Vous êtes sur la page 1sur 6

Distribution Network Capacitor Resonance A Case Study

Authors:
Chris Halliday
Director of Technical Services
and Training
Electrical Consulting and
Training Pty Ltd

Frank Iannelli
Power Quality Technician

Dr Robert Barr
Director

Country Energy

Electric Power Consulting


Pty Ltd

This paper was presented at the ICHQP 2008 - 13th International Conference on Harmonics and
Quality of Power, University of Wollongong 28th September 1st October 2008. It was also
presented previously at the EESAs Energy NSW 2007....Balancing the New Energy Equation
Conference & Trade Exhibition in Sydney, Wednesday 12 to Friday 14 September 2007.
Abstract
Harmonics are generally caused by customer non-linear loads interacting with network impedances.
Capacitor banks used for voltage support can resonant and cause excessive levels of harmonics that
may cause problems for customer equipment.
This case study looks at the problems associated with a capacitor bank in Country Energys
Narrandera Zone Substation, the levels of network harmonics at various locations, the effects on
customer equipment and the solution implemented to overcome the problem.

1.

Introduction

Country Energys regional electricity network covers 95% of NSW. This network supplies
approximately 870,000 customers and is supported by approximately 4,000 employees.
The distribution network consists of over 195,000 kilometres of subtransmission, high voltage and
low voltage distribution lines. There are approximately 1.4 million power poles for the overhead
component of this network. The distribution network is supplied and radiated out from
approximately 340 zone substations via approximately 1360 distribution feeders. One of these
zone substations is located at Narrandera (see Map 1) and it is this zone substation that is the focus
of this paper.

Map 1: Showing NSW


and Narrandera
Narrandera

Harmonics are generated by customer non-linear loads interacting with network impedances.
Harmonics in Australia are typically at low levels and generally cause no problems. At some
locations, harmonics can reach high levels due usually to a combination of local load and network
circumstances. This case study is one of those rare situations.
Distribution Network Capacitor Resonance A Case Study

Capacitors are used in banks by distribution companies, such as Country Energy, to correct poor
power factor, to provide voltage support and minimise losses. These capacitors can resonate at or
around the 5th or 7th harmonic if measures arent taken to prevent such resonance. Harmonic
resonances can result in damage to capacitor banks and customer equipment as well as increased
network losses and maloperation of customer equipment.
Problems occurred at Narrandera in 2006 due to a relatively low level of customer generated
harmonic currents generated at the end of a rural line that was interacting with the capacitor bank
at Narrandera Zone Substation (see Map 1 to show the location of Narrandera in relation to NSW).
This paper looks at the effects on customers, the process taken to identify the problem and cause,
the solution implemented and effectiveness of this solution.

2.

Effects to Customers

Only one customer supplied from the zone substation had reported problems. The customers
installation is connected to the end of a lightly loaded radial rural feeder that is a combination of
HV 7/.064 copper conductor, 7/4.5 aluminium, 6/1/2.5 ACSR and 35 mm Aluminium
underground cable: a total of 50.6 kms of powerline from transformer Tx 1 at Narrandera Zone
Substation (see Sketch 1 for the single line diagram from the zone substation to the site).
Sketch 1: Single Line Diagram. Zone Sub to Site
Narrandera
Zone Sub
66/11kV

3.2 km
7/4.5 AAC

22.8 km
7/064 HDBC

Note: Numerous spurs and distribution transformers are connected


all the way along the feeder but are not shown for simplicity. Other
feeders from the zone substation are also neglected

11 km
7/4.5 AAC

9 km
6/1/2.5 ACSR
4.6 km
35 mm
al XLPE
150 kVA Distribution
Transformer

The transformer supplying the site was a 3 phase 150 kVA padmount transformer, set on the
11275/433 tap position and with a percentage impedance of 4.1%. The load was typically 30-35
amps but at times getting up to 50 amps not a significant amount of load by any means.
The customer premise was a communication receiver station that comprised of racks of sensitive
electronic communication equipment, switch mode power supplies and amplifiers. The site had a
backup generator that was starting intermittently from an unknown cause since the site was
commissioned in 1999. This resulted in an enormous amount of unnecessary generator starts over
this time which was costing the customer a significant amount of money in terms of fuel cost, wear
and tear on the generator and other equipment e.g. a changeover contactor had to be replaced.
There was also the inconvenience and labour cost associated with topping up the generator fuel
and ensuring it was ready for use at all times. The customers consultant initially thought that
voltage sags were causing the problem but monitoring proved that voltage sags did not cause any
change in the status of the generator.
In one seven day period alone the generator started unnecessarily 25 times and ran for
approximately 47 hours. The generator changeover sensing relay was set as follows:

Voltage Unbalance - 15% with a 10 sec delay;

Under Voltage - 85% with a 10 sec delay.

Distribution Network Capacitor Resonance A Case Study

3.

Identifying the Problem and Cause

Initial investigations were focused at the customer who was having the problems. A Gridsense
Powermonic PM30 was installed at the distribution transformer. This locations was selected as it
was the point of supply and as voltage sags from the medium voltage network was suspected as
the cause of the problems.
The monitoring established that the supply voltage was within standards and the substation was
not overloaded (see Graph 1).
Graph 1 Voltage and Current at the Distribution Transformer Supply the Receiver Site

The graphs showed that the generator was starting when Total Harmonic Distortion (THD) levels
exceeded approximately 9.8% (see Graph 2). This level is in excess of the required 8%
compatibility level as set down by AS/NZS61000.3.6. The graphs also showed that the 5th and 7th
harmonics were the most significant harmonics by far. The generator changeover relay appeared to
be confused by such high levels of THD and sensed the need to swap to the generator.
THD reduces by approximately 4% when the generator cuts in as shown by Graph 2 and so the
customers load was contributing significantly to the problem. The generator changeover relay
would sense when the harmonic distortion dropped to below 9% voltage THD and the generator
would be stopped and mains supply would return. The generator would cycle in and out unless the
THD remained below about 9.8%.
Graph 2 Voltage THD percentage at the customers premise

