Vous êtes sur la page 1sur 33

TME/B1

Part B - Technical Specifications for Fire Hydrant System


1

General

1.1

The Fire Hydrant System shall comprise of both pillar and underground
hydrant, pipe works complete with sluice valves, fittings, supports, gauges,
valves, chambers, chamber covers, collapsible identifiers and accessories.

1.2

All equipment and material shall be acceptable to the Fire Safety And Shelter
Department (FSSD), Airport Emergency Section (AES) and/or to PUB and
shall meet the requirements stipulated in the Schedule of Equipment.

1.3

The fire hydrant system shall be executed by a Licensed Plumber and by a


BCA registered company under the Fire Protection trade.

1.4

All manhole/ chamber covers are to be F900 class to withstand aircraft


loading.

1.5

The Contractor shall engage the service of Licensed Water Service Worker
and QP and liase with RSAF/ DSTA/ AES for the design, installation,
supervision, relocation, testing & commissioning and handing over of the
completed system, including all statutory submission e.g. FSSD, DSTA, CAG
pertaining to design, consultation, submission, testing & commissioning,
inspection, approval and issuance of fire safety certificate of the relocated fire
hydrant system.

1.6

The Contractor is deemed to have made all necessary allowances in the


Contract Sum for compliance with the requirements of this clause. No claims
whatsoever for any additional cost or time in respect thereof or on grounds of
lack of knowledge of any of the aforesaid shall be entertained.

1.7

The pipes and fittings shall be internally lined such that they are suitable to
convey NeWater as a source of water supply for the hydrant system. ( Refer to
PUBs TECHNICAL SPECIFICATION FOR SPECIAL INTERNAL LINING OF
PIPES AND PIPE FITTINGS)

EQUIPMENT AND MATERIALS

2.1

Fire Hydrants
Fire Hydrants shall comply with the requirements of Latest SS 575.

2.2

Piping and Fittings


Only pipes and fittings under the Product Listing Scheme, TUV SUD PSB
approved labelled shall be used for the fire hydrant installations. On delivery of
each batch of pipes and fittings to the site, Contractor shall hand over to the

Particular Specifications
Mechanical and Electrical Works

TME/B2

Superintending Officer (SO) a copy of the documents showing its origin, proof of
manufacture and approval from the Product Listing Scheme for its use.
a)

Markings
All pipes and fittings shall be legibly marked with the following:-

b)

i)

Manufacturer's name and trademark

ii)

Reference number of the conformed standard

iii)

Quality class reference

iv)

Nominal size and the mark of PUB

Pipe Sizes and Materials


Pipe sizes mentioned throughout the specifications are nominal sizes
and those pipe sizes shown on the drawings or indicated in the contract
documents are the minimum acceptable sizes.
Sizes for ductile iron pipes with approved lining indicate Nominal Bore
Diameter (NB).
All pipe materials for the fire hydrant installation shall be ductile iron pipes
conforming to BS EN598. They shall be of Class K9 with PUB approved
internal cement lining. The pipes and fittings shall be internally lined such
that they are suitable to convey NeWater as a source of water supply for
the hydrant system. (Refer to Appendix PUBs TECHNICAL
SPECIFICATION FOR SPECIAL INTERNAL LINING OF PIPES AND
PIPE FITTINGS)
Joints for the pipes shall be spigot and socket or flanged type.
i)

Pipe Fittings

Ductile iron fittings shall conform to BS EN598. Tee, Wye and


Cross Fittings shall be Class K14. All other fittings shall be
Class K12.All fittings must be from the same pipe
manufacturer.

Flanges for pipe fittings shall be type NP16. Flexible joints


shall be the Bolted Gland Type or approved equivalent. For
coupling, Double Socket Collars of the Bolted Gland Type shall
be used. Lead Joint Socket Ends are unacceptable. All fittings,
except collars, shall be cement lined.

Particular Specifications
Mechanical and Electrical Works

TME/B3

ii)

Bolts and Nuts


Bolts and Nuts for use in jointing shall be high strength stainless
steel SS 316.

iii)

Rubber Rings
Contractor shall state the type and quality of rubber rings used in
the flexible joints of pipes and fittings. They shall be Class C
rubber rings of BS 2494: Rubber Rings for Gas Mains, Water
Mains and Sewers. All associated rubber rings for spigot and
socket fittings must be from same pipe manufacturer.

iv)

Protective Coatings and Linings


Coatings shall be executed in accordance with BS 4164, for use in
a tropical country. All materials shall be new, without rust. The
interior of pipes and fittings shall be cement-lined in accordance
with current regulations and requirements and by-laws of the
Water Department, Public Utilities Board.

v)

vi)

Valves

All valves shall be under the Product Listing Scheme, TUV


SUD PSB approved manufacture and shall be installed in
positions where they are easily accessible for maintenance
and operating purposes.

All valves shall be constructed in accordance with the


appropriate standards.

For working pressures up to and including 1000 kPa, all valves


larger than 50mm nominal bore shall be flanged. Valves
operating at this pressure but below 50mm nominal bore shall
be screwed. All valves shall be flanged where the working
pressure is above 1000kPa.

All valves must have opening direction indicator plate.

Construction

All valves shall have bronze valve faces and seats and
manganese bronze spindle with instil screws.

Valves installed in ferrous piping up to and including 75mm


nominal bore shall be of bronze bodies.

Particular Specifications
Mechanical and Electrical Works

TME/B4

vii)

Valves installed in ferrous piping above 75mm nominal bore


shall have cast iron bodies.

Stop Valve
Stop valve shall be provided on pipes smaller than 75mm
diameter and shall conform to SS 75: Part 2.

viii)

ix)

x)

Sluice Valve

Sluice valves shall be provided on pipes 75mm diameter and


over and shall conform to BS 5163: Double Flanged Cast Iron
Wedge Gate Valves for Waterworks purposes.

Sluice valves shall be rated at 16 bars.

They shall be provided with valve caps secured by socketheaded set-screws. The direction of closing shall be clockwise.

All valves shall be capable of being opened or closed by one


man with a maximum required torque of 40 Newton metre.

Air Relief Valves

Single Small Orifice Air Relief Valves of 25mm diameter, shall


be tested to 250m head of water and shall be of a type
approved by the Water Department of the Public Utilities
Board. They shall be supplied complete with isolation valves.
All air relief valves must be install within a valve pit/chamber.
The specification for the valve pit/chamber shall comply with
F900 class to withstand aircraft loading.

Both Single Large Orifice and Double Orifice Air Relief Valves
shall be of the aerodynamic type designed to overcome the
problems of premature closing due to a high discharge
velocity. They shall be tested to 250m head of water and be
supplied complete with isolating sluice valves of pressure
rating PN16 having mitre gearing and end flanges of type
NP16. They shall be of a type approved by the Water
Department of the Public Utilities Board.

Surface Boxes and Covers

All surface boxes and covers shall comply with the


requirements of EN124.

Particular Specifications
Mechanical and Electrical Works

TME/B5

Minimum
Class

Type of Area

Loading

Subjected to Air
F900
Craft Loading

Remarks
Covers shall be provided with
both lifting key recesses (open
type) and prising bar recesses

The Contractor shall allow for at least one (1) sample of the
product be taken from site by the Superintending Officer and
sent to the approved testing laboratory/institute for compliance
test.

