Académique Documents
Professionnel Documents
Culture Documents
Reservoir Properties:
The Haggis sand was deposited in a turbidite environment. It is quite homogeneous with an
average porosity and permeability of 22% and 200 mD, respectively. The reservoir sand, however, is
anisotropic with a Kv/Kh ratio of 0.1. The top of the sand was encountered at 6400 ft TVDSS, and
the oil-water contact is at 6500 ft TVDSS.
The reservoir is normally pressured with an initial reservoir pressure of 3300 psia and little or
no aquifer support. Reservoir pressure has declined with production to 2800 psia at present.
Pressure maintenance was not considered when the field was being developed.
Table 1 lists the PVT data for the Haggis fluids at current reservoir conditions.
150 F
Reservoir Temp.
40 deg. API
Oil API Gravity
0.80
Gas Sp. Gravity
550 SCF/STB
GOR
2115 psia
Pb
1.27
Bo
0.66 cp
Oil Visc.
0.0047
Bg
0.022 cp
Gas Visc.
1.023
Bw
0.67 cp
Water Visc.
200000 ppm
Water Salinity
Table 1: Haggis PVT Data
Haggis wells:
The Haggis field wells have an economical limit of 1500 STB Oil/d/well; i.e. producing at lower
rates is not economically feasible.
Haggis-3 was drilled in May 1995. It is taken to be the case study for this field as it has average
parameters for Haggis wells. Figure 1 is the completion diagram for Haggis-3. Above the wellhead,
the well was completed with the same 5 1/2" OD production tubing encased in a mud line (no
insulation). The mud line connects the wellhead (on the sea-bed) to the Xmas tree on the platform.
Results of a recent pressure survey from Haggis-3 are listed in Table 2.
Depth
Pressure
600
555
1500
725
2500
3350
4700
990
1190
1610
Table 2: Haggis-3 Pressure Survey
5600
1930
6480
2240
ft MD
psia
Haggis-3's well parameters, and results from both well testing and production logging are
summarised in Table 3. Table 3 also contains data on Haggis-1. Haggis-3 and Haggis-1 are
___________________________________________________________________________________
Exercise Version Jan 2012
Page 1 of 12
essentially twin wells, except that completion damage has resulted in Haggis-1 being considered the
worst well in the field. N.B. Big Kahuna uses Vogel IPR correlation for all well modelling.
Haggis-3
5000
30
65
Haggis-1
3958
28
65
445
2.92
12.35
7.17
9.11
50%
25%
12
0.100
4000
Table 3: Well Data
STB/d
%
F
psia
STB/d/psi
Inches
ft
The Scenario:
The rate of oil production decline in the Haggis field is alarming, and if no action is taken,
Haggis will become uneconomical by the end of this year. The Operators of the field, Big Kahuna
Oil Inc., did not accept this situation and have fired the field's former team leader for improper
management of the field. Big Kahuna has hired you to improve production from the Haggis field.
Your Mission:
Big Kahuna Oil Inc. has asked you to study the fields potential. The report shall outline A) the
model you have used for your study, B) the potential of the base case scenario, C) your assessment of
production enhancement proposals from the Haggis engineers, and D) your recommendation for a
project which will enhance production from Haggis. Include all relevant calculations and graphs in
clearly labelled appendices. Save your well models, named as requied below, on your drive.
The paragraphs below are an elaboration on the sections of the report you will submit to
management.
A) Develop a Well Model for Haggis-3:
Using Haggis-3 as your case study, complete the missing data in figure 2. Next, using the
company approved software (FloSystem WellFLo), develop a model for the Haggis field wells
so that you can use it to fulfil tasks B and C. Determine how detailed the model should be.
Unnecessary detail means longer computing time and higher costs making you inefficient in
managing resources.
1) Identify and list the major components contributing significant pressure drops along Haggis3s completion string. Include only these components in your model.
[5%]
2) Determine the best flow correlation model for Haggis-3 and state the reasons for your choice.
