Académique Documents
Professionnel Documents
Culture Documents
TABLE OF CONTENTS
1- INTRODUCTION
2- Scope of work
3- SITE DATA
3.1- Climate
3.1.1-Location
3.1.2-Elevation:
3.1.3- Atmosphere:
3.1.4- Temperatures:
3.1.5- Wind:
3.1.6- Humidity:
3.1.7- Rainfall:
3.1.8- Earth Quake:
4- APPLICABLE CODES, STANDARDS AND PRACTICE
5- Basis of Design
5.1- Feed Composition & Rates
TP
REV.
PAGE:
7- Preliminary P&IDs
8- Tie-in Points
8.1-Feed Raw Gas
8.2-Condensate Feed
8.3-Naphtha Rundown to Storage
8.4-C3
8.5-LPG
8.6-Sales Gas
8.7-Potable water
8.8-Fire water
8.9-Cable power
9- Special Considerations
9.1-Waxy Condensate
9.2-Desalter System;
10- Plant Performance Test & Process Guarantees
10.1- Plant Throughput
10.2- Plant Production
10.2.1-Feed at Design Rate
10.2.1.1- Raw Gas
10.2.1.2-Condensate to stabilizer
10.2.2- Raw Gas and Condensate Feed at Lower than
Design Rate
10.2.2.1- Raw Gas
10.2.2.2- Condensate To the Stabilizer
10.2.3-Product Specification
10.2.3.1- C3 Specification
10.2.3.2-LPGspecification
TP
REV.
PAGE:
10.2.3.3-Sales Gas
10.2.3.4-Stable Condensate (Naphtha)Specification
10.2.3.5- Stabilizer production specification
11-Process Calculations
12.1-Process Simulations
12.2-Flare System Design
12-Subsystems And Utilities
12.1- Process Control System PCS
12.2- Telecommunications and Security Systems
12.3- Electrical Network
12.4- Propane Refrigeration
12.5- Heating Oil Unit
12.6- Flare and blow down
12.7- Instrument air system
12.8- Fire water and water cooling system
12.9- Fuel gas system
12.10- Draining system
12.11- POTABLE WATER
12.12-Inert or Purge Gas
12.13-Heating, Ventilating and Air Conditioning (HVAC)
12.14- Instr. Air system
13-Civil Design
14-Summary
TP
REV.
PAGE:
TP
REV.
PAGE:
1- INTRODUCTION
Sirte Oil Company, for Production Manufacturing of Oil and Gas plans, is
Plant to replace the existing gas plant built in 1967 consist from two
trails, the capacity for each one is 250000 MMSCFD, this gas plant
handling the raw gas from Naser, Wadi, Jebel, lehib and raguba
facilities and the sour condensate from Attahady and Hateba..
facilities at the field, the composition and the amount of the raw gas
clear as per the table 1.The composition and the amount of the sour
condensate in the table 2. The product from the gas plant as per the
table 3. Since this gas plant was constructed in years 1967 As badly
weathered affected and damaged by a severe corrosive and generally
hostile environment (rough sea and sand storms), the lifetime for this
gas plan is roughly finished, so its required to build new gas plant
able to replace this gas plant and handling the raw gas from Naser,
Wadi, Jebel, lehib and raguba facilities at the field with new Gas
Plant capacity f 150 MMSCFD. We take in our consideration the
production capacity of 2015 and 2016.
TP
REV.
PAGE:
2- Scope of work
The scope of this document is providing the basic process
information to enable the consultant services engineering company
to provide technical and project Management services to the New
Gas Plant project up to the award of Front End Engineering Design
and include the following:
i.
ii.
iii.
iv.
v.
vi.
TP
REV.
PAGE:
3- SITE DATA
3.1- Climate
3.1.1-Location
The Gas Plant is located at Marsa El Brega, which is right on
the coast of the Gulf of Sirte. There is a main road that links
Brega with Tripoli to the west and Benghazi to the east.
Marsa El Brega has port facilities of international standards.
The environmental conditions for the equipment will be open
air in a salt laden corrosive seacoast atmosphere with strong
winds blowing fine sand, high solar radiation and with
occasional torrential rains. Moisture condensation is
experienced on various surfaces at night. The atmosphere
may contain traces of hydrogen sulphide and ammonia from
time to time. The subsoil contains salt and sulphates.
The map location has been attached.
