, how this conclusion was arrived at. In
the first place, the contractual provision being relied upon by respondents
is Article 14, "Independent Contractors," which states: "Nothing contained
herein shall be construed as establishing or creating between the
COMELEC and MEGA the relationship of employee and employer or
principal and agent, it being understood that the position of MEGA and of
anyone performing the Services contemplated under this Contract, is that
of an independent contractor."
In the case of WeSolv and SK C&C, their MOAs state that their liabilities,
while joint and several with MPEI, are limited only to the particular areas of
work wherein their services are engaged or their products utilized. As for
Election.com and ePLDT, their separate "Teaming Agreements" specifically
ascribe to them the role of subcontractor vis--vis MPEI as contractor and,
based on the terms of their particular agreements, neither Election.com
nor ePLDT is, with MPEI, jointly and severally liable to Comelec. 45 It follows
then that in the instant case, there is no justification for anyone, much less
Comelec, to resort to the rules on partnership and partners liabilities.
Obviously, the intent behind the provision was simply to avoid the creation
of an employer-employee or a principal-agent relationship and the
"2. Mega Pacific shall have full powers and authority to represent
the Consortium with the Comelec, and to enter and sign, for and in
behalf of its members any and all agreement/s which maybe
required in the implementation of the Project.
"3. Each of the individual members of the Consortium shall be
jointly and severally liable with the Lead Firm for the particular
products and/or services supplied by such individual member for
the project, in accordance with their respective undertaking or
sphere of responsibility.
"4. Each party shall bear its own costs and expenses relative to this
agreement unless otherwise agreed upon by the parties.
"5. The parties undertake to do all acts and such other things
incidental to, necessary or desirable for the attainment of the
objectives and purposes of this Agreement.
"6. Any dispute arising from this Agreement shall be settled
amicably by the parties whenever possible. Should the parties be
unable to do so, the parties hereby agree to settle their dispute
through arbitration in accordance with the existing laws of the
Republic of the Philippines." (Underscoring supplied.)
It will be noted that the two Agreements quoted above are very similar in
wording. Neither of them contains any specifics or details as to the exact
nature and scope of the parties respective undertakings, performances
and deliverables under the Agreement with respect to the automation
project. Likewise, the two Agreements are quite bereft of pesos-andcentavos data as to the amount of investments each party contributes, its
respective share in the revenues and/or profit from the Contract with
Comelec, and so forth -- all of which are normal for agreements of this
nature. Yet, according to public and private respondents, the participation
of MPEI, WeSolv and SK C&C comprises fully 90 percent of the entire
undertaking with respect to the election automation project, which is worth
about P1.3 billion.
As for Election.com and ePLDT, the separate "Teaming Agreements" they
entered into with MPEI for the remaining 10 percent of the entire project
undertaking are ironically much longer and more detailed than the MOAs
discussed earlier. Although specifically ascribing to them the role of
subcontractor vis--vis MPEI as contractor, these Agreements are,
however, completely devoid of any pricing data or payment terms. Even
the appended Schedules supposedly containing prices of goods and
services are shorn of any price data. Again, as mentioned earlier, based on
the terms of their particular Agreements, neither Election.com nor ePLDT -with MPEI -- is jointly and severally liable to Comelec.
Note: This
particular
requiremen
needs furthe
verification
Let us now move to the second subtopic, which deals with the substantive
issue: the ACMs failure to pass the tests of the Department of Science and
Technology (DOST).
After respondent "consortium" and the other bidder, TIM, had submitted
their respective bids on March 10, 2003, the Comelecs BAC -- through its
Technical Working Group (TWG) and the DOST -- evaluated their technical
6. Machine can detect previously counted ballots
proposals. Requirements that were highly technical in nature and that
and prevent previously counted ballots from
required the use of certain equipment in the evaluation process were
being counted more than once?
referred to the DOST for testing. The Department reported thus:
7. Stores results of counted votes by precinct in
external (removable) storage device?
TEST RESULTS MATRIX
Note: This
particular
requiremen
needs furthe
verification
47
MEGA-PACIFIC
CONSORTIUM
YES
NO
TOTAL
8. Data stored in external media is encrypted?
INFORMATION
MANAGEMENT
YES
Note: This
particular
requiremen
needs furthe
verification
NO
media?
