Vous êtes sur la page 1sur 212

Mill with Classifier

Operating Instructions

LOESCHE Mill with Classifier

Type: LM 63.3+3 CS with LSKS 107 CSr

Project: P09961
Codeword: Tan Truong Clinker

Date of issue: 2011-07-09 / gu

Document No: P09961-M10X00.980 en Rev. A


Original Operating Instructions

LOESCHE Mill with Classifier

Copyright by
LOESCHE GmbH
Hansaallee 243
D-40549 Dsseldorf
Federal Republic of Germany
Phone: +49 (0)211 5353-0
Fax:
+49 (0)211 5353-500
E-mail: loesche@loesche.de
Internet: www.loesche.com

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

Table of Contents
List of Tables .................................................................................................................8
List of Figures................................................................................................................9
1

Liability and warrant conditions ........................................................................11

1.1

Intended use.............................................................................................................. 12

1.2

Reasonably foreseeable misuse ............................................................................... 14

About the instruction manual ............................................................................15

2.1

Subject matter of this instruction manual................................................................... 15

2.2

Plant identification ..................................................................................................... 16

2.3

Reference documents ............................................................................................... 16

2.4

Explanation of symbols used to identify text.............................................................. 16

2.5

Signal words .............................................................................................................. 17

2.6

Pictorial symbols........................................................................................................ 18

2.7

Conversion table........................................................................................................ 21

2.8

Abbreviations ............................................................................................................. 22

Safety ...................................................................................................................23

3.1

Obligations of the operator ........................................................................................ 23

3.2

Obligations of personnel ............................................................................................ 23

3.3
3.3.1
3.3.2
3.3.3
3.3.4
3.3.5

Safety instructions for specific operating phases....................................................... 24


Transport ....................................................................................................................24
Assembly ....................................................................................................................24
Commissioning ...........................................................................................................24
Operation....................................................................................................................25
Maintenance ...............................................................................................................25

3.4
3.4.1
3.4.2

Safety requirements .................................................................................................. 26


Organisational issues .................................................................................................26
Requirements of personnel ........................................................................................26

3.5
3.5.1
3.5.2
3.5.3
3.5.4

Information about specific types of risk...................................................................... 27


Risks posed by electrical energy ................................................................................27
Risks posed by hydraulic and pneumatic energy .......................................................27
Risks posed by harmful gases, vapours and dusts ....................................................27
Risks posed by vibration and noise ............................................................................27

3.6

Duties of the operator ................................................................................................ 28

3.7

Safety checks ............................................................................................................ 29

3.8

Interfaces at the roller grinding mill............................................................................ 30

3.9

Operating and hazardous areas ................................................................................ 31

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

3.10

Shutdown procedure ..................................................................................................32

3.11
3.11.1
3.11.2
3.11.3
3.11.4

Safety instructions for the roller grinding mill components .........................................33


Safety instructions pertaining to the LOESCHE mill................................................... 33
Safety instructions pertaining to the classifier ............................................................33
Safety instructions pertaining to the hydraulic systems.............................................. 34
Safety instructions pertaining to the swinging device................................................. 35

3.12

Installed safety systems .............................................................................................36

Technical Data .....................................................................................................41

4.1
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
4.1.6

Technical Data, LOESCHE roller grinding mill ...........................................................41


Production data, LOESCHE roller grinding mill.......................................................... 42
Electrical data.............................................................................................................42
Water injection............................................................................................................43
Sealing air supply .......................................................................................................43
Ambient data ..............................................................................................................43
Coating and choice of colours .................................................................................... 44

4.2

Technical Data, LOESCHE mill..................................................................................44

4.3

Technical Data, classifier ...........................................................................................45

4.4
4.4.1
4.4.2
4.4.3

Technical Data, hydraulic system...............................................................................46


Hydraulic cabinet HSLM.............................................................................................46
Hydraulic cabinet HSSW ............................................................................................47
Hydraulic cabinet HSMS ............................................................................................ 47

4.5
4.5.1
4.5.2

Technical Data, swinging device ................................................................................48


Hydraulic cabinet, HSAV ............................................................................................48
Swinging device cpl....................................................................................................49

Description of the machine ................................................................................50

5.1
5.1.1

Overview of the roller grinding mill .............................................................................50


Functional description ................................................................................................51

5.2
5.2.1
5.2.2
5.2.3
5.2.4
5.2.5
5.2.6
5.2.7
5.2.8
5.2.8.1
5.2.8.2
5.2.9
5.2.10
5.2.11
5.2.12
5.2.12.1
5.2.13
5.2.14
5.2.15

LOESCHE mill............................................................................................................53
Mill stand cpl...............................................................................................................54
Mill body cpl................................................................................................................57
Lining cpl. ...................................................................................................................59
Grinding bed sprinkler cpl........................................................................................... 60
Table cpl.....................................................................................................................62
LM drive......................................................................................................................65
Grinding parts cpl. ...................................................................................................... 66
Roller (M) cpl. .............................................................................................................67
Roller rotation monitor cpl. .........................................................................................69
Slip-ring sealing cpl. ...................................................................................................70
Rocker arm (M) cpl..................................................................................................... 71
Lever sealing (M) cpl. .................................................................................................73
Rocker arm monitor (M) cpl........................................................................................ 75
Roller (S) cpl...............................................................................................................77
Roller rotation monitor (S) cpl.....................................................................................79
Rocker arm (S) cpl. ....................................................................................................80
Lever sealing (S) cpl...................................................................................................81
Rocker arm monitor (S) .............................................................................................. 82

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

5.3
5.3.1
5.3.2
5.3.3
5.3.4
5.3.5
5.3.6
5.3.7
5.3.8
5.3.9
5.3.10

Swinging device......................................................................................................... 84
Swinging the grinding roller ........................................................................................84
Swinging the support roller .........................................................................................85
Preparatory work for swinging out ..............................................................................86
Swinging-out process .................................................................................................86
Swinging-in process ...................................................................................................87
Lubrication line cpl......................................................................................................88
Seal-air piping.............................................................................................................89
Sealing air monitoring cpl. ..........................................................................................90
Vibration monitoring cpl. .............................................................................................91
Name plate .................................................................................................................92

5.4
5.4.1
5.4.2
5.4.3
5.4.4
5.4.5
5.4.6
5.4.7

Hydraulic system of the grinding roller....................................................................... 93


Hydraulic spring assembly - mode of operation..........................................................95
Spring characteristic ...................................................................................................96
Working pressure (spring stiffness) hydraulic bladder accumulator ........................96
Counterpressure function ...........................................................................................98
Roller relief pressure (RRP) partial load operation ..................................................98
Functions of hydropneumatic spring assembly system ..............................................99
Service functions ......................................................................................................101

5.5
5.5.1
5.5.2

Hydraulic system of the support roller ..................................................................... 102


Mode of operation.....................................................................................................103
Functions of hydraulic positioning device .................................................................103

5.6
5.6.1
5.6.2
5.6.2.1
5.6.2.2
5.6.2.3
5.6.3
5.6.4
5.6.5
5.6.6
5.6.7

Design and construction of the classifier ................................................................. 105


Classifier housing cpl................................................................................................106
Rotor cpl. ..................................................................................................................107
Upper bearing cpl. ....................................................................................................108
Lower bearing cpl. ....................................................................................................108
Classifier temperature sensor cpl. ............................................................................109
Classifier lining cpl....................................................................................................110
Classifier upper housing lining cpl. ...........................................................................111
Classifier drive cpl. ...................................................................................................112
Classifier lubrication line cpl. ....................................................................................113
Name plate ...............................................................................................................114

Transport ...........................................................................................................115

6.1

Scope of supply ....................................................................................................... 115

6.2
6.2.1
6.2.1.1
6.2.1.2
6.2.1.3
6.2.1.4
6.2.2

Delivery and packaging ........................................................................................... 115


Transport sketches ...................................................................................................116
Standard transport sketches for the LOESCHE Milll ................................................116
Standard transport sketches for the classifier...........................................................121
Standard transport sketches for the hydraulic cabinets............................................124
Standard transport sketch for the swinging device ...................................................124
Weight of the components ........................................................................................125

6.3

Checking the delivery status.................................................................................... 127

6.4

Interim storage of supplied parts ............................................................................. 127

6.5
6.5.1
6.5.2

Transport to the installation site............................................................................... 128


Crane transport.........................................................................................................128
Transport with a fork-lift truck ...................................................................................128

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

6.6

Disposal of the packaging ........................................................................................129

6.7

Joining parts on the construction site .......................................................................129

Installation .........................................................................................................130

7.1

Installation reference documents .............................................................................130

7.2

Description of the assembly sequence.....................................................................131

Commissioning .................................................................................................132

8.1
8.1.1
8.1.2
8.1.3
8.1.4

Cold start-up.............................................................................................................132
Requirements ...........................................................................................................132
Applicable documents .............................................................................................. 132
Extent of cold start-up ..............................................................................................133
Cold start-up sequence ............................................................................................134

8.2

Warm start-up...........................................................................................................135

8.3

Commissioning the hydraulic system .......................................................................136

8.4

Commissioning the hydraulic positioning device for support rollers (S) ...................136

8.5
8.5.1
8.5.2
8.5.3
8.5.4
8.5.5

Starting the mill when unfilled or filled ......................................................................137


Master rollers (M) .....................................................................................................137
Support rollers (S) ....................................................................................................138
Shutting down the mill during normal operation .......................................................138
Emergency Stop.......................................................................................................138
On-site operation......................................................................................................138

Operation ...........................................................................................................139

9.1
9.1.1

Local control panels .................................................................................................140


Operation..................................................................................................................140

9.2
9.2.1
9.2.2

Operating modes......................................................................................................140
Local operation......................................................................................................... 140
Automatic mode .......................................................................................................141

9.3
9.3.1
9.3.2
9.3.3
9.3.4
9.3.5
9.3.6

Switching the grinding plant on and off ....................................................................141


Switching the plant on .............................................................................................. 141
Starting the grinding circuit.......................................................................................141
Start sequence .........................................................................................................142
Operating the grinding plant .....................................................................................143
Switching the plant off .............................................................................................. 144
Unlocking the Emergency Stop functions................................................................. 145

9.4
9.4.1
9.4.2

Failure of power supplies .........................................................................................145


Switching the plant off in the event of a power failure .............................................. 145
Switching the plant off in the event of a hydraulic-system failure............................. 145

9.5

Electrical engineering ...............................................................................................146

10

Troubleshooting ................................................................................................147

10.1

11
6

Customer service .....................................................................................................150

Maintenance.......................................................................................................151
P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

11.1

General notes on maintenance works ..................................................................... 151

11.2

Inspection ................................................................................................................ 153

11.3

Cleaning .................................................................................................................. 154

11.4
11.4.1
11.4.2
11.4.3
11.4.4
11.4.5
11.4.5.1
11.4.6
11.4.6.1
11.4.7
11.4.7.1
11.4.7.2
11.4.7.3
11.4.7.4
11.4.7.5
11.4.8
11.4.8.1
11.4.8.2
11.4.9
11.4.9.1
11.4.10
11.4.11
11.4.12
11.4.13
11.4.14
11.4.15
11.4.16
11.4.17
11.4.18

Maintenance ............................................................................................................ 156


Lubrication ................................................................................................................156
General maintenance information for assemblies and machines .............................157
Maintenance: Mill stand cpl. .....................................................................................158
Maintenance: Mill body cpl. ......................................................................................159
Maintenance: Table cpl. ...........................................................................................160
Auxiliary equipment: table cpl...................................................................................163
Maintenance: Rocker arms.......................................................................................167
Auxiliaries: Rocker arm (M) cpl.................................................................................169
Maintenance: Roller..................................................................................................172
Auxiliaries: Roller (M) cpl. .........................................................................................175
Auxiliaries: Roller (S) cpl. .........................................................................................178
Auxiliary equipment: lifter cpl. ...................................................................................179
Auxiliary equipment: tyre profile ruler cpl..................................................................182
Auxiliaries: Oil drain device cpl. ................................................................................183
Maintenance: Spring assembly cpl. ..........................................................................185
Auxiliaries: Spring assembly (M) cpl.........................................................................187
Auxiliaries: Spring assembly (S) cpl. ........................................................................188
Maintenance: Hydraulic accumulators......................................................................190
Auxiliary equipment: Fill and test unit cpl..................................................................193
Maintenance: Hydraulic cabinets..............................................................................194
Maintenance: LM-Drive ............................................................................................196
Maintenance: Gearbox lubrication unit .....................................................................197
Maintenance: Central lubrication unit .......................................................................198
Maintenance: Sealing air system..............................................................................199
Maintenance: Piping system.....................................................................................200
Maintenance: Swinging device .................................................................................200
Maintenance: Grinding bed sprinkler cpl. .................................................................201
Maintenance: Classifier ............................................................................................202

11.5

Checks after maintenance work .............................................................................. 204

12

Spare parts ........................................................................................................205

13

Decommissioning, dismantling and disposal ................................................ 206

13.1

Qualifications of dismantling personnel ................................................................... 206

13.2

Requisite conditions for dismantling ........................................................................ 206

13.3

Carrying out dismantling and disposal..................................................................... 207

14

Supplier documentation ...................................................................................208

Index ........................................................................................................................... 209

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

List of Tables
Tab. 1: Conversion factors ......................................................................................................................... 21
Tab. 2: Abbreviations used......................................................................................................................... 22
Tab. 3: Shutdown procedure ...................................................................................................................... 32
Tab. 4: Characteristic data, LOESCHE roller grinding mill......................................................................... 41
Tab. 5: Limit dimensions, LOESCHE roller grinding mill ............................................................................ 41
Tab. 6: Production data, LOESCHE roller grinding mill.............................................................................. 42
Tab. 7: Electrical data ................................................................................................................................. 42
Tab. 8: Water injection................................................................................................................................ 43
Tab. 9: Sealing air....................................................................................................................................... 43
Tab. 10: Ambient data ................................................................................................................................ 43
Tab. 11: Characteristic data, LOESCHE mill.............................................................................................. 44
Tab. 12: Characteristic data, classifier ....................................................................................................... 45
Tab. 13: Characteristic data, hydraulic cabinet HSLM ............................................................................... 46
Tab. 14: Characteristic data, hydraulic cabinet HSSW .............................................................................. 47
Tab. 15: Characteristic data, hydraulic cabinet HSMS............................................................................... 47
Tab. 16: Characteristic data, swinging device............................................................................................ 48
Tab. 17: Characteristic data, hydraulic cabinet HSAV ............................................................................... 48
Tab. 18: Characteristic data, swinging device cpl. ..................................................................................... 49
Tab. 19: Roller grinding mill, transport weights of components ............................................................... 126
Tab. 20: Fault, Cause, Remedy table....................................................................................................... 149
Tab. 21: Function checks, inspection intervals......................................................................................... 153
Tab. 22: Cleaning intervals....................................................................................................................... 155
Tab. 23: Maintenance table, mill stand..................................................................................................... 159
Tab. 24: Maintenance table, mill body...................................................................................................... 159
Tab. 25: Maintenance table, table ............................................................................................................ 162
Tab. 26: Maintenance table, rocker arm................................................................................................... 168
Tab. 27: Maintenance table, roller ............................................................................................................ 174
Tab. 28: Maintenance table, spring assembly.......................................................................................... 186
Tab. 29: Maintenance table, bladder accumulator ................................................................................... 191
Tab. 30: Maintenance table, hydraulic cabinet......................................................................................... 195
Tab. 31: Maintenance table, LM drive ...................................................................................................... 196
Tab. 32: Maintenance table, gearbox lubricating unit............................................................................... 197
Tab. 33: Maintenance table, central lubricating unit................................................................................. 198
Tab. 34: Maintenance table, sealing air system ....................................................................................... 199
Tab. 35: Maintenance table, swinging device .......................................................................................... 200
Tab. 36: Maintenance table, grinding bed sprinkler ................................................................................. 201
Tab. 37: Maintenance table, classifier ...................................................................................................... 203

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

List of Figures
Fig. 1: LOESCHE roller grinding mill, assembly groups overview ............................................................. 12
Fig. 2: LOESCHE roller grinding mill interfaces, schematic sketch............................................................ 30
Fig. 3: LOESCHE roller grinding mill overview........................................................................................... 50
Fig. 4: Flow of grinding material through mill, pictorial representation....................................................... 51
Fig. 5: LOESCHE Mill, assembly overview ................................................................................................ 53
Fig. 6: Mill stand cpl.................................................................................................................................... 54
Fig. 7: Mill body cpl..................................................................................................................................... 57
Fig. 8: Lining cpl. ........................................................................................................................................ 59
Fig. 9: Grinding bed sprinkler cpl................................................................................................................ 60
Fig. 10: Table cpl. ....................................................................................................................................... 62
Fig. 11: LM drive cpl., schematic sketch .................................................................................................... 65
Fig. 12: Roller (M) cpl. ................................................................................................................................ 67
Fig. 13: Roller rotation monitor cpl. ............................................................................................................ 69
Fig. 14: Slip-ring sealing cpl. ...................................................................................................................... 70
Fig. 15: Rocker arm cpl. ............................................................................................................................. 71
Fig. 16: Lever sealing cpl............................................................................................................................ 73
Fig. 17: Rocker arm monitor cpl. ................................................................................................................ 75
Fig. 18: Roller (S) cpl.................................................................................................................................. 77
Fig. 19: Roller rotation monitor (S) cpl., schematic sketch......................................................................... 79
Fig. 20: Rocker arm (S) cpl......................................................................................................................... 80
Fig. 21: Lever sealing (S) cpl...................................................................................................................... 81
Fig. 22: Rocker arm monitor (S) cpl. .......................................................................................................... 82
Fig. 23: Swinging the grinding roller ........................................................................................................... 84
Fig. 24: Swinging the roller (S) ................................................................................................................... 85
Fig. 25: Sealing air system ......................................................................................................................... 89
Fig. 26: Sealing air monitoring cpl. ............................................................................................................. 90
Fig. 27: Vibration monitoring cpl., schematic sketch .................................................................................. 91
Fig. 28: Name plate .................................................................................................................................... 92
Fig. 29: Interplay, working pressure/counterpressure system.................................................................... 95
Fig. 30: Diagram: Spring stiffness .............................................................................................................. 97
Fig. 31: Spring assembly (S) cpl. ............................................................................................................. 102
Fig. 32: Classifier, assembly overview ..................................................................................................... 105
Fig. 33: Classifier housing cpl., schematic sketch.................................................................................... 106
Fig. 34: Rotor cpl. ..................................................................................................................................... 107
Fig. 35: Upper bearing cpl. ....................................................................................................................... 108
Fig. 36: Lower bearing cpl. ....................................................................................................................... 108
Fig. 37: Schematic sketch of classifier temperature sensor, cpl. ............................................................. 109
Fig. 38: Classifier lining cpl....................................................................................................................... 110
Fig. 39: Classifier upper housing lining cpl............................................................................................... 111
Fig. 40: Classifier drive cpl. ...................................................................................................................... 112
Fig. 41: Schematic sketch of the classifier lubrication line, cpl. ............................................................... 113
Fig. 42: Name plate .................................................................................................................................. 114
Fig. 43: Transport sketch, foundation frame............................................................................................. 116
Fig. 44: Transport sketch, pedestal (left fig.), gearbox baseplate ............................................................ 116
Fig. 45: Transport sketch, bridge.............................................................................................................. 117
Fig. 46: Transport sketch, ring duct.......................................................................................................... 117
Fig. 47: Transport sketch, table (left fig.), gas duct .................................................................................. 118
P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

Fig. 48: Transport sketch, mill body.......................................................................................................... 118


Fig. 49: Transport sketch, cover ............................................................................................................... 119
Fig. 50: Transport sketch, rocker arm (M) (left fig.), rocker arm (S)......................................................... 119
Fig. 51: Transport sketch, roller (M) (left fig.), roller (S) ........................................................................... 120
Fig. 52: Transport sketch, foot-bridges..................................................................................................... 120
Fig. 53: Transport sketch, classifier upper housing.................................................................................. 121
Fig. 54: Transport sketch, classifier lower housing .................................................................................. 121
Fig. 55: Transport sketch, frame............................................................................................................... 122
Fig. 56: Transport sketch, grit funnel ........................................................................................................ 122
Fig. 57: Transport sketch, Rotor ............................................................................................................... 123
Fig. 58: Transport sketch, motor console ................................................................................................. 123
Fig. 59: Transport sketch, hydraulic cabinets........................................................................................... 124
Fig. 60: Transport sketch, cylinder swinging device................................................................................. 124
Fig. 61: Grinding plate segment alignment............................................................................................... 161
Fig. 62: Auxiliary equipment: table cpl...................................................................................................... 163
Fig. 63: Support cpl................................................................................................................................... 165
Fig. 64: Flange-sleeve connection............................................................................................................ 169
Fig. 65: Taper-pin connection................................................................................................................... 170
Fig. 66: Auxiliary equipment: roller (M) cpl. .............................................................................................. 175
Fig. 67: Auxiliary equipment: roller cpl., roller bearing removal................................................................ 176
Fig. 68: Auxiliary equipment: roller (S) cpl................................................................................................ 178
Fig. 69: Lifter cpl. ...................................................................................................................................... 179
Fig. 70: Changing the tire ......................................................................................................................... 180
Fig. 71: Tire profile ruler cpl...................................................................................................................... 182
Fig. 72: Oil drain device (M) cpl................................................................................................................ 183
Fig. 73: Oil drain device cpl. ..................................................................................................................... 184
Fig. 74: Dismantling the spring pin ........................................................................................................... 188
Fig. 75: Assembling the spring pin ........................................................................................................... 189

10

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Liability and warrant conditions

Liability and warrant conditions


Our "General terms and conditions of sale and delivery" apply. Warranty and
liability claims for material damage and personal injury will not be accepted if
they can be attributed to one or more of the following causes:
Failure to use the machine as intended (see chapter "1.1 Intended use", on
page 12)
Improper mounting, putting into operation, running and maintenance of the
machine
Operation of the machine when safety switching devices are defective or
when safety relays and protective devices have been improperly fitted or
are not in perfect working order
Non-compliance with the information in the instruction manual with regard to
the transportation, storage, assembly, commissioning, operation,
maintenance and repair of the machine
Unauthorised changes to the design and structure of the machine
Unauthorised technical modifications (e.g. drive ratios, output and/or speed)
Failure to monitor machine parts which are prone to wear
Improperly completely repairs
Catastrophes attributable to extraneous causes and force majeure
Deployment of untrained personnel

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

11

LOESCHE Mill with Classifier


Liability and warrant conditions

1.1

Intended use
38

1
2

37
3

36
35

34
33
32
31
30
29
28
27

26

25

24

23

10

22

11

21

12
13

20
19
17

14

18

15

001219

16

Fig. 1: LOESCHE roller grinding mill, assembly groups overview

12

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Liability and warrant conditions

Key
1 Classifier drive cpl.
2 Classifier platform cpl.
3
4
5
6
7
8
9
10
11
12
13

Raw material inlet


Star feeder
Hydraulic oil supply, support rollers
Sealing air pipeline cpl.
Lever sealing (M) cpl.
Roller (M) cpl.
LM lubrication line
Roller rotation monitor (M) cpl.
Rocker arm monitoring (M) cpl.
Rocker arm (M) cpl.
Mill stand cpl.

14 Spring assembly (M) cpl.


15 Ring pipeline cpl./
Connecting pipeline cpl.
16 LM-drive cpl.
17 Hydraulic oil supply, grinding rollers
18 Swinging device
19 Table cpl.
20 Grinding parts cpl.
21 Roller (S) cpl.
22 Lever sealing (S) cpl.
23 Rocker arm monitoring (S) cpl.
24 Roller rotation monitor (S) cpl.
25 Rocker arm (S) cpl.
26 Spring assembly (S) cpl.

27 Lining cpl.
28 Mill body cpl.
29 Classifier housing cpl.
30 Rotor support cpl.
31 Lining cpl.
32 Lower bearing cpl.
33 Guide vane carrier cpl.
34 Rotor
35 Upper bearing cpl.
36 Classifier upper housing lining cpl.
37 Finished material outlet
38 Classifier lubrication line cpl.

The LOESCHE roller grinding mill serves exclusively to grind grinding stock in
accordance with the specifications given in the chapter "Technical Data.
The grinding stock is fed to the roller grinding mill in metered amounts via a
conveyor. The grinding process is generated by pressure and friction under the
effect of a hydropneumatic roller spring assembly.
The ground stock is thrown outwards by centrifugal force and carried by the gas
flow to the classifier. The finished product passes through the classifier with the
desired fineness, is discharged and dispatched for further use.
This LOESCHE roller grinding mill is intended for commercial use and was
developed, designed and constructed solely for this purpose.

WARNING
Personal and/or machine damage!
This machine is intended solely for the purpose described above. Any other use
or modification of the machine without the written consent of the manufacturer is
deemed unacceptable. The manufacturer accepts no liability for damage
resulting from such use. The risk is borne solely by the operator.
The machine may only be put into operation if the superior system in which it is
being installed complies with regulations and once there is an assurance that all
safety switching devices have been assembled and are fully functional.

Intended use also includes observation of the manufacturer's instructions


regarding the assembly, disassembly and reassembly, commissioning,
operation and maintenance (inspection, servicing, repair) of the roller grinding
mill.

Note on application of the EC Directive EMC 2004/108/EEC:


According to DIN EN 61000-6-4 (Generic standards - Emitted interference for
industrial environments) the machine may not be used in residential, business or
industrial areas or in small businesses unless it also satisfies the standard DIN
EN 61000-6-3 (Emitted interference).

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

13

LOESCHE Mill with Classifier


Liability and warrant conditions

1.2

Reasonably foreseeable misuse


Use of the roller grinding mill to grind materials contaminated by packaging
materials is prohibited.
It is not permitted to operate the roller grinding mill without the metal separator
connected upstream.

14

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


About the instruction manual

2
2.1

About the instruction manual


Subject matter of this instruction manual
This instruction manual describes all necessary tasks and activities relating to
the machine. These include transportation, assembly, operation,
troubleshooting and maintenance.
A separate document describes the electrical equipment and the electrical
installation work. It also features the corresponding drawings.
The instruction manual contains information which is important for the safe,
correct and efficient running of the machine. Observation of this information will
help to prevent risks, avoid repairs and downtimes as well as increase the
reliability and service life of the machine(s).
This instruction manual must be supplemented with information derived from
applicable national regulations governing accident prevention and the protection
of the environment.
The instruction manual must be read and used by everyone charged with
working with/on the machine.
The instruction manual must be available and accessible at all times in the
machine's place of use.
You must read this instruction manual before using the machine(s).
Compliance with the safety instructions is mandatory.
You must also comply with the binding regulations in force in the country of
use with regard to accident prevention and acknowledged rules for safe and
proper working.
The tasks described in this instruction manual are listed in such a way as to be
understood
in the chapters Control and Operation by an instructed person,
in the chapters Transportation, Erection and Assembly, Maintenance,
Fault/Cause/Rectification by a skilled worker.
The chapters Transportation, erection and Assembly, Maintenance,
Fault/Cause/Rectification are intended for skilled workers only. Tasks
described in this chapter may only be carried out by skilled workers.
Instructed person
A person who has been instructed or trained by a skilled worker in the tasks
assigned to him/her and the potential hazards of improper operation, in addition
to the necessary safety devices and safety measures.
Skilled worker
A skilled worker is a person who, by combining his or her specialist training,
knowledge and experience with awareness of applicable standards, is able to
assess the tasks with which or he she has been assigned and identify potential
hazards (definition based on EN 60204-1).
The figures in this manual have been provided for illustrative purposes only.
The specific drawings supplied with each purchase are your primary source of
reference.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

15

LOESCHE Mill with Classifier


About the instruction manual
2.2

Plant identification
The information in this instruction manual applies only to the machine whose
type designation is give on the title page.
The name plate containing the machine data is attached to the machine (for
position, see Technical Drawings).
For all enquiries, it is important to specify correctly:
the designation
the type designation
This is the only way of ensuring that your enquiry is dealt with quickly and
correctly.

2.3

Reference documents
Additional documents should be referred to in conjunction with this instruction
and installation manual; please refer to the list in the superordinated main
table of contents.
We do not accept liability for damage due to non-compliance with the
information in this instruction manual.
The scope of the product includes this manual and all associated reference
documents.
Should ownership of the product be transferred, this instruction manual,
along with all associated reference documents, must be handed over to the
new owner.

2.4

Explanation of symbols used to identify text


Symbol identifying a list of items
In the text, each item in a standard list is preceded by a dash.
Symbol identifying an instruction
Instructions describing actions to be carried out are preceded by bullet
points. Actions must be completed in the sequence described.
Symbol identifying separate documents
The opened book indicates additional separate documents.
Cross-references
Cross-references are links either to a section of text in this instruction manual or
to another document. In the case of cross-references to a section of text, either
the chapter, a figure number or a page number will be indicated.
In the case of cross-references to another document, a document name, a
drawing number or a document number will be indicated (e.g. see supplier
documentation).

16

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


About the instruction manual

2.5

Signal words
DANGER
Indicates a hazardous situation which, if not avoided, WILL result in death or
serious injury.

WARNING
Indicates a hazardous situation which, if not avoided, COULD result in death or
serious injury.

CAUTION
Indicates a hazardous situation which, if not avoided, COULD result in minor or
moderate injury.

NOTICE
Indicates a hazardous situation which, if not avoided, COULD result in property
damage.

Note
Indicates useful or additional information for easy and safe usage of the
machine(s) and the manual.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

17

LOESCHE Mill with Classifier


About the instruction manual

2.6

Pictorial symbols
Please note the following symbols which have been used in the manual to
identify safety information:
Safety symbols comprise a warning triangle and a symbol against a yellow
background. In the instruction manual, the following symbols have been used to
identify risks to personal safety:
DANGER
Direct risk to life and limb!

DANGER
Toxic substances!

DANGER
Risk of electrocution!

DANGER
Risk of falling!

DANGER
Explosive materials!

DANGER
Suspended loads!

CAUTION
Hot surfaces!

18

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


About the instruction manual

CAUTION
Risk of tripping!

WARNING
Risk of injuries to the hands!

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

19

LOESCHE Mill with Classifier


About the instruction manual

Other signs:
NOTICE
Possible risk to machine!

Note
Useful information and special notes.

Note on environmental care!


Useful information and special notes:

Switching symbol
prompts the user to interrupt the power supply.

Lock symbol
prompts the user to lock a switch state.