3.1.2-Elevation:
3 meter above sea level.
Attached site location layout
3.1.3- Atmosphere:
Sea side, very corrosive, salty,
occasionally very humid, salty and dusty.
3.1.4- Temperatures:
High :
Low :
TP
REV.
PAGE:
3.1.5- Wind:
Prevailing direction
Mean velocity
Design
Particulates born
:
:
:
:
from N-NW
18 to 35 mph.
90 mph.
by sand storms
(up to 15days per year)
3.1.6- Humidity:
High
Low
Average
3.1.7- Rainfall:
:
:
Annual
Monthly
Hourly
Stormy
:
:
:
:
16.7 in , max.
6.6 in, max.
1in, max.
1in /hr for 9hrs.
TP
REV.
PAGE:
ISA
API
NFPA
/NFC
EMI
OCIMF
IMO
ISO
IEC
WHO
OSHA
ASME/ANSI
ASTM
AWS
TP
REV.
PAGE:
NACE
SSPC
SOC-BP
5- Basis of Design
5.1- Feed Composition & Rates
5.1.1- Feed Sour Gas Composition & Rates
The Raw Gas produced from field facilities Naser, Wadi, Jebel, lehib
and raguba Facilities, these five raw gas products will combined in one
stream to feed the new Gas Plant at one time the composition of the
Raw gas from field facilities as indicated below.
The Gas Plant must be designed to process the companied gas at feed
rate of 150 MMSCFD where we put in the consideration the future
increasing of the production.
The gas should be treated using MDEA technology where we used this
technology in the existing plant unless the consultant company
suggests better solution, depending on the expected H2S and CO2 in
the feed Raw Gas
The production of the gas plant will be Treated Gas, C3, LPG and
Condensate.
Treated Gas will be sent to Petrochemical or Coastal Pipeline
C3 will send to the existing Storage Tanks, where we already using it.
LPG will send to the existing Storage Tanks where it already exists
TP
REV.
PAGE:
Componen
t
Raw Gas
From
Raw Gas
Raw Gas
Raw Gas
Raw Gas
From
From
From
From
comm
Wadi
Jebel
Lehib
Ragub
on
Raw
Naser
Actual
Gas
Nitrogen
0.206739
0.0045
0.005859
0.014000
0.010562
0.021245
CO2
0.08976
0.060100
0.001313
0.049200
0.016142
0.027706
H2S
0.013837
0.0000
0.000000
0.0000
0.000000
0.000820
H2O
0.013837
0.0000
0.000000
0.00000
0.000000
0.004888
Methane
0.582533
0.591300
0.797677
0.744600
0.695297
0.735589
Ethane
0.119811
0.1700
0.113232
0.109600
0.147868
0.118870
Propane
0.029627
0.091400
0.05101
0.046000
0.085492
0.053131
i-Butane
0.005535
0.018600
0.007071
0.010000
0.013153
0.009500
n-Butane
0.005372
0.031900
0.013333
0.014200
0.021921
0.015282
i-Pentane
0.0002574
0.01170
0.003535
0.004700
0.003587
0.004558
n-Pentane
0.001202
0.009100
0.002828
0.004400
0.001993
0.003757
n-Hexane
0.001317
0.005500
0.002222
0.003300
0.003986
0.002988
n-Heptane
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
n-Octane
0.001668
0.005900
0.002828
0.0000000
0.000000
0.001666
n-Nonane
0.0000000
0.000000
0.000000
0.0000000
0.000000
0.000000
TP
REV.
PAGE:
Total
100.00
100.00
100
100
100.00
Average
85
85
85
85
85
Temperatur
Average
290
290
290
290
290
100.00
Pressure(psi
Flow
Table 1
5.1.2- Sour Feed Condensate Composition & Rates
The condensate produced from field facilities Attahady, Hateiba
.Facilities, these condensate products will combined in one stream to
feed the stabilizer in the new Gas Plant at one time.
The maximum condensate feed rate from the field facilities to the
Stabilizer is expected to be 20 MBPD. The design feed rate to the
Stabilizer should be 30 MBPD.
The normal operating pressure of the condensate at the inlet to the
stabilizer is between .. psia and psia, and the average
temperature is between 55-90 F, depending on winter and summer
conditions. The average temperature is expected to be around 70 F.