Note: This
particular
requirement
needs further
verification
nerates printouts
requirement
needs further
verification
Note: This
particular
requiremen
needs furthe
verification
Note: This
particular
requiremen
needs furthe
verification
rd copy
ft copy
requiremen
needs furthe
verification
Note: This
particular
requirement
needs further
verification
Note: This
particular
Note: This
particular
requiremen
needs furthe
verification
Note: This
particular
requiremen
needs furthe
verification
dit Trail
Audit Trail
Note: This
particular
requiremen
needs furthe
verification
Note: This
particular
requirement
needs
further
27. Can
the results of the
verification
provincial/district/national
consolidation be stored
in a data storage device?
Note: This
particular
requiremen
needs furthe
verification
Note: This
particular
requirement
needs further
verificationAccording to respondents, it was only after the TWG and the DOST had
conducted their separate tests and submitted their respective reports that
the BAC, on the basis of these reports formulated its
comments/recommendations on the bids of the consortium and TIM.
Note: ThisThe BAC, in its Report dated April 21, 2003, recommended that the Phase II
particularproject involving the acquisition of automated counting machines be
awarded to MPEI. It said:
requirement
needs further
verification
"After incisive analysis of the technical reports of the DOST and the
Note: This
particular
requirement
needs further
verification
"In the DOST test, TIM obtained 12 failed marks and mostly
attributed to the counting machine itself as stated earlier. These
are requirements of the RFP and therefore the BAC cannot
disregard the same.
"Mega-Pacific failed in 8 items however these are mostly on the
software which can be corrected by reprogramming the software
and therefore can be readily corrected.
"The BAC verbally inquired from DOST on the status of the retest of
the counting machines of the TIM and was informed that the report
will be forthcoming after the holy week. The BAC was informed that
the retest is on a different parameters theyre being two different
machines being tested. One purposely to test if previously read
ballots will be read again and the other for the other features such
as two sided ballots.
"The said machine and the software therefore may not be
considered the same machine and program as submitted in the
Technical proposal and therefore may be considered an
enhancement of the original proposal.
The BAC, however, also stated on page 4 of its Report: "Based on the 14
April 2003 report (Table 6) of the DOST, it appears that both Mega-Pacific
and TIM (Total Information Management Corporation) failed to meet some
of the requirements. Below is a comparative presentation of the
requirements wherein Mega-Pacific or TIM or both of them failed: x x x."
What followed was a list of "key requirements," referring to technical
requirements, and an indication of which of the two bidders had failed to
meet them.
The first of the key requirements was that the counting machines were to
have an accuracy rating of at least 99.9995 percent. The BAC Report
indicates that both Mega Pacific and TIM failed to meet this standard.
Mega-Pacific:
But that grim prospect is not all. The BAC Report, on pages 6 and 7,
indicate that the ACMs of both bidders wereunable to print the audit
trail without any loss of data. In the case of MPC, the audit trail system
was "not yet incorporated" into its ACMs.
At this point, the Court stresses that the essence of public bidding is
violated by the practice of requiring very high standards or unrealistic
specifications that cannot be met -- like the 99.9995 percent accuracy
rating in this case -- only to water them down after the bid has been award.
Such scheme, which discourages the entry of prospective bona fide
bidders, is in fact a sure indication of fraud in the bidding, designed to
eliminate fair competition. Certainly, if no bidder meets the mandatory
requirements, standards or specifications, then no award should be made
and a failed bidding declared.
This particular deficiency is significant, not only to this bidding but to the
cause of free and credible elections. The purpose of requiring audit trails is
to enable Comelec to trace and verify the identities of the ACM operators
responsible for data entry and downloading, as well as the times when the
various data were downloaded into the canvassing system, in order to
forestall fraud and to identify the perpetrators.
Thus, the RFP on page 27 states that the ballot counting machines and
ballot counting software must print an audit trail of all machine operations
for documentation and verification purposes. Furthermore, the audit trail
must be stored on the internal storage device and be available on demand
for future printing and verifying. On pages 30-31, the RFP also requires that
the city/municipal canvassing system software be able to print an audit
trail of the canvassing operations, including therein such data as the date
and time the canvassing program was started, the log-in of the authorized
users (the identity of the machine operators), the date and time the
canvass data were downloaded into the canvassing system, and so on and
so forth. On page 33 of the RFP, we find the same audit trail requirement
with respect to the provincial/district canvassing system software; and
again on pages 35-36 thereof, the same audit trail requirement with
respect to the national canvassing system software.