Book symbol
Notice to additional documents

20

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


About the instruction manual

2.7

Conversion table
The following conversion factors can be used to convert metric values into US
units:
Convert from

into

Multiply by

mm

inch

0.3937

inch

mm

25.4

ft

3.208084

ft

0.30479

m2

ft2

10.76391

cm

in

0.155

cm3

in3

0.061

gal (US)

0.264178

kg

lbs

2.204622

lbs

kg

0.45359

lbs

2204.622

lbs

0.0004536

kN

lbf

224.809

kW

HP

1.34

daN/cm2

lbf/in2

lbf/in

14.50378
2

daN/cm

0.06895

bar

psi

14.50378

psi

bar

0.06895

m/s

ft/s

3.28084

Nm

lbf ft

0.7375

1.8 x C+32

(F-32)/1.8

t/m2

lbs/ft2

204.8

m /t

ft /lbs

0.04882

Tab. 1: Conversion factors

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

21

LOESCHE Mill with Classifier


About the instruction manual

2.8

Abbreviations
The following abbreviations are used in this manual:
Abbreviation

Stands for

HSLM

Hydraulic cabinet LOESCHE mill

HSMS

Hydraulic cabinet grinding roller lubrication

HSSW

Hydraulik cabinet support-roller

HSAV

Hydraulic cabinet swinging-out device

HSBF

Hydraulic cabinet filling unit (optional)

M-... or (M)

Master-... (e. g. M-roller, rocker arm (M), etc.)

S-... or (S)

Support-... (e. g. S-roller, spring assembly (S), etc.)

PPE

Personal protective equipment

Fig.

Figure

Tab.

Table

Tab. 2: Abbreviations used

22

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Safety

Safety
The machine has been designed and built in accordance with the state of art
and acknowledged safety engineering practice. However, its use can pose risks
to the life and limb of its user and/or third parties. There is also the potential for
damage to the machine or other equipment and property.
No changes, additions or conversions may be made to the machine without the
manufacturer's approval. This also applies to welding on load-bearing parts.
Written permission must be obtained from the manufacturer for all conversion
work.

3.1

Obligations of the operator


The operator is obliged:
Only to use trained personnel equipped with personal protective equipment
who are familiar with the fundamental regulations governing occupational
safety and accident prevention and have been instructed in the running and
operation of the machine.
Only to use personnel who have read the safety chapter and the safety
instructions in this instruction manual and have signed a declaration
indicating their understanding of their content.
To have personnel undergo annual instruction in occupational safety and
accident prevention
To comply with legal requirements regarding operational safety and
reliability
To carry out regular checks to ensure that personnel are working in a way
which exhibits an awareness of safety

3.2

Obligations of personnel
All persons charged with working on/with the machine are obliged:
To comply with the fundamental regulations governing occupational safety
and accident prevention
To read the safety chapter and the safety instructions in this instruction
manual and sign a declaration indicating their understanding of their content
To comply with the safety instructions in the supplier documentation
To keep all safety and hazard instructions on the machine in a legible
condition
To keep transport routes clear and free from obstacles

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

23

LOESCHE Mill with Classifier


Safety

3.3
3.3.1

Safety instructions for specific operating phases


Transport

3.3.2

Assembly

3.3.3

Only use a suitable transport vehicle with sufficient load-bearing capacity.


Secure the load safely. Use designated rigging points.
When loading equipment, only use lifting devices and load-bearing
equipment with sufficient load-bearing capacity.
Designate a competent banksman for lifting operations.
Machine parts must only be lifted properly and with lifting devices as per the
specifications in the instruction manual (rigging points for load-bearing
equipment, etc.).
Use safe lifting devices bearing the CE mark.

Secure the areas in which work will be taking place to prevent unauthorised
access.
Co-ordinate assembly work with all companies involved.
Ensure that all auxiliary equipment used (e.g. ladders) is safe. Risk of
falling!
When carrying out assembly work overhead, use ladders/scaffolding and
working platforms which have been tested for safety. Do not use machine
parts as a means of accessing overhead locations!
Do not conduct welding current through bearings!

Commissioning
Make sure that
prior to powering up machines, these cannot pose a risk of potential injury.
the safety instructions pertaining to cold start-up and the supplier
documentation are read, digested and followed.
working areas are protected.
edges are made safe.
all auxiliary equipment used (e.g. ladders or safety harnesses) is safe. Risk
of falling!
ear defenders are worn in the event of noise pollution in excess of 85 dB(A).
hazardous areas are closed off to unauthorised persons.
prior to the test run, an acoustic signal is issued to warn personnel if a startup test is only possible with the safety devices inactive.
the main switch is turned off during necessary retrofit or adjustment
operations and that machines are secured against unintentional poweringup.
the activities during commissioning are carried out by qualified skilled
personnel only.
safety distances are observed.
machine parts are not used as a means of accessing overhead locations.
safety devices are removed only when the machine is at a standstill.
a warning is given before safety devices are shut down for start-up work,
and that immediately after this work is completed these safety devices are
reinstalled are restarted.

24

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Safety
3.3.4

Operation

3.3.5

Prior to power-up, check that this cannot pose a risk of personal injury.
Check the machine at least once per shift for any visible external evidence
of damage and check that safety switching devices are in perfect working
order. If you detect a problem, stop the machine immediately and rectify the
cause.
Only operate the machine if all safety switching devices are in place and
fully operational.
Do not switch off or remove exhaustion devices or ventilation equipment
when the machine is running.
In the event of malfunctions, stop and secure the machine immediately.
Have the causes of such problems rectified immediately.

Maintenance

Carry out prescribed setting, maintenance and inspection work at the


required intervals.
Inform operators before starting service and maintenance work.
Stop the infeed of materials.
Seal off the area in and around which work will be carried out.
The machine must be stopped and disconnected from the voltage supply
prior to commencing cleaning, service and maintenance work. Secure the
machine to prevent restarting.
Lock the main switch and remove the key. Affix a sign warning against
restarting.
Depressurise pneumatic, vapour pressure and hydraulic equipment and let
off any remaining pressure.
Secure all system components and operating media (e.g. compressed air
and hydraulics) upstream and downstream of the machine to prevent
accidental starting.
Use suitable arresting devices to lock moving parts.
When replacing larger components, rig and secure them carefully to lifting
devices. Do not stand or work under suspended loads.
Check that all screwed union connections are tight.
Once maintenance work is complete, check that all safety switching devices
are in working order.
When carrying out assembly work overhead, use ladders/scaffolding and
working platforms which have been tested for safety. Do not use machine
parts as a means of accessing overhead locations! Safety harnesses to
protect against falling must be worn when carrying out maintenance work
overhead.
There must be no evidence of soiling, oil, grease, snow and ice on handles,
steps, railings, resting places, platforms, ladders, etc.
Any machine parts which are not in perfect working order must be replaced
immediately.
Only original spare and wear parts may be used. If third-party products are
used, we cannot guarantee that they will have been designed and built to
provide the requisite levels of performance and safety.
Ensure that all auxiliary equipment used (e.g. ladders) is safe. Risk of falling
Use safe lifting devices bearing the CE mark.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

25

LOESCHE Mill with Classifier


Safety

3.4

Safety requirements

3.4.1

Organisational issues

3.4.2

The operator must provide suitable personal protective equipment.


The instruction manual must be supplemented by additional instructions
including information about supervision and reporting duties taking account
of individual operating conditions, e.g. with regard to how work is organised,
operational sequences, the deployment of personnel, etc.
Personnel working on or with the machine must tie back long hair and must
not wear loose clothing or jewellery (including rings). Non-compliance with
this requirement could result in injuries due to becoming suspended from or
dragged into the machine.
Check safety switching devices regularly to ensure that their inspections are
up to date, see chapter 3.12 Installed safety systemson page Seite 36.
Make sure that you are aware of the possible means of reporting and
fighting fires.
Specify the type of fire-extinguishing equipment to be used.
Provide information about where fire extinguishers are located and how to
use them.
Provide instructions for emergency procedures.

Requirements of personnel

26

The machine's safety switching devices are described in chapter 3.12


Installed safety systemson page Seite 36.
Maintain the requisite safety clearances specified.
The fitting of any part components for safety switching devices resourced by
the operator is solely his or her responsibility.
Isolating or non-isolating safety switching devices might be required in
addition to those supplied with the machine.
Safety switching devices must not be removed until after the machine has
been stopped and secured against restarting.
Before taking safety switching devices out of service (e.g. for maintenance
work), issue warnings accordingly and replace such devices or put them
back into service immediately on completion of this work. Safety switching
devices must also be checked prior to operation being resumed.
Safety switching devices must be checked regularly to ensure that they are
in full working order. Inspection intervals and procedures must be complied
with and logged, see chapter 3.12 Installed safety systemson page Seite
36.
Comply with the safety instructions in the supplier documentation.

Only personnel who have undergone training and instruction may work on
the machine.
Relevant experience is required for work involving each of the assembly,
operation, refurbishing, maintenance and service of the machine.
Make sure that only personnel authorised to do so work on the machine.
Personnel must wear personal protective equipment. The supervisor must
check that this requirement is met.
Responsibilities in respect of the assembly, operation, refurbishing,
maintenance and service of the machine must be clearly defined.
P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Safety

3.5
3.5.1

Information about specific types of risk


Risks posed by electrical energy

3.5.2

Depressurise system sections and pressure lines (hydraulic, compressed


air) to be opened in the context of repairs prior to starting work.
Only personnel with specialist knowledge and experience of hydraulics are
permitted to work on hydraulic equipment.
Hydraulic and compressed air lines must be laid and assembled correctly.
Do not mix up connections! Valves and fittings and the length and quality of
flexible hoses must meet requirements.
All lines, hoses and couplings must be checked regularly for leaks and
visible evidence of external damage. Damage must be made good
immediately. Leaks can lead to injuries and fires.
Even if there is no visible evidence of a defect which might pose a risk to
safety, hydraulic flexible hoses must be replaced at regular intervals.

Risks posed by harmful gases, vapours and dusts

3.5.4

Only skilled electricians working in compliance with correct electrical


engineering practice are permitted to work on electrical installations and
equipment.
Be aware of the possibility of damage affecting electrical equipment and
carry out regular inspections accordingly. Risk due to loose connections and
scorched cables. This problem must be rectified immediately.
The switching cabinet must be kept locked at all times. Access must only be
permitted to authorised personnel who are in possession of a key or tool.
When working on live parts, seek the assistance of a second person who, in
the event of an emergency, will be able to activate the emergency stop or
main switch to disconnect the voltage supply.
In the event of faults affecting the power supply, the machine must be shut
down immediately.

Risks posed by hydraulic and pneumatic energy

3.5.3

Personnel undergoing training on the machine must be under the


permanent supervision of an experienced worker.

Harmful gases, vapours and/or dusts can escape when covers are open.
Ensure that adequate ventilation (a means of exhaustion might be required)
is provided.
A dust mask must be worn when cleaning the inside of the classifier
housing.
Express permission must be obtained prior to carrying out any welding,
firing or grinding work. The machine must be cleaned of any dust and
flammable substances prior to commencing such work. Fire and explosion
risk!
Observe any applicable national regulations when working in confined
spaces.

Risks posed by vibration and noise

During operation, any sound insulation devices on the machine must be


activated.
Wear personal hearing protection as prescribed.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

27

LOESCHE Mill with Classifier


Safety

3.6

Duties of the operator


Note
In the EEA (European Economic Area) it is compulsory to observe the national
implementation of the framework directive (89/391/EEC), the associated
individual directives and in particular Directive (89/655/EEC) covering the
minimum health and safety requirements pertaining to the use of work materials
and equipment by employees in the workplace (the latest version thereof in each
case).
In Germany the Ordinance on Industrial Safety and Health of October 2002 must
be observed (implementation of the above-mentioned directive in national law).
The operator must obtain the local type approval and adhere to the conditions
associated therewith.
The operator must also adhere to the local statutory provisions governing
the safety of personnel (accident-prevention regulations)
the safety of work equipment and materials (protective equipment and
maintenance)
the disposal of products (waste legislation)
the disposal of materials (waste legislation)
cleaning (cleaning agents and disposal)
environmental-protection conditions
CAUTION
Risk of burns due to contact with hot surfaces!
Before operating the plant, the operator must ensure that the insulation and
protective coverings are fitted on hot machine parts.

Connections
Before operating the plant, the operator must ensure that the local regulations
(e.g. for electrical connection) are observed during installation and start-up
operations if these operations are carried out by the operator himself.

Lighting
The operator must ensure that the machine is adequately and uniformly
illuminated in all areas.
An illuminance level of 300 lux is recommended in the operating area
(maintenance value; ASR 7/3 applicable in Germany).

28

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Safety

3.7

Safety checks
The following safety checks are carried out by the manufacturer before the
machine leaves the factory:
1. Airborne noise measurement in accordance with the Machinery Directive,
Annex 1 (item 1.7.4/f)
2. Check and inspection in accordance with DIN EN 60204-1:2007-06
Inspection to verify compliance of the electrical equipment with the
technical documentation
Continuous connection of the protective conductor system
Insulation resistance tests
Voltage tests
Protection against residual voltages
Function tests
Verification test
The functions of the electrical equipment, particularly those affecting
safety and protective measures, have been tested.
Note
The roller grinding mill contacts the building's steel frame at several positions.
This ensures earthing and that a connection exists to the buildings equipotential
bonding.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

29

LOESCHE Mill with Classifier


Safety

3.8

Interfaces at the roller grinding mill

4
1
4
6

000501

Fig. 2: LOESCHE roller grinding mill interfaces, schematic sketch


Key
1 Finished material outlet
2 Inspection opening
3 Process air inlet

4 Access platform
5 Hydraulik system
6 Grinding material inlet

Further interfaces not shown (observe mill installation diagram):


Outgoing-air discharge
Compressed-air supply
Seal-air supply
Electrical supply
Control elements

30

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Safety

3.9

Operating and hazardous areas


For the operator the areas on the switching cabinet and control desk (central
control room) and on the local control panel are operating areas
For the purpose of carrying out refurbishing, cleaning, maintenance and repair
work the immediate area around the machine and the interior of the machine
are hazardous areas. Only skilled personnel adhering to the safety regulations
are permitted to work in the hazardous areas.
DANGER
The hazardous area for maintenance and repair work stretches roughly 1 m
around the machine or component assembly.
The swinging range of the switching-out device of the rollers and the swinging
range of the opening switching-cabinet doors must also be taken into
consideration.
Keep the area around the machine free of objects.
Observe the local safety regulations is the installation diagram is altered by
the customer.
Electrical current!
Beware of the hazards due to electrical current when handling the
machine. Current is applied ahead of the main switch or maintenance switch
even in the "0" position.
Perform the shutdown procedures (see Chapter 4.5) before carrying out
cleaning, maintenance and repair work.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

31

LOESCHE Mill with Classifier


Safety

3.10 Shutdown procedure


Shutdown procedure
It is essential to observe the following shutdown procedure prior to cleaning,
maintenance or repair work (by skilled personnel only).
1. Run the machine empty
This takes approx. 60 minutes.
2. Shut off the process gas supply
3. De-energise the machine:
Switch the mains isolator (main switch) on the switching cabinet to "0.
Make sure that no voltage is applied.
Short-circuit and earth/ground the plant.
Secure the main switch against anauthorised turning on with a padlock.
4. Shut off the pneumatic system:
Close the stop valve.
Check whether the plant is depressurised.
Secure the stop valve against reopening.
5. Shut off the hydraulic system:
Switch off the hydraulic unit.
Check whether the system is depressurised.
Secure the hydraulic unit against switching on again.
6. Shut off the seal-air supply:
Close the stop valve.
7. Close the opened electrical cabinets when cleaning so as to prevent the
ingress of water, steam or dust.
Failure to comply with this instruction results in danger to life and limb.
Tab. 3: Shutdown procedure

32

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Safety

3.11 Safety instructions for the roller grinding mill components


3.11.1 Safety instructions pertaining to the LOESCHE mill
The following safety instructions must be observed in particular:
In the case of large mills, it is not permitted to remain in the mill pedestal
("mill stand" assembly) during grinding operation. Accident hazard!
Make sure that the mill motor cannot be started before entering the grinding
chamber.
Persons are not permitted to remain either in the grinding chamber or in the
area of the rollers during the roller swinging-out and swinging-in processes.
The hydraulic accumulators of the roller spring assembly are covered in the
country of manufacture by an inspection interval of 2 years.
The operator must ensure that the hydraulic accumulators are operated in
accordance with the statutory provisions of the country of erection.
Carry out maintenance work on the hydraulic system only after the system is
depressurised and if necessary has been completely drained.
Open inspection doors/covers only when the plant has been shut down and
is in the rest state.
To prevent accidents resulting from falls, use safety belts during
maintenance work which calls for the platform to be disassembled.
During all maintenance and inspection work observe the statutory accidentprevention regulations of the relevant country of erection.

3.11.2 Safety instructions pertaining to the classifier


The following safety instructions must be observed in particular:
Observe the statutory accident-prevention regulations of the relevant country
of erection during all maintenance and inspection work.
Open the inspection covers of the classifier and the classifier drive only after
stopping all the rotating parts of the classifier and LOESCHE mill.
Secure the drives against unauthorised turning on, e.g. with a padlock.
Install the safety devices properly before starting up the machine.
Make sure that the interior of the classifier is adequately ventilated during
maintenance work.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

33

LOESCHE Mill with Classifier


Safety

3.11.3 Safety instructions pertaining to the hydraulic systems


The following safety instructions must be observed in particular:
The hydraulic cabinet may only be used for the purpose intended by the
manufacturer.
The limits specified by the manufacturer for the ratio of hydraulicaccumulator operating pressure to fill pressure must not be over- or
undershot.
When filling the accumulator with the necessary gas filling pressure the
correction factor for the ambient temperature, specified by the manufacturer,
must be considered! (see technical information hydraulic system).
The pressure-limiting valves (6...) set by the manufacturer in the HSLM must
not be altered (see Technical Documents for Hydraulic System).
The quality, cleanliness and operational viscosity of the hydraulic medium
are crucial to determining the operational safety and reliability, economy and
service life of the machine.
Make sure that the LOESCHE hydraulic scheme is available in the hydraulic
cabinet.
Make sure that communication between the workers on or in the mill and the
hydraulic-cabinet operator is possible and is practised during safety-related
work.
Make sure during maintenance work (local operation of the hydraulic
cabinets) that there are no persons remaining in the area of the rollers when
the latter are being raised or lowered. Accident hazard!
Lay spacers underneath when the rollers are raised.
Carry out maintenance work on the hydraulic system only after the system is
depressurised and has been completely drained.
Use only nitrogen (N2) to refill the hydraulic accumulators. Oxygen or air
may cause an explosion when combined with oil!
The nitrogen (N2) purity has to be at last 99,995 %, filtered < 3 m.
Use exclusively the original filling unit to fill the hydraulic accumulators.
Observe the information in the hydraulic scheme.
Change filters only after you have made sure that the pump motor cannot be
started.
Use only the specified hydraulic oil in accordance with LOESCHE
recommendations. The cleanliness class of the hydraulic oil used should
meet the requirements of ISO 4406 19/17/14 at the very least.

34

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Safety

3.11.4 Safety instructions pertaining to the swinging device


The following safety instructions must be observed in particular:
Do not remain in the swinging range of the rollers while they are being
swung out and in.
When a complete roller is removed from the rocker arm, the latter must
remain coupled with the hydraulic swinging-out cylinder. This prevents the
rocker arm from also being raised when the roller axle is pulled upwards by
frictional locking in the conical clamping sleeves and from springing back as
soon as the axle is free. Accident hazard!
Do not use the hydraulic cylinders without the line-break retainers.
Ensure that personnel are adequately protected during all operations where
the rollers are swung in and out.
To prevent accidents resulting from falls, use safety belts during
maintenance work which calls for the platform to be disassembled.
Check the high-pressure hoses for damage prior to each use. Replace these
hoses if necessary. Use only high-pressure hoses of the required pressure
stage.
Use only the specified hydraulic oil in accordance with LOESCHE
recommendations. The cleanliness class of the hydraulic oil used should
meet the requirements of ISO 4406 19/17/14 at the very least.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

35

LOESCHE Mill with Classifier


Safety

3.12 Installed safety systems


DANGER
Direct risk to life and limb!
It is strictly forbidden to override safety systems or change their method of
operation.
The operator must ensure that unauthorised persons (not including operating
and maintenance personnel) are allowed to access the operating area.
Risk of electrocution!
Secure the maintenance switch through the use of a padlock after it has
been switched off before you begin with commencing refurbishing,
maintenance, overhaul or cleaning work.
Electrical cabinets can only be opened using a special key. The special key may
only be issued to one authorised person.
Ensure that doors/flaps on electrical cabinets are only opened by specialist
personnel for maintenance purposes and troubleshooting, and otherwise
remain closed and locked.

Operating and maintenance personnel will be trained by LOESCHE GmbH


personnel at the plant operation location. If you have any questions or are
uncertain of anything, please contact LOESCHE GmbH.

Note
This operating manual is a component of the equipment and must always be
accessible to operating personnel.
All safety information contained therein must be observed.

36

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Safety

The safety systems fitted must be checked at regular intervals using suitable
inspection methods (see following table).

Inspection intervals

Inspection methods

daily

weekly

visual check

monthly

function check

quarterly

measurement

half yearly

annually

The grinding plant is equipped with the following safety systems:


Mains isolator

Inspection

(Main switch or maintenance switch)


Interval
The machine is connected to the power supply or
y
disconnected from it by activating the main switch or
the maintenance switch. These switches are located
at the electro cabinet.
Further separation facilities are:
Pneumatics
pressure relief,
Hydraulics
pressure equalisation valve,
Sealing air
stop valve.

Method
F

Emergency stop system

Inspection

The machine is equipped with several emergency


stop systems. The machine is put into a safe
operating state immediately when the emergency
stop switch is pressed.
The location and effect of the emergency stop
switch is determined by the owner.
Emergency stop switches may be located:
on the switching cabinet (superordinated
system)
on the mill (activates interlock overall system)
on the classifier (activates interlock overall
system)
on the sealing air fan (activates interlock overall
system)
on the grease pump (emergency stop pump,
maintenance switch)

Interval

Method

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

37

LOESCHE Mill with Classifier


Safety

Plant control

Inspection

The plant control is carried out internally with a 5Interval


core cabling system, 3-phase, with loadable MP and
y
separate earth cable jacketed with
GREEN/YELLOW colouring.

Metal separation

S, F, M

Inspection

A metal detector with ferrous metal separation in the Interval


raw coal feed prevents metal parts which might
M
cause sparks entering the grinding chamber.

38

Method

Method
F

Resting places and railings

Inspection

In order to guarantee secure walking routes and


standing locations for operating and maintenance
personnel, appropriate areas on the machine have
been secured using platform and guardrail
equipment.

Interval

Method

V, F

Contact protection

Inspection

Piping carrying heat, in addition to machine parts


which heat up, are provided with insulation or
protective coverings on site to prevent burns.

Interval

Method

V, F

Vibration monitoring

Inspection

A vibration pickup is mounted above the upper


housing mill door to monitor how the mill runs
("vibration monitoring cpl." according to the
drawing).
As soon as the indicator (in the measuring cabinet)
exceeds a preset value, the normal shutdown
process is initiated for grinding plant.

Interval

Method

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Safety

Sealing air monitor

Inspection

The sealing air operational system is monitored by a Interval


pressure monitor to prevent foreign bodies from
m
getting into the system. The entire plant is shut
down if the pressure drops below the permissible
value.

Method
FC

Overload protection

Inspection

The electric motors are equipped with overload


protection to protect the machine against
overheating or overloading.

Interval

Method

F, M

Inspection door

Inspection

The mill has been fitted with a bolted door to allow


carrying out of inspection, maintenance, cleaning
and repair work.

Interval

Method

V, F

Roller rotation monitor

Inspection

Rotation of the rollers is monitored by means of


Interval
sensors. Irregularities (speed fluctuations, stoppage)
m
are signalled in the control room.

Rocker arm monitor

Method
FC

Inspection

Stop buffers or proximity switches at the rocker arm Interval


limit its swivel range. So, direct metal contact
between rollers and grinding track is prevented. The Y
position of the rocker arm with lifted rollers is
monitored electronically.

Method
V, F

Hydraulic monitoring

Inspection

The hydraulic system is fitted with control lamps


which signal or prevent an unprogrammed fall in
hydraulic pressure.

Interval

Method

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

39

LOESCHE Mill with Classifier


Safety

40

Temperature monitor, rotor bearings

Inspection

Each of the classifier rotor bearings is monitored by


a temperature sensor with two independent
measuring points. In the event of the permissible
temperatures being exceeded, the signal from the
sensors will generate an alarm in the central control
room.

Interval

Method

FC, M

Classifier outlet temperature monitoring

Inspection

Two independent temperature sensors in the


classifier gas duct exit measure the gas
temperature. Exceeding the limit values defined
during initial start-up leads to an alarm being
displayed in the central switch room or intervention
in the process control.

Interval

Method

F, M

Lubricating system fill level monitoring

Inspection

A lubrication compound dispensing vessel is


installed on the automatic lubrication pump.
The fill level in the container is monitored by a fill
level monitor (min; MinMin).

Interval

Method

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Technical Data

4
4.1

Technical Data
Technical Data, LOESCHE roller grinding mill
Note
The materials/media needed for operation of the machine in compliance with its
intended use are procured and used by the its operator. Proper handling of
these materials/media and the associated risks are the sole responsibility of the
operator. The operator must draw up a set of instructions for dealing with risks
and disposal instructions for operating and maintenance personnel. The
information in the safety data sheets issued by the manufacturer(s) of the
material and media must be observed.

Characteristic data, LOESCHE roller grinding mill


Year of construction

Tan Truong Clinker

Order/project number

P09961

Password

2011

Tab. 4: Characteristic data, LOESCHE roller grinding mill

Dimensions and weight, LOESCHE roller grinding mill


Height

approx. 23.8 m

Width

approx. 15.6 m

Depth

approx. 19.0 m

Total weight consisting of:


LOESCHE mill
Classifier
Hydraulic cabinets
Swinging device

approx. 919,318 kg

Tab. 5: Limit dimensions, LOESCHE roller grinding mill

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

41

LOESCHE Mill with Classifier


Technical Data

4.1.1

Production data, LOESCHE roller grinding mill


Designation

OPC

PLC

Quick Cement

Clinker

95%

68%

86%

Gypsum

5%

5%

5%

Limestone

20%

9%

Puzzolana

Raw material mix

Raw material grain size


before LOESCHE mill

100% < 100 mm


90% < 70 mm

Material moisture
(average)

0.46% H2O

2.36% H2O

Grinding-stock quality

No metallic filings permitted, solvent-free

Throughput

280 t/h

255 t/h

320 t/h

Product grain size

3,300 cm/g

4,200 cm/g

3,200 cm/g

Product moisture

1.06% H2O

0.3% H2O

Tab. 6: Production data, LOESCHE roller grinding mill

For details, please see "Delivery contract".


4.1.2

Electrical data
Designation

Unit

Value

Operating voltage

V 5%

230/400

No. of phases

Ph / PE

Neutral conductor

Current-carrying N (in the plant)

Protective conductor

Separate PE (yellow/green)

Frequency

Hz + 2%

50

Protection class

min. IP 55

Installation specifications

in accordance with BS

Insulation class

F to B

Lighting

VAC

230

Control voltage

VAC

230

Control voltage

VDC

24

Analogue output signals

mA

4-20

kVA

approx. 110

Power supply
Installed power
Tab. 7: Electrical data

42

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Technical Data

DANGER
Risk of electrocution!
In the case of machines with a matching transformer, it is absolutely essential if
altering the network configuration or the earthing/grounding principle to consult
the machine manufacturer.
Incorrect installation may result in electronic components being destroyed
(caused by overcurrent and overvoltage).
The specified voltages must be observed without fail.

4.1.3

Water injection
Water injection
Delivery rate

7.5 m/h

Pressure

6 bar

Tab. 8: Water injection

4.1.4

Sealing air supply


Only sealing air which is free from foreign substances (e.g. dust, oil, steam,
gases and similar ) may be used.
Sealing air
Volume

2,060 m/h

Pressure drop

26 bar

Tab. 9: Sealing air

4.1.5

Ambient data
Ambient data (foundry atmosphere)
Lower limit temperature

+10 C

Upper limit temperature

+40 C

Switching cabinet/Control desk

max. 40 C

Humidity

max. 80%

Noise level (ear defenders)

LPA < 75 dB (A)

Tab. 10: Ambient data

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

43

LOESCHE Mill with Classifier


Technical Data

4.1.6

Coating and choice of colours


Note
Coating is carried out on the basis of the LOESCHE QS - corrosion-protection
plan no. 4.Q09961-2609/01.
The data sheets for the assemblies concerned are included in the technical
documentation

4.2

Technical Data, LOESCHE mill


Characteristic data, LOESCHE mill
Machine type

LM 63.3+3 CS

SAP no. mill

10242593

Machine drawing

043691-00-0

Dimension sheet

M927230-00-1

Machine weight (per mill)

approx.773.410 kg

Motor power

7,300 kW

Table speed

max. 21.30 min-1

Tab. 11: Characteristic data, LOESCHE mill

Mill type-designation
LM

63

.3

+3

CS
Clinker / Slag
Number of support rollers
Number of grinding rollers
Table nominal diameter [dm]
LOESCHE Mill

44

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Technical Data

4.3

Technical Data, classifier


Characteristic data, classifier
Machine type

LSKS 107 CS r

SAP no. classifier

10242594

Machine drawing

101334-00-3

Dimension sheet

M956607-00-2

Machine weight per classifier

approx. 134,875 kg

Motor power

500 kW

Nominal reduction rate

i = 16.0

Rotor speed

37-92 min-1

Tab. 12: Characteristic data, classifier

Classifier type-designation
LSKS

107

r
right-hand rotation
Slag
Clinker
Classifier nominal diameter [dm]
LOESCHE bar cage classifier

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

45

LOESCHE Mill with Classifier


Technical Data

4.4
4.4.1

Technical Data, hydraulic system


Hydraulic cabinet HSLM
Characteristic data, hydraulic cabinet HSLM
Machine type

HSLM 2200/120/2

SAP number

10242504

Machine drawing

see manufacturer's documentation

Dimension sheet

M932581-00-3

Machine weight

approx. 1,500 kg

LOESCHE hydraulic scheme

917850-00-0

Tab. 13: Characteristic data, hydraulic cabinet HSLM

Hydraulic cabinet-designation
HSLM

2200

/120

/2
Number of pumps
Delivery rate [l/m]
Tank volume [l]
Hydraulic cabinet LOESCHE mill

46

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Technical Data

4.4.2

Hydraulic cabinet HSSW


Characteristic data, hydraulic cabinet HSSW
Machine type

HSSW 200/3-3

SAP no.

