Académique Documents
Professionnel Documents
Culture Documents
Mechanical Means:
Due to mechanization of construction works, rate analyses for various items have been prepared
using mechanical means. However, manual means have also been provided for certain cases,
where access may be inaccessible for machines or quantum of work may not be large enough to
justify the use of machines.
3.
Overhead Charges:
3.1 The overhead charges provided in the analysis for road works is 10(Ten) percent which shall
include the following elements:
i)
Site accommodation, setting up plant, access road, water supply, electricity and general
site arrangements.
ii)
iii)
Expenditure on
a) Corporate Office of contractor.
b) Site supervision.
c) Documentation and as built drawings.
iv)
Mobilisation/de-mobilisation of resources.
v)
vi)
Light vehicles for site supervision including administrative and managerial requirements.
vii)
Laboratory equipments and quality control including field and laboratory testing.
viii)
Minor T&P and survey instruments and setting our works, including verification of line,
dimension, trial pits and bore holes, where required.
1
4.
ix)
x)
xi)
xii)
Sundries.
xiii)
Financing expenditure.
xiv)
xv)
Work insurance/compensation.
Contractors Profit:
Contractors profit is also been taken uniformly as 10 percent, over the cost of items including
overhead charges.
5.
Basic Inputs:
The rates for material and labour adopted in the S.O.R. are as per the current market rate and
Labour Department, Government of Meghalaya.
6.
7.
A dozer is proposed for excavation where cutting and filling for the roadway is within
100m. For longer leads, a combination of hydraulic excavator and tipper is proposed.
6.2
Keeping in view the job and managerial factors and the age factor of machines, the output
of plant and equipment is taken approximately 70 percent of the rated capacity given by
the manufacturer under ideal conditions.
6.3
It has been assumed that a water tanker would make one trip per hour on an average.
Water charges have not been included for items where the requirement is very nominal. It
is assumed that the same would be covered under sundries.
6.4
6.5
The usage charges for machine include ownership charges, cost of repair and maintenance
including replacement of tyres and running and operating charges which include crew, fuel
and lubricants.
Materials:
2
8.
9.
7.1
Quantities of material given in the rate analysis are approximate for the purpose of
estimating and include normal wastages. Actual consumption would have to be based on
mix design.
7.2
The rates for material should include basic cost at locations of stone crusher, loading,
unloading, cost of carriage and stacking at plant sites as the case may be.
7.3
The alternative proposal for crushing own aggregate by installing crusher should be
compared with procurement of crushed aggregates from the market and proposal found
economical may be adopted.
7.4
Labour:
8.1
The wages for skilled, semi-skilled and unskilled labour, adopted in the S.O.R. have been
taken as per the latest Government Circular issued from Labour Department. However, the
rates for Head Mason, Carpenter, Welder, Blacksmith, Driller, Painter, etc., have been
adopted as per the actual current labour rates prevailing in the construction industry.
8.2
Carriage of Materials:
9.1
9.2
10
The Unit for vehicle for carriage has been taken as under:
a.
In hours where lead is defined including time required for loading and unloading.
b.
In tonne - Km. where lead is variable. The loading and unloading for such cases
have been provided separately.
Where the quantity of material to be transported is small such as dismantled materials and
the same are required to be loaded manually, provision of tractor-trolley has been made
instead of tipper.
General:
3
10.1
The clause numbers refer to MORT&H specifications for Road and Bridge works. (Fourth
Revision).
10.2
Assumptions made have been indicated in respective chapter in the form of notes where
required.
10.3
Sundries to cater for unforeseen contingency and miscellaneous items have been added in
the overhead charges.
10.4
Arrangement for traffic during construction shall be as per Clause 112 of MORT&H
specifications for Road and Bridge works. (Fourth Revision).
10.5
The supply of materials will be taken either at the location of mixing plant or at the work
site as the case may be.
10.6
Contractor will make his own arrangement for borrowing of earth. However,
compensation for earth taken from private land has been included in the rate analysis for
construction of embankment with borrowed earth.
10.7
The requirement of machinery have been worked out assuming effective working periods
of six hours per shift of 8 hours.
10.8
The cost of earthwork in urban roads will be comparatively higher due to following
reasons:
a)
There is mixed traffic on urban roads like slow moving hand and animal driven
carts, rickshaws, cycles, two/three wheeler apart from the usual vehicular traffic
resulting into traffic jams. This causes loss of working time, which may be in the
range of 10 - 15 percent.
b)
c)
Cost of living in urban areas is comparatively more resulting into higher wages.
d)
At times, work is executed during night time due to heavy traffic during day time.
This involves extra expenditure by way of making arrangement for lighting and
special transport of working parties due to odd hour.
In the light of above, the authorities engaged in preparing the cost estimates may exercise
their judgment and cater for the additional cost to the extent of 2 to 3 percent, keeping in view the
4
severity of factors mentioned above. Support details for extra cost based on actual site conditions in
specific cases will have to be given in justification.
10.9
10.10 In the rate analysis of stone items, the quantities of sub-items involved in that analysis like
excavation for foundation, concrete, painting, lettering, etc., have been given. The rates for
such items may be taken from relevant chapters where the same have already been
analyzed.
10.11 The source of material and samples are required to be approved by the Engineer before
start of any work.
10.12 The rates of items include cost of testing of soil, materials and works.
10.13 The use of surface by construction vehicles shall be governed by Clause 119 of MORT&H
specifications. (Fourth Revision).
10.14 The contractor shall arrange to provide and maintain an adequate equipped field laboratory
as per Clause 121.
10.15 Quality control of works shall be governed by Section 900 of MORT&H specifications.
10.16 The various activities of works shall also be documented by photographs and video
cassettes as per Clauses 125 & 126 of MORT&H specifications.
10.17 The classifications of soil shall be as per Clause 301.2 of MORT&H specification.
10.18 The earth excavated from foundation has been considered to be backfilled and balance
utilized locally for road work except in the case of marshy soil.
10.19 The rate analysis for removal of unsuitable soil does not provide for replacement by
suitable soil which will have to be paid separately.
10.20 Item for hilly terrain have been analyzed separately.
10.21 The hire charges rate for machinery and equipments are applicable as present usage rate.
Suitable escalation may be added for subsequent years depending upon the market
situation.
10.22 10 percent extra cement may be provided for concreting under water, where required.
10.23 Grade of cement may be adopted as per mix design.
10.24 Quantities of cement in various grades of cement concrete have been taken as per IRC 212000 and IC 18-2000.
5
10.25 The rate for road delineators, boundary pillars and metal beam crash barriers have been
analyzed in Chapter 8.
10.26 The coarse and fine aggregates shall conform to IS:383.
10.27 Certain equipment like road rollers, are required to be available at site for complete period
of the shift though from the consideration of their output, they may be required only for 3
to 4 hours. This is necessitated to match with the output of other associated machines like
HMP, Pavers, etc,. In such cases, the hire charges or road rollers have been multiplied with
a factor of 0.65 to account for the idle period.
10.28 For pricing of RCC slab culvert, the items given in respective chapters in bridges section
may be referred.
10.29 Wherever electric generator has not been provided to run a plant or equipment, it is
assumed that it is fitted with a diesel engine.
10.30 Some of the firms in the field of construction chemicals have evolved new brands of
chemical for water proofing, sealing of cracks, cementing compounds, etc,. the market can
be explored to meet such requirements.
10.31 Some of the major steel producing firms have evolved thermo-mechanically treated steel
which has enhanced strength, better corrosion resistance, ductility, weld ability and high
temperature thermal resistance. Enquiries from these firms can be made on technical
specification and use of such products considered in works based on performance in works
where these have already been used.
10.32 Provision of Fly ash has been made in embankment construction, Sub-base construction
and Cement Concrete Pavement.
10.33 The Standard Data Book is for department use only. It cannot be produced in Court of
Law as reference/authority and thus it is Privilege Document.
10.34 In case it is decided to include the following items and their maintenance in the BOQ, the
scope and specifications should be worked out and defined in the detailed manner in the
tender document to avoid any dispute during execution.
MORT&H Clause Item.
120
122
124
B - BRIDGE WORKS
6
Site accommodation, setting up plant, access road, water supply, electricity and general
site arrangements.
2)
3)
Expenditure on
4)
5)
6)
Light vehicles for site supervision including administrative and managerial requirements.
7)
Laboratory equipment and quality control including field and laboratory testing.
8)
Minor T&P and survey instruments and setting out works, including verification of line
dimensions, trial pits and bore holes, where required.
9)
10)
11)
12)
Sundries.
13)
Financing expenditure.
14)
15)
Work insurance/compensation.
7
For the purpose of calculation of overhead charges, the projects or categorized into three basic
types depending upon width of carriageway, length of the bridge and the present cost.
Category 1: Major Bridge including State of the Art Bridges and Minor Bridges 25%
Category 2: Minor Bridge included in the Road Packages
20%
30%
For the bridge having more than two lanes, equivalent length and cost can be adjusted
accordingly.
Contractors Profit:
Contractors profit is also been taken uniformly as 10 percent, over the cost of items including overhead
charges.
Basic Inputs:
The rates for material and labour adopted in the S.O.R. are as per the current market rate and Labour
Department, Government of Meghalaya.
Plants and Equipments:
The usage hire charges of machinery/equipment have been worked out based upon the present cost of
equipment, repairs, POL and operational charges. These charges are applicable for the current base year.
For subsequent years, these are required to be escalated depending upon the market situation.
In the analysis of rates, for any items of work, capacity of equipment with corresponding output has been
indicated which is most common in use for estimation purpose. Seeing the volume of job, different
capacity equipment with corresponding output can be provided for preparing estimate.
Materials:
The rates of materials should include basic cost at crushing units, cost of carriage including loading and
unloading and stacking of material at site of work and shall be determined through market enquiries.
Labour:
1. The wages for skilled, semi-skilled and unskilled labour, adopted in the S.O.R. have been taken as
per the latest Government Circular issued from Labour Department. However, the rates for Head
Mason, Carpenter, Welder, Blacksmith, Driller, Painter, etc., have been adopted as per the actual
current labour rates prevailing in the construction industry.
2. One mate has been provided for 25 labourers.
Carriage of Materials:
The Unit for vehicle for carriage has been taken as under:
a.
In hours where lead is defined including time required for loading and unloading.
8
b.
In tonne-Km. where lead is variable. The loading and unloading for such cases have been
provided separately.
General:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
(x)
Bridge bearings and expansion joints are readymade items commercially produced by
specialized firms and in certain cases using imported technology and parts. The rates of these
items are to be obtained directly from different manufacturers approved by the Ministry and
shall be adopted after comparison.
Normal methods of curing has been covered in the schedule.
The testing of material and finished items of work is covered under overhead charges.
Traffic arrangements during construction are covered under overhead charges. Provision of
temporary division, where required shall be governed by Clause 112.3.
In the items for well foundation, provision for nominal island/temporary protection, deep
island/cofferdams with wooden ballies and sheet piles has been made.
For some of the items, certain size/specifications have been assumed. If sizes/specifications
other than the same are adopted, corresponding modifications may be made in the input of
analysis.
The items do not cover all components of bridge projects for all situations. There may be
specialized items for specific cases, which need to be analysed keeping in view the basic
approach.
In case bridge construction works are to be done on wide and deep water channel in major
rivers, etc., provision of floating barrages, etc., for taking the construction materials and
equipments beside water shall also be made separately.
Analysis for sinking of wells covers diameters from 6m to 12m and twin D Type of size 12m x
6m. For other shapes like rectangular or any other size, the rates of sinking may worked out on
prorata basis.
The lift for casting of concrete in well seining may be 2 to 2.5m restricting the free fall of
concrete to 1.5m and concreting layer to 450mm.
The Standard Data Book is for Department use only. It cannot be produced in Court of Law as
reference/authority and this is a privilege document.
CHAPTER 1
1. CARRIAGE OF MATERIALS
1.1 Preamble :
9
1.1.1
The provision of tipper has been made in hours where lead is known like disposal of the materials
upto 1 KM. In case where lead is variable like carriage of hot mix from plants or earth from
borrow areas, provision has been made in terms of tonne-kilometer (t-km), which can be adopted
as per actual conditions.
1.1.2
The cost of carriage will vary depending upon the riding surface of the road. Provision has
accordingly been made considering surface roads, unsurfaced graveled roads and katcha tracks.
1.1.3
The analysis for loading and unloading of Stone Boulders, stone aggregates, sand, kankar,
moorum, etc., has been done for manual means, as per site conditions.
1.1.4
Analysis of rate for loading and unloading have been done for manual means for adoption as per
actual situations.
Sl
No
Reference
to
MoRT&H
Specificat
ions
Rate
Item
No.
Descriptions
10
Unit
In
figure
s
(`)
In words
1.1
1.2
1.3
1.4
(i)
Surfaced Road
(ii)
(iii)
cum
153.00
cum
169.00
tonn
e
234.00
tonn
e-km
tonn
e-km
tonn
e-km
CHAPTER 2
2.
2.1.1
SITE CLEARANCE
Preamble :
11
7.00
8.00
16.00
Unless otherwise stated, the rates include sorting and disposal of unserviceable material and
stacking of serviceable material with all lifts and upto a lead of 1000 m.
2.1.2
2.1.3
2.1.4
Preservation of Property/Amenities :
(i)
Roadside trees, shrubs, any other plants, poles lines, fences, signs, monuments, buildings,
pipelines, sewers and all highway facilities within or adjacent to the Highway which are
not to be disturbed shall be protected from injury or damage. The Contractor shall provide
and install at his own expense, suitable safeguards approved by the Engineer for this
purpose.
(ii)
During clearing and grubbing, the Contractor take all adequate precautions against soil
erosion, sedimentation, water pollution, etc., The Contractor shall submit to the Engineer
for approval, his work plan including the procedure to be followed for disposal of waste
materials, etc., and the schedules for carrying out temporary and permanent erosion
control works.
Only such methods, tools and equipment as approved by the Engineer and which will not
affect the property to be preserved shall be adopted for the Work. If the area has thick
vegetation/roots/trees, a crawler or pneumatic tyred dozer of adequate capacity may be
used for clearance purposes. The dozer shall have ripper attachments for removal of tree
stumps.
(ii)
All trees, stumps, etc,. falling within excavation and fill lines shall be cut to such depth
below ground level that in no case these fall within 500 mm of the sub-grade. Also, all
vegetation such as roots, under-growth, grass and other deleterious matter unsuitable for
incorporation in the embankment/sub-grade shall be removed between fill lines to the
satisfaction of the Engineer. On areas beyond these limits, trees and stumps required to be
12
removed as directed by the Engineer shall be cut down to 1 m below ground level so that
these do not present an unsightly appearance.
2.1.5
(iii)
All branches of trees extending above the roadway shall be trimmed as directed by the
Engineer.
(iv)
All excavations below the general ground level arising out of the removal of trees, stumps,
etc., shall be filled with suitable material and compacted thoroughly so as to make the
surface at these points conform to the surrounding area.
(v)
Ant-hills both above and below the ground, as are liable to collapse and obstruct free
subsoil water flow shall be removed and their workings, which may extend to several
metres, shall be suitably treated.
Disposal of materials
(i)
All materials arising from clearing and grubbing operations shall be the property of
Government and shall be disposed of by the Contractor and hereinafter provided or
directed by the Engineer.
(ii)
Trunks, branches and stumps of trees shall be cleaned of limbs and roots and stacked. Also
boulders, stones and other materials usable in road construction shall be nearly stacked as
directed by the Engineer. Stacking of stumps, boulders, stones etc., shall be done at
specified spots with all lifts and upto a lead of 1000m.
(iii)
All products of clearing and grubbing which, in the opinion of the Engineer, cannot be
used or auctioned shall be cleared away from the roadside in a manner as directed the
Engineer. Care shall be taken to see that unsuitable waste materials are disposed of in such
a manner that there is no likelihood of these getting mixed up with the materials meant for
embankment, sub-grade and road construction.
(iv)
Dismantling of utilities like water pipe lines, electric and telephone lines, should be done
under the supervision of concerned departments and prior information to the users should
be disseminated.
(v)
In certain items of dismantling, like, pipe culverts, utilities, etc., excavation in earth and
dismantling of masonry works is not included in this analysis for which suitable notes
have been inserted. These items are required to be priced separately based on actual
quantities at site and nature of work.
(vi)
The dismantled materials should be examined and a realistic assessment and provision
made after due process for the credit for such materials, which can be utilised for works or
auctioned.
13
(vii)
In case where lead for disposal is more than 1000m, extra cost of carriage is required to be
added based on tonne-kilometerage.
(viii)
All minor T&P items required for dismantling are already included in overhead charges.
(ix)
For dismantling of utility services like water pipe lines, electric and telephone lines, prior
intimation should be given to users.
Sl
No
Reference
to
MoRT&H
Specificat
ions
Rate
Item
No.
Descriptions
14
Unit
In
figure
s
(`)
In words
2.1
201
(i)
(ii)
(iii)
(iv)
2.2
2.3
201
(i
201
each
234.00
each
531.00
each
865.00
each
1496.0
0
hectar
e
9959.0
0
hectar
e
31043.
00
hectar
e
42168.
00
15
Eight only'
(ii)
2.4
By Mechanical Means
hectar
e
43272.
00
hectar
e
52524.
00
cum
411.00
cum
451.00
cum
922.00
cum
827.00
cum
1256.0
0
cum
331.00
202
Dismantling of Structures.
Dismantling
of
existing
structures like culverts, bridges,
retaining
walls
and
other
structure
comprising
of
masonry,
cement
concrete,
wood work, steel work, including
T&P and scaffolding wherever
necessary,
sorting
the
dismantled material, disposal of
unserviceable
material
and
stacking
the
serviceable
material with all lifts and lead of
1000 metres.
Lime /Cement Concrete
(i)
I
A
B
C
II
A
By Manual Means
Lime Concrete, cement
concrete grade M-10 and
below
Cement Concrete Grade M15 & M-20
Prestressed / Reinforced
cement concrete grade M-20
& above
By Mechanical Means for
items No. 202( b) & ( c)
Cement Concrete Grade M15 & M-20
Prestressed / Reinforced
cement concrete grade M-20
& above
Rupees Eight
Hundred and Twenty
Seven only
Rupees One
Thousand Two
Hundred and Fifty
Six Only
In lime mortar
16
Rupees Three
Hundred and Thirty
One Only
In cement mortar
cum
371.00
In mud mortar
cum
315.00
cum
308.00
cum
347.00
cum
371.00
cum
331.00
cum
323.00
cum
315.00
cum
331.00
cum
636.00
Rupees Three
Hundred and
Seventy One Only
Rupees Three
Hundred and Fifteen
Only
Rupees Three
Hundred and Eight
Only
(iii)
A
(iv)
(v)
Including dismembering
tonne
1285.0
0
Excluding dismembering.
tonne
969.00
tonne
10.00
(vi)
17
Rupees Three
Hundred and Forty
Seven Only
Rupees Three
Hundred and
Seventy One Only
Rupees Three
Hundred and Thirty
One Only
Rupees Three
Hundred and Twenty
Three Only
Rupees Three
Hundred and Fifteen
Only
Rupees Three
Hundred and Thirty
One Only
Rupees One
Thousand Two
Hundred and Eighty
Five Only
Rupees Nine Hundred
and Sixty Nine Only
Rupees Ten Only
In lime/Cement mortar
In mud mortar
697.00
249.00
(vii)
cum
281.00
In Mud mortar
cum
59.00
sqm
12.00
(viii)
(ix)
2.5
1000
numbe
rs
1000
numbe
rs
Up to 600 mm dia
metre
103.00
metre
141.00
Above 900 mm
metre
240.00
202
Dismantling
of
Flexible
Pavements
Dismantling
of
flexible
pavements and disposal of
dismantled materials up to a
lead of 1000 metres, stacking
serviceable and unserviceable
materials separately.
By Manual Means
I
A
Bituminous courses
cum
742.00
Granular courses
cum
584.00
II
Rupees Seven
Hundred and Forty
Two Only
Rupees Five Hundred
and Eighty Four Only
By Mechanical Means
A
Bituminous course
cum
18
527.00
2.6
2.7
2.8
2.9
2.1
0
202
202
Dismantling
of
Cement
Concrete
Pavement.
Dismantling of cement concrete
pavement by mechanical means
using pneumatic tools, breaking
to pieces not exceeding 0.02
cum in volume and stock piling
at designated locations and
disposal of dismantled materials
up to a lead of 1000 metres,
stacking
serviceable
and
unserviceable
materials
separately.
Dismantling Guard Rails:
202
202
202
5th KM stone
cum
1833.0
0
Rupees One
Thousand Eight
Hundred and Thirty
Three Only
metre
88.00
metre
27.00
metre
40.00
each
385.00
Ordinary KM Stone
each
216.00
Hectometre Stone
each
43.00
19
Rupees Three
Hundred Eighty Five
Only
Rupees Two Hundred
Sixteen Only
Rupees Forty Three
Only
.11
2.1
2
2.1
3
2.1
4
202
202
202
202
Dismantling
of
Fencing:
Dismantling of barbed wire
fencing/ wire mesh fencing
including
posts,
foundation
concrete, back filling of pit by
manual
means
including
disposal of dismantled material
with all lifts and up to a lead of
1000
metres,
stacking
serviceable
material
and
unserviceable
material
separately.
Dismantling of CI Water Pipe
Line:
Dismantling of CI water pipe line
600 mm dia including disposal
with all lifts and lead upto 1000
metres
and
stacking
of
serviceable
material
and
unserviceable
material
separately under supervision of
concerned department.
Removal of Cement Concrete
Pipe
of
SewerGutter:
Removal of cement concrete
pipe of sewer gutter 1500 mm
dia under the supervision of
concerned department including
disposal with all lifts and up to a
lead of 1000 metres and
stacking of serviceable and
unserviceable
material
separately but excluding earth
excavation and dismantling of
masonry works.
Removal of Telephone /
Electric
Poles
andLines:
Removal of telephone / Electric
poles including excavation and
dismantling
of
foundation
concrete and lines under the
supervision
of
concerned
department, disposal with all
lifts and up to a lead of 1000
metres
and
stacking
the
Serviceable and unserviceable
material separately.
metre
40.00
metre
139.00
metre
184.00
each
162.00
CHAPTER 3
3. EARTHWORK, EROSION CONTROL AND DRAINAGE
20
Scope :
This work shall consist of excavation, removal and satisfactory disposal of all materials necessary
for the construction of roadway, side drains and waterways in accordance with requirements of
MoRT&H Specifications and the lines, grades and cross-sections shown in the drawings or as
indicated by the Engineer. It shall include the hauling and stacking of or hauling to sites of
embankment and subgrade construction, suitable cut materials as required, as also the disposal of
unsuitable cut materials in specified manner, trimming and finishing of the road to specified
dimensions or as directed by the Engineer.
3.1.2
Construction Operation :
After the site has been cleared, the limits of excavation shall be set out true to lines, curves,
slopes, grades and sections as shown on the drawings or as directed by the Engineer. The
Contractor shall not excavate outside the limits of excavation. Subject to the permitted tolerances,
any excess depth/ width excavated beyond the specified levels/ dimensions on the drawings shall
be made good at the cost of the Contractor with suitable material of characteristics similar to that
removed and compacted to the requirements of Clause 305.
3.1.4
Excavation General :
(i) All excavations shall be carried out in conformity with the directions laid here-in-under
and in a manner approved by the Engineer. The work shall be executed in such a manner
so that the suitable materials available from excavation are satisfactorily utilised as
decided upon beforehand.
(ii) The Contractor shall provide all labour, survey instruments and materials such as strings,
pegs, nails, bamboos, stones, lime, mortar, concrete etc., required in connection with the
setting out of works and the establishment of Bench Marks. The Contractor shall be
responsible for the maintenance of Bench Marks and other marks and stakes as long as in
the opinion of the Engineer, they are required for the work.
(iii)
While planning or executing excavations, the Contractor shall take all adequate
precautions against soil erosion, sedimentation, water pollution etc., and take appropriate
drainage measures to keep the site free from water logging etc.
(iv)All debris and loose material on the slopes of cuttings shall be removed. No backfilling
shall be allowed to obtain required slopes excepting that when boulders or soft materials
are encountered in cut slopes, these shall be excavated to approved depth on instructions
21
of the Engineer and the resulting cavities filled with suitable material and thoroughly
compacted in an approved manner.
(v) After excavation, the sides of excavated area shall be trimmed and the area contoured to
minimize erosion and ponding, allowing for natural drainage to take place. If trees were
removed, new trees shall be planted, as directed by the Engineer. The cost of planting new
trees shall be deemed to be incidental to the work.
3.1.5
3.1.6
Rock excavation :
(i)
Rock, when encountered in road excavation, shall be removed upto the formation level or
as otherwise indicated on the drawings. Where, however, unstable shales or other
unsuitable materials are encountered at the formation level, these shall be excavated to the
extent of 500 mm below the formation level or as otherwise specified. In all cases, the
excavation operations shall be so carried out that at no point on cut formation the rock
protrudes above the specified levels. Rocks and large boulders which are likely to cause
differential settlement and also local drainage problems should be removed to the extent of
500 mm below the formation level in full formation width including drains and cut
through the side drains.
(ii)
Slopes in rock cutting shall be finished to uniform lines corresponding to slope lines
shown on the drawings or as directed by the Engineer. Notwithstanding the foregoing, all
loose pieces of rock on excavated slope surface which move when pierced by a crowbar
shall be removed.
3.1.7
3.1.8
This shall comprise topsoil, turf, sand, silt, loam, clay, mud, peat, black cotton soil, soft shale
or loose moorum, a mixture of these and similar material which yields to the ordinary
application of pick, spade and/or shovel, rake or other ordinary digging implement. Removal
of gravel or any other nodular material having dimensions in any one direction not exceeding
75 mm occurring in such strata shall be deemed to be covered under this category.
(B) Ordinary Rock (not requiring blasting)
(i)
Rock types such as laterites, shales and conglomerates, varieties of limestone and
sandstone etc., which may be quarried or split with crow bars, also including any rock
which in dry state may be hard, requiring blasting but which, when wet, becomes soft and
manageable by means other than blasting;
(ii)
Macadam surfaces such as water bound and bitumen/tar bound; soling or roads, paths etc,
and hard core; compact moorum or stabilised soil requiring grafting tool or pick or both
and shovel, closely applied; gravel and cobble stone having maximum dimension in any
one direction between 75 and 300 mm;
(iii)
Lime concrete, stone masonry in lime mortar and brick work in lime/cement mortar below
ground level, reinforced cement concrete which may be broken up with crow bars or picks
and stone masonry in cement mortar below ground level; and
(iv)
Boulders which do not require blasting having maximum dimension in any direction of
more than 300 mm, found lying loose on the surface or embedded in river bed, soil, talus,
slope wash and terrace material of dissimilar origin.
Any rock or cement concrete for the excavation of which the use of mechanical plant
and/or blasting is required.
(ii)
Reinforced cement concrete (reinforcement cut through but not separated from the
concrete) below ground level; and
(iii)
i)
3.1.9
All the excavated materials shall be the property of the Employer. The material obtained from the
excavation of roadway, shoulders, verges, drains, cross-drainage works etc., shall be used for filling up of
(i) roadway embankment, (ii) the existing pits in the right-of-way and (iii) for landscaping of the road as
directed by the Engineer, including leveling and spreading with all lifts and lead upto 1000 m and no
extra payment shall be made for the same.
(ii)
All hard materials, such as hard moorum, rubble, etc., not intended for use as above shall
be stacked neatly on specified land as directed by the Engineer with all lifts and lead upto
1000m.
(iii)
Unsuitable and surplus material not intended for use within the lead specified above shall
also, if necessary, be transported with all lifts and lead beyond initial 1000 m, disposed of
or used as directed by the Engineer.
3.1.10 Backfilling :
Backfilling of masonry/concrete/hume pipe drain excavation shall be done with approved material
after concrete/masonry/hume pipe is fully set and carried out in such a way as not to cause undue
thrust on any part of the structure and/or not to cause differential settlement. All space between
the drain walls and the side of the excavation shall be refilled to the original surface making due
allowance for settlement, in layers generally not exceeding 150 mm compacted thickness to the
required density, using suitable compaction equipment such as mechanical tamper, rammer, or
plate compactor as directed by the Engineer.
3.1.11 Blasting Operations:
(i)
Blasting shall be carried out in a manner that completes the excavation to the lines
indicated in drawings, with the least disturbance to adjacent material. It shall be done only
with the written permission of the Engineer. All the statutory laws, regulations, rules, etc.,
pertaining to the acquisition, transport, storage, handling and use of explosives shall be
strictly followed.
(ii)
The Contractor may adopt any method or methods of blasting consistent with the safety
and job requirement. Prior to starting any phase of the operation the Contractor shall
provide information describing pertinent blasting procedures, dimensions and notes.
