METHOD STATEMENT

PM6.05_E
Rev.1

SYSTEM : AIR CONDITION & VENTILATION


Issued 12/1/53

METHOD STATEMENT FOR


FAN COIL UNIT INSTALLATION
1. GENERAL
This method statement describes the Fan Coil Unit installation. Detail of the procedure contained herein
may be modified based on the actual site condition.
2. EQUIPMENT AND TOOLS
Basic equipment for installation of ventilation fan is as follows;
2.1 Ladder
2.2 Scaffolding
2.3 Drilling machine
2.4 Wrench
2.5 Adjustable wrench
2.6 Chain lock
2.7 Spirit level
3. WORKING PROCEDURE
3.1 Site Preparation
3.1.1 Check the builder.s work and installation location.
3.1.2 Check setting out of pipe route lines
3.2 Equipment Check
3.2.1 Check FCU type and model.
3.2.2 Check visible damage of FCU.
3.2.3 Rotate fan blower by hand for abnormality check of blower and housing.
3.2.4 Ensure that there is no foreign material inside blower and housing.
3.3 Installation
3.3.1 Check dimension of FCU base and mounting points.
3.3.2 Fix expansion bolts, rods.
3.3.3 Size of hanger rods and type of vibration isolator shall be followed the summary table.
3.3.4 Hang or mount FCU with rubber pads or spring vibration isolator in accordance with
standard installation drawing.
3.3.5 Adjust FCU level to meet drain water flow to direction of condensate drain pipe. Fix
bolts, nuts and washers.
3.3.6 In case of FCU install in the conceal area, service panel minimum size 450x450 mm.
shall be provided. Service panel location and its detail drawing shall be coordinated with
architectural work in working drawing stage.

Page 1 of 4
PM6.05_E

METHOD STATEMENT

PM6.05_E
Rev.1

SYSTEM : AIR CONDITION & VENTILATION


Issued 12/1/53

4. QUALITY CONTROL
Quality control works should be performed in the particular works as discussed in the following.
4.1 FCU type and Model shall be checked before transportation to installation place.
4.2 Installation work shall be performed in accordance with approved shop drawing and acceptance
by inspection and check list as per attachment.

Page 2 of 4
PM6.05_E

METHOD STATEMENT

PM6.05_E
Rev.1

SYSTEM : AIR CONDITION & VENTILATION


Issued 12/1/53

AIR HANDLING UNIT INSTALLATION FLOW CHART

START
CHECK TYPE, MODEL AND DIMENTION OF FCU.S BASE OR SUPPORT
PREPARE FOR FCU.S SUPPORT OR HANGER
INSTALL
ADJUST LEVEL
FIX BOLTS, NUTS AND WASHERS
END

Page 3 of 4
PM6.05_E

PM6.05_E

METHOD STATEMENT

Rev.1

SYSTEM : AIR CONDITION & VENTILATION


Issued 12/1/53

CHECK LIST FOR FAN COIL UNIT INSTALLATION


PROJECT NAME : ____________________________
REF. NO. : ____________
LOCATION : ______________________________
DATE : ____/____/____
GRID LINE : ______________________________
REFER DRAWING NO. : _______________ REV. NO. : _______________
FCU

: UNIT NO. __________________


: TYPE
__________________
: MODEL __________________

ITEM

DESCRIPTION

Equipment Type & Model


Type and Model

1
2
3
4

Installation
Hanger and/or Support
Adjust Level
Bolts & Nuts
Vibration Isolator

INSPECTION AND
TEST REQUIRED

STATUS
REMARK
SATISFIED UNSATISFIED

Check Type & Model

Physical Check
Physical Check
Physical Check
Physical Check











Note : _____________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Inspected by :

Approved by :

Signature : _______________
Name : __________________
Date : ___________________

Signature : _______________
Name : __________________
Date : ___________________

Page 4 of 4