10242581

Machine drawing

see manufacturer's documentation

Dimension sheet

M932596-00-3

Machine weight

approx. 530 kg

LOESCHE hydraulic scheme

917830-00-1

Tab. 14: Characteristic data, hydraulic cabinet HSSW

Hydraulic cabinet-designation
HSSW

200

/3

-3
Number of pumps
Delivery rate [l/m]
Tank volume [l]
Hydraulic cabinet support roller

4.4.3

Hydraulic cabinet HSMS


Characteristic data, hydraulic cabinet HSMS
Machine type

HSMS 1350/10-6/3

SAP number

10242543

Machine drawing

see manufacturer's documentation

Dimension sheet

M932589-00-3

Machine weight

approx 1,085 kg

LOESCHE lubrication scheme

917860-00-2

Tab. 15: Characteristic data, hydraulic cabinet HSMS

Hydraulic cabinet-designation
HSMS

1350

/10

-6

/3
Number of pumps
Delivery rate [l/m]
Intake capacity [l/m]
Tank volume [l]
Hydraulic cabinet grinding-roller
lubrication

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

47

LOESCHE Mill with Classifier


Technical Data

4.5

Technical Data, swinging device


Characteristic data, swinging device
SAP number

10255933

Machine drawing

021818-00-3

Machine weight

approx. 7,925 kg

Tab. 16: Characteristic data, swinging device

The swinging device consists of


Machine "Hydraulic cabinet HSAV"
Assembly "Swinging device cpl."
4.5.1

Hydraulic cabinet, HSAV


Characteristic data, hydraulic cabinet HSAV
Machine type

HSAV 125/50

SAP number

10257248

Machine drawing

see manufacturer's documentation

Machine weight

approx. 295 kg

LOESCHE hydraulic scheme

932634-00-2

Tab. 17: Characteristic data, hydraulic cabinet HSAV

Hydraulic cabinet-designation
HSAV

125

/50
Delivery rate [l/m]
Tank volume [l]
Hydraulic cabinet swinging-out
device

48

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Technical Data

4.5.2

Swinging device cpl.


Characteristic data, swinging device cpl.
SAP number

10257581

Machine drawing

053716-00-0

Machine weight

approx. 7,630 kg

Hydraulic-cylinder type

380/170-3200

Hydraulic-cylinder drawing

see manufacturer's documentation

Tab. 18: Characteristic data, swinging device cpl.

Hydraulic cylinder-designation
380

/170

-3200
Cylinder stroke [mm]
Cylinder-rod diameter [mm]
Cylinder-piston diameter [mm]

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

49

LOESCHE Mill with Classifier


Description of the machine

5
5.1

Description of the machine


Overview of the roller grinding mill

2
3

000500

Fig. 3: LOESCHE roller grinding mill overview


Key
1 Classifier
2 LOESCHE mill

50

3 LM drive
4 Hydraulic system

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.1.1

Functional description

13
11

12

5
10

000876

Fig. 4: Flow of grinding material through mill, pictorial representation


Key
1 Grinding material inlet via air lock
2 Classification of material in classifier
3 Material is carried by hot gas to classifer
4 Material rejected by classifier
5 Grinding material drops through chute onto centre of table
6 LM drive drives table
7 Reject material

8
9
10
11
12
13

Hot gas inlet


Scrapers push reject material into reject funnel
Hot gas flows through louvre ring
Material is intercepted by hot gas flow
Rollers grind material
Finished material outlet

The LOESCHE roller grinding mill for grinding clinker/slag consists primarily of
the feed material gate;
the mill;
the classifier;
the mill gearbox with clutch and drive motor;
hydraulic control and lubrication cabinets for the rollers.
The individual machines are assembled into a "roller grinding mill" functional
unit or interconnected by pipes.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

51

LOESCHE Mill with Classifier


Description of the machine
The grinding material is dumped through an air gate into the feeding chute on
the classifier. Gravity forces it centrally onto the table, which is set into rotatory
motion by an electric motor and the mill gearbox. The centrifugal force acting on
the table delivers the grinding material to the rollers. The grinding material is
crushed between the respective master roller and the grinding route by
pressure and friction under the influence of the hydropneumatic roller spring
assembly system. A support roller for preparing the grinding bed is located
upstream of the master roller in each case. Crushed grinding material is
discarded via the table edge into the area of the louvre ring. There it is
interecepted by the air flow which is drawn in through the mill and the classifier
to carry and classify the grinding material.
Material already crushed to final fineness exits the LOESCHE cement mill
together with the air flow via an outlet fitting on the classifier. Oversized material
is rejected by the classifier and redirected via a directing cone to the table to be
crushed again. Grit which is neither intercepted by the rollers for crushing nor
routed by the air flow to the classifier falls through the louvre ring into the ring
duct surrounding the table and from there directed via a reject hopper to the
external reject handling system.

52

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.2

LOESCHE mill
1
14

2
3
4

13

5
6
7

12

9
10

000502

11

Fig. 5: LOESCHE Mill, assembly overview


Key
1 Mill body
2 S roller
3 M roller
4 S spring assembly, positioning device
5 S rocker arm
6 M arm seal
7 M rocker arm

8
9
10
11
12
13
14

M sprain assembly
Swinging device
Mill stand
Ring / connecting pipelines
LM drive
Table
Lining

The following describes the individual complete assemblies of the machine in


detail.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

53

LOESCHE Mill with Classifier


Description of the machine

5.2.1

Mill stand cpl.


X-X
8

2
3

X
6

001138

Fig. 6: Mill stand cpl.


Key
1 Railing
2 Bridge
3 Ring duct
4 Anchoring rods
5 Foundation frame

6
7
8
9

Gas duct with funnel


Pedestal cpl.
Support block
Gearbox baseplate

Structure
The "Mill stand cpl. is a combined cast/welded construction whose foundation
frame is mounted in a reinforced concrete foundation using foundation bolts.
Foundation frame
The foundation frame is a supporting structure made of wide-flanged girders.
The frames support the pedestals and the mill gearbox via the gearbox
baseplate.
The foundation frame is divided into one main part and an additional part for
transport purposes. The prefabricated structural elements are welded together
on site to form one unit. Suitable anchoring points must be provided for aligning
the parts.
Gearbox baseplate
The gearbox baseplate is a precise supporting surface for the mill gearbox and
connects this to the lower housing. It is aligned using jackscrews. A balancing
mass is provided between gearbox baseplate and foundation frame so that the
physical weight of the gearbox and table can be transferred into the foundation
across its whole area.
Gearbox foot flange, gearbox baseplate and foundation frames are fixed
together with gearbox mounting bolts. In addition, the gearbox foot flange is
directly supported by the foundation frame via driving wedges.

54

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

Pedestals
The pedestals for the mill stand are located symmetrically around the mill
centre. They are aligned, bolted and welded to the foundation frame.
The pedestals are a combination of cast and welded construction. A bearing
block containing the cam follower bearings with 2 bearing housings is welded
onto a box carrier made of sheet metal. Sheet metal plates welded into the
pedestal increase its torsional resistance.
A mounting housing for the M (Master) buffer to the M rocker arm is welded in
below the bearing block. It transfers the forces acting on the buffer to the steel
construction of the M pedestal.
The pedestal incorporates heavy welded plates with bores to which the
cylinders of the M spring assembly are linked.
The mounting for the swinging-out device for the roller/rocker arm unit is located
on the outside of the pedestal.
The pedestal has doors which seal off the assembly opening for the hydraulic
cylinders of the M spring assembly.
Bridges
The bridges are box girder structures. They are inserted between the pedestals
at bearing block height, bolted to them and welded to form a torsionally-stiff ring
structure.
The bridges contain a nonslip stud or checkered plate floor and form the mill
platform together with the railings.
Railing
DANGER
Risk of falling!
Platform components must be removed from the pedestals before swinging out
the rollers.
Always use safety belts when dismantling the platforms and carry out the
following maintenance work.
The railings are welded to the bridges to form the mill platform on site. Platform
components on the pedestals can be dismantled to allow the rollers to be
swung out.
Access to the platform is possible via the building or a separate access.
Ring duct
The ring duct is a gas-tight sheet steel housing which is supported on the
pedestals and bridges via a flanged connection.
The floor of the ring duct is double-walled to provide heat insulation.
As an option, the ring duct can be wholly or partially jacketed with a wearresistant lining.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

55

LOESCHE Mill with Classifier


Description of the machine

Gas duct
The gas ducts are welded to form a gas-tight sheet steel housing together with
the ring duct. The floor of the gas duct is made to form a slide which allows
foreign bodies to fall out of the mill stand. As an option, the gas duct can be
wholly or partially jacketed with a wear-resistant lining.
Reject flap
The reject hopper in the gas duct leads to a chute which is closed off by a flap.
The flap is hinged so that it closes itself due to self-weight and mill vacuum
pressure.

Function
The mill stand housing has two functions:
The mill base supports the milling tools and power transmission elements
via the pedestals. In addition to this, it guides the hot gases to the louvre
ring, which is located in the upper section of the ring duct. The hot gases
flow to the gas duct via the ring duct into the mill. In the ring duct, the hot
gas distributes itself around the table neck and flows evenly through the
louvre ring into the grinding chamber.
Foreign bodies and grinding material parts which fall through the louvre ring
into the ring duct are pushed by scrapers on the table into the floor opening
of a gas duct and then fall out of the reject opening.

56

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.2.2

Mill body cpl.


X
4

X
1

001139

Fig. 7: Mill body cpl.


Key
1 Cover (rocker arm-roller unit (S))
2 Cover (rocker arm-roller unit (M))
3 Mill body
4 Door

Structure
The mill body is a welded structure. The cylindrical housing is welded to the mill
stand.
The housing is made in 2 parts for transportation if necessary. The housing
halves then have prepared areas for welds at the sweeping point.
The two halves, which are kept dimensionally stable by welded-in struts, are
welded to each other during assembly.
The mill body contains large passage openings for swinging the M and S rollers
in and out. These openings are closed off by covers which are bolted to the
housing.
The passage openings for the rocker arms in the mill body are sealed by
sealing systems (see "Rocker arm seal" assemblies).
M roller covers
The M roller covers are a steel plate/welded construction and bolted to the mill
body. The M rocker arm collar reaches into the grinding chamber through an
opening in the cover recess. The rocker arm passage is sealed with the "Lever
sealing (M) cpl.".
S roller covers
The S roller covers seal the openings for the S rocker arm passages. In the
upper area the covers are supported against the mill body.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

57

LOESCHE Mill with Classifier


Description of the machine
Articulated lugs for accommodating hydraulic cylinders ("Spring assembly (S)
cpl.") are located here.
Lugs with integrated joints are located at the lower end of the S roller covers.
These comprise hollow journals which are guided in bearing blocks.
The bearing blocks are welded to the bridges during assembly at the
construction site. Equalising rings can be used to align the bearing points
exactly and to provide distortion-free welding.
Mill door
Two doors with quick-release locks are provided to inspect the interior of the
mill.

Function
The mill body has the following functions:
forming a grinding chamber which encloses the dust/gas mixture between
table and classifier and guides it;
closing off the rocker arm passages in the housing;
supporting the forces from the S roller systems via the integriated S covers;
supporting the classifier, which is welded to the LM body flange.

58

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.2.3

Lining cpl.
X

001140

Fig. 8: Lining cpl.


Key
1 Mill body
2 Lining plates
3 Lining, cover of rocker arm-roller unit (S)
4 Lining, cover of rocker arm-roller unit (M)
5 Lining, mill door

Structure and function


The interior of the mill body is protected against wear by blast jet and impacts
by highly wear-resistant steel plates. The plates are plug-welded to the mill
body. They are applied in a specific, prescribed arrangement, which is shown in
the "Lining cpl." drawing.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

59

LOESCHE Mill with Classifier


Description of the machine

5.2.4

Grinding bed sprinkler cpl.

1
2

3
4
5

001302

3
4
5

Fig. 9: Grinding bed sprinkler cpl.


Key
1 Grinding roller
2 Support roller
3 Compressed-air line
4 Water line

5
6
7
8

Grinding aid supply


Tire
Grinding plate
Sprinkler pipe

Structure and function


The grinding bed sprinkler is a piece of auxiliary equipment which can be used
to influence the properties of the grinding bed. It has been demonstrated in
many plants for clinker and blast furnace slag comminution that a water
sprinkler helps to stabilise the grinding bed significantly, thereby enabling the
mill to run more smoothly.
Water is introduced ahead of each grinding roller as closely as possible above
the grinding bed. The amount of water is so small that it has only a negligible
effect on the mill's heat balance and is of no process engineering significance.
As an option, a liquid grinding aid can be added to the water.

60

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

The effect of the grinding bed sprinkler is greater the close the water is
introduced ahead of the grinding rollers. On the other hand, there is a risk of the
hot grinding rollers being destroyed if they come into direct contact with cold
water.
NOTICE
Possible tire damage!
Position the grinding bed sprinkler as indicated in the drawing so as to
prevent the tires from being destroyed by temperature stress (see "Grinding
bed sprinkler cpl. drawing).
A hose connects the water line to the sprinkler pipe. The sprinkler pipe can be
released from the pipe holder for servicing and pulled out of the grinding
chamber.
Orifice plates are installed in the water lines ahead of the connecting hose. The
orifice plates increase the pressure in the water lines and ensure flawless pump
delivery and uniform distribution of the water volume to the sprinkler pipes.
The openings in the sprinkler pipes can be freed of deposit build-ups and
residual water blown out of the pipes by means of compressed air blasted
through additional lines.
If the mill is to be operated for an extended period without the grinding bed
sprinkler, the complete pipe holder can be removed and the opening in the mill
body sealed with the cover provided.

Delivery and flow rate


The orifice plate is designed in such a way that the upper flow rate limit value
(see assembly drawing) is achieved at max. pump capacity. It is possible to
alter the range of the effective flow rate (see supplier's documentation) by using
a different orifice plate size.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

61

LOESCHE Mill with Classifier


Description of the machine

5.2.5

Table cpl.

10

4
5
6

7
001148

Fig. 10: Table cpl.


Key
1 Clamping ring
2 Cover
3 Cover
4 Table casting
5 Ring duct

6
7
8
9
10

Scraper
Mill gearbox
Louvre ring
Armour ring
Dam ring

Structure
Table casting
The table casting is a heavy cast rotational body which is fixed via screw bolts
to the drive flange on the LM gearbox. The drive torque is transferred from the
gearbox via the bolted connections and 2 or 4 drive pins onto the base body.
The horizontal top side of the table casting is lined using the grinding plate and
forms the grinding route. Bores can be provided as an option in the grinding
plate and the table casting. Unwanted iron parts can be discharged through
these bores.
The table works as an anvil due to its large weight and its material properties.
Alternating loads are absorbed by the rollers. Dynamic loading is only partially
transferred to the gearbox axial bearings.
Grinding plate and clamping ring
The highly wear-resistant grinding plate, which is divided into segments, is the
grinding route lining. The segments are cylindrically ground around their outside
diameter so that they contact the table casting collar perfectly. The segments
are tensioned between inside and outside table collars using the clamping ring
clamping piece and bolts.
62

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

Dam ring
The dam ring is bolted from above onto the outside table casting collar. The
dam ring height determines the layer thickness (grinding bed) of the grinding
material on the table.
A high grinding bed leads to high energy consumption within the mill without
correspondingly increasing the milling effect. For this reason, the dam ring
height should be kept as low as possible. A lower dam ring retains less grinding
material on the table and the grinding material quantity flung off by centrifugal
force puts more load on the louvre ring.
The dam ring height is selected to match the application when the mill is
shipped. Despite this, it may be necessary to adjust the height during initial
start-up.
The dam ring comprises a solid basic ring with turned collar for centring on the
table collar. A pack of flat steel rings is screwed to the basic ring bolted to the
table. It is possible by removing or adding flat steel rings to adjust the overall
height of the dam ring over the grinding plate.
Note
In order to guarantee perfect milling, the rollers should be located as close as
possible to the dam ring wear ring!

Scatter ring (if fitted)


The scatter ring is a metal ring divided into segments. It distributes the milled
material thrown off the by the dam ring and guides it to the louvre ring. It covers
the wide air gap between the outside diameter of the table and the inner louvre
ring jacket ring.
In doing so, it forms a long, narrow gap which causes a high airflow resistance
together with the flat ring on the inside diameter of the louvre ring. For this
reason, the primary gas flows against the lower resistance caused by the louvre
ring into the LM upper housing.
If the mill does not have a separate scatter ring, the specially designed dam ring
acts as a scatter element.
Louvre ring
A segmented louvre ring is fixed stationary around the table. The exterior of the
louvre plates is protected against wear by a lining shell.
Each segment can be flexibly aligned. This enables the gap between the
segments to be minimised. This means that undesirable bypass flow of the gas
with increased wear is avoided. Bypass flow adjacent to this is prevented by the
temperature-resistant insulation material which is plugged between the louvre
ring segments and the ring duct.
The louvre ring directs the primary gas flowing out of the ring duct from above
and, due to the inclined location of the louvres, causes the necessary grinding
material particle circulation in the grinding chamber.
Armour ring
The segmented armour ring causes the extension of the external jacket ring
from the louvre ring. It also supports the primary gas guidance away from the
upper section wall. Individual armour ring segments are each bolted to a louvre
ring segment.
P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

63

LOESCHE Mill with Classifier


Description of the machine

Scraper
Foreign bodies and grinding material particles which have fallen through the
louvre ring or the grinding route openings against the primary gas flow are
collected on the floor of the ring duct. During operation, or when the mill starts,
the particles are caught by the scrapers and pushed to the reject hopper in the
gas entrance of the LM lower housing.

Function
The main function of the table is to support the grinding bed and to transfer the
forces caused by the rollers into the gearbox located below, and to transfer the
torque from the drives into the grinding zone.
Together with the ring duct, the table forms a ring-shaped chamber from which
the primary gas flows into the grinding chamber via the louvre ring.
The table is the second milling tool inside the mill in addition to the rollers.

64

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.2.6

LM drive

000519

Fig. 11: LM drive cpl., schematic sketch


Key
1 Mill gearbox
2 Coupling
3 Mill motor

4 Motor frame
5 Motor base frame
6 Coupling guard

Structure and function


The mill motor drives the table via the rubber-elastic coupling and the mill
gearbox. The table is bolted directly to the gearbox output flange.
The mill motor is supported by the motor frame, which is bolted and pinned to
the motor base frame set in concrete after the mill motor is aligned to the mill
gearbox.
The coupling guard ensures that rotating parts cannot be accidentally touched
during grinding operation.
If damaged, the mill gearbox can, after removal of the mill motor (with motor
frame) and raising of the table, be pulled out under the mill for removal on socalled tracks, which are welded on the motor base frame set in concrete.
Note
Refer to the separate gearbox documentation for information on installation,
operation and maintenance of the mill gearbox.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

65

LOESCHE Mill with Classifier


Description of the machine

5.2.7

Grinding parts cpl.


Setup and function
The "Grinding parts cpl." assembly consists of the grinding plate (functional part
of the "Table cpl." assembly) and the tires for the rollers (M) and (S).
Grinding plate
The grinding plate is the mill grinding route lining. It comprises a wear-resistant
casting. The grinding plate is divided into segments whose surface-ground
contact faces rest flat on the table. The segments are clamped between the
inner and outer table collars.
M tire
The rollers are crushing tools and are therefore subject to wear. A tire is used
as a wear part. The tire is a highly wear-resistant casting and is formed as a
single-component ring with tapered runway.
Refer to the drawing "Roller (M) cpl." for the type of tire mounting.
S tire
The S rollers are used to prepare the grinding bed. They operate with low
specific pressure and theoretically exert no sliding movement on the grinding
bed. The tire comprises a wear-resistant casting. The non-profiled surface has a
working width which is adapted to the M roller.
Refer to the drawing "Roller (S) cpl." for the type of roller mounting.
Wear
Grinding plate
The grinding plate is brittle on account of its structure. If a segment cracks as a
result of mechanical or thermal stresses, it does not have to be replaced
immediately. However, fragments of a segment must not creep upwards and
create holes in the grinding track.
Cracked grinding plate segments are usually wedged by the penetration of
grinding material so firmly against each other that they do not have to be
replaced before the normal wear time has elapsed.
It is not planned to replace the grinding plate at regular intervals. Wear usually
occurs in a limited area. Here the grinding plate can be relined by means of
build-up welding.
Lining is performed using mobile welding equipment (see separate
manufacturer's documentation) inside the mill. The grinding plate does not need
to be removed. Experience shows that rewelding has to be performed at the
latest when the wear recess has reached a maximum depth of 10 mm.
M tire
The M tire is subject to wear in a ring-shaped area. In this case, as with the
grinding plate, regular relining by means of build-up welding (see above) is
provided for.
S tire
Rolling wear of the S tires is minimal on account of their function as preparation
rollers.

66

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.2.8

Roller (M) cpl.

16

15

14

13

6
7
8

12
9

11

001147

10

Fig. 12: Roller (M) cpl.


Key
1 Hub
2 Guard
3 Axle
4 Cover disc with ring
5 Dipstick
6 Distance ring
7 Slip ring sealing
8 Sealing sleeve

9 Cylindrical roller bearing


10 Distance sleeves
11 Hub cover
12 Cover disc
13 Cover
14 Spherical roller bearing
15 Sleeve
16 Clamping ring

Number and location


Depending on the design, the mill is fitted with two or three M rollers, each of
which is clamped in a rocker arm. The M rollers are spaced equidistant from
each other and are held with a marginal axial inclination to the horizontal
grinding route in the zero setting.
Bearings
Each M roller runs in a cylindrical roller bearing located on the rocker arm side
and in a dual-row taper roller bearing on the hub cover side. Whereas the
cylindrical roller bearing takes up only radial forces, the taper roller bearing
transfers both radial and axial forces. Both bearings are supported against each
other using distance sleeves and clamped using the hub cover and sealing
sleeve bolts.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

67

LOESCHE Mill with Classifier


Description of the machine

Note
The achievable bearing service life is very much dependent on:
the way the mill is operated
the use of perfectly functioning lubricants
sufficient lubrication
observance of the stipulated operating temperature for the mill.

Lubrication
The roller bearings are generally lubricated by circulating oil, whereby pumps in
the HSMS hydraulic cabinet supply the oil. A radial bore in the hub ensures a
constant minimum M roller oil level (see "Hydraulic cabinet HSMS" instruction
manual).
Seals
Each M roller is fitted with different seals:

Sealing gas seals


The roller bearings are under atmospheric pressure. Since this is higher
than the pressure in the grinding chamber, no dust can penetrate the
bearings. (See "Sealing air piping cpl." instruction manual).

Mechanical seals
The roller bearing space is protected by mechanical seals against the dust
atmosphere in the mill:
An O-ring seals the hub cover against the hub. The rotating roller parts are
sealed against the fixed axle via a slip-ring system (see "Slip-ring seal cpl."
instruction manual).

Roller settings
The position of the M roller on the table (distance to dam ring) can be changed
using a ring. This ring is inserted between the conical sleeve on the rocker arm
and the corresponding axle shoulder.
Note
Only fit this ring for making roller settings if the roller is touching the dam ring
along its internal diameter (see drawing information).

68

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

Wear
NOTICE
Possible tire damage!
The clamping surfaces on the tires and hubs are manufactured with very tight
tolerances. The use of imprecisely manufactured tires leads to increased danger
of breakage and destruction of the cone seat!
The rollers are crushing tools and are therefore subject to wear. A tire is used
as a wear part. The tire is a highly wear-resistant casting and is formed as a
single-component ring with tapered runway.
It is pulled over the roller hub using a clamping ring with tee-head bolts, disc
springs and nuts. The disc springs accept push points which affect the bolts.
The hub is protected against wear by blast jet by a revolving bell housing in
wear-resistant material.
A removable protection plate is optionally connected to the bell housing. This
protects the rocker arm seal against wear by blast jet.
5.2.8.1

Roller rotation monitor cpl.

2
3

000536

Fig. 13: Roller rotation monitor cpl.


Key
1 Protected feed line
2 Proximity switch
3 Connecting screw (slip-ring seal - hub)

4 Roller

Rotation monitoring of the roller takes place using a proximity switch, and is
therefore contactless. The proximity switch is guided through the rocker arm
with the help of a tube, and is given its pulses by the screws which connect the
slip-ring seal with the rotating hub.
P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

69

LOESCHE Mill with Classifier


Description of the machine

5.2.8.2

Slip-ring sealing cpl.

000507

Fig. 14: Slip-ring sealing cpl.


Key
1 Sealing ring (rotating)
2 Roller axle
3 Sliding ring

4 O-ring
5 Thrust ring (fixed)

The slip-ring seal holds the lubricant in the mill roller bearing space.
For this purpose, the rotating mill parts are sealed via the slip-ring system
against the fixed axle.

70

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.2.9

Rocker arm (M) cpl.


1

X
3
10
4

11

12

13

14

000508

Fig. 15: Rocker arm cpl.


Key
1 Rocker arm
2 Clamping sleeves
3 Roller axle
4 Cylindrical roller bearing (locating bearing)
5 Ring
6 Pedestal
7 Pivot point of spring-assembly cylinder

8 Clamping sleeves
9 Fork
10 Central lever
11 Bearing block on pedestal
12 Cylindrical roller bearing (floating bearing)
13 Flange centring sleeve
14 Rocker-arm axle

Structure
The mill is fitted with M rocker arms which are each hinged on a bearing block
on the LM lower housing. Two or three M rocker arms are symmetrically
arranged in relation to the mill centre.
Each M rocker arm consists of a central lever, fork, axle and radial and axial
bearings in the LM lower housing bearing block.
The central lever is shrunk onto the axle. The upper part of the lever contains
the seat opening for the roller axle which is fixed using tapered sleeves at right
angles to the lever axis.
The fork grips the lever from both sides. This is also fixed to the axle using
tapered flange centring sleeves. Screwed and bolted connections transfer any
torque occurring (see "Rocker arm (M) cpl." drawing).
Each fork side wall is pulled against the central lever using bolts. Torque is
either transferred via the surface friction between fork and lever or via a taper
P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

71

LOESCHE Mill with Classifier


Description of the machine
pin connection on each fork side wall (see also "LM auxiliary equipment: Rocker
arm cpl.").
The bottom end of the fork is formed as a box and is completed by one or two
straps with transverse drillhole. This is where the cylinder(s) on the hydropneumatic spring assembly are hinged.
An armoured sealing cap to seal off the rocker arm opening in the mill body is
bolted onto the face of the rocker arm collar (see "Lever sealing (M) cpl."
assembly).
Bearings
The M rocker arm shaft is supported in two bearing housings in the pedestal
bearing block.
Spherical roller bearings, in which the rocker arm shaft is hinged, take up radial
forces. Changing axial thrust is taken up by fixed thrust washers.
Any impact force occurring on the bearing housing bolts during mill operation is
relieved via friction in disc springs.
Lubrication
All lubrication points are lubricated with grease. All lubrication bores are sealed
by grease nipples during transportation and arm installation. After mill assembly
all the lubrication bores are connected to a central grease lubrication system
(see "Lubrication line cpl." assembly).
A specification of the heavy-duty lubricating greases is contained in the
maintenance table.

Function
The M rocker arm transmits the forces caused by the double-acting hydraulic
cylinder onto the rollers and the grinding bed. The hydraulic cylinders are
hinged on the bottom end of the M rocker arm by joint pins.
Hydraulic cylinder and M rocker arm a located so that the bearing reaction
forces are always transmitted into the pedestals.
Separation of the central lever from the fork allows the roller (M) to be swung
out without having to dismantle the fork and spring assembly cylinder.
Sealing air is fed into the ring gap between roller axle and M rocker arm via a
drillhole with connecting unions on the top of the lever. This prevents dust
penetrating the roller bearings (see also "Sealing air system").
A geometrically adapted sealing box seals the M rocker arm against the mill
body (see also "Lever sealing cpl." assembly).

72

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.2.10 Lever sealing (M) cpl.


1
3

10

Y
8

Y
3
4

000509

5
6

Fig. 16: Lever sealing cpl.


Key
1 Sealing bar (secured to the mill body)
2 Mill body
3 Sealing cap
4 Sealing bar (secured to the mill body)
5 Seal

6
7
8
9
10

Sealing bar (secured to the rocker arm)


Sealing bar (secured to the mill body)
Seal
Rocker arm
Seal

Design
The "Lever sealing (M) cpl." assembly consists of moved parts mounted on the
rocker arm and static parts which are bolted to the mill body.
a) Moved parts
The components fixed to the rocker arm (M) are:
the sealing cap with side wall lining,
the armour ring,
the upper lining plate on the sealing cap and the lower sealing segment
which is bolted to the sealing cap,
the armour ring bolted to the sealing cap.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

73

LOESCHE Mill with Classifier


Description of the machine
b) Static parts
The static parts are bolted to the cover and the mill body:
an upper and lower sealing channel which match the moved sealing
segments with their curves,
2 right-hand and 2 left-hand "side walls" (angled strips),
various rubber and sheet strips which are bolted to the sealing
segments.

Function
The rubber and sheet strips can be readjusted using longitudinal holes up to the
moved parts (sealing caps). The same applies to the sealing segments and
angled strips.
Tight and long labyrinth gaps are formed between the moved and static parts
using the adjustable strips. They prevent dust penetrating the external sealing
strips. The fabric-reinforced rubber sealing strips can be cut out of used rubber
conveyor belts.
To keep leak air entry into the mill as low as possible, special corner seals have
been bolted to the sealing caps and upper housing cover to seal off the right
angled corners.

74

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.2.11 Rocker arm monitor (M) cpl.

8
7
6
5
4

1
3

X
6

8
2

000510

Fig. 17: Rocker arm monitor cpl.


Key
1 Rocker arm
2 Bearing block
3 Flange centring sleeve
4 Holder

5
6
7
8

Encoder
Displacement sensor
Guard plate
Holder

Structure and function


The rocker arm monitor cpl. continuously monitors the up and down movements
of the rocker arm. A reference mark sensor is attached to the moving rocker
arm.
This is moved over a transducer in a constant distance (dimension A, see
drawing information). The transducer is statically mounted to the bearing block
of the pedestal. The transducer and reference mark sensor are protected by a
common cover.
Note
For more information about the transducer and reference mark sensor, please
refer to the manufacturer documentation.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

75

LOESCHE Mill with Classifier


Description of the machine

Adjusting the rocker arm monitor cpl.


NOTICE
Possible risk to the machine!
Incorrect or faulty adjustments of the rocker arm monitor cpl. can lead to
damage of the machine!
The rocker arm monitor cpl. must be adjusted:
after the initial installation
after the pivoting procedure of the rollers and
after replacing the transducer, the reference mark sensor or their holders.

The checking of the dimension A (see drawing information) and the


determination of the measuring points for the roller positions "Roller too deep"
and "Roller raised" are part of the adjustment.
This means:
Roller too deep

The roller position falls below the position of


the minimally required grinding bed thickness.

Roller raised

The roller is in the highest position possible


(cylinder end stop)

Both positions are shown by signals in the central central control room.
Grinding bed thickness
The measuring range of the grinding bed thickness is limited by the measuring
points of both roller positions "Roller too deep" and "Roller raised".
The position of the reference mark sensor in relation to the transducer changes
with the changing of the pivoting angle of the rocker arm.
The position signal is converted into a value in the evaluation unit which directly
specifies the grinding bed thickness. The value is displayed in the central
central control room.

76

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.2.12 Roller (S) cpl.

2
4
1

5
3
6
7
8
9

16

10

15
14
11

13

001367

12

Fig. 18: Roller (S) cpl.