(iii)
The replacement of unsuitable soil by suitable soil shall be included separately in the
estimate. The rate analyses for removal of unsuitable soil does not provide for replacement
by suitable soil.
(iv)
The possibility of using the blasted rock fragments for backfilling behind structures of
backfilling of foundation pits or filling in medians/ separators or use in service road shall
be examined before proposing disposal of excavated rock.
(v)
In case of hill roads, the cut earth can be pushed down the valley in case there is no
objection. In that case, cost of disposal is not required to be provided.
24
(vi)
For inhabited areas, controlled blasting with limited charges of explosives has been
provided. This involves smaller drill holes and additional requirement of electric
detonators. Provision has accordingly been made.
(vii)
Earth excavated from drains can be used in roadway berms. Hence, carriage for disposal
of same is not provided.
Reference
to
MoRT&H
Specificat
ions
301
Rate
Item
No.
Descriptions
Unit
In
figure
s (`)
cum
156.00
25
In words
Rupees One Hundred
and Fifty Six Only
3.2
3.3
3.4
3.5
301
301
301
301
26
cum
197.00
cum
140.00
cum
235.00
cum
412.00
3.6
3.7
3.8
3.9
301
Excavation
in
Soil
using
Hydraulic Excavator CK 90 and
Tippers with disposal upto
1000 metres:
Excavation for roadwork in
soil with hydraulic excavator of
0.9 cum bucket capacity including
cutting and loading in tippers,
trimming bottom and side slopes,
in accordance with requirements
of lines, grades and cross
sections, and transporting to the
embankment location within all
lifts and lead upto 1000 metres.
Excavation in Ordinary Rock
using Hydraulic Excavator CK90 and Tippers with disposal
upto
1000
metres:
Excavation
for
roadway
in
ordinary rock with hydraulic
excavator of 0.9 cum bucket
capacity including cutting and
loading in tippers, transporting to
embankment site within all lifts
and lead upto 1000 m, trimming
bottom and side slopes in
accordance with requirements of
lines, grades and cross sections.
Excavation
in
Hard
Rock
(blasting
prohibited):
Excavation for roadway in hard
rock (blasting prohibited)
with
rock breakers including breaking
rock, loading in tippers and
disposal within all lifts and lead
upto 1000 metres, trimming
bottom and side slopes in
accordance with requirements of
lines, grades and cross sections.
301
301
301
cum
74.00
cum
110.00
Mechanised
cum
703.00
Manual Method
cum
1097.0
0
Excavation
in
Hard
Rock
(controlled blasting)
with
disposal upto 1000 metres:
Excavation for roadway in hard
rock with controlled blasting by
drilling, blasting and breaking,
trimming of bottom and side
slopes
in
accordance
with
requirements of lines, grades and
cross
sections,
loading
and
disposal of cut road with in all lifts
and leads upto 1000 metres.
cum
507.00
27
Rupees Seven
Hundred Three Only
Rupees One
Thousand Ninety
Seven Only
3.1
0
3.1
1
3.1
2
3.1
3
301
301
303
304
(i)
A
B
(ii)
A
28
cum
80.00
cum
74.00
sqm
156.00
cum
159.00
cum
57.00
cum
199.00
B
(iii)
A
(iv)
A
(v)
A
B
3.1
4
3.1
5
3.1
6
3.1
7
305.4.3
305.4.3
305
305
Mechanical Means
Hard
rock
blasting )
77.00
cum
435.00
cum
1013.0
0
Rupees One
Thousand and
Thirteen Only
cum
611.00
cum
214.00
sqm
29.00
sqm
7.00
cum
540.00
cum
183.00
requiring
Manual Means
Hard
rock
prohibited )
Rupees Seventy
Seven Only
cum
blasting
Mechanical Means
Marshy soil
Manual means ( upto 3 m
depth)
Mechanical Means
Scarifying Existing Granular
Surface to a Depth of 50 mm
by
Manual
Means:
Scarifying the existing granular
road surface to a depth of 50 mm
and disposal of scarified material
within all lifts and leads upto 1000
metres.
Scarifying existing bituminous
surface to a depth of 50 mm
by
mechanical
means:
Scarifying the existing bituminous
road surface to a depth of 50 mm
and disposal of scarified material
with in all lifts and lead upto 1000
metres.
Construction of embankment
with Material Obtained from
Borrow
Pits:
Construction of embankment with
approved material obtained from
borrow pits with all lifts and leads,
transporting to site, spreading,
grading to required slope and
compacting to meet requirement
of Table 300-2
Construction of Embankment
with material deposited from
Roadway
Cutting:
Construction of embankment with
approved materials deposited at
site from roadway cutting and
excavation
from
drain
and
foundation of other structures
graded and compacted to meet
requirement of Table 300-2
29
3.1
8
3.1
9
305
305.3.4
Case
-I
Case
-II
3.2
0
305
3.2
1
3.2
2
307
30
cum
565.00
cum
88.00
cum
59.00
cum
141.00
cum
84.00
sqm
81.00
3.2
3
3.2
4
3.2
5
3.2
6
309
Manual Means
Manual Means
309
309
309
Sub
Surface
Drains
with
Perforated
Pipe:
Construction of subsurface drain
with perforated pipe of 100 mm
internal
diameter
of
metal/
asbestos
cement/
cement
concrete/PVC,
closely
jointed,
perforations ranging from 3 mm to
6 mm depending upon size of
material surrounding the pipe,
with 150 mm bedding below the
pipe and 300 mm cushion above
the
pipe,
cross
section
of
excavation 450 x 550 mm.
Excavated material to be utilised
in roadway at site
Aggregate
SubSurface
Drains:
Construction of aggregate sub
surface drain 300 mm x 450 mm
with aggregates conforming to
Table 300-4, excavated material
to be utilised in roadway
31
metr
e
metr
e
metr
e
metr
e
90.00
40.00
182.00
60.00
metr
e
374.00
Rupees Three
Hundred and Seventy
Four Only
Metr
e
118.00
3.2
7
3.2
8
3.2
9
310
313
301
3.3
0
3.3
1
Preparation
and
Surface
Treatment
of
formation:
Preparation and surface treatment
of formation by removing mud
and slurry, watering to the extent
needed to maintain the desired
moisture content, trimming to the
required line, grade, profile and
rolling with 8-10 tonne smooth
wheeled roller, complete as per
clause 310.
Construction
of
Rock
fill
Embankment:
Construction
of
rock
fill
embankment with broken hard
rock fragments of size not
exceeding 300 mm laid in layers
not exceeding 500 mm thick
including filling of surface voids
with stone spalls, blinding top
layer with granular material, rolled
with vibratory road roller, all
complete as per clause 313
A
301
32
Sqm
4.00
Cum
103.00
Cum
181.00
Cum
191.00
Cum
260.00
3.3
2
3.3
3
301
301
33
cum
341.00
Rupees Three
Hundred and Forty
One Only
cum
424.00
CHAPTER 4
4. SUB-BASES, BASES ( NON-BITUMINOUS) AND SHOULDERS
4.1 Preamble:
4.1.1
Quantities of materials provided are approximate and are meant for the purpose of estimating
only. Actual quantities shall be as per mix design.
4.1.2
4.1.3 While providing for the rate of materials, detailed local enquiries have been made and prevailing
market rates ascertained from concerned suppliers in the area keeping in view the location of
crushing plants and lead involved.
4.2. GRANULAR SUB-BASE
4.2.1
Scope :
This work shall consist of laying and compacting well-graded material on prepared subgrade in
accordance with the requirements of MoRT&H specifications. The material shall be laid in one or
more layers as sub-base or lower sub-base and upper sub-base (termed as sub-base hereinafter) as
necessary according to lines, grades and cross-sections shown on the drawings or as directed by
the Engineer.
4.2.2
Materials :
(i)
The material to be used for the work shall be natural sand, moorum, gravel, crushed stone
or combination thereof depending upon the grading required. Materials like crushed slag,
crushed concrete, brick metal and kankar may be allowed only with the specific approval
of the Engineer. The material shall be free from organic or other deleterious constituents
and conform to one of the three gradings given in Table. 4.1.
Table 4.1. (Table 400-1) Grading for Close-Graded Granular Sub-base Materials
IS Sieve
Per cent by weight Passing the IS sieve
Designation
Grading I
Grading II
Grading III
75.0 mm
100
53.0 mm
80-100
100
26.5 mm
55-90
70-100
100
9.50 mm
35-65
50-80
65-95
4.75 mm
25-55
40-65
50-80
2.36 mm
20-40
30-50
40-65
0.425 mm
10-25
15-25
20-35
0.075 mm
3-10
3-10
3-10
CBR Value (Minimum)
30
25
20
34
(iii)
While the gradings in Table 4.1 are in respect of close-graded granular sub-base materials,
one each for maximum particle size of 75 mm, 53 mm and 26.5 mm, the corresponding
gradings for the coarse-graded materials for each of the three maximum particle sizes are
given at Table 4.2 The grading to be adopted for a project shall be as specified in the
Contract.
Table. 4.2 (Table 400-2) Grading for Coarse Graded Granular Sub-base Materials
IS Sieve
Per cent by weight passing the IS sieve
Designation
Grading I
Grading II
Grading III
75.0 mm
100
53.0 mm
100
26.5 mm
55-75
50-80
100
9.50 mm
4.75 mm
10-30
15-35
25-45
2.36 mm
0.425 mm
0.075 mm
<10
<10
<10
CBR Value (Minimum)
30
25
20
Note: The material passing 425 micron (0.425 mm) sieve for all the three gradings when
tested according to IS : 2720 (Part 5) shall have liquid limit and plasticity index not more than
25 and 6 per cent respectively
4.2.3
Physical requirements :
The material shall have a 10 per cent fines value of 50 kN or more (for sample in soaked
condition) when tested in compliance with BS:812 (Part 111). The water absorption value of the
coarse aggregate shall be determined as per IS: 2386 (Part 3). If this value is greater than 2 per
cent, the soundness test shall be carried out on the material delivered to site as per IS: 383. For
Grading II and III materials, the CBR shall be determined at the density and moisture content
likely to be developed in equilibrium conditions which shall be taken as being the density relating
to a uniform air voids content of 5 per cent.
4.2.4
4.2.5
Strength of sub-base :
(i)
It shall be ensured prior to actual execution that the material to be used in the sub-base
satisfies the requirements of CBR and other physical requirements when compacted and
finished.
(ii)
When directed by the Engineer, this shall be verified by performing CBR tests in the
laboratory as required on specimens remoulded at field dry density and moisture content
and any other tests for the quality of materials, as may be necessary.
Preparation of subgrade :
Immediately prior to the laying of sub-base, the subgrade already finished to Clause 301 or 305 as
applicable shall be prepared by removing all vegetation and other extraneous matter, lightly
35
sprinkled with water if necessary and rolled with two passes of 80 100 kN smooth wheeled
roller.
4.2.6
The sub-base material of grading specified in the Contract shall be spread on the prepared
subgrade with the help of a motor grader of adequate capacity, its blade having hydraulic
controls suitable for initial adjustments and for maintaining the required slope and grade
during the operation or other means as approved by the Engineer.
(ii)
(iii)
Manual mixing shall be permitted only where the width of laying is not adequate for
mechanical operations, as in small-sized jobs. The equipment used for mix-in-place
construction shall be a rotavator or similar approved equipment capable of mixing the
material to the desired degree. If so desired by the Engineer, trial runs with the equipment
shall be carried out to establish its suitability for the work.
(iv)
Moisture content of the loose material shall be checked in accordance with IS:2720 (Part
2) and suitably adjusted by sprinkling additional water from a truck mounted or trailer
mounted water tank and suitable for applying water uniformly and at controlled quantities
to variable widths of surface or other means approved by the Engineer so that, at the time
of compaction, it is from 1 per cent above to 2 per cent below the optimum moisture
content corresponding to IS:2720 (Part 8). While adding water, due allowance shall be
made for evaporation losses. After water has been added, the material shall be processed
by mechanical or other approved means like disc harrows, rotavators until the layer is
uniformly wet.
(v)
Immediately thereafter, rolling shall start. If the thickness of the compacted layer does not
exceed 100 mm, a smooth wheeled roller of 80 to 100 kN weight may be used. For a
compacted single layer upto 225 mm the compaction shall be done with the help of a
vibratory roller of minimum 80 to 100 kN static weight with plain drum or pad foot-drum
or heavy pneumatic tyred roller of minimum 200 to 300 kN weight having a minimum
tyre pressure of 0.7 MN/m2 or equivalent capacity roller capable of achieving the required
compaction. Rolling shall commence at the lower edge and proceed towards the upper
edge longitudinally for portions having unidirectional crossfall and super elevation and
shall commence at the edges and progress towards the centre for portions having crossfall
on both sides.
(vi)
Each pass of the roller shall uniformly overlap not less than one-third of the track made in
the preceding pass. During rolling, the grade and crossfall (camber) shall be checked and
any high spots or depressions, which become apparent, corrected by removing or adding
fresh material. The speed of the roller shall not exceed 5 km per hour.
36
(vii)
Rolling shall be continued till the density achieved is at least 98 per cent of the maximum
dry density for the material determined as per IS:2720 (Part 8). The surface of any layer of
material on completion of compaction shall be well closed, free from movement under
compaction equipment and from compaction planes, ridges, cracks or loose material. All
loose, segregated or otherwise defective areas shall be made good to the full thickness of
layer and re-compacted.
4.3. WATER BOUND MACADAM SUB-BASE/BASE
4.3.1
4.3.2
Scope :
(i)
This work shall consist of clean, crushed aggregates mechanically interlocked by rolling
and bonding together with screening, binding material where necessary and water laid on a
properly prepared subgrade/ sub-base/ base or existing pavement, as the case may be and
finished in accordance with the requirements of MoRT&H Specifications and in close
conformity with the lines, grades, cross-sections and thickness as per approved plans or as
directed by the Engineer.
(ii)
It is, however, not desirable to lay water bound macadam on an existing thin black topped
surface without providing adequate drainage facility for water that would get accumulated
at the interface of existing bituminous surface and water bound macadam.
Coarse aggregates :
Coarse aggregates shall be either crushed or broken stone, crushed slag, overburnt (Jhama) brick
aggregates or any other naturally occurring aggregates such as kankar and laterite of suitable
quality. Materials other than crushed or broken stone and crushed slag shall be used in sub-base
courses only. If crushed gravel/ shingle is used, not less than 90 per cent by weight of the gravel/
shingle pieces retained on 4.75 mm sieve shall have at lease two fractured faces. The aggregates
shall conform to the physical requirements set forth in Table. 4.3. The type and size range of the
aggregate shall be specified in the Contract or shall be as specified by the Engineer. If the water
absorption value of the coarse aggregate is greater than 2 per cent, the soundness test shall be
carried out on the material delivered to site as per IS: 2386 (Part 5).
4.3.3
37
Combined
IS:2386
30 per cent (Max)
Flakiness and
(Part-1)
Elongation
Indices (Total)
***
Aggregate may satisfy requirements of either of the two tests.
** Aggregates like brick metal, kankar, laterite etc. which get softened in presence of water
shall be tested for Impact value under wet conditions in accordance with IS:5640.
*** The requirements of flakiness index and elongation index shall be enforced only in the
case of crushed broken stone and crushed slag.
Grading requirement of coarse aggregates :
The coarse aggregates shall conform to one of the Gradings given in Table. 4.4 as specified,
provided, however, the use of Grading No.1 shall be restricted to sub-base courses only.
1.
90 mm to 45 mm
125 mm
90 mm
63 mm
45 mm
22.4 mm
100
90-100
25-60
0-15
0-5
2.
63 mm to 45 mm
90 mm
63 mm
53 mm
45 mm
22.4 mm
100
90-100
25-75
0-15
0-5
3.
53 mm to 22.4 mm
63 mm
100
53 mm
95-100
45 mm
65-90
22.4 mm
0-10
11.2 mm
0-5
Note : The compacted thickness for a layer with Grading 1 shall be 100 mm while for layer
other Gradings i.e. 2 & 3, it shall be 75 mm.
4.3.5
with
Screenings :
(i)
Screenings to fill voids in the coarse aggregate shall generally consist of the same material
as the coarse aggregate. However, where permitted, predominantly non-plastic material
such as moorum or gravel (other than rounded river borne material) may be used for this
purpose provided liquid limit and plasticity index of such material are below 20 and 6
respectively and fraction passing 75 micron sieve does not exceed 10 per cent.
(ii)
Screenings shall conform to the gradings set forth in Table. 4.5. The consolidated details
of quantity of screenings required for various grades of stone aggregates are given in
Table. 4.6. The table also gives the quantities of materials (loose) required for 10 m 2 for
sub-base/ base compacted thickness of 100/75 mm.
(iii)
The use of screenings shall be omitted in the case of soft aggregates such as brick metal,
kankar, laterites, etc. as they are likely to get crushed to a certain extent under rollers.
Size of
Screenings
IS Sieve
Designation
39
n
A
13.2 mm
13.2 mm
11.2 mm
5.6 mm
180 micron
100
95-100
15-35
0-10
11.2 mm
11.2 mm
5.6 mm
180 micron
100
90-100
15-35
Table. 4.6 (Table 400-9) Approximate Quantities of Coarse Aggregates and Screenings
Required for 100/75 mm Compacted Thickness of Water Bound Macadam (WBM)
Sub-Base/ Base Course for 10m2 Area.
Compacte
d
thickness
Classifica
- tion
Size
Range
Grading
1
90 mm
to 45
mm
100 mm
1.21 to
1.43 m3
Grading
2
63 mm
to 45
mm
75 mm
0.91 to
1.07 m3
Type A
0.12 to
13.2 mm 0.15 m3
-do-
0.22 to
0.24
m3
-do-
-do-
-do-
Type B
0.20 to
11.2 mm 0.22 m3
-do-
-do-
53 mm
to 22.4
mm
75 mm
-do-
-do-
-do-
-doGrading
3
Loose
Qty.
Screenings
Stone Screening
Crushable Type
such as Moorum or
Gravel
Grading For WBM Grading
Loose
Classifi- Sub-base/ Classifica Qty.
cation & base
tion &
Size
course
Size
(Loose
quantity)
Type A
0.27 to
Not
0.30 to
3
13.2 mm 0.30 m
uniform
0.32
m3
-do-
0.18 to
0.21 m3
Binding material :
(i)
Binding material to be used for water bound macadam as a filler material meant for
preventing raveling, shall comprise of a suitable material approved by the Engineer having
40
a Plasticity Index (PI) value of less than 6 as determined in accordance with IS: 2720
(Part-5).
(ii)
The quantity of binding material where it is to be used, will depend on the type of
screenings. Generally, the quantity required for 75 mm compacted thickness or water
bound macadam will be 0.06-0.09 m3 /10m2 and 0.08-0.10m3/10m2 for 100 mm compacted
thickness.
(iii)
The above mentioned quantities should be taken as a guide only, for estimation of
quantities for constructions etc.
(iv)
Application of binding materials may not be necessary when the screenings used are of
crushable type such as moorum or gravel.
4.4. WET MIX MACADAM SUB-BASE/BASE
4.4.1
4.4.2
Scope:
(i)
Wet Mix Macadam Sub-base/Base : This work shall consist of laying and compacting
clean, crushed, graded aggregate and granular material, premixed with water, to a dense
mass on a prepared subgrade/sub-base/base or existing pavement as the case may be in
accordance with the requirements of MoRT&H Specifications. The material shall be laid
in one or more layers as necessary to lines, grades and cross-sections shown on the
approved drawings or as directed by the Engineer.
(ii)
The thickness of a single compacted Wet Mix Macadam layer shall not be less than 75
mm. When vibrating or other approved types of compacting equipment are used, the
compacted depth of a single layer of the sub-base course may be increased to 200 mm
upon approval of the Engineer.
Physical requirements :
(i)
Coarse aggregates shall be crushed stone. If crushed gravel/shingle is used, not less than
90 per cent by weight of the gravel/shingle pieces retained on 4.75 mm sieve shall have at
least two fractured faces. The aggregates shall conform to the physical requirement set
forth in Table. 4.7 below.
Table 4.7 (Table 400-10) Physical Requirements of Coarse Aggregates for Wet Mix
Macadam for Sub- Base/Base Courses
Test
1.
* Los Angeles
Test Method
IS: 2386 (Part-4)
41
Requirements
40 per cent (Max.)
Abrasion value
Or
* Aggregate
Impact value
2.
IS:2386 (Part-1)
30 per cent
(Max)**
If the water absorption value of the coarse aggregate is greater than 2 per cent, the
soundness test shall be carried out in the material delivered to site as per IS:2386
(Part-5).
Grading requirements :
The aggregates shall conform to the grading given in Table. 4.8
Table 4.8 (Table 400-11) Grading requirements of Aggregates for Wet Mix Macadam
IS Sieve Designation Per cent by weight passing the IS sieve
53.00 mm
100
45.00 mm
95-100
26.50 mm
22.40 mm
60-80
11.20 mm
40-60
4.75 mm
25-40
2.36 mm
15-30
600.00 micron
8-22
75.00 micron
0-8
Materials finer than 425 micron shall have Plasticity Index (PI) not exceeding 6.
The final gradation approved within these limits shall be well graded from coarse to fine and shall
not vary from the low limit on one sieve to the high limit on the adjacent sieve or vice versa.
4.5 SHOULDERS, ISLANDS AND MEDIAN
4.5.1
Scope :
42
The work shall consist of constructing shoulder (hard/paved/earthen with brick or stone block
edging) on either side of the pavement, median in the road dividing the carriageway into separate
lanes and islands for channelising the traffic at junctions in accordance with the requirements of
MoRT&H Specifications and in conformity with the lines, grades and cross-sections shown on the
drawings or as directed by the Engineer.
4.5.2
4.5.3
Materials :
(i)
Shoulder on either side of the road may be of selected earth/granular material/ paved
conforming to the requirements of Clause 305/401 and the median may be of selected
earth conforming to the requirements of Clause 305.
(ii)
Median/ Traffic islands shall be raised and kerbed at the perimeter and the enclosed area
filled with earth and suitably covered with grass turf/ shrubs as per Clause 307 and/or
paved as per Clause 409.3.4 or 409.3.5.
(iii)
Paved shoulders shall consist of sub-base, base and surfacing courses, as shown in the
drawings and materials for the same shall conform to relevant Specifications of the
corresponding items. Where paved or hard shoulders are not provided, the pavement shall
be provided with brick/stone edgings as shown in the drawings. The bricks shall conform
to Clause 1003 of MoRT&H Specifications. Stone blocks shall conform to Clause 1004 of
MoRT&H Specifications and shall be of size 225 mm x 110 mm x 75 mm.
Size of Shoulders/Median/Islands :
Shoulder (earthen/hard/paved)/median/traffic island dimensions shall be as shown on the
drawings or as directed by the Engineer.
4.6 MEDIAN AND ISLANDS
4.6.1
Scope :
Median and Islands shall be constructed in a manner similar to shoulder up to the road level.
Thereafter the median and islands, if raised, shall be raised at least 300 mm by using kerb stones
of approved material and dimensions and suitably finished and painted as directed by the
Engineer. If not raised, the median and islands shall be differentiated from the shoulder/pavement
as the case may be, as directed by the Engineer. The confined area of the median and islands shall
be filled with local earth or granular material or any other approved material and compacted by
plate compactor/power rammer. The confined area after filling with earth shall be turfed with
grass or planted with shrubs and in case of granular fill it can be finished with tiles/slabs as
directed by the Engineer.
4.7. FOOTPATHS AND SEPARATORS
4.7.1
Scope :
43
The work shall consist of construction footpaths and/or separators at locations as specified in the
drawings or as directed by the Engineer. The lines, levels and dimensions shall be as per the
drawings. The scope of the work shall include provision of all drainage arrangements as shown in
the drawings or as directed.
4.7.2
Materials :
The footpaths and separators shall be constructed with any of the following types :
(a) Cast-in-situ cement concrete of Grade M20 as per Section 1700 of the Specifications.
(b) Precast cement concrete blocks/tiles of Grade M20 as per Section 1700 of the Specifications.
The minimum thickness of the cement concrete block/tile shall be 25 mm and minimum size
shall be 300 mm x 300 mm.
(c) Natural stone slab cut and dressed from stone of good and sound quality, uniform in texture,
free from defects and at least equal to a sample submitted by the Contractor and approved by
the Engineer. The minimum thickness of the natural stone slab shall be 25 mm and minimum
size shall be 300 mm x 300 mm.
Sl
No
44
4.1
401
A
(i)
cum
3096.0
0
(ii)
cum
3146.0
0
(iii)
cum
3028.0
0
Rupees Three
Thousand and Ninety
Six Only
Rupees Three
Thousand One
Hundred and Forty
Six Only
Rupees Three
Thousand and Twenty
Eight Only
4.2
401
(i)
cum
2193.0
0
(ii)
cum
2242.0
0
(iii)
cum
2125.0
0
45
Rupees Two
Thousand One
Hundred and Ninety
Three Only
Rupees Two
Thousand Two
Hundred and Forty
Two Only
Rupees Two
Thousand One
Hundred Twenty Five
Only
4.3
4.4
4.5
(i)
cum
2172.0
0
(ii)
cum
2292.0
0
(iii)
cum
1760.0
0
402
402
403
Rupees Two
Thousand One
Hundred and Seventy
Two Only
Rupees Two
Thousand Two
Hundred and Ninety
Two Only
Rupees One
Thousand Seven
Hundred Sixty Only
Lime
Stabilisation
for
Improving
Subgrade:
Laying and spreading available soil
in the subgrade on a prepared
surface, pulverising, mixing the
spread soil in place with rotavator
with 3 % slaked lime having
minimum content of 70% of CaO,
grading with motor grader and
compacting with the road roller at
OMC to the desired density to form
a layer of improved sub grade
A
By Mechanical Means
cum
508.00
By Manual Means
cum
459.00
cum
646.00
cum
994.00
46
sub-base/base.
4.6
403
(i)
(ii)
4.7
4.8
4.9
404.3.1
404.3.2
404
Rupees Two
Thousand Eight
Hundred and Ninety
Three Only
Rupees Two
Thousand Three
Hundred and Seventy
Seven Only
cum
2893.0
0
cum
2377.0
0
sqm
3.00
sqm
6.00
cum
1431.0
0
Making 50 mm x 50 mm
Furrows: Making 50 mm x 50
mm furrows, 25mm deep, 45 to
the center line of the road and at
one metre interval in the existing
thin bituminous wearing coarse
including sweeping and disposal of
excavated material within 1000
metres lead
i. 25mm deep furrow cutting
ii. 50mm deep furrow cutting
Inverted-Choke:
Construction of inverted choke by
providing, laying, spreading and
compacting screening B type/
coarse sand of specified grade in
uniform layer on a prepared
surface with motor grader and
compacting with power roller etc
Water Bound Macadam
47
Rupees One
Thousand Four
Hundred and Thirty
One only
A
(i)
(ii)
(iii)
B
(i)
(ii)
(iii)
4.1
0
406
cum
2605.0
0
cum
2694.0
0
cum
3035.0
0
cum
2518.0
0
cum
2606.0
0
cum
2948.0
0
cum
3329.0
0
Rupees Two
Thousand Six
Hundred and Five
Only
Rupees Two
Thousand Six
Hundred and Ninety
Four Only
Rupees Three
Thousand and Thirty
Five Only
Rupees Two
Thousand Five
Hundred and
Eighteen Only
Rupees Two
Thousand Six
Hundred and Six Only
Rupees Two
Thousand Nine
Hundred and Forty
Eight Only
48
Rupees Three
Thousand Three
Hundred and Twenty
Nine Only
4.1
1
4.1
2
409
Suggestiv
e
sqm
1800.0
0
Rupees One
Thousand and Eight
Hundred Only
cum
690.00
CHAPTER 5
5. BASE AND SURFACE COURSES (BITUMINOUS)
5.1 GENERAL REQUIREMENTS FOR BITUMINOUS PAVEMENT LAYERS
5.1.1
Scope:
49
5.1.2
(i)
Bituminous pavement courses shall be made using the materials described in the following
Specifications.
(ii)
Binder :
The binder shall be an appropriate type of bituminous material complying with the relevant Indian
Standard (IS), as defined in the appropriate Clauses of MoRT&H Specifications, or as otherwise
specified herein. The choice of binder shall be stipulated in the Contract or by the Engineer.
Where penetration grades of bitumen are specified, they are referred to by a single-figure
designation in accordance with IS:73. Thus bitumen Grade 35 refers to a bitumen in the
penetration range 30 to 40. Where Modified Binder is specified, the Clause 521 of MoRT&H
Specifications shall apply.
5.1.3
5.1.4
Coarse Aggregates :
(i)
The coarse aggregates shall consist of crushed rock, crushed gravel or other hard material
retained on the 2.36 mm sieve. They shall be clean, hard, durable, of cubical shape, free
from dust and soft or friable matter, organic or other deleterious matter.