Fire Hydrant Mains


Surface boxes for sluice valves (above 150mm dia) of the
hydrant water mains shall be cast iron, with 300mm x 300mm
clear opening, 100mm deep, with cover chained to box, and
the letters 'SVP' and year of manufacture legible casted on the
top of the cover.
For sluice valves of size 150mm and below, the surface boxes
shall be cast iron, with 300mm x 150mm clear opening,
100mm deep, with cover chained to box, and with the letter
legibly casted on the top of the cover.

Air Valve Boxes and Covers

Surface boxes for single small orifice air relief valves shall be
cast iron, with 320mm x 320mm clear opening; 100mm deep,
perforated to facilitate air release and provide ventilation. The
letters 'AV' shall be legible casted on the top of the chained
cover.
Surface boxes for large or double orifice air relief valves shall
be the same as for single air relief valves, except that the clear
opening shall be at least 600mm x 450mm.

Surface Boxes and Covers for Washouts

The surface boxes for washouts shall be cast iron, with


750mm x 650mm clear opening, 100mm deep, and with the
letters 'WO' and the year of manufacture legibly casted on the
top of the cover.
xi)

Valve Keys, Lifting Keys and Prising Bars

The Contractor shall provide 10 nos. T-bar valve key operators


for each type of valve. The key operators shall be designed

Particular Specifications
Mechanical and Electrical Works

TME/B6

with ample strength to open and close valves against the full
head of the pipelines (10 bars) without distortion or
overstressing. They shall be of length 1.80 metres.

Pipeworks

3.1

General

3.2

The Contractor shall also provide 10 nos. lifting keys and 10


nos. prising bars of ample strength for each type of surface
boxes and covers provided.

The Contractor shall provide extra 5% of each type of covers


each for the various surface boxes provided.

a)

The Contractor shall exercise all care and ensure that pipes, fittings,
valves or specials, are not damaged during loading, unloading or
transporting, or while stored at site. The Contractor shall make good all
damages caused, at his expense. He shall allow for the cost of
loading, transporting and unloading of these items in his Contract Sum.

b)

Where there is no space alongside the proposed pipe trench for


placing the pipes prior to laying, the pipes shall be unloaded at a
temporary storage ground approved by the SO. The pipes shall be
transported subsequently for laying from the temporary storage ground
to the site of laying.

c)

The pipes at the storage ground shall be stacked not higher than 2m
such that they do not rest on their sockets. All stacks shall be set up
level on a hardwood or similar base. Each size of pipe shall be
separately stacked.

d)

The Contractor shall allow for the cost of stacking and shifting the pipes
in his Contract Sum for pipe laying.

Handling of Pipes, Fittings, etc


a)

Contractor shall handle all pipes with care and prevent breakage or
damage to the internal lining, external coating or wrapping and shall
ensure that the inside of the pipes, particularly at the ends are clean
before they are lowered into the trench. Where the lining, coating or
wrapping has been damaged by handling, the Contractor shall make
good the lining, coating or wrapping as directed by the S.O. The

Particular Specifications
Mechanical and Electrical Works

TME/B7

material used in the repair of damaged coatings must be compatible


with the coating material.

3.3

b)

All handling and hauling equipment shall be approved by the SO. Bare
cables, chains, hooks, wire ropes, metal bars, and narrow skids, which
may damage the pipe coating or wrapping, shall not be used.

c)

Scrupulous care shall be taken by the Contractor to ensure that all


pipes and fittings are cleaned internally when laid, and that no foreign
material is permitted to enter them after laying. A temporary pipe stop
shall be placed to cover each open end of pipe whenever work is
stopped.

d)

Each pipe shall be carefully lowered onto its prepared bed with slings
and tackle. If the prepared bed is damaged or stones are dislodged
into the trench, the pipe shall be raised, the bed made good and stones
removed before the pipe is laid. Any fractured pipes shall be replaced
at the Contractor's expense.

Cover to pipes
All pipes shall be laid to the depth shown on the Drawings or as directed by
the S.O. The pipes shall be laid with a minimum earth cover of 1000mm
outside paved areas and a minimum cover of 1000mm under paved areas.

3.4

Pipes laid to gradient and line set out


a)

When in the trench, the pipes shall be laid to proper gradient and true
to line, as shown on the Drawings or as directed by the SO. The
Contractor shall set up the necessary pegs sight rails, for pipe laying
and checking purposes.

b)

The pipes shall be laid in straight lines or regular curves to avoid any
unnecessary resistance to flow. All pipes must be laid on compacted
bedding. Inspection shall be carried out to ensure the compacted
bedding has compacted to 98%.

c)

The position of the pipes when laid shall not deviate from that shown
on the Drawings by 1.5 metres.

d)

The pipe work shall be laid not less than 1 metre below finished ground
level. The pipes shall be joined by flanges conforming to BS 4504
complete with rubber jointing washer unless otherwise specified in the
drawing.

e)

After joining the pipes, and on completion of testing, the granular


bedding material shall be brought up equally on both sides of the pipes
to the level of the centre of the pipeline and then the bedding or backfill
material shall be brought up to a level of 300mm, above the top of the

Particular Specifications
Mechanical and Electrical Works

TME/B8

pipe barrel in layers, each not more than 100mm thickness, and carefully
compacted by hand for the full width of the trench.
f)

3.5

Concrete thrust blocks shall be installed at all pipe offsets, under valves
and where required.

Jointing of Pipes
Procedure for jointing will vary according to the type of joint being used. Basic
requirements for all types are: a)

Cleanliness of all parts;

b)

Correct location of components;

c)

Centralisation of spigot within socket; and

d)

Strict Compliance with Manufacturer's jointing instructions.

e)

Flanged Joints

f)

i)

Where flanged joints are to be made, the Contractor shall clean all
flanged surfaces, cut insert rubber sheeting and make the joint as
specified or directed by the SO.

ii)

In flanged joints, the rubber jointing rings shall be properly fixed


and the bolts uniformly tightened.

iii)

The flanged joints shall be painted with two (2) sets of bitumastic
paint.
The Contractor shall supply all necessary identifying items, paint,
bands, stencils, etc.

Mechanical and Bolted Gland Joints


When making Bolted Gland Joints, the spigot shall penetrate into the
sockets for the required depth, the jointing rings shall be properly fixed
and the joints tightened, all in accordance with the manufacturer's
instructions, to make thoroughly sound and watertight joints.

g)

Slip-on Joints
Slip-on joints shall be made strictly in accordance with the manufacturer's
instructions, to achieve thoroughly sound and watertight joints.

3.6

Air Valves, Hydrants, etc.


a)

The Contractor shall install air valves, washout valves, sluice valves,
fire hydrants, bends, etc, as shown in the Drawings, or as directed by

Particular Specifications
Mechanical and Electrical Works

TME/B9

the SO. The contractor shall do all necessary excavation; make joints,
have the joints coated with bitumastic paint (2 coats) as shown on the
Drawings or as directed by the SO. A tapping saddle shall be used for
the installation of small orifice air relief valves.

