Académique Documents
Professionnel Documents
Culture Documents
SAEP-16
Project Execution Guide
for Process Automation Systems
Process Control Standards Committee Members
24 October 2009
Scope............................................................. 2
Applicable Documents................................... 2
Definitions...................................................... 3
Instructions..................................................... 7
Responsibilities............................................ 14
Approval, Deviation and Exceptions............ 15
Page 1 of 19
SAEP-16
Project Execution Guide
for Process Automation Systems
Scope
This Saudi Aramco Engineering Procedure (SAEP) defines the procedures and
responsibilities for the execution of Process Automation Systems (PAS) projects with
the exception of royalty custody metering facilities. Royalty custody metering facilities
project execution is governed by SAEP-21 and SAEP-50. SAEP-16 is applicable to all
Saudi Aramco capital projects (SAEP-1020) and BI-1900 projects which include
process automation systems, and where the overall cost of the PAS portion is at least
$1,000,000. The cost shall include all direct Saudi Aramco costs to design, procure,
install and commission the system. PAS projects utilizing Main Automation Contractor
(MAC) concept shall follow SAEP-1650.
In the event that some or all of the steps are executed by contractors or vendors, the
project management team (PMT) shall ensure that the project is executed within the
framework of this procedure.
Applicable Documents
The latest edition of the applicable reference documents shall be applied:
Saudi Aramco Engineering Procedures
SAEP-12
SAEP-14
Project Proposals
SAEP-21
SAEP-50
SAEP-302
SAEP-303
SAEP-1020
SAEP-1610
SAEP-1622
SAEP-1624
SAEP-1626
SAEP-1628
SAEP-16
Project Execution Guide
for Process Automation Systems
SAEP-1630
SAEP-1634
SAEP-1636
SAEP-1638
SAEP-1650
GI-0020.500
Expenditure Control
Definitions
3.1
Acronyms
CDR
DBSP
DCS
ER
Expenditure Request
ERA
E&PM
ESD
FAT
FPD
FSD
GI
General Instructions
HVAC
ID
Inspection Department
I/O
Input/Output
Page 3 of 19
SAEP-16
Project Execution Guide
for Process Automation Systems
IT
Integration Test
LPD
MAC
MCC
MIS
MSAER
NCR
Non-Conformance Report
NMR
Non-Material Requirements
OO
Operating Organization
PAC
PAS
PAT
PC
Personal Computer
P&CSD
PDR
PEP
PLC
PMCC
PMT
PO
PRB
PS&CD
SAEP
SAMSS
SAT
SCADA
SDD
SDP
SRC
Page 4 of 19
3.2
SAEP-16
Project Execution Guide
for Process Automation Systems
Terms
Bid Package: The package of documentation supplied to a bidder to quote the
job. A Bid Package includes Instructions to Bidders, Pro Forma Contract, Job
Specifications, Functional Specifications Document, relevant SAMSS
specifications, and other documents as applicable.
Bid Evaluation Team: A team that reviews the contractor's or vendor's bids
and prepare technical and commercial recommendations. Refer to the
Contracting Manual for additional information.
Bid Slate: A list of qualified contractors or vendors to bid on the project.
Control System Input Document: A brief overview of the integrated Process
Automation solution covered by the Design Basis Scoping Paper (DBSP). It
identifies process plants and plant units that require control, instrumentation,
information, and applications.
Field Proven: A software and/or hardware which has been in successful
operation at a field installation for six months or more excluding beta testing.
Integration Specifications Document: A document prepared by the PAS
integrator that provides the technical specifications for all the different systems
and sub-systems' hardware interfaces, applications interfaces, data
communications requirements, and testing procedures. This document is only
required if the project is comprised of multiple systems linked via a common
backbone or a wide-area network. Examples are: DCS/MIS, SCADA/MIS,
DCS/SCADA or DCS/SCADA/MIS. Systems connected by serial interfaces do
not fall under this category.
Job Specification: The scope of the work to be performed pursuant to a contract.