(ii)
The aggregates shall satisfy the physical requirements set forth in the individual relevant
clause for the material in question.
Fine Aggregates :
Fine aggregates shall consist of crushed or naturally occurring material, or a combination of the
two, passing 2.36 mm sieve and retained on the 75 micron sieve. They shall be clean, hard,
durable, dry and free from dust, and soft or friable matter, organic or other deleterious matter.
5.1.5
Source of material :
The source of all materials to be used on the project must be tested to the satisfaction of and be
expressly approved by the Engineer. The Engineer may from time to time withdraw approval of a
specific source, or attach conditions to the existing approval. Any change in aggregate source for
bituminous mixes, will require a new mix design, and laying trials, where the mix is based on a
job mix design. Stockpiles from different sources, approved or otherwise, shall be kept separate,
such that there is no contamination between one material and another. Each source submitted for
approval shall contain sufficient material for at least 5 days work.
5.2 PRIME COAT OVER GRANULAR BASE
5.2.1
Scope:
This work shall consist of the application of a single coat of low viscosity liquid bituminous
material to a porous granular surface preparatory to the superimposition of bituminous treatment
or mix.
50
5.2.2
Primer :
The choice of a bituminous primer shall depend upon the porosity characteristics of the surface to
be primed as classified in IRC:16. These are :
i) Surface of low porosity; such as wet mix macadam and water bound macadam.
ii) Surfaces of medium porosity; such as cement stabilized soil base.
iii) Surfaces of high porosity; such as a gravel base.
5.2.3
Primer Viscosity :
The type and viscosity of the primer shall comply with the requirements of IS 8887, as sampled
and tested for bituminous primer in accordance with these standards. Guidance on viscosity and
rate of spray is given in Table 5.1.
Table 5.1. (Table 500-1) Viscosity Requirement and Quality of Liquid Bituminous Primer
Type of surface
5.2.4
Kinematic Viscosity
of Primer at 60oC
Low porosity
30 60
Quantity of Liquid
Bituminous Material
per 10 Sq.m (kg)
6 to 9
Medium porosity
70 140
9 to 12
High porosity
250 500
12 to 15
Choice of primer :
The primer shall be bitumen emulsion, complying with IS 8887 of a type and grade as specified in
the Contract or as directed by the Engineer. The use of medium curing cutback as per IS 217 shall
be restricted only for sites at sub-zero temperature or for emergency applications as directed by
the Engineer.
Scope :
This work shall consist of the application of a single coat of low viscosity liquid bituminous
material to an existing bituminous road surface preparatory to the superimposition of a bituminous
mix, when specified in the Contract or as instructed by the Engineer.
5.3.2
Binder :
The binder used for tack coat shall be bitumen emulsion complying with IS 8887 of a type and
grade as specified in the Contract or as directed by the Engineer. The use of cutback bitumen as
per IS 217 shall be restricted only for sites at sub-zero temperature or for emergency applications
as directed by the Engineer.
51
5.3.3
The application of tack coat shall be at the rate specified in the Contract, and shall be
applied uniformly. If rate of application of Tack Coat is not specified in the contract then it
shall be at the rate specified in Table 5.2 below. The normal range of spraying temperature
for a bituminous emulsion shall be 20oC to 70oC and for a cutback, 50oC to 80oC if RC70/MC-70 is used. Where a geo-synthetic is proposed for use, the provisions of Clauses
703.3.2 and 703.4.4 shall apply. The method of application of the tack coat will depend on
the type of equipment to be used, size of nozzles, pressure at the spray bar, and speed of
forward movement. The Contractor shall demonstrate at a spraying trial, that the
equipment and method to be used is capable of producing a uniform spray, within the
tolerances specified.
(ii)
Where the material to receive an overlay is a freshly laid bituminous layer, that has not
been subjected to traffic, or contaminated by dust, a tack coat is not mandatory where the
overlay is completed within two days.
Table 5.2(Table 500-2) Rate of Application of Tack Coat
Type of surface
i)
ii)
0.25 to 0.30
iii
)
0.25 to 0.30
0.35 to 0.40
0.30 to 0.35
iv)
Scope :
This work shall consist of construction in a single course having 50mm to 100mm thickness or in
multiple courses of compacted crushed aggregates premixed with a bituminous binder on a
previously prepared base to the requirements of MoRT&H Specifications. Bituminous macadam
is more open graded than the dense graded bituminous materials described in Clauses 507, 508
and 509 of MoRT&H, Hand Book of Specification for Roads & Bridge Work.
5.4.2
Bitumen :
The bitumen shall be paving bitumen of Penetration Grade complying with Indian Standard
Specifications for Paving Bitumen IS:73, and of the penetration indicated in Table 5.4.
5.4.3
Coarse Aggregate :
52
5.4.4
(i)
The coarse aggregates shall consist of crushed rock, crushed gravel or other hard material
retained on the 2.36 mm sieve. They shall be clean, hard, durable, of cubical shape, free
from dust and soft or friable matter, organic or other deleterious matter.
(ii)
The aggregates shall satisfy the physical requirements set forth in Table 5.3.
Fine aggregates :
Fine aggregates shall consist of crushed or naturally occurring material, or a combination of the
two, passing 2.36 mm sieve and retained on 75 micron sieve. They shall be clean, hard, durable,
dry and free from dust, and soft or friable matter, organic or other deleterious matter.
Table 5.3 (Table 500-3) Physical Requirements for Coarse Aggregates for Bituminous
Macadam
Property
Cleanliness
Particle shape
Test
Specification
1
Grain size analysis
Max 5% passing 0.075 mm sieve
Flakiness and Elongation Index
Max 30 %
2
(Combined)
Strength*
Los Angeles Abrasion Value3
Max 40 %
3
Aggregate Impact Value
Max 30 %
4
Durability
Soundness
Max 12 %
Sodium Sulphate
Max 18 %
Magnesium Sulphate
Water Absorption Water absorption5
Max 2 %
Stripping
Coating and Stripping of Bitumen Minimum retained coating
Aggregate Mixtures6
95%
7
Water Sensitivity
Retained Tensile Strength
Min 80 %
Notes : 1. IS: 2386 Part 1
4. IS: 2386 Part 5
2. IS: 2386 Part 1
5. IS: 2386 Part 3
(the elongation test to be done only on non-flaky aggregates in the sample)
3. IS: 2386 Part 4*
6. IS: 6241
7. The water sensitivity test is only to be carried out if the minimum retained coating in the
stripping test is less than 95%.
* Aggregate may satisfy requirements of either of these two tests.
Grading 1
Grading 2
40 mm
19 mm
80 100 mm
50 75 mm
Cumulative % by weight of total aggregate passing
53
45
100
37.5
90-100
26.5
75-100
100
19
90-100
13.2
35-61
56-88
4.75
13-22
16-36
2.36
4-19
4-19
0.3
2-10
2-10
0.075
0-8
0-8
Bitumen content, % by
3.1 3.4
3.3 3.5
weight of total mixture
Bitumen grade
35 to 90
35 to 90
Notes : 1. Appropriate bitumen contents for conditions in cooler areas of India may be up to 0.5
% higher subject to the approval of the Engineer.
Table 5.5( Table 500-5) Manufacturing and Rolling Temperatures
Bitumen
Penetratio
n
Bitumen
Mixing (oC)
Aggregate
Mixing (oC)
Mixed
Material (oC)
Rolling
(oC)
Laying
(oC)
35
160 -170
160 175
170 Maximum
65
150 165
150 170
165 Maximum
90 Minimum
125 Minimum
90
140 - 160
140 165
155 Maximum
80 Minimum
115 Minimum
5.5.2
Scope :
(i)
(ii)
Bitumen :
Clause 504.2.1. shall apply. Where permitted by the Engineer, an appropriate grade of emulsion
complying with IS 8887 may be used.
54
5.5.3
Aggregates :
(i)
(ii)
The aggregate shall satisfy the physical requirements set out in Table 5.3. The coarse and
key aggregates for built-up spray grout shall conform to the grading given in Table 5.6.
Table 5.6(Table 500-7) Grading Requirements for Coarse and Key Aggregates for Built-up Spray
Grout.
IS Sieve
Designation (mm)
53.0
26.5
22.4
13.2
5.6
2.8
Bitumen :
The bitumen shall be paving bitumen of Penetration Grade complying with Indian Standard
Specifications for Paving Bitumen IS: 73, and of the penetration indicated in Table 5.9 for
dense bitumen macadam, or this bitumen as modified by one of the methods specified in Clause
521, or as otherwise specified in the Contract. Guidance on the selection of an appropriate grade
of bitumen is given in The Manual for Construction and Supervision of Bituminous Works.
5.6.2
Coarse Aggregates :
(i)
5.6.3
The coarse aggregates shall consist of crushed rock, crushed gravel or other hard material
retained on the 2.36 mm sieve. They shall be clean, hard, durable, of cubical shape, free
from dust and soft or friable matter, organic or other deleterious substances. The
aggregates shall satisfy the physical requirements specified in Table 5.7, for dense
bituminous macadam.
Fine Aggregates :
(i)
(ii)
(iii)
They shall be clean, hard, durable, dry and free from dust, and soft or friable matter,
organic or other deleterious matter.
The fine aggregate shall have a sand equivalent value of not less than 50 when tested in
accordance with the requirement of IS:2720 (Part 37).
The Plasticity Index of the fraction passing the 0.425 mm sieve shall not exceed 4, when
tested in accordance with IS: 2720 (Part 5).
Table 5.7 (Table 500-8) Physical Requirements for Coarse Aggregate for Dense Graded Bituminous
Macadam
Property
Cleanliness(dust)
Particle shape
Strength*
Durability
Water Absorption
Stripping
Water Sensitivity**
Test
Grain size analysis1
Flakiness and Elongation Index
(Combined)2
Los Angeles Abrasion Value3
Aggregate Impact Value4
Soundness5
Sodium Sulphate
Magnesium Sulphate
Water absorption6
Coating and Stripping of Bitumen
Aggregate Mixtures7
Specification
Max 5% passing 0.075 mm sieve
Max 30 %
Min 80 %
Max 35 %
Max 27 %
Max 12 %
Max 18 %
Max 2 %
Minimum retained coating
95%
Filler :
(i)
Filler shall consist of finely divided mineral matter such as rock dust, hydrated lime or
cement approved by the Engineer.
(ii)
The filler shall be graded within the limits indicated in Table 5.8.
(iii)
5.6.5
0.3
95 100
0.075
85 100
The filler shall be free from organic impurities and have a Plasticity Index not greater than
4. The Plasticity Index requirement shall not apply if filler is cement or lime. When the
coarse aggregate is gravel, 2 per cent by weight of total aggregate, shall be Portland
cement or hydrated lime and the percentage of fine aggregate reduced accordingly.
Cement or hydrated lime is not required when the limestone aggregate is used. Where the
aggregates fail to meet the requirements of the water sensitivity test in Table 5.7, then 2
per cent by total weight of aggregate, of hydrated lime shall be added without additional
cost.
5.6.6
Table 5.9 (Table 500-10) Composition of Dense Graded Bituminous Macadam Pavement Layers
Grading
1
2
Nominal aggregate size
40 mm
25 mm
Layer Thickness
80 100 mm
50 75 mm
IS Sieve1 (mm)
Cumulative % by weight of total aggregate passing
45
100
37.5
95 100
100
26.5
63 93
90 100
19
71 95
13.2
55 75
56 80
9.5
4.75
38 - 54
38 54
2.36
28 42
28 42
1.18
0.6
0.3
7 21
7 21
0.15
0.075
28
28
Bitumen content % by
Min 4.0
Min 4.5
mass of total mix2
Bitumen grade (pen)
65 or 90
65 or 90
Notes: 1. The combined aggregate grading shall not vary from the low limit on one sieve to the
high limit on the adjacent sieve.
2. Determined by the Marshall method.
Table 5.10( Table 500-11) Requirements for Dense Graded Bituminous Macadam
Minimum stability (kN at 60oC)
9.0
57
2
4
75 blows on each of the
two faces of the specimen
Per cent air voids
36
Per cent voids in mineral aggregate (VMA) See Table 5.11 below
Per cent voids filled with bitumen (VFB)
65 75
The requirements for minimum per cent voids in mineral aggregate (VMA) are set out in
Table 5.11.
Table 5.11( Table 500-12) Minimum per cent Voids in Mineral Aggregate (VMA)
Nominal Maximum
Particle Size1 (mm)
5.6.7
Table 5.12(Table 500-13) Permissible Variations from the Job Mix Formula
Description
Permissible variation
Base/binder course
Wearing course
8%
7%
7%
6%
6%
5%
4%
2%
0.3%
10oC
5%
4%
3%
1.5%
0.3%
10oC
5.7.2
5.7.3
Scope :
This clause specified the construction of Semi Dense Bituminous Concrete, for use in
wearing/binder and profile corrective courses. This work shall consist of construction in a single
or multiple layers of semi dense bituminous concrete on a previously prepared bituminous bound
surface. A single layer shall be 25mm to 100mm in thickness.
Bitumen :
The bitumen shall be paving bitumen of Penetration grade complying with Indian Standard
Specification for Paving Bitumen, IS:73 and of the penetration indicated in Table 5.14, for semi
dense bituminous concrete, or this bitumen as modified by one of the methods specified in Clause
521, or as otherwise specified in the Contract. Guidance on the selection of an appropriate grade
of bitumen is given in the Manual for Construction and Supervision of Bituminous Works.
Coarse Aggregates :
The coarse aggregates shall be generally as specified in Clause 507.2.2, except that the aggregates
shall satisfy the physical requirements of Table 5.13.
Table 5.13(Table 500-14) Physical Requirements for Coarse Aggregate for Semi Dense
Bituminous Concrete Pavement Layers
Property
Cleanliness(dust)
Particle shape
Strength*
Polishing
Durability
Water Absorption
Stripping
Water Sensitivity**
Test
Grain size analysis1
Flakiness and Elongation Index
(Combined)2
Los Angeles Abrasion Value3
Aggregate Impact Value4
Polished Stone Value5
Soundness6
Sodium Sulphate
Magnesium Sulphate
Water absorption7
Coating and Stripping of Bitumen
Aggregate Mixtures9
Specification
Max 5% passing 0.075 mm sieve
Max 30 %
Min 80 %
Max 35 %
Max 27 %
Min 55
Max 12 %
Max 18 %
Max 2 %
Minimum retained coating
95%
Fine aggregates :
The fine aggregates shall be all as specified in Clause 507.2.3.
5.7.5
Filler :
Filler shall be generally as specified in Clause 507.2.4. Where the aggregates fail to meet
the requirements of the water sensitivity test in Table 5.13 then 2 per cent by total weight of
aggregate, of hydrated lime shall be added without additional cost.
5.7.6
5.7.7
5.7.8
Binder content :
The binder content shall be optimised to achieve the requirements of the mixture set out in
Table 5.15 and the traffic volume as specified in the Contract. The Marshall method for
determining the optimum binder content shall be adopted as described in the Asphalt Institute
Manual MS-2, replacing the aggregates retained on the 26.5mm sieve and retained on the 22.4mm
sieve, where approved by the Engineer.
Table 5.14 (Table 500-15) Composition of Semi Dense Bituminous Concrete Pavement
Layers
Grading
1
2
Nominal aggregate size
13 mm
10 mm
Layer Thickness
35 40 mm
25 30 mm
1
IS Sieve (mm)
Cumulative % by weight of total aggregate passing
45
60
37.5
26.5
19
100
13.2
90 100
100
9.5
70 - 90
90 100
4.75
35 - 51
35 51
2.36
24 39
24 39
1.18
15 - 30
15 30
0.6
0.3
9 19
9 19
0.15
0.075
38
38
Bitumen content % by
Min 4.5
Min 5.0
mass of total mix2
Bitumen grade
65*
65*
(penetration)
Notes: 1. The combined aggregate grading shall not vary from the low limit on one sieve to the
high limit on the adjacent sieve.
2. Determined by the Marshall method.
3. Only in exceptional circumstances, 80/100 penetration grade may be used, as approved by
the Engineer.
Table 5.15 ( Table 500-16) Requirements for Semi Dense Bituminous Pavement Layers
Minimum stability (kN at 60oC)
Minimum flow (mm)
Maximum flow (mm)
Compaction level (Number of blows)
Per cent air voids
Per cent voids in mineral aggregate (VMA)
Per cent voids filled with bitumen (VFB)
5.7.9
8.2
2
4
75 blows on each of the
two faces of the specimen
35
See Table 5.11
65 78
Scope :
This clause specifies the construction of Bituminous Concrete, for use in wearing and profile
corrective courses. This work shall consist of construction in a single or multiple layers of
61
bituminous concrete on a previously prepared bituminous bound surface. A single layer shall be
25mm to 100mm in thickness.
5.8.2
Bitumen :
The bitumen shall be paving bitumen of Penetration grade complying with Indian Standard
Specification for Paving Bitumen IS:73 and of the penetration indicated in Table 5.17, for
bituminous concrete, or this bitumen as modified by one of the methods specified in Clause 521,
or as otherwise specified in the Contract. Guidance on the selection of an appropriate grade of
bitumen is given in The Manual for Construction and Supervision of Bituminous Works.
5.8.3
Coarse Aggregates :
The coarse aggregates shall be generally as specified in Clause 507.2.2, except that the aggregate
shall satisfy the physical requirement of Table 5.16.
5.8.4
Fine Aggregate :
The fine aggregate shall be all as specified in Clause 507.2.3.
5.8.5
Filler :
Filler shall be generally as specified in Clause 507.2.4. Where the aggregate fail to meet the
requirements of the water sensitivity test in Table 5.16 then 2 per cent by total weight of
aggregate, of hydrated lime shall be added without additional cost.
5.8.6
5.8.7
5.8.8
Binder content :
The binder content shall be optimised to achieve the requirements of the mixture set out in Table
5.18 and the traffic volume as specified in the Contract. The Marshall method for determining the
optimum binder content shall be adopted as described in the Asphalt Institute Manual MS-2,
replacing the aggregates retained on the 26.5mm sieve and retained on the 22.4mm sieve, where
approved by the Engineer.
5.8.9
62
Table 5.16 (Table 500-17) Physical Requirements for Coarse Aggregate for Bituminous
Concrete Pavement Layers.
Property
Cleanliness(dust)
Particle shape
Strength*
Polishing
Durability
Water Absorption
Stripping
Water Sensitivity**
Test
Grain size analysis1
Flakiness and Elongation Index
Los Angeles Abrasion Value3
Aggregate Impact Value4
Polished Stone Value5
Soundness6
Sodium Sulphate
Magnesium Sulphate
Water absorption7
Coating and Stripping of Bitumen
Aggregate Mixtures9
Specification
Max 5% passing 0.075 mm sieve
Max 30 % (Combined)2
Max 30 %
Max 24 %
Min 55
Min 80 %
Max 12 %
Max 18 %
Max 2 %
Minimum retained coating
95%
Layer Thickness
50 65 mm
30 45 mm
1
IS Sieve (mm)
Cumulative % by weight of total aggregate passing
45
37.5
26.5
100
19
79 - 100
100
13.2
59 79
79 100
9.5
52 - 72
70 88
4.75
35 - 55
53 71
2.36
28 44
42 58
1.18
20 - 34
34 48
0.6
15 - 27
26 38
0.3
10 20
18 28
0.15
5 - 13
12 20
0.075
28
4 10
Bitumen content % by
5.0 6.0
5.0 7.0
mass of total mix2
Bitumen grade
65
65
(penetration)
Notes: 1. The combined aggregate grading shall not vary from the low limit on one sieve to the
high limit on the adjacent sieve.
2. Determined by the Marshall method.
Table 5.18 (Table 500-19) Requirements for Bituminous Pavement Layers
Minimum stability (kN at 60oC)
Minimum flow (mm)
Maximum flow (mm)
Compaction level (Number of blows)
Per cent air voids
Per cent voids in mineral aggregate (VMA)
Per cent voids filled with bitumen (VFB)
Loss of stability on immersion in water at
60oC (ASTM D 1075)
9.0
2
4
75 blows on each of the
two faces of the specimen
36
See Table 5.11
65 75
Min. 75 per cent
retained strength
Specifications. For information on the Design of Surface Dressing refer to the Manual for
Construction and Supervision of Bituminous Works.
5.9.2
Binder :
The binder shall have a kinematic viscosity lying in the range 1x10 4 to 7x105 centistokes at the
expected range of road surface temperatures at the construction site during the period of laying.
The type of binder to be used will be stated in the Contract documents and shall comply with one
of the following:
Paving Bitumen
IS: 73
Bitumen Emulsion
IS: 8887
5.9.3
Aggregates :
The chips shall conform to the requirements of Clause 504.2.2., except that their water absorption
shall be restricted to a maximum of 1 per cent and they shall have a Polished Stone value, as
measured by the method given in BS812 (Part 114), of not less than 60. The chips shall be single
sized, clean, hard, durable, of cubical shape, free from dust and soft or friable matter, organic or
other deleterious matter and conforming to one of the gradings given in Table 5.19 below.
Table 5.19(Table 500-21) Grading Requirements for Chips for Surface Dressing
IS Sieve
Designation
mm
26.5
19.0
13.2
9.5
6.3
4.75
3.35
2.36
0.60
0.075
Minimum 65%
by weight of
aggregate
5.9.4
Application of binder :
The equipment and general procedures shall all be in accordance with the Manual for
Construction and Supervision of Bituminous Works. The application temperature for the grade of
binder used shall be as given in Table 5.21 and the rate of spray as given in 510.2.3.
Table 5.21 (Table 500-22) Spraying Temperatures for Binders
Binder grades
Whirling spray jets
Slot jets
o
o
Min C
Max C
MinoC
MaxoC
Penetration Grades
400/500
160
170
140
150
280/320
165
175
150
160
180/200
170
190
155
165
80/100
180
200
165
175
5.10
5.10.1 Scope :
This work shall consist of the preparation, laying and compaction of an open-graded premix
surfacing material of 20mm thickness composed of small-sized aggregate premixed with a
66
5.11
0.18m3
0.09 m3
0.27 m3
9.5 kg
5.1 kg
14.6 kg
5.11.1 Scope :
67
This work shall consist of the preparation, laying and compaction of an open graded premix
surfacing of 20mm thickness composed of small-sized aggregate premixed with a cationic
bitumen emulsion on a previously prepared surface, in accordance with the requirements of
MoRT&H Specifications, to serve as a wearing course.
5.11.2 Binder :
The binder for Premix wearing course shall be cationic bitumen emulsion of Medium Setting
(MS) grade complying with I.S.8887 and having a bitumen content 65 per cent minimum by
weight. For liquid seal coat RS grade of Cationic bitumen emulsion shall be used. Where
expressly specified in the Contract MS grade emulsion shall be used or otherwise directed by the
Engineer. Slow Setting (SS) grade Cationic bitumen Emulsion shall be used for premix seal coat.
5.11.3 Aggregate :
The requirements of Clause 511.1.2.2 shall apply.
5.11.4 Proportioning of materials :
The materials shall be proportional as quantities given in Tables 5.23 and 5.24.
Table 5.23(Table 500-24) Quantities of Aggregate for 10m2 Area
(A)
(a)
(b)
(B)
Premix Carpet
Coarse aggregate nominal 13.2 mm size; passing IS
22.4mm sieve and retained on IS 11.2 mm sieve
Coarse aggregate nominal 11.2 mm size; passing IS
13.2mm sieve and retained on IS 5.6 mm sieve
For Seal Coat
Refer to Clause 513.
0.18m3
0.09 m3
5.12
12 to 14 kg
10 to 12 kg
5.12.1 Scope :
(i)
This work shall consist of the preparation, laying and compaction of a close-graded
premix surfacing material of 20 mm thickness composed of graded aggregates premixed
with a bituminous binder on a previously prepared surface, in accordance with the
requirements of MoRT&H Specifications, to serve as a wearing course.
(ii)
Close graded premix surfacing shall be of Type A or Type B as specified in the Contract
documents.
5.12.2 Binder :
The provisions of Clause 511.1.2.1 shall apply.
5.12.3 Coarse aggregates :
The provisions of Clause 511.1.2.2 shall apply.
5.12.4 Fine aggregates:
The fine aggregates shall consist of crushed rock quarry sands, gravel/ sand or a mixture of both.
These shall be clean, hard, durable, un-coated, mineral particles, dry and free from injurious, soft
or flaky particles and organic or deleterious substances.
5.12.5 Aggregate gradation:
The coarse and fine aggregates shall be so graded or combined as to confirm to one or the other
gradings shown in Table 5.25 below as specified in the Contract.
Table 5.25 (Table 500-26) Aggregate Gradation
IS Sieve
Designation
(mm)
13.2 mm
11.2 mm
5.6 mm
2.8 mm
0.090 mm
(i)
This work shall consist of the application of a seal coat for sealing the voids in a
bituminous surface laid to the specified levels, grade and cross fall (camber).
(ii)
(A) Liquid seal coat comprising of an application of a layer of bituminous binder followed by a
cover of stone chips.
(B) Premixed seal coat comprising of a thin application of fine aggregate premixed with
bituminous binder.
5.13.2 Binder :
(i)
(ii)
The quantity of bitumen per 10 square metres, shall be 9.8 kg for Type A, and 6.8 kg for
Type B seal coat. Where bituminous emulsion is used as a binder the quantities for Type A
and Type B seal coats shall be 15 kg and 10.5 kg respectively.
Bitumen shall be heated to 150oC-163oC and sprayed at the rate specified on the dry
surface in a uniform manner with a self-propelled mechanical sprayer as described in the
Manual for Construction and Supervision of Bituminous Works.
(ii)
Immediately after the application of binder, stone chips, which shall be clean and dry, shall
be spread uniformly at the rate specified on the surface preferably by means of a selfpropelled or towed mechanical grit spreader so as to cover the surface completely. If
necessary, the surface shall be brushed to ensure uniform spread of chips.
70
(iii)
Immediately after the application of the cover material, the entire surface shall be rolled
with a 8 10 tonne smooth wheeled steel roller, 8 10 tonne static weight vibratory roller,
or other equipment approved by the Engineer after laying trials if required.
Rolling shall commence at the edges and progress towards the centre except in superelevated and unidirectional cambered portions where it shall proceed from the lower edge
to the higher edge. Each pass of the roller shall uniformly overlap not less than one-third
of the track made in the preceding pass. While rolling is in progress, additional chips shall
be spread by hand in necessary quantities required to make up irregularities. Rolling shall
continue until all aggregate particulars are firmly embedded in the binder and present a
uniform closed surface.
A mixer of appropriate capacity and type approved by the Engineer shall be used for
preparation of the mixed material. The plant shall have separate dryer arrangements for
heating aggregate.
(ii)
The binder shall be heated in boilers of suitable design, approved by the Engineer to the
temperature appropriate to the grade of bitumen or as directed by the Engineer. The
aggregates shall be dry and suitably heated to a temperature between 150 oC and 165oC or
as directed by the Engineer before these components are placed in the mixer. Mixing of
binder with aggregates to the specified proportions shall be continued until the latter are
thoroughly coated with the former.
(iii)
The mix shall be immediately transported from the mixing plant to the point of use and
spread uniformly on the bituminous surface to the sealed.
(iv)
As soon as a sufficient length has been covered with the premixed material, the surface
shall be rolled with an 8 10 tonne smooth-wheeled roller. Rolling shall be continued
until the premixed material completely seals the voids in the bituminous course and a
smooth uniform surface is obtained.
5.14.1 Scope :
(i)
This work shall consist of constructing of a single layer of mastic asphalt wearing course
for road pavements and bridge decks.
(ii)
5.14.2 Binder:
Subject to the approval of the Engineer, the binder shall be a paving grade bitumen meeting the
requirements given in Table 5.26.
5.14.3 Coarse Aggregate:
(i)
The coarse aggregate shall consist of crushed stone, crushed gravel/ shingle or other
stones. They shall be clean, hard, durable, of fairly cubical shape, uncoated and free from
soft, organic or other deleterious substances. They shall satisfy the physical requirements
given in Table 5.3.
(ii)
The percentage and grading of the coarse aggregate to be incorporated in the mastic
asphalt depending upon the thickness of the finished course shall be as specified in Table
5.27 below.
Table 5.27 (Table 500-30) Grade and Thickness of Mastic Asphalt paving, and
Grading of Coarse Aggregate
72
Application
Thickness
range(mm)
Nominal size
of coarse
aggregate(mm)
13
13
Coarse aggregate
content, % by
mass of total mix
40 10
45 10
13 mm
Cumulative % passing by weight
100
88 96
05
The filler shall be limestone powder passing the 0.075 mm sieve and shall have a calcium
carbonate content of not less than 80 percent by weight when determined in accordance
with IS: 1514.