Key
1 Rocker arm (S)
2 Angle ring
3 Slip-ring seal
4 Wear ring
5 Sealing sleeve
6 Tire
7 Hub
8 Roller axle

9 Clamping ring
10 Hub cover
11 Cover disc
12 Spherical roller bearing
13 Guard
14 Cylindrical roller bearing
15 Flanged connection
16 Tube bundle

Structure
Depending on the design, the mill is equipped with two or three S-rollers. The
rollers are each permanently connected to an S-rocker arm. The S-rollers are
positioned between the M-rollers. In the zero setting the conical working surface
is parallel to the horizontal grinding route.
In order to achieve as clean a rolling effect as possible, the inclined roller axle
and the vertical table axle meet in the working plane.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

77

LOESCHE Mill with Classifier


Description of the machine

Bearings
Each S-roller runs in a cylindrical roller bearing located on the rocker arm side
and in a spherical roller bearing on the hub cover side.
Whereas the cylindrical roller bearing takes up only radial forces, the spherical
roller bearing transfers both radial and axial forces. The axial forces are
generated by the inclined arrangement of the S-roller in relation to the table.

Seals
Each S-roller is fitted with different seals.
Sealing gas seal
The non-contact sealing gas seal prevents the roller bearing assembly from
being contaminated by dust from the grinding chamber (see "Sealing air
system cpl." instruction manual).
The roller bearing assembly is under atmospheric pressure via a filter and
bores. Since this is higher than the pressure in the grinding chamber, no
dust can penetrate the bearings.

Mechanical seals
The roller bearing space is protected by mechanical seals against the dust
atmosphere in the mill. An O-ring seals the hub cover against the hub. The
sealing sleeve is bolted to the hub using sealing compound. The rotating
components of the roller are sealed off against the fixed axle via a slip-ring
system.

Roller settings
The S-roller is not a grinding roller, but rather a preparation roller. Its function is
to compress, i.e. prepare, the ventilated and inhomogeneous grinding bed of
feed material and re-circulating material for the subsequent grinding roller (Mroller).
The working level of the S-roller is therefore significantly higher than that of the
M-roller. There are two possible ways of selecting the position of the S-roller
above the table surface:
by adjusting the buffer spindle of the S-buffer, whereby the S-rocker arm is
mechanically adjusted to a desired height with the S-roller;
with the aid of the S-hydraulics by positioning with a hydraulic cylinder.

Lubrication
The roller bearings are lubricated in the oil bath. Refer to the lubricant table for
oil quantity and oil quality.

78

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

Wear
The S-rollers are used to prepare the grinding bed. They operate with low
specific pressure and theoretically exert no sliding movement on the grinding
bed. Rolling wear is therefore minimal.

Tire
The S-tire is part of the "Grinding parts cpl." assembly and is described in
the instruction manual under the same name.

S-tire fastening
The S-tire has two cylindrical seats of different sizes on the S-hub. The tire
is clamped with the aid of a bolted clamping ring against a flat hub collar
surface.

Bell housing / guard


Depending on the S-roller design, the hub is protected against wear by blast
jet by a rotating bell housing or guard made of wear-resistant material.

5.2.12.1 Roller rotation monitor (S) cpl.

000535

Fig. 19: Roller rotation monitor (S) cpl., schematic sketch


Key
1 Rocker arm (S)
2 Roller (S)
3 Hub cover
4 Shaft

5 Cam disc
6 Proximity switch
7 Hood

The rotating S roller drives a shaft. The shaft is guided longitudinally by the
roller axle and the rocker arm. A cam disc is attached to the shaft outside the
mil. The pulses of the rotating cam disc are recorded by a proximity switch.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

79

LOESCHE Mill with Classifier


Description of the machine

5.2.13 Rocker arm (S) cpl.


X

13

11
1

12

11

14

4
5

15

10
9

16

8
7

001368

Fig. 20: Rocker arm (S) cpl.


Key
1 Mill body
2 Rotation/swing axle
3 Guard
4 Flanged joint
5 Oil dipstick tip
6 Roller (S)
7 Tube bundle
8 Rocker arm (S)

9 Plate
10 Jib
11 Oil dipstick
12 Stop spindle
13 Positioning device
14 Bush
15 Axle
16 Sealing air connection

Structure
The S rocker arm is a welded construction. It is mounted in the upper housing
cover. The cross-struts are provided with sleeve bearing bushes for this
purpose and form the swivel joints with the axle bolts secured in the upper
housing.
On the side projecting into the mill the S roller is secured by means of a flanged
fitting.
A tube bundle flanged on the S roller, which is guided outwards by the rocker
arm, provides a connection with the roller interior for oil filling and checking and
rotation monitoring.
The reverse side of the S rocker arm has a jib, which serves as the articulated
point of the S assembly hydraulic cylinder and to accommodate the stop
spindle.

80

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

Function
The function of the S rocker arm is to:
secure the S roller so that it swivels,
support the S roller resiliently on the S buffer and to maintain it at a defined
minimum distance above the grinding route,
direct into the S roller additional hydraulic forces from the effect of the
hydraulic cylinder acting at the top on the S rocker arm,
seal the S rocker arm/roller unit via a flanged sealing shield on the housing
passage (see also "Arm seal (S) cpl." assembly).
Sealing air is supplied through the hollow journals into the annular gap between
the roller axle and S rocker arm, which serves to seal the rocker arm/roller
internally against penetration by dust into the roller bearings.
For this purpose the transport protection cover must be replaced at the planned
connection point by the sealing air connection piece (see "Sealing air system"
instruction manual).
5.2.14 Lever sealing (S) cpl.
1

2
3

000512

Fig. 21: Lever sealing (S) cpl.


Key
1 Rocker arm (S)
2 Clamping ring
3 Seal
4 Clamping frame
5 S-cover at mill body

Design
The "Lever sealing (S) cpl." assembly is composed of moving parts fitted to the
S-rocker arm and of stationary parts bolted to the mill body.
a) Moving Parts
A rounded ring is welded to the rocker arm (S) The bellows is clamped between
this ring and another one with the aid of bolts. These parts are sealed with
sealing compound (e. g. silicon) against the rocker arm (S).

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

81

LOESCHE Mill with Classifier


Description of the machine
b) Stationary Parts
A frame made of flat steel bars attaches the bellows to the mill body with bolts.

Function
The flexible bellows seales the opening in the mill body for the moving rocker
arm (S).
5.2.15 Rocker arm monitor (S)
X
1

2
Y

001141

Fig. 22: Rocker arm monitor (S) cpl.


Key
1 Rocker arm (S)
2 Cover
3 Cover of the rocker arm-roller unit (S)

4 Holder
5 Transducer
6 Displacement sensor

Structure and function


The rocker arm monitor cpl. continuously monitors the up and down movements
of the S rocker arm.
A position sensor is mounted on the moving S rocker arm. This sensor is guided
at a constant distance (dimension A, see drawing information) via a
displacement sensor.
The displacement sensor is statically secured to the cover of the mill body. The
displacement and position sensors are protected by a common body.
Note
Please refer to the manufacturer's documentation for further information on the
displacement and position sensors.

82

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

Adjusting the rocker arm monitor (S) cpl.


NOTICE
Possible risk to the machine!
Incorrect or poor adjustment of the rocker arm monitor (S) cpl. may result in
damage to the machine!
The rocker arm monitor (S) cpl. must be adjusted:
after initial assembly
after the rollers have been swung in, and
after replacing the displacement sensor, the position sensor or their holders.
Adjustment involves checking dimension A (see drawing information) and
determining the measuring points for the roller positions "roller too low and
"roller raised.
Position meanings:
Signal

Meaning

Roller too low

The roller position drops below the position of


the minimum required grinding bed thickness.

Roller raised

The roller is in the highest possible position


(cylinder end stop).

Both positions are indicated by signals in the central control room.


Grinding bed thickness
The measuring range of the grinding bed thickness is limited by the measuring
points of the two roller positions "roller too low" and "roller raised.
The position of the position sensor in relation to the displacement sensor
changes as the swivel angle of the S rocker arm changes. The position signal is
converted in the evaluator unit into a value which specifies the grinding bed
thickness directly. The value is displayed in the central control room.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

83

LOESCHE Mill with Classifier


Description of the machine

5.3

Swinging device

5.3.1

Swinging the grinding roller

B
1
6

000540

Fig. 23: Swinging the grinding roller


Key
1 Grinding roller, swung out
2 Hydraulic cylinder
3 Joint seating

84

4 Hydraulic cabinet, HSAV


5 Pedestal
6 Grinding roller, swung in

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.3.2

Swinging the support roller

3
4

000541

Fig. 24: Swinging the roller (S)


Key
1 Roller (S), swung out
2 S cover on mill body
3 Positioning device blocked with auxiliary equipment
4 Hydraulic cylinder

5 Hydraulic cabinet HSAV


6 Joint seating
7 Roller (S), swung in

The grinding parts of the LOESCHE mill can be quickly changed with the
hydraulic swinging device.
The roller is swung out of the mill body and the rocker arm supported with a
hydraulic cylinder.
Tire and grinding plate are freely accessible after swinging out.
For swinging the lower rod end of the hydraulic cylinder is connected to joint
seating. The piston rod incorporates a fork element with pin, which is engaged
in a strap on the rocker arm.
The hydraulic cylinder is equipped with non-return valves with restriction at both
ends. Quick-release coupling facilitate the connection of maximum-pressure
hoses. The couplings can be opened under pressure without the loss of oil.
The supply system, the HSAV, consists of a frame with an oil tank and pump
mounted on top, a manually actuated control valve, an electrical control box,
two maximum-pressure hoses for connecting with the swinging cylinder and an
electrical cable for connecting the pump motor to the mains power supply.
The valve control lever is used to preselect the working direction of the
hydraulic cylinder and to switch on the pump. The pump runs for as long as the
slide is actuated. The cylinder must be filled with oil when the piston is
retracted.
The tank must not be filled completely as oil displaced by the piston flows back
and requires a volume reserve.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

85

LOESCHE Mill with Classifier


Description of the machine
5.3.3

Preparatory work for swinging out


For grinding roller
Release the taper pin and flange sleeve connections between the arm and
fork of the "Rocker arm cpl." assembly (see also "LM auxiliaries cpl."
assembly).
Screw off and remove the cover from the mill body.
If fitted, remove the 2-part protection plates for the roller cpl.
For roller (S)
Block the hydraulic cylinder of the positioning device with auxiliary
equipment.
Detach the hydraulic hoses from the hydraulic cylinder.
Detach the S cover from the mill body.
Further for grinding roller and roller (S)
Remove any platforms in the rocker arm swinging area.
In the case of oil circulating lubrication, have a collecting container ready for
oil from the roller.
Close the vent bore on the roller.
Suspend the rod end bearing of the hydraulic cylinder from the joint seating
of the pedestal (grinding roller) or from the foundation (roller (S)) and
secure.
Move the HSAV to the hydraulic cylinder.
Attach the two hydraulic hoses of the HSAV with their quick-release
couplings to the corresponding cylinder connections.
Connect the HSAV via the mains cable to the mains supply.
Actuate the control lever and extend the piston rod.
The control lever switches the pump motor on and off.
During commissioning or after changing a seal, move the piston back and
forth to vent the cylinder.
Extend the piston rod up to the rod end bearing of the rocker arm.
Connect the fork end of the piston rod with the pin to the rocker arm rod end
bearing.
Secure the pin with a split pin.

5.3.4

Swinging-out process

Place the hand lever of the control valve in the "Swing out" position until the
pump motor runs.
The pump motor is switched off when the control lever is in the centre position.
Hold the valve lever in the working position until the axle of the swung-out
roller is vertical.

86

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

Note
When it is released, the valve lever returns automatically to the "0" position.
To avoid uncontrolled movements, the oil flow is braked by throttle check valves
in the hydraulic cylinder.
These are set by the hydraulic cylinder supplier to their minimum values. Make
sure when resetting that the oil flow does not become too high so that the fuses
in the hydraulic cylinder do not operate unintentionally.
The rocker arm moves downwards to its end position, which is limited by a
mechanical stop.

Move the valve lever to the "0" position; the pump motor switches off.

The hydraulic system is protected by an overflow valve which is an integral part


of the pump unit.
The HSAV has a motor circuit-breaker with bimetal tripping device.
5.3.5

Swinging-in process
The swinging-in process happens in reverses sequence to the swinging-out
process. Place the control valve in the "Swing in" position here.
The swinging-in process is concluded when the rocker arm has assumed its
normal working position.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

87

LOESCHE Mill with Classifier


Description of the machine

5.3.6

Lubrication line cpl.


This assembly comprises the oil lines of the recirculating oil lubrication system
for the rollers (M) and the grease lines for the rocker arms (M).
Design and function
Oil lines
The oil lines are installed in accordance with the "Lubrication line cpl." assembly
drawing between the connecting line of the HSMS hydraulic cabinet and
grinding rollers. Refer to the assembly drawing or lubrication scheme for
identification of the pipe connections.
Connection is established to the roller axle via hoses, permitting free
adjustability both during mill operation while the rocker arm (M) is moving and
during the swinging-out operation.
Note
Subsequent reductions in the pipe cross-sections may result - particularly in the
return line to the tank - in impaired lubrication system operation.
Grease lines
The grease lines are installed in accordance with the "Lubrication line cpl."
assembly drawing between one or more motor-driven lubrication pumps (see
parts list for number) and the respective lubrication points. These include the
radial and thrust bearings of the rocker arms (M).
Piston distributors with force control ensure that grease is distributed precisely
to the lubrication points. Fault-free operation of the piston distributors is only
guaranteed when all the outlets to the consumers are connected.

88

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.3.7

Seal-air piping
8

3
4

000515

Fig. 25: Sealing air system


Key
1 Grinding chamber
2 Rotating parts of roller (M)
3 Grinding chamber
4 Rotating parts of roller (S)

5
6
7
8

Fixed parts of roller (S)


Fixed parts of roller (M)
Sealing air
Sealing air pipe

Structure and function


In order to prevent the roller bearings and the slip-ring seal of the M and S
rollers being damaged by dust from the grinding chamber, the very tight annular
gap between the wear ring of the rollers and the wear ring of the M or S rocker
arm is pressuresed with sealing air.
This air is supplied through the sealing air pipe which surrounds the LM upper
housing. The sealing air pipe enters through an upper bore at the M rocker arm.
In the case of the S rocker arm, the sealing air is routed from the side into the
rocker arm.
In the case of both rocker arm types, the sealing air then flows through the
rocker arm past the slip-ring seal and through the sealing air gap into the
grinding chamber.
The sealing air gap is structurally determined by the difference in the diameters
of the two wear rings. It cannot be adjusted.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

89

LOESCHE Mill with Classifier


Description of the machine

5.3.8

Sealing air monitoring cpl.

000854

Fig. 26: Sealing air monitoring cpl.


Key
1 Sealing air pipe
2 Sensor, pressure transducer
3 Ball valve

4 Mill body
5 Classifier

Structure and function


CAUTION
Overpressure!
Escaping compressed air may cause injuries.
Replace the pressure transducer only with the valve closed!
Sealing air is used in the roller and rocker arm assemblies and in the drive of
certain classifiers (see the corresponding chapters) to prevent the ingress of
dust into the bearings.
The sealing air monitor causes an alarm if the sealing air supply is disturbed.
The sealing air stream is monitored by an electronic pressure transducer.
If the pressure in the sealing air system is too high or too low, an alarm will be
set off.
A ball valve situated between the air stream and the sensor allows the sensor to
be exchanged whilst the mill is in operation. Under normal circumstances the
valve must be kept in the open position.

90

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.3.9

Vibration monitoring cpl.

2
3

000517

Fig. 27: Vibration monitoring cpl., schematic sketch


Key
1 Mill body
2 Electrical cable
3 Holder
4 Vibration pickup
Dimension X, see drawing "Vibration monitoring cpl."

Vibration evaluation of the mill is performed in accordance with VDI Guideline


2056. The LOESCHE roller grinding mill must be classified into Group "D".
Recorded in this group are machines which are rigidly mounted and bring about
non-compensatable mass actions. For Group "D" there are no evaluation scales
on account of the non-compensatable mass actions. The mill is therefore
classified as an alternative in Group "G", where rigidly mounted machines (on
heavy foundations) are recorded with only revolving masses.

Structure and function


In order to monitor mill operation a vibration pickup is mounted above the mill
door on the body in accordance with the drawing "Vibration monitoring cpl.".
The vibration pickup measures the movements of the body in the horizontal
direction (mm/s). What is indicated is not foundation vibrations, which are to be
evaluated directly in accordance with VDI Guideline 2056. Instead, a
significantly increased vibration velocity over the foundation vibration is
signalled at the height of the mill door.
The measured values converted from mechanical into electrical signals are
directed via a cable to a contact instrument in the measuring cabinet abd then
indicated by the instrument. The grinding plant's normal shutdown procedure is
initiated as soon as the indication exceeds a preselected value.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

91

LOESCHE Mill with Classifier


Description of the machine

001302

5.3.10 Name plate

Fig. 28: Name plate

The name plate is attached to the outside of the LOESCHE mill. It is located on
the mill stand.
Information on the name plate:
Type
Serial number
Year of construction
Order number
Manufacturer

92

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.4

Hydraulic system of the grinding roller


The grinding tools in the LOESCHE roller grinding mill are the table and the
grinding rollers. The table is fitted with a horizontal grinding route and is driven
at constant speed.
While in raw meal dry grinding plants the feed material is ground with all the
rollers, a distinction is made in clinker/slag grinding plates between the master
roller (M roller, also roller (M)) and the support roller (S roller, also roller (S)).
The two roller types differ in design and size, based on their respective function.
They are located in pairs opposite the table.
The M rollers crush the grinding material through their own weight and
additionally applied hydraulic pressing force; the grinding material is merely
prepared by the S rollers by way of low contact pressure on the grinding bed.
The pressing force of the M rollers on the grinding material is generated by the
hydro-pneumatic spring assembly system.
The grinding clearance of the S rollers above the grinding route is adjusted with
the hydraulic positioning device.
A stop buffer on the rocker arm prevents the tires from coming into direct
contact with the grinding plates.

Structure and function


Spring assembly cpl.
Every M roller in the mill is fitted with a spring assembly. These consist,
depending on the mill type, of one or two hydraulic cylinders which are
connected to the M rollers via the rocker arm. The hydraulic cylinders are each
fixed as a hinge by the rod end bearing to the LM lower housing and fixed to the
rocker arms with a rod head.
Hydraulic cabinet HSLM
The HLSM hydraulic cabinet provides the supply system for the hydropneumatic
mill roller spring assembly.
Please see the separate manufacturer's documentation for detailed information
about the HLSM setup.
Ring/connecting pipeline cpl.
The oil supply system (hydraulic cabinet) and the hydropneumatic spring
assembly for the mill are connected to each other via a pipe system. The crosssectional areas stated in the drawing must be observed for each pipe. Welded
pipes are descaled and conserved at manufacture by pickling, and must be
protected by hermetic sealing of the flange against corrosion and the
penetration of dirt until final assembly.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

93

LOESCHE Mill with Classifier


Description of the machine

NOTICE
Possible risk to the machine!
If the piping is laid in a foundation duct, its top surface must be painted with oilresistant paint to prevent damage to the concrete. A drain fitted to the duct
ensures that leaked oil and water can flow away during cleaning work.

Hydraulic bladder accumulator


A bladder accumulator consists of a liquid and a gas section with a bladder as a
gas-proof separating element. The liquid components around the bladder are
connected to the hydraulic circuits so that if the pressure increases the bladder
accumulator is filled, which compresses the gas. If the pressure reduces, the
compressed gas expands again and displaces the accumulated pressurised
liquid into the circuit.
Hydraulic piston accumulator
A piston accumulator consists of a liquid and a gas section with a piston as a
gas-proof separating element. The gas side is pre-filled with nitrogen. The liquid
components around the bladder are connected to the hydraulic circuits so that if
the pressure increases the piston accumulator takes in fluid, which compresses
the gas. If the pressure reduces, the compressed gas expands again and
displaces the accumulated pressurised liquid into the circuit.
Hydraulic cylinder
The hydraulic cylinder construction can be seen from the separate
manufacturer's documentation.
Stop buffer cpl.
WARNING
Heavy machine parts. Possible loss of body parts!
Remaining in the vicinity of moving parts belonging to systems transmitting
grinding power is not permitted for safety reasons.
Use shims of sufficient thickness between roller and table in order to prevent
unintentional lowering of the rollers.
Use suitable auxiliary equipment, such as e.g. rods, to place the metal
plates under the rollers.
The stop buffer consists of the welded housing, the adjustable spindle and the
pretensioned elastomer for absorbing impacts.
The housing is bolted to the pedestal in the LM lower housing.
The spindle can be readjusted in accordance with the wear on the grinding
parts. Adjustment is performed by inserting a 10 mm plate under the rollers on
the empty table.
The spindle is secured from the outside against subsequent rotation during
operation.
If wear arises on the grinding parts, it is necessary to check the spindle
adjustment in good time as otherwise the stop buffer will be subjected to
unnecessarily frequent load from striking by the fork.
94

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.4.1

Hydraulic spring assembly - mode of operation

B
1

11

10
3

A
5

12

000537

Fig. 29: Interplay, working pressure/counterpressure system

The hydraulic cylinders (4) are connected to the working pressure system (10)
on the piston rod side (12) and the counterpressure system (9) on the piston
side (7).
A: During mill operation, the rollers are raised by the grinding material lying on
the table. In doing so, the rocker arms are deflected. The pistons (6) in the
hydraulic cylinders move upwards and displace oil (3) from the working
pressure system into the hydraulic bladder accumulator (11). The nitrogenfilled accumulator bladder (1) in the bladder accumulators is compressed by
the inflowing oil.
At the same time the counterpressure system works on the piston side of
the hydraulic cylinder. In the case described above, oil is pressed by
nitrogen pressure (5) out of the hydraulic piston accumulator (8) back into
the piston side of the hydraulic cylinder.
B: If the grinding rollers roll into a "grinding bed valley" the process is reversed.
Oil is pressed out of the hydraulic bladder accumulator in the working
pressure system into the piston rod side of the hydraulic cylinder. At the
same time, oil is displaced out of the piston side of the hydraulic cylinder
into the hydraulic piston accumulator.
The rollers continually make vertical movements in a certain working range (2)
due to the unevenness of the grinding bed. The processes described above
alternate continuously.
To run the mill in and shut it down it is possible to raise the rollers hydraulically
from the grinding bed. Due to varying resistance in the hydraulic system, the
rollers do not raise simultaneously but one after the other. Their movement is
limited mechanically at the top. Once all rollers have reached their top end
position this condition is signalled electrically.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

95

LOESCHE Mill with Classifier


Description of the machine
Once the rollers are raised it is possible to start a mill in in its filled condition.
The mill motor must apply around 40% of its nominal torque when starting a
filled mill. The residual milled material on the table is ground extremely quickly
when the rollers are lowered. Lowering the rollers takes place with a delay after
switching on the material feed. For this reason, the grinding bed sets itself up
slowly. The required motor torque slowly increases to 100%. Full load operation
is achieved at around 30 seconds in this process.
A stop buffer prevents metallic contact between the roller tires on the grinding
roller and the grinding plates if the milled goods feed to the mill is interrupted
and the rollers are not hydraulically raised in time. The permissible lowest point
of the rollers is electrically monitored.
5.4.2

Spring characteristic
The hydropneumatic spring system together with the HSLM hydraulic cabinet
allows the roller force to be adapted to the grinding material being processed,
and to keep the grinding bed thickness constant within tight limits.
It consists of two separate systems, the so-called working system, which
provides the piston rod side with pressure and the counterpressure system,
which provides the piston side with pressure. Regulation normally takes place
depending on the current milling task.
Diagram: Roller spring stiffness
Please see the documentation parts list for the hydraulic cabinet for the drawing
number of the "Diagram: Roller spring stiffness".
Diagram: Roller force
Please see the documentation parts list for the hydraulic cabinet for the drawing
number of the "Diagram: Roller force".

5.4.3

Working pressure (spring stiffness) hydraulic bladder accumulator


Spring characteristic
The spring characteristic, in other words the spring stiffness, can be selected by
setting the ratio between the hydraulic working pressure p2 and the nitrogen
filling pressure in the hydraulic bladder accumulator p1 . The roller stiffness can
even be changed within certain limits during the operation without changing the
nitrogen filling pressure.
The following applies: the gas spring becomes stiffer the lower the filling
pressure and the higher the working pressure. Exact adjustment of the spring
characteristic is performed by LOESCHE personnel.
The "Diagram: Roller spring stiffness" states the limits which must be observed.
Procedure
The "Diagram: Roller spring stiffness" displays the roller stiffness cwf (= spring
stiffness related to the rollers) via the nitrogen (accumulator bladder) filling
pressure p1. The different hydraulic working pressures p2 or the roller forces FW
are displayed as parameters.

96

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

[kN/mm]

Description of the machine

8,0
7,0

6,0

cwf

5,0

4,0
3,0

p2

2,0

1
1,0

0,0

20,0

40,0

60,0

80,0

120,0
[bar]

000538

p1

100,0

Fig. 30: Diagram: Spring stiffness


Key
cwf
p1
p2
A

Spring stiffness of the roller


Charging pressure of the hydraulic accumulator
Operating pressure
Operating range

Please note: p1max = 0.8 * p2min


p1min = 0.25 * p2max
Sequence:
1. Selection of working pressure p2 (depending on "Diagram: Roller force" (see
documentation parts list "HSLM"))
2. Selection of accumulator filling pressure p1 within operating area
3. Form intersection with vertical on bladder accumulator filling pressure and
p1 working pressure p2
4. Determine intersection horizontal on roller stiffness cwf and read off relevant
roller stiffness
The roller stiffness states by how much the force increases if the roller is
deflected by 1 mm.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

97

LOESCHE Mill with Classifier


Description of the machine

The smaller the difference between p2 and p1, the softer the spring. This means
that the force increase for a soft spring is low if the roller is deflected. The
maximum p1 pressure of the nitrogen filling in the accumulator may not exceed
80% of the operating pressure p2, otherwise the rubber bladder may be
destroyed.

5.4.4

Counterpressure function
Introduction
The hydraulic cylinders are downstream of piston-side piston accumulators.
These ensure a harmonic sequence of oil exchange (due to roller movement)
during mill operation in this location.
Procedure
The function of the piston accumulator system requires a so-called
counterpressure on the cylinder piston side. The counterpressure should be
kept at a low level in order to counteract the spring characteristics of the pistonsided working pressure as little as possible. It must, however, always be
greater than 0.7 Mpa (7 bar).
Adjusting the hydraulic counterpressure p4 takes place depending on the
nitrogen filling pressure p3 in the piston accumulator.
NOTICE
Possible risk to the machine!
The nitrogen filling pressure 3 in addition to the piston accumulator
counterpressure p4 may only be set within a range of 10 % of the values
stated in the "Diagram: Roller spring stiffness"!
During mill operation, the piston accumulator piston must be moving in the
central range of the piston accumulator stroke (guide value).

5.4.5

Roller relief pressure (RRP) partial load operation


General
If necessary, the facility is provided to operate the mill with roller relief.
A pre-requirement for partial load operation is the installation of a roller rotation
monitor (see chapter "5.2.8.1 Roller rotation monitor cpl." on page 69). It must
be ensured that the roller is turning during mill operation.
Procedure
In principle, the working pressure is regulated for higher load ranges and the
counterpressure is held at a low constant level. The commissioning engineer
will set the working system so that regulation of the roller force is possible from
100% down to around 50%. 100% working pressure (roller force) is the
necessary pressure to achieve maximum milled product performance, and it
varies with the job characteristics. If, however, a lower roller force than 50% is
required (partial load) the working pressure is kept at its minimum value and the
counterpressure is increased. This means that the effective working pressure
(and therefore the roller force) remains reduced.

98

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.4.6

Functions of hydropneumatic spring assembly system


WARNING
Heavy machine parts. Possible loss of body parts!
Remaining in the vicinity of moving parts belonging to systems transmitting
grinding power is not permitted for safety reasons.
Use shims of sufficient thickness between roller and table in order to prevent
unintentional lowering of the rollers.
Use suitable auxiliary equipment, such as e.g. rods, to place the metal
plates under the rollers.

NOTICE
Possible damage to machine caused by improper operation!
Ensure that the LOESCHE hydraulic scheme (drawing "Scheme:
Hydraulics) is available in the HSLM.

Note
Operation of the HSLM must be carried out by at least one instructed person
who has been instructed or trained by a specialist in the tasks assigned to him
and the possible hazards of improper operation, in addition to the necessary
safety devices and safety measures.

(For valve settings, see "Scheme: Hydraulics" in the HSLM)


Oil supply to the hydraulic system takes place by the pump unit. Pump run-up is
only necessary during mill operation if leakage losses which could lead to
pressure drops need to be compensated. The HSLM outfeed pipes are fitted
with a pressure monitor in the hydraulic cabinet.
a) Increasing (raising) the working pressure
The working pressure setpoint and the regulation characteristics can be
preselected in the control engineering system. During the operation, the pump
runs automatically until the stated setting has been reached. The pump is
stopped as soon as the higher pressure is achieved.
b) Reducing (lowering) the working pressure
The working pressure setpoint and the regulation characteristics can be
preselected in the control engineering system.
Please check whether the ratio between the nitrogen filling pressure and the
hydraulic working pressure is within the permitted tolerance using the spring
diagram. If necessary, the nitrogen filling pressure must be corrected. This is
only permissible when the mill is at a standstill and the working pressure has
been completely relieved.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

99

LOESCHE Mill with Classifier


Description of the machine

c) Increasing (raising) the counterpressure


The counterpressure setpoint and the regulation characteristics can be
preselected in the control engineering system. A valve closes once the higher
pressure has been reached.
d) Reducing (lowering) the counterpressure
The counterpressure setpoint and the regulation characteristics can be
preselected in the control engineering system. A valve closes as soon as the
lower pressure has been reached.
e) Raising the rollers
When in automatic operating mode, a solenoid valve is switched to the required
position in accordance with the hydraulic scheme. The process is carried out by
pressing the "Raise rollers" button when operating on-site.
The pump unit starts automatically and continues to run until all rollers have
reached their top end position, which is monitored by the proximity switch on the
rocker arms. After this, the pump unit is switched off automatically.
While the rollers are being raised, the working pressure value is increased.
Safety valves ensure that the maximum permissible system pressure cannot be
exceeded.
As an alternative, oil can be fed from the working pressure side to the
counterpressure side through a valve when the rollers are being raised. This
can take place depending on time or pressure. These settings will be made by a
LOESCHE engineer during commissioning.
f) Keep rollers raised (automatic operation)
If, due to leaks in the hydraulic system, one or more rollers leave their top end
position, the pump unit is started automatically in accordance with the "Raise
rollers" process.
g) Lowering rollers (automatic operation)
The oil flows from the counterpressure system back to the tank until the
counterpressure has been reached. The lowering speed of the rollers will be
determined by the LOESCHE commissioning engineer.
h) Reducing pressure
If the entire hydraulic system needs to be brought down to atmospheric
pressure, for example during accumulator filling pressure measurement or
during maintenance work, the hydraulic system must be enabled for "on-site
operation".
The regulating function is out of action.
Once the stopcock has been opened manually (in accordance with the function
tables on the hydraulic scheme) the oil will flow back to the tank.
i) Bypass filtering
The tank contents can be circulated automatically through the filter at specified
intervals by this regulation (in addition to normal main flow filtering).
Operationally-caused pump starts have priority compared with bypass filtering.