It describes or refers to the applicable drawings, standards, specifications as well
as the administrative, procedural, and technical requirements that the contractor
shall satisfy or adhere to in accomplishing the work.
Main Automation Contractor: A highly qualified, large projects experienced,
and well resourced control systems contractor assigned to engineer,
supply/procure and manage Process Automation Solutions and associated
instrumentation for all project process areas and facilities.
Non-Conformance Report: A report issued by Inspection Department to
highlight any deviation from the standards and specifications.
Non-Material Requirements: The complete set of documentation required
from the vendor and/or the contractor during the design and development phase
of the project. There are three categories of NMRs:
Page 5 of 19
SAEP-16
Project Execution Guide
for Process Automation Systems
601 NMRs
602 NMRs
603 NMRs
Page 6 of 19
SAEP-16
Project Execution Guide
for Process Automation Systems
Instructions
4.1
Project Conception
Once the need for the project is identified, viable approaches are
developed, and recommendations are made. PAS Feasibility Study
should be completed by a team from P&CSD, FPD and Operating
Organization to determine the best value control system technology for
the proposed project.
DELIVERABLES:
4.1.2
Scope Definition
A brief description of what needs to be achieved and a synopsis of how
the requirements are to be accomplished are defined in the DBSP.
PAS Business Case Analysis should be completed by a team from
P&CSD, FPD and Operating Organization to determine the best value
control system architecture alternatives. Control System Input
Document should be completed by P&CSD for the selected alternative
to define the control system architecture and required applications.
The DBSP should state if a PAS project is to be executed utilizing
MAC concept. The DBSP constitutes an agreement between the
proponent organization, PMT, P&CSD, and FPD on the project scope
and schedule. At the time of DBSP approval, conceptual cost
estimates (40%) and preliminary economic analysis are performed.
DELIVERABLES:
4.1.3
DBSP
4.1.4
SAEP-16
Project Execution Guide
for Process Automation Systems
Bid Period
Upon finalization of the contracting plan, the MAC Bid Package is
prepared and sent out to the bidders on the bid slate. When bid
responses are received, technical and commercial evaluations are
conducted by the bid evaluation team. Refer to Saudi Aramco
Contracting Manual Chapter VII or Saudi Aramco Worldwide
Purchasing Manual for more details on this phase of the project.
DELIVERABLES:
4.1.5
Project Proposal
During this stage, the detailed project scope, cost estimate basis,
schedule, and quality system are established. This includes the
proposed facility size and general layout and the appropriate functional
and performance specifications. MAC scope is established per
SAEP-1650. Waiver approval is obtained for any MSAER that will not
be met according to the Project Proposal (refer to SAEP-302). P&CSD
shall be requested to conduct one formal review of the Project Proposal
Package per SAEP-303 requirements.
Conduct Process Hazardous Analysis (PHA) at the Project Proposal
stage as required by project scope or applicable standards.
DELIVERABLES:
4.1.6
ER Package
Page 8 of 19
4.1.7
SAEP-16
Project Execution Guide
for Process Automation Systems
Detailed Design
During the detailed engineering phase of the project, the PAS design is
reviewed at two milestones: Preliminary Design Review and Critical
Design Review. Waiver approval is obtained for any additional
MSAER that will not be met (beyond those approved at Project
Proposal). P&CSD shall be requested to conduct one formal review of
the Detail Design Package per SAEP-303 requirements.
Conduct Process Hazard and Operability (HAZOP) study at the Detail
Design stage of the project as required by project scope or applicable
standards.
DELIVERABLE:
4.1.7.1
4.1.7.2
4.1.8
SAEP-16
Project Execution Guide
for Process Automation Systems
Integration
When the CDR review is completed, the PAS is manufactured and
staged for configuration and testing. P&CSD shall be consulted on the
PAS Integration Specification Document.
A review of the 603 NMRs is required at this stage. Appendix B
includes a recommended list.
DELIVERABLES:
4.1.9
4.1.10
FAT Report
Integration Test
This test is only required if the project is delivering multiple systems
that are required to be integrated.