3.7

b)

After installation, the external surface of all sluice valves, air-valves,


hydrant pipes and underground fire hydrants shall be cleaned, wirebrushed, primed with approved primer, and painted with two coats of
approved bitumastic paint. All pipework, valves and fittings shall be
painted and provided with identification markings and labels. Fire
hydrants shall be set plumb. The colour of the paint and labelling shall
be subjected to the discretion of the SO

c)

The Contractor shall supply all necessary identifying items, paint, bands,
stencils, etc.

Cutting of Pipes
Cutting of pipes shall be done by means of a patent cutter of a type approved
by the SO. The cut shall be true, straight and square to the axis of the pipe.
Any burrs left after cutting shall be trimmed off by filling or grinding.

3.8

Preparation of Spigots on Site


All spigots for jointing into sockets must be chamfered. Where spigots require
preparation on site, the outside of the spigot shall be filed to produce an angle
of approximately 30 degrees to facilitate the entry of the spigot past the
gasket.

3.9

Thrust Blocks and Anchors


a)

Pipe lines shall be securely anchored at dead ends, tees, bends,


tapers and valves to resist thrust arising from internal pressure. Thrust
blocks shall be to the dimensions specified or as indicated by the SO.
Brackets for securing of pipes and fittings to thrust blocks shall be set
in concrete and fixed by the Contractor as directed.

b)

All concrete shall be of C30 / 37 concrete mix unless otherwise directed


by the SO.

c)

All design and calculation of thrust blocks and anchors shall be


submitted and endorsed by the Contractors Professional Engineer.

d)

Steeply inclined pipelines shall be secured by in accordance with the


following tabulation:

Particular Specifications
Mechanical and Electrical Works

TME/B10

Table 1
Gradient

Spacing (m)

1 in 2 and steeper

5.5

Below 1 in 2 to 1 in 4

11.0

Below 1 in 4 to 2 in 5

16.5

Below 1 in 5 to 1 in 6

22.0

Flatter than 1 in 6

Not required

Thrust blocks shall be cast in place so that they will bear against an area of
undisturbed soil in the trench wall with the pipe joint accessible for inspection
and repair. Minimum area of Bearing Face of Concrete Thrust Blocks Against
Horizontal Thrusts is given in Table 2. Where thrust blocks occur at location of
soft and unstable soil, the soft soil shall be replaced with more stable
materials.
Table 2
Ductile Iron (Area in Sq Metre)
Nominal
1/4 Bend
Size
100
0.30

0.20

Tees, Plugs,
Caps, Hydrants
0.30

150

0.65

0.40

0.50

200

1.100

0.60

0.75

250

1.60

0.85

1.12

300

2.30

1.21

1.60

350

2.90

1.68

2.14

400

3.91

2.15

2.80

450

4.93

2.70

3.44

500

6.04

3.25

4.28

550

8.55

4.65

6.14

1/8 Bend

Notes: Basis for Table 2:


i)
ii)
iii)
iv)

Soil Resistance = 9800 kgf/m2 (2,000 lb/ft2)


Water Pressure = 17 bars (250 psi)
Weight of Cover and Pipe not taken into account
Correction factors for other soils: Soft clay ..............
4

Particular Specifications
Mechanical and Electrical Works

TME/B11

Sand ....................
Sand and Gravel ........
Shale ...................
3.10

3.11

2
1.33
0.4

Encased Pipes
a)

Where it is deemed necessary for the pipes to be laid, strapped and


encased with concrete, especially under areas subject to aircraft
vehicular traffic, or areas most likely to be subjected to settlement
caused by excavation works for proposed developments in and around
the vicinity, the Contractor is advised to clarify with the SO. the actual
extent, material, size and method of construction of the encased pipes.
All concrete for encased pipe shall be of C20/ 25 mix.

b)

The Contractor shall ensure that the trench bed is well compacted and
inspected by the SO. before commencing to concrete all pipe
encasement work.

Identification of Mains
Where the potable water mains, fire hydrant mains, and industrial water mains
run, they shall be identified by means of PVC tape, at least 150mm wide, laid
directly over them at a height not greater than 300mm from the crown of the
mains. The colours of the tapes used for the various mains shall be light blue,
signal red and black, respectively.

3.12

Chambers for Valves, etc.


The Contractor shall ensure that the bedding is mechanically well compacted
before seating the chamber firmly on it. Selected fill shall be well rammed
around the valve up to the top flange.

Fire Hydrant Post

4.1

The Contractor shall supply and install PVC spring loaded frangible posts or
frangible posts (890mm high and 60mm diameter) on to the concrete pits of
the underground fire hydrants and the works included the drilling, tightening of
stainless steel anchoring bolts and etc.

4.2

The posts must be wrap up with 3M red reflective diamond sticker and comply
with ICAO Document 9157 Part 6, 3.3 (Frangibility requirement) that means.
a)

The posts and its supports should be frangible in order to ensure that
they will break, distort or yield in the event that they are accidentally
impacted by an aircraft. The design materials selected should preclude
any tendency for the components, including the electrical conductors,
etc, to wrap around the colliding aircraft or any part of it.

Particular Specifications
Mechanical and Electrical Works

TME/B12

b)

The posts should be designed to withstand the static and operation


wind or jet blast loads with suitable factor of safety but should break,
distort or yield readily when subjected to the sudden collision forces of
3000 kg aircraft airborne and travelling at 140 km/h (75 kt) or moving
on the ground at 50 km/h (27 kt).

c)

The frangibility of the design should be proven either by means of fullscale tests, computer evaluation or by calculation based on comparison
with similar already approved structures possibly supported by
additional component tests.

Testing And Commissioning

5.1

General

5.2

a)

The whole works shall be carried out to the entire satisfaction of the
Superintending Officer The Contractor shall submit detailed checklist
and test procedures to the Superintending Officer for approval. Tests
shall be executed by the Contractor and witnessed by the
Superintending Officer and test results shall be recorded in writing and
certified by the Contractor before submission for approval by the SO

b)

The Superintending Officer shall be at liberty to order such tests to be


carried out to verify the reliability and performance of the system and
check compliance with specifications herein provided. The Contractor
shall provide all equipment and things necessary and bear all costs for
executing the necessary tests except where specified herein.

c)

All defects and deficiencies in performance, reliability, safety,


efficiency, appearance of finish shall be rectified and retested by the
Contractor to the entire satisfaction of the SO. before acceptance.

d)

Upon the completion of all the work, the Contractor shall then
commission the system installed in the presence of the SO. The
system shall be in complete and perfect operational condition by then.

e)

All tests shall be carried out in the presence and to the satisfaction of
the SO.

f)

After testing, test records shall be submitted to the SO. in a format


approved by the SO.

g)

The entire fire hydrant installation shall be tested for its proper
installation and reliable intended function during commissioning to the
satisfaction of the SO.