100

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.4.7

Service functions
a) Nitrogen pressure test in accumulator
The nitrogen pressure in the bladder accumulators can be checked with this
function.
b) Keeping the rollers raised during service operation
Raise rollers automatically.
"On-site operation" released by control room. The regulating function is out of
action.
The stopcocks must be in the preset setting in accordance with the hydraulic
scheme tables when the rollers are raised.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

101

LOESCHE Mill with Classifier


Description of the machine

5.5

Hydraulic system of the support roller

1
6

000539

Fig. 31: Spring assembly (S) cpl.


Key
1 Mill body
2 Roller (S)
3 Rocker arm (S)

4 Stop buffer
5 Hydraulic cylinder
6 Cover (S)

Design and function


The function of the hydraulic positioning device of the rollers (S=Support) is to
maintain the S rollers at a preselected distance (working height) from the table
grinding plate during mill operation.
The following assemblies are required for this purpose:
Spring assembly (S) cpl. of mill (hydraulic cylinder, stop buffer)
Roller rotation monitor (S) cpl. of mill
Connecting pipeline cpl. of mill
Hydraulic cabinet HSSW
Hydraulic cylinder
See separate manufacturer's documentation

102

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

Stop buffer
The stop buffer serves to absorb impacts. The buffer unit comprises the
bracket, the elastomer and the adjustable spindle.
Spindle adjustment is performed by inserting a plate under the S roller on the
grinding route. Here the spindle is bolted from the outside to the S roller rocker
arm.
This adjustment ensures that there is no metallic contact between the S roller
and the grinding plate.
The adjustment must be checked in good time if the grinding parts are worn.
Connecting pipeline cpl.
Pipelines connect the HSSW hydraulic cabinet to the hydraulic cylinders of the
S rollers.
Hydraulic cabinet HSSW ...
The HSSW hydraulic cabinet provides the supply system for the hydraulic
positioning device of the S rollers.
Please see the separate manufacturer's documentation and the HSSW ....
hydraulic scheme for detailed information about the HSSW setup.
5.5.1

Mode of operation
The S rollers are adjusted during mill operation individually to a distance above
the metallic grinding route with the aid of the hydraulic positioning device.
The intention is for the S rollers to be rotated without slip by friction with the
grinding material and thereby for the grinding bed to be prepared for
subsequent crushing under the grinding rollers.
The height is dependent on the respective grinding material and is determined
during start-up. The height can be measured by means of stroke monitoring.
Deviations from this working height can occur during normal operation (see also
HSSW ... hydraulic scheme) under the following conditions:
Foreign bodies in the grinding material
Grinding bed too high
Oil leaks in the hydraulic system.

5.5.2

Functions of hydraulic positioning device


WARNING
Heavy machine parts. Possible loss of body parts!
Remaining in the vicinity of moving parts belonging to systems transmitting
grinding power is not permitted for safety reasons.
Use shims of sufficient thickness between roller and table in order to prevent
unintentional lowering of the rollers.
Use suitable auxiliary equipment, such as e.g. rods, to place the metal
plates under the rollers.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

103

LOESCHE Mill with Classifier


Description of the machine

NOTICE
Possible damage to machine caused by improper operation!
Ensure that the LOESCHE hydraulic scheme (drawing "Scheme: Hydraulics
HSSW ) is available in the hydraulic cabinet HSSW.

Note
Operation of the HSSW must be carried out by at least one instructed
person who has been instructed or trained by a specialist in the tasks
assigned to him and the possible hazards of improper operation, in addition to
the necessary safety devices and safety measures.
(For valve settings, see "Scheme: Hydraulics" in the HSLM)
a) Raising the S roller
The S roller is raised after the control valve is switched and the pump is started.
The oil displaced from the other cylinder chamber flows via the adjustable flow
restrictor, the valve and the filter back into the tank.
b) Holding the S roller at the top
Hold the control valve in position 1. The pump only has to be started if the S
roller lowers due to an oil leak.
c) Lowering the S roller
The S roller is lowered after the control valve is switched and the pump is
started. The oil displaced from the other cylinder chamber flows via the
adjustable flow restrictor, the valve and the filter back into the tank.
d) Controlling the S roller in Service mode
"On-site operation" enabled by the control room. The regulating function is out
of action.
The S roller can be raised or lowered using the button integrated in the HSSW
hydraulic cabinet.

104

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.6

Design and construction of the classifier

1
9

7
2

6
5
3

000787

Fig. 32: Classifier, assembly overview


Key
1 Classifier drive cpl.
2 Classifier platform cpl.
3 Lining cpl.
4 Guide vane cpl.
5 Rotor cpl.

6
7
8
9

Classifier housing cpl.


Classifier upper housing lining cpl.
Name plate
Classifier platform cpl. (classifier drive)

The following describes the individual complete assemblies of the machine in


detail.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

105

LOESCHE Mill with Classifier


Description of the machine

5.6.1

Classifier housing cpl.

12
1
10
11

3
5

000789

Fig. 33: Classifier housing cpl., schematic sketch


Key
1 Classifier upper housing
2 Chute
3 Shock blower
4 Grit funnel
5 Support tube
6 Support block for bracking pipes.

7
8
9
10
11
12

Classifier lower housing


Deflector ring
Guide vane carrier
Frame
Attachment point for uncoupling rotor
Inspection cover

Structure and function


The "classifier housing cpl." assembly comprises the static parts of the
classifier:
The classifier lower housing is welded or bolted to the mill body.
One or two feeding chutes for the grinding material is/are integrated in the side
of the classifer lower housing. Two chutes serve to feed dry and moist grinding
material separately. They can additionally be equipped with shock blowers.
These remove any deposited material from the chutes by means of
intermittently escaping compressed air.
The grit funnel with support pipes is mounted in the classifier lower housing.
Flat bars in the grit funnel reduce the swirling rate of the grit, thereby reducing
wear.
106

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine
Four passages are provided in the classifier lower housing to support the lower
rotor bearing. Support blocks are welded to the appropriate points on the
outside for mounting the bracing pipes (see also "Rotor support cpl." drawing).
The frame rests on the upper flange of the classifier lower housing. It
accommodates the guide vane carrier. Sectional rings are also attached in the
immediate vicinity to seal off the rotor and prevent coarse particles.
The classifier upper housing rests on the upper flange of the frame. An
inspection cover in the classifier upper housing enalbes this area to be
inspected and accessed.
The classifier upper housing directs and guides the dust/gas flow. It supports
the upper bearing with the suspended rotor and the drive unit. The outlet
connection on the classifier upper housing is connected to the overall grinding
plant.
5.6.2

Rotor cpl.

1
6

2
3

000735

Fig. 34: Rotor cpl.


Key
1 Upper bearing
2 Rotor
3 Assembly kit (comprising turnbuckle, shackle, sling chain)
4 Blades

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

5 Rotor support cpl.


6 Rotor cpl.
7 Lower bearing (not shown)

107

LOESCHE Mill with Classifier


Description of the machine

5.6.2.1

Upper bearing cpl.

1
9

8
3
6

000736

Fig. 35: Upper bearing cpl.


Key
1 Plug
2 Bore for the temperature sensor
3 Feed of the lubrication line
4 Seal gap
5 Sealing ring

5.6.2.2

6
7
8
9

Bolt for aligning the rotor


Axial spherical roller bearing
Sealing ring
Shaft

Lower bearing cpl.

1
9
2
3
5

8
7

000737

Fig. 36: Lower bearing cpl.


Key
1 Axle
2 Seal gap
3 Sealing ring
4 Bearings
5 Temperature sensor position

108

6
7
8
9

Cover
Washer
Plug
Connection lubrication line

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

Structure and function


The direction of rotation of the rotor is determined by the swirl generated by the
louvre ring and the alignment of the guide vanes or guide flaps in the classifier.
The "Upper bearing cpl." is centred by the classifier upper housing and is
screwed to the rotor. The mounting ring supplied with the machine is welded to
the classifier upper housing using the flat bar ring once the rotor has been
aligned.
Attached to the rotor underside is the "Lower bearing cpl." which centres the
rotor on the underside via the "Rotor support cpl.". The four bracing pipes of the
"Rotor support cpl." can be adjusted in length inside and are prestressed on the
outer side of the classifier lower housing.
The shaft inside of the upper bearing as well as the axle inside the lower
bearing are guided in roller bearings and lubricated with grease. The lubricant is
supplied via two separate lines (see "Classifier lubrication cpl." assembly).
The roller bearing temperature can be monitored continuously with a
temperature sensor (available as an optional extra).
5.6.2.3

Classifier temperature sensor cpl.

000741

4
5

Fig. 37: Schematic sketch of classifier temperature sensor, cpl.


Key
1 Upper bearing
2 Temperature sensor for upper bearing
3 Lower bearing

4 Temperature sensor for lower bearing


5 Power supply line (see electrical
documentation)
6 Power supply line (see electrical
documentation)

Structure and function


Each of the classifier rotor bearings is monitored by a temperature sensor with
two independent measuring points. In the event of the permissible temperatures
being exceeded, the signal from the sensors will generate an alarm in the
central control room.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

109

LOESCHE Mill with Classifier


Description of the machine

5.6.3

Classifier lining cpl.

000786

Fig. 38: Classifier lining cpl.


Key
1 Lining on classifier lower housing
2 Lining on bracing pipes
3 Lining on support pipes

4 Lining on shock blowers


5 Lining on chute

Structure and function


The inside of the classifier lower housing is armored. The wear protection can
consist eg. of metal or ceramic.
If a shock blower is connected to the chute , the feed side requires additional
protect ion with lining shells. The outside of the chute and the area of the
incident air flow has to be protected with wear-restistant lining shells.
The supports of the grit funnel and the bearing cartridge as well as the
connecting pipeline of the shock blower ha ve to be protected against wear with
angular lining sheets.
The area of the incident air flow around the grit funnel can be protected with
wear-restistant material eg. ceramics.

110

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.6.4

Classifier upper housing lining cpl.

4
A

A-A

000788

Fig. 39: Classifier upper housing lining cpl.


Key
1 Ceramic lining on classifier upper housing
2 Ceramic lining on braces

3 Ceramic lining on inspection cover


4 Ceramic lining on classifier upper housing

The classifier upper housing with outlet connection as well as parts of the
bearing cartridge can be optionally equipped with a special lining to protect
against wear (see parts list Classifier lining cpl.).

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

111

LOESCHE Mill with Classifier


Description of the machine

5.6.5

Classifier drive cpl.


1

11

10

9
8
4
6
7

000548

Fig. 40: Classifier drive cpl.


Key
1 Gearbox
2 Coupling
3 Motor
4 Console
5 Classifier upper housing
6 Coupling guard

7
8
9
10
11

Bearing cartridge / upper bearing


Coupling
Bell housing
Proximity switch
Castellated disc

Structure and function


The gearbox is supported by a bell housing which is centred and secured on the
bearing cartridge or the upper bearing housing of the "rotor cpl." assembly.
Once the gearbox has been aligned with the rotor shaft, it is pinned to the bell
housing as showing in the drawings. An elastic coupling transmits torque from
the gearbox to the rotor shaft.
The electric motor and its support console are aligned with the gearbox input
shaft during assembly. The console is then welded to the classifier upper
housing as indicated in the drawings.
There is also an elastic coupling between the motor and the gearbox. The
coupling is protected by a coupling guard.
The rotation of the rotor is monitored. This is achieved using a fixed proximity
switch and a castellated disc which turns with the rotor shaft.
The rotor speed is adapted to meet the dust grain size requirements of the
material to be classified. This is achieved steplessly by adjusting the motor
frequency; such changes can be made during active operation of the classifier.

112

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Description of the machine

5.6.6

Classifier lubrication line cpl.

000549

Fig. 41: Schematic sketch of the classifier lubrication line, cpl.


Key
1 Bearing cartridge
2 Dispensing vessel
3 Grease pump unit

4 Lubrication line
5 Distributor

Structure and function


The classifier lubrication line lubricates the two roller bearings in the "bearing
cartridge cpl." assembly (in the case of larger classifiers there are two separate
assemblies, "upper bearing cpl." and "lower bearing cpl.").
The lubrication pump and its grease container are attached to a mounting plate
on the classifier upper housing on the classifier platform (classifier drive) or
towards the top of the classifier lower housing. The arrangement of components
and the route of the lubrication line will vary from one machine to another;
please refer to the corresponding assembly drawings for information. A single
lubrication line runs from the pump outlet to a distributor to which the two
lubrication lines for the upper and lower bearings are connected.
The filling level in the dispensing vessel is usually monitored. If it sinks under a
specific level, this is signaled in the control room.
The running time of the pump and the required grease volume are specified in
"Lubrication scheme: Classifier lubrication line".

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

113

LOESCHE Mill with Classifier


Description of the machine

Name plate

001302

5.6.7

Fig. 42: Name plate

The name plate is attached to the outside of the classifier. It is located on the
classifier upper housing and can be accessed from the classifier platform.
Information on the name plate:
Type
Serial number
Year of construction
Order number
Manufacturer

114

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Transport

6
6.1

Transport
Scope of supply
The scope of supply consists of:
LOESCHE roller grinding mill LM 63.3+3 CS with LSKS 107 CSr with
auxiliary equipment, safety equipment and hydraulic installations, material
feeding unit
Instruction manual
Technical documentation
Separate manufacturer's instruction manuals
The precise and detailed scope of supply can be found in the order
confirmation.
Note
The detailed assembly documentation will be provided to the operator
together with the machine.

6.2

Delivery and packaging


LOESCHE will provide information concerning the scope of supply prior to the
delivery.
The notification will provide information concerning the following points:
the delivery date
the number and type of transport units
kind of delivery (train, truck, ship)
necessary tools for unloading
The transport units are accompanied by package lists that contain information
concerning the content of the transport units, the weight, and the assembly
status.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

115

LOESCHE Mill with Classifier


Transport

6.2.1
6.2.1.1

Transport sketches
Standard transport sketches for the LOESCHE Milll

Foundation frame

5960

5305

3550

680

3550

680

680

680

3550

001137-1

5814

4500

4410

Fig. 43: Transport sketch, foundation frame

Pedestal cpl., gearbox baseplate


4 Ringschrauben
DIN 580-M56

140

. 45
min

EYE BOLT
anneau de levage

3530
3200

4070

4150

VRBS 16t
(4x)

4
8.5
4150

500

001137-2

4500

6840

900

Fig. 44: Transport sketch, pedestal (left fig.), gearbox baseplate

116

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Transport

Bridge

X
VRBS 6,7t
(4x)

2700

2700

11118

750

725

. 45
m in

2972
1500

2700

3
5,5

001137-3

2700

Fig. 45: Transport sketch, bridge

Ring duct
8470

3
min

5,5

Trennlinie
Cutting Line
ligne de dmarcation

001137-4

2420

. 45

VRBS 6,7t
(6x)

Fig. 46: Transport sketch, ring duct

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

117

LOESCHE Mill with Classifier


Transport

Table, gas duct

X
4040

3181
min
. 45

6650

4300

X
2945

2600

800 700

001137-5

2605
1896

3
4

VRBS 4t
(4x)

Fig. 47: Transport sketch, table (left fig.), gas duct

Mill body
X
3

8920

Trennlinie
CUTTING LINE
ligne de dmarcation

001137-6

4100

VRBS 6,7t
(6x)

4930

4350

5,5

Fig. 48: Transport sketch, mill body

118

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Transport

Cover
X

580

2650

001137-7

1615

3995

4210

3770

Fig. 49: Transport sketch, cover

Rocker arm (M), rocker arm (S)


1120

X
3325
2440

3065

2070

5065

2590

001137-8

922

Fig. 50: Transport sketch, rocker arm (M) (left fig.), rocker arm (S)

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

119

LOESCHE Mill with Classifier


Transport

Roller
Transport
TRANSPORT
transport

Transport

3600

1860

TRANSPORT
transport

2900

3 Ringschrauben
DIN 580-M42

3 Ringschrauben
DIN 580-M100x6

INSTALLATION
installation

Eye Bolt
anneau de levage

Eye Bolt
anneau de levage

Einbau

INSTALLATION
installation

001137-9

Einbau

1944

Fig. 51: Transport sketch, roller (M) (left fig.), roller (S)

Foot-bridges
3
4
min

. 45

. 45

mi n

130

VRBS 4t
(2x)

130

2980
500

500

500
VRBS 4t
(2x)

3
4

1990

001137-10

910

820

500

Fig. 52: Transport sketch, foot-bridges

120

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Transport

6.2.1.2

Standard transport sketches for the classifier

Classifier upper housing


X

4000

4360

ca. 7780

001136-1

6870

Fig. 53: Transport sketch, classifier upper housing

Classifier lower housing


X
X

8720
ca. 10450

001136-2

7350

8100

Fig. 54: Transport sketch, classifier lower housing

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

121

LOESCHE Mill with Classifier


Transport

Frame
X

350

8100

001136-3

8100

Fig. 55: Transport sketch, frame

Grit funnel
X

1120

7520

001136-4

6025

Fig. 56: Transport sketch, grit funnel

122

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Transport

Rotor
X

6600

001136-5

ca. 4300

Fig. 57: Transport sketch, Rotor

Motor console

1260

1030

001136-6

1000

Fig. 58: Transport sketch, motor console

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

123

LOESCHE Mill with Classifier


Transport

6.2.1.3

Standard transport sketches for the hydraulic cabinets

HSLM, HSMS and HSSW


HSMS

HSSW

2000

1300

2000

1300

1880

1100

1000

000797

2200

2200

HSLM

Fig. 59: Transport sketch, hydraulic cabinets

Standard transport sketch for the swinging device

430

6.2.1.4

001136-7

4575

Fig. 60: Transport sketch, cylinder swinging device

124

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Transport

6.2.2

Weight of the components

Assembly / Transport
unit

Weight per transport Centre of


unit
gravity

Attachment
points

Lifting gear

Foundation frame

approx. 21,960 kg

Centre

as per dwg.

Crane with lifting


accessories

Gearbox baseplate

approx. 15,300 kg

Centre

as per dwg.

Crane with lifting


accessories

Pedestal cpl.

approx. 43,220 kg

Off-centre

as per dwg.

Crane with lifting


accessories

Support cpl.

approx. 1,205 kg

Off-centre

as per dwg.

Crane with lifting


accessories

Bridges

approx. 9,660 kg

Off-centre

as per dwg.

Crane with lifting


accessories

Ring duct

approx. 17,325 kg

Centre

as per dwg.

Crane with lifting


accessories

Gas duct

approx. 6,305 kg

Off-centre

as per dwg.

Crane with lifting


accessories

Gas duct

approx. 5,320 kg

Off-centre

as per dwg.

Crane with lifting


accessories

Gearbox

see manufacturer's
specifications

Off-centre

Transport lugs

Crane with lifting


accessories

Table

approx. 97,150 kg

Centre

as per dwg.

Crane with lifting


accessories

Mill body

approx. 19,780 kg

Centre

Transport lugs

Crane with lifting


accessories

Cover, left

approx. 5,105 kg

Off-centre

as per dwg.

Crane with lifting


accessories

Cover, right

approx. 3,140 kg

Off-centre

as per dwg.

Crane with lifting


accessories

Rocker arm (M) cpl.

approx. 37,675 kg

Off-centre

Transport lugs

Crane with lifting


accessories

Rocker arm (S) cpl.

approx. 2,200 kg

Off-centre

Transport lugs

Crane with lifting


accessories

Spring assembly
cylinder (M)

approx. 2,300 kg

Centre

Transport lugs

Crane with lifting


accessories

Spring assembly
cylinder (S)

approx. 415 kg

Centre

Transport lugs

Crane with lifting


accessories

Roller (M) cpl. with tire

approx. 43,560 kg

Centre

Transport lug

Crane with lifting


accessories

Roller (S) cpl. with tire

approx. 6,510 kg

Centre

Transport lug

Crane with lifting


accessories

LOESCHE mill 63.3+3 CS

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

125

LOESCHE Mill with Classifier


Transport

Assembly / Transport
unit

Weight per transport Centre of


unit
gravity

Attachment
points

Lifting gear

Hydraulic unit - HSLM

approx. 1,500 kg

Centre

Transport lugs

Crane with lifting


accessories

Hydraulic unit - HSMS

approx. 1,085 kg

Centre

Transport lugs

Crane with lifting


accessories

Hydraulic unit - HSSW

approx. 530 kg

Centre

Transport lugs

Crane with lifting


accessories

Grit funnel

approx. 11,035 kg

Centre

Transport lugs

Crane with lifting


accessories

Classifier lower housing

approx. 25,365 kg

Centre

Transport lugs

Crane with lifting


accessories

Frame

approx. 6,075 kg

Centre

Transport lugs

Crane with lifting


accessories

Rotor incl. blades

approx. 19,790 kg

Centre

Transport lugs

Crane with lifting


accessories

Classifier upper housing

approx. 12,060 kg

Centre

Transport lugs

Crane with lifting


accessories

Chute

approx. 785 kg

Off-centre

Transport lugs

Crane with lifting


accessories

Chute

approx. 430 kg

Off-centre

Transport lugs

Crane with lifting


accessories

Guide vane carrier incl.


guide vanes

approx. 895 kg

Off-centre

Transport lugs

Crane with lifting


accessories

Bearing, upper

approx. 3,645 kg

Centre

as per dwg.

Crane with lifting


accessories

Bearing, lower

approx. 900 kg

Centre

as per dwg.

Crane with lifting


accessories

Classifier drive cpl.

approx. 4,645 kg

Off-centre

as per dwg.

Crane with lifting


accessories

approx. 2,800 kg

Centre

Transport lugs

Crane with lifting


accessories

Hydraulic cabinets

Classifier LSKS 107 CS r

Swinging device
Hydraulic cylinder

Tab. 19: Roller grinding mill, transport weights of components

126

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Transport

6.3

Checking the delivery status


The machines and the equipment made by LOESCHE are thoroughly inspected
and packaged prior to their dispatch, but damage cannot be excluded during the
transport. Transport units will be delivered to the construction site on transport
pallets.
The following checks also apply to the supply of spare and replacement parts.
Incoming inspection
Check the incoming goods for completeness using the delivery note!
Check the incoming goods for signs of damage (visual inspection)!
Procedure in the event of complaints or damaged goods
Immediately contact the last carrier! Complain to them about the damage.
Keep the packaging (so that it can be checked by the carrier or used to
return the goods).
Packaging for returning goods
If parts are damaged to such an extent that they must be returned to the
manufacturer, please contact LOESCHE GmbH.
Please package the machine parts or transport units in such a way that
there is no risk of further damage during the transport.
Packaging for transport by lorry
For the transport by lorry, the transport units are placed on suitable transport
pallets, fastened, and secured with lifting accessories.

6.4

Interim storage of supplied parts


The freight packaging of the machine and of the spare and replacement parts is
designed for 3 months of storage as of the day of delivery.
Bearings and similar parts are also preserved for this period.
The following storage conditions apply to all of the parts:
Closed and dry room with a room temperature of + 5 C to + 40 C.
The maximum relative air humidity must not exceed 80 % (noncondensing).
Other requirements may be stated on the package lists.
In order to avoid long periods of storage, we recommend storing the supplied
machines and parts near the assembly location and providing a warehouse
container or similar for small parts.
Please place desiccants into the electrical and operating cabinets.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

127

LOESCHE Mill with Classifier


Transport

6.5

Transport to the installation site


DANGER
Overturning parts!
Please refer to the information concerning the centre of gravity in the
transport sketches and on the machine parts!
If necessary, secure the transport units with suitable lifting accessories prior
to the transport.
Only specialised personnel is authorised to transport the goods. The local
conditions must be taken into consideration.
Secure the transport units so that they cannot overturn after the removal of
the freight packaging.
Take the weight of the transport unit (see the package list) into
consideration for the transport.

6.5.1

Crane transport
In order to lift the goods with a crane, the operator must provide suitable crane
types, load-bearing equipment, and lifting gear.
Please fulfil the following requirements:
The crane must be suitable for the weight of the transport unit.
The operator must be authorised to operate the crane.
Fasten the lifting accessories (e.g. load-bearing equipment, belts, multipoint
suspension gear, chains) to the transport unit only at the specified lifting
points.

NOTICE
Possible risk to the machine!
Use only the lifting points that are specified in the transport sketches. Avoid
any lateral application of force to these points.

6.5.2

Use the existing lifting points for the transport of the electrical equipment.

Transport with a fork-lift truck


Please fulfil the following requirements:
The fork-lift truck must be suitable for the weight of the transport unit.
The driver must be authorised to drive the fork-lift truck.
Move the forks of the fork-lift truck between or under the bars of the
transport pallet or transport unit. The forks must protrude on the other side.
Lift the transport unit up and transport it.

128

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Transport

6.6

Disposal of the packaging


The operator is responsible for the correct disposal of the packaging.
Dispose of the packaging in accordance with the national rules and
regulations.

6.7

Joining parts on the construction site


NOTICE
Possible risk to the machine!
Do not damage the mill when performing welding or grinding work above the
mill. Beware of flying sparks.
During welding, place the earth electrode as close to the welding point as
possible and not near shaft ends or bearings.
Please refer to the reference documents Q900024-00-4 "Welding of parts
made of ferritic material" and Q900560-00-4 "Quality assurance guideline
for the production".

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

129

LOESCHE Mill with Classifier


Installation

Installation
It is always preferable to have the machine installed by a specialist engineer
from LOESCHE GmbH. If you choose to have the machine installed by a
specialist assembly company, that company must provide personnel with
experience in the assembly of heavy industrial machinery. The work of the
assembly companies involved must be carefully co-ordinated.
The area in and around which the machine is to be assembled and installed
must be sealed off.
The figures used in the description which appears below are for illustrative
purposes only. The drawings, installation diagrams and the plant layout
included in the scope of supply must be referred to when assembling and
installing the machine.
The customer must provide the various lifting devices and tools, load-bearing
equipment, lifting gear, racks and supporting structures required for assembly
and installation.
The assembly sequence will vary depending on local conditions on site. These
include the available space, the load-bearing capacities of floors, the availability
of power points, etc.
Solid and even foundations are vital to achieving the best installation and
assembly results with regard to angularity, evenness and dimensional accuracy.
It is equally important when assembling and installing system components on
the corresponding machine. The assembly and installation reports for these
system components must be inspected before the assembly and installation of
the classifier can commence, in order that their integrity can be verified.
Check the structure of the building/foundation to ensure that it is able to
support the load of the machines and ensure that any additional support
necessary has been put in place.
Keep the routes leading to the area in which the machines are being
assembled and installed clear in order that the process of assembling the
machines will not be hindered.
Note
These mounting instructions, including the instructions and guidelines they
contain, serve solely as a supplement to the drawings and must only be used in
conjunction with them.

7.1

Installation reference documents


Note
The LOESCHE-Mill LM 63.3+3 CS with LSKS 107 CSr and its assembly groups
may be found in the customers parts list (see technical documents).

130

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Installation

7.2

Description of the assembly sequence


Note
More detailed information for assembly you will find in the speratly delivered
document "assembly instruction", which is part of the delivery to the grinding
plant.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

131

LOESCHE Mill with Classifier


Commissioning

Commissioning

8.1

Cold start-up
Note
Cold start-up can only be carried out or monitored by a LOESCHE
commissioning engineer, who is normally an electrotechnician or
electrotechnical engineer with procedural knowledge.
The following is merely a brief summary of the complex procedures for
commissioning a LOESCHE mill.

Definition of the term cold start-up


Cold start-up is the term used for initial start-up of a plant without feeding the
goods to be milled.
8.1.1

Requirements
In order to commence cold start-up, the mechanical and electrical fitting work
must be completed and the fitting acceptance protocol must be signed.

8.1.2

Applicable documents
The following documents must be taken into account for carrying out cold startup.
1. LOESCHE documentation:
Fitting instructions
Documentation for electrical equipment
Start-stop sequences
Interlocking diagrams
Hydraulic schemes
Lubrication instructions
List of electrical consumers
Instrument list
UM datasheets (machine monitoring)
UP datasheets (process control)
Protocols, checklists, forms
Drawings
2. Supplier's documentation
The LOESCHE company accepts absolutely no liability for damages which are
caused by non-observance of this manual for cold start-up and all further
applicable documentation.

132

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Commissioning

8.1.3

Extent of cold start-up


If possible, commissioning should ideally take place in the opposite direction to
material flow. For the most part, however, the sequence of commissioning is
determined by which plant components are already finally assembled and
electrically connected.
During cold commissioning each individual plant component is first started up.
The commissioning engineer here must check in each case whether all the
stipulated preconditions are satisfied. Preconditions applicable to every plant
component:
The plant component is mechanically correctly installed
The plant component is electrically connected
The plant component is pre-filled with the required media
In addition, it is necessary for different plant components to satisfy different
preconditions, which are always listed in the relevant chapter on cold
commissioning.
The commissioning engineer monitors the tests carried out by customer
personnel and, if necessary, the rectification of any faults occurring. He/she also
logs the test results.
After this, plant components are matched to each other in groups using
sequence tests.
The cold run for the entire plant is then carried out for calibration and for the
presetting of process variables and controlled process variables. The cold run
also includes heating up the plant using the hot gas source. Material is not fed
in during this phase. The results of the cold run are logged by the
commissioning engineer.
After the successful completion of sequence tests and the cold run itself, cold
commissioning is deemed to be completed.
The plant is handed over to the commissioning engineer who is to perform hot
commissioning together with the protocols of the idle running test and the
testing of the start/stop sequences and interlockings.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

133

LOESCHE Mill with Classifier


Commissioning

8.1.4

Cold start-up sequence


DANGER
Wide range of hazards!
Secure hazard areas with safety devices or, if necessary, blocking off!
Sound an acoustic warning signal before starting any drives!

NOTICE
Possible risk to machine!
Before starting any drive, always ensure that no other plant components can
be damaged!

The cold start-up of individual plant components normally follows a particular


scheme:
1. The commissioning manager checks the correct mechanical assembly of
components.
2. The commissioning manager checks that components are correctly
electrically connected.
3. The commissioning manager checks the control system hardware and
software in accordance with the LOESCHE interlocking diagram.
4. The commissioning manager sets the time delays (timer) and values for
warning or alarm in the hardware and software in agreement with the
LOESCHE UM and UP datasheets.
5. The commissioning manager checks that all lubricants have been filled up
in accordance with the LOESCHE lubricant list.
6. The commissioning manager carries out signal tests (I/O checks) on the
relevant electrical consumers and instruments.
7. The commissioning manager ensures that motors are rotating in the right
direction.
8. The commissioning manager parameterises the instruments in accordance
with the LOESCHE and supplier documentation.
9. The commissioning manager checks interlocking in accordance with the
LOESCHE interlocking diagram.
10. The commissioning manager checks whether motors are coupled to the
associated machines using supplier documentation.
11. The commissioning manager tests the function and interlocking of
appropriate components during a trial run.
12. If the relevant components have been commissioned, the commissioning
manager carries out a function and trial run (sequence test) on the
component groups.
13. Once all component groups have been commissioned, the commissioning
manager carries out a cold run for the entire plant in accordance with the
LOESCHE starting sequence. This start includes heating up the system with
the hot gas producer or another hot gas source. Material is not fed in.