(ii)
The grading of the fine aggregate inclusive of filler shall be as given in Table 5.28 below.
Table 5.28(Table 500-31) Grading of Fine Aggregate (Inclusive of Filler)
IS Sieve (mm)
Passing 2.36 mm but retained on 0.600 mm
Passing 0.600 mm but retained on 0.212 mm
Passing 0.212 mm but retained on 0.075 mm
Passing 0.075
Slurry seal are mixtures of fine aggregate, Portland cement filler, bitumen emulsion and additional
water. When freshly mixed, they have a thick consistency and can be spread to a thickness of 1.5
5 mm. They may be used to seal cracks, arrest fretting and fill voids and minor depressions, to
provide a more even riding surface or a base for further treatment; they may also be used on top of
a single coat surface dressing.
5.15.2 Emulsified bitumen :
The emulsified bitumen shall be a cationic rapid setting type as approved by the Engineer,
conforming to the requirements of IS:8887. Where special mobile mixing machines are available,
Class A4* rapid setting or Class K3* road emulsions to BS 434: Part 1 should be used to obtain
very early resistance to traffic and rain. Generally, emulsion for slurry seal should be capable of
producing a slurry that will develop early resistance to traffic and rain and is sufficiently stable to
permit mixing with the specified aggregate, without breaking during the mixing and laying
processes. If approved by the Engineer, a slow setting emulsion may be used. Guidance on
selection of an appropriate grade of emulsion is given in the Manual for Construction and
Supervision of Bituminous Works.
5.15.3 Water :
(i)
Water shall be of such quality that the bitumen will not separate from the emulsion before
the slurry seal is in place.
(ii)
The pH of the water must lie in the range 4 to 7, and if the total dissolved solids in the
water amount to more than 500ppm, the Engineer may reject it, or order the Contractor to
conduct a trial emulsion mix to demonstrate that it does not cause early separation.
5.15.4 Aggregate :
The aggregate shall be crushed rock, or slag and may be blended, if required, with clean, sharp,
naturally occurring sand free from soft pieces and organic and other deleterious substances to
produce a grading as given in Table 5.29. The aggregates shall meet the requirements of the film
stripping test (IS:6241), and a suitable amount and type of anti-stripping agent added, as may be
needed (details given in Appendix 5).
5.15.5 Additives :
It is usual to use ordinary Portland cement, hydrated lime or other additives to control consistency,
mix segregation and setting rate. The proportion of the additive should not normally exceed 2
percent by weight of dry aggregates.
Table 5.29(Table 500-33) Aggregate Grading, Binder Content and Approximate Coverage
Rate
Sieve Size (mm)
9.5
4.75
3.35
2.36
1.18
0.600
0.300
0.150
0.075
Quantity or residual binder,
percentage by mass of
aggregate
Approximate coverage
rate(kg/m2)
5 mm
100
90-100
65-90
45-70
30-50
18-30
10-21
5-15
7.5 13.5
3 mm
100
80-100
75-100
55-90
35-70
20-45
10-25
5-15
10 - 16
1.5 mm
100
95-100
70-95
55-75
30-50
10-30
5-15
12 - 20
8 - 15
4-6
2-4
(ii)
Before use these emulsions shall be diluted, 1 part emulsion to 1 part water. Alternatively,
Class A 1-40* or K1-40* emulsions complying with the requirements of BS434:Part
1:1984 may be used. These emulsions have a lower viscosity than the above ASTM
grades, they are rapid setting and they do not require to be diluted. Because of their low
viscosity they should be used as soon as possible after delivery. If this is not possible, the
drums should be very thoroughly rolled before use.
75
Spraying shall not take place when the temperature is below 10 oC, nor in windy or dusty
conditions, nor when it is raining or the surface to be sprayed is wet (a damp surface is acceptable
but refer to Clause 518.4.2).
5.17 MODIFIED BINDER
5.17.1 Scope :
Modified binders comprise a base binder, to which is added either natural rubber, crumb rubber or
a polymer. The purpose is to achieve a high performance binder with improved properties,
particularly at extremes of temperature.
5.17.2 Base Binder :
The base binder into which the modifier is incorporated shall conform to IS: 73. The choice of
grade shall be such that it is compatible with the modifier and, when mixed shall have the
properties described in Clause 521.3.
5.17.3 Modifier :
The modifier shall be a natural rubber, crumb rubber or any other polymer which is compatible
with the base binder and which allows the properties given in Clause 521.3 to be achieved. For
further details, IRC:SP:53-1999 may be referred to. The modifier, in the required quantity shall be
blended at the refinery or at the site plant capable of producing modified binder.
5.17.4 Modifier Proportions :
The quantity of modifier to be added shall be determined by tests on the base binder and the
modified binder and the properties desired. A reference may be made to the Manual for
Construction and Supervision of Bituminous Works for indicative dosage of different types of
modifiers. The properties of the modified binder shall be as given in Table 5.30 and 5.31.
according to the requirements of the Contract.
Designation
Method of Test
IS:1203-1978
18
IS:1205-1978
59
-12
50
220
50
(30)**
4
4-8
IS:1205-1978
IS:9381-1978
IS:1208-1978
IS:1209-1978
ASTM
D5976-1996
ASTM
D5976-1996
IS:1206-1978
12
IS:1203-1978
1.0
5
IS:9382-1979
IS:1205-1978
35
IS:1203-1978
35
(25)**
ASTM
D5976-1996
Table 5.31(Table 500-46) Requirements of Polymer Modified Binders (Treated with Modified
Crumb Rubber)
77
Designation
CRMB
70
50-60
Method of
Test
CRMB4
0
40-60
IS:1203-1978
55
60
IS:1205-1978
35
30
ASTM
D5976-1996
60
60
IS:1203-1978
IS:1205-1978
20
15
ASTM
D5976-1996
The rates of spread of binder and aggregate shall be according to one of the size alternatives in
Table 5.32, as specified by the Contract.
Table 5.32 (Table 500-47) Quantity of Materials Required for 10 Sq.m of Road Surface for
Stress Absorbing membrane
Sl.
No
Specification of SAM
to be applied
1.
2.
3.
4.
5.
6.
7.
12 14
Reference
Item
Descriptions
79
Unit
Rate
No
5.1
to
MoRT&H
Specificat
ions
502
In
figure
s
(`)
No.
Prime coat
Providing and applying primer
coat with bitumen emulsion on
prepared surface of granular base
including clearing of road surface
and spraying primer at the rate of
0.60 kg/sqm using mechanical
means.
I. Low Porosity
II. Medium Porosity
III.High Porosity
5.2
503
(i)
(ii)
(iii)
(iv)
(v)
5.3
In words
504
(i)
(ii)
Tack coat.
Providing and applying tack coat
with bitumen emulsion using
emulsion pressure distributor at
the rate of 0.20 kg per sqm on the
prepared
bituminous/granular
surface cleaned with mechanical
broom.
Normal Bituminous surface @
0.25kg/sqm
Dry
and
Hungry
Bituminous
Surface @0.3kg/sqm
Granular surface treated with
primer @0.3kg/sqm
Non
bituminous
surface
@0.4kg/sqm
Cement
Concrete
base
@0.35kg/sqm
Bituminous Macadam
Providing and laying bituminous
macadam with 100-120 TPH hot
mix plant producing an average
output of 75 tonnes per hour using
crushed aggregates of specified
grading premixed with bituminous
binder, transported to site, laid
over a previously prepared surface
with paver finisher to the required
grade, level and alignment and
rolled as per Clauses 501.6 and
501.7 to achieve the desired
compaction
For Grading I ( 40 mm nominal
size )
For GradingII (19 mm nominal
size)
80
sqm
59.00
sqm
77.00
sqm
95.00
sqm
17.00
Rupees Seventeen
Only
sqm
20.00
sqm
20.00
sqm
26.00
sqm
23.00
cum
9571.0
0
cum
9703.0
0
Rupees Nine
Thousand Five
Hundred and Seventy
One Only
Rupees Nine
Thousand Seven
5.5
506
Built-Up-Spray Grout:
507
(i)
(ii)
5.6
508
sqm
445.00
cum
11059.
00
cum
11060.
00
Semi
Concrete
Dense
Bituminous
81
Rupees Eleven
Thousand and Fifty
Nine Only
Rupees Eleven
Thousand and Sixty
Only
I
(i)
(ii)
II
(i)
(ii)
III
(i)
(ii)
5.7
509
82
cum
11904.
00
cum
12744.
00
cum
12933.
00
cum
13888.
00
cum
12055.
00
cum
12911.
00
Rupees Eleven
Thousand Nine
Hundred and Four
Only
Rupees Twelve
Thousand Seven
Hundred and Forty
Four Only
Rupees Twelve
Thousand Nine
Hundred and Thirty
Three Only
Rupees Thirteen
Thousand Eight
Hundred Eighty Eight
Only
Rupees Twelve
Thousand and Fifty
Five Only
Rupees Twelve
Thousand Nine
Hundred and Eleven
Only
I
(i)
(ii)
II
(i)
(ii)
III
(i)
(ii)
5.8
510
cum
13174.
00
cum
13184.
00
cum
14342.
00
cum
14351.
00
cum
13345.
00
cum
13355.
00
Rupees Thirteen
Thousand One
Hundred and
Seventy Four Only
Rupees Thirteen
Thousand One
Hundred and Eighty
Four Only
83
Rupees Fourteen
Thousand Three
Hundred and Forty
Two Only
Rupees Fourteen
Thousand Three
Hundred and Fifty
One Only
Rupees Thirteen
Thousand Three
Hundred and Forty
Five Only
Rupees Thirteen
Thousand Three
Hundred and Fifty
Five Only
Case
I
Case
II
5.9
511
Case
I
i
ii
iii
Case
II
5.1
0
512.00
84
sqm
126.00
sqm
103.00
sqm
195.00
sqm
209.00
sqm
197.00
sqm
235.00
sqm
250.00
Type B
sqm
II
Type B
III
Crumb
rubber
Bitumen(CRMB-55)
Type A
513
(i)
(ii)
5.1
2
5.1
3
515
516
sqm
272.00
sqm
245.00
sqm
254.00
sqm
230.00
sqm
97.00
sqm
73.00
Rupees Seventy
Three Only
sqm
1008.0
0
Modified
Type B
5.1
1
227.00
Seal Coat
Providing and laying seal coat
sealing the voids in a bituminous
surface laid to the specified levels,
grade and cross fall using Type A
and B seal coats
Providing and laying of premix
sand seal coat with HMP of
appropriate capacity not less than
75 tonne/ hours using crushed
stone chipping 6.7 mm size and
penetration bitumen of suitable
grade.
Mastic Asphalt
Providing and laying 25 mm thick
mastic asphalt wearing course
with
paving
grade
bitumen
meeting the requirements given in
Table 500-29, prepared by using
mastic cooker and laid to required
level and slope after cleaning the
surface,
including
providing
antiskid surface with bitumen
precoated fine-grained hard stone
chipping of 13.2 mm nominal size
at the rate of 0.005 cum per 10
sqm and at an approximate
spacing of 10 cm center to center
in both directions, pressed into
surface when the temperature of
surfaces is not less than 100 C,
protruding 1 mm to 4 mm over
mastic surface, all complete as per
Clause 515
Slurry Seal:
Providing and laying slurry seal
consisting of a mixture of fine
aggregates, portland cement filler,
bituminous emulsion and water on
85
Rupees One
Thousand and Eight
Only
i.
5.1
4
85.00
sqm
58.00
sqm
35.00
sqm
48.00
sqm
56.00
i. PMB-70
sqm
102.00
ii. CRMB-55
sqm
94.00
3 mm thickness
iii
1.5 mm thickness
518
(i)
Case
I
sqm
ii.
(ii)
5.1
5
Fog Spray
Providing
and
applying
low
viscosity bitumen emulsion for
sealing cracks less than 3 mm
wide or incipient fretting or
disintegration
in
an
existing
bituminous surfacing.
.In case it is decided by the
engineer to blind the fog spray,
the following may be added
Crack Prevention Courses
Stress Absorbing Membrane
(SAM) crack width less than 6
mm:
Providing and laying of a stress
absorbing membrane over a
cracked road surface, with crack
width below 6 mm after cleaning
with a mechanical broom, using
modified binder complying with
clause 521, sprayed at the rate of
9 kg per 10 sqm and spreading 5.6
mm crushed stone aggregates @
0.11 cum per 10 sqm with
hydraulic chip spreader, sweeping
the surface for uniform spread of
aggregates and surface finished to
conform to Clause 902.
Case
II
86
11.2
mm
crushed
stone
aggregates @ 0.12 cum per 10
sqm, sweeping the surface for
uniform spread of aggregates and
surface finished to conform to
Clause 902.
Case
III
i. PMB-70
sqm
118.00
ii.CRMB-55
sqm
109.00
sqm
156.00
sqm
143.00
87
CHAPTER 6
6. CEMENT CONCRETE
6.1 DRY LEAN CEMENT CONCRETE SUB-BASE
6.1.1
6.1.2
Scope :
(i)
The work shall consist of construction of dry lean concrete sub-base for cement concrete
pavement in accordance with the requirements of these Specifications and in conformity
with the lines, grades and cross-sections shown on the drawings or as directed by the
Engineer. The work shall include furnishing of all plant and equipment, materials and
labour and performing all operations, in connection with the work, as approved by the
Engineer.
(ii)
The design parameters of dry lean concrete sub-base, viz., width, thickness, grade of
concrete, details of joints, if any, etc, shall be as stipulated in the Contract drawings.
Materials :
The Contractor shall indicate to the Engineer the source of all materials with relevant test data to
be used in the lean concrete work sufficiently in advance and the approval of the Engineer for the
same shall be obtained at least 45 days before the scheduled commencement of the work. If the
Contractor later proposed to obtain the materials from a different source, he shall notify the
Engineer for his approval at least 45 days before such materials are to be used.
6.1.3
Cement :
(i) Any of the following types of cement may be used with prior approval of the Engineer.
(a)
IS: 269
(b)
IS: 455
(c)
IS: 1489
(ii) If the subgrade is found to consist of soluble sulphates in a concentration more than 0.5 per
cent, cement used shall be sulphate resistant and shall conform to IS:6909.
88
(iii)
Cement to be used may preferably be obtained in bulk form. It shall be stored in accordance
with stipulation contained in Clause 1014 and shall be subjected to acceptance test prior to its
immediate use.
6.1.4
Aggregates :
Aggregates for lean concrete shall be natural material complying with IS:383. The aggregates
shall not be alkali reactive. The limits of deleterious materials shall not exceed the requirements
set out in IS:383. In case the Engineer considers that the aggregates are not free from dirt, the
same may be washed and drained for at least 72 hours before batching, as directed by the
Engineer.
6.1.5
Coarse Aggregates :
Coarse aggregates shall consist of clean, hard, strong, dense, non-porous and durable pieces of
crushed stone or crushed gravel and shall be devoid of pieces of disintegrated stone, soft, flaky,
elongated, very angular or splintery pieces. The maximum size of the coarse aggregate shall be 25
mm. The coarse aggregate shall comply with Clause 602.2.4.2.
6.1.6
Fine aggregates :
(i)
The fine aggregate shall consist of clean, natural sand or crushed stone sand or a
combination of the two and shall conform to IS:383. Fine aggregate shall be free from soft
particles, clay, shale, loam, cemented particles, mica, organic and other foreign matter. The
fine aggregate shall comply with Clause 602.2.4.3.
(ii)
The coarse and fine aggregates may be obtained in either of the following manner :
(a)
In separate nominal sizes of coarse and fine aggregates and mixed together intimately before use.
(b)
Separately as 25mm nominal single size, 12.5 mm nominal size graded aggregates and fine aggregate of
crushed stone dust or sand or a combination of these two.
(iv)
The material after blending shall conform to the grading as indicated in Table 6.1.
26.50 mm
19.00 mm
9.50 mm
4.75 mm
600.00 micron
75.00 micron
89
6.1.7
Water :
Water used for mixing and curing of concrete shall be clean and free from injurious amounts of
oil, salt, acid, vegetable matter or other substances harmful to the finished concrete. It shall meet
the requirements stipulated in IS: 456.
6.2.2
Scope :
(i)
The work shall consist of construction of unreinforced, dowel jointed, plain cement
concrete pavement in accordance with the requirements of MoRT&H Specifications and in
conformity with the lines, grades and cross sections shown on the drawings. The work
shall include furnishing of all plant and equipment, materials and labour and performing
all operations in connection with the work, as approved by the Engineer.
(v)
The design parameters, viz., thickness of pavement slab, grade of concrete, joint details
etc. shall be as stipulated in the drawings.
Source of materials :
The Contractor shall indicate to the Engineer the source of all materials to be used in the concrete
work with relevant test data sufficiently in advance, and the approval of the Engineer for the same
shall be obtained as least 45 days before the scheduled commencement of the work. If the
Contractor later proposed to obtain materials from a different source, he shall notify the Engineer
for his approval, at least 45 days before such materials are to be used with relevant test data.
6.2.3
Cement :
(i)
Any of the following types of cement capable of achieving the design strength may be
used with prior approval of the Engineer, but the preference should be to use at least the 43
Grade or higher.
(a)
(b)
(c)
(ii)
If the soil around has soluble salts like sulphates in excess of 0.5 per cent, the cement used
shall be sulphate resistant and shall conform to IS: 12330.
(iii)
Guidance may be taken from IS: SP: 23, Handbook for Concrete Mixes for ascertaining
the minimum 7 days strength of cement required to match with the design concrete
strength. Cement to be used may preferably be obtained in bulk form. If cement in paper
bags are proposed to be used, there shall be bag-splitters with the facility to separate
90
pieces of paper bags and dispose them of suitably. No paper pieces shall enter the concrete
mix. Bulk cement shall be stored in accordance with Clause 1014. The cement shall be
subjected to acceptance test just prior to its use.
6.2.4
Admixtures :
Admixtures conforming to IS:6925 and IS:9103 shall be permitted to improve workability of the
concrete or extension of setting time, on satisfactory evidence that they will not have any adverse
effect on the properties of concrete with respect to strength, volume change, durability and have
no deleterious effect on steel bars. The particulars of the admixture and the quantity to be used,
must be furnished to the Engineer in advance to obtain his approval before use. Satisfactory
performance of the admixtures should be proved both on the laboratory concrete trial mixes and in
trial paving works. If air entraining admixture is used, the total quantity of air in air-entrained
concrete as a percentage of the volume of the mix shall be 5 1.5 per cent for 25mm nominal size
aggregate.
6.2.5
6.2.6
6.2.7
Aggregates :
(i)
Aggregates for pavement concrete shall be natural material complying with IS: 383 but
with a Los Angeles Abrasion Test result not more than 35 per cent. The limits of
deleterious materials shall not exceed the requirements set out in IS: 383.
(ii)
The aggregates shall be free from chert, flint, chalcedony or other silica in a form that can
react with the alkalies in the cement. In addition, the total chlorides content expressed as
chloride ion content shall not exceed 0.06 per cent by weight and the total sulphate content
expressed as sulphuric anhydride (SO3) shall not exceed 0.25 per cent by weight.
Coarse aggregates :
(i)
Coarse aggregate shall consist of clean, hard, strong, dense, non-porous and durable pieces
of crushed stone or crushed gravel and shall be devoid of pieces of disintegrated stone,
soft, flaky, elongated, very angular or splintery pieces. The maximum size of coarse
aggregate shall not exceed 25mm for pavement concrete. Continuously graded or gap
graded aggregates may be used, depending on the grading of the fine aggregate. No
aggregate which has water absorption more than 2 per cent shall be used in the concrete
mix. The aggregates shall be tested for soundness in accordance with IS: 2386 (Part-5).
After 5 cycles of testing the loss shall not be more than 12 per cent if sodium sulphate
solution is used or 18 per cent if magnesium sulphate solution is used.
(ii)
Dumping and stacking of aggregates shall be done in an approved manner. In case the
Engineer considers that the aggregates are not free from dirt, the same may be washed and
drained for at least 72 hours before batching as directed by the Engineer.
Fine aggregates :
The fine aggregate shall consist of clean natural sand or crushed stone sand or a combination of
the two and shall conform to IS: 383. Fine aggregate shall be free from soft particles, clay, shale,
loam, cemented particles, mica and organic and other foreign matter. The fine aggregate shall not
contain deleterious substances more than the following :
91
6.2.8
Clay lumps
Water :
Water used for mixing and curing of concrete shall be clean and free from injurious amount of oil,
salt, acid, vegetable matter or other substances harmful to the finished concrete. It shall meet the
requirements stipulated in IS: 456.
6.2.9
Dowel bars shall be mild steel rounds in accordance with Clause 602.2.6 with
details/dimensions as indicated in the drawing and free from oil, dirt, loose rust or scale.
They shall be straight, free of irregularities and burring restricting slippage in the concrete.
The sliding ends shall be sawn or cropped cleanly with no protrusions outside the normal
diameter of the bar.
(ii)
Unless shown otherwise on the drawings, dowel bars shall be positioned at mid depth of
the slab within a tolerance of 20mm, and centered equally about intended lines of the
joint within a tolerance of 25mm. They shall be aligned parallel to the finished surface
of the slab and to the centre line of the carriageway and to each other within tolerances
given hereunder, the compliance of which shall be checked as per Clause 602.10.7.
(iii)
Dowel bars shall be covered by a thin plastic sheath for at least two-thirds of the length
from end for dowel bars in contraction joints or half the length plus 50 mm for expansion
joints.
Tie bars in longitudinal joints shall be deformed steel bars of strength 415 MPa complying
with IS:1786 and in accordance with the requirements given below. The bars shall be free
from oil, dirt, loose rust and scale.
(ii)
Tie bars projecting across the longitudinal joint shall be protected from corrosion for
75mm on each side of joint by a protective coating of bituminous paint with the approval
of the Engineer. The coating shall be dry when the tie bars are used.
Number of
Measurement
An average of 5
measurements
An average of 5
measurements
93
1.00
0.25
-0.35
traffic.
6.3
6.3.1
6.3.2
Scope :
(i)
The work shall consist of construction of rolled concrete base course for cement concrete
pavement in accordance with the requirements of MoRT&H Specifications and in
conformity with the lines, grades and cross sections shown on the drawings or as directed
by the Engineer. The work shall include furnishing of all plant and equipment, material
and labour and performing all operations in connection with the work, as approved by the
Engineer.
(ii)
The design parameters of rolled cement concrete base course viz., width, thickness, grade
of concrete, details of joints, if any, etc. shall be as stipulated in the contract drawings.
Materials :
The Contractor shall indicate to the Engineer the source of all materials to be used in the lean
concrete work with relevant test data sufficiently in advance and the approval of the Engineer for
the same shall be obtained at least 60 days before the scheduled commencement of the work. If
the Contractor later proposes to obtain the materials from a different source, he shall notify the
Engineer for his approval at least 60 days before such materials are to be used.
6.3.3
Cement :
Any of the following types of cement may be used with prior approval of the Engineer.
(i)
(ii)
IS: 455
(iii)
If the subgrade is found to consist of soluble sulphates in a concentration more than 0.5 per cent,
cement used shall be sulphate resistant and shall conform to IS: 12230. Cement to be used may
preferably be obtained in bulk form. It shall be stored in accordance with stipulated contained in
Clause 1014 and shall be subjected to acceptance test prior to its immediate use.
6.3.4
Aggregates :
Aggregates for lean concrete shall be natural material complying with IS: 383. The aggregates
shall not be alkali reactive. The limits of deleterious materials shall not exceed the requirements
94
set out in IS: 383. In case the Engineer considers that the aggregates are not free from dirt, the
same may be washed and drained for at least 72 hours before batching as directed by the
Engineer.
6.3.5
Coarse aggregate :
Coarse aggregates shall consist of clean, hard, strong, dense, non-porous and durable pieces of
crushed stone or crushed gravel and shall be devoid of pieces of disintegrated stone, soft, flaky,
elongated, very angular or splintery pieces. The maximum size of the coarse aggregate shall be
25mm. The coarse aggregate shall comply with the Clause 602.2.4.2.
6.3.6
Fine aggregate :
(i)
The fine aggregate shall consist of clean natural sand or crushed stone sand or a
combination of the two and shall conform to IS: 383. Fine aggregate shall be free from
soft particles, clay, shale, loam, cemented particles, mica, organic and other foreign matter.
The fine aggregate shall comply with the Clause 602.2.4.3.
(ii)
The coarse and fine aggregates may be obtained in either of the following manner:-
(a)
In separate nominal sizes of coarse and fine aggregates and mixed together intimately
before use.
(b)
Separately as 25mm nominal single size, 12.5mm nominal size graded aggregate and fine
aggregate of crushed stone dust or sand or a combination of these two.
(iii)
The material after blending shall conform to the grading as indicated in Table 6.3 below:
Table 6.3(Table 600-4) Aggregate Gradation for Dry Lean Concrete
Sieve Designation
37.5 mm
19.0 mm
9.5 mm
4.75 mm
600 micron
75 micron
95
Sl
No
6.1
6.2
Reference
to
MoRT&H
Specificat
ions
601
602
Rate
Item
No.
Descriptions
Unit
In
figure
s
(`)
In words
96
cum
cum
4342.0
0
7931.0
0
Rupees Four
Thousand Three
Hundred and Forty
Two Only
Rupees Seven
Thousand Nine
Hundred and Thirty
One Only
expansion,
construction
and
longitudinal joints, joint filler,
separation membrane, sealant
primer, joint sealant, debonding
strip,
dowel
bar,
tie
rod,
admixtures as approved, curing
compound, finishing to lines and
grades as per drawing
6.3
603
Rolled
Base:
Cement
Concrete
97
cum
4483.0
0
Rupees Four
Thousand Four
Hundred and Eighty
Three Only
CHAPTER 7
7. PIPE CULVERTS
7.1
DESCRIPTION
7.1.1
Scope :
7.1.2
This work shall consist of furnishing and installing reinforced cement concrete pipes, of the type,
diameter and length required at the locations shown on the drawings or as ordered by the Engineer
and in accordance with the requirements of MoRT&H Specifications.
Materials :
(i)
(ii)
All materials used in the construction of pipe culverts shall conform to the requirements of
Section 1000 of MoRT&H Specifications.
Each consignment of cement concrete pipes shall be inspected, tested, if necessary, and
approved by the Engineer either at the place of manufacture or at the site before their
incorporation in the works.
7.2
7.2.1
The foundation bed for pipe culverts shall be excavated true to the lines and grades shown on the
drawings or as directed by the Engineer. The pipes shall be placed in shallow excavation of the
natural ground or in open trenches cut in existing embankments, taken down to levels as shown on
the drawings. In case of high embankments where the height of fill is more than three times the
external diameter of the pipe, the embankment shall first be built to an elevation above the top of
the pipe equal to the external diameter of the pipe, and to width on each side of the pipe of not
less than five times the diameter of pipe, after which a trench shall be excavated and the pipe shall
be laid.
98
7.2.2
Where trenching is involved, its width on either side of the pipe shall be a minimum of 150 mm or
one-fourth of the diameter of the pipe whichever is more and shall not be more than one-third the
diameter of the pipe. The sides of the trench shall be as nearly vertical as possible.
7.2.3
The pipe shall be placed where the ground for the foundation is reasonably firm. Installation of
pipes under existing bridges or culverts shall be avoided as far as possible. When during
excavation the material encountered is soft, spongy or other unstable soil, and unless other special
provisions, such unsuitable material shall be removed to such depth, width and length as directed
by the Engineer. The excavation shall then be backfilled with approved granular material which
shall be properly shaped and thoroughly compacted upto the specified level.
7.2.4
Where bed-rock or boulder strata are encountered, excavation shall be taken down to at least 200
mm below the bottom level of the pipe with prior permission of the Engineer and all
rock/boulders in this area be removed and the space filled with approved earth, free from stone or
fragmented material, shaped to the requirements and thoroughly compacted to provide adequate
support for the pipe.
Trenches shall be kept free from water until the pipes are installed and the joints have hardened.
7.2.5
7.4.1
The bedding surface shall provide a firm foundation of uniform density throughout the length of
the culvert, shall conform to the specified levels and grade, and shall be of one of the following
two types as specified on the drawings :
(i)
First Class bedding : Under first class bedding, the pipe shall be evenly bedded on a
continuous layer of well compacted approval granular material, shaped concentrically to
fit the lower part of the pipe exterior for at least ten per cent of its overall height or as
otherwise shown on the drawings. The bedding material shall be well graded sand or
another granular material passing 5.6 mm sieve suitably compacted/ rammed. The
compacted thickness of the bedding layer shall be as shown on the drawings and in no
case shall it be less than 75 mm.
(ii)
Concrete cradle bedding : When indicated on the drawings or directed by the Engineer, the
pipe shall be bedded in a cradle constructed of concrete having a mix not leaner than M 15
conforming to Section 1700. The shape and dimensions of the cradle shall be as indicated
on the drawings. The pipes shall be laid on the concrete bedding before the concrete has
set.