That this requirement for printing audit trails is not to be lightly brushed
aside by the BAC or Comelec itself as a mere formality or technicality can
be readily gleaned from the provisions of Section 7 of RA 8436, which
authorizes the Commission to use an automated system for elections.
The said provision which respondents have quoted several times, provides
that ACMs are to possess certain features divided into two classes: those
that the statute itself considers mandatory and other features or
capabilities that the law deems optional. Among those considered
mandatory are "provisions for audit trails"! Section 7 reads as follows: "The
System shall contain the following features: (a) use of appropriate ballots;
(b) stand-alone machine which can count votes and an automated system
which can consolidate the results immediately; (c) with provisions for
audit trails; (d) minimum human intervention; and (e) adequate
safeguard/security measures." (Italics and emphases supplied.)
In brief, respondents cannot deny that the provision requiring audit trails is
indeed mandatory, considering the wording of Section 7 of RA 8436.
Neither can Respondent Comelec deny that it has relied on the BAC Report,
which indicates that the machines or the software was deficient in that
respect. And yet, the Commission simply disregarded this shortcoming and
awarded the Contract to private respondent, thereby violating the very law
it was supposed to implement.
C.
Inadequacy of Post Facto Remedial Measures
Respondents argue that the deficiencies relating to the detection of
previously downloaded data, as well as provisions for audit trails, are mere
shortcomings or minor deficiencies in software or programming, which can
be rectified. Perhaps Comelec simply relied upon the BAC Report, which
states on page 8 thereof that "Mega Pacific failed in 8 items[;] however
these are mostly on the software which can be corrected by reprogramming x x x and therefore can be readily corrected."
The undersigned ponentes questions, some of which were addressed to
Commissioner Borra during the Oral Argument, remain unanswered to this
day. First of all, who made the determination that the eight "fail" marks of
Mega Pacific were on account of the software -- was it DOST or TWG? How
can we be sure these failures were not the results of machine defects? How
was it determined that the software could actually be re-programmed and
thereby rectified? Did a qualified technical expert read and analyze
the source code49 for the programs and conclude that these could be saved
and remedied? (Such determination cannot be done by any other means
save by the examination and analysis of the source code.)
Who was this qualified technical expert? When did he carry out the study?
Did he prepare a written report on his findings? Or did the Comelec just
make a wild guess? It does not follow that all defects in software programs
can be rectified, and the programs saved. In the information technology
sector, it is common knowledge that there are many badly written
programs, with significant programming errors written into them; hence it
does not make economic sense to try to correct the programs; instead,
programmers simply abandon them and just start from scratch. Theres no
telling if any of these programs is unrectifiable, unless a qualified
programmer reads the source code.
And if indeed a qualified expert reviewed the source code, did he also
determine how much work would be needed to rectify the programs? And
how much time and money would be spent for that effort? Who would
carry out the work? After the rectification process, who would ascertain and
how would it be ascertained that the programs have indeed been properly
rectified, and that they would work properly thereafter? And of course, the
most important question to ask: could the rectification be done in time for
the elections in 2004?
Clearly, none of the respondents bothered to think the matter through.
Comelec simply took the word of the BAC as gospel truth, without even
bothering to inquire from DOST whether it was true that the deficiencies
pleadings, though -- including the DOST reports submitted to this Court -have not heretofore mentioned any statement, allegation or representation
to the effect that a particular set of software was to be developed and/or
delivered by the supplier in connection with the testing and acceptance of
delivered ACMs.
What the records do show is that the imported ACMs were subjected to the
testing and acceptance process conducted by the DOST. Since the initial
batch delivered included a high percentage of machines that had failed the
tests, Comelec asked the DOST to conduct a 100 percent testing; that is, to
test every single one of the ACMs delivered. Among the machines tested
on October 8 to 18, 2003, were some units that had failed previous tests
but had subsequently been re-tested and had passed. To repeat, however,
until now, there has never been any mention of a second set or type of
software pertaining to the testing and acceptance process.