134

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Commissioning
14. The commissioning manager checks the sequential and processing into
locks in accordance with LOESCHE documentation.
15. The commissioning manager runs the entire plant down in accordance with
the LOESCHE stop sequence.
16. The commissioning manager tests the emergency stop sequence in
accordance with the LOESCHE emergency stop sequence diagram.
8.2

Warm start-up
Note
Hot commissioning can only be carried out or monitored by a qualified
LOESCHE commissioning engineer, who is normally an electrical engineer or a
mechanical engineer with process engineering knowledge.

Definition
Hot commissioning is the term used for initial start-up of a plant including
feeding the raw material to be ground. It follows on in the LOESCHE sequence
diagram at the point where cold commissioning was concluded: With material
feed.
Hot commissioning is divided into the following phases:
1.
First warm-up
2.
Plant stop
3.
First inspection
4.
Optimisation phase
5.
Performance verification test
6.
Verification of reliability
7.
Performance run
8.
Handover to the operator

Objectives
The objectives of hot commissioning are
1.
integrating the LOESCHE mill with classifier and the customer's scope of
supply into the normal operational sequence of the grinding plant.
2.
achieving stable grinding operation.
3.
achieving the contractually warranted product qualities.
4.
achieving the contractually warranted product quantities.
5.
achieving the contractually warranted values.

Preconditions
To be able to begin hot commissioning, it is necessary to satisfy the following
conditions:
The plant cold run has been successfully completed and the necessary
protocols and reports have been drawn up, signed and handed over in
accordance with the LOESCHE overview of protocols, reports and drafts for
commissioning.
P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

135

LOESCHE Mill with Classifier


Commissioning

8.3

All the plant components are in full working order, ready for operation and
safe in accordance with the supplier's documentation.
The operator makes available feed material in/of sufficient quantity and
quality so that the start of hot commissioning is not delayed and
measurement results are not negatively influenced.
The operator makes available further consumables required such as e.g.
electric current, water, air, hot gases, oil, lubricant, fuel, etc. in/of sufficient
quantity and quality so that the start of hot commissioning is not delayed
and measurement results are not negatively influenced.
The operator makes available sufficiently qualified and experienced
personnel so as to ensure 24-hour operation. The operator must also make
available standby personnel for repairs.
The operator makes available all the required tools, vehicles, machines and
spare parts.
The operator ensures that measurements and settings can be carried out
on all plant components.
All protective devices are adjusted, in proper working order and ready for
operation.
The LOESCHE commissioning engineer is knowledgeable about the plant
documentation such as e.g. heat balances, spring stiffness, layouts and
settings.
The operator warrants the fault-free functioning of its scope of supply by
means of written release.

Commissioning the hydraulic system


Commissioning is performed in this order:
Check the position of the hand valves in the hydraulic system in accordance
with the drawing "Scheme: Hydraulic HSLM ..." and "Scheme: Hydraulic
HSSW ...".
Check electrical monitors and locks in accordance with the electrical
documentation.
Fill the hydraulic accumulators with nitrogen. The filling pressure is
determined during commissioning by the LOESCHE running-in engineer.
Leaded safety valves (6....) in the HSLM hydraulic cabinet must be
examined for undamaged lead seals.
Fill the overall hydraulic system with prescribed oil up to the upper tank
marking - including pipelines and cylinders.
Clean the overall hydraulic system with flushing oil.
Adjust the proximity limit switches on the rocker arms in accordance with
the "Rocker arm monitor cpl." drawing (see mill parts list). These limits
switches are mounted on each rocker arm.
Bleed the hydraulic system several times until the system is completely gasfree.
Preserve the piston rods of the hydraulic cylinders on the S rollers.

8.4

Commissioning the hydraulic positioning device for support rollers (S)


When commissioning the mill and when making important changes to the
grinding material composition, it is necessary to determine the correct working
height for the support rollers by testing. The aim is to minimise the vibration
velocity of the mill in order to ensure safe and fault-free machine operatioin.
The following measures, which are carried out during commissioning by the
LOESCHE running-in engineer, are required:

136

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Commissioning

Raising or lowering of the support rollers in 5 - 10 mm increments until their


swinging range is covered. The initial height of the support roller is freely
preselected.
Noting down of the values of support roller speed and relative mill vibration
velocity (measured on the mill body) in a table for each working height.
Raising or lowering of all the S rollers in the same direction at the same time
during measurement.
After measurement the LOESCHE running-in enginerr adjusts for Automatic
mode the working height for the S rollers at which the mill vibrations are
minimal.
The throttle valves are adjusted and checked by the LOESCHE running-in
engineer during commissioning. They influence the lowering and raising speed
of the support rollers. The LOESCHE running-in engineer adjusts the throttle
valves in such a way that the pressure reducer valve does not open during the
normal raising operation (see "Hydraulic scheme HSSW ...).
8.5
8.5.1

Starting the mill when unfilled or filled


Master rollers (M)
After the hydropneumatic spring assembly system of the rollers is electrically
enabled, the following processes occur automatically in accordance with the
electrical sequence plan. The respective position of the hand and solenoid
valves is set out in the function table in the drawing "Scheme: Hydraulic
HSLM ...".
The rollers are raised until a mechanical stop is reached (the end of movement
is determined by limitation of the piston stroke on the cylinder cover).
After all the rollers have reached their upper position, the relevant pump motor
is switched off by the proximity switches.
Note
While the pistons move out of the cylinder when the rollers are raised, the
pressure in the working pressure and counterpressure systems rises in relation
to the set pressure as long as the solenoid valve(s) is/are not activated.
The regulating function is out of action while the rollers are raised or lowered.
The higher working pressure or counterpressure can be read off at the relevant
pressure gauges (see drawing "Scheme: Hydraulic HSLM ...").
If, while the rollers are raised, a pressure loss occurs in the system, e.g. due to
leakage oil, one or more rollers move downwards. The respective high-pressure
pump starts automatically to counteract this. It runs until the switching point of
the upper proximity switch is reached again.
During the "Lower rollers" process the rollers move downwards in response to
the force of gravity and the additional force of the gas cushion in the
accumulators onto the table. The regulating function is out of action while the
rollers are being lowered.
In order to ensure that the rollers are immersed slowly into the grinding bed as
they are lowered, the return oil to the tank is routed via an adjustable flow
restrictor.
The relevant preconditions for activating the individual processes can also be
taken from the sequence diagram in the LOESCHE electrical documentation.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

137

LOESCHE Mill with Classifier


Commissioning
8.5.2

Support rollers (S)


The processes of the hydraulic positioning device of the support rollers also
take place in parallel to the M rollers after electrical enabling, whereby the
respective position oif the hand and solenoid valves can be taken from the table
featured in the drawing "Scheme: Hydraulic HSSW ...".
The relevant preconditions for activating the individual processes can also be
taken from the sequence diagram in the LOESCHE electrical documentation.

8.5.3

Shutting down the mill during normal operation


If the mill is to be stopped, transportation of the grinding material is shut down.
The mill motor can be deactivated with a delay if after a few rotations the
grinding material still on the table has been thrown off as a result of centrifugal
force.
When the supply of material is interrupted, the hydraulic pressure is usually
switched over in the hydropneumatic spring assembly system to the piston side
of the spring assembly cylinders, which causes the master rollers to be lifted off
the table.
The process runs in the same way when the S rollers are raised.

8.5.4

Emergency Stop
In the event of an emergency stop or a power failure, both the master rollers
and the support rollers remain in contact with the grinding material. It takes
max. one rotation to brake the table.

8.5.5

On-site operation
In the event of maintenance work enabling is performed for "on-site operation"
by the control room. The regulating function is out of action.
The rollers can then be raised at the HSLM and HSSW hydraulic cabinets,
whereby the pumps are started on site.

138

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Operation

Operation
DANGER
Accident hazard!
The plant may only be operated by skilled personnel who are qualified and
have been trained to do so.

NOTICE
Possible risk to machine!
Check before starting production that there are no objects (e.g. tools,
residual materials or similar) in the machines, units and piping

Note
It is essential when operating the individual machines to observe the relevant
information and specifications provided in the separate instruction manuals
The individual machines can be operated in the Manual or Set-up mode from
the local control panels (determined by the operator).
The machines are operated within the framework of the function of the overall
system (higher-level control room) in Automatic mode and controlled from the
central control room.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

139

LOESCHE Mill with Classifier


Operation

9.1
9.1.1

Local control panels


Operation
The following control elements can be located on the local control panel
(determined by the operator):
1. Maintenance switch (rotary switch), optional
The component is connected to or disconnected from the power supply by
actuating the maintenance switch.
DANGER
Accident hazard!
If the maintenance switch is switched off for the performance of cleaning,
maintenance and repair work, it must be mechanically secured against
unintentional switching on through the use of a padlock.
2. Emergency Stop button (red palm button switch), optional
The complete grinding plant is brought to a safe operating state when this
button is actuated. The Emergency Stop button can be released again by
pulling or turning counterclockwise/clockwise.
3. On (green illuminated pushbutton), optional
The control system is switched on when this button is actuated; lights up
permanently after switching on.

9.2
9.2.1

Operating modes
Local operation
For the performance of refurbishing, maintenance and repair work all the
electrical drives can be switched over from their local control points to Manual
mode and thereby operated. (Determined by the operator)
This may occur only after consultation with the responsible plant operator and is
permitted only when the plant is stopped. The plant fails complete when
switched over from Automatic mode to Local mode during operation.
All the designated locks must be activated for Local mode so as to ensure that
the individual machines are protected.
Process-relevant locks are partially deactivated.
In Local mode the operator bears the responsibility for operating individual
components of the plant. Operation of individual components and of machine or
plant components may only be performed by experienced and specially trained
persons, taking into account potential effects on persons and plant components.

140

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Operation

9.2.2

Automatic mode
In normal operation the complete plant is operated in Automatic mode. The
complete plant is controlled and monitored here from the central control room.
NOTICE
Possible risk to the machine!
Operation of the complete plant is permitted for production only in Automatic
mode!
All the designated locks must always be activated. This guarantees the
protection of persons and of the individual machines and prevents longer plant
stoppages on account of damaged machines.

9.3
9.3.1

Switching the grinding plant on and off


Switching the plant on
Before starting the grinding plant, especially after a longer stoppage, inspect the
complete plant to ensure that all openings and access doors in the grinding
circuit are closed, tools have been removed and auxiliary scaffolding and
platforms have been disassembled.
Also check:
Stop cocks ahead of the transducers opened, all measurements ready for
operation, 0 point and measuring ranged adjusted and checked
Start up all the shut-off devices in the mill lube-oil circuit
Check the oil level in the mill gearbox and after an inspection, correcting if
necessary
Oil level in the gearbox of the grinding-stock feeder OK
Oil level at the bearing block of the mill blower OK
Before starting after an extended stoppage, run all the flap drives locally
once. Check external "OPEN" / "CLOSED" end position to ensure
operational reliability
The shut-off devices of the mill hydraulic system are in the operating
position in accordance with the hydraulic scheme
Grinding stock present in the feeder, layer height > min.

9.3.2

Starting the grinding circuit


If scheduled by the operator, it is possible after commissioning is completed to
start the complete plant by actuating the corresponding button (Master
Start/Stop - Start button).
The individual sequences are started automatically as soon as the start
conditions are satisfied.
Independently of the above, however, the operator can start the grinding plant
in individual steps as follows:

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

141

LOESCHE Mill with Classifier


Operation

9.3.3

Start sequence
Auxiliary units "ON"
The lube-oil pump of the mill gearbox should remain in operation in winter in
order to keep the lube-oil circuit at an operating temperature of min. 15 C.
Note
The lube-oil temperature must be > 15 C before the mill is started.

The group is started by actuating the corresponding button (Mill auxiliary


drives).
The following functions are executed with this command:
Lube-oil pump of mill gearbox ON, coolant on standby
Note: If the oil temperature rises to > 30C, a control valve in the coolant
line opens automatically
Classifier drive ON
Mill hydraulic system ON, "Raise rollers
Start "Warm-up"
Starting of the flap program (different depending on the plant circuit)
Start "Mill motor"
Requirement:
All the rollers are in the "Top Position
When the corresponding button
(Mill motor) is actuated, the mill motor is started.
Note
The list of limit values containing the setting parameters and operating data for
the grinding plant is created during commissioning(IBN) depending on the raw
material
Start "Grinding operation"
Requirement:
Grinding operation is started by actuating the corresponding button (Mill
material feed).
Program sequence:
The gas volume ahead of the mill approaches the start setpoint value
Start of the grinding-stock feeder with the start setpoint value; see list of
limit values
Lowering of the grinding rollers after start of material feed; waiting time,
see list of limit values.
When the back pressure has reached the setpoint value, the grinding plant is
properly in grinding mode.

142

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Operation
Automatic pressure control becomes active after a short waiting period. The
feeder speed can be increased in several increments while observing the mill
outlet temperature. If this start is implemented fully automatically, the different
moisture of the feed material must be taken into consideration. In other words, 2
start sequences must be developed where necessary for summer and winter
operation.
9.3.4

Operating the grinding plant


The grinding plant is in stable grinding mode after the start sequence is
completed and the setpoint value for the feeder speed has been reached. All
the control loops are in Automatic mode. If a "warning" is issued, the operator
must react accordingly and re-establish a normal operating state through
appropriate manual interventions. In hazardous situations the grinding plant
must be powered down in case of doubt. (Change of setpoint values, rotational
speeds, flap positions...). The essential control loops and principles for constant
grinding operation are described in the following.
Monitoring of differential pressure over mill
The differential pressure over mill is a value calculated from the measured
pressure after mill and the measured pressure before mill.
The differential pressure rises as the feed quantity increases. Furthermore, a
change in grindability from easy to hard at a constant working pressure is
manifested in a rise in the pressure loss over mill.
The limit value for the differential pressure must be set accordingly. Max.
setpoint value, see list of limit values.
Note
When the plant resistance rises above the setpoint value, sufficient internal
material circulation in the mill is no longer guaranteed on account of an
inadequate gas volume through the mill.
Consequences:
The grinding plant becomes increasingly unsteady, vibrations increase
There is an increased incidence of rejects
The setpoint gas volume can no longer be achieved.
Control of temperature after mill
The gas temperature is set during commissioning depending on the residual
moisture in the finished stock. The temperature is measured in the classifier
outlet of the grinding plant.
In situations in which an automatic correction of deviations from the setpoint
value is not possible, limit monitors send signals to the central control room. In
the interests of guaranteeing machine safety, an alarm is issued or an
intervention is made in the process control system (detailed structrure, see
electrical documentation).
Note
During grinding drying the setpoint value for temperature control after mill must
not be < 80 C, as otherwise sufficient drying of the grinding stock is no longer
guaranteed.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

143

LOESCHE Mill with Classifier


Operation

Measuring the air flow after filter


A constant air flow through the mill is an essential requirement for stable
grinding operation and consistent product quality.
The minimum gas volume is determined among other things by the amount of
reject material obtained. Increasing the gas volume has negative effects on the
kWh demand of the mill blower and on wear in the mill.
The setpoint value for the gas volume is specified by the operator, the gas
volume is maintained by the swirl flap or by the variable speed of the mill
blower.
Product quality
Comminution is dependent on:
Feed quantity
Total gas volume
Working pressure
Classifier speed
Feed moisture of the grinding stock
The level of the working pressure has a direct influence on the product quantity
/ quality.
Reducing the working pressure results in the case of a high feed quantity in a
rise in the differential pressure over mill and in the case of extreme changes in
increased rejection of grinding stock via the louvre ring into the reject boxes.
The classifier speed should, on account of the required grinding fineness, be
adjusted to the currently measured product fineness.
9.3.5

Switching the plant off


Intentional powering down of the grinding plant is performed by actuating the
corresponding button (Master Start/Stop - Stop button).
Material feed is automatically stopped. The stop sequence is explained in detail
in the electrical documentation.
The mill motor runs on to ensure that the grinding table is emptied to the
greatest possible extent. The grinding plant can be started up from this state
during the next start by the operator.
If an extended grinding-plant stoppage is scheduled
(> 1 week), the following plant components can be shut down by the operator.
Stop - gearbox lubrication
Stop HSLM
(See electrical documentation).
Note
Gearbox lubrication should wherever possible remain in continuous operation in
the winter months.

144

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Operation

9.3.6

Unlocking the Emergency Stop functions


The Emergency Stop function is unlocked after the cause has been eliminated
at the Emergency Stop button. Acknowledgement of the
Emergency Stop indication is performed from the central control room (for
details, see electrical documentation).

9.4
9.4.1

Failure of power supplies


Switching the plant off in the event of a power failure
The following plant components are protected by an uninterruptible power
system against failure for 30 minutes:
Plant control system (SPC), optional
Plant visualisation, optional
Gas analysis (if provided), (exception: tracing)
In the event of an extended power failure (> 30 min), the operator must supply
the above-mentioned safety-relevant plant components with power by means of
a separate power supply (e.g. diesel generator). When electrical power is
restored, the plant must be returned to its basic setting and restarted.

9.4.2

Switching the plant off in the event of a hydraulic-system failure


When hydraulic pressure is restored, the plant component or if necessary the
plant must be returned to its basic setting and restarted.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

145

LOESCHE Mill with Classifier


Operation

9.5

Electrical engineering
Note
The operation, function and mode of action of the grinding plant can be found in
the separate "Electrical documentation" which is included in supply with the
grinding plant.

146

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Troubleshooting

10 Troubleshooting
DANGER
Accident hazard!
The facts and notes to "faults, causes and troubleshooting" mentioned in this
instruction are described in a way, that it can be understood by trained skilled
personnel (see definition chapter Requirements of personnel on page 26 " in:
electricity / electronics
mechanics / maintenance
The adequate tools and test equipement has to be allocated to the trained and
skilled personnel.
Specially before all maintenance and repair work essentially the shutdown
procedure has to be operated (see chapter 3.10).
If the measures mentioned above end in failure, please contact LOESCHE
GmbH.
Faults are indicated by means of colour-coding on the process flow screen in
the control room. Alarm indications appear in plain text and include information
about which components have been affected. A distinction is drawn between
process faults and machine-specific faults.
Intervention - by trained skilled personnel only - is required to rectify the
machine-specific faults listed below.
Should investigations into a fault identify a need for maintenance and repair
work, the shutdown procedure for the machine (see "Maintenance on page
151") or the higher-level control will need to be followed prior to such work
commencing.
You will find information about troubleshooting purchased components in the
separate manufacturer's instructions, see "Supplier documentation".

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

147

LOESCHE Mill with Classifier


Troubleshooting

Fault

Cause

Remedy

Main switch/maintenance switch


set to "0".

Switch the main


switch/maintenance switch on.

Overcurrent protection triggered

Request skilled worker for fault


rectification

Emergency Stop button pressed

Determine and rectify cause, and


unlock Emergency Stop button,
cancel Emergency Stop

Sealing air pressure too


low/sealing air exhausted.

Identify the cause and restore the


sealing air system to working
order

Lubrication system fault


indication; insufficient or no
lubrication compound available

Top up with lubricant

Strong vibrations

Feed pieces too great

Reduce feed pieces to


permissible value

Mill resistance increases

Armour ring worn

Replace armour rings

Blocked roller

Check bearing

Unsteady mill operation

Dam ring worn

Replace dam ring

Increased temperature at
grinding rollers

Oil level in roller too low!

Check oil level

Oil is overaged

If necessary, top up with oil


Check when last oil change was
carried out

Bearing faulty

Check bearing, replace if


necessary

Oil discharge at grinding rollers

Slip-ring seal faulty

Check slip-ring seal, replace if


necessary (in pairs)

Heavy discolouration by
microscopic floating particles in
oil

Sliding rings worn

Replace sliding rings (in pairs)

Sealing air pressure too high

Sealing air system is fouled

Clean the sealing air system

Sealing air pipes are damaged,


e.g. kinked

Replace defective pipes

Sealing air seal in the roller is


fouled

Clean the roller sealing gap


Check the sealing air gap in the
roller

Sealing air system is leaking

Locate and seal leaks

Mill
Control will not power up.

Machine shuts down; fault


indications in the control room

Sealing air pressure too low

Wear ring, roller/rocker arm, worn Replace wear rings if sealing air
gap too large
Shortened switch-on intervals of
pump in HSLM

Working pressure drops too


quickly

Check piston seals in hydraulic


cylinder, replace if necessary
Check valves in cabinet

148

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Troubleshooting

Fault

Cause

Remedy

Connection between arm and


fork (pin connection and screws)
not released

Check connection, release if


necessary

Bearing faulty

Check bearing, replace if


necessary

Swing-out cylinder cannot be


moved

Check bearing, replace if


necessary

Swinging device
Roller cannot be swung out

Increase pressure or check


condition of line-break fastener
Classifier
Classifier running unsteadily;
vibrations

Rotor; blade faulty

Check classifier rotor; replace


parts if necessary

Increased temperature at
classifier drive

Fault at bearings/drive
Oil loss

Check bearings/drive
Check oil level

Specific fault indications are shown via the control system in the control room of the higher-level system.
Tab. 20: Fault, Cause, Remedy table

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

149

LOESCHE Mill with Classifier


Troubleshooting

10.1 Customer service


Should you require further information, please contact our customer service
team directly:
LOESCHE GmbH
Hansaallee 243
40549 Dsseldorf
Germany
Tel.:
+49 (0)211 5353-0
Fax:
+49 (0)211 5353-500
e-mail: loesche@loesche.de

150

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11 Maintenance
11.1 General notes on maintenance works
The standard "DIN 31051, Fundamentals of maintenance" divides maintenance
works into the sectors
inspection
cleaning
service/preventive maintenance

DANGER
Accident hazard!
The chapter Maintenance/Cleaning is intended for skilled workers only.
Maintenance, cleaning and repair work may only be carried out by skilled
personnel.

Skilled worker
A person who, by combining his or her specialist training, knowledge and
experience with awareness of applicable standards, is able to assess the tasks
with which or he she has been assigned and identify potential hazards.
Definition in accordance with EN 60204-1.

Note
Operating and maintenance personnel will be trained by LOESCHE GmbH
personnel at the machine installation site. If any questions or uncertainties arise,
please contact LOESCHE GmbH.
To ensure fault-free operation, it is absolutely vital that the machine will be
cleaned and serviced at regular intervals.
Record all maintenance work completed in a maintenance logbook.
Record the operating hours of bearings and components subject to
particular wear.
During operation, the machine is subject to vibrations which can cause
screwed/bolted and clamp connections to come loose.
To prevent damage, check the machine at regular intervals (recommended
interval for single-shift operation 6 months) for loose connections.
Note
Refer to the external manufacturer instruction manuals for information on
servicing / cleaning the individual bought-in components (especially motors
and gearboxes).

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

151

LOESCHE Mill with Classifier


Maintenance

General hazards associated with maintenance, cleaning and lubrication

DANGER
Accident hazard!
Before carrying out cleaning, maintenance and repair work, it is absolutely
essential to follow the shutdown procedures (see Chapter "Shutdown
procedure Page 32).
Before carrying out burning and welding work, obtain the necessary
approvals. When carrying out welding work, always observe the applicable
safety regulations.
Hydraulic accumulators are pressure vessels and must be pressure-tested
at regular intervals in accordance with the regulations of the technical
inspection authorities. Operation of hydraulic accumulators is subject to
mandatory reporting in most countries. Strict compliance is required!
When carrying out cleaning and maintenance work, open the inspection
covers only after the plant has been run empty and shut down. Duration of
emptying, see Chapter "Shutdown procedure Page 32
Do not use any sharp objects or tools for cleaning which are not expressly
intended for this purpose.
Observe the data and useful life intervals of hydraulic connections and
hydraulic hoses so as to be able to carry out in good time the prescribed
replacements.
Explosive materials
Oxygen or air can cause explosions in connection with oil.
Only nitrogen gas may be used to fill up the rubber bladder in the
accumulator or in the piston accumulator.

152

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.2 Inspection
Component

Interval for one-shift operation


d

Main switch

1y

Emergency Stop button

Locks on cabinets

Check cables for tight seating

Setting values on circuit-breaker

Buttons on electrical switching cabinet and local control


panels

X
X

Check all plug, screwed and clamp connections for tight


seating, retightening if necessary

Pneumatic system; check set air pressure on maintenance


unit

Check pressure at maintenance unit, adjust if necessary

Hydraulic unit; check set hydraulic pressure on hydraulic


unit

Tab. 21: Function checks, inspection intervals

Key
d
w
m
y
C

daily
weekly
monthly
yearly
Clean when openend

The intervals are calculated for one-shift operation (8 hours/working day 12 months/year).

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

153

LOESCHE Mill with Classifier


Maintenance

001382

11.3 Cleaning

Cleaning work is performed only on the outer areas of the machine.


DANGER
Work involves a high danger potential!
Danger to life and limb
Observe the shutdown procedures (see Ch. "Shutdown procedure Page 32)
before starting cleaning, maintenance and repair work.

NOTICE
Possible risk to the machine!
Do not use any sharp objects or tools for cleaning which are not expressly
intended for this purpose.

General cleaning instructions:


Regularly clean all areas of the machine (well swept).
Dispose of material remnants, cleaning waste and cleaning materials in an
environmentally compatible manner.
Clean the filters of the compressed-air system on a regular basis. Cleaning
is carried out according to the filter manufacturers' instructions.
At the beginning of maintenance/repair work clean the machine,
connections and screwed joints to remove oil, fuel or care products. Do not
use any aggressive cleaning agents. Use fluff-free cleaning cloths.
Before cleaning the machine with water or a steam jet (high-pressure
cleaner) or other cleaning agents, cover/tape closed all openings into which
water/steam/cleaning agents are not permitted to enter for safety and/or
functional reasons. Electric motors and switching cabinets are at particular
risk.
Make sure when cleaning the machine hall that temperature sensors of the
fire alarm and extinguishing systems do not come into contact with hot
cleaning agents. The extinguishing system could otherwise be set off.
Remove all covers and taping after cleaning.

154

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

After cleaning check all the fuel, engine oil and hydraulic oil lines for leaks,
loosened connections, abrasion and damage. Rectify identified defects
immediately.

Note
When carrying out cleaning work, following the information and instructions
provided in external instruction manuals and corresponding in-house
instructions.

Activity

Interval

Make sure that cooling fins of electric motors are not clogged by dirt so as to prevent the risk
of motor overheating; clean if necessary.

Clean switches, buttons and information plates/signs on switching cabinets and control
panels (on the outside) with a fluff-free cloth (plates/signs that are no longer legible must be
replaced).

Keep all access routes, steps and platforms free of dirt on a regular basis and if necessary
eliminate any existing slipping hazards.

Dispose of material remnants, cleaning waste and cleaning materials on a regular basis in an
environmentally compatible manner.
Tab. 22: Cleaning intervals

The intervals are calculated for one-shift operation (8 hours per working day 12
months per year).
Key
d
m
y

daily
monthly
yearly

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

155

LOESCHE Mill with Classifier


Maintenance

11.4 Maintenance

001381

11.4.1 Lubrication

NOTICE
Possible risk to the machine!
Use only lubricants which are featured in the LOESCHE lubricants list.

156

All lubrication points are lubricated with grease.


Follow the notes and instructions in the lubricant tables when carrying out
lubrication tasks.
The lubrication points on the plant must be regularly lubricated with the aid
of appropriate lubrication tools.
On larger mills all the lubrication bores are connected to a central grease
lubrication system.
The lubrication intervals must be determined by the operator on the basis of
the operating hours to be performed by the plant.
All lubrication bores are sealed by grease nipples during transportation.
The piston and piston rods in the hydraulic cylinders are lubricated
automatically by the hydraulic oil (oil change in accordance with
maintenance table).
On larger raw meal and clinker/slag grinding plants the roller bearings are
lubricated by the HSMS (see parts lists or delivery contract). Refer to the
lubricant table for oil quantity and oil quality.
When lubricating gearboxes, follow the instructions in the separate
manufacturer instruction manuals.
Mechanical damage to pipes must be repaired immediately. Hoses must be
checked on a regular basis as to their good condition and if necessary
replaced.
The grease containers of the lubrication pumps must be regularly refilled
with the grease specified in the lubricant table. The cover of the grease
container must be sealed tight to prevent dust from getting into the
container.
The rod head and hydraulic cylinder roller bearings are kneaded full of
grease. Re-greasing the bearing takes place using a hand grease gun on
the grease nipples at long periods in accordance with the maintenance
table. Since the bearings are moved through small pivoting angles, grease
consumption is low. The grease has a long useful life.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

001380

11.4.2 General maintenance information for assemblies and machines

These abbreviations are used in the following maintenance instructions:


Key
I
d
w
m
M
W
Y
OH

Interval
daily
weekly
monthly
Months
Weeks
Years
Operating hours

MP
M
E

Maintenance personnel
Mechanic
Electrician

OC
O
S

Operating condition
In operation
Stoppage

Table of Contents Maintenance


Maintenance: Mill stand cpl. .............................................................................158
Maintenance: Mill body cpl. ..............................................................................159
Maintenance: Table cpl. ...................................................................................160
Maintenance: Rocker arms ..............................................................................167
Maintenance: Roller .........................................................................................172
Maintenance: Spring assembly cpl...................................................................185
Maintenance: Hydraulic accumulators .............................................................190
Maintenance: Hydraulic cabinets .....................................................................194
Maintenance: LM-Drive ....................................................................................196
Maintenance: Gearbox lubrication unit.............................................................197
Maintenance: Central lubrication unit ...............................................................198
Maintenance: Sealing air system .....................................................................199
Maintenance: Piping system ............................................................................200
Maintenance: Swinging device.........................................................................200
Maintenance: Grinding bed sprinkler cpl..........................................................201
Maintenance: Classifier ....................................................................................202

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

157

LOESCHE Mill with Classifier


Maintenance

11.4.3 Maintenance: Mill stand cpl.


DANGER
Risk of falling!
Wear protective gear during maintenance work with disassembly of platform
parts.
Cordon off danger areas from unauthorized persons

Tighten bolts on bearing cap immediately after commissioning. Repeat the


process after 8 operating hours and then secure bolt heads in accordance
with drawing information.
Retighten hex nuts inside and outside the pedestals and then weld after
around 100 mill operating hours in accordance with drawing information.
Retighten hex bolts and gearbox foot flanges after around 24 operating
hours and secure in accordance with gearbox documentation.
Check driving wedges (if fitted) for secure seating after around 24 hours,
knock in again if required and weld lightly together.
Keep (reject) flaps closed during operation to prevent leak air ingress into
the mill.
Check (reject) flaps for good seating on edges and check reject chute, align
if necessary.
Check (reject) flap seals for correct functioning, replace if necessary.

