Académique Documents
Professionnel Documents
Culture Documents
Monitoring Period
02/04/2007 to 31/05/2008
(Both days included)
Version: 06
Date: 25/01/2009
Rice Husk based power project at Satia Paper Mills Limited (SPML), Punjab,
India.
UNFCCC Reference No.- 0955
Project Site:
Table of contents
Current Status of the Project.............................................................................................................3
Monitoring Period ...........................................................................................................................4
Parameters monitored.......................................................................................................................5
Recorded observations for monitored parameters ............................................................................8
Emission reduction .........................................................................................................................10
Details of Down Time at the plant .................................................................................................12
Measures to ensure the Results / uncertainty analysis....................................................................13
Roles & Responsibilities ...............................................................................................................13
Training Procedure ........................................................................................................................13
Turbine details
Description
Fully condensing
Make
Siemens
Power (MW)
Boiler details
Prior to the project activity two rice husk boilers (capacity 15 TPH and 27 TPH respectively)
were operational to meet the total steam requirements (23 TPH) of the process. The boiler with
installed capacity of 27 TPH was running on lower capacity in pre project scenario. After
installation of turbine, 27 TPH boilers runs on full capacity and generates 19 TPH of extra high
pressure steam which is used to run the project turbine. The electricity produced from project
turbine shall displace equivalent amount of electricity supply from the grid which would have
otherwise happened in absence of the project activity.
The configuration details of the boilers are as follow:
Description
Parameter
15
14.06
Steam temperature (0 C)
200
Description
Parameter
27
32.9
Steam temperature ( C)
400 10
Monitoring Period
The Monitoring Period is chosen from 02/04/2007 to 31/05/2008 (both days included).
Parameters monitored
The following parameters have been monitored:
Data / Parameter:
Data unit:
kWh
Description:
Data reported in :
Accuracy class
Data / Parameter:
Auxiliary Consumption
Data unit:
kWh
Description:
Data reported in :
Accuracy class
annually.
As measure of quality assurance, efficient compilation and easy
accessibility of the data logged for the monitored parameter, the observed
readings are reported in the excel sheet as well.
1.0
Data / Parameter:
Data unit:
kWh
Description:
Data reported in :
Description of
measurement
methods and
procedures to be
applied:
QA/QC procedures
to be applied:
Data / Parameter:
Data unit:
Tones
Description:
Data reported in :
Weighto meter
Data / Parameter:
Calorific Value
Data unit:
kCal/kg
Description:
Data reported in :
Test Reports
Description of
measurement
methods and
procedures to be
applied:
QA/QC procedures
to be applied:
The net calorific value of the rice husk samples sent by SPML is tested by
the third party agency.
Biomass Availability:
An independent third party has conducted biomass assessment study for the period 01/12/2007 to
31/12/2008. The biomass assessment study clearly demonstrates that the quantity of available
biomass in the region (50 km radius), is 26.9% larger than the quantity of biomass (rice husk) that
is utilized including the project activity.
The biomass assessment report concludes that the surplus rice husk available in the command
area is 72622 MTPA when the requirement of biomass is around 269958 MTPA.
Month
Total
Electricity
Generated
(kWh)
Auxiliary
Consumption
(kWh) *
Power
Supplied to
the Plant
(kWh)
Rice Husk
Quantity
(Tonnes)
Net
Calorific
Value
(kCal/Kg)
Apr-07
1639783
128800
1510983
2507
3380
May-07
1095582
94300
1001282
2343
3480
Jun-07
2755022
154500
2600522
3859
3690
Jul-07
889263
63000
826263
2704
3680
Aug-07
1846531
95400
1751131
3082
3982
Sep-07
701731
37800
663931
2232
4070
Oct-07
3168168
144700
3023468
5106
4067
Nov-07
2964822
127600
2837222
4741
3770
Dec-07
2599422
118600
2480822
4560
3548
Jan-08
2880720
129900
2750820
5072
3660
Feb-08
2953491
124200
2829291
4725
3865
Mar-08
3165180
136800
3028380
5082
4079
Apr-08
2856308
129200
2727108
4765
4260
May-08
2630030
122000
2508030
4683
4290
Total
32146053
1606800
30539253
55461
Auxiliary Components
Auxiliary components for the project activity (Boiler No.4 and Turbo Generator) consist of CT
FAN & CWP-3 .CWP-2 (Stand by). The technical specifications for the auxiliary components are
follows:
CT FAN
Make
Paltech
Quantity
10 Nos
Capacity
12.5 HP
CWP-3
Make
KSB
Quantity
1 No.
Flow
900m3/hr
Head
35m
Motor
KSB
Quantity
1 No.
Flow
900m3/hr
Head
35m
Motor
Emission reduction
Baseline and project emissions are calculated as per the formulas mentioned in Section E of the
PDD. The same is given below:
Formulae used
The emission reduction is given by
Emission reduction = Baseline emissions Project emissions
Baseline emissions
BEY = EFY X EGY
BEY
EGY
net quantity of electricity generated by the project activity during the year y (KWh)
EFY 1
CO2 baseline emission factor for the electricity displaced due to the project activity
The grid emission factor has been taken from the registered PDD.
http://cdm.unfccc.int/Projects/DB/TUEV-SUED1171633439.48/view
10
Emission reductions
Period
02/04/2007 -31/05/2008
Baseline
Net
Emission
Power
factor
produced
(tCO2/MWh)
(KWh)
(A)
(B)
0.751
30539253
11
Project
emissions
(t CO2)
Baseline
emissions
(t CO2 )
(C=
A*B)
22935
Emission
reductions
(t CO2)
(C-F)
22935
Outage Period
Serial Number
Start from
Up To
(Days)
15/05/2007
25/05/2007
11
07/07/2007
24/07/2007
18
12/08/2007
14/08/2007
03
24/08/2007
31/08/2007
08
01/09/2007
22/09/2007
22
24/12/2007
26/12/2007
03
21/02/2008
21/02/2008
01
04/05/2008
05/05/2008
02
67
Total
The Downtime period is defined as the period during which the Turbine Generator (TG) was not in
operation / production was stopped due to scheduled preventive maintenance or brake down maintenance /
equipment failure / modification / equipment installation etc. or any of the reason.
12
13
Director
Director (Tech.)
Vice President (works)
Manager-Utilities
Monitoring Supervisormechanical
Monitoring Supervisor-electrical
14
Training Procedure
SPML would ensure the efficient working of the RICE HUSK BASED POWER PROJECT by
conducting training programmes. Aim of the procedure is to ensure training of SPML employees
associated with Project activity. The training will be on the following aspects of activity involved
in the Project operation, maintenance, monitoring of parameters, precautions, safety instructions
etc. These trainings will be meant to address the following key requirements related to the project
activity:
1. Corrective and preventive maintenance It would include the procedures for the general
inspection to be carried out, the maintenance required to ensure the uninterrupted
operation of the project plant.
2. Proper maintenance of the log books & reporting.
3. Calibration requirements of the monitoring equipments.
4. Monitoring of Fuel Efficiency
5. To take care of the other monitoring requirements of the CDM project activity.