[8.5 %]
B) Base Case Analysis:
As a good manager, the first thing you have to do is evaluate the potential of what you have in
hand at the moment. To achieve that, you must determine what effect the decline in reservoir
pressure and the increase in water cut will have on Haggis-3's production if nothing is done to
___________________________________________________________________________________
Exercise Version Jan 2012
Page 2 of 12
improve its production. In other words, determine the reservoir pressure and the water cut at
which Haggis-3 becomes uneconomical to produce under the current setup.
Table B.1 is designed to assist you with that determination.
PRes.
2800
2700
2600
2500
WC
5000
30%
35%
40%
45%
Table B.1: Haggis-3 Oil Production Forecast
Psia
[5%]
You discuss these figures with the fields engineers. Since artificial lift can not be supported at
present by the production facilities on the Haggis platform, you all agree that you have to start a
water injection scheme to maintain the reservoir pressure at 2800 psia. Determine the
production improvements from the Haggis field with this scheme in place in terms of the
maximum water-cut at which Haggis-3 can produce economically. This will be considered as
the base case scenario for this study, against which all the others will be compared.
[2.5%]
Save this well model as Haggis-B.wfl.
You realise that with water injection, you should expect higher water production from the well,
and thus a shorter field life. To overcome this problem, operators often plug the "watered out"
perforations.
What are the advantages and disadvantages of such an operation?
[4%]
C) Further Projects:
You phone management and convince them to fund the pressure maintenance scheme. In
addition, they agree to provide a budget for an extra project to improve Haggiss production. In
this section you must select the best project from your engineers suggestions below.
Since production, and thus revenue, from Haggis is greatly affected by water production form
the field, Big Kahuna Oil Inc. defines the best production enhancement project for the Haggis
field as the one that sustains economical production from Haggis-3 at the highest water-cut.
Therefore, this should be one of the criteria you use to select the project you recommend to
management.
___________________________________________________________________________________
Exercise Version Jan 2012
Page 3 of 12
2000 ft-MD
6 months
$850 /ft-MD
$15 / bbl of oil
$8 / bbl of oil
1) Economics based on undiscounted
cash flows
___________________________________________________________________________________
Exercise Version Jan 2012
Page 4 of 12
Motor
562 Series
562 Series
562 Series
562 Series
562 Series
Cable Size
#2
#2
#2
#2
#2
Given the current conditions choose the optimum pump for Haggis-3 given the details and
engineering assumptions below,
Pump Types:
Setting Depth:
Minimum Equipment OD:
Maximum Equipment OD:
Platform Electricity Supply Frequency:
Assumptions:
Centrilift
5000ft
5
6.8
60Hz
___________________________________________________________________________________
Exercise Version Jan 2012
Page 5 of 12
b) As water production is the limiting factor, the production technologist suggests halting water
injection and allowing the reservoir pressure to drop. Determine which pump would be
suitable in these conditions. Table C.3 is designed to assist you with that determination.
PRes.
Psia
2800
2700
2600
2500
Pump
GC 8200
HC 7000
HC 9000
HC 12000
KC 15000
Table C.3: Haggis-3 Oil Production Forecast with ESP installed,
* denotes rate outwith the operating range of the pump (e.g. 5923* - outwith, but 5923 in the range).
Explain the reasons for your choice in your report.
[5%]
c) Using your choice of pump from part b), determine the benefit from installing an ESP in
Haggis-3 in terms of the maximum feasible water-cut at which the optimised pump will
sustain economic production prior to suspending water injection (i.e. no depletion, reservoir
pressure 2800psia).
(Use this result to compare the benefits from this project to the other proposed projects, and
as a basis for your recommendations in section D).
[2.5%]
Save this well model as Haggis-C3a.wfl.