Ring duct - Scraper


Inspection can be carried out through the inspection openings in the gas duct or
ring duct.
Replace worn scrapers.
Remedy signs of wear on the scraper rods by hard-facing with hard
electrodes.
Component

Description

MP

OC

Mill stand

Check pedestal welded seams

6M

Op

Check welded seams on bridges

6M

Op

Check welded seams on bearing blocks

6M

Op

Check bolted connections for completeness

6M

Op

Check bolted connections for tight fitting

6M

Op

Inspect for rust formation

12 M M

Op

Check gas duct

12 M E

Check seal air piping

6M

Check bolted connections on seal air piping

6M

Op

Check expansion joints for damage and sealtightness

6M

Op

158

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

Component

Description

MP

OC

Ring duct

Check surface coatings, look for rust formation

6M

Check for holes

3M

Check for damage and wear

3M

Check scrapers for damage and wear

3M

Check distance between scrapers and ring duct floor, correct

3M

Tab. 23: Maintenance table, mill stand

11.4.4 Maintenance: Mill body cpl.

The "0" setting of the grinding roller can be set on a scale on the rocker arm
using a fixable pointer on the mill body cover. To do this, the rollers need to
be in the lowest position. When the mill is operating, the scale moves
relative to the fixed pointer. Both the median grinding bed thickness and the
thickness variation can be read off.
After a certain operating duration, the indicator gives information about
the grinding roller wear condition.
Ensure that the door seals are replaced in time to prevent leak air entry.
Inspect the lining plates regularly for wear. Heavily damaged plates can be
replaced by less worn plates or new ones.

Component

Description

MP

OC

Mill body

Check the mill body for holes

6M

Op

Check surface coatings, look for rust formation

6M

Op

Check bolted connections for completeness and tight fitting

6M

Op

Check that all weld seams are continuous

6M

Op

Check connected piping and tubing for damage and


sealtightness

6M

Op

Check all connected electrics

12 M E

Check rubber seals for damage and wear

6M

Check measuring points for blockage

6M

Op

Check expansion joints for damage and sealtightness

6M

Op

Check linings for damage and wear

6M

Op

Check distance between adjusting screw and sensor

6M

Op

Door monitoring

Tab. 24: Maintenance table, mill body

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

159

LOESCHE Mill with Classifier


Maintenance

11.4.5 Maintenance: Table cpl.


NOTICE
Damage hazard for mill parts
Strong currents are produced during electrical welding work, which can
damage sensitive components.
The earth must be connected immediately next to the welding location
during all welding work on the grinding plant to avoid bearing damage.
It is also important to connect the earthing cable to the gearbox (see
gearbox manufacturer's documentation).
Damage hazard for grinding plates and table!
Doing operation, the table casting achieves steady state temperatures of
over 100 C. Once the mill has been switched off, do not open reject flaps
and mill doors immediately.
Allow the table to cool down to around 60 C before opening the grinding
plant to avoid thermal tension and crack formation in the table due to
exposure to cold air.
Do not use liquids to accelerate this process!

Grinding plate
The grinding plate material is very brittle. Cracked grinding plate segments
must, however, only be replaced if pieces have broken off which cause holes in
the milling route. The intended lifetime is normally achieved by wedging any
cracked grinding plate parts.
You should replace the grinding plate at the latest if the mill throughput
performance has fallen below that given in a guarantee data.
Replacing the grinding plates is not necessary if the tires are only worn.
NOTICE
Possible risk to the machine!
Only one clamping ring segment per grinding plate segment (see figure)!
Falsely fitted clamping rings lead to insufficient fixing of the grinding plate
segments. Wear to the table collar or grinding plate segment breakage can
result.
Ensure the clamping ring is correctly assembled.

160

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

X
X
1

000623

3
4
Fig. 61: Grinding plate segment alignment
Key
1 Table casting
2 Grinding plate
3 Clamping ring
4 Correct alignment (1 clamping ring segment for 1 grinding plate segment)

When hard-facing the grinding plates in the mill, observe the operating
manual for the mobile welding equipment (see manufacturer's
documentation).

Amour ring
If segments have varying levels of wear, rearrange the segments to avoid
damage to the primary gas flow and any consequential damages. This
increases the armour ring lifetime considerably.
Scatter ring (applies only to appropriate LM version)
The scatter ring should have a small a gap as possible to the appropriate
counter ring on the louvre ring.
To reduce the mill power consumption, remove the relevant scatter ring
segment and align it if it has been deformed by the presence of foreign
bodies and scrapes across the rings.
If necessary, you can set the ring a little higher by fitting washers to avoid
contact with the louvre ring.
Dam ring
Constant dam ring height around the entire table circumference is a basic
requirement for smooth mill running.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

161

LOESCHE Mill with Classifier


Maintenance

You should even out unevenness and dents which occur due to wear or
contact with foreign bodies as quickly as possible. If items are worn, the
entire metal ring wearing insert can be burnt out and replaced by a new flat
iron ring (see also "Work instructions: Assembly of dam edge", whose
number is in the parts list.
If the effective dam ring height has become larger due to wear to the
grinding parts at around half way through the mills and effective service life,
the dam ring height can be reduced to the initial effective height in order to
achieve the original specific power consumption (kWh/t) as closely as
possible.

Louvre ring
Individual louvre ring segments can be replaced. Segments with varying wear
can be exchanged with one another. The component lifetime will be increased
by such evening out.
To remove a segment, burn two short strips of metal which are welded to
the ring duct and the segment out. When inserting new segments, locate
them so that the gap between the segments is as small as possible, and fix
each segment with new metal strips to the ring duct.
Component

Description

MP

OC

Table

Check that all weld seams are continuous

6W

Clamping ring

Check for damage and wear

6W

Check fixing bolts for completeness

6W

Check bolt retainers for damage

6W

Grinding plate

Check segments for damage and wear

6W

Amour ring

Check segments for correct alignment and fixing

6W

Check for damage and wear

6W

Check segments for correct alignment and fixing

6W

Check for damage and wear

6W

Wear ring

Check for damage and wear

6W

Scatter ring

Check for damage and wear

6W

Check fixing bolts for completeness

6W

Check bolt retainers for damage

6W

Louvre ring

Tab. 25: Maintenance table, table

162

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.5.1 Auxiliary equipment: table cpl.


Removing / installing the table

1.

2.
1
9
8

10

A-A

7
6

14

13
3
2

A
12
4

000857-1

11

Fig. 62: Auxiliary equipment: table cpl.


Key
1 Hand lever pump
2 Distance holder
3 Ring duct
4 Through-passage for support
5 Gearbox output flange
6 Support pipe
7 Hydraulic jack

8 Table
9 Table in raised state
10 Table in operating state
11 Gearbox
12 Support cpl.
13

For the purpose of installing and removing the mill gearbox, the table is
released from the gearbox cover flange, then raised and supported.
Before the table is removed, the rollers must be raised and mechanically
secured or swung out (see following note on safety).

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

163

LOESCHE Mill with Classifier


Maintenance

DANGER
Heavy, moving machine parts!
The rollers must be swung out if a mechanical securing device which locks the
rollers in the raised position is not provided.
It is not permitted to hold the rollers in the top position with the aid of the spring
assembly hydraulic system.
Direct risk to life and limb by possible failure of the hydraulic system with rollers
lifted!.

a)

Removal

DANGER
Suspended loads!
Damaged supports can break.
Check that the supports are in perfect condition prior to use.
No persons are permitted to remain in the ring duct or in the grinding chamber
while the table is moving.
It is not permitted to stand under the supported table after the gearbox has been
removed.
Fence off the hazardous area without fail.
Ensure that arrangements are made between employees.

Clean the entire ring duct.


Raise the rollers and secure them mechanically using the corresponding
auxiliary equipment (see above). Swing out the rollers if a mechanical
securing device is not provided. Accident hazard (see above).
Mount the support rings on the ring duct.
Remove the cover, if fitted, from the centre of the table.
Remove the table bolts.
Flange on the hydraulic jack(s) that is/are part of the auxiliary tools after
inserting intermediate supports in the table.
Extend the jack(s) with the supplied hand lever pumps. Make sure that the
table is raised uniformly.
Repeat the procedure until the distance holders can be inserted between
the table and the gearbox cover flange. Depending on the type of
construction, the ring may have to be removed from the table seal
beforehand. Observe the information provided in the "Table cpl." drawing for
this purpose.

Note
Position the distance holders next to the jack supports (see drawing
"Auxiliaries: table cpl."). This ensures that the distance holders are evenly
distributed around the edge of the table.

164

Uniformly lower the table onto the distance holders.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

Mounting the supports

1
2

8
5

000860

Fig. 63: Support cpl.


Key
1 Upper support section
2 Ring duct
3 Guide piece
4 Retaining rod

5
6
7
8

Lower support section


Mounting plate
Foundation frame
Bolt connection between support pipes

The supports are slid into each other when delivered and stored.
Separate the support parts.

Mounting the upper support section


Remove the covers from the mounting hatches in the ring duct

Note
The positions of the mounting hatches are shown in the drawing "Auxiliaries:
table cpl.".

Bolt the guide piece to the ring duct


Slide the upper support section through the guide piece and lock it with
the retaining rods

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

165

LOESCHE Mill with Classifier


Maintenance

Mounting the lower support section


Remove the guard plates from the welded-on mounting plates on the
mill foundation.

Note
The positions of the mounting plates are shown in the drawing "Mill stand cpl.".

Position the lower support section on the mounting plate, align it and
bolt it hand-tight

Connecting upper and lower support sections


Release the upper support section from the retaining fixture
Lower the upper section onto the lower support section
Bolt both flange plates
Tighten down the fixing bolts on the foot plate of the lower support
section
Mount the remaining supports in the same way

Lowering the table


Raise the table uniformly with the hydraulic jacks. Remove all the
distance holders.
Uniformly lower the table onto the supports.
After supporting the table, remove the hydraulic jack(s). Remove the
gearbox.

b)
Installation of the tabel
Proceed in reverse order when reassembling the table.
The locating bores on the underside of the table must be positioned exactly
over the driving pins.
Lower the table without tilting in the gearbox cover flange.
Tighten and secure the table bolts in accordance with the construction
drawing "Table cpl.".

166

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.6 Maintenance: Rocker arms


Rocker arm (M) cpl.
When replacing rollers, observe the location of the separating slits in the
tapered sleeves in accordance with construction drawing "Rocker arm cpl.".
The clamping connection between fork and axle must be tight during operation.
Even minimum play in this clamping connection leads to immediate deflection of
the fork drillhole and the danger of fork breakage.
Lubricate all bearing locations continuously since lubrication interruption
leads to seizure of the bearing seats (see operating manual "Lubrication line
cpl.").
When transporting the rocker arm, use lifting brackets. They are included in
delivery and shown on the assembly drawings.
If a transparent hose is fitted to the rocker arm, check it for leaking oil. This
can run from the sealing air chamber down to the M rocker arm axle. If
leaking oil is found, check the roller slip-ring seal.
Replace the stop plate at the bottom end of the fork if it becomes deformed
due to regular contact with the spring buffer.
Rocker arm (S) cpl.
Plain bearings are provided with solid lubricant for lifetime.
In fact no further greasing is required.
check the fastening screws of the axle pins for being tight during periodical
inspections of the mill.
Lever Sealing (M) cpl.
Ensure there is a narrow gap between standing and moving parts.
Always support the rubber strips on both sides with metal strips. The rubber
strip should protrude past the metal strips by maximum 2 mm. Larger
protrusion means excessive working in the rubber and the danger of
breakage due to fatigue.
If the armour ring becomes worn, replace it in good time to protect the
sealing air seals from becoming worn externally.
Carry out regular checks for wear on the highly wear-resistant lining plates
on the sealing cap; replace them early before basic body components of the
sealing cap can be affected.
Lever Sealing (S) cpl.
Because the S rocker arm is only moved relatively infrequently, major wear is
not expected on the lever sealing.
Replace a boot if worn.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

167

LOESCHE Mill with Classifier


Maintenance

Rocker arm monitor cpl.


Before swinging out the rollers, disassemble the rocker arm monitor cpl.
Fix and adjust the rocker arm monitor cpl. after swinging the rollers back in
(in this case, please refer to Chapter "Adjusting the rocker arm monitor cpl.
in this manual).
Check electrical connections regularly and check rocker arm monitor bolts
for tight fitting.
Check the distance spacing A (see chapter "Rocker arm monitor cpl.)
regularly.
Component

Description

MP

OC

Rocker arm

Check for damage

6M

Check fixing bolts for completeness

6M

Retighten fixing bolts if necessary

6M

Check gland box for wear and tight connection

3M

Check whether the roller bearings are tightly in position

12 M M

Check bearing play

24 M M

Check lubrication level, correct

1W

Check sealing air gap to mill body

6M

Lever Sealing

Check for minimum distance to rocker arm

6M

Buffer

Check for damage and wear

3M

Rocker arm
monitor

Check correct functioning of proximity sensor

6M

Check fixing of proximity sensor

6M

Check electrical connections

12 M E

Tab. 26: Maintenance table, rocker arm

168

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.6.1 Auxiliaries: Rocker arm (M) cpl.


Installing/removing the rocker arms
Before swinging out the rollers, it is necessary to release or remove the
following connections:
Flange-sleeve connection between fork and axle
Taper-pin connection of arm and fork
Note
See also construction drawing "Rocker arm cpl.".

1
2
3
4

5
001143

Fig. 64: Flange-sleeve connection


Key
1 Flange sleeve
2 Jacking screw
3 Axle
4 Clamping sleeve
5 Rocker-arm fork

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

169

LOESCHE Mill with Classifier


Maintenance

1
2

8
3
4
5

000528

Fig. 65: Taper-pin connection


Key
1 Rocker-arm fork
2 Connecting screw
3 Cover
4 Disc springs (removed !)
5 Hexagon screw + washer

6
7
8
9

Taper pin
Cover screw
Sleeve
Central arm of rocker arm

Disassembly
WARNING
Heavy, moving machine parts!
If you do not follow the instructions, there is
danger of acute injuries and
machine parts can not be assembled.
Depressurise the hydraulic system prior to disassembly.
Release the connecting screws only after separating the taper-pin
connection.
a) Remove the taper pin
Release the cover screws and remove the cover
Remove the disc springs
Reinstall the cover with cover screws
Twist the hexagon screw with washer into the taper pin until the taper
pin is released from the sleeve
Unscrew the cover and remove the taper pin and sleeve
Slacken but do not remove the connecting screws between fork and
arm
b) Remove the flange-sleeve connection
Release and remove the fixing screws
170

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

Insert the jacking screws until the flange sleeve is released


Withdraw the flange sleeve up to the bearing block
Remove the connecting screws between fork and arm

Assembly
Note

Ensure conditions of absolute cleanliness and use assembly grease during


assembly operations

a) Insert the connecting screws between fork and arm hand-tight


b) Establish the flange-sleeve connection
Remove the jacking screws without fail
Prior to assembly degrease all the seating surfaces and treat with anitcorrosion agent
Firmly tighten the flange sleeve using the fixing screws
c) Establish the taper-pin connection
Slide the sleeve with slot downwards into the bore for arm and fork
Tighten the connecting screws to the torque specified in the drawing
"Rocker arm cpl.
Guide the taper pin into the sleeve
Lay the disc springs on the taper pin and tighten the cover and cover
screws up to the stop

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

171

LOESCHE Mill with Classifier


Maintenance

11.4.7 Maintenance: Roller


NOTICE
Component breakage hazard!
All parts must be regularly checked for radiation or impact abrasion and
must be replaced if necessary.
Repair welding may only be carried out in consultation with the
manufacturer as far as possible.

S-roller
When the S roller is removed, it is swung out together with the mill body cover
(see "Swinging device cpl." assembly).
Note
Only in case of clamping sleeve connection!
Observe during assembly the drawing information on the position of the slits in
the conical sleeves. The slit in the taper sleeve must be caulked gas-tight with
lead in accordance with the design drawing ("Rocker arm (S) cpl.") so that no
sealing gas can escape or so that no dust can enter.

172

Check the slip-ring seal regularly (see "Slip-ring seal cpl.")

Oil level - check using the oil dispstick supplied


The dipstick features 2 markings. The lower marking applies to new grinding
parts, the upper marking to worn grinding parts. Top up oil to the upper
marking no later than after 3000 operating hours.

Checking the roller bearings


1. Close off the drill hole in the roller axle to prevent oil discharging from
this area
2. Bring the S roller into the vertical position using the swinging device
3. Remove the hub cover, check the bearings
4. When you refit the hub cover, you must always fit a new O-ring. You
may only use cast O-rings in accordance with the parts list
specifications.
5. Tighten the cover bolts in accordance with information in the drawing
and secure the bolts.
6. The inspection cover in the hub cover can be opened to enable the
spherical roller bearing to be inspected occasionally. Make sure when
reattaching the cover that it is adequately sealed and secured.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

M-roller
Ensure the mill is running smoothly (tight closing of sliders and flaps in gas
piping; dam ring height...).
Ensure the dam ring height remains at the same height above the milling
route around its whole circumference
Set the roller force in accordance with the spring diagram
Check the effectiveness of sealing air sealing by placing the flat of your
hand on the drillholes leading outwards from the sealing cap through the
rocker arm. Your hand must be noticeably sucked in if the sealing function
is correct. If this is not the case, either the gap between the sealing sleeve
and the sealing cap on the rocker arm has become too large due to wear, or
the sealing cap has become soiled with dust on the inside.
In the first case, the 2-part rings on the sealing sleeve which form the
rinsing air gap must be replaced; In the second case, these spaces should
be cleaned out as quickly as possible by removing the complete rollers,
otherwise there is serious danger of damage to the roller bearings.

Removing the roller


1 Swing the roller out of the mill together with the rocker arm
2 Release the clamping sleeves in accordance with the "Auxiliary
equipment cpl." instruction manual
3 When reassembling, note the location of the slits in the conical clamping
sleeves in accordance with the drawing
4 Caulk the slits in the taper sleeve in accordance with the group drawing
("Rocker arm (M) cpl.") gas tight with lead so that no sealing gas can
escape or so that no dust can enter.

Checking the roller bearings:


1 Close off the sealing air drill hole in the roller axle in accordance with
information on the drawing to prevent oil discharging from this area.
2 Bring the roller into the vertical position using the swinging-out device.
3. Remove the hub cover, check the bearings
4. When you refit the hub cover, you must fit a new O-ring in each case.
You may only use cast O-rings in accordance with the parts list
specifications.
5. Tighten the cover bolts in accordance with information in the drawing
and secure the bolts.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

173

LOESCHE Mill with Classifier


Maintenance

Slip-ring seal (M- and S-rollers)


NOTICE
Possible risk to machine!
Note limit temperature!
Exceeding the contractually agreed limit temperature for the male leads to
hardening of the elastomer O-rings and therefore to early failure of the seal.
The slip-ring seal is a wear part, and therefore leads to be replaced regularly (at
the latest before each major change) to avoid damage to the roller bearings due
to leakage.
The condition of the slip-ring seal can only be checked indirectly. When the
rollers are swung out, the oil runs downwards out of the roller bearing space
through the central drillhole in the axle.
If the drained-off oil has heavy colouring due to microscopic suspended
particles, it is possible that the slip-ring seal is worn.
In this case, disassemble the rollers and check the condition of the slip ring.
Slip rings should only be replaced as pairs.
Tire
A tire profile ruler has been supplied with the "Auxiliary equipment cpl."
assembly for checking roller tire wear. You can find information about setting it
up and using it in the chapter "Auxiliary equipment: Tire profile ruler".
When hard-facing the roller tire, observe the instruction manual for the
mobile welding equipment (see manufacturer's documentation).
Component

Description

MP

OC

Tire

Check for damage and wear

6W

Check bolt retainers for damage

6W

Check for ease of rotation

6W

Check distance between roller and milling route, adjust if


necessary

6W

Check distance between tire and wear ring

6W

Check oil level and top up if necessary

6W

Check for oil leakages

6W

Check guard for damage, wear and correct fixing

6W

Check to see whether material is located between guard and


roller axle

6W

Check to see whether sealing air gaps are blocked

6W

Roller axle

Tab. 27: Maintenance table, roller

174

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.7.1 Auxiliaries: Roller (M) cpl.

30

30

9
8

10

7
5
001142

Fig. 66: Auxiliary equipment: roller (M) cpl.


Key
1 Roller (M)
2 Eye bolt
3 Rocker arm (M)
4 Block (see swinging device cpl.)
5 Hand pump

6
7
8
9
10

Hydraulic jack
Support
Claw ring
Distance ring
Ring

Disassembly/assembly of the roller


a)
Disassembly
To dismantle the rollers, in other words to pull the rollers out of the rocker arm,
lifting eye nuts and/or eye bolts are provided. Please see the drawing entitled
"Auxiliaries: roller cpl." for details.
swing out rollers
screw eyebolts into hub cover
loosen and remove fixing bolts on roller axle
bolt ring onto claw ring
bolt hydraulic pressing cylinder into ring
use hand lever pump from spammer assembly aids to press roller axle out
of rocker arm
use crane to pull rollers out of lever.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

175

LOESCHE Mill with Classifier


Maintenance

b)

Assembly

Note

Clean clamping sleeve bracing surfaces and treat with roller bearing
lubricant to prevent fretting corrosion

Align notches on front face of roller axle in accordance with drawing "Roller
cpl."

Caulk slots in taper sleeve in accordance with drawing "Rocker arm cpl."
with lead

Refitting generally takes place in reverse sequence.


The roller should be fixed in a position stated on drawing "Roller cpl.".
If a temperature sensor is fitted, see "Roller temperature monitoring cpl."
operating manual.

5
2

000855

Fig. 67: Auxiliary equipment: roller cpl., roller bearing removal


Key
1 Hand pump
2 Hub
3 Roller axle with bearing

176

4 Jacking screw
5 Bearings

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

Removing the roller bearings


A so-called hydraulic brace is provided to facilitate removal of the roller bearings
from the roller.
Pump highly viscous oil into the channels in the roller bearing seat using the
hand lever pump which is required for disassembling the table and roller.
The oil expands the bearing seat in its hub, which simplifies disassembling the
bearing.
To disassemble the bearings, connect a hose with the appropriate bore hole
in the hub. This is normally plugged with a threaded plug (see drawing
"Roller cpl.").
Screw bolts into the hub bores to press the roller bearings out of the bearing
seats.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

177

LOESCHE Mill with Classifier


Maintenance

11.4.7.2 Auxiliaries: Roller (S) cpl.

1
max. 30

2
3

000785

Fig. 68: Auxiliary equipment: roller (S) cpl.


Key
1 Hand pump
2 Upper roller bearing
3 Hub
4 Lower roller bearing

Disassembly of roller bearings


A so-called hydraulic brace is provided to make disassembling the roller
bearings from the roller easier.
Pump highly viscous oil into the channels in the roller bearing seat using the
hand lever pump which is required for disassembling the table and roller.
The oil expands the bearing seat in its hub which simplifies disassembling the
bearing.
To disassemble the bearings, connect a hose with the appropriate bore hole
in the hub. This is normally plugged with a threaded plug (see drawing
"Roller cpl.").

178

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.7.3 Auxiliary equipment: lifter cpl.

2
5
3

001145

Fig. 69: Lifter cpl.


Key
1 Chain
2 Hook
3 Holder

4 Hub
5 Tire
6 Lug at holder

The tire is raised for installation or removal with the lifter and hoisting gear. The
load-bearing capacity corresponds to the weight of a new tire.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

179

LOESCHE Mill with Classifier


Maintenance

Changing the tire


DANGER
Lifted loads!
Misuse may lead to danger for life due to falling loads.
Check that the lifter is in perfect condition prior to use.
Do not under any circumstances exceed the lifter's maximum load-bearing
capacity (see drawing "Lifter cpl.").
Use the lifter only to transport the tire.
It is not permitted to raise the roller with the lifter.
Do not stay under lifted loads
The roller tire and the hub are designed with a small clearance so that assembly
and dismantling can be easily accomplished.
On assembly, the roller tire must have at least the same temperature as the
hub. If this is not the case, the tire may be gently warmed with a soft flame or
heating blankets in the area of the cylindrical seat until it has attained a
temperature of 30 to 40C above that of the hub.

3
4
6

001366

Fig. 70: Changing the tire


Legende
1 Tire
2 Clamping ring
3 Tee head bolt

180

4 Disc spring
5 Nut
6 Flat bar

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

Dismantling
Swing the roller with rocker arm out of the mill
Release the nuts of the tee-head bolts
Remove the tee-head bolts and roller clamping ring
Release the tire from the hub. To do so, heat the tire evenly over its entire
circumference by 30 to 40 C with a weak flame or a heating blanket
Remove the now loosened tire from the hub with the lifter

Assembly
If necessary, warm the cylindrical seat of the tire as described above.
The assembly of the tire is accomplished in the reversed sequence like the
dismantling.
Tighten finally disc spring up to block
Turn back nut by 40 and secure it with flat bar

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

181

LOESCHE Mill with Classifier


Maintenance

11.4.7.4 Auxiliary equipment: tyre profile ruler cpl.

10

001144

3
Fig. 71: Tire profile ruler cpl.
Key
1 Profile ruler
2 Tire
3 Hub
4 Holder

Check the wear of the grinding parts in accordance with the maintenance
schedule so as to be able to provide clear statements about the anticipated
service life and to provide comparisons of the grinding-stock and wear-part
quality during replacement.
Comparable measurements can be performed with the tire profile ruler.
Mount the tire profile ruler as shown in the drawing "Tire profile ruler cpl.".
Adjust the ruler during the first measurement to a distance of approx.
10 mm to the tire surface.
This distance vary slightly on new tires on account of the unfinished-casting
tolerance. The actual distance when new must be noted down and subracted
from the respective profile (tread) depths.
Document the measured values.
Note
We recommend our pre-printed form 3.F 1158 for documenting and
evaluating the measurement results.

182

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.7.5 Auxiliaries: Oil drain device cpl.


Oil drain device for the grinding roller

X
5

6
5

001146

Fig. 72: Oil drain device (M) cpl.


Key
1 Roller swung in
2 Oil drain hose
3 Sealing nipple
4 Roller swung out

5 Plug
6 Adaptor
7 Quick-release coupling

During the swinging-out movement of the roller, the oil, intended for the
lubrication of the roller bearings, returns through the breather bore of the roller
axle. The swinging-out procedure should be slow enough to give the oil
sufficient time, even at low temperatures and high viscosity, to flow to the rear
end of the roller axle.
Conversion Sequence:
Disconnect the two hoses from the rear end of the roller axle.
Remove all three adapters.
Install the new adapter with sealing ring, the two fittings and the self-sealing
coupling into the upper right hand tapped hole.
Seal the two remaining holes with plugs and sealing rings.
P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

183

LOESCHE Mill with Classifier


Maintenance

After swinging-out the roller, fit the selfsealing coupling onto the oil suction
hose (larger diameter) and connect to the previously fitted coupling on the
axle.
Whilst the oil flows away to the tank the upper left plug must be removed to
allow air to replace the oil.
Watch the oil level in the sight class of the HSMS. When it ceases to rise
the bulk of the oil will have been drained from the roller.

Note
More information can be seen in the drawing "Oil Drainage cpl.".

Oil drain device for the support roller

1
2
3

000526

Fig. 73: Oil drain device cpl.


Key
1 Slide
2 Roller axle
3 Transparent hose
4 Collecting container

When the roller is swung out, the oil which lubricates the roller bearings flows
back through the central bore of the roller axle.
Remove the wet air filter.
Install the adaptor and the gate valve.
Install the slide with a transparent hose.
The oil return flow can be observed through the hose.
Feed the hose into a collecting container of sufficient size.
The size of the collecting container can be determined using the LOESCHE
lubricant table.
Swing out the roller slowly so that the oil, even at low temperatures and with
high viscosity, has sufficient time to flow to the end face of the roller axle.
Refill the mill with the drained oil or with fresh oil prior to start-up.
184

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.8 Maintenance: Spring assembly cpl.


WARNING
Hydraulic overpressure!
Possible serious injuries
To prevent accidents, any maintenance work on a hydraulic system may
only be carried out once the oil pressure has been completely relieved.

Lubrication
The rod head and hydraulic cylinder roller bearings are kneaded full of grease.
Re-greasing the bearing takes place using a hand grease gun on the grease
nipples at long periods in accordance with the maintenance table.
The piston and piston rods in the hydraulic cylinder are lubricated automatically
by the hydraulic oil. The maintenance table also applies to oil changes in this
case.
Leaked oil
Lubricant replacement takes place according to the information in the
maintenance table.
Leaked oil from the piston rod-sided working space which flows past the piston
seals is automatically transported back into the tank via the piston-sided
cylinder space by piston movements. If leaked oil quantities become too large,
this can be seen in the shortened switch-on intervals used by the high-pressure
pump because the working pressure is dissipated very quickly. In this case, the
seals need to be replaced on the piston.
Leaked oil in the piston rod movement area of the cylinder is visible from
outside and points to wear in the sleeve gaskets.
Couplings
Check all hose, tube and flanged couplings regularly.
Since the hydraulic piping is subject to pulsating pressure, it is possible that
some couplings will loosen during operation.
Always retighten loosened couplings immediately.
Hoses
Check hoses in the cylinder area, especially after fitting work, for external
damage or ageing cracks. Replace them if necessary.
Hydraulic accumulator
The hydraulic accumulator is supplied with a gas filling pressure of 1 MPa
(=10 bar) so that the oil valve located in the floor can be closed safely and so
that the oil chamber is protected against the penetration of foreign bodies. You
can find more information in the separate HSLM operating manual.
Hydraulic cylinder
The hydraulic system needs to be depressurised before carrying out any
maintenance work on the hydraulic cylinder. Once the covers have been
removed from the mill stand, the bolts can be pulled out of the hydraulic
P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

185

LOESCHE Mill with Classifier


Maintenance
cylinder. After this, take the bolts out of the rod head in a similar manner,
uncouple the hydraulic piping and dismantle the hydraulic cylinder. Please see
the manufacturer's documentation for more information.
Roller bearings
If there is bearing damage to the rod head or a rod end bearing on the hydraulic
cylinder, the corresponding bearing bolts must be drawn.
The spherical roller bearing seat on the bolts should be treated with roller
bearing lubricant when replacing bearings so that removing the bolt is made
easier. Otherwise, roller bearings are maintenance-free.
Component

Description

MP

OC

Piping

Check fixings

6M

Check for rust and surface damage

6M

Check connections for tight seating and safety

6M

Check fittings for tight seating and sealtightness

6M

Check hoses for wear

6M

12 M M

Check rod head seals

6M

Check leakage oil container, empty if necessary

1W

Check bearing fixing bolts for tight seating

12 M M

Check bearing play

24 M M

Lubricate bearing

1W

Check base eye

6M

Check clamping nut bolts for completeness and tight seating

6M

Check boot for tight seating

6M

Check boot for damage

6M

Lubricate rod head

1M

Hydraulic cylinder Check fixings

Tab. 28: Maintenance table, spring assembly

186

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.8.1 Auxiliaries: Spring assembly (M) cpl.