Hydrostatic and Leakage Testing

Particular Specifications
Mechanical and Electrical Works

TME/B13

a)

Testing and commissioning shall not begin until the system has been
completed and is in full working order. The Contractor shall put all
systems and equipment into full operation after verifying that all drain
connections and vents are clear. The pipe work shall be flushed clean
prior to testing. All pipe work and valves shall be pressure tested and
leakage tested to the satisfaction of the SO.

b)

The testing and commissioning of the system shall include all items of
equipment as specified individually. Equipment susceptible to damage
under the test pressure shall be isolated and tested commissioned
separately.

c)

The tests shall be carried out progressively on completion of every 200


metres or less of pipelines. All joints shall be left exposed for inspection
during testing. Pipes with cement lining shall be allowed to stand full of
water for at least 24 hours before proceeding with the test.

d)

The test shall include flushing out the outlets and checking of outlet
connections. The flow and pressure at the outlets shall be measured and
recorded.

e)

The joints shall be left uncovered until the tests have been completed
satisfactorily. Sufficient material shall be backfilled over the centre of
each pipe to prevent movement under the test pressure. Concrete
surrounds to pipes shall be executed only after the joints have passed
the tests.

f)

Each installation shall be adjusted as necessary to established balanced


flow rates as required for the efficient performance of the system. The
Contractor shall supply all necessary equipment, materials and labour,
etc, for carrying out the above tests. He must satisfy the SO. as to the
accuracy of the meters and gauges supplied.

g)

The section under test shall be slowly filled with water, taking care that all
air is displaced. After filling, the pipeline shall be left under operating
pressure for a period in order to achieve conditions as stable as possible
for testing.

h)

The test pressure shall be the max. working pressure of 135m plus
50% whichever is the greater and the test pressure shall be maintained
by the pump for about two(2) hour and if there is any leakage it shall be
measured by the quantity of water pumped into the main in that time.
Any leakages are found; the Contractor shall immediately remove and
replace the defective pipes and the section of pipe to be re-tested as
above until no leakage is found.

i)

If leakage occurs, the Contractor shall trace the leaks to their source, and
remedy them to the satisfaction of the SO. The main shall then be

Particular Specifications
Mechanical and Electrical Works

TME/B14

retested, and the process of testing, repairing the leaks and re-testing
shall be continued until no leakage.

j)

Any leakage shall be measured by the quantity of water pumps into the
main in that time. The leakage shall not exceed 0.2 litres per millimetre of
pipe diameter per kilometre of pipeline at each 100 metre test pressure
head for every 24- hours testing duration. Any visible individual leakage
shall be repaired.

k)

All costs incurred in carrying out all these tests and re-tests shall be
borne by the Contractor and tests are to be carried out in the presence
of the SO.

l)

Upon completion of T&C, the Contractor shall perform a final round of


flushing of the whole pipe circuit prior to the handover to SO.

Spare Parts
The Contractor shall also include in the Contract, 5% spare valve covers of the
total numbers of each type of valves cover used. The valves shall be held by the
SO.
All valves and manhole covers shall be of F900 type.

Particular Specifications
Mechanical and Electrical Works

TME/C1

Part C - Technical Specifications for Cold Water Supply


1

General

1.1

The water supply system shall include construction of the proposed potable
water system, inclusive of construction of meter chamber, laying of water
mains, water manholes, valves and underground supports for providing
potable water supply to the facilities as indicated in the drawings.

1.2

The Contractor shall liaise with and make all necessary applications and
submissions to all appropriate authorities (CAAS, PUB, SCDF, DSTA, RSAF,
CAG etc) where required.

1.3

The Contractor shall be solely responsible for obtaining the Authorities


approval of his works prior to the handing over of the whole water reticulation
system to the Superintending Officer.

1.4

The Licensed Plumber shall apply for and make all necessary arrangements/
inspections with the RSAF/ DSTA and PUB for the connection and installation
of CAGs bulk meter.

Pipeworks

2.1

In general, all water pipes used in the project shall be as follows, unless
otherwise as shown in drawings.
a)

Underground Pipe
i)

b)

80mm diameter and above shall be heavy duty ductile iron pipe
with cement lined to BS EN 545.

Aboveground Pipe
i)

80mm diameter and above shall be heavy duty ductile iron pipe
with cement lined to BS EN 545

The Contractor shall exercise all care and ensure that pipes, fittings,
valves or specials, are not damaged during loading, unloading or
transporting, or while stored at site. The Contractor shall make good all
damages caused, at his expense. He shall allow for the cost of
loading, transporting and unloading of these items in his Contract Sum.
Where there is no space alongside the proposed pipe trench for
placing the pipes prior to laying, the pipes shall be unloaded at a
temporary storage ground approved by the SO. The pipes shall be
transported subsequently for laying from the temporary storage ground
to the site of laying.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C2

The pipes at the storage ground shall be stacked not higher than 2m
such that they do not rest on their sockets. All stacks shall be set up
level on a hardwood or similar base. Each size of pipe shall be
separately stacked.
The Contractor shall allow for the cost of stacking and shifting the
pipes in his Contract Sum for pipe laying.
Handling of Pipes, Fittings, etc

2.2
a)

The Contractor shall handle all pipes with care and prevent breakage
or damage to the internal lining, external coating or wrapping and shall
ensure that the inside of the pipes, particularly at the ends are clean
before they are lowered into the trench. Where the lining, coating or
wrapping has been damaged by handling, the Contractor shall make
good the lining, coating or wrapping as directed by the SO. The
material used in the repair of damaged coatings must be compatible
with the coating material.

b)

All handling and hauling equipment shall be approved by the SO. Bare
cables, chains, hooks, wire ropes, metal bars, and narrow skids, which
may damage the pipe coating or wrapping, shall not be used.

c)

Scrupulous care shall be taken by the Contractor to ensure that all


pipes and fittings are cleaned internally when laid, and that no foreign
material is permitted to enter them after laying. A temporary pipe stop
shall be placed to cover each open end of pipe whenever work is
stopped.

d)

Each pipe shall be carefully lowered onto its prepared bed with slings
and tackle. If the prepared bed is damaged or stones are dislodged
into the trench, the pipe shall be raised, the bed made good and
stones removed before the pipe is laid. Any fractured pipes shall be
replaced at the Contractor's expense.
Cover to pipes

2.3

All pipes shall be laid to the depth shown on the Drawings or as


directed by the SO. The pipes shall be laid with a minimum earth cover
of 1000 mm outside paved areas and a minimum cover of 1000 mm
under paved areas.
Pipes laid to gradient and line set out

2.4
a)

When in the trench, the pipes shall be laid to proper gradient and true
to line, as shown on the Drawings or as directed by the SO. The
Contractor shall set up the necessary pegs and sight rails, for pipe
laying and checking purposes.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C3

b)

The pipes shall be laid in straight lines or regular curves to avoid any
unnecessary resistance to flow. All pipes must be laid on compacted
bedding. Inspection shall be carried out to ensure the compacted
bedding has compacted to 98%.

c)

The position of the pipes when laid shall not deviate from that shown
on the Drawings by 1.5 metres.

d)

The pipe work shall be laid not less than 1 metre below finished ground
level. The pipes shall be joined by flanges conforming to BS 4504
complete with rubber jointing washer unless otherwise specified in the
drawing.

e)

After joining the pipes, and on completion of testing, the granular


bedding material shall be brought up equally on both sides of the pipes
to the level of the centre of the pipeline and then the bedding or backfill
material shall be brought up to a level of 300mm, above the top of the
pipe barrel in layers, each not more than 100mm thickness, and carefully
compacted by hand for the full width of the trench.

f)

Concrete thrust blocks shall be installed at all pipe offsets, under valves
and where required.
Jointing of Pipes

2.5

Procedure for jointing will vary according to the type of joint being used.
Basic requirements for all types are: a)

Cleanliness of all parts;

b)

Correct location of components;

c)

Centralisation of spigot within socket; and

d)

Strict Compliance with Manufacturer's jointing instructions.