7.4 LAYING OF PIPE
No pipe shall be laid in position until the foundation has been approved by the Engineer. Where
two or more pipes are to be laid adjacent to each other, they shall be separated by a distance equal
to at least half the diameter of the pipe subject to a minimum of 450 mm.
99
7.4.2
The arrangement for lifting, loading and unloading concrete pipes from factory/yard and at site
shall be such that the pipes do not suffer any undue structural strain, any damage due to fall or
impact. The arrangement may be got approved by the Engineer.
7.4.3
Similarly, the arrangement for lowering the pipe in the bed shall be got approved by the Engineer.
It may be with tripod-pulley arrangement or simply by manual labour in a manner that the pipe is
placed in the proper position without damage.
7.4.4
The laying of pipes on the prepared foundation shall start from the outlet and proceed towards the
inlet and be completed to the specified lines and grades. In case of use of pipes with bell-mouth,
the belled end shall face upstream. The pipes shall be fitted and matched so that when laid in
work, they form a culvert with a smooth uniform invert.
Any pipe found defective or damaged during laying shall be removed at the cost of the Contractor.
7.4.5
7.5
JOINTING
7.5.1
The pipes shall be jointed either by collar joint or by flush joint. In the former case, the collars
shall be of RCC 150 to 200 mm wide and having the same strength as the pipes to be joined.
Caulking space shall be between 13 and 20 mm according to the diameter of the pipe. Caulking
material shall be slightly wet mix of cement and sand in the ratio of 1:2 rammed with caulking
irons. Before caulking, the collar shall be so placed that its centre coincides with the joint and an
even annular space is left between the collar and the pipe.
7.5.2
Flush joint may be internal flush joint or external flush joint. In either case, the ends of the pipes
shall be specially shaped to form a self centering joint with a joining space 13 mm wide. The
jointing space shall be filled with cement mortar, 1cement to 2 sand, mixed sufficiently dry to
remain in position when forced with a trowel or rammer. Care shall be taken to fill all voids and
excess mortar shall be removed.
7.5.3
For joining pipe lines under light hydraulic pressure, the recess at the end of the pipe shall be
filled with jute braiding dipped in hot bitumen or other suitable approved compound. Pipes shall
be so jointed that the bitumen ring of one pipe shall set into the recess of the next pipe. The ring
shall be thoroughly compressed by jacking or by any other suitable method.
7.5.4
All joints shall be made with care so that their interior surface is smooth and consistent with the
interior surface of the pipes. After finishing, the joint shall be kept covered and damp for at least
four days.
7.6 BACKFILLING
Trenches shall be backfilled immediately after the pipes have been laid and the jointing material
has hardened. The backfill soil shall be clean, free from boulders, large roots, excessive amounts
of sods or other vegetable matter, and lumps and shall be approved by the Engineer. Backfilling
upto 300 mm above the top of the pipe shall be carefully done and the soil thoroughly rammed,
tamped or vibrated in layers not exceeding 150 mm, particular care being taken to thoroughly
consolidate the materials under the haunches of the pipe. Approved pneumatic or light mechanical
tamping equipment can be used.
7.6.1
100
7.6.2
Filling of the trench shall be carried out simultaneously on both sides of the pipe in such a manner
that unequal pressures do not occur.
7.6.3
In case of high embankment, after filling the trench upto the top of the pipe in the above said
manner, a loose fill of a depth equal to external diameter of the pipe shall be placed over the pipe
before further layers are added and compacted.
7.2
7.3
7.4
Reference
to MoRT&H
Specificatio
ns
408
2700
Rate
Item
No.
Descriptions
In
figures
(`)
In words
cum
5337.00
Rupees Five
Thousand Three
Hundred Thirty
Seven Only
cum
5420.00
Rupees Five
Thousand Four
Hundred Twenty Only
5636.00
Rupees Five
Thousand Six
Hundred and Thirty
Six Only
Unit
101
cum
Cas
eI
7.5
7.6
1400/2200
7.8
1400/2200
7.1
0
7.1
1
cum
6574.00
MT
85062.0
0
cum
3738.00
Rupees Three
Thousand Seven
Hundred and Thirty
Eight Only
cum
188.00
Steel
reinforcement
for
R.C.C.
works
including
bending,
binding
and
placing in position.
HYSD
7.9
6353.00
7.7
cum
Coursed
Rubble
stone
masonry in cement sand
mortar 1:3 in foundation
unto a depth of 1.50m and
also 1.50m above ground
level/bed level
Extra for coursed rubble
stone
masonry
in
superstructure
upto
a
height of 4 metre or part
thereof above 1.50 m from
ground/bed level.
Random
Rubble masonry
(coursed) in cement sand
mortar 1:3 in foundation
unto a depth of 1.50m and
1.50m above.
Providing regular dry stone
masonry wall with hammer
dressed or blunt chisel
dressed stone, stone of
heavy section (size not less
than 25cm x 25cm x 30cm
long) with proper key stone
each not less than 25cm x
25cm x 75cm long in
foundation upto a depth of
1.50m and 1.50 above
ground/bed level.
Cement pointing 1:2 deep
variety (out or weather) on
Brick and tile work.
102
3636.00
Rupees Three
Thousand Six
Hundred and Thirty
Six Only
cum
1908.00
Rupees One
Thousand Nine
Hundred and Eight
Only
sqm
77.00
cum
Rupees Seventy
Seven Only
7.1
2
7.1
3
7.1
4
2500.00
7.1
5
710.1.4 of
IRC : 78 &
2200
1400.00
Dry boulder
flooring
7.1
8
2900
2900
in
7.1
6
7.1
7
pitching
sqm
119.00
cum
3237.00
cum
1094.00
cum
979.00
Rm
17.00
metr
e
8072.00
metr
e
8850.00
103
Rupees Nine
Hundred and Seventy
Nine Only
Rupees Seventeen
Only
Rupees Eight
Thousand and
Seventy Two Only
Rupees Eight
Thousand Eight
Hundred and Fifty
Only
7.1
9
metr
e
10052.0
0
metr
e
10515.0
0
metr
e
12992.0
0
metr
e
14190.0
0
metr
e
20255.0
0
metr
e
21180.0
0
2900
Rupees Ten
Thousand and Fifty
Two Only
Rupees Ten
Thousand Five
Hundred and Fifteen
Only
Rupees Twelve
Thousand Nine
Hundred and Ninety
Two only
Rupees Fourteen
Thousand One
Hundred and Ninety
Only
Rupees Twenty
Thousand Two
Hundred and Fifty
Five Only
Rupees Twenty One
Thousand One
Hundred and Eighty
Only
CHAPTER 8
8. TRAFFIC SIGNS, MARKINGS AND OTHER ROAD APPURTENANCES
8.1
8.1.1
TRAFFIC SIGNS
Scope :
104
8.1.2
8.1.3
(i)
The colour, configuration, size and location of all traffic signs for highways other than
Expressways shall be in accordance with the Code of Practice for Road Signs, IRC: 67 or
as shown on the drawings. For Expressways, the size of the signs, letters and their
placement shall be as specified in the Contract drawings and relevant Specifications of
MoRT&H for Roads & Bridge Works. In the absence of any details or for any missing
details, the signs shall be provided as directed by the Engineer.
(ii)
(iii)
In general, cautionary and mandatory signs shall be fabricated through process of screen
printing. In regard to informatory signs with inscriptions, either the message could be
printed over the reflective sheeting, or cut letters of non-reflective black sheeting used for
the purpose which must be bonded well on the base sheeting as directed by the Engineer.
Materials :
(i)
Concrete shall be of the grade shown on the Contract drawings or otherwise as directed by
the Engineer.
(ii)
Reinforcing steel shall conform to the requirement of IS: 1786 unless otherwise shown on
the drawing.
(iii)
High strength bolts shall conform to IS: 1367 whereas precision bolts, nuts, etc., shall
conform to IS: 1364.
(iv)
Plates and support sections for the sign posts shall conform to IS: 226 and IS: 2062 or any
other relevant IS Specifications.
(v)
Aluminium sheets used for sign boards shall be of smooth, hard and corrosion resistant
aluminium alloy conforming to IS: 736-Material designation 24345 or 1900.
(vi)
Signs with a maximum side dimension not exceeding 600 mm shall not be less than 1.5
mm thick. All others shall be at least 2 mm thick. The thickness of the sheet shall be
related to the size of the sign and its support and shall be such that it does not bend or
deform under the prevailing wind and other loads.
(vii)
In respect of sign sizes not covered by IRC:67, the structural details (thickness, etc.) shall
be as per the approved drawings.
evidence of cracking, scaling, pitting, blistering, edge lifting or curling and shall have negligible
shrinkage or expansion. A certificate of having tested the sheeting for these properties in an
unprotected outdoor exposure facing the sun for two years and its having passed these tests shall
be obtained from a reputed laboratory, by the manufacturer of the sheeting. The reflective sheeting
shall be either of Engineering Grade material with enclosed lens or of High Intensity Grade with
encapsulated lens. The type of the sheeting to be used would depend upon the type, functional
hierarchy and importance of the road.
8.1.4
Entrance
Angle (in
degree)
-4
+30
-4
+30
White
Yellow
Orange
Green/
Red
Blue
250
150
95
65
170
100
62
45
100
60
30
25
45
25
15
10
20
11
7.5
5.0
When totally wet, the sheeting shall not show less than 90 per cent of the values of retroreflectance indicated in Table 8.1. At the end of 7 years, the sheeting shall retain at least 75 per
cent of its original retro-reflectance.
8.1.5
Installation :
(i)
Sign posts, their foundations and sign mountings shall be so constructed as to hold these in
a proper and permanent position against the normal storm wind loads or displacement by
vandalism. Normally, signs with an area upto 0.9 sq.m shall be mounted on a single post,
and for greater area two or more supports shall be provided. Sign supports may be of mild
steel, reinforced concrete or galvanized iron (G.I). Post-end(s) shall be firmly fixed to the
ground by means of properly designed foundation. The work of foundation shall conform
to relevant Specifications as specified.
(ii)
All components of signs and supports, other than the reflective portion and G.I posts shall
be thoroughly de-scaled, cleaned, primed and painted with two coats of epoxy paint. Any
part of mild steel (M.S) post below ground shall be painted with three coats of red lead
paint.
106
(iii)
The signs shall be fixed to the posts by welding in the case of steel posts and by bolts and
washers of suitable size in the case of reinforced concrete or G.I. posts. After the nuts have
been tightened, the tails of the bolts shall be furred over with a hammer to prevent
removal.
8.2. ROAD MARKINGS
8.2.1
Scope:
The colour, width and layout of road markings shall be in accordance with the Code of Practice
for Road Markings with paints, IRC: 35, and as specified in the drawings or as directed by the
Engineer.
8.2.2
Materials :
Road markings shall be of ordinary road marking paint, hot applied thermoplastic compound, or
reflectorised paint as specified in the item and the material shall meet the requirement as specified
below.
8.2.3
(i)
Ordinary paint used for road marking shall conform to Grade I as per IS: 164.
(ii)
The road marking shall preferably be laid with appropriate road marking machinery.
(iii)
8.2.4
8.2.5
The work under this section consists of marking traffic using a thermoplastic compound
meeting the requirements specified herein.
(ii)
(c)
The colour of the compound shall be white or yellow (IS colour No.356) as specified in
the drawings or as directed by the Engineer.
(d)
Thermoplastic Material :
The thermoplastic material shall be homogeneously composed of aggregate, pigment, resins and
glass reflectorising beads.
107
8.2.6
Requirements :
(i)
Composition : The pigment, beads, and aggregate shall be uniformly dispersed in the
resin. The material shall be free from all skins, dirt and foreign objects and shall comply
with requirements indicated in Table 8.3.
Table 8.3 (Table 800-3) Proportions of Constituents of Marking Material
(Percentage by weight)
Component
White
Yellow
Binder
18.0 min.
18.0 min.
Glass Beads
30 40
30 40
Titanium Dioxide
10.0 min.
Calcium Carbonate and
42.0 max.
See
Inert Fillers
Yellow Pigments
Note
Note : Amount of yellow pigment, calcium carbonate and inert fillers shall be at the option of the
manufacturer, provided all other requirements of MoRT&H Specification are met.
8.2.7 Reflectorising glass beads :
8.2.8
(i)
MoRT&H Specifications covers two types of glass beads to be used for the production of
reflectorised pavement markings.
(ii)
Type 1 beads are those which are a constituent of the basic thermoplastic compound vide
Table 8.3 and Type 2 beads are those which are to be sprayed on the surface vide Clause
803.6.3.
(iii)
The glass beads shall be transparent, colourless and free from milkiness, dark particles and
excessive air inclusions.
(iv)
Specific requirements :
(A) Gradation : The glass beads shall meet the gradation requirements for the two types as given
in Table 8.4
Table 8.4 (Table 800-4) Gradation Requirements for Glass Beads
Sieve size
1.18
850 micron
600 micron
425 micron
Type 2
0 to 5
5 to 20
-
300 micron
180 micron
Below 180 micron
0 to 10
-
30 to 75
10 to 30
0 to 15
(B) Roundness : The glass beads shall have a minimum of 70 per cent true spheres.
(C) Refractive Index : The glass beads shall have a minimum refractive index of 1.50.
(D) Free flowing properties : The glass beads shall be free of hard lumps and clusters and shall
dispense readily under any conditions suitable for paint stripping. They shall pass the free
flow-test.
8.3. HECTOMETRE/ KILOMETRE STONES
8.3.1
Scope:
(i)
The work covers the supply, painting, lettering and fixing of distance measurement stones
and shall include:
(a)
Hectometre stones
(b)
Kilometre stones
(c)
(ii)
The dimension of the stones and the size, colour, arrangement of letters and script shall be
as per IRC: 26 Type Designs for 200 Metre Stones and IRC: 8 Type Designs for
Highway Kilometre Stones.
(iii)
The hectometer/kilometre stones may be made of local stones, concrete or any other
material available locally and approved by the Engineer. The stones shall be bedded into
the ground with adequate foundations as indicated in the drawings or in the relevant I.R.C.
Specifications or as directed by the Engineer. The orientation and location of the stones
shall be as indicated in the drawings or in the relevant I.R.C. Specifications or as directed
by the Engineer.
8.4.2
Scope :
(i)
The work covers supplying and fixing roadway indicators, hazard markers and object
markers.
(ii)
The design, materials to be used and the location of the road delineators shall conform to
Recommended Practice for Road Delineators, IRC : 79, and to relevant drawings or as
otherwise directed by the Engineer.
Measurement for Payment :
The measurement shall be made in numbers of delineators fixed at site.
8.4.3
Rate :
109
The Contract unit rate for Road Delineators shall be payment in full compensation for furnishing
all labour, materials, tools, equipment for preparing, supplying and fixing at site and all other
incidental costs necessary to complete the work to MoRT&H Specifications.
8.5 BOUNDARY STONES
8.5.1
Scope :
The work comprises of supplying and fixing boundary stones as per designs and Specifications
given in IRC: 25 Type Designs for Boundary Stones and at locations indicated in the drawings
or as directed by the Engineer.
8.5.2
8.5.3
Rate :
The Contract unit rate for boundary stones shall be payment in full compensation for furnishing
all labour, materials, tools, equipment for preparing, supplying and fixing and all other incidental
costs necessary to complete the work to MoRT&H Specifications.
8.6 FENCING
8.6.1
(iii)
Scope :
(i)
The work comprises of fixing Mild Steel (M.S) posts and providing barbed wire fencing
including necessary stays and entry gates as shown in the drawing(s) and as directed by
the Engineer.
(ii)
The M.S. posts shall conform to IS:226 and shall be of angle iron of size indicated in the
drawings. The angle iron shall be embedded in concrete to a sufficient depth below ground
as indicated in the drawings. The steel shall be fabricated and painted to conform to
Section 1900 of MoRT&H Specifications.
The barbed wire shall be of galvanised iron and shall conform to IS:278.
(iv)
8.6.2
Entry gate(s) shall be made of M.S. rods or other metal as per the design shown in the
drawing(s).
8.6.3
Rate :
The Contract unit rate for fencing shall be payment in full compensation for furnishing all labour,
materials, tools, equipment for fabrication and fixing at site and all other incidental costs
necessary to complete the work to the Specifications.
8.7 METAL BEAM CRASH BARRIER
8.7.1
Scope :
110
8.7.2
(i)
This work shall consist of furnishing and erection of metal beam crash barrier of
dimensions and at locations as shown on the drawing(s) or as directed by the Engineer.
(ii)
Metal beam crash barrier shall generally be located on approaches to bridge structures, at
locations where the embankment height is more than 3 metres and at horizontal curves.
Materials :
(i)
Metal beam rail shall be corrugated sheet steel beams of the class, type, section and
thickness indicated on the plans. Railing posts shall be made of steel of the section, weight
and length as shown on the plans. All complete steel rail elements, terminal sections,
posts, bolts, nuts, hardware and other steel fittings shall be galvanised. All elements of the
railing shall be free from abrasions, rough or sharp edges and shall not be kinked, twisted
or bent.
(ii)
Steel beam elements and terminal sections shall be galvanised (zinc coated, 0.55 kg per
square metre, minimum single spot) unless otherwise specified. The galvanising on all
other steel parts shall conform to the relevant IS Specifications. All fittings (bolts, nuts,
washers) shall conform to the IS: 1367 and IS: 1364. All galvanising shall be done after
fabrication.
8.8 ROAD TRAFFIC SIGNALS
8.8.1
8.8.2
Scope :
(i)
The traffic signal, its configuration, size and location shall be in accordance with IRC: 93
and IS: 7537 and as shown in the drawings or as directed by the Engineer. Prior to
installation of signals, the Contractor shall submit to the Engineer, for approval, detailed
proposals showing the signal type, sizes, paint and structural details of the signal posts
including control system.
(ii)
The traffic signals shall have a complete electronic mechanism for controlling the
operation of traffic with an auxiliary manual controller. The time plan of signals shall be as
per drawing and shall be modified as directed by the Engineer.
Materials :
The various materials and fabrication thereof shall conform to the following:
8.8.3
Signal foundation :
The signal foundations shall be constructed as per Specifications given in Clause 13 of IRC : 93
or as shown in the drawings.
8.8.4
Constructional requirements :
The constructional requirements for post, signal head assembly, signal head, optical system, lamp
and holder, visor, post, supports for overhead mounted signals, equipment housing, locks, interconnecting cables, earthing, mains termination, controller electrical components, etc., shall
111
conform to IS: 7537 unless otherwise stated in IRC: 93. The post shall be painted and protected as
per Clause 3.7 of IS: 7537.
8.8.5
Optical requirements :
The shape of all signal lenses shall be circular and shall be of specified colour and size and as
shown in the drawing. Quality of lenses, arrangement of lenses, illuminations, visibility and
shielding of signals shall be as per relevant Clauses of IRC: 93 and IS: 7537.
Sl
No
Reference
to
MoRT&H
Specificat
ions
Rate
Item
No.
Descriptions
112
Unit
In
figure
s
(`)
In words
8.1
408
8.2
408
Rm
386.00
Rupees Three
Hundred and Eighty
Six Only
Rm
703.00
Rupees Seven
Hundred and Three
only
8.3
801
(i)
(ii)
113
cm
heig
ht
per
letter
cm
heig
ht
per
letter
1.00
0.60
8.4
801
Retroreflectorised
Traffic
signs:
Providing and fixing of retroreflectorised
cautionary,
mandatory and informatory sign
as per IRC
:67 made
of
encapsulated lens type reflective
sheeting vide clause 801.3, fixed
over aluminium sheeting, 1.5 mm
thick supported on a mild steel
angle iron post 75 mm x 75 mm x
6 mm firmly fixed to the ground
by means of properly designed
foundation
with
M15
grade
cement concrete 45 cm x 45 cm x
60 cm, 60 cm below ground level
as per approved drawing
(i)
90 cm equilateral triangle
each
12372.
00
( ii )
60 cm equilateral triangle
each
7163.0
0
( iii )
60 cm circular
each
10573.
00
( iv )
80 mm x 60 mm rectangular
each
15862.
00
(v)
60 cm x 45 cm rectangular
each
10224.
00
(vi )
60 cm x 60 cm square
each
12640.
00
90 cm high octagon
each
21017.
00
( vii )
114
Rupees Twelve
Thousand Three
Hundred Seventy Two
Only
Rupees Seven
Thousand One
Hundred Sixty Three
Only
Rupees Ten Thousand
Five Hundred Seventy
Three Only
Rupees Fifteen
Thousand Eight
Hundred Sixty Two
Only
Rupees Ten Thousand
Two Hundred Twenty
Four Only
Rupees Twelve
Thousand Six
Hundred Forty Only
Rupees Twenty One
Thousand Seventeen
Only
8.5
801
Direction
and
Place
Identification signs upto 0.9
sqm size board:
Providing and erecting direction
and place identification retroreflectorised sign as per IRC:67
made of encapsulated lens type
reflective sheeting vide clause
801.3, fixed over aluminium
sheeting, 2 mm thick with area
not exceeding 0.9 sqm supported
on a mild steel single angle iron
post 75 x 75 x 6 mm firmly fixed
to the ground by means of
properly designed foundation with
M15 grade cement concrete 45 x
45 x 60 cm, 60 cm below ground
level as per approved drawing
8.6
8.7
8.8
801
803
803
sqm
25830.
00
sqm
26389.
00
sqm
88.00
sqm
82.00
Direction
and
Place
Identification signs with size
more than 0.9 sqm size board:
Providing and erecting direction
and place identification retroreflectorised sign asper IRC :67
made of encapsulated lens type
reflective sheeting vide clause
801.3, fixed over aluminium
sheeting, 2 mm thick with area
exceeding 0.9 sqm supported on
a mild steel angle iron post 75
mm x 75 mm x 6 mm, 2 Nos.
firmly fixed to the ground by
means of properly designed
foundation with M 15 grade
cement concrete45 cm x 45 cm x
60 cm, 60 cm below ground level
as per approved drawing
Painting Two Coats on New
Concrete
Surfaces:
Painting two coats after filling the
surface with synthetic enamel
paint in all shades on new
plastered concrete surfaces
Painting on Steel Surfaces:
Providing and applying two coats
of ready mix paint of approved
brand on steel surface after
through cleaning of surface to
give an even shade
115
8.9
803
Painting
Lines,
Dashes,
Arrows etc on Roads in Two
Coats
on
New
Work:
Painting lines, dashes, arrows etc
on roads in two coats on new
work with ready mixed road
marking paint conforming to
IS:164 on bituminous surface,
including cleaning the surface of
all dirt, dust and other foreign
matter, demarcation at site and
traffic control
(i)
(ii)
8.1
0
803
sqm
112.00
Up to 10 cm in width
sqm
96.00
Over 10 cm in width
sqm
72.00
Up to 10 cm in width
sqm
77.00
Rupees Seventy
Seven Only
sqm
2305.0
0
Rupees Two
Thousand Three
Hundred and Five
Only
4541.0
0
Rupees Four
Thousand Five
Painting
Lines,
Dashes,
Arrows etc on Roads in Two
Coats
on
Old
Work:
Painting lines, dashes, arrows etc
on roads in two coats on old work
with ready mixed road marking
paint confirming to IS: 164 on
bituminous
surface,
including
cleaning the surface of all dirt,
dust and other foreign matter,
demarcation at site and traffic
control
(i)
(ii)
8.1
1
8.1
2
Over 10 cm in width
Road
Marking
with
Hot
Applied
Thermoplastic
Compound with Reflectorising
Glass Beads on Bituminous
Surface
:
Providing and laying of hot
applied thermoplastic compound
2.5
mm
thick
including
reflectorising glass beads @ 250
gms per sqm area, thickness of
2.5 mm is exclusive of surface
applied glass beads as per
IRC:35 .The finished surface to be
level, uniform and free from
streaks and holes
Kilo Metre Stone:
804
(i)
Reinforced
cement
concrete
M15grade kilometre stone of
standard design as per IRC:81980, fixing in position including
painting and printing etc
5th kilometre stone (precast)
116
each
(ii)
(iii)
8.1
3
8.1
4
8.1
5
Ordinary
(Precast)
Kilometer
stone
805
Road Delineators:
806
807
117
each
2641.0
0
each
788.00
each
2375.0
0
Rupees Two
Thousand Three
Hundred and Seventy
Five Only
each
606.00
metr
e
376.00
Rupees Three
Hundred and Seventy
Six Only
8.1
6
8.1
7
807
810
A
metr
e
643.00
metr
e
4850.0
0
Rupees Four
Thousand Eight
Hundred Fifty Only
CHAPTER 9
9. MAINTENANCE OF ROAD
9.1 DESCRIPTION
9.1.1
Scope :
118
The Specifications shall apply to all items of road maintenance works as required to be carried out
under the Contract or as directed by the Engineer. The works shall be carried out in conformity
with the relevant Specifications to the required level, grade and lines using approved materials,
the works shall be carried out using light duty machinery or manual means provided the quality of
the end product does not suffer. In execution of maintenance works, a reference is made to the
IRC publications: Manual for Maintenance of Roads and Code of Practice for Maintenance for
Bituminous Surfaces of Highways, IRC 82-1982 for guidance and compliance wherever
applicable. Wherever the Specification is not clear, good engineering practice shall be adopted in
the construction to the satisfaction of the Engineer.
9.2
9.2.1
Scope :
The work shall consist of earthwork for restoration of rain cuts in the embankment and shoulders,
using suitable material, and compacting the same.
9.2.2
Materials :
The materials used for restoration of rain cuts shall consist of soil conforming to Clause 305.2.
9.2.3
Construction Operation :
(i)
(ii)
The area affected by rain cuts shall be cleared of all loose soil benched. The width of the
benches shall be at least 300 mm and they shall extend continuously for a sufficient
length. The height of the benches shall be in the range of 150-300 mm.
Fresh material shall be deposited in layers not exceeding 250 mm loose thickness and
compacted so as to match with the benching at a moisture content close to the optimum.
Compaction shall be carried out using suitable equipment such as plate compactors and
rammers or by suitable implements handled manually. The finished work shall conform to
alignment, levels and slopes as indicated in the drawing.
9.3 MAINTENANCE OF EARTHEN SHOULDER
9.3.1
Scope :
The work of maintenance of earthen shoulder shall include making up the irregularities/loss of
material on shoulder to the design level by adding fresh approved soil and compacting it with
appropriate equipments or to strip excess soil from the shoulder surface as per the requirement of
MoRT&H Specification.
9.3.2
Material :
The material to be added to the shoulder, if required, shall be a select soil conforming to Clause
305 of MoRT&H Specification.
9.3.3
Construction Procedure :
119
9.4.3
9.4.4
This work shall include repair of pot-holes and patching of all types of bituminous
pavement.
(ii)
The work shall include the removal of all failed material, in the pavement courses and, if
necessary, below the pavement, until the root cause of the failure is removed; the trimming
of the completed excavation to provide firm vertical faces; the replacement of material of
at least as high a standard as that which was originally specified for the pavement layer;
the painting of tack coat on to the sides and bases of excavations prior to placing of any
bituminous materials and the compaction, trimming and finishing of the surfaces of all
patches to form a smooth continuous surface, level with the surrounding road.
Crack Sealing :
Crack sealing shall consist of one or more of the following operations as instructed under
the Contract.
(i)
fog seal
(ii)
filling cracks with a binder, or a combination of crusher dust and a binder.
(iii)
by treating the crack sealing as a patch repair.
Crack filling :
Crack filling shall be carried out using a binder of a suitable viscosity, normally a slowcuring bitumen emulsion, as instructed by the Engineer. For wider cracks, in excess of an average
of 3mm in width the application of emulsion may be preceded by an application of crusher dust,
or other fine material acceptable to the Engineer.
Sl
No
Reference
to
MoRT&H
Specificat
ions
Rate
Item
No.
Descriptions
120
Unit
In
figure
s
(`)
In words
9.1
9.2
9.3
9.4
9.5
9.6
3002
3003
3003
3004.2
3004.3.3
3004.4
Cum
250.00
Sqm
41.00
sqm
110.00
sqm
200.00
metr
e
4.00
sqm
1.00
121
9.7
9.8
9.9
3000
3000
3000
metr
e
22.00
cum
71.00
cum
137.00
cum
970.00
Additional Item
9.1
0
Providing
temporary
restoration work in the form of
a pallasiding with empty bags
fully filled up with approved
locally available sand moorum,
gravel etc. including stiching
the bags with jute strings of
required diameter and placing
the filled up sand cement bags
in proper slope to withstand
temporarily the road structure
from sliding (sand and cement
bag will be
supplied
by
contractor up to work site)
complete as directed
122
Chapter 10
10. FOUNDATIONS
10.1
Preamble:
10.1.1 Excavation for structure has been provided both by manual and mechanical means. The rate
relevant to a particular situation may be adopted.