C.3.2: Gas Lift Design
a) Given the current conditions carry out a gas lift design for Haggis-3 with the details and
engineering assumptions below (again the target liquid rate is 9000 STB/d),
Max casing head (and kick-off) pressure:
1200 psi
Gas available for injection:
10MM scf/d
Injected gas gravity:
0.6
Maximum setting depth:
3900 ft
Valve differential pressure:
100 psia
Minimum spacing:
450 ft
Kill brine (static fluid) density:
0.465 psi / ft
Minimum safety factor (Casing closing pressure margin)
50 psi
Assumptions:
1) Production tubing is unaltered.
2) Unload the tubing full of static fluid
against the well head pressure (i.e. static
fluid to 0ft MD).
3) No transfer margin is required.
Show the gas lift design plot in your report, determine the required gas injection rate for the
design production rate and explain briefly the different roles of valves in your design. Should
the unloading valves be open or closed when assessing gas lift capabilities?
[6%]
___________________________________________________________________________________
Exercise Version Jan 2012
Page 6 of 12
b) Determine the technical optimum injection rate as the reservoir pressure declines and
summarise the results in Table C.4 (Answer Form).
PRes.
2800
2600
2400
2200
2000
Psia
Technical
optimum
injection rate
MMscf/day (to the nearest 0.5 MMscf/d)
Table C.4: Technical optimum gas injection rate for Haggis-3.
Explain the reasons for your choice in your report. Why are technical optimum injection
rates not applicable in practice? What other possible factors have you considered in
completing the table C.4? Explain to management the reason why greater gas injection rates
do not result in greater production as the reservoir declines.
[6%]
c) Set the optimum gas injection rate for 2800 psia. Determine the benefit from installing
Gas Lift in Haggis-3 in terms of the maximum water-cut at which the optimised injection
rate will sustain economic production.
(Use this result to compare the benefits from this project to the other proposed projects, and
as a basis for your recommendations in section D).
[2.5%]
Save this well model as Haggis-C3b.wfl.
C.4 Suggestions from the Facilities Engineer:
Walking to your car after a long first day at the new job, the gentleman behind you reintroduces
himself to you as the Haggis field's facilities engineer. He shares with you a very interesting
discovery he made today. He explains that if you agree to provide a dedicated line from the
Haggis wells to the low-pressure separator, you can lower the average Xmas tree pressure to
only 100 psia. He points out that suggestions from the other department have large uncertainties
associated with them since they deal with the subsurface, while his suggestion is simple and
neat, and will solve all of the field's problems.
a) Evaluate the benefits from lowering the Xmas tree pressure, in terms of the maximum watercut you can economically produce Haggis-3 with, after lowering the Xmas tree pressure to
100 psia.
(Use this result to compare the benefits from this project to the other proposed projects, and
as a basis for your recommendations in section D).
[2.5%]
Save this well model as Haggis-C4.wfl.
b) Report the advantages and disadvantages of such a scheme.
[4%]
D) Recommendations to Management:
1) Assess the production enhancement projects proposed by the Haggis field engineers in section C
above and compare them to one another and to the base case scenario. Put in mind that Big
Kahuna Inc. has set the ranking criteria for these projects to be the maximum water-cut at which
Haggis-3 can sustain economic production (i.e. > 1500 STB oil/d).
___________________________________________________________________________________
Exercise Version Jan 2012
Page 7 of 12
___________________________________________________________________________________
Exercise Version Jan 2012
Page 8 of 12
Appendix
Further Instructions on The Haggis Field Exercise
Please read and follow the following instructions when carrying out the Haggis Field exercise.
Read the exercise before you attend the tutorial session, and fill-out the missing data in
Figure 2 (for yourself, you do not need to submit Figure 2). With the aid of this appendix,
attempt to carry-out this exercise.
In most sections of this exercise you have more information than you need. This is to help
you verify that the model you are using is correct.
Choose liquid flow rates corresponding to 5% - 95% of AOF. Try to minimise the number
of flow rates used in calculations without affecting the calculated operating rate. This will
reduce calculation time.