Flanged Joints

e)

i)

Where flanged joints are to be made, the Contractor shall clean


all flanged surfaces, cut insert rubber sheeting and make the joint
as specified or directed by the SO.

ii)

In flanged joints, the rubber jointing rings shall be properly fixed


and the bolts uniformly tightened.

iii)

The flanged joints shall be painted with two (2) sets of bitumastic
paint.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C4

The Contractor shall supply all necessary identifying items, paint,


bands, stencils, etc.
f)

Mechanical and Bolted Gland Joints


When making Bolted Gland Joints, the spigot shall penetrate into the
sockets for the required depth, the jointing rings shall be properly fixed
and the joints tightened, all in accordance with the manufacturer's
instructions, to make thoroughly sound and watertight joints.

g)

Slip-on Joints
Slip-on joints shall be made strictly in accordance with the
manufacturer's instructions, to achieve thoroughly sound and watertight
joints.
Valves and Pipes Installation

2.6

2.7

a)

The Contractor shall install air valves, washout valves, sluice valves,
bends, etc, as shown in the Drawings, or as directed by the SO. The
contractor shall do all necessary excavation; make joints, have the
joints coated with bitumastic paint (2 coats) as shown on the Drawings
or as directed by the SO. A tapping saddle shall be used for the
installation of small orifice air relief valves.

a)

After installation, the external surface of all sluice valves, air-valves and
water pipes shall be cleaned, wire-brushed, primed with approved
primer, and painted with two coats of approved bitumastic paint. All
pipework, valves and fittings shall be painted and provided with
identification markings and labels. The colour of the paint and labelling
shall be subjected to the discretion of the SO

b)

The Contractor shall supply all necessary identifying items, paint, bands,
stencils, etc.
Cutting of Pipes

Cutting of pipes shall be done by means of a patent cutter of a type approved


by the SO. The cut shall be true, straight and square to the axis of the pipe.
Any burrs left after cutting shall be trimmed off by filling or grinding.
2.8

Preparation of Spigots on Site


All spigots for jointing into sockets must be chamfered. Where spigots
require preparation on site, the outside of the spigot shall be filed to produce
an angle of approximately 30 degrees to facilitate the entry of the spigot past
the gasket.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C5

0Blocks and Anchors

2.9
a)

Pipe lines shall be securely anchored at dead ends, tees, bends,


tapers and valves to resist thrust arising from internal pressure. Thrust
blocks shall be to the dimensions specified or as indicated by the SO.
Brackets for securing of pipes and fittings to thrust blocks shall be set
in concrete and fixed by the Contractor as directed.

b)

All concrete shall be of C35 / 37 concrete mix unless otherwise directed


by the SO.

c)

All design and calculation of thrust blocks and anchors shall be


submitted and endorsed by the Contractors Professional Engineer.

d)

Steeply inclined pipelines shall be secured by in accordance with the


following tabulation:

Table 1
Gradient

Spacing (m)

1 in 2 and steeper

5.5

Below 1 in 2 to 1 in 4

11.0

Below 1 in 4 to 2 in 5

16.5

Below 1 in 5 to 1 in 6

22.0

Flatter than 1 in 6

Not required

Thrust blocks shall be cast in place so that they will bear against an area of
undisturbed soil in the trench wall with the pipe joint accessible for inspection
and repair. Minimum area of Bearing Face of Concrete Thrust Blocks Against
Horizontal Thrusts is given in Table 2. Where thrust blocks occur at location
of soft and unstable soil, the soft soil shall be replaced with more stable
materials.
Table 2
Ductile Iron (Area in Sq Metre)
Nominal
1/4 Bend
Size
100
0.30

0.20

Tees, Plugs,
Caps, Hydrants
0.30

150

0.65

0.40

0.50

200

1.100

0.60

0.75

250

1.60

0.85

1.12

300

2.30

1.21

1.60

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

1/8 Bend

TME/C6

350

2.90

1.68

2.14

400

3.91

2.15

2.80

450

4.93

2.70

3.44

500

6.04

3.25

4.28

550
8.55
Notes: Basis for Table 2:

4.65

6.14

i)
ii)
iii)
iv)

Encased Pipes

2.10

2.11

Soil Resistance = 9800 kgf/m2 (2,000 lb/ft2)


Water Pressure = 17 bars (250 psi)
Weight of Cover and Pipe not taken into account
Correction factors for other soils: Soft clay ..............
4
Sand ....................
2
Sand and Gravel ........
1.33
Shale ...................
0.4

a)

Where it is deemed necessary for the pipes to be laid, strapped and


encased with concrete, especially under areas subject to aircraft
vehicular traffic, or areas most likely to be subjected to settlement
caused by excavation works for proposed developments in and around
the vicinity, the Contractor is advised to clarify with the SO. the actual
extent, material, size and method of construction of the encased pipes.
All concrete for encased pipe shall be of C20/ 25 mix unless specified
in the drawing whichever is more stringent.

b)

The Contractor shall ensure that the trench bed is well compacted and
inspected by the SO. before commencing to concrete all pipe
encasement work.
Identification of Mains

Where the potable water mains, fire hydrant mains, and industrial water
mains run, they shall be identified by means of PVC tape, at least 150mm
wide, laid directly over them at a height not greater than 300mm from the
crown of the mains. The colours of the tapes used for the various mains shall
be light blue, signal red and black, respectively.

2.12

Chambers for Valves, etc.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C7

The Contractor shall ensure that the bedding is mechanically well compacted
before seating the chamber firmly on it. Selected fill shall be well rammed
around the valve up to the top flange.

Materials And Jointing Of Water Supply Pipes

3.1

All piping materials shall be of type/brands found in the list of approved fittings
and pipes for water service installation and approved in PUB listing.

3.2

An indication of the suitability of available pipe and jointing materials for the
various effluents and ground water conditions is given as follows:-

3.3

Every joint in the water supply shall be made air-tight and water-tight and
shall remain so during use.

3.4

No jointing material shall protrude inside the bore of the pipe.

3.5

If cast or ductile iron pipe is used then the joint shall be made as follows:a)

Tyton or Approved Flexible Joints


The pipe and fittings shall be cement lined and supplied with
bituminous coating externally. The spigot and socket fairings shall be
clear before the rubber ring is fitted in the spigot groove. Lubricant
shall be applied to the socket fairing before the spigot is inserted into
the socket and then with a slight side-to-side movement push home.
No mechanical means shall be applied for jointing.
The spigot shall be pushed forward into the mating socket until the
rubber is compressed, making a perfect air-tight and water-tight seal,
which allows both angular and telescopic movement only.

b)

Flanged Joint
Shall be made with jointing rings of best quality, smooth, hard,
compressed fibre board (not less than 1.5mm thick), and of such width
as to fit inside the circle of bolts. The rings shall be smeared thinly with
graphite paste. Alternatively, the jointing rings may be of rubberinsertion or may be corrugated rings of non-corrosive alloy together
with a suitable jointing paste. The nuts shall be carefully tightened, in
opposite pairs, until the jointing ring is sufficiently compressed between
the flanges to ensure water-tightness of the joint under the desired
water pressure.

Excavation And Backfilling To Underground Water Pipes

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C8

4.1

All excavation shall be carried out to the required lengths, breaths, depths,
inclinations and curvatures as may be necessary for the construction of the
works.