10.1.2 The earth excavated from foundation has been proposed to be backfilled and balance quantity
utilised for road work locally except for marshy soil where disposal has been provided.
10.1.3 The rock foundations are required to be prepared which has been analysed.
10.1.4 In case of rocks, excavation has been considered upto a depth of 3 m only.
10.1.5 Embedment of foundation in soft and hard rocks has been provided as required by the
Specifications.
10.1.6 De-watering has been provided in excavation for foundation. In case de-watering is not required
for a particular site condition, the same may be omitted.
10.1.7 Mixing of cement concrete has been considered both by using concrete mixer and batching plant.
The rate can be adopted depending upon availability of equipment and as approved by the
Engineer.
10.1.8 Concrete batching plant is generally placed within one km of the bridge site. In case of longer
lead, transportation cost may be worked out based on tonne km.
10.1.9 The coarse and fine aggregate for cement concrete shall as per IS:383.
10.1.10 Description of items has been given very briefly. Relevant clauses of MoRT&H Specifications
may be referred for detailed specification.
10.1.11 The rate analysis for well foundation has been included for well diameter of 8.0 m. Well for twin
D type has also been included.
10.1.12 Steel reinforcement for cement concrete works are required to be provided separately. The rate
for the same has been analysed.
10.1.13 Appendix-4 of IRC:78-2000 may be referred regarding precautions to be taken during sinking of
wells.
10.1.14 In case of blasting during sinking of wells the inner face of the curb is required to be protected
with the steep plates of thickness not less than 10 mm upto top level of well curb. For height
above top of curb, the thickness of steel plate may be reduced to 6 m. This extra height of steel
lining should be limited to 3 m.
10.1.15 The concrete mix used in bottom plug shall have a minimum cement content of 330 kg/cum and
a slump of about 150 mm to permit easy flow of concrete through tremie to fill-up all cavities.
10.1.16 Necessary safety precautions shall be taken for excavation on open foundations for which
guidance may be taken from IS:3764.
10.1.17 A leveling course of 100 mm thickness in M 10(1:3:6) shall be provided before laying open
foundations.
123
10.1.18 In the case of open foundation, de-watering shall not be permitted from the time of placing of
concrete upto 24 hours after placement.
10.1.19 In case of open foundations in rock, the trenches around the footing shall be filled-up with
concrete of M 15 grade upto a level of 0.6 m for hard rock and 1.5 m for soft rock above the
foundation level. The portion above this may be filled by boulders grouted with cement.
10.1.20 When there are two or more compartments in a well, the lower edge of the cutting edge of the
middle stems of such wells shall be kept about 300 mm above that of outer stems to prevent
rocking.
10.1.21 The well curb shall be in RCC of mix not leaner than M 25 grade with minimum steel
reinforcement of 72 kg/cum excluding bond rods.
10.1.22 The top of the bottom plug shall be at least 300 mm above top of curb.
10.1.23 No de-watering shall be carried out within 7 days of casting of bottom plug.
124
CHAPTER-10 : FOUNDATIONS
Sl
No
10.
1
Referenc
e to
MoRT&H
Specificat
ions
304.0
Rate
Item
No.
Descriptions
Unit
In
figures
(`)
In words
I
A
Manual Means
(i)
upto 3 m depth
cum
76.00
(ii)
3 m to 6 m depth
cum
98.00
(iii)
Above 6 m depth
cum
130.00
cum
77.00
Rupees Seventy
Seven Only
Rupees Eighty Eight
Only
B
(i)
Mechanical Means
Depth upto 3 m
(ii)
Depth 3 m to 6 m
cum
88.00
(iii)
Depth above 6m
cum
105.00
II
cum
109.00
Mechanical Means
cum
101.00
cum
396.00
Rupees Three
Hundred and Ninety
Six Only
cum
707.00
Rupees Seven
Hundred and Seven
Only
A
(i)
B
Hard
rock
blasting )
III
A
A
V
(i)
requiring
Manual Means
Hard
rock
prohibited )
IV
blasting
Mechanical Means
Marshy soil
upto 3 m depth
125
10.
3
304.0
10.
4
Subanalysis
(Addl)
Manual means
cum
557.00
Mechanical Means
cum
123.00
cum
1297.00
cum
4228.00
cum
5185.00
cum
3591.00
cum
3011.00
D
10.
5
1400.0
Cement
mortar1:2
(1cement :2 sand)
Cement
mortar1:4
(1cement :4 sand)
Cement
mortar1:6
(1cement :6 sand)
Stone
masonry
work
in
cement
mortar
1:3
in
foundation
complete
as
drawing
and
Technical
Specification.
(a)
10.
6
Cement
mortar1:3
(1cement :3 sand)
1500,
1700 &
2100
cum
3829.00
Rupees Three
Thousand Eight
Hundred and Twenty
Nine Only
Plain/Reinforced
cement
concrete in open foundation
complete as per drawing and
technical specifications.
A
cum
6114.00
cum
6906.00
Case
I
E
Case
I
G
Case
I
cum
7137.00
Rupees Seven
Thousand One
Hundred and Thirty
Seven Only
Rupees Seven
Thousand Six
Hundred and Sixty
Six Only
cum
7666.00
cum
7679.00
126
Rupees Seven
Thousand Six
10.
8
1200
&1900
1200,
1500
&1700
A
MT
132414
00
(i)
cum
8235.00
(ii)
cum
8867.00
Well steining
Rupees Eight
Thousand Two
Hundred and Thirty
Five Only
Rupees Eight
Thousand Eight
Hundred and Sixty
Seven Only
(I)
cum
6468.00
(ii)
cum
7306.00
(iii)
cum
7549.00
(iv)
cum
8128.00
C
(i)
Bottom Plug
PCC Grade M20
cum
8306.00
Rupees Eight
Thousand Three
Hundred and Six Only
cum
5880.00
Rupees Five
Thousand Eight
Hundred and Eighty
Only
cum
7078.00
cum
7679.00
D
(i)
E
(i)
(ii)
Top plug
Grade M15 PCC
Well cap
RCC Grade M20
RCC Grade M30
127
Rupees Seven
Thousand and
Seventy Eight Only
Rupees Seven
Thousand Six
section
1200
Sinking of 8 m external
diameter well
(other than
pneumatic method of sinking )
through all types of strata
namely sandy soil,
clayey
soil and rock as shown
against each case, complete
as per drawing and technical
specifications.
Depth
of
sinking is reckoned from bed
level.
A
Sandy soil
(i)
metr
e
10624.0
0
(ii)
metr
e
13211.0
0
(iii)
metr
e
17447.0
0
(iv)
metr
e
32726.0
0
metr
e
39271.0
0
metr
e
14437.0
0
metr
e
37630.0
0
metr
e
49697.0
0
metr
e
52182.0
0
(v)
B
Add
20%
of
cost
for
Kentledge
including
supports,
loading
arrangement and Labour .
Beyond 30m upto 40 m
(i)
(ii)
(iii)
128
Rupees Fourteen
Thousand Four
Hundred and Thirty
Seven Only
Rupees Thirty Seven
Thousand Six
Hundred and Thirty
Only
Rupees Forty Nine
Thousand Six
Hundred and Ninety
Seven Only
Rupees Fifty Two
Thousand One
Hundred and Eighty
Two Only
(iv)
a
C
(i)
D
(i)
10.
10
1207.0
Beyond
20m
m(including
Kentledge)
upto
25%
30
for
Add
5%
for
cost
of
dewatering on the cost if
required.
metr
e
116523.
00
metr
e
122350.
00
metr
e
20049.0
0
metr
e
34924.0
0
cum
1297.00
soft
rock
strata
Rupees Twenty
Thousand and Forty
Nine Only
Rupees Thirty Four
Thousand Nine
Hundred and Twenty
Four Only
Rupees One
Thousand Two
Hundred and Ninety
Seven Only
CHAPTER 11
11. SUB-STRUCTURE
11.1
DESCRIPTION
11.1.1 Scope :
The work shall cover furnishing and providing of masonry or reinforced concrete sub-structure in
accordance with the drawings and MoRT&H Specifications or as directed by the Engineer.
129
11.1.2 Materials :
Materials shall conform to Section 1000 of MoRT&H Specifications for Roads & Bridge Works
(Fourth Revision)
11.2 GENERAL
11.2.1 (i)
A method statement for construction indicating the following shall be submitted by the
Contractor for approval of the Engineer, well in advance of the commencement of substructure :
(a)
Sources of Materials
(b)
(c)
(d)
(e)
(f)
(ii)
Arrangements for execution under water wherever necessary, shall be included in method
statement.
(iii)
Dimensions, lines and levels shall be set out and checked with respect to permanent
reference lines and permanent bench mark.
11.3 PIERS AND ABUTMENTS
11.3.1 Masonry, formwork, concrete and reinforcement for piers and abutments shall conform to relevant
sections of MoRT&H Specifications. In case of concrete piers, the number of horizontal
construction joints shall be kept minimum. Construction joints shall be avoided in splash zones
unless specifically permitted by the Engineer and provided they are treated in accordance with
special provisions. No vertical construction joint shall be provided. The work shall conform
strictly to the drawings or as directed by the Engineer.
11.3.2 In case of tall piers and abutments, use of slipform shall be preferred. The design, erection and
raising of slipform shall be subject to special specifications which will be furnished by the
Contractor. The concrete shall also be subject to additional specification as necessary. All
specifications and arrangements shall be subject to the approval of the Engineer.
11.3.3 The surface of foundation/well cap/pile cap shall be scrapped with wire brush and all loose
materials removed. In case reinforcing bars projecting from foundations are coated with cement
slurry, the same shall be removed by tapping, hammering or wire brushing. Care shall be taken to
remove all loose materials around reinforcements. Just before commencing masonry or concrete
work, the surface shall be thoroughly wetted.
11.3.4 In case of solid (non-spill through type) abutments, weep holes as shown on the drawings or as
directed by the Engineer, shall be provided in conformity with Section 2706 of MoRT&H
Specifications.
130
11.3.5 The surface finish shall be smooth, except the earth face of abutments which shall be rough
finished.
11.3.6 In case of abutments likely to experience considerable movement on account of backfill of
approaches and settlement of foundations, the construction of the abutment shall be followed by
filling up of embankment in layers to the full height to allow for the anticipated movement during
construction period before casting of superstructure.
11.4
11.4.1 Formwork, reinforcement and concrete shall conform to relevant sections of MoRT&H
Specifications.
11.4.2 The locations and levels of pier cap/abutment cap/pedestals and bolts for fixing bearings shall be
checked carefully to ensure alignment in accordance with the drawings of the bridge.
11.4.3 The surface of cap shall be finished smooth and shall have a slope for draining of water as shown
on the drawings or as directed by the Engineer. For short span slab bridges with continuous
support on pier caps, the surface shall be cast horizontally. The top surface of the pedestal on
which bearings are to be placed shall also be cast horizontally.
11.4.4 The surface on which elastomeric bearings are to be placed shall be wood float finished to a level
plane which shall not vary more than 1.5 mm from the straight edge placed in any direction across
the area. The surface on which other bearings (steel bearings, pot bearings) are to be placed shall
be cast about 25 mm below the bottom level of bearings and as indicated on the drawings.
11.5
11.5.1 Masonry, concrete and reinforcement shall conform to relevant sections of MoRT&H
Specifications.
11.5.2 In case of cantilever return walls, no construction joint shall generally be permitted. Wherever
feasible, the concreting in cantilever return walls shall be carried out in continuation of the ballast
wall.
11.5.3 For gravity type masonry and concrete return and wing wall, the surface of foundation shall be
prepared in the same manner as prescribed for construction of abutment. No horizontal
construction joint shall be provided. If shown on drawing or as directed by the Engineer, vertical
construction joint may be provided. Vertical expansion gap of 20 mm shall be provided in return
wall/ wing wall at every 10 metre intervals or as directed by the Engineer. Weep holes shall be
provided as prescribed for abutments or as shown in the drawings.
11.5.4 Formwork, reinforcement and concrete in dirt/ ballast wall shall conform to relevant sections of
MoRT&H Specifications.
11.5.5 The finish of the surface on the earth side shall be rough while the front face shall be smooth
finished.
11.5.6 Architectural coping for wing wall/ return wall in brick masonry shall conform to section 1300 of
MoRT&H Specifications.
131
11.6
11.6.1 The materials shall be tested in accordance with MoRT&H Specifications and shall meet the
prescribed criteria.
11.6.2 The work shall conform to MoRT&H Specifications and shall meet the prescribed standards of
acceptance.
11.7 TOLERANCES IN CONCRETE ELEMENTS
(a) Variation in cross-sectional dimensions
10mm, -5 mm
10 mm
10mm
5mm
10mm
5 mm
Bearing areas
3 mm
CHAPTER 11 : SUB-STRUCTURE
Sl
No
11.
1
Reference
to
MoRT&H
Specificat
ions
1400
&2200
Rate
Item
No.
Descriptions
Unit
132
In
figure
s
(`)
In words
A
11.
2
11.
3
11.
4
1500,
1700 &
2200
cum
3966.0
0
Rupees Three
Thousand Nine
Hundred and Sixty
Six Only
Plain/Reinforced
cement
concrete in sub-structure
complete as per drawing
and
technical
specifications.
RCC Grade M30
(a)
Height upto 5m
cum
8162.0
0
(b)
Height 5m to 10m
cum
8392.0
0
( c)
cum
8719.0
0
each
508.00
2706 &
2200
710.1.4 of
IRC:78
and 2200
Granular material
cum
1576.0
0
Sandy material
cum
2106.0
0
133
Rupees Eight
Thousand One
Hundred and Sixty
Two Only
Rupees Eight
Thousand Three
Hundred and Ninety
Two Only
Rupees Eight
Thousand Seven
Hundred and
Nineteen Only
Rupees One
Thousand Five
Hundred and Seventy
Six Only
Rupees Two
Thousand One
Hundred and Six Only
11.
5
11.
6
11.
7
11.
8
11.
9
710.1.4 of
IRC:78
and 2200
2000,
1000 &
2200
2000,
1000 &
2200
2000 &
2200
2000 &
2200
134
cum
1068.0
0
Rupees One
Thousand and Sixty
Eight Only
tonne
capacity
725.00
Rupees Seven
Hundred and Twenty
Five Only
tonne
capacity
565.00
tonne
capacity
338.00
Rupees Three
Hundred and Thirty
Eight Only
cubic
centimet
re
1.60
CHAPTER 12
12. CONCRETE SUPERSTRUCTURE
12.1 DESCRIPTION
12.1.1 Scope :
The work shall cover furnishing and providing of concrete superstructure in accordance with the
drawings and as per MoRT&H Specifications for Roads & Bridge Works (Fourth Revision) or as
directed by the Engineer.
12.1.2 Materials :
Materials shall conform to Section 1000 of MoRT&H Specifications
12.2 GENERAL
12.2.1 (i)
A method statement for construction indicating the following shall be submitted by the
Contractor for approval of the Engineer, well in advance of the commencement of
superstructure :
(a)
Sources of Materials
(b)
(c)
(d)
(e)
(f)
(g)
Equipment details
(h)
(iii)
Dimensions, lines and levels shall be set out and checked with respect to permanent
reference lines and permanent bench mark so that the final product is in accordance with
the drawings or as directed by the Engineer.
135
(iv)
(v)
The work shall conform to the following sections besides stipulations in this section with
regard to specific type of construction:
(a) Formwork
Section 1500
Section 1600
Section 1700
(d) Pre-stressing
Section 1800
Additionally, some of the common types of superstructure construction shall have features
as discussed in this Section.
12.3
Where adjacent span of slab has already been casted, the expansion joint and filler board
shall be placed abutting the already cast span which shall form the shutter on that side of
the new span to be casted. The whole of the slab shall be casted with reinforcement
embedded for the road kerb and railings. No other construction joint shall be allowed
except with the permission of the Engineer.
(ii)
Where wearing coat is required to be provided, after the deck slab has been casted, the
surface of the slab shall be finished rough, but true to lines and levels as shown on the
drawings, before the concrete has hardened. The areas of construction joints shall be
treated in the prescribed manner.
(iii)
The top of the slab shall be covered with clean moist sand as soon as the top surface has
hardened. Curing shall be carried out as per Section 1700 of MoRT&H Specifications.
(iv)
Where the slab is resting on bearings, the same shall be placed in position in accordance
with the drawings, before casting of deck slab.
12.4
12.4.1 Provision of construction joint shall conform to the drawings or as per directions of the Engineer.
No construction joint shall be provided between the bottom bulb and the web. If not indicated on
the drawing, construction joint may be provided at the junction of the web and the fillet between
the web and the deck slab with the permission of the Engineer.
12.4.2 The portions of deck slab near expansion joints shall be casted alongwith reinforcements and
embedments for expansion joints. For this purpose, the portion of deck slab near expansion joints
may be casted in a subsequent stage, if permitted by the Engineer.
12.4.3 The surface finish of the deck slab shall be finished rough but true to lines and levels as shown in
the drawings before the concrete has hardened. Care shall be taken for setting of bearings as
indicated in the drawings.
136
Conditions of Exposure
Moderate
Severe
M 25
M 30
M 35
M 40
M 35
M 40
a) PCC members
b) RCC members
c) PSC members
Conditions of Exposure
Moderate
Severe
M 15
M 20
M 20
M 25
a) PCC members
b) RCC members
Notes : Applicable to Tables 12.1 & 12.2
(i)
The minimum cement content is based on 20mm aggregate (nominal max. size). For 40mm and
larger size aggregate, it may be reduced suitably but the reduction shall not be more than 10 per
cent.
(ii)
(iii)
(iv)
For underwater concreting, the cement content shall be increased by 10 per cent.
Severe conditions of exposure shall mean alternate wetting and drying due to sea spray, alternate
wetting and drying combined with freezing and buried in soil having corrosive effect.
Moderate conditions of exposure shall mean other that those mentioned in (iii) above
The cement content shall be as low as possible but not less than the quantities specified above. In no
case shall it exceed 540 kg/cu.m. of concrete.
12.6 PROPORTIONING OF CONCRETE
Prior to the start of construction, the Contractor shall design the mix in case of Design Mix
Concrete or propose nominal mix in case of Nominal Mix Concrete, and submit to the
Engineer for approval, the proportions of materials, including admixture to be used. Waterreducing admixtures (including plasticisers or super-plasticisers) may be used at the Contractors
137
option, subject to the approval of the Engineer. Other types of admixtures shall be prohibited,
unless specifically permitted by the Engineer.
12.6.1 Requirements of Consistency :
(i)
(ii)
The mix shall have the consistency which will allow proper placement and consolidation
in the required position. Every attempt shall be made to obtain uniform consistency.
The optimum consistency for various types of structures shall be as indicated in Table
12.3, or as directed by the Engineer. The slump of concrete shall be checked as per IS:516.
Type
(a) Structures with exposed inclined surface requiring low
slump concrete to allow proper compaction
(b) Plain cement concrete
RCC structures with widely spaced reinforcements; e.g. solid
columns, piers, abutments, footings, well steining
RCC structures with fair degree of congestion of reinforcement;
e.g. pier and abutment caps, box culverts well curb, well cap,
walls with thickness greater than 300mm
RCC and PSC structures with highly congested reinforcements
e.g. deck slab girders, box girders, walls with thickness less than
300mm
Underwater concreting through tremie e.g bottom plug, cast-insitu piling
Slump (mm)
25
25
40 50
50 75
75 125
100 - 200
M 25
M 30
M 35
M 40
M 45
M 50
M 55
11
12
12
12
13
13
14
36
42
47
52
58
63
69
The initial current margin given in Table 1700.4 shall be used till sufficient data is
available to determine the current margin as per sub-clause (i) above.
12. 7
ADMIXTURES
12.7.1 Use of admixtures such as super plasticisers for concrete may be made with the approval of the
Engineer.
12.7.2 As the selection of an appropriate concrete admixture is an integral part of the mix design, the
manufacturers shall recommend the use of any one of his products only after obtaining complete
knowledge of all the actual constituents of concrete as well as methodologies of manufacture,
transportation and compaction of concrete proposed to be used in the project.
12.8
12.8.1 The size (maximum nominal) of coarse aggregates for concrete to be used in various components
shall be given in Table 12.5.
Table 1700-7
Components
i)
ii)
iii)
iv)
v)
vi)
20
As specified by Engineer
12.8.2 Maximum nominal size of aggregates shall also be restricted to the smaller of the following
values :
a)
10mm less than the minimum lateral clear distance between main reinforcements
b)
10mm less than the minimum clear cover to the reinforcements
139
12.8.3 The proportions of the various individual size of aggregates shall be so adjusted that the grading
produces densest mix and the grading curve corresponds to the maximum nominal size adopted
for the concrete mix.
CHAPTER-12 : SUPER-STRUCTURE
Sl
No
12.
1
Reference
to
MoRT&H
Specificat
ions
Rate
Item
No.
1500,
1600 &
1700
A
Cas
eI
(i)
(ii)
B
Cas
eI
(i)
(ii)
C
Cas
e1
(i)
Description
Unit
In
figure
s (`)
In words
Furnishing
and
Placing
Reinforced/Prestressed
cement concrete in superstructure as per drawing and
Technical Specification.
RCC Grade M25
Using Concrete Mixer
For solid slab super-structure,
20-30 percent of (a+b+c)
For T-beam & slab,
percent of (a+b+c)
cum
9189.0
0
cum
9556.0
0
cum
9293.0
0
cum
9665.0
0
25-35
Rupees Nine
Thousand One
Hundred and Eighty
Nine Only
Rupees Nine
Thousand Five
Hundred and Fifty Six
Only
RCC Grade M 30
Using Concrete Mixer.
For solid slab super-structure,
20-30 percent of (a+b+c)
For T-beam & slab,
percent of (a+b+c)
25-35
Rupees Nine
Thousand Two
Hundred and Nine
Three Only
Rupees Nine
Thousand Six
Hundred and Sixty
Five Only
140
cum
9321.0
0
Rupees Nine
Thousand Three
Hundred and Twenty
One Only
(ii)
(iii)
12.
2
12.
3
12.
4
12.
5
1600
2702
515 &
2702
2703,
1500,
1600 &
1700
23-33
Rupees Nine
Thousand and Seven
Hundred Only
Rupees Eleven
Thousand Two
Hundred and Sixteen
Only
cum
9700.0
0
cum
11216.
00
MT
94117.
00
cum
12995.
00
Rupees Twelve
Thousand Nine
Hundred and Ninety
Five Only
sqm
541.00
metr
e
3900.0
0
Mastic Asphalt
Providing and laying 12 mm
thick mastic asphalt wearing
course on top of deck slab
excluding prime coat with paving
grade
bitumen
meeting
the
requirements given in Table 50029,
prepared by using mastic
cooker and laid to required level
and slope after cleaning the
surface,
including providing
antiskid surface with bitumen
precoated fine grained hard stone
chipping of 9.5 mm nominal size
at the rate of 0.005cum per 10
sqm and at an approximate
spacing of 10 cm center to center
in both directions, pressed into
surface when the temperature of
surfaces not less than 100 deg. C,
protruding 1 mm to 4 mm over
mastic surface, all complete as
per Clause 515.
Construction of RCC railing of
M30 Grade in-situ with 20 mm
nominal size aggregate, true
to line and grade, tolerance
of vertical RCC post not to
exceed 1 in 500, centre to
centre
spacing
between
vertical post not to exceed
2000 mm, leaving adequate
space between vertical post
for expansion,
complete as
per approved drawings and
141
Rupees Three
Thousand and Nine
Hundred Only
Technical Specifications.
12.
6
2705
12.
7
2700
12.
8
1500,
1600,
1700 &
2704
12.
9
2607
PCC
M15
Grade
leveling
course below approach slab
complete as per drawing and
Technical Specification
Reinforced cement concrete
approach
slab
including
reinforcement and formwork
complete as per drawing and
Technical Specification
Strip Seal Expansion Joint
Providing and laying of a strip seal
expansion
joint
catering
to
maximum horizontal movement
upto 70 mm, complete as per
approved drawings and standard
specifications to be installed by
the manufacturer/supplier or their
authorised
representative
ensuring
compliance
to
the
manufacturer's instructions for
installation.
Rupees Seven
Thousand Six
Hundred and Forty
Six Only
Rupees Five
Thousand Eight
Hundred and Eighty
One Only
each
7646.0
0
cum
5881.0
0
cum
12274.
00
Rupees Twelve
Thousand Two
Hundred and Seventy
Four Only
metr
e
15441.
00
Rupees Fifteen
Thousand Four
Hundred and Forty
One Only
CHAPTER 13
13. REPAIR OF STRUCTURES
13.1 DESCRIPTION
13.1.1 Scope :
(i)
(ii)
Repair of structures shall be carried out in accordance with the repair plans and MoRT&H
Specifications or as directed by the Engineer. Where repair work is not covered by
MoRT&H Specifications, special specification may be framed.
Implementation of repair schemes shall also conform to provisions of IRC:SP:40.
13.2 SEALING OF CRACKS BY INJECTION OF EPOXY RESIN
142
13.2.1 General :
(i)
The work of epoxy adhesive utilising the Structural Concrete Bonding Process shall
conform to MoRT&H Specifications.
(v)
13.2.2 Personnel :
The Contractors personnel shall be qualified and experienced in epoxy injection process.
13.2.3 Material :
The material for injection shall be suitable two-component low viscosity epoxy resin, having the
required characteristics of bonding with concrete and resistance to moisture penetration. Epoxy
mortar or polysulphide resin may be used for sealing the surface.
The material for epoxy injection shall conform to the following:
(i)
The mixing ration of resin and hardener shall generally be between 1 to 1 and 2 to 1 by
volume subject to manufacturers recommendation.
(ii)
Neither the mixed epoxy adhesive nor their individual components shall contain solvents
and thinners.
(iii)
The components shall be free of lumps or foreign material. The viscosity of the individual
components shall not change more than 15 per cent when kept in closed containers at 25
degrees Celsius after two weeks.
(iv)
Consistency requirement.
Standard
Version
cps
(200-300)
Low Viscosity
Version
Cps
(100-190)
13.3.1 Material :
(i)
Grouting shall normally be performed with a mixture of neat Portland Cement and water.
Other additives and admixtures may be added to improve the impermeability, strength, etc.
on the approval of the Engineer. The size of the particles and the consistency of the grout
must be suited to the passageways it must follow. Neat grout will not flow freely into holes
smaller than about three times the largest cement particle. Except in large cavities where
thick mortar can be placed, the sand should all pass the 28-mesh sieve and have a large
portion passing the 50- and the 100- mesh sieves. The proportions of Ordinary Portland
Cement to sand will depend upon the size of the spaces to be filled and will vary from a
neat grout to about 1:1 mix. The amount of water to be added depends upon the
consistency required. Grouts with as little as 16 litres of water per bag of cement could be
handled and it should seldom be necessary to use more than 35 to 40 litres of water per
bag of cement.
(ii)
Where necessary and approved by the Engineer, admixtures to Portland Cement grout
mixtures may be added for delaying the setting time, increasing flow ability, minimising
segregation and shrinkage.
13.3.2 Preparation:
The surface shall be cleaned with wire brush and compressed air, 15mm dia and 150 to
200 mm deep holes along the length of the cracks at a spacing of 500 mm may be drilled
by wet drilling using rotary percussion drills nipples inserted in these holes.
13.3.3 Proportioning, Mixing and Equipment for Grouting :
(i)
The cement grout shall be mechanically mixed using a system of power-driven paddles of
high speed centrifugal pump. The grout pump to be used shall permit close control of
pressures to allow a flexible rate of injection with minimum clogging of valves and ports.
The most satisfactory equipment for injecting grout is a pump of the double-acting flexible
reciprocating type giving a steady flow. The grout pump shall be so placed as to reduce the
waste in cleaning lines. It is preferable to add 50 per cent or more of the mixing water into
the mixer before adding the dry ingredients and then the remaining water. A continuous
supply of grout is preferable to an intermittent one. Consistency of the grout may be
determined by trials starting with thin grout i.e. about 40 litres of water per bag of cement
and progressively decreasing the water content to about 15 litres per bag of cement.
(ii)
Where the mixer and pump are combined in one unit, the dry material shall be screened
before mixing. If the mixer and pump are in separate units, the grout shall pass through a
screen before it enters the pump.
13.3.4 Application :
(i)
Highest practical pressure within the limits 100-400 kPa should be used in order to force
the surplus water from the grout. As the pressure may be distributed hydraulically over
considerate areas, vigilance must be exercised to prevent damage or the needles waste of
144
(iii)
Pressure shall be steady to ensure a continuous flow of grout. Grouting shall not be
continued till the hole consumes mix at the rate of not less than 30 litres in 20 minutes or
until refusal at the grouting pressure of 400 kPa at any hole until refusal. Should the grout
escape from an adjacent nipple, it should be plugged of capped. Any seam, crack or joint
through which grout escapes shall be caulked with epoxy mortar as soon as thick grout
appears.