You now have a tuned model that you can use as a base case throughout the exercise.
___________________________________________________________________________________
Exercise Version Jan 2012
Page 9 of 12
2.
3.
4.
5.
you MUST write more (strongly not recommended); then continue the answer on an
additional page at the end, indicating in the text that you have done so.
Please keep saving your models as asked along the task you will have to submit
them
Every new optimization scenario you have to apply to the base case model
Water cut values needed should have precision to the first per cent, oil rates to the
first barrel, i.e. NO DECIMALS for them!
Figures size is half a page. Example of a supporting figure and table for the max
economic water cut calculation (along with oil rate @ 30% WC) is provided below:
Figure 9b: A certain scenario, sensitivity to water cut
(STB/d)
7146.91
3010.32
2797.74
Scenario
Certain
(STB/d)
5002.84
1505.16
1370.89
Water
Rate
(STB/d)
2144.07
1505.16
1426.85
Maximum Economic
Water Cut
50%
(SCF/STB)
550
550
550
Stable
Stable
Stable
___________________________________________________________________________________
Exercise Version Jan 2012
Page 10 of 12
Figure 1
Dev
Min
Max
ID"
OD"
4.767
5.953
4.767
3.500
5.953
9.200
Flow coupling
5.5" Pup Joint
5.5", 17 ppf tubing
4.767
4.767
4.767
6.072
5.953
5.953
4.151
5.364
1000
1000
5.5" Tubing
4.767
5.953
1500
1500
2700
2695
3944
3950
3957
3972
3988
4000
3989
degs
Tubing hanger
10 3/4" Casing
MD-RKB TVD-RKB
ft
350
ft
850
8-1/2" Hole
Casing
Size, in
Weight, ppf
Grade
Steel
Thread
MD, ft
Top:
Bottom:
ID, in
Roughness
Liner
Tubing
7
29
L80
5 1/2
17
L 80
EU
350
4000
4.767
EU
4000
5600
4.151
10.75
55.5
N80
9.625
53.5
L80
350
1000
9.604
NVam NVam
1000
5600
5900
6550
8.5
6.059
4.767
4.767
4.767
4.872
4.767
4.884
4.750
6.185
4.151
4.151
4.151
4.151
4.135
4.151
4.151
4.151
4.151
4.151
4.125
4.151
4.151
4.151
4.151
4.151
4.000
4.151
4.151
4.151
4.151
4.151
4.151
6.059
6.059
6.059
6.059
6.059
6.059
6.059
6.059
6.059
6.059
6.059
6.059
6.059
6.059
6.059
6.072
5.953
5.953
8.125
5.364
6.468
8.150
7.027
7.693
5.364
5.364
6.072
6.050
6.078
5.364
5.364
5.364
6.077
5.950
5.364
5.364
5.364
5.364
6.124
5.950
6.077
5.364
5.364
5.364
5.364
5.451
7.512
7.512
7.512
7.512
7.512
7.512
7.512
7.512
7.512
7.512
7.512
7.512
7.512
7.512
7.512
6.059
6.059
6.059
6.059
6.059
6.059
7.512
7.512
7.512
7.512
7.512
7.512
4102
4765
5500
5600
5600
5577
5577
6480
6450
6530.5
6500
6581
6550
Perforations:
18
L 80
0.0012 in
Cap (bbls/ft)
RKB to ...
ML
350 ft
Supervisor:
Engineer:
Drg No.:
Water
MSL Depth
50 ft
300 ft
The Boss
Joe Someone
Rev: 0 Date:
Completion
Date
Long time ago
Rig
Shark Co.
Today
___________________________________________________________________________________
Exercise Version Jan 2012
Page 11 of 12
Depth
ft TVD-RKB
0
Riser/Mud Line
ft
Seabed / Wellhead
ft
SSV
ft
Top of Reservoir
ft
OWC
Figure 2:
___________________________________________________________________________________
Exercise Version Jan 2012
Page 12 of 12