The approved Integration Test procedure (see SAEP-1630) shall be
used to demonstrate the seamless integration of the PAS. The focus of
the Integration Test shall be to verify a) the proper functioning of the
required interfaces and b) the data transfer rates among the different
components of the PAS.
DELIVERABLES:
Page 10 of 19
4.1.11
SAEP-16
Project Execution Guide
for Process Automation Systems
4.1.12
Packing List
4.1.13
4.1.14
SAT Report
Pre-Commissioning
A commissioning plan shall be developed by the Operating
Organization and supported by the Project Management Team.
P&CSD shall be consulted on as needed basis during this stage of the
project. Complete loop testing from the sensing element(s) to the final
control element(s) is performed. This test will verify the instruments,
the wiring, the I/O cards, and the I/O configuration.
Page 11 of 19
DELIVERABLES:
SAEP-16
Project Execution Guide
for Process Automation Systems
Commissioning Plan
Loop Acceptance Sheets
4.1.15
4.1.16
4.1.17
None
4.2
PRB Criteria
When deemed necessary by the PMT, a Project Review Board shall be
established for projects which are considered as high risks.
Page 12 of 19
SAEP-16
Project Execution Guide
for Process Automation Systems
b.
PRB Timing
Projects shall be evaluated:
4.2.3
a.
b.
PRB Objectives
The objective of the Project Review Board is to reduce the risk of a
project by ensuring:
4.2.4
a.
b.
PRB Makeup
The Project Review Board shall consist of the following:
a.
b.
c.
OO technical representative
d.
Page 13 of 19
SAEP-16
Project Execution Guide
for Process Automation Systems
Responsibilities
5.1
Execution Responsibilities
Step
4.1.1
Deliv.
4.1.2
Deliv.
***
4.1.3
4.1.4
4.1.5
Deliv.
4.1.6
Deliv.
***
4.1.7
Deliv.
4.1.8
Deliv.
4.1.9
Deliv.
4.1.10
Deliv.
4.1.11
Deliv.
4.1.12
Deliv.
4.1.13
Deliv.
4.1.14
Deliv.
4.1.15
Deliv.
4.1.16
Deliv.
4.1.17
Deliv.
*
**
Activity
Project Conception
Feasibility Study EPI
Scope Definition
DBSP
PRB First Checkpoint
MAC Bid Package
Bid Period
Bid Slate
Bid Package
Technical Evaluation
Commercial Evaluation
Award Recommendation
Project Proposal
PEP
Proposal Package
FSD
ERA
ER Package
PRB Second Checkpoint
Detailed Design
601 NMRs
602 NMRs
Integration
603 NMRs
FAT
FAT Report
Integration Test (If Req'd.)
IT Report
Packing and Shipping
Packing List
Installation and Checkout
None
SAT
SAT Report
Pre-Commissioning
Loop Acceptance Sheets
Commissioning Plan
MCC
Feedback Form
MCC Form (SA-7213)
PAS Form
Start-up and Commissioning
None
PAT
PAC Form (SA-7214)
Perform
OO/FPD
FPD/P&CSD/OO
FPD
FPD/P&CSD
Consult
P&CSD
PMT/PO
PMT/PO
PMT/P&CSD
PMT/PO
PMT/OO/P&CSD
PMT/PO
P&CSD/FPD/OO
OO/P&CSD
PMT
OO/P&CSD
Approve
OO
OO/P&CSD
PMT
FPD/P&CSD/OO/PMT*
See SAEP-1650
See SAEP-1620
See Contract Manual
See Contract Manual
See Contract Manual
See Contract Manual
See SAEP-12
See SAEP-14
See SAEP-1610
PMT/FPD
PSCD
PMT
PMT
P&CSD
See SAEP-11
PMT/OO
PMT/OO
PMT
ID
PMT/OO/P&CSD
P&CSD
PMT/OO/P&CSD
P&CSD
PMT
ID
PMT
ID
PMT/OO
P&CSD
OO/PMT
P&CSD
PMT/OO
PMT/OO/P&CSD
PMT/OO/ P&CSD
PMT
PMT/OO
PMT/OO
PMT/OO
PMT
PMT/OO
OO
OO
PMT
OO/PMT
P&CSD
PMT/OO
Page 14 of 19
5.2
SAEP-16
Project Execution Guide
for Process Automation Systems
a.
b.