In any event, apart from making that misplaced and uncorroborated claim,
Comelec in the same submission also professes (in response to the
concerns expressed by this Court) that the reprogrammed software
has been tested and found to have complied with the
requirements of RA 8436. It reasoned thus: "Since the software
program is an inherent element in the automated counting system, the
certification issued by the MIRDC-DOST that one thousand nine hundred
seventy-three (1,973) units passed the acceptance test procedures is an
official recognition by the MIRDC-DOST that the software component of the
automated election system, which has been reprogrammed to comply with
the provisions of Republic Act No. 8436 as prescribed in the Ad Hoc
Technical Evaluation Committees ACM Testing and Acceptance Manual,
has passed the MIRDC-DOST tests."
Project Director
"Dear Commissioner Borra:
"We are pleased to submit 11 DOST Test Certifications representing
11 lots and covering 158 units of automated counting machines
(ACMs) that we have tested from 02-12 December 2003.
"To date, we have tested all the 1,991 units of ACMs, broken down
as follow: (sic)
1st batch - 30 units 4th batch - 438 units
2nd batch - 288 units 5th batch - 438 units
3rd batch - 414 units 6th batch - 383 units
"It should be noted that a total of 18 units have failed the test. Out
of these 18 units, only one (1) unit has failed the retest.
"Thank you and we hope you will find everything in order.
"Very truly yours,
"ROLANDO T. VILORIA, CESO III
Executive Director cum
The fact that a total of 1,973 of the machines has ultimately passed the
MIRDC-DOST tests does not by itself serve as an endorsement of the
soundness of the software program, much less as a proof that it has been
reprogrammed. In the first place, nothing on record shows that the tests
and re-tests conducted on the machines were intended to address the
serious deficiencies noted earlier. As a matter of fact, the MIRDC-DOST
letter does not even indicate what kinds of tests or re-tests were
conducted, their exact nature and scope, and the specific objectives
thereof.53 The absence of relevant supporting documents, combined with
the utter vagueness of the letter, certainly fails to inspire belief or to justify
the expansive confidence displayed by Comelec. In any event, it goes
without saying that remedial measures such as the alleged reprogramming
cannot in any way mitigate the grave abuse of discretion already
committed as early as April 15, 2003.
Rationale of Public Bidding Negated
by the Third Type of Software
Respondent Comelec tries to assuage this Courts anxiety in these words:
"The reprogrammed software that has already passed the requirements of
Republic Act No. 8436 during the MIRDC-DOST testing and acceptance
procedures will require further customization since the following additional
elements, among other things, will have to be considered before the final
software can be used on election day: 1. Final Certified List of Candidates x
x x 2. Project of Precincts x x x 3. Official Ballot Design and Security
Features x x x 4. Encryption, digital certificates and digital signatures x x
x. The certified list of candidates for national elective positions will be
finalized on or before 23 January 2004 while the final list of projects of
precincts will be prepared also on the same date. Once all the above
elements are incorporated in the software program, the Test Certification
Group created by the Ad Hoc Technical Evaluation Committee will conduct
meticulous testing of the final software before the same can be used on
election day. In addition to the testing to be conducted by said Test
Certification Group, the Comelec will conduct mock elections in selected
areas nationwide not only for purposes of public information but also to
further test the final election day program. Public respondent Comelec,
therefore, requests that it be given up to 16 February 2004 to comply with
this requirement."
The foregoing passage shows the imprudent approach adopted by Comelec
in the bidding and acquisition process. The Commission says that before
the software can be utilized on election day, it will require "customization"
through addition of data -- like the list of candidates, project of precincts,
and so on. And inasmuch as such data will become available only in
January 2004 anyway, there is therefore no perceived need on Comelecs
part to rush the supplier into producing the final (or near-final) version of
the software before that time. In any case, Comelec argues that the
software needed for the electoral exercise can be continuously developed,
tested, adjusted and perfected, practically all the way up to election day,
at the same time that the Commission is undertaking all the other distinct
and diverse activities pertinent to the elections.
Given such a frame of mind, it is no wonder that Comelec paid little
attention to the counting and canvassing software during the entire
bidding process, which took place in February-March 2003. Granted that
the software was defective, could not detect and prevent the re-use of
previously downloaded data or produce the audit trail -- aside from its
other shortcomings -- nevertheless, all those deficiencies could still be
corrected down the road. At any rate, the software used for bidding
purposes would not be the same one that will be used on election day, so
why pay any attention to its defects? Or to the Comelecs own bidding
rules for that matter?
Clearly, such jumbled ratiocinations completely negate the rationale
underlying the bidding process mandated by law.
