Rate Analysis

Providing & Fixing at all height false ceiling of 12.50 MM Thick tapered edge Gypsum Board
conforming to IS:2095 including providing & fixing of frame work made of special section power pressed
from M.S.Sheet & galvanized in accordance with zinc coating 600 as per IS:277 & Consisting Angle
cleats of size 25mm wide X 16 mm thick with flanges of 22 mm& 37 mm at 1200mm center to center one
flange to the ceiling with desh fastner 12.5 mm dia X 40 mm long with 6 mm dia bolts to the angle
hangers of 25 x 25 x 5 mm of required length & other end of angle hanger being fixed with nut & bolts to
G.I.Channels 45 mm X 15mm X 0.90 mm running at the rate of 1200 mm center to center to which the
ceiling section 0.5 mm thick bottom wedge of 80 mm with tapered flanges of 26 mm each having clips of
10.5mm at 450 mm center shall be fixed in a direction perpendicular to G.I.Channel with connecting clips
made out of 2.64 mm dia X 230 mm long G.I.wire at every junction including fixing the gypsum Board
with ceiling section & perimeter channels 3.5 mm thick 27 mm high having flanges of 20 mm & 30 mm
long. the perimeter of ceiling to wall partition with the help of rawl plugs at 450 mm center to center with
25 mm long drive all screws @ 230 mm interval including jointing & fixing to a dust finish of tapered &
square edges of the gypsum board with recommended filler , Paper tapes, finisher & two coats of primer
suitable for gypsum board as per manufactures specification & also including the coat of making
openings for Light fittings, grills, diffusers, cutouts made with frame of perimeter channels suitable fixed
all complete as per drawing & specification & direction of the Engineer in charge but excluding the
coat of Painting.

Considering Room size: 5.77 mm x 8.40 mm = 48.47 Smt.


1

Gypsum board 12.5 mm thick


Area of board =
1 x 5.77 x 8.40 +2 x 7.66 x 0.40 + 2 x 5.03 x 0.40 =
48.47 +6.13 +4.02 = 58.62Sqm.
Cost =
58.62 x 1.05 x RS 175.00 / Sqm.=RS. 10771.42
...(1)

Perimeter Channel section of size 20mm x 27mm x 30mm x 0.55mm


Length =
88 x 8.40 +8 x 5.77 + 8 x 1.20 + 8 x 0.30 = 67.20 + 46.16 +
9.60 + 2.40 = 125.36
Cost =
125.36 x1.05 x RS. 22.00 / Mt. RS.
2895.82.......(2)

Intermediate Channel section of size 15 mm x 45mm x 0.9 mm @ 1220 mm


c/c
Length =
4 x 8.40 = 33.60 Mt.
Cost =
33.60 x 1.05 x RS. 35.00 / Mt. RS.
1234.80.......(3)

Ceiling section of size 80mm x 26 mm x 0.5 mm @ 457 mm c/c


Length =
16 x 5.77 = 92.32 Mt.
Cost =
92.32 x 1.05 x RS. 35.00 / Mt. = RS.
3392.76......(4)

Ceiling angles of size 25 mm x 10 mm


Length =
8 x 6 x 0.80 mm = 38.40 mm
Cost =
38.40 mm x 1.05 x RS. 25.00 = RS. 1008.00 ..
.(5)

Soffit cleat of size 22 mm x 37 mm


Total NOS, = 8 x 6 = 48 NOS,
Cost =
48 x 1.05 x RS. 2.30 / Per No = RS. 115.92..
......(6)

Rawl / Plugs
Total =

8 x 6 = 48 NOS,

Cost =
48 x 1.05 x RS. 5.80 / No = RS.
292.32..(7)

Nut bolts
Total =

2 x 8 x 6 = 96 NOS

Cost =
96 x 1.05 x RS. 1.50 / No = RS. 151.20..
....(8)

Connecting clip
Total =

16 x 4 = 64 NOS

Cost =
64 x 1.05 x RS. 4.95 / No = RS. 332.64..
........(9)

10

Jointing Fiber Tape

Length =

8 x 7.66 + 20 x 5.03 = 61.28 + 100.60 = 161.88 Mt.

Cost =
161.88 x 1.05 x RS. 0.95 / Mt. = RS.
161.48..(10)

11

Jointing Compound
Considering 55 Kgs / 100 Sqm.=
Area of work:

58.62 Sqm.

Jointing Compound Required:


58.62 x 1.05 x 55/100 = 33.85 Kgs.
Cost =
33.85 x RS. 27.75 / kg. = RS.
939.34....(11)

12

Dry wall top coat


Considering 15 Lt. / 100 Sqm. =
Area of work = 58.62 Sqm.
Top coat required:
58.62 x 15/100 = 8.79 Lt.
Cost =
8.79 x 1.05 x RS. 67.25 / Lt. =
620.68........(12)

13

RS.

Labour Charges
Considering labour charges RS. 95.00 / Sqm.
Labour charges = 58.62 x RS. 95.00 = RS. 5568.90.
....(13)

14

Flat Point two coats with primiering coat.


Area of work =
58.62 Sqm.
Cost =
58.62 x RS. 95.00 / Sqm. = RS.
5568.90(14)

15

Labour charges for Light fittings & diffusers.


No. of fittings =
8 x RS. 30.00 / Nos.
Cost =
RS.
240.00..(15)

16.

Plastic Paint
Area of Work =

58.62Sqm

Cost =

Total RS.
Add 15% C.P. RS.

Total cost RS.

Cost per Sqm.

58.62 X Rs. 84.50/Sqm = Rs. 4953.39

=38247.59
5737.13

43984.72

43984.72 / 58.62 Sqm.


=RS. 750.33 / Sqm.

RS. 750.00 / Per Sq. Mt.