Note: Labour Constants have been taken from IS: 7272 (Part I)
1 Excavation and Earth Works a) Excavation over areas (Hard/dense soil ), depth
up to I.5 m and removal ( up to one metre from edge ) Quantity Considered Sr. No
1 a) b) Labour/Material/Others Labour Mate Mazdoor Sum 2 Water @ Sum 3 Contract
or's Profit @ Total For 10m3 3 Therefore, Per m 10 m3 Day 1 1 earthwork 3 Quatit
y/10m Rate Per 0.6 6.2 1.50% 10% 162 day 166 day Amount in Rs. 97.38 1030.13 112
7.51 16.91 1144.42 114.44 1258.86
126.00
2 Plain Cement Concrete Unreinforced concrete 1 : 4 : 8 in foundations including
mixing, pouring, consolidating and curing: 1) Hand mixed cement concrete Quanti
ty Considered Sr. No Labour/Material/Others a) b) c) 2 a) b) c) 1 Labour Mason M
azdoor Bhistie Materials Cement bags Sand Coarse Aggregates Sum 3 Water @ 4 Tool
s and Machinery Sum
3 10 m
concrete Quatity/10m3 Rate Per 1 21.3 7 34.34 4.77 182 day 166 day 162 day 329 b
ag 3 437 m
3
Day 1 1 1
Amount in Rs. 181.80 3539.00 1136.10 11290.99 2083.54 10217.34 28448.77 426.73 5
00.00 29375.50 Page 1 of 6
Calculation of Materials For 10 m dry concrete = 15.5 m3 wet concrete Therefore,
cement required = 15.5 / (1 + 4+
3
8)
Therefore, cement required = Density of Cement = Cement Required = Therefore, Ce
ment Required = 1 bag of cement = No. of Cement bags reqd. = No. of Cement bags
reqd. = Sand Required = Coarse Aggregates Reqd. =
1.19 1440 1.19 1717
m kg/m3 x 1440 kg
3
50 kg 1717 / 50 34.34 bags 3 4.77 m 3 9.54 m
9.54 1071 m 1.50% Lump sum
1 a) b) c) 2 a) b) c)
Labour Mason Mazdoor Bhistie Materials Bricks Cement bags Sand Sum Sum
1 1 1
9.4 18 2 5000 20.08 2.79 1.50% 10%
182 day 166 day 162 day 5.8 nos 329 bag 3 437 m
1708.92 2990.70 324.60 29000.00 6602.30 1218.67 41845.20 627.68 42472.88 4247.29
46720.17
Size of Actual Brick is For 1 m3, Actual volume of by bricks=
y bricks= Volume of cement mortar = Volume of cement mortar =
tions = Add 10% for frogs, wastage = For 10 m3 of brickwork =
work = 3 For 10 m dry mortar = For 10 m3 of c.m, Cement = For
For 2.79 m3 of c.m. = Density of Cement = Cement Required = 1
. of Cement bags reqd. = Sand Required =
Actual volume of b
Add 10% for undula
For 10 m3 of brick
2.79 m3 of c.m. =
bag of cement = No
12.5 m wet mortar 3 2.08 m 0.12 0.03 1440 36.3 50 0.73 x 2.083 / 10 m3 of cement
kg/m3 kg kg bags
3
3 0.13 m
b) 3 Water @
Sand Sum Sum
0.18 1.50% 10%
3 437 m
4 Contractor's Profit @ Total For 10m Therefore, Per m2
2
78.62 993.29 14.90 1008.19 100.82 1109.01
On c.m. c.m. Add Add
10 m2, the quantity of cement mortar in top layer, in top Layer= 10 x 0.005 in t
op Layer= 0.050 m3 1% for undulations = 0.051 m3 10% for wastage, etc. = 0.056 m
3 12.5 3.13 0.056 0.017 1440 25 50 0.5 m3 wet mortar m3 x 3.125 / 10 m3 of cemen
t kg/m3 kg kg bags
3
111.00
3 For 10 m dry mortar = For 10 m3 of c.m, Cement = For 0.06 m3 of c.m. = For 0.0
6 m3 of c.m. = Density of Cement = Cement Required = 1 bag of cement = No. of Ce
ment bags reqd. =
Sand Required =
0.05 m
6 Flooring: Precast terrazo tile flooring 20 mm thick laid over thick cement mor
tar: 1: 4 including Laying, cutting, grinding and polishing Quantity Considered
Sr. No 1 a) b) c) d) e) 2 a) b) c) 3 Water @ Sum 4 Contractor's Profit @ Total F
or 10m2 10% Labour/Material/Others Labour Mason Mazdoor Bhistie Mazdoor Machine
Materials Tiles Cement bags Sand Sum 10 m Day 1 1 1 1 1
2
10 mm Size of a Terrazo tile is In 1
3
Calculation of Materials 250 x 250 1 / 16 160 1 0.010 0.011 0.012 10 0.12 0.25 /
0.25 nos nos x 0.01 m3 m3 m3 x 0.012 m3 of cement mortar m3 of cement mortar 3
12.5 m wet mortar 3 2.5 m 0.12 0.03 1440 43.6 50 0.87 x 2.5 / 10 m3 of cement kg
/m3 kg kg bags
surface area, over which flooring is laid. Quatity/10m Rate Per 182 166 162 166
182 day day day day day Amount in Rs. 218.16 332.30 162.30 830.75 727.20 12000.0
0 286.06 52.42 14609.18 219.14 14828.32 1482.83 16311.15 Page 4 of 6
m2, no of tiles =
1.2 2 1 5 4 160 0.87 0.12 1.50%
75 nos 329 bag 3 437 m
In 1 m2, no of tiles = In 10
e of cement mortar = Add 10%
f terrazo tiling = For 10 m2
m3 of c.m, Cement = For 0.12
Therefore, Per m2 Following has been assumed: Labour Mate Mason Mazdoor Bhistie
Mixer Operator Mixer Vibrator Machine Operator Rate/day 162.3 181.8 166.15 162.3
181.8 181.8 181.8 181.8
1632.00
Sand Required = Material Rate Per Unit Cement Sand Coarse Aggregates Bricks Terr
azo Tiles
3 0.12 m
Rate 329 bag 437 m3 1071 m3 5.8 no 75 no
Austin S. Rodrigues, Lecturer, Government
Polytechnic Panaji