4.2

Pockets shall be formed for sockets, flanges, valves etc., so as to give the
barrel of each pipe a full support throughout its entire length. Sufficient timber
support shall be provided to prevent trenches from collapsing.

4.3

The Contractor is required to provide good de-watering system for keeping


the excavation clear of water at all times.

4.4

The bottom of all trenches shall be free from mud and water, trimmed clean
and thoroughly consolidated by iron shot rammers. All soft or defective
portions shall be cut and filled in with selected excavated material well
consolidated in layers.
a)

5
5.1

Backfilling shall be commenced only after the pipeline has been tested
shall be approved by the SO. It shall be done in stages as follows:i)

Fine and dry material selected from the excavated earth shall be
packed and well rammed underneath and at the sides of the
pipeline up to half pipe height.

ii)

The filling shall then be carried up to 300mm above the socket


of the pipes with selected material and well rammed.

iii)

The remainder of the excavation shall be filled in with the most


suitable portions of the excavated material in layers of not more
than 300mm deep. Each layer shall be well rammed before the
next layer is placed.

iv)

The top of trenches shall be filled with material originally taken


from the surface and set aside for subsequent reinstatement.

Valves
All valves shall be suitable for operating pressures up to 1 MPa. Valves
up to 64mm diameter shall have bronze bodies and trim with screwed
connections. Valves 75mm diameter and above shall have cast iron or cast
steel bodies, bronze trim with flanged connections. All valves shall be located
in accessible positions for ease of operation. All valves shall be approved
and stamped by the Water (Network) Department, Public Utilities Board. All
underground valves shall be housed within a chamber as stipulated in the
drawing c/w F900 manhole. The valve chamber and cover shall be designed
to take aircraft loading. All valves and fitting shall be from the same
manufacturer where available.
a)

Stop Valves

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C9

Stop valves shall be gate valves with non-rising stems, renewable


seats and cast iron or plastic handwheels.
b)

Stop Cocks
Stop cocks shall be chromium plated with renewable rubber disc seats
to British Standards BS 5433 and BS 1010-2.

c)

Check Valves
Check valves shall be swing check type with replaceable seats.

d)

Strainers
Strainers shall be Y-type with removable stainless steel basket.

e)

Sluice Valve
Sluice valve shall be of heavy water works type complying with BS
6700:2006+A1:2009 and be of the rising spindle type.

g)

Air Vents
Key operated air vent cocks of an adequate size shall be provided at all
high points on water supply, whether shown on the Drawings or not.
Where such high points are unaccessible, air bottles shall be provided
with the vent pipe turned over and carried down to a point 1,200mm
above floor level, terminating in a vent cock.
Each vent shall incorporate a lockshield valve and the discharge pipe
shall be run to the nearest agreed drain point.

h)

Drain Points
Adequately size drain valves shall be provided at all low points on the
piping system, whether shown on the Drawing or not, for draining of the
system.

g)

Valve Keys, Lifting Keys and Prising Bars


The Contractor shall provide 10 nos. T-bar valve key operators for each
type of valve. The key operators shall be designed with ample strength
to open and close valves against the full head of the pipelines (10 bars)
without distortion or overstressing. They shall be of length 1.80 metres.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C10

The Contractor shall also provide 10 nos. lifting keys and 10 nos.
prising bars of ample strength for each type of surface boxes and
covers provided.
The Contractor shall provide extra 5% of each type of covers
each for the various surface boxes provided.
6

Installation Of Water Pipes

6.1

Underground water pipes


a)

All pipes shall be laid to line and level as indicated in the specifications,
drawings or as instructed by the Superintending Officer but full
allowance shall be made by the Contractor for the detailed development
and co-ordination of the scheme and for the future removal and
dismantling of sections of the Work.

b)

All pipes shall be bedded on concrete at least 100mm thick and


properly haunched in concrete at least 100mm on either side of the
pipe or as per detail drawings whichever is more stringent. It shall be
free from burrs, rust and scale and shall be thoroughly cleaned before
installation.

c)

Before laying, each pipe and fitting shall be thoroughly cleansed


internally and the ends temporarily plugged to prevent ingress of dirt
and on completion each system shall be thoroughly flushed out with
clean water. After laying and jointing, the leading end shall remain
temporarily plugged to prevent access of water, soil etc. Precautions
should be taken to prevent flotation of the plugged pipes should the
trench become flooded. Wooden bungs shall not be used for plugging
pipework

d)

Any coating, sheathing or wrapping of the pipes shall be examined for


damage and repaired where necessary, and shall also be made
continuous over joints.

e)

Where there is a gradient, pipe laying shall preferably proceed in an


uphill direction to facilitate joint making.

f)

Except in the case of small pipes made low pressure, thrust-blocks of


concrete shall be formed at all bends, branches and dead-ends to
transmit the hydraulic thrust on the undisturbed ground and to spread it
over a sufficient area. Where the hydraulic thrust is in an upward
direction, anchor-blocks of sufficient weight shall be formed to which
the pipe shall be secured with steel straps.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C11

7.1

g)

Every ground pipe entering a building shall do so at a level not less


than 500mm below the outside ground surface and at the point of the
entry pipe shall be accommodated in a sleeve which shall have
previously been solidly built-in, and the space between the pipe and
sleeve shall be filled with bituminous or other suitable material for a
minimum length of 150mm at both ends to prevent the passage of
water, gas or vermin.

h)

Surface boxes shall be provided to give access to operating valves and


shall be supported on concrete or brickwork which must not be allowed
to rest on the pipes and transmit traffic loads to them, allowance being
made for settlement. The cover shall be of F900 loading class

i)

Precautions against contamination of the pipe shall be taken when


making a connection, and where any risk exists, the pipe shall be
subsequently sterilized.

Testing and Commissioning Of Water Pipes


General
The Contractor shall carry out all necessary testing and commissioning
procedures comprising tests at maker's works, site tests during construction,
commissioning and acceptance tests all as specified below.
Tests shall be carried out in accordance with the appropriate Latest Code of
Practice and Singapore Standards.
All tests may be witnessed by the SO, and in the case of pressure tests at the
manufacturer's works, by parties nominated by the SO. Not less than
fourteen days' notice shall be given by the Contractor for this purpose.
All tests shall be properly recorded in a manner to be agreed with the
Superintending Officer and triplicate copies of all records shall be issued to
the Superintending Officer on completion.
These test records, and performance data shall be supplied for all tests,
whether or not they have been witnessed by the SO. The information given
on such test records and services shall be sufficient to identify the material or
equipment to which the records refers, and shall also bear the Contract
reference and heading given in equipment sections.
Only when the installations have been so recorded and all test figures and
other relevant information has been recorded in the prescribed manner and
accepted by the Superintending Officer will the Superintending Officer issue
the completion certificate.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C12

The Contractor shall provide all labour, tools, instruments, material, equipment
and recorders required to carry out the tests.
Six months before commissioning or testing any of the installations, the
Contractor shall submit to the Superintending Officer for comment a
comprehensive testing and commissioning procedure. This document shall
outline all steps to be taken by the Contractor in testing and commissioning of
the installations. Details of each instrument to be employed are to be
provided.
Manufacturer's works test shall include all routine electrical and mechanical
tests in accordance with the relevant British Standards, and in addition, any
tests called for by the Superintending Officer to ensure that the plant being
supplied meets the requirements of this Specification. For plant not covered
by any British Standards or specifically mentioned in this Specification, the
tests shall be agreed with the SO.
All items of equipment of each type and rating supplied under this Contract
shall be subjected to type tests of electrical and mechanical performance as
appropriate and as specified in the relevant British Standards or equal. In the
event of the Contractor supplying recorded copies of type test records
covering equipment of similar design, rating and construction, the
Superintending Officer may waive such tests entirely. The Contract Sum shall
include for the carrying out of such tests where records are not already held.
All instruments shall have been recalibrated within three months of the start of
commissioning or testing.
Calibration of all instruments shall be certified by the instrument manufacturer
or an approved calibration agency. Copy of the certificate shall be submitted
for review and record.
7.2

After laying, jointing and anchoring, the pipes shall be slowly and carefully
charged with water, so that all air is expelled, allowed to stand full for several
days and then tested under pressure.