At the very outset, the Court has explained that Comelec flagrantly
violated the public policy on public biddings (1) by allowing MPC/MPEI to
participate in the bidding even though it was not qualified to do so; and (2)
by eventually awarding the Contract to MPC/MPEI. Now, with the latest
explanation given by Comelec, it is clear that the Commission further
desecrated the law on public bidding by permitting the winning bidder to
change and alter the subject of the Contract (the software), in effect
allowing a substantive amendment without public bidding.
This stance is contrary to settled jurisprudence requiring the strict
application of pertinent rules, regulations and guidelines for public bidding
for the purpose of placing each bidder, actual or potential, on the same
footing. The essence of public bidding is, after all, an opportunity for fair
competition, and a fair basis for the precise comparison of bids. In common
parlance, public bidding aims to "level the playing field." That means each
bidder must bid under the same conditions; and be subject to the same
guidelines, requirements and limitations, so that the best offer or lowest
bid may be determined, all other things being equal.
Thus, it is contrary to the very concept of public bidding to permit a
variance between the conditions under which bids are invited and those
under which proposals are submitted and approved; or, as in this case, the
conditions under which the bid is won and those under which the awarded
Contract will be complied with. The substantive amendment of the contract
bidded out, without any public bidding -- after the bidding process had
been concluded -- is violative of the public policy on public biddings, as
well as the spirit and intent of RA 8436. The whole point in going through
the public bidding exercise was completely lost. The very rationale of
public bidding was totally subverted by the Commission.
From another perspective, the Comelec approach also fails to make sense.
Granted that, before election day, the software would still have to be
Epilogue
Once again, the Court finds itself at the crossroads of our nations history.
At stake in this controversy is not just the business of a computer supplier,
or a questionable proclamation by Comelec of one or more public officials.
Neither is it about whether this country should switch from the manual to
the automated system of counting and canvassing votes. At its core is the
ability and capacity of the Commission on Elections to perform properly,
legally and prudently its legal mandate to implement the transition from
manual to automated elections.
Unfortunately, Comelec has failed to measure up to this historic task. As
stated at the start of this Decision, Comelec has not merely gravely abused
its discretion in awarding the Contract for the automation of the counting
and canvassing of the ballots. It has also put at grave risk the holding of
credible and peaceful elections by shoddily accepting electronic hardware
and software that admittedly failed to pass legally mandated technical
requirements. Inadequate as they are, the remedies it proffers post facto
do not cure the grave abuse of discretion it already committed (1) on April
15, 2003, when it illegally made the award; and (2) "sometime" in May
2003 when it executed the Contract for the purchase of defective machines
and non-existent software from a non-eligible bidder.
For these reasons, the Court finds it totally unacceptable and
unconscionable to place its imprimatur on this void and illegal transaction
that seriously endangers the breakdown of our electoral system. For this
Court to cop-out and to close its eyes to these illegal transactions, while
convenient, would be to abandon its constitutional duty of safeguarding
public interest.
As a necessary consequence of such nullity and illegality, the purchase of
the machines and all appurtenances thereto including the still-to-beproduced (or in Comelecs words, to be "reprogrammed") software, as well
as all the payments made therefor, have no basis whatsoever in law. The
public funds expended pursuant to the void Resolution and Contract must
therefore be recovered from the payees and/or from the persons who made
possible the illegal disbursements, without prejudice to possible criminal
prosecutions against them.
Furthermore, Comelec and its officials concerned must bear full
responsibility for the failed bidding and award, and held accountable for
the electoral mess wrought by their grave abuse of discretion in the
performance of their functions. The State, of course, is not bound by the
mistakes and illegalities of its agents and servants.
True, our country needs to transcend our slow, manual and archaic
electoral process. But before it can do so, it must first have a diligent and
competent electoral agency that can properly and prudently implement a
well-conceived automated election system.
At bottom, before the country can hope to have a speedy and fraud-free
automated election, it must first be able to procure the proper
computerized hardware and software legally, based on a transparent and
valid system of public bidding. As in any democratic system, the ultimate
goal of automating elections must be achieved by a legal, valid and aboveboard process of acquiring the necessary tools and skills therefor. Though
the Philippines needs an automated electoral process, it cannot accept just
any system shoved into its bosom through improper and illegal methods.
As the saying goes, the end never justifies the means. Penumbral
contracting will not produce enlightened results.
SO ORDERED.