WARNING
Hydraulic overpressure!
Direct risk to life and limb
To prevent accidents, all maintenance works are only permitted when the
hydraulic system (HSLM) is depressurised!
Crushing hazard!
The tasks described pose a potential crushing hazard between the springassembly cylinder and the pedestal or the mill stand.
Ware personal protective equipment.
Ensure that there is a sufficient spacing.

NOTICE
Possible risk to the machine!
Observe the drawing "Auxiliary eqpt.: spring assembly, cpl." without fail in
order to avoid personal injury and/or machine damage.
Make sure when using spindles that the collar nut is correctly aligned during
removal and installation.
Before the clamping nut is reassembled, the spring rod has to be extended
with the provided auxiliary to the dimension given in the drawing.

The work sequences of disassembly and assembly of the bolts, rod heads and
the hydraulic cylinders are described step by step in the detailed drawings
"Aux.: Spring Assembly (M); cpl.".

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

187

LOESCHE Mill with Classifier


Maintenance

11.4.8.2 Auxiliaries: Spring assembly (S) cpl.


The pins for connecting the hydraulic cylinders of the S spring assemblies to the
S rocker arms and the covers of the mill body can be easily removed and
installed using the auxiliary equipment.
Note
The spindle used as a tension or thrust rod should be treated with grease prior
to use so as to ensure smooth handling.

Dismantling

2
3

000529

Fig. 74: Dismantling the spring pin


Key
1 Rocker arm (S)
2 Bell housing
3 Collar nut
4 Spindle

5 Disc
6 Spring pin
7 Hand pump

In the event of roller bearing damage and when dismantling the hydraulic
cylinder, the pins must be pulled out of the respective bores.
The seat of the spherical roller bearing on the pin can be hydraulically
expanded using the oil injection expansion method:
Remove the discs with the bolts which are located in the pin at the end face.
Connect the hand pump (included in the delivery specification) via a hose to
the pin at one end.
Then force the pin out of the bores using the supplied device. Support the
procedure hydraulically with the hand pump.

188

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

Assembly

000530

Fig. 75: Assembling the spring pin


Key
3 Collar nut turned!

The pin is reassembled with the same device, with the collar nut inserted on the
other side.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

189

LOESCHE Mill with Classifier


Maintenance

11.4.9 Maintenance: Hydraulic accumulators


Mineral oils release certain quantities of gases which can discharge from the
mill during operation.
Since this air bubble formation can lead to damage to hydraulic components,
the hydraulic system needs to be regularly vented after initial start-up (monthly).
The gas quantity is operationally and medium-dependent. For this reason, the
intervals between venting measures must be adapted to the operating
conditions.
Measuring connections located in several locations around the hydraulic system
are used for venting (e.g. cylinder, accumulator etc. - see assembly drawings).
The venting process must be carried out until gas-free oil discharges!
Technical monitoring of pressure tank
Hydraulic accumulators are pressure tanks and must be subjected to a pressure
test at regular intervals, which must be carried out in accordance with the
relevant regulations for the country of use by a technical monitoring body. In
most countries, monitoring of pressure accumulators and equipment operated
with pressure accumulators is prescribed. This must be carefully observed.

Bladder accumulator
For mill operation, the bladder accumulator is filled with nitrogen from standard
steel bottles with the help of a special filling device which is included in delivery.
The filling pressure can be read off from the pressure gauge fitted to the filling
unit. As delivered, the accumulators are normally filled with sufficient nitrogen
filling pressure so that the rubber bladder fills up the entire steel enclosure, in
other words is lying in close contact with the enclosure and closes the oil-sided
mushroom valve. This prevents penetration of dirt into the hydraulic working
space in the accumulator. You must ensure that the gas valve is sealed off via
the shut-off cap belonging to the accumulator. The gas valve alone does not
seal off sufficiently tightly.
Filling up with gas
DANGER
Explosive materials!
Only nitrogen gas (N2) has to be used to fill up the rubber bladder in the
accumulator or in the piston accumulator.
The nitrogen gas (N2) purity has to be at last 99,995 %, filtered < 3 m.
Oxygen or air could cause explosions in connection with oil.

190

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

Setting the valve (for N2 filling pressure checked and N2 pressure


increase)
To check the correct nitrogen filling level both for the hydraulic bladder
accumulator and the hydraulic piston accumulator, it is absolutely imperative
that the pressure on the oil side is completely vented. For this purpose:
set the main switch to the "manual operation" position",
open the stopcock in accordance with the function table on "Scheme:
hydraulic HSLM ...".
If this rule is not observed, the incorrect N2 pressure will be displayed or filled
up. In addition to this, the accumulator bladder can be destroyed.
Checking interval for controlling gas filling pressure
After initial start-up, the gas pre-filling pressures in the bladder accumulator
must be checked at regular intervals and corrected if necessary.
After the 1st week;
After the 4thweek;
After the 3rd month;
Half-yearly.
Component

Description

MP

OC

Bladder
accumulator

Check pressure, refill with NITROGEN (N2) if necessary (see


above)

3M

Check bladder sealtightness

12 M M

Check to see that connections are tight and correctly


positioned

12 M M

Check bottle for tight seating and correct position

12 M M

Check bottle for rust damage and wear

12 M M

Check to see that valve is secured, tightly seeded and


undamaged

12 M M

Tab. 29: Maintenance table, bladder accumulator

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

191

LOESCHE Mill with Classifier


Maintenance

Piston accumulator
Filling of the top piston accumulator with nitrogen takes place in a similar
manner. For more information, see manufacturer's documentation for the
"Spring assembly cpl." assembly in the mill.
It is possible that gas losses can occur due to operational conditions at the
piston accumulators, and on the other hand oil can be transported to the gas
side by the piston movement. For this reason, the following checks should be
carried out at regular intervals:
Checking the gas pre-filling pressure in the piston accumulator:
if there is a pressure loss of 30 % of the original filling pressure, only one
refilling is necessary.
if there is a pressure increase of 30 % of the original filling pressure,
there is a danger that oil is present in the gas-side accumulator space
Checking procedure:
1 Vent the gas completely using the fill and test unit. Open the valve screw by
1.5 turns.
2 Remove the fill and test unit.
3 Fit a plastic hose (provided by customer) over the gas valve body. Put the
free end in a collecting trough (provided by customer).
4 Press the "Raise rollers" button on the hydraulic cabinet. If the pump is
running, the accumulator piston will be moved upwards and presses the oil
out of the gas-side space.
5 Remove hose, fit fill and test unit and refill the accumulator with gas again
(see chapter "4.3 Filling the hydraulic accumulator").
6. Checking intervals:
After the 1st week;
After the 2nd week;
After the 4th week;
monthly;
After the 6thmonth - half yearly.

192

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.9.1 Auxiliary equipment: Fill and test unit cpl.


DANGER
Explosive materials!
Only nitrogen gas (N2) may be used to fill up the rubber bladder in the
accumulator or in the piston accumulator.
Oxygen or air can cause explosions in connection with oil.

This device is a combined item of auxiliary equipment for filling the bladder and
piston accumulators with nitrogen and a measuring instrument.
The gas pressure in the hydraulic accumulators can be measured with the aid
of the fill and test unit. Filling and gas-pressure measurement may only be
carried out after the oil pressure has been reduced (see supplier's instruction
manual).

Note
The fill pressure of the bladder accumulators must be selected in correct relation
to the hydraulic working pressure. Refer to the "Diagram: spring stiffness" for the
permissible limit values (see documentation parts list "HSLM").

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

193

LOESCHE Mill with Classifier


Maintenance

11.4.10 Maintenance: Hydraulic cabinets


WARNING
Hydraulic overpressure!
Possible serious injuries
To prevent accidents, any maintenance work on a hydraulic system may
only be carried out once the oil pressure has been completely relieved.

Hydraulic oil
Use only the specified hydraulic oil in accordance with LOESCHE
recommendations. The cleanliness class of the hydraulic oil used should
meet the requirements of ISO 4406 19/17/14 at the very least.
Observe the specified oil change intervals.
Always fill the hydraulic system using a suitable filtering system (which
meets the specified cleanliness class) with fresh oil.

Component

Description

Hydraulic cabinet

Check for damage

12 M M

Op

Check for rust and surface damage

12 M M

Op

Function check

12 M M

Op

Check for easy running

6M

Op

Check oil level and correct if necessary

3M

Check oil quality, replace if necessary

6M

Check all connections for tight seating

6M

Op

Check filter for deposits and damage

6M

Replace filter

6M

Check for easy running

3M

Op

Check warm start-up

3M

Op

Check correct fixings

3M

Lubricate bearing

3M

Check cooling air connection for cleanliness

3M

Check electrical connections

12 M E

Function check

12 M M

Op

Check for leaks

12 M M

Op

Check for damage

12 M M

Op

Check 0 point when depressurised

12 M M

Pump

Motor

Pressure gauge

194

MP

OC

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

Component

Description

Solenoid valve 7.x Function check

Valve 5.x

MP

OC

12 M M

Op

Check for tight seating

12 M M

Op

Check for damage

12 M M

Op

Check electrical connections

12 M E

Op

Function check

12 M M

Op

Check for tight seating

12 M M

Op

Check for damage

12 M M

Op

Check electrical connections

12 M E

Op

Tab. 30: Maintenance table, hydraulic cabinet

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

195

LOESCHE Mill with Classifier


Maintenance

11.4.11 Maintenance: LM-Drive


NOTICE
Possible risk to the machine!
Strong currents are produced during electrical welding work, which can damage
sensitive components.
The earth must be connected immediately next to the welding location during all
welding work on the grinding plant to avoid bearing damage.
It is also important to connect the earthing cable to the gearbox (see gearbox
manufacturer's documentation).

Component

Description

MP

OC

Motor

Check for easy running

6M

Op

Check warm start-up

6M

Op

Check fan

12 M M

Check electrical connections

12 M E

Op

Lubricate bearing

6M

Op

Check motor fixing

3M

Op

Check slip ring for wear

12 M E

Check carbon brushes for wear, replace if necessary

12 M E

Check rectifier for wear

12 M E

Check for easy running

6M

Op

Check temperature

6M

Op

Check oil level and top up if necessary

3M

Check coupling for wear, check alignment

6M

Check electrical connections to the thermoelement connected

12 M M

Check clearance X (gearbox output flange to gearbox


housing)

12 M M

Check all connected pipes and hoses for damage

6M

Check all connected tubes and hoses for tight seating

6M

Op

Gearbox

Tab. 31: Maintenance table, LM drive

196

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.12 Maintenance: Gearbox lubrication unit

Component

Description

MP

OC

Low pressure
pump

Function check

3M

Op

Check for easy and constant operation

3M

Op

Check for leaks

3M

Op

Check connections are tight

3M

Op

Check for leaks

6M

Op

Check filter for deposits and damage

6M

Function check

3M

Op

Check for easy and constant operation

3M

Op

Check for leaks

3M

Op

Check connections are tight

3M

Op

Check for ease of movement

12 M M

Op

Check for warm running

12 M M

Op

Check ventilation grille

12 M M

Lubricate bearing

3M

Check electrical connections

12 M E

Check motor fixing

12 M M

Function check

12 M M

Op

Check for leaks

12 M M

Op

Check 0 point when depressurised

12 M M

Temperature
monitoring

Function check

12 M M

Op

Pressure switch

Function check

6M

Op

Check for leaks

6M

Op

Check piping fixings for sealtightness

6M

Op

Check electrical connections

12 M E

Function check

6M

Op

Check for leaks

6M

Op

Check piping connections for tight seating

6M

Op

Check electrical connections

12 M E

Check for damage and sealtightness

6M

Check piping fixings for sealtightness

6M

Filter
High-pressure
pump

Pump motors

Pressure gauge

Flow meter

Expansion joint

Tab. 32: Maintenance table, gearbox lubricating unit

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

197

LOESCHE Mill with Classifier


Maintenance

11.4.13 Maintenance: Central lubrication unit

If there is mechanical damage to the pipes, rectify this immediately. Check


hoses regularly for good condition. Replace them if necessary.
Fill up the grease container in the lubrication pump regularly with the grease
specified in the lubrication table.
Ensure that the grease container cover is closed tightly to prevent
penetration of dust.

Component

Description

MP

OC

Lubrication unit

Check lubrication lines for sealtightness

6M

Op

Check piping fixings for sealtightness

6M

Op

Check hoses for damage

6M

Op

Check lubrication points for sufficient supply

1M

Op

Function check

3M

Op

Check pump delivery rate

3M

Op

Check fill level of lubricant container, refill if necessary

6M

Op

Check for damage

6M

Op

Check the sealtightness of all connections

1M

Op

Check for leaks

3M

Op

Check the sealtightness of the gland box or slip ring

3M

Op

Check for ease of movement

3M

Op

Check for warm running

3M

Check motor fixing

3M

Lubricate bearing

3M

Check cleanliness of cooling air inlet

3M

Check electrical connections

12 M E

Lubrication pump
unit

Motor

Tab. 33: Maintenance table, central lubricating unit

198

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.14 Maintenance: Sealing air system


The pressure in the sealing air system is monitored by the "sealing air
monitoring" unit. It triggers an alarm if there are irregularities in the sealing air
flow. Possible causes for an alarm and the measures for rectification are
described in the "Sealing air monitoring cpl." operating manual.
Check the wear rings by remeasuring the diameter for wear if the rollers are
disassembled during major inspections.
Replace worn wear rings otherwise the sealing air gap will be too large. The
resulting insufficient "sealing air sealing" can lead to the entry of foreign
bodies and to subsequent damage to the roller bearings or the slip-ring
sealing.
Component

Description

MP

OC

Fan

Check for smooth operation

1M

Op

Check connections for damage and tightness

1M

Check fan grill for existence and fixing

1M

Check absorber elements for wear

6M

Check shaft cover plate for existence and fixing

1M

Check silencer for damage

3M

Lubricate bearing

3M

Check for easy running

12 M E

Op

Check warm start-up

12 M E

Op

Clean grills

12 M E

Check electrical connections

12 M E

Check motor fixing

12 M E

Check for damage and fastening

3M

Motor

Coupling

Tab. 34: Maintenance table, sealing air system

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

199

LOESCHE Mill with Classifier


Maintenance

11.4.15 Maintenance: Piping system


WARNING
Hydraulic overpressure!
Possible serious injuries
To prevent accidents, any maintenance work on a hydraulic system may
only be carried out once the oil pressure has been completely relieved.

Maintenance on the piping is restricted to checks for sealtightness.


Sealing of compression joints must take place in accordance with the
manufacturer's instructions.
If new welded piping is used, this must be de-burred and de-scaled and
preserved immediately after cleaning.
Test pressure: 210 bar, 2 hours!

11.4.16 Maintenance: Swinging device


NOTICE
Possible risk to machine!
After use, hang up the hydraulic cylinder vertically or deactivate it.
Otherwise the piston weight can permanently deform the sleeve gaskets which
leads to lack of sealtightness.

Before swinging out, always check the bolts and joint seatings for damage
and rust pocks.
Do not disconnect the swinging cylinder from the roller during roller
dismantling
Protect the hydraulic cylinder and its piston rod from external damage.
Keep high-pressure hoses in a place where they cannot be damaged. Only
use hoses with a burst pressure of more than 200 bar.

Component

Description

Cylinder

Function check

12 M M

Op

Check for leaks

12 M M

Op

Function check

12 M M

Op

Check hydraulic oil fill level, refill if necessary

12 M M

Check hoses and connections for damage and sealtightness

12 M M

S/Op

HSAV

MP

OC

Tab. 35: Maintenance table, swinging device

200

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

11.4.17 Maintenance: Grinding bed sprinkler cpl.

Check the sprinkler pipes regularly for damage and free drillholes.
They can be pulled from the outside out of the pipe holder for this purpose.
If this is not possible, the pipe must be inspected inside the mill and if
necessary repaired. Deposit build-ups should be removed if necessary. If
replacement is necessary, the pipe can be cut through at the end of the pipe
holder where necessary and the remainder pulled from the outside out of
the holder.
Protect the water hoses against mechanical damage. Replace them if
necessary.
Reseal the screw connections after repairs with sealing tape or hemp.
Regularly check the pipe holders on the mill body for tight fitting.

Component

Description

MP

OC

Grinding bed
sprinkler

Check sprinkler pipes for damage

1M

Check sprinkler pipes for free drillholes

1M

Check hoses for damage and sealtightness, replace if


necessary

3M

Check pipe holders for tight seating

3M

Tab. 36: Maintenance table, grinding bed sprinkler

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

201

LOESCHE Mill with Classifier


Maintenance

11.4.18 Maintenance: Classifier

Carry out regular visual checks of the machine for early detection of any
possible damage.
Checked all screwed/bolted connections regularly for secure seating. Treat
all bolted threads with corrosion protection to prevent fretting corrosion and
corrosion.
Always remove deposits of grinding material from rotating parts
immediately.
Carry out regular checks on the lining (not standard) the blades and the
guide vanes for wear. The covers in the classifier upper and lower housings
should be opened or removed to carry out visual checks.
In the case of large classifiers with accessible rotors, worn blades and guide
vanes should be replaced from the inside of the rotor. The blades should be
partially disassembled in order to replace the guide vanes.
In the case of smaller, non-accessible classifiers, either the rotor or the
guide vanes or the guide vane support segments must be lowered into the
interior of the mill in order to replace worn blades and guide vanes. In both
cases, the multiple-part grit funnel must be removed and if necessary the
rollers swung out.
If the blades are replaced, the rotor should be checked for sufficient
balance. To do this, the blades are weighed individually and sorted so that
each 2 strips of similar weights are mounted in opposing positions.
When maintaining the bearings, ensure that the rotary shaft seal has the
correct installation position in accordance with information on the drawings.
During inspections, carry out regular checks to see that there is a sufficient
grease collar on the rotary shaft seal on the rotor bearings. This will ensure
that the bearing is lubricated sufficiently.
When replacing the guide vane supports, ensure that the nuts are secured
with tack welds after tightening.

Exchange of the classifier guide vanes, large classifier


Dismantling
Remove the inspection cover in the upper body of the classifier to gain
access to the inside of the rotor.
Grind off the tack-welds which secure the nuts
Remove the screws on the guide vanes
Remove the guide vanes from their carriers

Assembly
The assembly of the guide vanes is accomplished in the reversed sequence to
that of the dismantling.
Tighten the screws of the guide vanes to the torque quoted in the drawing
"Guide vanes cpl.".
Secure the nuts with a tack-weld.
Reinstall and secure the blades of the rotor.
Rhombic hardfacing can slow down further wear on slit guide vane supports.

202

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Maintenance

Component

Description

MP

OC

Housing

Check connections are tight

6M

Check paint finish for damage

6M

Check outside for rust

6M

Check weld seams are continuous

6M

Check for ease of movement

6M

Check lubricant level and top up if necessary

6M

Check bearing play

6M

Check alignment and fastening

6M

Check for wear

6M

Check blades for damage and wear

6M

Check for imbalance

12 M M

Check for damage and wear

3M

Check bolted connections

6M

Remove deposits

6M

Check for ease of movement

6M

Check for warm running

6M

Check lubricant level and top up if necessary

1M

Change lubricant

12 M M

Check for leaks

12 M M

Check thickness of coupling discs

6M

Check alignment

6M

Check fastening

6M

Check for ease of movement

3M

Check for warm running

3M

Check fastening

3M

Lubricate bearing

3M

Check cleanliness of cooling air inlet

3M

Check electrical connections

12 M E

Bearing cartridge

Guide vane
Rotor
Grit funnel

Gearbox

Coupling (clutch)

Motor

Tab. 37: Maintenance table, classifier

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

203

LOESCHE Mill with Classifier


Maintenance

001383

11.5 Checks after maintenance work

Carry out a visual inspection in the electrical switching cabinet. Check:


the wiring for kinks, abrasions and burns,
the covers and insulation for damage,
the switching cabinet doors for ease of movement.
Check if the protection conductor connections are tight.
Make sure the repair work has actually been completed.
Make sure that there are no tools in the machine and carry out a function
test of the machine.
Remove all tolle that you used for the maintenance work
Carry out a function check of all the assemblies in Set-up mode and Manual
mode.
After checking and replacing spare parts and wearing parts, check the
functionality of the installed safety systems (see Chapter "Installed safety
systems Page 36").

When all the functions are fault-free, the machine is handed over to the
operator.

204

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Spare parts

12 Spare parts
We expressly point out those spare parts and accessories which are not
supplied by us were also not examined by us and released. The installation and
/ or use of such products may therefore affect the constructive given
characteristics of your machine in a negative manner. For damage caused by
the use of non-original parts and non-original equipment parts, the liability of the
company LOESCHE GmbH is excluded.
We recommend using only original LOESCHE spare parts for your own safety.
Standard parts may be purchased from specialized dealers.
Please refer to the spare parts lists for information concerning the spare
parts.
Order information
In order to avoid mistakes when ordering spare parts, please state the drawing
number and the item number or send in a sample of the required spare part.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

205

LOESCHE Mill with Classifier


Decommissioning, dismantling and disposal

13 Decommissioning, dismantling and disposal


13.1 Qualifications of dismantling personnel
Only (skilled) personnel who have undergone the requisite instruction/training
are permitted to dismantle the machine in accordance with the instruction
manual.
Specialist skilled personnel need to be deployed for certain specialist areas,
e.g. hydraulics and electrical engineering.
13.2 Requisite conditions for dismantling

You must run the machine completely empty (or, if it is part of a plant, as far
as necessary) prior to dismantling.
Remove general evidence of soiling. Components soiled with hazardous
substances will need to be cleaned thoroughly.
Set the main switch to "OFF" and lock it in this position.
Disconnect the machine from the power supply and secure to prevent
reconnection.
Disconnect the machine.
Depressurise pressurised components and connecting pipelines at the
designated points.
Allow components and connecting pipelines to cool down.
Seal the connections on removing the lines.
Release components under tension, such as springs and similar.

Collection of hazardous substances


Used oils and operating supplies (drilling fluid, propellants, etc.) can contain
hazardous substances. Clean components soiled with hazardous substances
prior to disassembly.
Collect used oil, grease and other harmful substances in containers and
have them disposed of properly in compliance with legal requirements.

206

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier


Decommissioning, dismantling and disposal

13.3 Carrying out dismantling and disposal


If the machine comprises a variety of recyclable materials or materials which
need to be disposed of separately, dismantle the machine on this basis if at all
possible.
Dismantle the machine into units/pieces which can easily be transported.
Dismantle the machine on the basis of the different materials which need to
be separated.
Compliance with legal requirements is mandatory!
The machine must be disposed of in compliance with applicable laws and
ordinances.
Parts soiled with hazardous substances must be marked accordingly prior to
shipment.
Separate materials for disposal in material groups.
Dispose of metal parts as scrap steel
Dispose of non-ferrous metals for metal recycling
Dispose of plastics and compounds for plastic recycling
Dispose of electric/electronic parts as special waste

Note
European law governing hazardous substances
EU directives state that the owner of machinery which has come into contact
with hazardous substances (acids, lye, solutions, etc.) shall be responsible for
its disposal in an appropriate manner or for issuing an expert declaration in
relation to the transportation of such machinery.

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

207

LOESCHE Mill with Classifier


Supplier documentation

14 Supplier documentation
Note
The general documentation contains a list of supplier documentation in table
format. Each entry has an inventory code and is accompanied by a folder
number for cross-referencing purposes, e.g. in the event of maintenance being
required.

208

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

Index
Abbreviations................................................... 22
Assembly ................................................. 24, 131
Assembly instruction...................................... 132
Assembly Instructions.................................... 131
Assembly sequence ...................................... 132
Automatic mode............................................. 142
Auxiliaries
Oil drain device cpl. .................................... 184
Rocker arm (M) cpl. .................................... 170
Roller (M) cpl. ............................................. 176
Roller (S) cpl............................................... 179
Spring assembly (M) cpl............................. 188
Spring assembly (S) cpl. ............................ 189
Auxiliary equipment
Fill and test unit cpl..................................... 194
lifter cpl. ...................................................... 180
table cpl. ..................................................... 164
tyre profile ruler cpl..................................... 183

B
Bladder accumulator...................................... 191
Book symbol .................................................... 20

C
Checking the delivery status.......................... 128
Classifier drive cpl. ........................................ 112
Classifier housing cpl..................................... 106
Classifier lining cpl......................................... 110
Classifier lubrication line cpl. ......................... 113
Classifier outlet temperature monitoring.......... 40
Classifier temperature sensor cpl.................. 109
Classifier upper housing lining cpl................. 111
Classifier, design and construction................ 105
Cleaning......................................................... 155
cold start-up..................................................... 24
Cold start-up .................................................. 133
Cold start-up sequence ................................. 135
Commissioning ........................................ 24, 133
Contact protection ........................................... 38
Conversion table.............................................. 21
Counterpressure function ................................ 98
Customer service........................................... 151

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

D
Decommissioning .......................................... 207
Delivery ......................................................... 115
Diagram: Spring stiffness ................................ 96
Disassembly .................................................. 207
Dismantling.................................................... 207
dismantling personnel, qualifications ............ 207
Disposal................................................. 207, 208

E
Electrical engineering .................................... 147
Emergency stop system .................................. 37
Extent of cold start-up ................................... 134

F
Faults............................................................. 148
Functional description ..................................... 51

G
General maintenance information for assemblies
and machines............................................ 158
Grinding bed sprinkler cpl. .............................. 60
Grinding parts cpl. ........................................... 66

H
Hazardous areas ............................................. 31
Hydraulic monitoring........................................ 39
Hydraulic oil................................................... 195
Hydraulic system, grinding roller ..................... 93
Hydraulic system, support roller.................... 102

I
Inspection ...................................................... 154
Inspection door................................................ 39
Installation ..................................................... 131
Instructed person............................................. 15
Instruction manual, notes ................................ 15
Intended use.................................................... 12

209

LOESCHE Mill with Classifier

Joining parts on the construction site ............ 130

Name plate ........................................ 16, 92, 114

Leaked oil ...................................................... 186


Lever sealing (M) cpl. ...................................... 73
Lever sealing (S) cpl. ....................................... 81
Liability and warrant conditions ....................... 11
Lighting ............................................................ 28
Lining cpl.......................................................... 59
LM drive ........................................................... 65
Local control panels....................................... 141
Local operation .............................................. 141
Lock symbol..................................................... 20
LOESCHE mill ................................................. 53
Lubricating system fill level monitoring ............ 40
Lubrication ..................................................... 157
Lubrication line cpl. .......................................... 88

oil cleanliness class ....................................... 195


Operating and maintenance personnel ........... 36
Operating areas............................................... 31
Operating the grinding plant .......................... 144
Operation................................................. 25, 140
Operator, Duties of the .................................... 28
Operator, Obligations of the ............................ 23
Organisational issues ...................................... 26
Overload protection ......................................... 39

M
Machine Description ........................................ 50
Mains isolator................................................... 37
Maintenance .................................... 25, 152, 157
Central lubrication unit................................ 199
Classifier ..................................................... 203
Gearbox lubrication unit.............................. 198
Grinding bed sprinkler cpl........................... 202
Hydraulic accumulators .............................. 191
Hydraulic cabinets ...................................... 195
LM-Drive ..................................................... 197
Mill body cpl. ............................................... 160
Mill stand cpl. .............................................. 159
Piping system ............................................. 201
Piston accumulator ..................................... 193
Rocker arms ............................................... 168
Roller .......................................................... 173
Sealing air system ...................................... 200
Spring assembly cpl. .................................. 186
Swinging device.......................................... 201
Table cpl. .................................................... 161
Maintenance works........................................ 152
Metal separation .............................................. 38
Mill body cpl. .................................................... 57
Mill stand cpl. ................................................... 54
Misuse, foreseeable......................................... 14

210

P
Packaging...................................................... 115
Packaging, disposal ...................................... 130
Personnel, Obligations .................................... 23
Personnel, Requirements................................ 26
Pictorial symbols.............................................. 18
Plant control..................................................... 38
Plant identification ........................................... 16

R
Reference documents ..................................... 16
Reference documents, installation ................ 131
Resting places and railings ............................. 38
Risks, electrical energy ................................... 27
Risks, harmful gases, vapours and dusts ....... 27
Risks, hydraulic and pneumatic energy .......... 27
Risks, vibration and noise ............................... 27
Rocker arm (M) cpl.......................................... 71
Rocker arm (S) cpl........................................... 80
Rocker arm monitor......................................... 39
Rocker arm monitor (M) cpl............................. 75
Rocker arm monitor (S) ................................... 82
Roller (M) cpl. .................................................. 67
Roller (S) cpl.................................................... 77
Roller grinding mill, interfaces ......................... 30
Roller relief pressure ....................................... 98
Roller rotation monitor ..................................... 39
Roller rotation monitor (S) cpl.......................... 79
Roller rotation monitor cpl. .............................. 69
Rotor cpl. ....................................................... 107
P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

LOESCHE Mill with Classifier

S
Safety............................................................... 23
Safety checks .................................................. 29
Safety instructions
Classifier....................................................... 33
Hydraulic systems ........................................ 34
LOESCHE mill .............................................. 33
Operating phases ......................................... 24
Roller grinding mill components ................... 33
Swinging device............................................ 35
Safety requirements ........................................ 26
Safety systems ................................................ 36
Scope of supply ............................................. 115
Seal-air piping.................................................. 89
Sealing air monitor........................................... 39
Sealing air monitoring cpl. ............................... 90
Shutdown procedure ....................................... 32
Signal words .................................................... 17
Skilled worker .......................................... 15, 152
Slip-ring seal.................................................. 175
Slip-ring sealing cpl. ........................................ 70
Spare parts .................................................... 206
Specific types of risk........................................ 27
Standard transport sketches
Classifier..................................................... 122
Hydraulic cabinets ...................................... 125
LOESCHE Mill ............................................ 116
Swinging device.......................................... 125
Start sequence .............................................. 143
Storage, supplied parts.................................. 128
Supplier documentation................................. 209
Swinging device............................................... 84
Swinging the grinding roller ............................. 84
Swinging the support roller .............................. 85
Switching symbol............................................. 20
Switching the grinding plant on and off ......... 142
Switching the plant off ................................... 145

P09961-M10X00.980 en Rev. A
The copyright for this document and all appendices is reserved by LOESCHE GmbH

Symbols........................................................... 16

T
Table cpl.......................................................... 62
Technical Data ................................................ 41
Ambient data ................................................ 43
Classifier....................................................... 45
Coating and colours ..................................... 44
Electrical data............................................... 42
Hydraulic system .......................................... 46
LOESCHE mill.............................................. 44
LOESCHE roller grinding mill....................... 41
Production data ............................................ 42
Sealing air supply......................................... 43
Swinging device ........................................... 48
Water injection.............................................. 43
Temperature monitor, rotor bearings .............. 40
Transport ................................................. 24, 115
Crane.......................................................... 129
Fork-lift truck............................................... 129
Transport sketches........................................ 116
Transport, installation site ............................. 129
Troubleshooting............................................. 148
Type approval.................................................. 28

U
Unlocking the Emergency Stop functions ..... 146

V
Vibration monitoring ........................................ 38
Vibration monitoring cpl................................... 91

W
Warm start-up................................................ 136
Weight ........................................................... 126

211

Vous aimerez peut-être aussi