Conducting "in-depth" reviews with the project manager and the senior
operations representative. Quarterly review cycles are recommended;
however, the PRB may adopt an alternate schedule.
c.
d.
6.2
Document Approval
This document was approved by:
-
20 November 2007
24 October 2009
Revision Summary
Revised the "Next Planned Update". Reaffirmed the contents of the document, and
reissued with minor revisions to adopt MAC concept for optimizing project execution cycle
and improve cost effectiveness.
Editorial revision to replace Standards Committee Chairman.
Page 15 of 19
SAEP-16
Project Execution Guide
for Process Automation Systems
PEP
(SEE SAEP-12)
PRB
COMMERCIAL
EVALUATION
PROJECT
PROPOSAL
4.1.1
FEASIBILITY
STUDY
SCOPE
DEFINITION
4.1.2
PROJECT
PROPOSAL
4.1.3
ERA
4.1.4
FSD
ER
PACKAGE
(See SAEP-1610)
(SEE SEAP-11)
DBSP
CDR
80 90%
PRB
(SEE SAEP-14)
PROJECT
CONCEPTION
PDR
30% - 50%
EPI
STUDY
BID
PERIOD
4.1.5
BID
PACKAGE
DETAIL
DESIGN
4.1.6
601 NMR
INTEGRATION
4.1.7
603 NMR
( )
BID
SLATE
602 NMR
AWARD
()
RECOMMENDATION
FORM 4535
(SEE SAEP-200)
PROCUREMENT
DOCUMENT
PAT FORM
SA-7214
FROM
ACTIVITY
4.1.7
FAT
4.1.8
INTEGRATION
TEST
4.1.9
PACKING &
SHIPPING
REPORT
FAT
REPORT
IT
4.1.10
INSTALLATION&
CHECKOUT
4.1.11
SAT
PRE-COMMISSIONING
4.1.12
MCC
4.1.13
4.1.14
START UP &
COMMISSIONING
PAT
4.1.15
4.1.16
REPORT
PACKING
LIST
SAT
COMMISSIONING
PLAN
LOOP
ACCEPTANCE
SHEETS
MCC FORM
SA-7213
LEGEND
STEP
EVENTS
DELIVERABLES
Page 16 of 19
SAEP-16
Project Execution Guide
for Process Automation Systems
601 NMRS
Saudi Aramco's approval of these preliminary documents is required prior to any
fabrications. The following list is recommended. It may be revised as necessary
B.2
601.1
601.2
601.3
601.4
Bill of Materials
601.5
601.6
601.7
601.8
601.9
601.10
601.11
601.12
Power Requirements
601.13
HVAC Requirements
601.14
601.15
601.16
602 NMRS
These certified drawings, parts data and documents should be marked as final.
The following list is recommended. It may be revised as necessary.
602.1
602.2
602.3
B.3
SAEP-16
Project Execution Guide
for Process Automation Systems
602.4
602.5
602.6
602.7
602.8
602.9
602.10
602.11
602.12
602.13
602.14
602.15
List of Special Tools, Devices, and Test Equipment Required for Installation
602.16
603 NMRS
The following list is recommended. It may be revised as necessary.
603.1
603.2
Installation Instructions
603.3
Operating Instructions
603.4
Maintenance Manuals
603.5
Page 18 of 19
SAEP-16
Project Execution Guide
for Process Automation Systems
PROBLEM
RESOLUTION
Name: ____________________________________
Date: ___________________
Telephone #: _______________________________
E-mail Address:_____________________________
Notes:
1.
PMT/OO can use this typical form or any other free formatted form to provide the above information.
2.
Page 19 of 19