Académique Documents
Professionnel Documents
Culture Documents
Renewable Energy
EWP is aggressively investing in developing new energy sources to guarantee a steady supply of energy.
EWP is developing renewable energy sources to preserve the environment and sustain growth.
EWP is building two large scale power plants with the cooperation of IPPs (Independent Power Producers).
We are determined to provide affordable energy in a prompt and steady fashion.
These development projects are participatory, binding residents and developers together
to shape their own energy future.
Capacity
595MW x 2Units
580MW x 2Units
Construction Period
2012.12-2016.06
2013.06-2016.10
Cooperation with
Location
STX Energy
Dongbu Corp.
Seokmun-myeon,
Dangjin-si, Chungcheongnam-do
Photovoltaic Power
in operation 26.9 MW
under development 83.2 MW
Bioenergy
under development 105 MW
EWP is constructing a 30 MW
biomass power plant at the
Donghae power complex.
We are also planning to
build the world's first and
largest 5 MW biogas turbine.
Wind Power
in operation 19.8 MW
under development 20 MW
Fuel Cell
in operation 8 MW
under development 52.8 MW
developing 78.8 MW
Waste Energy
Chuncheon Combined
Heat & Power Project
Capacity
140MW
38MW
500MW
Construction Period
2014.02-2016.05
2014.04-2015.12
TBD
Cooperation with
Daesan Combined
Heat & Power Co., Ltd.
Daesan-eup, Seosan-si
Chungcheongnam-do
Seokmun-myeon, Dangjin-si
Chungcheongnam-do
Chuncheon-si,
Gangwon-do
Location
in operation 5 MW
under development 3 MW
developing 270 MW
developing 181.9 MW