The condensate stream from time to time, could contains free water
with a high salt content ( the possibility to utilize the existing new
Desalter should be checked, to remove any trace of water and salt that
may be present in the condensate , we attached the desalter data sheet,
P&ID and other related drawing).
We have to be sure that the condensate is always at a safe operating
margin above the condensate bubble point pressure to prevent flashing
of the condensate.
Composition of the condensate as its attached in the table 2
There are two feed compositions that need to be considered. These are:
TP
REV.
PAGE:
Condensate from
Attahady
Nitrogen
0.000
0.000699
CO2
0.013401
0.012077
H2S
0.00000
0.001996
H2O
0.000000
0.000000
Methane
0.0888809
0.070466
Ethane
0.042304
0.09948
Propane
0.086609
0.141731
i-Butane
0.041504
0.060285
n-Butane
0.048405
0.120571
i-Pentane
0.048205
0.090428
n-Pentane
0.034903
0.090428
n-Hexane
0.077408
0.140633
n-Heptane
0.086609
0.040024
n-Octane
0.081108
0.080347
TP
REV.
PAGE:
n-Nonane
0.062106
0.030143
n-Decane
0.075208
0.040224
n-C11
0.032003
0.000000
n-C12
0.024402
0.000000
n-C13
0.026603
0.000000
n-C14
0.019202
0.000000
n-C15
0.017702
0.000000
n-C16
0.013201
0.000000
n-C17
0.012001
0.000000
n-C18
0.010601
0.000000
n-C19
0.009601
0.000000
n-C20
0.009201
0.000000
n-C21
0.005501
0.000000
n-C22
0.005201
0.000000
n-C23
0.00460
0.000000
n-C24
0.004200
0.000000
n-C25
0.003800
0.000000
n-C26
0.002700
0.000000
n-C27
0.002200
0.000000
n-C28
0.001800
0.000000
n-C29
0.001600
0.000000
n-C30
0.007301
0.000000
Total
100.00
100.00
Average Temperature, ( F)
Average Pressure(psia)
500
Flow
20 MBPD
Table 2
12.5 MBPD
TP
REV.
PAGE:
TP
REV.
PAGE:
TP
REV.
PAGE:
will be mixed with the condensate from the separation drum before the
propane chiller and both streams will be delivered in one stream as feed
to the De Ethanizer unit, after reducing the stream pressure from about
585 psia to about 505 psia.
The re-boiler at the De-Ethanizer column will use hot oil as heating
effluent, unless the Consultant Engineering Company will advice in
different heating agent, if Consultant engineering company have
different advice should be discussed with the company f or approval.
The overhead stream at the De-Ethanizer will be cooled by propane
cooler up to 20 or 23 F (the consultant engineering company should
make their study to find out the optimum cooling temperature and
condition at the De-Ethanazer column) the stream at the top of the
De-Ethanizer will be directed to the separator to separate the C1& C2
gas, and liquid to be used as reflex, The C1& C2 stream from the top
products stream of the De-Ethanizer where this stream pressure about
500 psia and temperature is about 25F ( this gas stream could be used
as coolant to the top of De-Propanizer column stream, consultant
engineering to check this possibility where it could be more
efficient) will be directed to companied with the suction side of the
second compression stage.
The condensate at the bottom of the De-Ethanizer will be delivered to
the De-propanizer column, after reducing the condensate stream
pressure from about 500 psia to about 300 psia, where propane should
be separated from this condensate stream at the De-Propanizer .
The boiler at the bottom of De-Propanizer Column should use heated
oil as heating effluent unless Consultant engineering advice
TP
REV.
PAGE:
TP
REV.
PAGE:
TP
REV.
PAGE:
5.3-Turndown Requirements
The gas plant and stabilizer unit may not operate at this high feed rate
all the time. Therefore, whenever the feed rate is lower, the units shall
TP
REV.
PAGE:
be capable of processing the raw gas, at the same efficiency in the gas
plant, also condensate at stabilizer unit.
The gas plant and stabilizer unit shall be able to operate with a feed rate
down to 25% of the design rate defined earlier. The gas plant shall
operate in the range 150 MMSCFD down to 47.5 MMSCFD, and the
stabilizer shall be operated 30 MBPD down to 7.5 MBPD of feed rate
without loss of efficiency.