7.3

A long main shall be tested in sections as the work of laying proceeds, and it
is an advantage to leave the joints exposed for inspection during the testing.

7.4

The open end of the pipe may be temporarily closed for testing under
moderate pressure by fitting a blank flange. The end of the pipe shall be
secured by struts or otherwise, to assist the end thrust of the water pressure
in the pipe.

7.5

If the section of pipe tested terminates with a sluice valve, the wedge of the
valve shall not be used to retain the water; instead the valve shall be fitted
temporarily with a blank flange, and the wedge should be placed in the open
position while testing.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C13

7.6

The test pressure shall be applied by means of manually-operated test


pump or, in the case of long pipes or pipes of large diameter, by a powerdriven test pump which shall not be left unattended. In either case,
precautions shall be taken to ensure that the required pressure is not
exceeded. Pressure gauges shall preferably be recalibrated before the test.

7.7

The test pressure shall be 120 meters head or the max. working pressure
plus 50% whichever is the greater and the test pressure shall be maintained
by the pump for about two(2) hour and if there is any leakage it shall be
measured by the quantity of water pumped into the main in that time. Any
leakages are found; the Contractor shall immediately remove and replace
the defective pipes and the section of pipe to be re-tested as above until no
leakage is found.

7.8

The Contractor will notify the Superintending Officer three days in advance
of any test so that the Superintending Officer can witness the tests if he
wishes to.

Sterilization Of Main

8.1

Sterilisation of the potable water system shall be carried as per latest Code of
Practice CP: 48

8.2

After the pipework has been tested and approved, but before it is coupled, it
shall be sterilized with a solution of chloride of lime.

8.3

The approximate amount of chloride of lime required to sterilize pipework of


various sizes shall be as follows:
Diameter

Capacity/100 yds

Amount of Chloride of Lime

100 mm

730 dm3

200 g

150 mm

1640 dm3

265 g

8.4

The solution of the sterilizing agent shall be introduced into the main at a
constant rate to give the required concentration by ascertaining the rate of
discharge to the main through a valve.

8.5

The pipework shall be thoroughly flushed before supply is restored.

8.6

Upon completion of T&C, the contractor shall perform a final round of


flushing of the whole pipe circuit prior to the handover to SO.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/C14

Spare Parts
The Contractor shall also include in the Contract, 5% spare valve covers of
the total numbers of each type of valves cover used. The valves shall be held
by the SO.
All valves and manhole covers shall be of F900 type.

Pa r t i c u l a r Sp e c i f i c a t i o n s
Mechanical and Electrical W orks

TME/D1

Part D PUBs Technical Specification for special internal lining of pipes


and pipe fittings
STANDARDS FOR SPECIAL INTERNAL LINING OF PIPES AND PIPE
FITTINGS TO BE USED FOR FIRE HYDRANT PIPES
General
The internal lining and external coating materials of the pipes and pipe
fittings shall conform to the requirements of any one of the following Standards:
(a) British Standard (BS EN 598:1995) on "Ductile Iron Pipes, Fittings,
Accessories and their Joints for Sewerage Applications
(b) Australian Standard (AS 4321:1995) on Fusion-bonded Medium-density
Polyethylene Coating and Lining for Pipes and Pipe Fittings
(c) American Standard (ASNI/AWWA C213) on Fusion Bonded Epoxy
Coating for the Interior and Exterior of Steel Water Pipelines
(d) Any other ISO, German (DIN), French or Japanese (JIS) Standards
suitable for sewerage applications or ultra pure water applications.
The lining materials shall be bonded to pipes in the factory, and shall
adhere perfectly to the inside of the pipes and pipe fittings. The lining materials
shall meet the minimum requirements of pull-off test for adhesion, as stipulated in
ISO 4624:1978, or its equivalent American (ANSI/NSF 61), Australian (AS 4321),
German (DIN EN 24624), French or Japanese Standards, but not less than 3
N/mm width of strip.
Finished lining materials shall be smooth, even and free from ridges,
corrugations, cracks, foreign matter, blemishes or other defects. The same shall
be applicable to the inside of the socket and the outside of the spigot end of pipes
and pipe fittings, which will be in contact with NEWater. The Contractor shall
ensure that all lining materials of the pipes and pipe fittings especially that portion
outside the spigot end is not damaged during transport and pipelaying, by
providing adequate protection to the pipes and pipe fittings.
Lining shall be inspected for continuity using a full-wave rectified direct
current output detector set at 1000 V to check for pinholes, holidays and
discontinuities. Thickness of the lining/ coating may be measured using a
magnetic thickness gauge or other instrument with high accuracy as approved by
the Board.
Pipes and pipe fittings requiring limited repair due to scars, slivers, lining
imperfections and other minor defects shall be repaired in accordance with the
manufacturers recommendations.

Particular Specifications
Mechanical and Electrical Works

TME/D2

The lining of the pipes and pipe fittings shall have no toxic effect to the
water in the pipeline, and must satisfy the requirements of SS 375 (Singapore
Standard 375 on suitability of non-metallic products for use in contact with water
intended for human consumption with regard to their effect on the quality of the
water), or BS 6920, or AS 3855 as applicable.
Tenders are to be accompanied by an analytical report on the total organic
carbon (TOC) content of water that has been in contact with the pipe. The test
procedure shall follow that described in the Clause 16.1 (d). The analytical report
must be prepared by a product conformance assessment body (certification
body/testing facility) accredited by the Singapore Accreditation Council (SAC) or
under its Mutual Recognition Agreements (MRAs). Tenders which do not comply
with the above may not be considered.
Total Organic Carbon (TOC) Test
(a)

Sample And Test Container Size


A pipe sample with a total surface area of 15,000 500 mm shall be used
for the test. Test containers shall be made of borosilicate glass and be of
sufficient volume to contain the pipe sample and 1,000 ml of test water.
The sample shall be made up from one or more articles drawn from the
same production batch or cut from a single larger product. The maximum
length and width of any single sample shall be 150 mm and 70 mm
respectively.

(b)

Test Water
Deionised water or any water with a total organic carbon (TOC) content of
less than 100 g/l shall be used as the test water for the blank and sample
extracts.