The gunite is a mixture of cement, sand and water. It comprises 100 parts by weight of
cement, 300 parts by weight quartz sand, 35-50 parts by weight water and 2 parts by
weight approved quick setting compound. In general, dry mix shotcrete shall be used.
(ii)
Ordinary Portland cement conforming to IS:269 shall be used in guniting.
Sand for guniting, shall comply with the requirements stipulated in IS:383. In general, sand should
neither be too coarse to increase the rebound nor too fine to increase the slump. Sand should preferably
have a moisture content between 3 to 6 per cent.
The grading of sand shall lie within the limits given below :
IS Sieve
Designation
4.75 mm
2.36 mm
1.18 mm
600 microns
300 microns
150 microns
145
(iv)
(v)
For thick sections it may be advantageous to incorporate coarse aggregate in the mix
provided adequate guniting equipment is available. Coarse aggregate, when used, shall
conform to grading given in Table I of IS: 9012. The percentage of coarse aggregate may
normally be kept as 20 to 40 per cent of the total aggregate and the mix shall be suitably
designed.
Water/cement ratio for guniting shall fall within the range 0.35 to 0.50 by mass, wet
enough to reduce the rebound. Drying shrinkage may be between 0.06 per cent to 0.10 per
cent. The quick setting compound shall be added at the nozzle with water just before
guniting.
13.4.1 Workmanship :
(i)
The cement and sand shall be batched and mixed and conveyed through a hose pipe with
the help of compressed air. A separate line shall bring the water under pressure. The
cement, sand and water mix shall be passed through and intimately mixed in a special
manifold and then projected at high velocity to the surface being repaired. The density of
gunite shall not be less than 2000 kg/cum. The strength of gunite shall not be less than 25
MPa. For effective guniting, the nozzle shall be kept 60 to 150 cm away from the surface,
preferably normal to that surface. While enclosing reinforcement bars during repairs the
nozzle shall be held closer at a slight angle and the mix shall be wetter than the normal.
(ii)
Test panels simulating actual field conditions shall be fabricated for conducting
preconstruction testing. The procedure for testing the cubes or cylinders taken from the
panels stipulated in clause 6 of IS:9012 shall be followed.
(iii)
It should be ensured from tests that a strength of about 25 MPa at 28 days is available for
the mortar/concrete mix.
(iv)
The defective concrete shall be cut out to the full depth till sound concrete surface is
reached. Under no circumstances should the thickness of concrete to be removed be less
than clear cover to the main reinforcement. No square shoulders shall be left at the
perimeter of the cut-off portion and all edges shall be tapered. Thereafter, all loose and
foreign materials should be removed and the surface be sandblasted to make it rough to
receive shotcrete after applying a coat of bonding epoxy as per recommendations of the
manufacturer @ 1.0 kg per 1.5 sq.m of surface area.
(v)
The exposed reinforcement shall be thoroughly cleaned free of rust, scales etc. by wire
brushing. Wherever the reinforcements have been corroded, the same shall be removed
and replaced by additional reinforcement. Before application of gunite, a coat of neat
cement slurry should be applied on the surface of the reinforcement.
(vi)
Sufficient clearance shall be provided around the reinforcement to permit encasement with
sound gunite. Care shall be taken to avoid sand pockets behind the reinforcement.
(vii)
(ix)
(x)
Where required, welded wire fabrics 5cm x 5cm x No.10 gauge shall be provided in the
first layer of guniting. The fabric shall be tied properly. In case the damage to the concrete
member is too deep, the specifications for guniting as well as requirement of placement of
wire mesh has to be decided as per field conditions.
The stipulations given in IS:9012 regarding application of gunite should be followed so as
to keep the rebound to the minimum. The quality of guniting and workmanship shall be
such that the percentage of rebound mentioned in IS:9012 can be adhered to. In no
circumstances shall the rebound material be re-used in the work.
It would be desirable that green gunite is moistened for at least 7 days. Guniting work
shall not be done during windy or rainy conditions.
13.5 DISMANTLING OF CONCRETE WEARING COAT
The existing expansion joint assemblies shall be removed carefully along the entire width
of the carriageway. The deck slab for a width of 400 mm on either side should be removed
for placing of reinforcement, anchor rods, anchor bolts and other fixing assemblies for the
new expansion joints and pouring of fresh concrete. The gap between the girders over the
piers should be cleared of all debris. A temporary platform in the gap at the end of girders
shall be erected to collect the materials falling down during concreting and fixing of
expansion joints.
(iv)
The service lines, if any, shall be disconnected/diverted before the dismantling work starts.
13.5.2 Dismantling of concrete wearing coat shall be carried out using jack hammers or suitable manual
methods as approved by the Engineer. Care should be taken to avoid any damage to the existing
structure including reinforcement or pre-stressing anchorages for cables, if any, located in the
deck slab.
(v)
dismantling, especially where tools like jack hammers are deployed to protect eyes from
injuries from flying pieces, dirt, dust etc. Leather or rubber gloves shall be worn by the
workers during the demolition of RCC work. Screens made up of GI sheets shall be placed
wherever necessary to prevent the flying pieces from injuring the workers.
Water should be sprayed to reduce the dust while removing concrete wearing course with
jack hammer. No work shall be taken up under the span when dismantling work is in
progress.
Reference
to MoRT&H
Specificati
ons
Rate
Item
No.
Description
Unit
148
In
figures
(`)
In words
13.1
13.2
13.3
13.4
2809
2807
2800
2806
A
13.5
13.6
13.7
2803
Cement Grout.
Sealing of crack / porous concrete
with Epoxy Grout by injection
through nipples complete as per
Clause 2803.1.
ADDITIONAL ITEM
Painting including supply of paint
over steel work with anticorrosive paint two coats after
properly cleaning the surface by
steel brushes, gunny bags, emry
cloth etc. complete as directed.
Painting including supply of paint
over steel work in built up girders
with alluminium paints two coats
after properly cleaning and filing
the surface by steel brushes,
gunny bags, emry cloth etc.
complete as directed.
149
278.00
sqm
2372.00
Rupees Two
Thousand Three
Hundred and Seventy
Two Only
each
154.00
kg
122.00
kg
1810.00
sqm
106.00
each
26958.0
0
sqm
13.7
13.8
0
150
each
40108.0
0
Rupees Forty
Thousand One
Hundred and Eight
Only
each
65751.0
0
each
83285.0
0
each
97531.0
0
each
195609.
00
sqm
106.00
sqm
101.00
Rate
Description of Labour
Uni
t
In
Figures
(`)
Mate / Supervisor
day
450.00
day
400.00
day
400.00
day
400.00
day
400.00
Driller
day
350.00
day
350.00
day
300.00
day
300.00
10
Mazdoor (Skilled)
day
170.00
11
day
150.00
12
Mazdoor (Un-skilled)
day
130.00
151
In Words
Rupees Four
Hundred Fifty Only
Rupees Four
Hundred Only
Rupees Four
Hundred Only
Rupees Four
Hundred Only
Rupees Four
Hundred Only
Rupees Three
Hundred Fifty Only
Rupees Three
Hundred Fifty Only
Rupees Three
Hundred Only
Rupees Three
Hundred Only
Rupees One
Hundred Seventy
Only
Rupees One
Hundred Fifty Only
Rupees One
Hundred Thirty
Only
APPENDIX II: RATES OF STONE BOULDERS, STONE AGGREGATES, STONECHIPS,GRANULAR SUB-BASE MATERIAL , SAND, etc
Rate
Sl.
Uni
In
N
Description
t
Figure
o.
s (` )
In Words
Stone Boulder of size 150 mm and
Cu
1
650.00 Rupees Six Hundred
below at Crusher Plant
m
Fifty Only
2
Cu
m
635.00
Cu
m
600.00
Cu
m
800.00
Cu
m
750.00
Rupees Seven
Hundred Fifty Only
Cu
m
700.00
Rupees Seven
Hundred Only
Moorum at Site
Cu
m
200.00
Cu
m
400.00
Cu
m
400.00
12
Cu
m
500.00
13
Cu
m
1200.0
0
14
Cu
m
1280.0
0
15
Cu
m
1310.0
0
16
Cu
m
1340.0
0
17
Cu
m
1350.0
0
152
Cu
m
1070.0
0
Cu
m
970.00
Cu
m
270.00
Cu
m
1000.0
0
22
Cu
m
1350.0
0
23
Cu
m
1100.0
0
24
Cu
m
1200.0
0
25
Cu
m
1420.0
0
26
Cu
m
1400.0
0
27
Aggregates 45 mm to 2.8 mm
Cu
m
1320.0
0
28
Aggregates 45 mm to 22.4 mm
Cu
m
1250.0
0
29
Aggregates 53 mm to 2.8 mm
Cu
m
1350.0
0
30
Aggregates 53 mm to 22.4 mm
(grade III)
Cu
m
1300.0
0
31
Aggregates 63 mm to 2.8 mm
Cu
m
1290.0
0
32
Aggregates 63 mm to 45 mm(grade
II)
Cu
m
1200.0
0
33
Aggregates 90 mm to 45 mm(grade I)
Cu
m
1000.0
0
34
Aggregates 10 mm to 5 mm
Cu
m
1690.0
0
35
Cu
m
1680.0
0
18
19
20
21
153
36
Cu
m
1650.0
0
37
Cu
m
1650.0
0
38
Aggregates 13.2 mm to 10 mm
Cu
m
1650.0
0
39
Aggregates 20 mm to 10 mm
Cu
m
1600.0
0
40
Aggregates 25 mm to 10 mm
Cu
m
1580.0
0
41
Aggregates 19 mm to 6 mm
Cu
m
1600.0
0
42
Aggregates 37.5 mm to 19 mm
Cu
m
1150.0
0
43
Aggregates 37.5 mm to 25 mm
Cu
m
1100.0
0
44
Cu
m
1650.0
0
45
Cu
m
1620.0
0
46
Cu
m
1600.0
0
47
Cu
m
1500.0
0
48
Cu
m
1400.0
0
49
Cu
m
1200.0
0
154
Sl.
No
Description of
Machineries
1.
2.
3.
4.
5.
6.
7.
8.
9.
Units of
Measureme
nts
Usage
Charge
(`/Hr)
Running
Charge
(`/Hr)
Total
Charge
without
Diesel
(`/Hr)
Total
Charge
with
Diesel
(`/Hr)
Air Compressor
170/250
Air Compressor with
Pneumatic chisel
attachment for
cutting hard clay
Capacity in
cfm/hour
3094
193.00
298.00
491.00
679.00
336.00
492.00
828.00
3821.00
3 Cum/hour
350.00
426.00
776.00
1199.00
15-20
Cum/hour
100-120 tph
747.00
739.00
1486.00
2332.00
1400.00
550.00
1950.00
2796.00
Sqm/hour
337.00
367.00
704.00
1033.00
1500
Capacity in ltr
4 tonnes
402.00
418.00
820.00
1290.00
399.00
360.00
759.00
1370.00
2850.00
6228.00
9707.00
1120.00
566.00
9078.00
(450/perso
n)
1686.00
20 Cum/hour
920.00
538.00
1458.00
1881.00
45 & 30
Cum/hour
1 Capacity in
cum
Cum/hour
56.00
299.00
355.00
590.00
10.00
83.00
93.00
93.00
150.00
306.00
456.00
550.00
Cum/hour
84.00
306.00
390.00
484.00
80 tonnes
873.00
618.00
1491.00
2713.00
155
2062.00
17. Crane
35 tonnes
622.00
551.00
1173.00
1784.00
18. Crane
3 tonnes
114.00
331.00
445.00
680.00
19. Crane
F-15
622.00
761.00
1383.00
1994.00
20. Crane
5-tonne
capacity
350.00
331.00
681.00
916.00
21. Crane
10 tonne
capacity
15 tonne
capacity
20 tonne
capacity
40 tonne
capacity
0.75 cm
600.00
331.00
931.00
1166.00
900.00
331.00
1231.00
1701.00
1600.00
331.00
1931.00
2401.00
3000.00
331.00
3331.00
3942.00
900.00
331.00
1231.00
1466.00
2800.00
500.00
3300.00
3864.00
75 cum per
hour
1250.00
500.00
1750.00
2314.00
Cum/hour
975.00
465.00
1440.00
2098.00
Cum/hour
1692.00
532.00
2224.00
3070.00
75
tonnes/hour
1750
Sqm/hour
1400.00
839.00
2239.00
8819.00
263.00
375.00
638.00
967.00
337.00
360.00
697.00
885.00
15.00
87.00
102.00
102.00
22. Crane
23. Crane
24.
Crane
Dozer D-80-A-12
Emulsion Sprayer
4 tonnes
Cum/hour
311.00
483.00
794.00
1170.00
125-160 KVA
164.00
326.00
490.00
725.0
KVA
143.00
286.00
429.00
617.00
37.
50 Cum/hour
377.00
402.00
779.00
1625.00
KVA
92.00
326.00
418.00
653.00
KVA
159.00
361.00
520.00
708.00
38.
39.
GSB Plant
Generator 33 KVA
Generator 100 KVA
156
40.
KVA
166.00
286.00
452.00
640.00
Cum/hour
2365.00
878.00
3243.00
14993.00
Cum/hour
1866.00
822.00
2688.00
13028.00
Cum/hour
1495.00
686.00
2181.00
11581.00
Cum/hour
970.00
615.00
1585.00
10985.00
Cum/hour
726.00
557.00
1283.00
8333.00
1500
Sqm/hour
Cum/hour
846.00
599.00
1445.00
1868.00
404. 00
492.00
896.00
1319.00
100 TPH
5590.00
588.00
6178.00
10314.00
200 TPH
2241.00
544.00
2785.00
4430.00
50.00
171.00
221.00
221.00
hour
105.00
146.00
251.00
298.00
80 Rm/hour
125.00
346.00
471.00
800.00
Cum/bucket
696.00
595.00
1291.00
1620.00
1 Capacity in
tone
1250
Sqm/hour
ED-30
56.00
249.00
305.00
399.00
230.00
323.00
553.00
882.00
298.00
323.00
621.00
997.00
Cum/hour
759.00
504.00
1263.00
1592.00
270 Sqm/hour
337.00
314.00
651.00
1074.00
Cum/hour
947.00
668.00
1615.00
1944.00
Cum/hour
1725.00
146.00
1871.00
2200.00
Cum/hour
274.00
668.00
942.00
1271.00
157
Rotavator
Ripper
Cum/hour
629.00
668.00
1297.00
1626.00
3525.00
509.00
4034.00
6149.00
2 Cum/hour
485.00
482.00
967.00
1296.00
1.5-2
Cum/hour
4 Cum/hour
1344.00
629.00
1973.00
2584.00
358.00
460.00
818.00
1147.00
52.00
340.00
392.00
439.00
1012.00
508.00
1520.00
1943.00
25 Cum/hour
18.00
216.00
184.00
231.00
60 Cum/hour
11.00
208.00
234.00
281.00
10 m/hour
26.00
248.00
299.00
346.00
541.00
336.00
877.00
885.00
297.00
409.00
706.0
1082.00
3450.00
467.00
3917.00
4152.00
120.00
112.00
232.00
232.00
185
416
601.00
789.00
223 Rm/hour
73.
74. Smooth Wheeled
Roller 8 tonne
75. Snow blower
equipment 140 HP @
600 cum per hour
76. Steel Drum 300mm
diameter 1.2 mtr
height
77. Spot Mix Plant
70 Cum/hour
8-10 tonnes
246.00
470.00
716.00
951.00
10-12 tonnes
179.00
448.00
627.00
721.00
Cum/hour
446.00
432.00
878.00
1301.00
Cum/hour
437.00
432.00
869.00
1074.00
Capacity in
HP
162.00
422.00
584.00
866.00
173.00
670.00
843.00
1172.00
180.00
588.00
768.00
1097.00
1350.00
433.00
1783.00
2206.00
6-10 tph
158
1250.00
500.00
1750.00
5886.00
Cum/hour
527.00
481.00
1008.00
1384.00
Capacity in KL
120.00
446.00
566.00
848.00
777.00
515.00
1292.00
8342.00
1750.00
701.00
2451.00
9501.00
1500.00
586.00
2086.00
9136.00
Description of Item
Unit
Rate
In
figure
s
(` )
Alluminium Paint
metre
250.0
0
litre
300.0
0
159
In words
Rupees Two Hundred Fifty Only
Barbed wire
kg
65.00
Binding wire
Kg
80.00
Brick
each
8.10
cum
66.00
Curing compound
liter
250.0
0
each
1600.
00
cum
180.0
0
10
Nos
26.00
11
GI bolt 10 mm Dia
Nos
39.00
12
litre
525.0
0
13
M.S. Clamps
Nos
60.00
14
Nipples 12mm
Nos
30.00
15
Kg
130.0
0
16
Paint
litre
280.0
0
17
Primer
Kg
120.0
0
18
cum
300.0
0
19
Kg
180.0
0
20
Nos
5.00
160
21
Nos
30.00
22
Nos
100.0
0
23
Unslaked lime
tonne
3600.
00
24
Water
KL
235.0
0
25
Kg
100.0
0
APPENDIX V : MARKET RATES OF ISI CLASS NP3 AND NP4 HUME PIPES
Sl
.
N
o.
1
ISI
Cla
ss
NP3
Intern
al
diame
ter
1.00m
Rate
Barrel
length
Barrel
thickn
ess
Unit
2.50m
100m
m
Runnin
gmetre
161
In
figures
(`)
In words
Rupees Seven
7560.00 Thousand Five
Hundred Sixty Only
Runnin
gmetre
Gelatin
Electric Detonators @ 1
detonator for 1/2
gelatin stick of 125 gms
each
100 Nos.
tonne
Bitumen (80-100
grade )
tonne
per tonne
kg
162
Bitumen (modified
graded,CRMB-55)
tonne
Bitumen (PMB-55)
tonne
tonne
54400.00
tonne
10
53719.00
tonne
11
Bitumen Emulsion
(Rapid Setting)
12
Bitumen Emulsion
( Medium Setting)
13
Bitumen
emulsion( Slow Setting)
43318.00
tonne
48440.00
tonne
45471.00
tonne
14
53447.00
163
Road Classification
1.
12.00
2.
9.00
4.
i)Single lane
7.50
ii)Two lane
9.00
7.50
TABLE II: ROADWAY WIDTH FOR SINGLE-LANE AND TWO-LANE ROADS IN MOUNTAINOUS AND STEEP
TERRAIN
Sl.No.
Road Classification
i)Single lane
6.25
ii)Two lane
8.80
2.
4.75
3.
4.00
Note:
1. The roadway width given above are exclusive of parapets (usual width 0.6m) and side drains (usual
width 0.6m).These should be provided in addition to the shoulders as necessary.
2. The road way width of village road are on the basis of a single lane carriageway of 3m. If a higher
pavement width is adopted, the roadway width should be increased correspondingly.
3. In hard rock stretches, or unstable locations where excessive cutting might lead to slope failure, width
of road way should be reduced by 0.8m on two lane road and 0.4m in other cases. However, where
such stretches occur in continuous long length, reduced in roadway width should not be effected unless
requisite passing place are provided.
4. On roads which are subjected to heavy snowfall, where snow regular clearance is done over long
periods to keep the road open to traffic, roadway width may be increased by 1.5m for MDRs, ODRs
and VRs.
164
Passing places are not necessary on two lane National and State Highways having roadway width
in accordance with Table I above. But on single lane sections having narrower roadway, it may be
desirable to provide some passing places depending on actual needs. On other roads, these should be
provided in general at the rate of 2-3 per cent kilometer. Their exact location should be judiciously
determined taking into consideration the available extra width on curves and visibility.
Normally, the passing places/lay-byes should be 3.0 m wide and 30m long on the inside edge (i.e.
towards the carriageway side) and 20m long on the farther side.
WIDTH OF CARRIAGE WAY
The standard width of carriageway shall be as indicated in Table III below. Total width should be
determined in relation to the design traffic and capacity of the roadway.
TABLE III: WIDTH OF CARRIAGE WAY
Width of carriage way (in metres)
Single lane
Two lanes
without kerbs
Multi-lane
pavement width
per lane
3.75**
7.0
7.5
3.5
Notes: 1.**
On village roads, the carriageway width may be restricted to 3.0m normally.
Widths greater than 3.0m may however be adopted judiciously depending on the types and
intensity of traffic cost and related factor.
2.
Except on important trunk routes, an intermediate carriageway width of 5.5 metres may
also adopted instead of regular two lanes if the same is considered advantageous.
Where the carriageway width changes i.e. from single lane to two lanes to four lanes, transition
should be effected through a taper of 1 in 15 to 1 in 20.
PERMANENT CAMBER OR CROSS-FALL:
The Camber or cross-fall on straight sections of roads should be as recommended in the Table IV
below for various types of surfaces. For a given surface type, the steeper value may be adopted in areas
having high intensity of rainfall and the lower values where the intensity of rainfall is low.
Sl.N
o.
Surface type
Camber/Cross-fall
1.
2.
3.
4.
Earth
Vehicle type
Equivalency factor
1.
1.0
2.
0.5
3.
3.0
4.
Cycle Rickshaw
1.5
5.
Horse-drawn vehicle
4.0
6.
Bullock cart
6-8
166
TABLE VI : MINIMUM TRANSITION LENGTH FOR DIFFERENT SPEEDS AND CURVE ROAD
Plain and rolling terrain
Curve
radius
Curve
radiu
P(met
re)
100
80
65
50
40
35
50
40
30
25
20
NA
70
14
NA
75
55
20
NA
NA
NA
NA
30
35
20
90
NA
74
45
35
25
NA
25
20
100
80
45
40
25
30
30
25
15
150
70
40
35
20
40
NA
25
20
15
170
NA
60
35
30
20
50
40
20
15
15
200
90
50
30
25
NR
55
40
20
15
15
240
75
40
25
20
70
30
15
15
15
NR
300
NA
60
35
20
20
80
NA
25
15
15
360
130
55
30
20
NR
90
55
25
15
15
400
115
45
25
NR
100
45
20
15
15
500
65
35
20
125
45
15
15
NR
600
80
35
20
150
35
15
700
70
30
NR
200
30
15
800
60
30
200
20
15
900
55
30
250
20
15
1000
50
NR
300
15
NR
1200
40
400
15
1500
35
500
NR
1800
30
2000
NR
NA - Not applicable.
The extra width of carriageway to be provided at horizontal curves on single and two-lane roads is
given in Table VII below. For multi-lane roads, the pavement widening may be calculated by adding half
the widening for two-lane roads to each lane.
TABLE VII : EXTRA WIDTH OF PAVEMENT AT HORIZONTAL CURVES
167
Radius of
curve
(m) Extra
width
(m)
Upto 20
21 to 40
41 to 60
61 to 100
101 to
300
Above
300
Two-lane
1.5
1.5
1.2
0.9
0.6
Nil
Singlelane
0.9
0.6
0.6
Nil
Nil
Nil
The widening should be effected by increasing the width at an approximately uniform rate along
the transition curve. The extra width should be continued over the full length of the circular curve. On
curve having no transition, widening should be achieved in the same way as the super-elevation i.e.
(two-third) being attained on the straight section before the start of the curve and (one-third) on the
curve.
The widening should be applied equally on both side of the carriageway, except that on hill roads
it will be preferable the entire widening is done on the inside. Similarly, the widening should be provided
only on the inside when the curve is plain circular and has no transition.
Recommended gradients for different classes of terrain are given in Table below:
TABLE VIII : GRADIENTS FOR ROADS IN DIFFERENT TERRAIN
Sl.N
o.
Terrain
1.
Plain or rolling
2.
Mountainous terrain,
steep terrain having
elevation more than
3,000m above the mean
seal level
3.
Ruling
gradient
Limiting
gradient
Exceptional
gradient
3.3 percent
5 percent
6.7 percent
(1 in 30)
(1 in 20)
(1 in 15)
5 percent
6 percent
7 percent
(1 in 20)
(1 in 16.7)
(1 in 14.3)
6 percent
7 percent
8 percent
(1 in 16.7)
(1 in 14.3)
(1 in 12.5)
Gradients upto the Ruling gradient may be used as a matter of course in design. However, in
special situations such as isolated over-bridges in flat country or roads carrying a large volume of slow
168
moving traffic it will be desirable to adopt a flatter gradient of 2% from the angle of aesthetic, traffic
operation and safety.
The limiting gradient are meant to be adopted only in difficult situations and for short lengths of
continuous grade steeper than the ruling gradient.
Exceptional gradients are meant to be adopted only in difficult situations and for short length not
exceeding 100m at a stretch in mountainous and steep terrain. Successive stretches of exceptional
gradient must be separated by a minimum length of 100m having gentler gradient (i.e. limiting gradient
or flatter gradient).
The rise in elevation over a 2 Km length shall not exceed 100m in mountainous terrain and 120m
in steep terrain.
VERTICAL CURVES
Vertical curves are introduced for smooth transition at grade changes. Convex vertical curves and known
as summit curves. Vertical concave curves are known as valley or sag curves. Both these should be designed as
square parabolas.
The length of the vertical curves is controlled by sight distance requirement but curves with greater length
are as aesthetically better.
Curves should be provided at all grade changes exceeding those indicated in the Table IX below. For
satisfactory appearance the minimum length should be as shown in the following Table.
TABLE IX : MINIMUM LENGTH OF VERTICAL CURVE
Design Speed
(Km)
Upto 35
1.5
15
40
1.2
20
50
1.0
30
65
0.8
40
80
0.6
50
100
0.5
60
Measuring - The quantity of cement shall be determined by weight. Ordinary Portland Cement
shall be taken to weigh 1440 kg/m3, and rapid hardening Portland cement to weigh 1210 kg/m3. The
quantities of fine and coarse aggregates shall be determined either by volume or preferably by weight.
The proportions given in Table XII are based on the assumption that the aggregates are dry. If aggregates
are wet, due allowance shall be made for bulking in accordance with IS : 2386 m (Part III) - 1963 :
Methods of test for Aggregates for Concrete: Part III- Specific Gravity, Density, Voids, Absorption and
bulking.
Mixing - Concrete shall normally be mixed in mechanical mixer.
Mixing shall be continued until there is a uniform distribution of the materials and the mass is
uniform in colour and consistency, but in no case shall mixing be done for less than two minutes.
When hand mixing is permitted by the Engineer-in-Charge, it shall be carried out on a water-tight
platform and care shall be taken to ensure that mixing is continued until the mass is uniform in colour and
consistency.
Transporting : Concrete shall be handled from the place of mixing to the place of final deposit as rapidly
as practicable by methods which will prevent the segregation or loss of any of the ingredients. If
segregation does occur during transport, the concrete shall be re-mixed before being placed.
During hot or cold weather, concrete shall be transported in deep containers. The deep containers on
account of their lower ratio of surface area to mass, reduce the rate of loss of water by evaporation during
hot weather and loss of heat during cold weather.
PLACING AND COMPACTING:
GENERAL: The concrete shall be placed and compacted before setting commences and should not be
subsequently disturbed. Method of placing should be such as to preclude segregation.
.
CONSTRUCTION JOINTS:- Concreting shall be carried out continuously up to construction joints, the
position and arrangement of which shall be pre determined by the designer.
When the work has to be resumed on a surface which has hardened, such surface shall be roughened. It
shall then be swept, clean, thoroughly wetted and covered with a 13 mm layer of mortar composed of
cement and sand in the same ratio as the cement and sand in the concrete mix. This 13 mm layer of
mortar shall be freshly mixed and placed immediately before placing of the concrete.
When the concrete has not fully hardened, all laitance shall be removed by scrubbing the wet surface with
wire or bristle brushes, care being taken to avoid dislodgement of particles of aggregate. The surface shall
be thoroughly wetted and all free water removed. The surface shall then be coated with cement grout. The
first layer of concrete to be placed on this surface shall not exceed 150 mm in thickness, and shall be well
rammed against old work, particular attention being paid to corners and clot spots.
Concrete shall be thoroughly compacted during the operation of placing, and thoroughly around the
reinforcement, embedded fixtures and into corners of the form work.
170
GRADE OF
CONCRETE
M 100
135
100
M 150
200
150
M 200
260
200
M 250
320
250
M 300
380
300
M 350
440
350
M 400
500
400
NOTE 1:
171
a)
b)
Preliminary Test -A test conducted in a laboratory on the trial mix* of concrete produced in the
laboratory with the object of :
1)
2)
Determining the adjustments required in the designed mix when there is a change in the materials
used during the execution of work, or
3)
Work Test -A test conducted either in the field or in a laboratory on the specimen made on the works, out
of the concrete being used on the works.