6- PFDs with Heat & Material Balances
Process Flow Diagrams with heat and material balances for the Gas
Plant also for stabilizer with the two cases.
a) Heavy Case
b) Light Case
Should be carried by the consultant engineering, the process should be
optimized to the optimum design criteria.
The main objective should be to maximize the C3 and LPG from the
raw gas in the gas plant, produce Sales Gas, C3, LPG and naphtha
within the specification, while minimizing the utility consumption. It
should be borne in mind, that the Gas Plant and the Stabilizer will
operate in parallel and continually, also we should be able to operate
one of them at the time. The PFD should be completed with heat and
material balance table for each of the mentioned referenced cases.
Consultant engineering company to provide, optimum process scheme
for an economic viewpoint and from simplicity and ease of operation.
We have attached simple PFD for your reference.
TP
REV.
PAGE:
7- Preliminary P&IDs
Preliminary P&IDs should basically show the major control loops and
provides an insight into the way wants to control and operate the Gas
plant and the Stabilizer. Preliminary hydraulic calculations should be
carried out.
8- Tie-in Points
The design and Process operating conditions at the tie-in points for the
major process streams in the Gas Plant and Stabilizer are defined as
below:
.. F Average
psia
F
..in
Location of the tie-in point clear in the attached P&ID and layout
drawing no
Raw gas composition as its in the attached table 1.
8.2-Condensate Feed
The compositions and the process operation conditions of the feed
condensate at the tie-in point
Operating pressure
TP
REV.
PAGE:
psia
Pipe design pressure for the pipe
Operating Temperature is
Design temperature for is
Pipe diameter at the tie-in
psia
70 F Average
. F
in
8.4-C3
TP
REV.
PAGE:
The compositions and the design & process operation conditions of the
C3 to storage at the tie-in point:
Tie-in point design pressure .psia
Tie-in point operating pressure .psia
Tie-in point operating temperature F
8.5-LPG
Tie-in point design pressure .psia
Tie-in point operating pressure .psia
Tie-in point design temperature F
Tie-in point operating temperature F
Pipe diameter at the tie-in point is in
Location of the tie-in point clear in the attached P&ID and
layout drawing no
Composition of the LPG to the storage as its clear in the Product
Specification section
8.6-Sales Gas
TP
REV.
PAGE:
The compositions and the design & process operation conditions of the
Sales Gas at the tie-in point:
Tie-in point design pressure .psia
Tie-in point operating pressure .psia
Tie-in point design temperature F
Tie-in point operating temperature F
8.7-Potable water
Design condition and location of the Potable water
Tie-in point design pressure .psia
Tie-in point design temperature .. F
Pipe diameter at the tie-in point is .in
Tie-in Operating pressure..psia
Tie-in Operating temperature.. F
Location of the tie-in point clear in the attached P&ID and
layout drawing no
8.8-Fire water
Design condition and location of the Fire water
Tie-in point design pressure .psia
TP
REV.
PAGE:
8.9-Cable power
9- Special Considerations
9.1-Waxy Condensate
The condensate from Attahaddy field, contains between 7-10 wt% wax,
as determined by analytical method UOP 46, carried out on
atmospheric condensate sample, with the light ends flashed off.
The waxy Attahaddy condensate flows, in the main 16 condensate
pipeline from the field facilities to Brega. A paraffin dispersant
chemical, EC-6002A supplied by Nalco, is added at Attahaddy plant
facility, to inhibit the potential of wax building up in the 16 pipeline.
The chemical acts as a surfactant. It coats the wax particles, and
prevents them from agglomerating and minimizes their adherence to
the pipe wall.
Since Nalco chemical EC-6002A does not depress the pour point of the
waxy Attahaddy condensate, a suitable pour point depressant is
currently being sought to overcome any potential problem that may
TP
REV.
PAGE:
surface with the onset of winter. The cooler ambient temperatures are
likely to fall below the natural pour point of the waxy condensate, and
the naphtha product. Naphtha product is also a concern since wax that
accompanies the Attahaddy condensate ends up, after processing, in the
naphtha product to storage.
During the design of the facility the presence of wax should be
considered. For example, all instruments, sight glasses, dead legs, etc,
wherein wax is likely to be encountered/deposited must be protected
by, for example, electric tracing. Pressure gauges must be protected by
diaphragms to prevent wax from coming into contact with the gauge
internals.