Generator cutting in and out

It was not easy to tong the medium voltage network to determine where the major harmonic
current sources were originating from so an analysis of customer loads connected to the network
was carried out to determine those customers likely to have been generating significant harmonics.
The only identified major harmonic producing load was a large plant in Narrandera township and
Distribution Network Capacitor Resonance A Case Study

this customer was supplied by the other Zone Substation transformer, Tx 2. Spot readings of THD
levels were taken at this site and found to be very low and it was concluded that this site was not
contributing greatly to the problem. It has since been concluded that the largest contributing
harmonic load from Tx1 was in fact the customer with problems (this can often be the case).

4.

The Identified Problem

Narrandera zone has 2 x 10MVA 66/11 kV transformers


operating in a split bus arrangement in the peak load
periods during summer and winter. This zone substation
had a capacitor bank (see Photo 1) that was used to
improve power factor on Tx 1 which supplies part of
Narrandera township and some of the surrounding rural
network.
Graphs taken at the zone substation showed the Voltage
THD at times to about 5.7% and with low levels of current
THD and individual harmonics. The voltage THD levels at
the zone substation are much less than those recorded at the
receiver site.
Photo 1 Old Capacitor Bank
It was decided that the old capacitor bank may be causing a
resonant affect and it was to be disconnected from the
network for a short period. This was to occur between 9 am 4th September to 4 pm on the 5th
September 2006. Monitoring at the receiver site was to be undertaken to monitor the change in the
harmonic distortion (see Graph 3). Unfortunately the current to the capacitor bank was not logged
at any stage to prove that resonance was or wasnt occurring. Also logs at the zone substation were
not taken when the capacitor bank was switched out to see the effect at that location.

Graph 3 THD at the Receiver site while Capacitor Bank Switched out

Voltage distortion reduced while


capacitor bank was switched out.
The generator did not cut in or out
during this period.

Total harmonic voltage distortion at the receiver site when the capacitor bank was disconnected
had reduced by approx 4 % and the operations of the generator had stopped due to the voltage
THD at the site staying below 9 %. THD levels at the zone substation reduced from peaks of 6%
down to approximately 3-4% at all times.
A link was therefore established between the cause of the generator operations at the receiver site
and the old capacitor bank. The capacitor bank was then disconnected from supply for an extended
period to assist the customer. No further reports of the generator cutting in and out were received
through this period.
Distribution Network Capacitor Resonance A Case Study

It is noted from the graphs taken at the receiver site that when the load on the feeder is high at
midnight to 3 am due to hot water load (resistive load) and during the day period from 8 am to 6
pm that the total harmonic distortion was somewhat lower than at lightly loaded times. Dugan, et
al [1] states that as little as 10% resistive loading can have a significant beneficial impact on peak
impedance and this is illustrated by the results of the graphs for this site.

5.

Modelling the Network

A model was set up in Excel to investigate what was occurring. A simplified sketch of this model
is provided at Sketch 2. The numerous parallel paths of connected spurs and distribution
transformers had not been included in the sketch for simplicity.
Sketch 2 Simplified drawing of model developed in Excel

This model showed consistency with the practical measured results. The model confirmed that
there was a resonance in the low order harmonics around the 5th harmonic (see Graph 4). The
graph produced from the model also supports that a reduction in harmonics was to be expected
when the capacitor bank was taken out of service.
Graph 4 Modelled Harmonic Impedances at Zone Substation 11 kV Busbar

PU Harmonic Impedance

70
60
50

with P.F. Correction


Capacitors
without P.F. Correction
Capacitors

40
30
20
10
0

10 11 12 13 14

Harmonic

Distribution Network Capacitor Resonance A Case Study

6.

Solution Implemented

The capacitor bank at Narrandera Zone Substation was planned to be replaced in the near future
due to its PCB dielectric. The capacitor bank was left out of service for a period until it was
replaced some months later. The new capacitor bank was installed with blocking inductors to
prevent resonance (see Sketch 3).

Sketch 3 New Capacitor Bank


Single Line Diagram (Courtesy
of ABB)

Harmonic filtering was also recommended for the receiver site to assist in reducing harmonic
levels generated.

7.

Solution Effectiveness

Levels of THD were measured again once the new capacitor bank was installed. This showed
voltage THD levels at the zone substation were maintained at similar levels as without the old
capacitor bank at approximately 3% and at the receiver site at approximately 7.6%. This is a
significant improvement and the customer is not having further problems.
Voltage THD levels are still nearing the compatibility limits allowed by the standards. Future
upgrading of the network will help to overcome this issue and/or emission limits may need to be
applied to customer.

8.

Conclusions
1. Electricity distributors need to be aware of the potential adverse harmonic impacts of shunt
capacitor bank resonances.
2. Modelling over the harmonic spectrum is an important part of avoiding harmonic related
problems.
3. Excessive harmonic voltages caused by capacitor resonances or other reasons can cause
sensitive customer equipment to malfunction.

Investigation techniques can always be improved and problems like this provide a learning
opportunity for all.

9.

Acknowledgements

Brendon McPhillips, Kris McCanna, Peter Day and others from Country Energy for information
and assistance provided in compiling this paper.

10. References
[1] Dugan, etal. 2002. Electrical Power Systems Quality, Second Edition. McGraw Hill.

Distribution Network Capacitor Resonance A Case Study

Vous aimerez peut-être aussi