TABLE XI : OPTIONAL WORKS TEST REQUIREMENTS OF CONCRETE
(Clause 5.2.2.1)
(All values in Kg/cm)
(All test conducted in accordance with IS: 516 -1959)
GRADE OF CONCRETE
COMPRESSIVE
STRENGTH ON 15 - cm
CUBES MIN AT 7 DAYS
MODULUS OF RUPTURE
BY
BEAMS TEST, MIN
At 72 - 2 hr
At 7 Day
M 100
70
12
17
M 150
100
15
21
M 200
135
17
24
M 250
170
19
27
M 300
200
21
30
M 350
235
23
32
M 400
270
25
34
NOTE - Notes 2 and 3 under Table 1 are also applicable to Table 11.
Grade of
Concrete
Ordinary Concrete
Total quantity of
Dry Aggregates
by Volume per 50
Kg of Cement, to
be taken as the
sum of the
Individual
Volumes of Fine
and Coarse
Aggregates, Max
Proportion of
Fine Aggregate
to Coarse
Aggregate
Quantity of Water
per 50 Kg of
cement max
Litres
Litres
M 100
300
M 150
220
M 200
160
M 250
100
* NOTE 1:
NOTE 2 :
34
32
30
27
The proportions of the aggregates should be adjusted from upper limit to lower
progressively as the grading of the fine aggregates becomes finer and the maximum
size of coarse aggregate become larger. Example : For an average grading of fine
aggregate (i.e., Zone II of IS: 383 -1963) the proportions shall be 1:1 , 1:2 and 1:3 for
maximum size of aggregate 10 mm and 40 mm respectively.
It may be noted for general guidance that M 100, M 150, M 200, M 250 of ordinary
concrete correspond approximately to 1:3:6, 1:2:4, 1:1:3 and 1:1:2 nominal mixes of
concrete currently used in the country.
OF AGGREGATE
mm
10
3.0
20
2.0
40
1.0
173
3.3 SELECTION OF WATER CONTENT AND FINE TWO TOTAL AGGREGATE RATIO
3.3.1: For the desired workability, the quality of mixing per unit volume of concrete and the ratio of fine
aggregate to total aggregate by absolute volume are to be estimated from Table V as applicable,
depending upon the nominal maximum size and type of aggregates.
TABLE XIV : APPROXIMATE SAND AND WATER CONTENTS PER CUBIC METRE
OF CONCRETE FOR GRADES UPTO M 35
NOMINAL MAXIMUM
SIZE OF AGGREGATE
mm
10
SAND AS PERCENT OF
TOTAL AGGREGATE
BY ABSOLUTE
VOLUME.
40
20
186
35
40
165
30
2
3
Cement concrete:1:1 : 3
1:2:4
1:3:6
1:4:8
Brick work Masonry 1:3
Mortar
Stone Masonry
1:3 Mortar with random rubble
masonry
1:3 Mortar Stone Masonry
1:4 Mortar
1:6 Mortar
Plastering 12 mm thick
1:2 Mortar
1:3 Mortar
1:4 Mortar
1:6 Mortar
Finishing on R.C.C. work
Finishing on Plain Concrete
Flush or rolled or cut or
weather pointing on brick with
mortar, 1:3
400 Kg
330 Kg
220 Kg
170 Kg
122.4
168.50 Kg
153 Kg
90 Kg
50 Kg
Brick Work
11.5 Kg/m
8.20 Kg /m2
6.20 Kg/m
4.35 Kg /m2
1:2:4
1:3:6
10.70 Kg /m
8.20 Kg /m
5.50 Kg /m
1.35 Kg /m
2.00 Kg/m
100 Sq.m
174
153 Kg
7
8
100 Sq.m
235 Kg
100 Sq.m
117 Kg
100 Sq.m
194Kg
If contractor misuses the quantity of cement in more than the above standards the cost will be
recovered from him at double the price specified in the recovery schedule.
Whenever the strength of concrete is specified in the tender, the variances of cement required to
obtain the design strength may be used even if it is at variance with the above standard, subject to the
approval by the Superintending Engineer-In-Charge in writing.
TABLE XVI : UTILISATION OF MATERIALS OF DIFFERENT ITEMS (TO BE ADOPTED FOR
DEDUCTION OF FOREST ROYALTY AND FOR CARRIAGE)
1
P.C.C
P.C.C.M 15
P.C.C.M 15
Per Sq.m
Pointing 1:2
Per Sq.m
Sand - 0.35
2
3
4
5
P.C.C.M. 25
P.C.C.M. 25
TABLE XVII : CONTROL TESTS AND THEIR MINIMUM FREQUENCY FOR SUB BASES AND
BASES (EXCLUDING BITUMEN BOUND BASES)
SI.
Type of Construction
Test
Frequency
175
No.
1
Granular sub-base
(i) Gradation
3.
As required
(vi) C.B.R.
As required
Regularly, through
procedural checks
Periodically as considered
necessary
As required
As required
176
(ii)Grading
903.4
903.4.1
The test and then minimum frequencies for the different types of bituminous works shall be as given
in Table XVIII.
903.4.2
Acceptance Criteria : The acceptance criteria for test on density and Marshall stability shall be
subjected to the condition that the mean value is not less than the specified value plus:
1.65 -
1.65
2.
Type of
Construction
Prime coat / tack coat/
Fog Spray
Seal Coat/Surface
Dressing
Test
Frequency
At regular close
177
(viii) Soundness
Magnesium &
Sodium Sulphate)
As Required
(x) Temperature of
binder at application
(xii) Percentage of
fractural faces
SI.
No.
Type of
Construction
Test
Frequency
3.
178
4.
Bituminous Macadam
5.
Bituminous
Penetration
Macadam/Built-up
Spray- Grout
179
Dense Bituminous
Macadam/Semi
Dense
Bituminous Concrete/
Bituminous Concrete
Mastic Asphalt
8.
9.
Slurry seal
Cold Mix
10.
Modified Binder
(i)Softening Point
(ii) Penetration at 250C and
40C
(iii) Elastic Recovery
(iv) Ductility
-do-
-do-
Initially on submission
-do-
-do-
182
The 3 metre straight edge may be made of steel of seasoned hard wood. When made of wood, it
may be 75 mm wide and 125 mm deep and its test face should preferably be shod with a metallic
plate. The edge should be perfectly straight and free from warps, rots or defects of any kind.
(ii)
Periodically, the straight edge should be checked for its trueness with a string or a metallic master
straight-edge. The straight-edge should be rectified/replaced as soon as the same has lost it
trueness.
(iii)
The depression under the straight edge are to be measured with a graduated wedge. The wedge
should preferably be metallic but may alternatively be of seasoned hard wood. These should be
graduated to read undulation upto 25 mm with a least count of at least 3 mm.
(iv)
For recordings undulation in the longitudinal profile the straight-edge is to be placed be sufficient
for a single lane pavement and along three lines for the two- lanes pavement. One additional line
may be covered for each additional line may be covered for each additional lane.
(v)
The straight -edge has limitations as regards the measurement of undulations at vertical curves.
Additional templates may be made for this purpose especially if the curves are sharp.
(vi)
The straight-edge may be placed at the starting point, wedge inserted between it and the test
surface where the gap is maximum and reading taken. The edge may then be slided forward by
about length, i.e., 1.5 m and the wedge reading repeated. This process should be continued. The
straightedge need not always be moved forward but may be moved backward and forward to
183
record maximum at allocation. Locations with undulation in excess of the specified magnitude
should be marked on the surface.
(vii)
A team of three persons consisting of two workmen and a supervisor and equipped with one
straight-edge and two graduated wedges would be required. The two workmen will operated the
straight-edge while the supervisor will take measurements with the wedge and do the marking on
the surface.
Type of construction
16
12
Cross Profile
Maximum
permissible
variation from
specified profile
under camber
template, mm
10
6
Earthen sub-grade
24
30
15
Stone Soiling/
Brick Soiling
Stabilised Soil
20
30
15
30
12
Water Bound
Macadam Oversize
metal
(40-90mmsize)
Water Bound
Macadam with
normal size
15
30
12
12
30
3
4
184
7
8
9
10
metal(20 - 50 mm
and 40-60 mm
size), penetration
macadam or BUSG
Surface dressing
(two coat) over
WBM (20-50 mm
or 40-63 mm size
metal),
penetration
macadam or BUSG
Open graded
premix carpet 2025 mm thick
Bituminous
Macadam
Asphaltic Concrete
Cement Concrete
12
20
10
30
10
20
10
10
NOTES:
1. *For surface dressing in all other cases the standard of surface evenness will be the same as for the surface
receiving the surface dressing.
2. These are for machines laid surface, if laid manually due to unavoidable reasons discretion of the
Engineer-in-Charge. However, this relaxation does not apply to the values of maximum undulation for
longitudinal profiles mentioned in column 3 of the table.
3. Surface evenness requirements in respect of both longitudinal and cross profiles should be simultaneously
satisfied.
Size
Area
(mm)
(cm)
Perimet
er
Weight
Kg/m
N/m
(cm)
6
0.283
1.89
0.222
2.18
0.503
2.51
0.395
3.87
10
0.785
3.14
0.617
6.05
12
1.131
3.77
0.888
8.71
16
2.011
5.03
1.579
15.48
18
2.645
5.65
1.997
19.59
20
3.143
6.28
185
2.467
24.2
22
3.801
6.91
2.985
29.27
25
.4.909
7.85
3.855
37.82
28
6.157
8.8
4.836
47.44
32
8.042
10.05
6.316
61.96
36
10.179
11.31
7.994
78.42
40
12.566
12.57
9.869
96.81
ISJB 150
ISJB 175
ISJB200
ISJB225
ISJB75
ISJB 100
ISGB 115
ISJB 150
ISJB 175
ISJB 200
ISJB226
ISJB275
ISJB 300
ISJB325
ISJB350
ISJB400
ISJB450
186
ISJB 500
65.3
83.14
450
170
13.4
8.6
ISJB 550
75.0
95.90
500
180
14.1
9.2
ISJB 600
86.3
ISJB 100
99.5
ISJB 125
11.5
ISJB 150
13.0
109.9
7
126.6
9
14.60
500
190
15.0
27536.
1
38759
8.0
9.9
000
210
15.5
10.5
100
75
7.2
4.0
125
75
7.6
53161.
6
72867.
6
4.4
ISJB 175
14.9
16.60
150
00
7.6
4.8
ISJB 200
19.3
19.00
175
9J
8.6
5.5
ISJB 225
25.4
24.62
200
100
10.8
5.7
ISJB 250
31.2
32.33
225
110
11.8
6.5
ISJB 275
37.3
39.72
200
125
12.5
6.9
ISJB 300
44.2
47.55
300
140
12.4
7.5
257.5
449.0
726.4
1272.0
2235.4
3441.8
56.26
853.0
18.20
3 20
1003.
9
20.10
.34
21.99
3.48
23.98
3.79
1281.
9
4.20
1.67
5.20
1.62
40.8
6.18
1.66
43.7
7.19
1.86
52.6
8.32
7.19
85.0
9.31
2.34
150.0
10.39
2.65
218:3
12.37
2.84
1335.
1
334.5
h1
Connection Details
h2
hi
c
mm
mm
mm
mm
mm
g1
(min)
mm
Maximum
size of
flange Rivet
mm
Designatio
n
429
3.7
5.0
1.5
91.5
130.4
9.80
23.50
3.00
30
45
ISJB 150
54.8
3.9
5.0
1.5
91.5
155.0
10.0
23.40
3.10
30
45
ISJB 175
78.1
5.8
5.0
15
91.5
1755
10.25
28.38
3.20
30
45
ISJB 200
116.3
10.1
6.5
1.5
91.5
201.1
11.95
38.15
3.35
40
45
12
ISJB225
19.4
4.0
6.5
2.0
91.5
51.7
11 65
2315
3.35
30
ISJB75
33.6
5.1
7.0
3.0
91.5
73.0
13.50
23 00
3.50
30
50
ISJB 100
65.1
11.6
8.0
3.0
91.5
954
14.80
35 30
3 70
35
50
12
ISJB 115
91.8
13.8
9.5
3.0
91.5
1169
16.55
37.60
3.90
40
50
12
ISJB 150
125.3
17.7
9.5
3.0
91.5
141.6
16.70
42.45
4 05
50
50
12
ISJB 175
169.7
23.1
9.5
3.0
91.5
1657
17.15
47.30
4.20
55
50
16
ISJB 200
222.4
22.5
12.0
6.0
98.0
180.3
22.35
47.10
4.45
55
55
16
ISJB225
297.4
30.9
13.0
6.5
98.0
202.6
23.70
59 45
4.55
65
60
22
ISJB 250
392.4
41.0
14.0
7.0
98.0
223.7
25.65
66.80
4.70
80
60
22
ISJB275
15.0
75
98.0
245.1
27.45
71.65
4.85
90
60
22
ISJB300
488.9
50.2
187
607.7
61.9
16.0
80
98.0
266.5
29.25
79.00
5.00
100
65
25
ISJB325
751.9
76.6
16.0
8.0
98.0
288.3
30.85
78.80
5.20
100
65
25
ISJB 350
965.3
86.8
16.0.
8.0
3362
31
78.50
5.50
100
65
25
ISJB400
100.4
16.0
8.0
98.0
98.0
384.0
33.00
80.70
5.80
100
70
28
ISJB 450
430.2
43.90
85.40
6.10
100
70
32
ISJB 500
476.1
36.95
90.05
6.45
100
70
32
ISJB 550
520.0
39.90
99.75
6.75
100
75
12
ISJB 600
65.0
17.50
35.50
3.50
35
55
12
ISJB 100
89.2
17.90
35.30
3.70
35
55
12
ISJB 125
113.9
18.05
37.60
3.90
40
55
12
ISJB 150
134.5
20.25
42.25
4.25
50
55
16
ISJB 175
152.7
23.65
47.15
4.35
55
60
20
ISJB 200
173.3
25.85
51.75
4.75
60
60
22
ISJB 225
1223.8
1543.2
1933.2
2428.9
51.5
71.8
96.9
145.4
223.5
118.2
140.5
173.5
10.9
11.7
13.1
18.9
30.0
17.0
18.0
20.0
9.0
9.0
9.0
10.0
11.0
8.5
9.0
10.0
4.5
98.0
98.0
98.0
98.0
98.0
4.5
4.5
5.0
5.5
98.0
98.0
98.0
98.0
305.9
39.7
12.0
6.0
410.5
53.5
13.0
6.5
98.0
194.1
27.95
59.05
4.95
65
65
22
ISJB 250
573.6
64.8
14.0
98.0
241.5
29.25
66.25
5.25
80
65
22
ISJB 300
778.9
76.8
14.0
7.0
7.0
98.0
288.0
31.00
65.95
5.55
80
65
22
ISJB 350
98.0
334.4
32.08
65.55
5.95
80
70
22
ISJB 400
7.0
1022.9
88.9
14.0
1350.7
111.2
15.0
7.5
98.0
379.2
35.40
70.30
6.20
90
70
22
ISJB 450
1808.7
152.2
17.0
8.5
98.0
242.1
37.95
84.90
6.20
100
70
28
ISJB 500
h1
Connection Details
h2
h1
c
g1
(min)
mm
Maximum
size of
flange Rivet
Designatio
n
75
32
ISMB 550
193.0
18.0
9.0
3000.4
252.5
20.0
10.0
111.9
19.0
8.0
4.0
172.5
30.2
8.0
4.0
262.5
47.0
9.0
348.5
59.8
9.0
4.5
4.5
475.4
85.7
10.0
654.8
99.0
11.0
5.0
5.5
887.0
117.6
12.5
6.0
1171.3
138.8
13.0
6.5
1558.1
170.7
14.0
7.0
2091.0
239.0
15.0
7.5
2723.9
299.2
16.0
3540.0
376.2
17.0
3854.2
194.1
423.9
57.6
98
98
96
96
96
96
96
96
96
96
96
96
8.0
96
8.5
96
mm
mm
mm
mm
mm
467.5
41.25
89.40
7.10
100
509.7
45.15
99.00
00
25,32
ISMB 600
116.6
16.70
47.30
7.50 140,10
0
4.20
55
55
16
ISWB 150
139.5
17.75
59.60
4.40
65
55
22
ISWB 175
158.8
20.60
66.95
4.55
00
55
22
ISWB 200
181.4
21.80
71.80
4.70
00
55
22
ISWB 225
203.8
23.10
00.65
4.85 140,10
0
5.20 140,10
0
5.50 140,10
0
140,10
5.80
0
140,10
6.10
0
00
22,32
ISWB 250
250.1
24.95
00.30
295.5
27.25
96.00
340.5
29.75
95.70
384.0
33.00
95.40
431.0
473.4
514.2
18.0
9.0
96
507.9
8.0
4.0
94
112.0
188
72.30
4.30
140
140
140
140
00
00
00
65
70
22,32
22,32
22,32
22,32
ISWB 300
ISWB 350
ISWB 400
ISWB 450
70
32
ISWB 500
75
32
ISWB 550
00
32
ISWB 600
00
32
ISWB 600
55
22
ISHB 150
205.3
00.2
8.0
4.0
94
218.1
63.2
8.0
4.0
360.8
96.7
9.0
4.5
372.2
98.6
9.0
4.5
469.3
120.3
10.0
5.0
487.0
123.0
618.9
156.9
10.0
5.0
94
94
94
94
94
10.0
5.0
94
10.0
5.0
94
638.7
159.7
836.3
175.5
11.0
5.5
863.3
178.4
11.0
5.5
1094.8
196.1
12.0
6.0
1131.6
199.4
12.0
6.0
1404.2
218.3
14.0
7.0
4441.2
221.3
14.0
1742.7
238.8
15.0
1792.3
242.1
15.0
94
94
94
94
94
7.0
94
7.5
94
7.5
94
112.0
19.0
70.80
5.70
00
55
22
ISHB 150
112.0
19.0
69.10 7.40
00
55
22
ISHB 150
158.4
20.8
55
22,32
ISHB 200
55
22,32
ISHB 200
180.5
55
28
ISHB 225
180.5
140
55
32
ISHB 225
203.5
140
00
32
ISHB 250
203.5
140
00
32
ISBH 250
249.8
140
00
249.8
140
00
296.0
296.0
340.1
340.1
386.2
386.2
158.4
140
140
140
140
140
140
32
00
00
ISBH 300
32
ISBH 300
32
ISBH 350
32
ISBH350
65
32
65
32
65
32
65
32
ISBH 400
ISBH 400
ISBH 450
ISBH 450
Weight
per
Perimete
r round
Sectional
square
Area
round
Perimete
r Square
Round
mm
5.0
5.5
6.0
7.0
8.0
9.0
10
11
12
14
16
18
20
22
25
28
32
36
40
Sq.Kg
0.20
0.24
0.28
0.38
0.50
0.64
0.78
0.95
1.13
1.54
2.01
2.54
3.14
3.80
4.91
6.15
8.04
10.17
12.56
Kg
0.15
0.19
0.22
0.30
0.39
0.50
0.62
0.75
0.89
1.21
1.58
2.00
2.47
2.94
3.95
4.82
6.31
7.99
9.86
cm2
0.25
0.30
0.36
0.49
0.64
0.81
1.00
1.21
1.44
1.96
2.56
3.24
4.00
4.84
6.25
7.84
10.24
12.96
16.00
cm2
0.20
0.24
0.28
0.38
0.50
0.64
0.79
0.95
1.13
1.54
2.01
2.54
3.14
3.80
4.91
6.16
8.04
10.18
12.57
cm2
2.0
2.2
2.4
2.8
3.2
3.6
4.0
4.4
4.8
5.6
6.4
7.2
8.0
8.0
10.0
12.2
12.8
14.4
16.0
Sq.cm2
1.57
1.77
1.88
2.20
2.51
2.83
3.14
34.46
3.77
4.40
5.03
5.65
6.28
6.91
7.85
8.80
10.05
11.31
12.57
189
45
50
56
63
71
80
15.90
19.62
24.62
31.16
39.47
50.24
12.49
15.41
19.34
24.47
31.08
39.36
20.25
25.00
31.36
39.69
50.41
64.00
15.9
19.64
24.63
31.17
39.49
50.27
18.0
20.0
22.4
25.2
28.4
32.0
Area
(sq.m)
W/t/Kg
(Metre)
Perimete
r
(cm)
6
8
10
12
14
16
18
20
22
25
28
32
36
40
0.283
0.503
0.785
1.131
1.539
2.011
2.545
3.142
3.801
4.909
6.157
8.042
10.179
12.566
0.222
0.395
0.617
0.888
1.208
1.578
2.000
3.466
2.98
3.854
4.83
6.313
7.99
9.864
1.89
2.51
3.14
3.77
4.4
5.03
5.65
6.28
6.91
7.85
8.8
10.05
11.31
12.57
Length
(per
tonne)
Metre
5410
2532
1631
1125
829
633
500
405
336
260
207
159
125
101
Materials
Weight in Kgs.
Per Remarks
14.14
15.71
17.59
19.78
22.31
25.13
1.
Earth alluvial
16CD
Cu.m
2.
Earth dry
1410-1850
Cu.m
3.
Earth Moist
1600-2000Cu.m
Cu.m
4.
2080
Cu.m
5.
1760
Cu.m
6.
1440
Cu.m
7.
1040
Cu.m
8.
Gravel Loose
1600
Cu.m
9.
Gravel Rammed
1920-2160
Cu.m
1460
Cu.m
10.
11.
1540-1600
Cu.m
12.
1840
Cu.m
13.
1769-2000
Cu.m
14.
Peat Dry
580-640
Cu.m
15.
Sand Compact
800
Cu.m
16.
360
Cu.m
II
BUILDING STONES
1.
Basalt
2600
Cu.m
2.
Gneiss
2400-2690
Cu.m
3.
Graphite
2690-2800
Cu.m
4.
Laterite
2080-2400
Cu.m
5.
Lime Stone
2400-2640
Cu.m
6.
Marble
7220
Cu.m
7.
Pumice
800-1220
Cu.m
8.
Quartzite
2640
Cu.m
9.
Sand stone
2240-2400
Cu.m
10.
Slate
2800
Cu.m
11.
Chalk
1600-1920
Cu.m
191
III BITUMINOUS
1.
Bituminous macadam
2282
Cu.m
2283
Cu.m
1600-1920
Cu.m
IV BRICKS
1.
2.
Engineering bricks
2160
Cu.m
3.
Bricks ballast
1200
Cu.m
4.
1000
Cu.m
1400
Cu.m
1050-1280
Cu.m
260
Cu.m
CEMENT
1.
2.
Rapid hardening
Aerated
2.
Brick aggregate
1760-1260
Cu.m
3.
Stone ballast
2240-2720
Cu.m
With 1% Steel
2310-2470
Cu.m
2.
With 2% Steel
2370-5530
Cu.m
3.
With 3% Steel
2560-2720
Cu.m
4.
1920
Cu.m
2080
Cu.m
1600-1840
Cu.m
1920
Cu.m
VIII MORTARS
1.
Cement
2.
Lime
IX MASONRY
1.
bricks
2.
2400
Cu.m
3.
2000
Cu.m
4.
2240-2640
Cu.m
Sq. inch
Sq. foot
Sq. yard
acre
Sq. mile
Sq. cm
Sq. m
Sq. m
acre
hectare
Bigah
2.54 centimetre
30.48 centimetre
91.44 centimetres 0.944 metre
2011.68 centimetres
66 feet
5.280 feet, 80 chains, 1760 yards,
6,076.115 feet/hour
1 metre
1 centimetre
1 metre
1 metre
1 kilometre
0.00064516 Sq.m
929.03 Sq.cm 0.0929 Sq.m
0.83613 Sq.m
0.40468 hectare
259 hectare - 2.58999 Sq. Km.
0.155 Sq. inch
10.7639 Sq. ft.
1.196 Sq.yd.
4046.86 Sq.mts.
2.471 acres - 10.000 Sq.m
(132 x 132)Sq.ft
193
1 Sq. Km.
VOLUME
1 cu.in
1 cu. ft
1 cu. yd.
1 gallon
cu.in
1 cu.m
1 litre
1 cu.decimetre
1 cu.m
1 cu.m
WEIGHT
1
1
1
1
1
1
1
1
1
100 Hectare
-
16.387 cu centimeters
0.0283168 cu.m = 28.317 litres
0.76455 cu.m = 28.317 litres
3.785 litres = 0.1336 cu.ft. = 231.00
61023.74 cu.in
0.0353 cu.ft.
61.024 cu.inch
35.3148 cu.ft
1.30795 cu.yrd
grain
penny weight
dram
ounce
pound
milligram
gram
kg
tonne
0.0648 gm
1.5552 gm
1.772 gm
28.350 gm, 437.5 grains
453.59 gm, 7000 grains 0.45359 Kg
0.015 grain
0.0022046 lbs 15.432 grain
100 Kg, 220, 46 lbs 1968 cwt
0.9842 tons, 2,2046 lbs
To convert
Into
Multiply by
1.
Metres
Feet
3.28084
0.3048
2.
Kilometre
Mile
0.6213
1.6093444
3.
Square Kilometre
Sq. miles
0.386101
2.58999
4.
Square metres
Sq. feet
10.7639
0.92903
5.
Cubic metres
Cu. feet
35.3147
0.028317
6.
Cubic metres
Gallon (IMP)
219.969
0.00464509
7.
Litre
Gallon
0.219976
4.5609
8.
Kilograms
Pounds
2.20462
0.453924
194
Maunds
(Avoir)
2.67923
0.373242
10.
Hundred
weight
1.96840
0.50802
11.
Tons (British)
0.9842
1.01605
12.
0.62137
1.60934
13.
0.91134
1.09728
14.
Pound per
cu.ft.
0.0624
16.018
15.
Pound per
cu.ft.
62.426
0.0160189
16.
0.09143
10.937
9.
(ha)
1
1
1
1
1
sq.
sq.
sq.
sq.
sq.
hectometer
decameter
m (m2)
decimeter (dm2)
cm (cm2)
=
=
=
=
=
CONVERSION FACTORS
1 Sq. inch
1 Sq. foot
=
=
1 Sq. yard =
=
=
6.45 sq. cm
=
645.16 sq.
929.03 sq. cms
0.093 sq. m
1 sq. mm =
mm 1 sq. cm
1 sq. dm
=
1 sq.m
or
1 centare
1 sq. dm
1 hectare =
CUBIC MEASURES
BRITISH UNITS
=
0.01196 Sq. yards
2.471 acres
METRIC UNITS
195
1728 Cu.ins=
Cu.cm
27 Cu.ft.
=
Cu.dm
1 Cu.in
1 Cu.m
=
Cu.ins
1 Cu.ft.
61.02Cu.ins
=
=
1 cu.ft
1000 Cu.mm
1 cu.yd
1000 Cu.mm`
16387 Cu.mm
1000 Cu.dm
1 cu.cm (cm3)
16.387 Cu.cm
=
1 cu.mts
Cm 4x0.024
in.4
in. 4x41.623
Cm.4
Cm 3x0.061
in.3
in. 3x16.387
Cm.3
Cm 2x0.155
in.2
in. 2x6.45
Cm.2
in x2.54
Cm
Cm x0.3937 =
in
0.061
1 cu.dm (dm3)
28,317 Cu.cm
2831.7 Cu.dm
0.028 Cu.m
=
0.035 Cu.ft.
35.315 Cu.ft.
1.308 Cu.yds.
=
=
ft. 4x0.0086
m.4
m. 4x115.862 =
ft.4
ft. 3x0.0283
m.3
m.3 x35.3147 =
ft.3
CONVERSION FACTORS
1/25 inch
1 inch
1 foot
1 yard
1 rod
1 furlong
1 mile
= 1mm
1mm
= 0.03937 inch
= 25.4 mm
1 cm
= 0.3937 or 2/5 inch
= 2.54 cm (exact)
1 dm
= 3.937 inches
= 30.48 cms
= 0.328 feet
= 0.3048 metres
1 metre
= 39.37 inches
= 0.9144 metres
= 3.281 ft.
= 91.44 cms
= 1.094 yds.
= 5.029 mts.
1 dkm
= 32.81 ft.
= 0.201 Km.
= 10.94 yds.
= 201.168 mts.
1 Hm
= 328 ft., 1 inch
= 1.609 Km.
1 km
= 32.80 ft. ,10 inch
= 1609 metres.
= 4.97 furlongs,1093.6 yards
= 5/8 or 0.621 mile
Inch
mm
inch
/16
1.58
7
9
/16
/8
3.17
5
5
/8
/16
4.76
2
11
/16
/4
6.35
0
/16
7.93
7
13
/16
/8
9.52
5
7
/8
/16
11.11
2
12.70
15
/16
mm
14.2
9
15.8
7
17.4
6
19.0
5
20.6
4
22.2
2
23.81
inch
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0.08
0.09
0.10
mm
0.25
4
0.50
8
0.76
2
1.01
6
1.27
1.52
4
1.778
2.03
2
2.28
6
2.540
197
25.40