Designer should consider skid mounted chemical injection system
comprising of suitably sized tank , pumps one in operation and stand
by, instrumentation, lines, etc to enable a wax dispersant chemical or a
pour point depressant chemical to be injected to maintain specific
concentration of the chemical in the naphtha product to storage.
9.2-Desalter System;
The possibility to utilize the existing desalter system with capacity of
55 MBPD should be considered, the desalter system data sheet,
specification and P&ID and layout drawing attached to this document.
TP
REV.
PAGE:
The plant performance test should be carried out as below, this as per
SOC request. If Consultant Engineering Company advice with any
extra beneficiary requirement for SOC or any correction should
discussed with SOC.
The plant performance test, shall be carried out within six months,
from the date of transfer of custody and responsibility of the plant to
the COMPANY.
The performance test will be carried out by the COMPANY. The
performance test shall be of 72 hours continuous duration, or shorter at
the sole discretion of the COMPANY. The test shall evaluate/confirm
the performance of Compressors units, MDEA Gas Treatment unit
Propane chiller unit, the De-Ethanizer tower, De-Propanizer tower, DeButanizer tower, Operation, also the Stabilizer tower operating with
Heavy and Light feed compositions and a composition in-between, and
a feed rate between 150 MMSCFD and 37.5 MMSCFD for the Gas
Plant and 30MBPD and 7,5 MBPD, depending upon the availability of
the condensate for the stabilizer.
Detailed procedure for the performance tests shall be developed by
CONTRACTOR and will be reviewed and approved by the
COMPANY.
The performance tests shall be carried out in accordance with the
approved procedures in order to determine whether the plant performs
in accordance with the design. The performance tests shall not only
enable the evaluation and verification of the performance of the overall
plant but of each item of equipment within the plant.
TP
REV.
PAGE:
TP
REV.
PAGE:
the performance test was indeed successful, COMPANY will issue the
provisional certificate.
It is recognized that exact duplication of the design conditions and
analyses serving the basis for guarantees may be improbable under
actual field conditions. Therefore, if actual conditions and analyses
vary from those used in the design calculations in sufficient degree to
influence the performance and efficiency of the plant, the gas feed and
condensate feed composition and rate obtained during the test run shall
be used as the basis for process calculations and the rerunning of the
computer simulation model, using the same program and method
utilized in the design of the plant, to determine the performance that
would have resulted and then comparing that to the actual test result. In
calculating performance in this manner, no operating conditions less
favorable than design shall be used if the conditions are less favorable
because of unsatisfactory operation or if insufficient
capacity/throughput is caused by the equipment installed by the
CONTRACTOR.
Should the performance test be deemed to be unsuccessful for reasons
attributable to the design of equipment items or units, the
CONTRACTOR shall take whatever remedial steps necessary to
correct or modify the defect to enable meeting of all the process
guarantees. In the event CONTRACTOR is unable or unsuccessful, the
CONTRACTOR shall be liable for these deficiencies as per the
Contract.
TP
REV.
PAGE:
Once remedial actions are carried out by the CONTRACTOR to fix the
deficiencies, the performance test shall be repeated in its entirety.
Alternatively, at the sole discretion of the COMPANY, performance
test may be repeated only for the affected area or areas of the plant.
COMPANY will issue the provisional acceptance certificate once the
COMPANY is satisfied that the plant performs as per design and no
process related deficiencies exist and that all process guarantees are
met as per the terms of the Contract, and accepted by the COMPANY.
The overall performance of the plant shall be measured based on the
following:
10.1- Plant Throughput
TP
REV.
PAGE:
TP
REV.
PAGE:
10.2.3-Product Specification
10.2.3.1- C3 Specification
The LPG shall meet the following composition and condition:
Component
C3
Nitrogen
CO2
0.000
0.000
H2S
0.000
H2O
0.000
Methane
0.000025
Ethane
0.020575
Propane
0.907009
i-Butane
0.057108
n-Butane
0.015246
i-Pentane
0.000030
TP
REV.
PAGE:
n-Pentane
0.000006
n-Hexane
0.000000
n-Heptane
0.000000
n-Octane
0.000000
n-Nonane
0.000000
Total
100.00
Average Temperature, ( F)
137
Average Pressure(psia)
297
Flow BPD
2856/
Table 3
10.2.3.2-LPG specification
The LPG shall meet the following composition and condition:
Component
LPG
Nitrogen
CO2
0.000
0.000
H2S
0.000
H2O
0.000
Methane
0.000000
Ethane
0.00000
Propane
0.023166
i-Butane
0.289149
n-Butane
0.476872
i-Pentane
0.150718
TP
REV.