(c)

Test Protocol And Report For Total Organic Carbon


The analysis for total organic carbon (TOC) content shall be carried out in
accordance with the test methodology given in the APHA/AWWA Standard
Methods for the Examination of Water and Wastewater (20th Edition) or
British Standards. The test instrument/method detection limit shall be 10 g/l
or lower.
The test report on TOC content shall state the method used for TOC
analysis and the instrument/method detection limit.

(d)

Test Procedure
Extraction Procedure
It shall be ensured that the extraction periods below are consecutive and
without a break; if a break in the sequence occurs, repeat the sequence
using fresh samples.

Particular Specifications
Mechanical and Electrical Works

TME/D3

First Extract
Rinse the sample and test containers with the test water for 5 minutes.
Place the sample in a clean test container. One container of test water shall
be used as a blank. Fill each test container with 1,000 ml of test water and
seal each container with a fresh piece of aluminum foil. If the density of the
sample is less than that of water, ensure the sample is kept totally
submerged in the test water for the duration of the test by using glassencapsulated weights.
Immerse the sample in the test water for 24 hours. At the end of this period,
extract 50 ml each of the test water and blank for analysis of TOC content.
Second Extract
Empty the sample test container and blank container of water. Rinse the
sample and test containers with fresh test water for 5 minutes.
Refill the containers as before and immerse the sample in the test water for
another 24 hours. At the end of the second 24-hour period, extract 50 ml
each of the test water and blank for analysis of TOC content.
Third Extract
Empty the sample test container and blank container of water. Rinse the
sample and test containers with fresh test water for 5 minutes.
Refill the containers as before and immerse the sample in the test water for
another 24 hours. At the end of the third 24-hour period, extract 50 ml each
of the test water and blank for analysis of TOC content.
Fourth Extract
Empty the sample test container and blank container of water. Rinse the
sample and test containers with fresh test water for 5 minutes.
Refill the containers as before and immerse the sample in the test water for
72 hours. At the end of the 72-hour period, extract 50 ml each of the test
water and blank for analysis of TOC content.
Fifth Extract
Empty the sample test container and blank container of water. Rinse the
sample and test containers with fresh test water for 5 minutes.
Refill the containers as before and immerse the sample in the test water for
24 hours. At the end of the 24-hour period, extract 50 ml each of the test
water and blank for analysis of TOC content.
Sixth Extract
Empty the sample test container and blank container of water. Rinse the
sample and test containers with fresh test water for 5 minutes.
Refill the containers as before and immerse the sample in the test water for
Particular Specifications
Mechanical and Electrical Works

TME/D4

another 24 hours. At the end of the 24-hour period, extract 50 ml each of the
test water and blank for analysis of TOC content.
Seventh Extract
Empty the sample test container and blank container of water. Rinse the
sample and test containers with fresh test water for 5 minutes.
Refill the containers as before and immerse the sample in the test water for
another 24 hours. At the end of the 24-hour period, extract 50 ml each of the
test water and blank for analysis of TOC content.

Internal Lining For Pipes & Pipe Fittings


Every part of the pipes and pipe fittings, including the socket inside and
spigot outside (portion to be pushed into the pipe socket) that will be in contact
with NEWater shall be lined with one of the following types of materials:
(a)
(b)
(c)
(d)

100% solids rigid polyurethane,


Fusion-bonded medium density polyethylene,
Fusion-bonded epoxy.
Any other lining materials as may be recommended by a reputable pipe
manufacturer with test reports indicating that the materials comply with a
Standard relevant to the application, and other supporting documents to
show that the materials is suitable for NEWater application (e.g.
technical assessment, history of the materials use for conveying ultrapure water or water of similar quality in one or more developed
countries).

100% Solids Rigid Polyurethane Lining for Pipes & Pipe Fittings
Polyurethane used for lining of the pipes and pipe fittings shall be of 100%
solids rigid polyurethane with a density of about 1600 kg/m3. The lining shall have
a thickness of at least 1.0 mm for all sizes of pipes and pipe fittings, and at least
0.3 mm for the socket and the outer portion of the spigot end. It shall have a
continuous protection to the metal part of the pipes and pipe fittings without
cracks. The dielectric resistance shall be about 200 kV/cm. The shock resistance
of the polyurethane lining shall be more than 12 N-m. It shall have an elongation
of more than 10%. The polyurethane shall have no effect subject to salt water
spray test of 1000 hours. It shall have the chemical resistance against chlorinated
water, water solution of salts, acids and bases of pH 5 to pH 9. In terms of head
loss, the roughness coefficient (k) in the Colebrook-White formula for the
polyurethane shall be less than 0.01 mm, or alternatively the Hazen William
coefficient in the Hazen William formula shall be 150 or higher.

Fusion-Bonded Medium Density Polyethylene Lining & Coating for Pipes &
Particular Specifications
Mechanical and Electrical Works

TME/D5

Pipe Fittings
Polyethylene used for lining and coating of the pipes and pipe fittings shall
be fusion-bonded medium density polyethylene with a density of about 930 kg/m3.
The lining shall have a thickness of at least 1.0 mm for all sizes of pipes and pipe
fittings. For the materials to be used as coating on the external surface of pipes
and pipe fittings, the minimum thickness shall be 1.8mm for 150mm, 300mm
and 500 mm dia pipes, and 2.3 mm for 700 mm and 900 mm dia pipes. The lining
and coating materials shall have a continuous protection to the metal part of the
pipes and pipe fittings without cracks. The dielectric resistance of the polyethylene
shall be about 200 kV/cm. The shock resistance of the polyethylene shall be more
than 18 N-m. The polyethylene shall have an elongation of more than 300%. It
shall have no effect subject to salt water spray test of 1000 hours and shall have
the chemical resistance against chlorinated water, water solution of salts, acids
and bases of pH 5 to pH 9. In terms of head loss, the roughness coefficient (k) in
the Colebrook-White formula for the polyethylene shall be less than 0.01 mm, or
alternatively the Hazen William coefficient in the Hazen William formula shall be
150 or higher.
Fusion-Bonded Epoxy Lining for Pipes & Pipe Fittings
Epoxy used for lining of the pipes and pipe fittings shall be fusion-bonded
epoxy for the straight section of pipes. At the socket end of a pipe, the epoxy used
for lining shall comprise fusion-bonded epoxy as first coat, and a second coat of
epoxy if required by the manufacturer. The lining shall have a total thickness of at
least 0.5 mm for all sizes of pipes and pipe fittings, and at least 0.3 mm for the
socket. The outer portion of the spigot end in contact with NEWater may be
coated with a first coat of zinc-rich paint follow with a second coat of epoxy of
about 0.3 mm, to give a total thickness of 0.33 mm, in place of fusion-bonded
epoxy if necessary.
The finished epoxy lining shall have a continuous protection to the metal
part of the pipes and pipe fittings without cracks. The shock resistance of the
epoxy shall be more than 11 N-m. It shall have no effect subject to salt water
spray test of 1000 hours and shall have the chemical resistance against
chlorinated water, water solution of salts, acids and bases of pH 5 to pH 9. The
fusion bonded epoxy shall have an elongation of more than 10%. In terms of head
loss, the roughness coefficient (k) in the Colebrook-White formula for the epoxy
shall be less than 0.01 mm, or alternatively the Hazen William coefficient in the
Hazen William formula shall be 150 or higher.

Particular Specifications
Mechanical and Electrical Works

Vous aimerez peut-être aussi