PAGE:
n-Pentane
0.060069
n-Hexane
0.000025
n-Heptane
0.000000
n-Octane
0.000000
n-Nonane
0.000000
Total
100.00
Average Temperature, ( F)
142
Average Pressure(psia)
98
Flow BPD
3423
Table 4
10.2.3.3-Sales Gas
The Sales Gas shall meet the following composition and condition:
Component
Sales Gas
Nitrogen
CO2
0.021974
0.000
H2S
0.000
H2O
0.000
Methane
Ethane
0.775864
0.134985
Propane
0.051285
i-Butane
0.006835
n-Butane
0.007252
i-Pentane
0.000996
TP
REV.
PAGE:
n-Pentane
0.000587
n-Hexane
0.000121
n-Heptane
0.000001
n-Octane
0.000000
n-Nonane
0.000000
Total
100.00
Average Temperature, ( F)
80
Average Pressure(psia)
586
Flow MMSCFD
146.2
Table 5
Component
Condensate product
(Naphtha)
Nitrogen
0.000000
CO2
0.000000
H2S
0.000000
H2O
0.000000
Methane
0.000000
Ethane
0.000000
Propane
0.000000
TP
REV.
PAGE:
i-Butane
0.000043
n-Butane
0.000717
i-Pentane
0.158932
n-Pentane
0.362466
n-Hexane
0.459420
n-Heptane
0.018422
n-Octane
0.000000
n-Nonane
0.000000
Total
100.00
Average Temperature, ( F)
125
Average Pressure(psia)
100
Flow BPD
976.9
RVP,psia(max)@ 100 F
13.5
90
10%
90min-160max
Table 6
Condensate product
(Naphtha)
Nitrogen
0.000000
CO2
0.000000
H2S
0.000000
H2O
0.000000
TP
REV.
PAGE:
Methane
0.000000
Ethane
0.000001
Propane
0.000918
i-Butane
0.026537
n-Butane
0.077638
i-Pentane
0.092995
n-Pentane
0.085839
n-Hexane
0.159713
n-Heptane
0.098132
n-Octane
0.123230
n-Nonane
0.071988
n-Decane
0.089924
n-C11
0.025851
n-C12
0.019790
n-C13
0.021575
n-C14
0.015573
n-C15
0.014357
n-C16
0.010707
n-C17
0.009733
n-C18
0.008598
n-C19
0.007787
n-C20+
0.039014
Total
100.00
Average Temperature, ( F)
125
Average Pressure(psia)
90
Flow BPD
26460
RVP,psia(max)@ 100 F
13.5
90
90min-160max
Table 7
11-
TP
REV.
PAGE:
Process Calculations
Consultant Engineering Company should carry out all
calculations in the Customary (Imperial) Units. Following
is a list of areas for which detailed calculations shall be
carried, as a minimum, meaning that the calculations
requirement shall not only be restricted to these areas.
11.1-Process Simulations
For process simulation work should use commercially
available program HYSYS. A complete set of the
simulation model computer diskettes shall be carried out
and for each case studied.
11.2-Flare System Design
All calculations for the design of the entire system should
be carried out. Computer programs, if used, should be
commercially available programs accepted by industry.
12-
I.
TP
REV.
PAGE:
II.
III.
IV.
V.
VI.
TP
REV.
PAGE:
Electrical System:
ii.
iii.
iv.
TP
REV.
PAGE:
TP
REV.
PAGE:
5 Bar g
Design pressure
10 Bar g
13-
TP
REV.
PAGE:
Civil Design
This Specification should describe the Scope of Work for
Civil Works and Steel Structures for Gas Plant Project.
All the international codes and NOC specification shall be
considered as integral part of this specification, as well as
their addenda.
SUMMARY
Consultant Engineering Company should take into consideration all the
information in this document, if there is any better option than Propane
Refrigerant unit as cooling agent, Hot Oil as heating gent, Compressors to be
gas turbine engine or electrical powered with one compression stage or two
compression stages, or if there is any changes in the system as described in
this document to have better smooth and safe process with high productivity
and less capital cost and/or operation cost, should advice SOC.
TP
REV.
PAGE: