Académique Documents
Professionnel Documents
Culture Documents
By
Waleed Mahfouz Mohammed Ali Youssef
By
Waleed Mahfouz Mohammed Ali Youssef
A Thesis Submitted to the
Faculty of Engineering at Cairo University
in Partial Fulfilment of the
Requirements for the Degree of
DOCTOR OF PHILOSOPHY
in
STRUCTURAL ENGINEERING
Approved by the
Examining Committee
____________________________
Prof. Dr. Osman Mohammed Osman Ramadan, Thesis Main Advisor
Professor of Structural Analysis and Mechanics
Faculty of Engineering, Cairo University
____________________________
Prof. Dr. Metwally Abdelaziz Ahmed, Internal Examiner
Professor of Structural Analysis and Mechanics
Faculty of Engineering, Cairo University
____________________________
Prof. Dr. Ibrahim Abdul Rashid Nosair, External Examiner
Professor of Construction Engineering and Management
Faculty of Engineering, Ain Shams University
ACKNOWLEDGMENTS
I would like also to express my special appreciation and thanks to my advisor Professor
Dr. Osman Ramadan, he has been a tremendous mentor for me. I would like to thank
Dr. Osman for encouraging my research and for allowing me to grow as a researcher.
Dr. Osmans advice on my research as well as on my career has been priceless.
I would like to express the deepest appreciation to Professor Dr. Karim El-Dash, for
making this research possible. His support, guidance, advice throughout the research, is
greatly appreciated. Indeed, without his guidance, I would not be able to put the topic
together. Professor Dr. El-Dash actually acted as a co-supervisor for me. However, as I was
busy on research, I did not follow-up the required paper work to add him as a co-supervisor
until it was too late. Therefore, the self-denial of Dr. Karim allowed this thesis to appear
without troubles or further delay.
( :)15
ii
DEDICATION
To The First
iii
TABLE OF CONTENTS
ACKNOWLEDGMENTS...i
DEDICATION...iii
TABLE OF CONTENTS..iv
LIST OF TABLES.....x
LIST OF FIGURES.....xiv
LIST OF SYMBOLS AND ABBREVIATIONS...xx
ABSTRACT........xxii
CHAPTER 1: INTRODUCTION....1
1.1. General..1
1.2. Problem Statement.......1
1.3. Objectives .....2
1.4. Methodology ....3
1.5. Thesis Outline ..4
iv
CHAPTER 3: METHODOLOGY........33
3.1. General....33
3.2.-Analytical Comparison of Construction Causes of Delay in the Middle
East......33
3.3. Time Scheduling Simulation Using Monte Carlo Simulation34
3.3.1. Monte Carlo Simulation Procedures for Scheduling......36
3.3.2. Objectives of Investigating Actual Durations.37
3.3.3. Evaluating Probability Distribution Patterns for Activities Durations...37
3.3.3.1. Probability Distribution Functions Utilized in Previous Studies38
3.3.3.2. Probabilistic Model for Actual Activities Durations...39
vi
vii
viii
REFERENCES....197
APPENDIX I: Example Project Illustrating Use of the Developed
Program.....211
ix
LIST OF TABLES
Table 2.1: Likelihood Rating, cited in (Cooper et al., 2005) ................................................. 24
Table 2.2: Distinct Uses of Simulation Techniques in Construction Industry ....................... 28
Table 2.3: The Common Probability Density Functions Selected for our Study ................... 32
Table 4.1: Classifications of Causes of Delay in Ghana ....................................................... 46
Table 4.2: Classifications of Causes of Delay in Asia .......................................................... 48
Table 4.3: Classifications of Causes of Delay in United Kingdom (UK) .............................. 49
Table 4.4: Classifications of Causes of Delay in Egypt ........................................................ 50
Table 4.5: Classifications of Causes of Delay in Kingdom of Saudi Arabia (KSA) .............. 52
Table 4.6: Classifications of Causes of Delay in Kuwait ...................................................... 53
Table 4.7 Classifications of Causes of Delay in Jordan ........................................................ 54
Table 4.8 Classifications of Causes of Delay in United Arab Emirates (UAE) ..................... 54
Table 4.9: Classifications of Causes of Delay in the USA .................................................... 55
Table 4.10: Suggested Classifications for Causes of Delay together with Referenced
Publications .................................................................................................... 57
Table 4.11: Causes of Delay under Design and Drawings Approval Category ..................... 58
Table 4.12: Causes of Delay under Construction Related Category ..................................... 59
Table 4.13: Causes of Delay under Contract Related Category ............................................ 59
Table 4.14: Causes of Delay under Suppliers and Sub-contractors Related Category ........... 60
Table 4.15: Causes of Delay under Financial and Economical-Related Category ................. 61
Table 4.16: Causes of Delay under Government and Regulations Related Category ......... 61
Table 4.17: Causes of Delay under Labour and Equipment Related Category ................... 62
Table-4.18: Causes of Delay under Management, Planning and Scheduling Related
Category........................................................................................................... 63
Table 4.19: Causes of Delay under Materials Related Category ........................................ 64
xi
xii
Table 6.3: The Periodical Actual Progress for Construction Activities of Different CSI
Divisions in a Single Project in Kuwait ............................................................. 171
Table 6.4: Budget per the Estimated and the Actual Durations in Kuwait Classified by CSI
Divisions ........................................................................................................... 172
Table 6.5: Regression Models, Model Constants, and r2 Coefficients for the Average Budget
of Construction Activities and the Actual Durations Classified by CSI
Divisions174
Table 7.1: Summary of Validating Regression Models on Deterministic Durations of Real
Projects in the Middle East ................................................................................ 187
Table 7.2: Summary Description of the Collected Questionnaires ..................................... 189
Table 7.3: The Effectiveness Index for Methods of Minimizing Construction Delays in the
Middle East Ranked by All Respondents ........................................................... 190
xiii
LIST OF FIGURES
Figure 2.1: Classifications of Construction Delays Based on (Al-Ghafly, 1995; Falqi,
2004)...16
Figure 2.2: Risk Management Process Comparison as cited in (Cooper et al., 2005) .......... 21
Figure 2.3: Outline of Quantitative Risk Approach, Modified from (Cooper et al., 2005) ... 26
Figure 2.4: Quantitative Analysis Risk Model Modified from (Cooper et al., 2005) ........ 26
Figure 2.5: Modelling and Simulation Processes, cited in (Oberkampf et al., 2000) ........... 30
Figure 3.1: General Monte Carlo Simulation Technique [Modified from (Youssef, 2005)] 36
Figure 3.2: True Regression Model for Scattered Data of (x,y) .......................................... 42
Figure 3.3: Comparing with the Residual as cited in (Walpole et al., 2012) .................... 43
Figure 4.1: Comparison among All Categories for Causes of Delay in Africa Average of
Nine Studies ...................................................................................................... 74
Figure 4.2: Comparison among Responsibilities for Causes of Delay in Africa Average of
Nine Studies ...................................................................................................... 75
Figure 4.3: Comparison among All Categories for Causes of Delay in Asia Average of
Nineteen Studies ................................................................................................ 76
Figure 4.4: Comparison among Responsibilities for Causes of Delay in Asia Average of
Nineteen Studies ................................................................................................ 76
Figure 4.5: Comparison among All Categories for Causes of Delay in Europe Average of
Two Studies ....................................................................................................... 77
Figure 4.6: Comparison among Responsibilities for Causes of Delay in Europe Average of
Two Studies ...................................................................................................... 78
Figure 4.7: Comparison among All Categories for Causes of Delay in the USA ................. 79
Figure 4.8: Comparison among Responsibilities for Causes of Delay in the USA............... 79
Figure 4.9: Comparison among All Categories for Causes of Delay in the Middle East
Countries Average of 31 Studies ...................................................................... 80
xiv
Figure 4.10: Comparison among Responsibilities for Causes of Delay in the Middle East
Countries Average of 31 Studies ..................................................................... 81
Figure 4.11: Comparison among All Categories for Causes of Delay in the Middle East
Countries: a) Egypt, b) KSA, and c) Kuwait....................................................... 82
Figure 4.12: Comparison among Responsibilities for Causes of Delay in the Middle East
Countries: a) Egypt, b) KSA, and c) Kuwait....................................................... 83
Figure 4.13: The Delayed Activities Percentages for Construction and Engineering Procurement Classified by Cases of Delay from Planned Dates: (1) Behind Early
Start, (2) Behind Late Start, (3) Behind Early Finish, (4) Behind Late Finish, and
(5) Greater Than the Estimated Duration ............................................................ 86
Figure 4.14: Relationship between the Actual Durations Percentiles (among 1271 Buildings
Construction)
and
the
Absolute
Maximum
Durationsof
the
Selected
Activities97
Figure 4.15: Percentage of Affected Number of Activities for each Risk .......................... 105
Figure 4.16: Percentage of Risk Contribution of the Total Delay of the Seven Activities in
a Single Housing Project in Kuwait.................................................................. 105
Figure 4.17: Relationship between the Delays Percentiles to the Maximum Delay (DPM) of
the Seven Activities Due to Different Risks ..................................................... 106
Figure 4.18: Risks Contribution of Delay for the Selected Seven Activities in a Single
Housing Project in Kuwait: a) Civil Works, and b) Electro-mechanical
Works...109
Figure 5.1: Case Studies of Evaluating the Best Probability Density Function to Represent
Activities in Construction Projects ................................................................... 114
Figure 5.2: Probability Density Function PDF and Curve Fitting for Construction Activities
Durations
for
All
Projects:
a)
Estimated
Durations,
and
b)
Actual
Durations..116
Figure 5.3 Probability Density Function PDF and Curve Fitting for Engineering Procurement Activities Durations for All Projects: a) Estimated Durations, and
b) Actual Durations.......................................................................................... 117
xv
Figure 5.4: Probability Density Function PDF and Curve Fitting for All Construction and
Engineering - Procurement Activities Durations for All Projects: a) Estimated
Durations, and b) Actual Durations .................................................................. 118
Figure 5.5: Probability Density Function PDF and Curve Fitting for Division (03 - Concrete
Works) Activities Durations for All Projects: a) Estimated Durations, and
b) Actual Durations.......................................................................................... 122
Figure 5.6: Probability Density Function PDF and Curve Fitting for Division (09 - Finishes
Works) Activities for All Projects: a) Estimated Durations, and b) Actual
Durations ......................................................................................................... 123
Figure 5.7: Probability Density Function PDF and Curve Fitting for Division (15 Mechanical Works) Activities for All Projects: a) Estimated Durations, and
b) Actual Durations.......................................................................................... 124
Figure 5.8: Probability Density Function PDF and Curve Fitting for Division (16 - Electrical
Works) Activities for All Projects: a) Estimated Durations, and b) Actual
Durations ......................................................................................................... 125
Figure 5.9: Probability Density Function PDF and Curve Fitting for Division (02 - Site
Works) Activities Actual Durations for One Project: a) Excavation up to
Foundation, and b) Backfill till Ground Beams ................................................ 129
Figure 5.10: Probability Density Function and Curve Fitting for Division (03 - Concrete
Works) Activities Actual Durations for One Project: a) Isolated Footings, and
b) Casting of Ground Beams ............................................................................ 130
Figure 5.11: Probability Density Function and Curve Fitting for Division (07 - Thermal and
Moisture Protection Works) Activities Actual Durations for One Project:
a) Bituminous Paint to Surfaces, and b) WP for Wet Areas .............................. 131
Figure 5.12: Probability Density Function and Curve Fitting for Division (08 - Doors and
Windows Works) Activities Actual Durations for One Project: a) Frames for
Doors and Windows, and b) Wooden Doors..................................................... 132
Figure 5.13: Probability Density Function and Curve Fitting for Division (09 - Finishes
Works) Activities Actual Durations for One Project: a) External Facade Works,
and b) Ceramic Tiles - Walls and Floors .......................................................... 133
xvi
Figure 5.14: Probability Density Function and Curve Fitting for Division (15 - Mechanical
Works) Activities Actual Durations for One Project: a) External Manhole and
Drainage, and b) Water Supply Pipes .............................................................. 134
Figure 5.15: Probability Density Function and Curve Fitting for Division (16 - Electrical
Works) Activities Actual Durations for One Project: a) Electrical Pipes for Walls,
and b) Pulling Electrical Wiring ....................................................................... 135
Figure 6.1: Cases of Analysis of Regression Models for the Estimated Durations or Budgets
and the Actual Durations in Construction Projects ........................................... 139
Figure 6.2: Regression Models for Estimated Durations of Construction Activities in the
Three Countries and Actual Durations Statistics: a) Mean, and b) Standard
Deviation ......................................................................................................... 143
Figure 6.3: Regression Models for Estimated Durations of Construction Activities in Egypt
and Actual Durations Statistics: a) Mean, and b) Standard Deviation .............. 145
Figure 6.4: Regression Models for Estimated Durations of Construction Activities in Kuwait
and Actual Durations Statistics: a) Mean, and b) Standard Deviation .............. 146
Figure 6.5: Regression Models for Estimated Durations of Construction Activities in KSA
and Actual Durations Statistics: a) Mean, and b) Standard Deviation .............. 148
Figure 6.6: Regression Models for Estimated Durations of (Engineering-Procurement
Activities) Three Countries and Actual Durations Statistics: a) Mean, and
b) Standard Deviation ...................................................................................... 149
Figure 6.7: Regression Models for Actual Durations of Critical Activities in the Three
Countries Grouped by Phase of Work: a) All Phases, b) Construction; and
c) Engineering Procurement .......................................................................... 151
Figure 6.8: Regression Model for Estimated Durations for Construction Activities in All
Projects in Kuwait under Division (02 Site Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation ................................................. 153
Figure 6.9: Regression Model for Estimated Durations for Construction Activities in All
Projects in Kuwait under Division (03 Concrete Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation ................................................. 154
xvii
Figure 6.10: Regression Models for Estimated Durations of Construction Activities in All
Projects in Kuwait under Division (04 Masonry Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation ................................................. 156
Figure 6.11: Regression Models for Estimated Durations of Construction Activities in All
Projects in Kuwait under Division (08 Doors and Windows Works) and Actual
Durations Statistics: a) Mean, and b) Standard Deviation ................................ 157
Figure 6.12: Regression Models for Estimated Durations of Construction Activities in All
Projects in Kuwait under Division (09 Finishes Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation ................................................. 158
Figure 6.13: Regression Models for Estimated Durations of Construction Activities in All
Projects in Kuwait under Division (15 Mechanical Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation ................................................. 160
Figure 6.14: Regression Models for Estimated Durations of Construction Activities in All
Projects in Kuwait under Division (16 Electrical Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation ................................................. 161
Figure 6.15: Regression Models for Estimated Durations of All Construction Activities in
a Single Project in Kuwait and Actual Durations Statistics: a) Mean, and
b) Standard Deviation ...................................................................................... 163
Figure 6.16: Regression Models for Estimated Durations of Construction Activities in
a Single Project in Kuwait under Division (02 Site Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation ................................................. 165
Figure 6.17: Regression Models for Estimated Durations of Construction Activities in
a Single Project in Kuwait under Division (03 Concrete Works) and Actual
Durations Statistics: a) Mean, and b) Standard Deviation ................................ 166
Figure 6.18: Regression Models for Estimated Durations of Construction Activities in
a Single Project in Kuwait under Division (15 Mechanical Works) and Actual
Durations Statistics: a) Mean, and b) Standard Deviation ................................ 167
Figure 6.19: Relationship between the Total Float and the Increment in Ratio of Mean
Actual Duration to Estimated Duration ............................................................ 169
Figure 6.20: The Actual Periodical Progress for Construction Activities in Different CSI
Divisions in a Single Project in Kuwait ............................................................ 170
xviii
Figure 6.21: Relationship between Activities Average Budget (1000 KD) and the Mean
Values of the Actual Durations ........................................................................ 173
Figure 6.22: Regression Models for the Relationship between Construction Activities
Budgets and Actual Durations in Kuwait Classified by CSI Divisions: a) Division
02, b) Division 03, c) Division 09, d) Division 15, and e) Division 16 .............. 177
Figure 7.1: Data Entry Interfaces for Researches and Risks Data ..................................... 179
Figure 7.2: Data Entry Interfaces for Projects and Activities ............................................ 180
Figure 7.3: Example for a Report of Risks Assigned to Activities .................................... 180
Figure 7.4: Example for a Report of Risks Contribution in the Overall Values of Projects
Risks ................................................................................................................ 181
Figure 7.5: Flowchart for Overall Simulation and Scheduling Process ............................. 183
Figure 7.6: Flowchart for Detailed Process of Simulation and Scheduling Using Microsoft
Project Software .............................................................................................. 184
Figure 7.7: Sample of Graphical Analysis and Curve Fitting by Automating MATLAB
Software .......................................................................................................... 185
xix
Actual Duration
AER
AHP
AOA
Activity On Arrow
CASs
CIB
COV
Coefficient of Variation
CPM
CSI
Division
ED
Estimated Duration
EF
Early Finish
EGP
Egyptian Pound
ENR
Engineering News-Record
EPC
ES
Early Start
FDL
Foundation Level
GDP
HVAC
KD
Kuwaiti Dinar
KSA
LC
Letter of Credits
LF
Late Finish
LS
Late Start
xx
MAD
MAR
Max
Maximum
MCS
MDMSMs
MER
Min
Minimum
MS
Microsoft
N/A
Not Applicable
PDM
PERT
PMR
RD
Duration Ratio
SPSS
SSE
SST
Std. Dev.
Standard Deviation
SWOT
TF
Total Float
UAE
UK
United Kingdom
USD
Ver.
Version
WP
Water Proof
xxi
ABSTRACT
The construction project management is about quality, timely, and costly managing
construction inputs and outputs. However, its achievement continues to present a major
challenge to most large construction projects all over the world due to the high degrees of
complexity and variability. For instance, delivery of construction projects has been adversely
influenced by several drastic risks. A major and critical concern in the time scheduling
process is the accurate determination of activities durations. This calls for
xxii
addition, the study developed predictive regression models to estimate the statistics of
activities durations. Finally, a special program that uses the concluded PDF and regression
models to predict the projects overall durations at different levels of confidence was
developed.
It is found that the three most influencing risks on the time performance of construction
activities in Kuwait are: (1) inadequate planning and time scheduling; (2) slow financial and
payment procedures; and (3) fluctuation of productivity levels. In addition, it is found that the
best PDF to represent activities in construction projects is the lognormal distribution, while
the second best PDF is the gamma distribution. Besides, it is shown that the normal
distribution has the lowest level of confidence. Furthermore, it is found that as the estimated
duration decreases, the relative duration slippage increases. The ratio of the highest, actual
activity duration to the corresponding mean duration is always more than 4 for projects in the
Middle East, which differs from that suggested in previous studies (1.25). As a general rule,
the forecasted projects overall duration- based on the proposed regression models and
utilizing lognormal distribution- tends to be greater than that calculated using conventionally
estimated activities. Nevertheless, validation tests showed that the forecasted projects
durations are good estimates of the real ones. Consequently, these forecasted projects
durations could oblige contractors to implement different methodologies and alternative plans
to reduce the projects duration.
xxiii
CHAPTER 1: INTRODUCTION
1.1. General
The construction industry is the key motivator for any economy. The success of
construction industry is indispensable to sustain strong national economies. In addition, the
construction management and construction planning are still inefficient of achieving their
objectives, in spite of the considerable resources and technologies allocated to the planning
and management functions. The conventional techniques of estimating activitys duration and
time scheduling have been proved themselves as unreliable techniques in front of the growing
challenges of construction projects. Therefore, simulation techniques have been utilized to
provide reliable solutions for scheduling the risky construction projects.
This study aims to extend the body of knowledge required for the development of more
reliable models for predicting the execution time of construction projects in the Middle East
area. These time prediction models include: (1) the evaluation of the best probability density
function for activities durations, and (2) the development of reliable regression models for the
relationship between the conventionally estimated durations and the statistics of the actual
durations. These predictive models could assist in constructing a more reliable simulation of
the scheduling process that deduces projects durations efficiently and reliably.
This chapter outlines: the problem statement, the objectives of the study, methodology
and incorporate an outline of the structure of the thesis.
and dynamic nature. In addition, the construction projects delivery has been adversely
influenced by several numbers of colossal drastic risks.
Time scheduling is the backbone for the construction projects planning, controlling, and
success. The major and the critical concern in time scheduling is the determination of
activities durations. It is widely accepted by construction managers and planning practitioners
that the more accurate the activity duration is the more efficient planning and scheduling will
be. In addition, the traditional estimation of activities durations used in Critical Path Method
(CPM) technique depends on a unique duration value for each activity. This unique duration
value resulted from the productivity rates of all resources assigned to each activity. Lana
(2006) outlined that using this estimation approach does not guarantee that the project will be
finished on time. Therefore, the development achieved by Program Evaluation and Review
Technique (PERT) was to use three point estimates for the duration of each activity. Both
techniques and all other traditional techniques ignored the effects of the potential risks that
the construction project may face. This made the traditional scheduling technique stands
powerless in front of the accelerated degrees of uncertainty and risks that the construction
projects may be exposed to. That may expose the involved parties in the construction
industries to unexpectedly immense losses. Moreover, numerous expected scenarios for
completing the project, however project managers and planners do not know anything about
the probability of each scenario. Consequently, simulation is considered the best method till
now to determine most scenarios in which it is possible to trace the stochastic critical paths of
activities in the construction projects (Lana, 2006).
There is an exigent need for a comprehensive study of the potential construction risks
(types, statistical characteristics, behaviour, representation and their impacts on construction
activities) and incorporating the development of models and algorithms for construction
projects scheduling optimization. These models should be reliable and unimpeachable for real
world uncertainties and risks. Generally, these models should consider the risky, complex and
the stochastic nature of the scheduling process, and to be adaptable and applicable to real
problems with different sizes.
1.3. Objectives
The thesis is preformed to accomplish four objectives:
1. To define, study and quantify the impacts of potential risks on the performance of
activities of large-scale construction projects in the Middle East especially Egypt
1.4. Methodology
To achieve the research objectives, the following methodology will be followed:
Conduct a comprehensive literature review of the causes of delay all over the
world.
Develop an analysis procedure for calculating the impact of risks on the time
performance of activities in Kuwait
Study the existing estimation techniques for projects and activities durations.
Study the statistical properties of the actual and the estimated durations of
activities in construction projects. The study will classify the analysis according
to the type of work, the CSI divisions, and the country of the project.
Develop regression models to describe the relationship between the mean values
of the actual durations and the budgets of activities.
Present a case study for a computer prototype in order to validate the results of
the developed methods.
the risk loaded detailed time schedule, extracts the statistical properties of activities duration
from predictive regression models, automates the simulation of time scheduling process,
predicts the projects overall duration according to the required confidence level, and
validates the application of the suggested PDF and regression models in compare with real
projects in the Middle East countries. Furthermore, chapter 7 presents the preparation of
a questionnaire that helps in identifying and exploring the practical solutions that can be
applied to reduce the delays of construction projects in the Middle East countries.
Chapter 8 summarizes the analysis, results, and conclusions presented in earlier chapters
and recommends for future studies.
2.2.1.
The International Council for Research and Innovation in Building and Construction
(CIB) estimates that a dollar spent on construction may generate up to three dollars of
economic activity in other sectors (Kohler and Moffatt, 2003). Besides, the budgets of
construction industry are approximately 3.4 trillion (3400 billion) USD yearly, or about 10%
of the (GDP) in both developing and developed countries. Meanwhile, Construction industry
powerfully contributes over 50% of the National Capital Investment. Furthermore, it provides
around 7% of world employment that represents about 28% of the total industrial
employment (Kohler and Moffatt, 2003).
On the first hand, the construction industry in the developed countries such as the United
States of America (USA) and Canada, contributes approximately 12% of Gross Domestic
Product (GDP). Besides, the construction industry contributes about 8% of the GDP in the
United Kingdom (UK) and about 10-11% of the GDP in all other European countries.
Moreover, the construction industry employs about two million people in UK and 1.2 million
in Canada that represents about 6% of the total Canadian employment (Falqi, 2004; Moosavi,
2012).
On the other hand, a significant concern has been directed to the construction industry in
developing countries such as the Middle East countries for the last four decades. The
spending in the construction sector in Egypt was estimated to increase about 46% between
2005 and 2015 (Global Insight, 2010). In United Arab Emirates (UAE), and Palestine, the
construction sector contributes about 14% and 33% of the (GDP) respectively (Faridi and ElSayegh, 2006; Enshassi and Abu Mosa, 2008).
2.2.2.
The construction industry contributes powerfully in the national economic and supports
a large number of ancillary industries and activities (Bonke and Olsen, 2010). A single
building may comprise over 60 basic materials and around 2000separate products, each with
its own lifetime and unique production/repair/disposal processes (Kohler and Moffatt, 2003).
The major participants in construction industry include architects, engineers, management
consultants, general contractors, heavy construction contractors, special trade contractors or
subcontractors, and construction workers, along with the owners, operators, and users of the
constructed facilities. The success of construction projects is very important for all project
participants as well as the community and the nation to sustain national development (Majid,
2006).
2.2.3.
Construction projects are unique, complex in nature and inherently include widespread
and diverse types of uncertainties and risks. The inherent uncertainties are generally not only
from the unique nature of the project, but also from the diversity of activities and their
resources (Guo, 2004). Although the key objectives of construction projects are time, cost,
and quality, these objectives are jeopardized by delays. In addition, Completion time is
extremely important in construction: "Time is of the Essence", and "Time is Money" (AlGhafly, 1995). Therefore, delays may lead to disruption of work, loss of productivity, late
completion of project, increased additional time related costs, claims, non-completion of the
work or even termination of contract (Majid, 2006). Moreover, the effects of construction
delays are not only confined to the construction industry, but also extend to other industries
and consequently influence the overall economy of a country (Faridi and El-Sayegh, 2006).
For these reasons, the performance of construction projects has been thoroughly investigated
by my researchers in both developing and developed countries.
In a study carried out by the World Bank on 1627 projects completed worldwide between
1974 and 1988, the major conclusion was that 90% of construction projects were delivered
late with a cost overrun varied between 50% and 80% (Menesi, 2007). Morris (1994)
undertook a study in the early 1980s, in which he examined 1449 separate construction
projects, and found that only 12 were delivered within budget.
On the first hand, there are multitudes of researches that investigate the construction
performance in developed countries. In the United Kingdom, a survey carried out by the
National Audit Office reported that 70% of the projects undertaken by government
departments and agencies were delivered late during 2001 (Falqi, 2004; Menesi, 2007).
Flyvbjerg et al.(2003) studied 258 projects in Denmark including 58 rail projects, 33 bridges
and tunnels projects, and 167 road projects in 20 different nations. The results showed that in
terms of costs, the transportation and infrastructure projects do not perform as planned. The
final conclusion was that approximately 90% of the total transportation and infrastructure
projects had fallen victim to time and cost overruns.
On the other hand, many investigations on the performance of construction projects in
the developing countries have been carried out. Al-Sultan (1989) surveyed the actual
performance of different types of public projects in Kingdom of Saudi Arabia (KSA) and
concluded that approximately 70% of the public projects (101 out of 145) had time overrun.
Al-Ghafly (1995) studied the delay in twenty of construction projects and found that the
average time extension for these projects was about 110% of the original projects duration.
In the United Arab Emirates (UAE), Faridi and El-Sayegh (2006) found that 50% of
construction projects encounter delays. In India, a study conducted by the Infrastructure and
Project Monitoring Division of the Ministry of Statistics and Program Implementation in
2004 reported that out of 646 central sector projects costing about $50 trillion, approximately
40% are behind schedule (Lyer and Jha, 2006). A research by Building Cost Information
Service (BCIS) found that nearly 40% of all studied projects had overrun the contract period
(Menesi, 2007). Al-Ghafly (1995) found that the small projects that had durations of 12
months and less had experienced severe delay (143%), while the average of extension of time
granted to large and medium projects was about 30.61 % to 42.97% of the original duration.
Al-Ghafly (1995) reported that only 65% of all cases that requested time extensions were
approved for the contractors.
It is worth mentioning that the performance of construction projects showed a gradual
decline, according to the published database with the 10th annual review by the World Bank.
This gradual decline in performance was attributed to the increased levels of risks and
uncertainty for construction projects. In addition, the declined performance caused cost
overruns up to 560% of their budgets, and average time overrun of about 61% of their
contractual durations (Panthi, 2007). Furthermore, Omoregie and Radford (2006) showed in
his survey that the mean percentage of time escalation for construction projects in Nigeria
was approximately 188% of the contractual durations. In general, the recorded workflow
reliability for construction projects ranges between 30 and 60% (Ballard, 1999).
10
management and administrative risks, and code related risks as elaborately explicated in
(Al-Khalil and Al-Ghafly, 1999; Ahmed et al., 2002; Odeh and Battaineh, 2002; Alwi and
Hampson, 2003; Falqi, 2004; Majid, 2006; Sambasivan and Soon, 2007; El-Sayegh, 2008;
Al-Kharashi and Skitmore, 2009; Fugar and Agyakwah-Baah, 2010). Therefore, the most
important function of project management is to foresee problems well in advance and
determine solutions before they arise (Mojahed, 2005).
2.3.1.
construction firms and projects managers to exert more effort in managing budget, time, and
productivity. For these reasons, the planning and scheduling appear as powerful and crucial
tasks for the completion of construction projects successfully (Wu and Soibelman, 2006).
The importance of planning has been investigated and surveyed recently by many
researchers. (Laufer & Tucker, 1987) studied the importance of implementing planning in
construction projects and concluded that the construction planning effectiveness could be
improved by enhancing the qualifications, orientations, and motivation of the parties involved
in the project. Callahan et al. (1992) reported through three surveys with the participation of
1741 construction industry participants (contractors, designers, subcontractors, construction
managers, and owners) that over half of the respondents considered the most threatening
factors to construction industry are poor planning, poor scheduling and poor contract
administration. Construction planning and scheduling provides the means to plan and manage
a construction project effectively (Prateapusanond, 2003). However, failure to manage time
properly could result in both schedule slippage and cost overruns. Therefore, tools and
techniques of control are vital to the completion of a construction project on time and within
budget. Wu and Soibelman (2006) attributed the poor quality of the planning and scheduling
to novices or junior planners who either learn planning from their experienced peers or
seniors, or accumulate their own knowledge by trials and errors. Such practices are therefore
error-prone, risk-motivator and time-consuming.
11
2.3.2.
Scheduling is the process of determining the timing and sequence of operations in the
project and their assembly to give the overall completion time (Al-Ghafly, 1995; PMI.,
2012). Time scheduling is undoubtedly the backbone for the construction projects planning,
monitoring, controlling, and success. Besides, Prateapusanond (2003) outlined the
importance of scheduling as it helps to: predict the completion time of the project and the
task, control financing, serve as a record, satisfy a contractual requirement, communicate the
construction plan, manage change and uncertainty, and support delay claims.
Projects managers and planners used many scheduling techniques ranging from simple
bar charts to sophisticated networks. The popular scheduling techniques include Critical Path
Method (CPM), Precedence Diagramming Method (PDM), and Program Evaluation and
Review Technique (PERT). However, the most widely used technique is the CPM, as
outlined by Kelleher (2004). Kelleher (2004) illustrated that, the implementation of the CPM
technique has increased among the top 400 contractors ranked by Engineering News-Record
(ENR) from 90% in 1974 to 98% in 2003. Meanwhile, the usage of CPM in estimation and
bidding has jumped from 19% to 54%. Furthermore, Kelleher(2004) manifested that about
75% of turnkey firms (architects, engineers and contractors) use CPM Software to plan,
schedule, monitor, control and forensic analyse delay.
The major and critical concern associated with the time scheduling process is the
determination of activities durations. The more accurate the activity duration is the more
efficient planning and scheduling will be. The conventional estimation techniques for
activities durations used in Critical Path Method (CPM) depend on a single value resulted
from the average productivity rates for all resources assigned to the activity. Most of the time
using this approach does not guarantee that the project will be completed on time
(Mulholland and Christian, 1999; Lana, 2006). The development accomplished by Program
Evaluation and Review Technique (PERT) was to use three point estimates instead of one
estimate for each activitys duration. Both CPM and PERT techniques and all other classic
techniques dont accurately consider the effects of the potential risks that the construction
project may encounter. Therefore, the traditional scheduling techniques could be considered
powerless in front of hasty degrees of uncertainties, variability and risks that the construction
projects are often exposed to (Mulholland and Christian, 1999). Consequently, the involved
parties in the construction industries might inevitably be jeopardized to unexpectedly
immense losses.
12
2.4.1.
The projects estimated duration is often based on the owners feasibility study irrelevant
to the construction plan or construction methodology. Consequently, the estimated duration
of the project is often not reliable and hence represents a significant threat during the
execution. Therefore, the estimation of realistic project duration can be considered the prime
parameter towards reducing the probability of delay and consequently decreasing the
expected disputes between owners and contractors. Significantly, the prediction of projects
overall duration constitutes a continual concern for construction researchers and project
managers. The techniques used for estimating projects overall fair duration has been outlined
in many studies and considered various input parameters such as: degree of complexity,
scope of work, area for project, number of levels, function of building, client type,
procurement rout, market constraints or opportunities and start date for the project (Bustani
and Izam, 1999; Ng et al., 2001; Chan and Kumaraswamy, 2002; Chehade, 2005; Ogunsemi
and Jagboro, 2006; Martin et al., 2006; Strong et al., 2007; Odabai, 2009; Choudhury, 2012).
Bromilow (Ogunsemi and Jagboro, 2006) developed a model to predict project duration
based on project time-budget relationship in 1974 through investigation of 370 building
projects in Australia. Another model was developed by Al-Momani (2000). He used real data
13
to develop different quantitative regression models to estimate the projects duration and
price. The sample consisted of 130 public projects in Jordan between 1990 and 1997. The
third model was developed by Martin et al. (2006) through surveying the performance of
2554 distinct building projects in the UK between 1998 and 2004. Martin et al. (2006)
produced a linear regression model for project duration according to building function
classification. The fourth model was developed by Abu Hammad et al. (2008). They
investigated real data for a sample of 140 construction projects in Jordan between 1994 and
2002 to develop regression models that predict projects cost and time. Abu Hammad et al.
(2010) developed the fourth model through focusing the study on 113 public projects in
Jordan between 1994 and 2002. They derived the multiple regression models to predict the
project cost and duration depending on the scope, the area, the estimated budget, and the
estimated duration of the project.
2.4.2.
The second parameter in reducing the probability of construction delay is the proper
estimation of activities duration. The duration estimate depends on many factors including,
construction execution methodology, resource availability, work quantity, nature, complexity
of work, labour and equipment productivity, quality of field management, weather changes,
site conditions and concurrent activities (Prateapusanond, 2003; Aliabadizadeh, 2009). It is
logically believed that the more activities durations are reliable the more accurate the project
completion time will be. However, (Willis, 1986; Callahan et al. 1992) pointed out that
activity durations are estimated, and that it is not essential for these estimates to be
consistently exact. In like manner, if all durations are reasonable, variations in activity
durations will compensate each other, resulting in reasonably accurate project duration. On
the contrary, (Prateapusanond, 2003) suggested that the accuracy in estimating activitys
duration should not be overemphasized because doing so could complicate the estimation
process of the reliable duration.
The estimation of construction activitys duration can be classified as deterministic and
stochastic depending on the projects nature, potential risks, productivity rates, available
resources, site conditions, site location, project environment, levels of complexity, levels of
quality, expert judgment, and degrees of uncertainty (Hendrickson et al., 1987; Harmelink
and Bernal, 1998; Cheng and Wu, 2006; PMI., 2012). The non-materialized parameters such
as uncertainty levels and potential risks are incorporated as a contingency percentage (PMI.,
14
2012). On the other hand, the stochastic estimation techniques or simulation techniques are
utilized to appraise and quantify the impact of uncertainty and potential risks on activitys
duration (Zhang et al., 2005; Cheng and Wu, 2006; Biruk and Jaskowski, 2010; Csbfalvi,
2012).
On the other hand, the critical path in the schedule is the longest path(s) of connected
critical activities through the project. Therefore, any change whether it involves reduction or
prolongation in the durations of those activities can affect the projects overall duration. The
paths that were originally critical may later become non-critical and vice versa. The only
available way till now to capture the uncertainty in the estimation or other risks that may
affect the total completion time is through creating dynamic models. The dynamic models
simulate most of possible scenarios depending on the probability distribution function
assigned to each activity in the project (Lana, 2006). It is worth mentioning that the dynamic
nature of the CPM process allows planners and schedulers to react with potential events and
predict the risk and uncertainty impacts on projects overall duration at any given point of
time (Prateapusanond, 2003).
2.4.3.
Construction Delays
Delay is a relative term in construction and it means the time overrun either beyond the
completion date specified in the contract for the delivery of a part of the project or the whole
project (Al-Ghafly, 1995; Prateapusanond, 2003; bin Yusof et al., 2007; Kaliba et al., 2009).
Furthermore, delay of construction activities can be defined as the late completion of works
as compared to the planned schedule or contract schedule (Ahmed et al., 2002; Majid, 2006;
Fugar and Agyakwah-Baah, 2010).The consequences of time overruns are always serious and
hard to resolve. Failure to meet contractual deadlines represents financial losses and more
often has a negative impact on the project profitability for the involved parties (Braimah,
2008; Kelleher, 2004). However, understanding the causes of delay may help to curb the
problem and contribute in reducing the delay and their impacts (Majid, 2006; bin Yusof et al.,
2007; Tumi et al., 2009).
It is worth noting that, when the project duration is tight and / or the contractor expects
more risks in the project; the contractor takes into consideration additional increase in the bid
to cover any loss that may occur. The later increase is not required in most cases.
Nevertheless, the contractor loses the incentive to improve project performance, when he fails
to recover the delayed period. Consequently, the delayed period will be increased
15
progressively to unrecoverable limits (Al-Ghafly, 1995; Ahmed et al., 2002; Falqi, 2004). In
addition, construction projects have tended recently to become more time constrained, and
the ability to deliver the project in its original duration is becoming an increasingly important
element in winning a bid.
Moreover, the government authorities in the Middle East are obliged to accept the lowest
bid. This situation sometime brings unqualified contractors that may have a shortage in
resources or capabilities, which may lead to poor performance, and consequently could cause
a delay in completing the project (Al-Ghafly, 1995). Therefore, studying construction delays
and potential risks becomes an exigent requirement in order to control the estimated fair time
for the projects overall duration. The fair projects overall duration enables contractors to
prepare their construction strategy and methodology effectively and meticulously.
2.4.3.1.
Concurrent
Independent
Excusable
Non-Compensable
Non-Excusable
Non-Critical
Critical
Compensable
16
2.4.3.2.
Excusable or non-excusable delays are based on the source of the causes. The main
principle for establishing whether a delay is either excusable or non-excusable is the
contractors liability for the delay (Prateapusanond, 2003 ; bin Yusof et al., 2007; Braimah,
2008). Delays resulting from the fault or negligence in the control of the main contractor or
his subcontractors, suppliers, or any party working on behalf of the contractor, all these
causes of delay are non-excusable (Kaliba et al., 2009; Olupolola et al., 2010). Therefore, the
contractor is not entitled to any time extension for the project. While, the causes of excusable
delays are those which do not result from the contractors obligations according to the
contract (Abdul-Malak et al., 2002). The basis of this should be taken from applicable
contract provisions and conditions of contract clauses (Ponce de Leon, 1987; Callahan et al.,
1992; Al-Ghafly, 1995; Majid, 2006).
2.4.3.3.
Delays can be classified according to their occurrence into two types: independent and
concurrent delays (Prateapusanond, 2003; Braimah, 2008). An independent delay is a delay,
which occurs as a result of causes related to one type of delays or one of the contracts
parties, either the contractor or the owner. This could be a non-excusable or excusable,
compensable or non-compensable delay. The concurrent delays are two or more independent
delays, which occur at the same time as a result of different causes that could be excusable or
non-excusable, compensable and / or non-compensable (Ponce de Leon, 1987; Al-Ghafly,
1995; Falqi, 2004).
2.4.3.4.
Delay could occur at any time during the construction duration of the project. The causes
of this delay could affect any of the projects activities on a critical or noncritical path in the
project time schedule (Prateapusanond, 2003; Braimah, 2008). Delays that result in extended
project completion times are known as critical delays. However, Non-critical delays are
those, which incurred off the critical path and do not delay the projects contractual
completion date (Ponce de Leon, 1987; Callahan et al., 1992; Al-Ghafly, 1995; Falqi, 2004).
17
18
In general, the predominant factor of all risks definitions is uncertainty. Some authors
considered risk and uncertainty as two similar and synonymous terms. Nevertheless,
(Al Salman, 2004) considered risk and uncertainty are two different terms meaning
completely different issues. Yoe (2009) concluded that all risks are uncertain, however not all
uncertainty is risky. In addition, certainty exists only when the decision maker can specify
exactly what will happen during the period of time covered by the decision. This type of
confidence is rarely occurring in a complex industry like construction.
19
individual risks relative to the other risks to support priority setting, focusing on major risks
and resource allocation; (4) strategies and decision making for Controlling the uncertain
aspects of construction projects and for treating the risks to Minimize potential damage, and
enhance potential opportunities; and (5) the process itself and the risk treatment strategies are
implemented effectively (Walewski and Gibson, 2003; Al Salman, 2004; Cooper et al., 2005;
Dikmen et al., 2008). In general, many different processes included in risk management and
developed by many government agencies, professional project management associations or
through many relevant standards as shown in Figure (2.2). (Guo, 2004; PMI., 2012) have
outlined six processes for the project risk management that include; (1) planning risk
management; (2) identifying risks; (3) performing qualitative risk analysis; (4) performing
quantitative risk analysis; (5) planning risk responses; and (6) monitoring and controlling
risks. As shown in Figure (2.2) the risk management processes can change from agency to
agency, but the main content and concept remain the same.
20
Figure 2.2: Risk Management Process Comparison as cited in (Cooper et al., 2005)
21
2.6.1.
It is the process of defining how to conduct risk management activities for a project
(Walewski and Gibson, 2003). It is concerned with developing a structure for the risk
identification and assessment tasks. In addition, planning risk management processes is
important to ensure that the degree, type and visibility of risk management are commensurate
with both the risks and the importance of the project to the organization (Cleland, 2004;
Dikmen et al., 2008). Planning is also important to provide sufficient resources and time for
risk management activities. The risk management plan describes how risk management will
be structured and performed on the project (Cooper et al., 2005; PMI., 2012).
2.6.2.
Identifying Risks
One of the major steps in project risk management is to determine and identify the
potential risks in the project (Dikmen et al., 2008). Every project normally involves different
degrees of risk; and yet, most project managers are ill prepared when it comes to identifying
or adequately addressing potential risks (Mulholland and Christian, 1999; Walewski and
Gibson, 2003; El-Sayegh, 2008). Identifying risk process is the process of determining which
risks may affect the project or the project objectives and documenting their characteristics.
(Al-Bahar and Crandall, 1990; Dikmen et al., 2008) defined the risk identification process as
the process of systematically and continually identifying, categorizing, and assessing the
initial significance of risks associated with a construction project. In addition, all involved
parties in construction projects should consider that the risks that havent been included or
identified cannot be studied and assessed, which leads to minimizing the projects probability
of success. Therefore, the process of risk identification should be extensive and iterative
(Mulholland and Christian, 1999).
Furthermore, many techniques can be used for risk identification, but brainstorming is
more preferred method because of its flexibility and capability of generating a wide and
diverse range of risks (Mulholland and Christian, 1999; Walewski and Gibson, 2003). The
other risk identification and information gathering techniques include; Delphi techniques,
interviewing and focus group discussions, survey and questionnaires, examination of
previous projects, scenario analysis, expert judgment, Work Breakdown Structure, and root
cause analysis, in addition to Strength, Weakness, Opportunities, and Threats (SWOT)
techniques (Cooper et al., 2005; PMI., 2012)).
22
2.6.3.
Risk assessment is the systematic process of quantifying and describing the nature,
likelihood and magnitude of risk associated with some substance, situation, action or event,
including consideration of relevant uncertainties (Cleland, 2004). Yoe (2009) defined the risk
analysis as the process of separating the whole of risk into its component parts by assessment
of the risk and related uncertainties for the purpose of efficacious management of the risk,
facilitated by effective communication about the risks. The objectives of risk analysis in any
field are to determine the probability of failure of a system to meet a predetermined level of
performance during a given period, to improve the decision-making process within projects,
and to help organizations to reduce risk exposure (Cleland, 2004; Guo, 2004).
Probability is an explicit way of dealing with uncertainty. It is a device that permits the
management to incorporate all the available information concerning the likelihood of risk
consequence into a single or combined number. However, without adequate data, the number
is of no use and value (Mulholland and Christian, 1999; del Cao and de la Cruz, 2002; Guo,
2004).The first tool of using risk assessment is the qualitative risk analysis. Qualitative risk
analysis is the process of prioritizing risks for further analysis or action by assessing and
combining their probability of occurrence and impact. Performing qualitative risk analysis
assesses the priority of the identified risks using their relative probability or likelihood of
occurrence as shown in Equation (2.2) or Equation (2.3) (Guo, 2004; PMI., 2012).
Risk = Sum {Probability Severity}..(2.2)
Or
Risk = Sum {Probability Severity Weight}.(2.3)
Cooper et al. (2005) have described the consequences and the likelihoods in terms of
five-point descriptive scale, showing the likelihoods of specific risks arising and leading to
the assessed levels of consequences. Table (2.1) provides the different level of rating in more
details.
23
Rating
Almost Certain
Likelihood Description
Very high, may occur at Least several times per year
Likelihood
Probability over 0.8
Likely
Probability 0.50.8
Possible
Probability 0.10.5
Unlikely
Probability 0.020.1
Rare
2.6.4.
Risk assessment through quantitative risk analysis process is the component of risk
analysis in which analysts describe the risks complete with their associated uncertainties.
Risk assessment is the systematic, scientific characterization of potential adverse effects
associated with hazardous substances, processes, actions or events (Dikmen et al., 2008).
It is the process of numerically analysing the effect of the identified risks on overall
project objectives. In this technique; many component uncertainties, possibly interacting or
interplaying with one another, simultaneously influence the overall uncertainty and risk
associated with a project (Cooper et al., 2005).
del Cao and de la Cruz (2002); and Guo (2004) have demonstrated the main currently
used quantitative techniques as:
Expected value tables, to compare expected values for different risk responses,
Decision trees to aid decision making when there are choices with uncertain
outcomes,
24
Fuzzy logic, with potential applications to scheduling, cost control, and multi-criteria
selection among several alternatives.
It is worth mentioning that risks are not always independent and static in construction
projects. The effect of two events is not necessarily the sum of their individual effects. Risks
are usually dynamic, that is, their characteristic, probability and impact can change during the
project process (Guo, 2004; Dikmen et al., 2008). The modelling of risk in a quantified model
involves establishing the boundaries of the model, structuring it to consider the interactive
relationships between the risks and the project, executing it and validating it in an iterative
process, and interpreting its outputs as illustrated in Figure (2.3). In this technique the
aggregate uncertainty of the project can be quantified or evaluated. Quantitative modelling
creates a framework within which integrating individual risks into an aggregate assessment
are taking place to assist and support decision-making and management control. (del Cao
and de la Cruz, 2002; Cleland, 2004; Guo, 2004) explained that sensitivity analysis, Monte
Carlo Simulation (MCS), and Probabilistic Influence Diagrams do not take into account the
possible correlation between risk aspects, however others do. The greater the maturity of the
organization and the projects magnitude, the more such a correlation should be taken into
account.
25
Figure 2.3: Outline of Quantitative Risk Approach, Modified from(Cooper et al., 2005)
Risk model parameters quantify uncertainty in the occurrence and the value of the
models components. Uncertainty in the occurrence of an event is described in terms of its
probability of occurring. Figure (2.4) manifests the inputs in the form of probability
distributions and the final probability distribution of the results or outputs.
Figure 2.4: Quantitative Analysis Risk Model Modified from (Cooper et al., 2005)
A quantitative risk analysis is performed on risks that have been prioritized by
performing qualitative risk analysis process as potentially and substantially impacting the
projects competing demands. In general, the projects scale and complexity have close
relation to the schedule of the project. In addition, the projects scale and complexity have
relations with the impact or severity of the risk (Guo, 2004).
26
2.6.5.
The purpose of planning risk responses is to determine what will be done in response to
the risks and what are the options and actions to enhance opportunities and to reduce threats
to project objectives (PMI., 2012).
2.6.6.
27
recognize any relationship among the system significant factors; and bottlenecks analysis to
identify the factors that cause system delays (Marzouk et al., 2007).
Halpin (1977) has introduced and developed CYCLONE (CYClic Operations NEtwork)
as one of the first major computer simulation packages for construction operations. Since that
time, numerous studies have been carried out to perform multitude purposes such as:
simulation for scheduling, earthmoving simulation, simulation for resource management as
summarized in Table (2.2).
Usage of Simulation
Reference
Shi (1997)
Earthmoving simulation
Jacinto (2002)
McCabe (2003)
Simulation for
bored piles
productivity assessment
10
11
12
13
2.7.1.
Abd-Allah(2008)
Simulation has been extensively used in the past to analyse construction operations and
processes. In addition, Simulation has been shown to be an effective tool for improving
construction process planning (Jacinto, 2002; Graham et al., 2004). Time scheduling or cost
estimate normally performed in a traditional and deterministic behaviour, however they are
including many uncertainties and variability that should force all involved parties to depend
28
on nondeterministic or stochastic analysis. Moreover, there are many expected scenarios for
completing the project; however project managers do not know anything about the
probability of each scenario and hence they know nothing about managing or controlling
such scenarios. Simulation up till now is the best way to determine all scenarios in which it is
possible to trace the stochastic critical paths (Lana, 2006).
On the other hand, most contracting companies in the Middle East Countries are still
relying on human planners to guide for important decisions through manual techniques of
generating, reviewing, and modifying project schedules and in a case-by-case manner (Wu
and Soibelman, 2006). In addition, large volumes of computerized schedules from previous
projects are not investigated, studied, or analysed for lessons learning and knowledge
discovery after projects are finished.
2.7.2.
The main activity of simulation process is getting computer machines to generate large
samples of observations and data records from different probability distributions, so that the
sample may be regarded as a genuine data set drawn from a population where the specified
probability distribution holds (Daly et al., 1995). Modelling and simulation are valuable tools
to assess the behaviour and performance of complex systems such as risks for construction
projects (Cleland, 2004). But, there still remains the need to evaluate the accuracy of
simulation by comparing computational predictions with experimental test data through the
process known as validation of computational simulations. To construct and setup realistic
models and simulation of complex systems, nondeterministic features of the system and the
environment must be included and vitally considered.
2.7.3.
Oberkampf et al. (2000) summarized the model develped by (Balci, 1990) and
demonstrated phases of modelling and simulation developed by the Society of Computer
Simulation as shown in Figure (2.5). The model included three main processes represented by
dashed arrows as follows: 1) analysis process that is used to construct a conceptual model of
reality; 2) programming process that converts the conceptual / mathematical model into a
computerized model; and 3) computer simulation process that is used to simulate reality.
Furthermore, the successful simulation program is the one that able to answer the
question who is going to use, what, why, and how often? (Kannan et al., 2000). Answering
29
the previous question to ensure the success of simulation program will be through defining
the functionality of a program that represents the range of added value features such as but
not limited to modelling ability and strength, database formulation and content, deterministic
and stochastic approaches, optimization, reliability and integration.
Figure 2.5: Modelling and Simulation Processes, cited in (Oberkampf et al., 2000)
2.7.4.
For the purpose of developing any simulation model or program, the researcher, engineer
or programmer should have the statistical understanding about the probability distribution
functions that might be used. Therefore, we will present for a number of continuous
probability distribution functions. These probability distribution functions are used in our
developed program, which will be described in chapter 5.
2.7.4.1.
30
average (or total) result over the replicates tends to have a normal distribution as the number
of replicates becomes large. The normal distribution was used by (Sakka and El-Sayegh,
2007) to evaluate the impact of float losses on time and cost for construction activities.
De Moivre (Montgomery and Runger, 2003; Soong, 2004) presented this fundamental
result, known as the central limit theorem, in 1733. Random variables with different means
and variances can be modelled by normal probability density functions with appropriate
choices of the centre and width of the curve. The mean (E(X) = ) determines the centre of
the probability density function and the Variance (V(X) = 2) determines the width as
summarized in Table (2.3).
2.7.4.2.
The Gamma Probability distribution function was used in the simulation process for
construction activities by Lana (2006), however the gamma distribution is not frequently used
as a model for a physical system (Montgomery and Runger, 2003; Soong, 2004). Gamma
distribution function and parameters are summarized in Table (2.3).
2.7.4.3.
Weibull distribution is often used to model the time until an event happens (i.e. failure of
many different physical systems). The parameters in the distribution provide a great deal of
flexibility to model systems in which the number occurring (failures) increases with time
(Montgomery and Runger, 2003; Pham, 2006). Weibull distribution function and parameters
are summarized in Table (2.3).
2.7.4.4.
31
Table 2.3: The Common Probability Density Functions Selected for our Study
2. Gamma
1. Normal
PDF Equation
() =
PDF Shapes
()
Or
() =
For x>0
( )
[ ( ) ]
3. Weibull
() = ()
() =
for 0<x<
([
( )
4. Lognormal
() = +
+
( )
V() =
32
CHAPTER 3: METHODOLOGY
3.1. General
The aim of this thesis is to contribute to the field of construction management through an
empirical research that would expand and existing knowledge from previous studies on the
performance of construction projects and the duration prediction models of activities. The
present study focuses on evaluating the best PDF to represent the durations of activities
through the simulation process of the scheduling of the construction project. In addition, the
present study focuses on developing a set of construction time prediction models to be used
by the construction industry in the Middle East.
This study can be regarded as a tool that support and help in facilitating the application
of Monte Carlo Simulation technique in scheduling of construction projects. In addition, this
study consists of three distinct sections which can guide projects managers, planners and
researchers to predict the impact of potential risks on the performance of construction
projects in the Middle East. The first subsidiary study includes the critical review of the
previous literature on the causes of delay. The first study also includes the statistical analysis
of the performance of construction projects in the Middle East countries. The last section in
the first study includes a quantitative analysis of the impact of construction risks on the
performance of a set of selected activities in a single project with a repetitive nature in
Kuwait. The second study includes the evaluation of the best PDF to represent activitys
duration during the simulation process. This study can be used as a general guidance for
selecting the best probability density function and the initial value of durations in the
scheduling process. The third study focus on evaluating regression models for predicting the
statistics of the activities durations based on the conventionally estimated durations. The
statistics of durations will also be used to represent activities through the simulation process.
The overall study includes projects in the Middle East countries such as Egypt, the
Kingdom of Saudi Arabia (KSA), Kuwait, Oman, and the United Arab Emirates (UAE).
33
construction projects all over the world. The risks are compiled and reviewed for both
developing and developed countries. Throughout the study, the author designed a custom
database to facilitate sorting, grouping and processing of tremendous numbers of risks from
different sources in different countries. The study suggests eleven categories for classifying
risks based on the previous literature and according to the source of risk. Besides, the study
suggests classifying risks into four groups according to the responsible party for risk. These
classifications will help as a basis for compare to conduct an analytical comparison study on
risks of similar classifications in different areas and countries.
In addition, the analytical comparisons of similar categories of risks in different
countries, areas, or continents will be applied by calculating the relative values of risks
according to the required level, such as the level of research, the level of country, the level of
area, or the level of continent. The Relative Risk Index (RRI) value for each risk in a research
as given be Equation (3.1)
Relative Risk Index (RRI) =
RII
..(3.1)
RII
Furthermore, the risks are stored in a comprehensive database to help planners, projects
managers, investors or researchers to prepare construction projects schedules with the
expected risks at early stages of the project. The preparation of schedules loaded with the
expected risks can be considered as a first step towards evaluating the reliable duration of the
project.
The second subsidiary study focuses on studying the statistical behaviour of the
construction projects in the Middle East countries. This section of the study introduces
statistics of activities according to the type of work (construction, and engineering procurement), the country of the project, and the CSI divisions. In addition, this study shows
the behaviour of the delayed activities behind their late start dates and their recover status.
Finally, the third subsidiary study focuses on the impact of risks on the performance of the
construction activities in a real project of a repetitive nature in Kuwait, as each activity is
repeated 1271 times.
34
the uncertainties specified at a detailed level of the project into their potential impact on
project objectives (Cleland, 2004; PMI., 2012). The conventional methods of scheduling
depend on utilizing deterministic values of activities durations as used in one point estimate
techniques like Critical Path Method (CPM) or even three point estimate like that used in
Program Evaluation and Review Technique (PERT).These techniques have proven
themselves to be insufficient tools to deal with multi-objectives projects or when dealing with
uncertainty environment.
Meanwhile, simulation of construction operations and processes has demonstrated
momentum in its ability to provide solutions and explain complex problems, especially for
iterative operations over the last three decades. The success of a simulation program lies in
harnessing the collaborative features within a complex pattern of hierarchical levels and user
groups (Kannan et al., 2000). One of the several methods for solving problems concerned
with uncertain parameters is Monte Carlo Simulation (MCS) Technique (Mulholland and
Christian, 1999; Cleland, 2004). Notwithstanding, it is found that one of the most observable
hindrances for the practitioners to use simulation systems for scheduling is the high level of
complexity in estimating input parameters for any simulation techniques. Nevertheless,
researchers presented many trials to develop different types of probabilistic models to include
construction project characteristics in scheduling risk boundaries (McCabe, 2003).
There are many types of simulation techniques that have been used during the last decades.
One of these techniques is the Monte Carlo Simulation (MCS) technique (Cleland, 2004).
Monte Carlo Simulation is a technique that identifies a deterministic model in which multiple
input variables are used to produce a single output value. The steps of MCS are illustrated in
Figure (3.1)
35
End of Simulation
Figure 3.1: General Monte Carlo Simulation Technique [Modified from (Youssef,
2005)]
36
F. The final step of Monte Carlo Simulation is to obtain the probability distribution
function of the projects overall duration, by drawing a histogram for the computed
output results and conclude their statistical parameters.
duration is tight and/or the contractor expects more risks in the project; the contractor takes
into consideration additional increase in the bid to cover any loss that may occur. The later
increase is not required in most cases as reported by Al-Ghafly (1995).
37
which is of course a great dilemma. Therefore, the process of risk assessment and evaluating
the probability distribution patterns to represent activitys duration becomes exigent
Lee et al. (2013) shown that most of the tools used to control risks are based on a number
of simplifying assumptions including: 1) the possibility to estimate accurately durations,
variances, and precedence relations of project activities; 2) the probability distribution used in
representing duration uncertainties is beta distribution; 3) it is possible to apply the central
limit theorem to represent other aggregate uncertainties; and 4) only focusing on the critical
path.
3.3.3.1.
Planning and scheduling for construction projects require an accurate estimate of the
input information relevant to comprising activities. This accuracy is required in order to
properly monitor and control the projects time and cost. The input data for any system or
model has three situations classified by AbouRizk et al. (1991): (1) Sample observations are
available and can be reduced to applicable deterministic or probabilistic models of the input
processes; (2) sample observations are not available, and the properties of the input processes
must be based on subjective information formulated or deducted from experts on those
processes; and (3) sample observations are available in relatively small quantities so that the
sample information must be combined effectively with subjective information to obtain the
required input models. It is difficult to define the probability distribution function (PDF) for
each activity due to lack of information (Afshar, 2008; Lee et al., 2013). A thorough survey
of studies relevant to modelling durations has proven that there is no particular probability
distribution function agreed upon (Lee et al., 2013). Almost all studies follow the first
classification introduced by AbouRizk et al. (1991) as mentioned above.
Lana (2006) selected gamma distribution function to represent activities without clear
justifications for this selection. Meanwhile, Leemis et al. (2006) explained that the triangular
distribution function can be used for representing stochastic activities networks because it
includes three model parameters: the optimistic, the most likely and the pessimistic times. In
addition, Lucko et al. (2009) used triangular distribution function in their study applying
a 5% reduction from the mean value to represent the minimum value and a 25% growth as
the maximum value. Furthermore, (AbouRizk et al., 1991; AbouRizk and Halpin, 1992;
McCabe, 2003; Nasir et al., 2003; Lee, 2005; Schexnayder et al., 2005) assumed utilizing
Beta distribution function because it can be approximated exploiting three parameters for its
definition: the lower or optimistic limit, the mode or most likely value, and the upper or
38
pessimistic limit. Schexnayder et al. (2005) derived Beta distribution by getting the minimum
and maximum activity duration values depending on the performance rates for the used
equipment, while the mean value was extracted by dividing the minimum duration by a factor
0.8.
One of the most important studies is that of AbouRizk and Halpin (1992) in which they
conducted a statistical analysis for seventy-one samples of durations of construction activities
and concluded that the beta distribution is the most suitable to exemplify construction activity
durations. The Beta distribution also fulfils the desired conditions of the probabilistic
modelling for activity duration as it is: continuous over the entire range; has a unique mode in
the range; and has two positive abscissa intercepts (Schexnayder et al., 2005).
3.3.3.2.
x 2 = n1
(Oi Ei )2
Ei
..........(3.2)
39
X 2 (1 / 2, ) X 2 X 2 ( / 2, )
Where is the coefficient of confidence,
40
regression model can be used for representing the relationship between two variables with
considered errors or residual. The fitted regression model can be defined by Equation (3.5).
Y = 0 + 1 x + ........(3.3)
y = 0 + 1 x......(3.4)
where 0 & 1 : regression parameters or coefficients ,
and random disturbance or random error
y = b0 + b1 x......(3.5)
Where y is predicted or fitted value,
and b0 & b1 are the fitted regression parameters or coefficients.
The strength of the relationship between variables and the adequacy of the fitted model is
defined by the residual. The residual is defined as the error in the fit of the model. The
residual is described by Equation (3.6) and illustrated in Figure (3.3).
ei = yi yi = 0 + 1 xi b0 b1xi ........(3.6)
Where ei is the residual between the true and the fitted regression lines.
Therefore,
yi = b0 + b1xi + ei ......(3.7)
The residual sum of squares is often called the sum of squares of the errors about the
regression line and is denoted by SSE. The minimization procedure for estimating the
parameters is called the method of least squares. Hence, we shall find b 0 and b1 so as to
minimize SSE as given in Equation (3.8).
41
Coefficient of determination R2 = 1
...........(3.9)
= =1( )2..........(3.10)
Therefore, for SSE = 0 and thus R2=1.0 that mean all residuals are zero and the fit
is perfect.
42
Figure 3.3: Comparing with the Residual as cited in (Walpole et al., 2012)
In this study, a variety of distinct regression models will be generated to delineate the
relationship between the estimated deterministic durations / estimated budgets and the
statistics of their actual durations. This derivation expands the previously reported studies and
analyse the actual results from currently running projects or completed before this study. The
generated models provide practical and easy tool for estimating the activity duration
stochastically. Besides, the generated regression models will help in defining the statistical
parameters of activities such as the mean and the standard deviation. These statistical
parameters of activities will be used in the Monte Carlo Simulation process of the scheduling
to predict a more reliable projects overall duration. Throughout the study, many Software
Packages such as Microsoft Access 2010, Primavera Project Planner 3.1, Primavera
Enterprise 6.7, Microsoft Project 2010, MATLAB 2010b, STATISTICA 10.0, Easy Fit 5.5
and IBM Statistics SPSS Ver. 22 have been utilized in order to collect, sort, analyse, derive
statistical parameters for distributions of activity durations, check the goodness of fit, and
develop regression models.
43
the United Arab Emirates (UAE), Qatar and Oman. The study included 20 distinct Projects
including most widespread types of construction projects for both Public and Private sector
projects, and for small and large projects between 1998 and 2013. Moreover, the projects
include high rise buildings, commercial malls, hotels, stadiums, banks, administration,
residential, infrastructure and highway projects.
In addition, the study was carried on a huge amount of various activities that exceeded
125,000 activities with a total budget of about fifteen billions Egyptian Pounds (EGP) and
including Engineering, Procurement and Construction (EPC) activities. The Engineering
activities represent all design and preparation activities such as design / shop drawings and
materials submittals including samples, manufacturer data, mock ups, and testing certificate
activities. Besides, the procurement activities represent all activities needed to secure the
delivery of the material to site including contracts, letters of credits (LC), manufacturing,
shipping and delivery to site. While, the Construction activities represent all tasks on site that
require manpower and equipment to be carried out in order to produce a structure or a part of
the structure, such as excavation, casting concrete, installation of steel structure, or fixing
Heating, Ventilation, and Air Conditioning (HVAC) ducts.
The study was also carried out on a special project with a repetitive nature, as it consists
of 1271 similar housing buildings in Kuwait state. Each building consists of ground, first
floor and a roof. Each building includes most of civil, mechanical and electrical activities.
The study includes 66 groups of similar activities that make the total activities under the
study is approximately 84,000 activities.
The data will be statistically analysed in order to deduce the statistical characteristics of
activities durations for different case studies such as:(1) analysis of all activities for all
countries under the study, (2) analysis of construction activities for all countries under the
study, (3) analysis of engineering procurement activities for all countries under the study,
(4) analysis of all activities in all projects of a single country, (5)analysis according to
Construction Specifications Institute (CSI) Master Format divisions for all projects,
(6)analysis for a single project containing activities with repetitive nature.
44
This chapter provides three subsidiary studies; the first study provides a comprehensive
critical review for causes of delay of construction projects, the second study investigates the
statistical properties of activities actual durations in the Middle East countries, and the third
45
study provides a quantitative analysis of the impact of different risks on a set of real activities
in a single project with a repetitive nature in Kuwait.
4.2.1.
Fugar and Agyakwah-Baah (2010) investigated the causes of delay in building projects
in Ghana. The investigation identified 32 causes of delay and categorized them into nine
major groups as summarized in Table (4.1).
Year
2010
Categories
1.
2.
3.
4.
5.
6.
7.
8.
9.
Material
Manpower
Equipment
Financing
Environment
Changes
Government action
Contractual relations
Scheduling and controlling
46
4.2.2.
Our review for the causes of delay in Asia included five countries and nine studies as
summarized in Table (4.2). Ogunlana et al. (1996) studied 26 causes of delay for 12 high rise
building projects in Thailand and classified the causes of delays into six groups depending on
the responsible party for the delay as summarized in Table (4.2).
In Malaysia, Abd. Majid and McCaffer (1998) studied the non-excusable factors of delay
that influence contractors performance and classified these factors into twelve groups
according to sources of occurrence as summarized in Table (4.2). In addition, Sambasivan
and Soon (2007) investigated 28 causes of delay for construction industry. Moreover, Wei
(2010) identified 52 causes of delay and their impact on construction projects. Both studies
follow the same categorization for the causes of delay as they categorized the causes of delay
into eight major groups as summarized in Table (4.2).
Chan and Kumaraswamy (1997) investigated the causes of construction projects delay in
Hong Kong in a comprehensive study including both building and civil projects. The study
identified 83 causes of delay that were categorized into eight groups as summarized in Table
(4.2).
In Indonesia, Alwi and Hampson (2003) studied 31 causes of delay in construction
projects. The levels of effect of these delays were defined by both large and small
contractors. The study categorized the causes of delay into six major groups as summarized
in Table (4-2). In addition, Majid (2006) investigated the causes of delay for construction
industry in Aceh city. The investigation included causes of delay in different projects such as
office and administration buildings, school buildings, medical centres, communication
facilities and civil projects. The investigation included 57 causes of delay that were
categorized into eight major groups as summarized in Table (4.2).
In Vietnam, Long (2004) and Le-Hoai et al. (2008) studied the causes of delay and cost
overrun in large buildings and industrial construction projects. The study included 21 causes
of delay that were grouped into six major groups as summarized in Table (4.2).
47
Reference
Ogunlana et al.
(1996)
Year
1996
Malaysia
1998
Sambasivan
Soon (2007)
2007
and
Wei (2010)
2010
Hong Kong
Chan and
Kumaraswamy
(1997)
1997
Indonesia
Alwi
and
Hampson ( 2003)
2003
Majid (2006)
2006
Long (2004)
2004
Vietnam
Le-Hoai
(2008)
et
al.
2008
Categories
1. Owners related
2. Designers related
3. Construction manager or inspector related
4. Contractors related
5. Resources suppliers related
6. Others or external related
1. Material related
2. Labour related
3. Equipment related
4. Financial related
5. Improper planning related
6. Lack of control related
7. Subcontractor related
8. Poor coordination related
9. Inadequate supervision related
10. Improper construction methods related
11. Technical personnel shortages related
12. Poor communication related
1. Client related
2. Contractor related
3. Consultant related
4. Material related
5. Labour and Equipment related
6. Contract related
7. Contract relationships related
8. External related
1. Project related
2. Client related
3. Design team related
4. Contractor related
5. Materials related
6. Labour related
7. Plant and equipment related
8. External related
1. People
2. Professional Management
3. Design And Documentation
4. Material
5. Execution
6. External related
1. Material Related
2. Labour Related
3. Equipment Related
4. Finance Related
5. Contractor Related
6. Client Related
7. Consultant Related
8. External Related
1. Consultant
2. Contractor
3. External
4. Material / Labour
5. Owner
6. Project
48
4.2.3.
The first part of (Falqi, 2004) study was the investigation of causes of delay of
construction projects in the United Kingdom. The survey included contractors, consultants
and owners review for 67 causes of delay that were categorized into ten major groups as
summarized in Table (4.3).
Year
2004
Categories
1. Contractor performance / Materials
2. Contractor performance / Equipment
3. Contractor performance / Manpower
4. Contractor performance / Project management
5. Contractor performance / Project finance
6. Owner
7. Early planning and Design
8. Government regulations
9. External factors
10. Consultant related issues
4.2.4.
In Egypt, six studies between 2005 and 2014 were compiled and reviewed. The first
study was conducted by Abdel-Gawad et al. (2005). They identified the sources of projects
risks relevant to schedule and cost overrun under joint ventures. Abdel-Gawad et al. (2005)
identified 44 risks in 6 major classifications as shown in Table (4.4).
The second study was conducted by Abdul Rashid and Bakarman (2005) as they
identified 71 risk factors that affect construction budget and schedule. The study included
interviews with contractors ranked according to the Egyptian Federation for Construction and
Building. Abdul Rashid and Bakarman (2005) grouped six grades of contractors into three
classes, as each class of contractors includes two grades of contractors such as first class
includes contractors with first and second grade and so on. The study classified the causes of
delay into eleven different categories as shown in Table (4.4).
49
The third study was performed by Marzouk et al.(2007) as they studied 44 causes of
disputes that affect schedule and costs of construction projects. The causes of disputes were
grouped into 4 major categories and then further subdivided into 9 groups as summarized in
Table (4.4).
The fourth study was conducted by Abd El-Razek et al. (2008), where they studied the
causes of delay on building construction projects and identified a list of 32 distinct causes of
delay. Abd El-Razek et al.(2008) grouped the causes of delay into 9 major categories as
manifested in Table (4.4).
The fifth study was conducted by Ammar et al. (2009). Ammar et al. (2009) investigated
the risks of barrage construction project and identified 40 distinct risks. The risks were
grouped in five major categories as illustrated in Table (4.4).
The sixth study was done by Marzouk and El-Rasas (2014) as they studied the causes of
delay in construction projects based on experts that represent contractors, consultants and
owners. The study identified 43 distinct causes of delay that were grouped into 7 major
categories as illustrated in Table (4.4).
Abdul Rashid
Bakarman (2005)
Year
al. 2005
and 2005
Marzouk et al.(2007)
2007
Categories
1. Financial risk
2. Legal and Cultural risks
3. Management risks
4. Market risks
5. Policy /Political risks
6. Technical risks
1. Construction & job site risks
2. Design risks
3. Financial & economic risks
4. Management risks
5. Owner risks
6. Supervision risks
7. Subcontractors risks
8. Site conditions risks
9. Adverse weather and natural risks
10. Legal risks
11. Government regulation and policies risks
1. Contractual matters
2. Cultural matters
3. Management and organization / Contractors
4. Management and organization / Owners
5. Management and organization / Consultants
6. Projects matters / External
50
2009
7.
8.
9.
1.
2.
3.
4.
5.
6.
7.
8.
9.
1.
2.
3.
4.
5.
1.
2.
3.
4.
5.
6.
7.
In the Kingdom of Saudi Arabia, five studies are included in our review. The five studies
were completed for a period of about 14 years between 1995 and 2009. The five studies
covered most types of construction projects, such as building, infrastructure, utilities, and
housing projects for both public and private sectors.
The first study was conducted by Al-Ghafly (1995) that studied causes of delay in the
construction of public utility projects, and classified risks into six major groups as
summarized in Table (4.5).
The second study was performed by Assaf et al. (1995) and extended by Assaf and AlHejji (2006) studied the causes of delays in large building construction projects. They
identified 56 causes of delay and grouped them into nine major groups as summarized in
Table (4.5).
The third study was conducted by Al-Khalil and Al-Ghafly (1999) on the causes of delay
in public utility construction projects. Al-Khalil and Al-Ghafly (1999) identified 60 causes of
delays that were categorized into six major categories. Then the contractors category was
further subdivided into five classifications as shown in Table (4.5).
51
The fourth study was performed by Falqi (2004) as he investigated causes of delay of
construction projects. The investigation included the review of contractors, consultants and
owners for 67 causes of delay that were categorized into six major categories. Then the
contractors category was further subdivided into five classifications as shown in Table (4.5).
The fifth study was conducted by Al-Kharashi and Skitmore (2009) in which they
investigated 29 causes of delay in public sector construction projects. The causes of delay
were categorized into six major categories as shown in Table (4.5).
Year
Al-Ghafly (1995)
1995
1995
Al-Khalil
and
Al- 1999
Ghafly (1999)
Falqi (2004)
2004
Al-Kharashi
and 2009
Skitmore (2009)
Categories
1. Contractor performance
2. Owner administration
3. Early planning and design
4. Government regulation and policies
5. Site and environmental conditions
6. Supervision and field inspection
1. Materials
2. Manpower
3. Equipment
4. Financing
5. Environment
6. Changes
7. Government relations
8. Contractual relationships
9. Scheduling and controlling techniques
1. Contractor performance / materials
2. Contractor performance / equipment
3. Contractor performance / manpower
4. Contractor performance / project management
5. Contractor performance / project finance
6. Owner administration
7. Early planning and Design
8. Government regulations
9. Site and environmental conditions
10. Site supervision
1. Contractor performance / materials
2. Contractor performance / equipment
3. Contractor performance / manpower
4. Contractor performance / project management
5. Contractor performance / project finance
6. Owner
7. Early planning and Design
8. Government regulations
9. External factors
10. Consultant related issues
1. Client related
2. Contractor related
3. Consultant related
4. Materials related
5. Labour related
6. Contract/Relationship related
52
In Kuwait, the first study was conducted by Al-Bahar and Crandall (1990) in which they
studied the causes of delay in construction projects and classified the causes of delay into six
main groups as summarized in Table (4.6).
The second study was performed by Al-Tabtabai (2002) in which he investigated the
causes of delay in building and housing type projects undertaken by governmental agencies.
The investigation included 53 causes of delay that were categorized into eight major groups
as summarized in Table (4.6).
and
Year
Crandall
1990
(1990)
Categories
1. Force Majeure
2. Physical
3. Financial and economics
4. Political and environmental
5. Design
6. Construction related risks
Al-Tabtabai (2002)
2002
1. Management related
2. Supervision
3. Contractor
4. Design
5. Project
6. Labour
7. Quantity
8. Contractual related
In Jordan, Odeh and Battaineh (2002) studied the causes of delay in building, road, and
water - sewer construction projects. Odeh and Battaineh (2002) identified 28 causes of delay
and grouped them into 8 major categories as shown in Table (4.7).
In the United Arab Emirates (UAE) three studies are included for the period between
2006 and 2010. The first study was conducted by Faridi and El-Sayegh (2006) as they
investigated 44 causes of delay and classified them into eight distinct categories as
summarized in Table (4.8).
53
Year
2002
Categories
1. Client
2. Contractor
3. Consultant
4. Material
5. Labour and Equipment
6. Contract
7. Contractual relationships
8. External
The third study was conducted by Motaleb and Kishk (2010) where they identified 42
distinct causes of delay that were grouped into six major categories as illustrated in Table
(4.8).
Year
2006
Categories
1. Contractor
2. Consultant / Designer
3. Owner
4. Financial
5. Planning and scheduling
6. Contractual relationship
7. Government regulations
8. Unforeseen conditions
54
El-Sayegh (2008)
2008
1. Owners
2. Designers
3. Contractors
4. Sub-Contractors
5. Suppliers
6. Political
7. Social & Cultural
8. Economic
9. Natural
10. Others
2010
1. Client factors
2. Consultant factors
3. Contractor factors
4. Financial factors
5. Project manager factors
6. Unforeseen factors
4.2.5.
Ahmed et al. (2002) studied the causes of delay in Florida region in the USA. They
identified 5o distinct causes of delay and classified them into six major categories as
illustrated in Table (4.9).
Year
2002
Categories
1. Force Majeure
2. Design-Related
3. Financial/Economical
4. Construction Related
5. Management And Administrative
6. Code Related
55
4.2.6.
56
Table 4.10: Suggested Classifications for Causes of Delay together with Referenced
Publications
RF.
Category*
Reference
No.
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11)
1
Abd El-Razek et al., 2008
2
Abd. Majid and McCaffer,
1998
3
4
Abdul Rashid and Bakarman, 2005
Al-Ghafly, 1995
8
Al-Khalil and Al-Ghafly, 1999
9
Al-Kharashi and Skitmore,
2009
10 Al-Tabtabai, 2002
12 Ammar et al., 2009
13 Assaf and Al-Hejji, 2006
16 Falqi ,2004
17 Faridi and El-Sayegh, 2006
2010
19 Long, 2004
20 Majid ,2006
21 Marzouk and El-Rasas, 2014
22 Marzouk et al, 2007
24 Odeh and Battaineh, 2002
26 Sambasivan and Soon, 2007
27 Wei, 2010
Total Number
7
6 12 2 17 12 14 14 16 13 11
* (1) Design and drawings approval related; (2) Construction related; (3) Contract
related: (4) Suppliers and subcontractors related; (5) Financial and Economical related;
(6) Government and regulation related; (7) Labour and equipment related; (8)
Management, planning, and scheduling related; (9) Materials related; (10) Site related
and; (11) Force Majeure related.
57
4.2.6.1.
The first category is the design and drawings approval related and it was referenced 7
out of 27 reports as shown in Table (4.10). This category describes the occurred causes of
delay during the design phase of the project, such as issuing poor, unclear, or incomplete
design drawings. In addition design and drawings approval related category includes some
occurred causes of delay during the construction phase but relevant to design phases, such as
discrepancies between design drawings, specifications, local regulations or building codes.
The design and drawings approval category and relevant causes of delay are summarized in
Table (4.11).
Table 4.11: Causes of Delay under Design and Drawings Approval Category
Category Title
1. Design
&
Causes of Delay
Approval - Related
drawings or specifications
2. Delay in reviewing and approval of shop drawings
3. Discrepancies
between
design
drawings,
4.2.6.2.
The second category is construction related causes of delay and it was referenced 6 out
of 27 reports as shown in Table (4.10). This category describes all causes of delay during
construction phase such as late mobilization of contractors staff, labours, or equipment, poor
or late preparation of shop drawings, improper selection or incomplete study of construction
methodology, and accidents during construction due to lack of safety precautions. All other
causes of delay that might face projects team during construction are summarized in Table
(4.12).
58
4.2.6.3.
Causes of Delay
Late mobilization
Poor or late preparation of shop drawings
Poor or improper construction method
Contractor inadequate preconstruction site inspection
Lack of safety during construction
Poor quality, error of construction and defective work
during construction
7. Lack of contractors staff experiences
8. Changes in design, specifications or quantities during or
after construction
1.
2.
3.
4.
5.
6.
The third category is contract related causes of delay and it was referenced 12 out of 27
reports as shown in Table (4.10). This category describes all causes of delay due to the
explanation or application of contract during any phase of the project such as selection of
contract type, adversarial approach in handling disputes, delay in resolving disputes, and misinterpretation of contract terms by any party. All other causes of delay that might face
projects team during construction are summarized in Table (4.13).
Causes of Delay
3. Contract - Related
59
4.2.6.4.
The fourth category of causes of delay is suppliers and subcontractors related category
and it was referenced 2 out of 27 reports as shown in Table (4.10). This category describes all
causes of delay due to delivery of materials to site, performance of special sub-contractors,
and poor performance of subcontractors. All other causes of delay that might face projects
team during construction are summarized in Table (4.14).
Table 4.14: Causes of Delay under Suppliers and Sub-contractors Related Category
Category Title
4. Suppliers and
subcontractors - Related
Causes of Delay
1. Delay of delivering materials to site
2. Delay of manufacturing special materials
3. Insufficient performance by subcontractors
4. Improper
method
of construction by sub-
contractors
5. Material
delivery
not
in
accordance
with
specifications
6. Lack of competent / reliable subcontractors or
suppliers
4.2.6.5.
The fifth category of causes of delay is financial and economical related category and it
was referenced 17 out of 27 reports as shown in Table (4.10). This category describes all
causes of delay due to financial or cash flow problems by any party in the project, delay in
approving and paying payments either to consultants, main contractors, subcontractors or
suppliers, or inaccurate estimate of the budget. All other causes of delay that might face
projects team during construction are summarized in Table (4.15).
60
Causes of Delay
1. Financial / Cash flow problems by owners
2. Financial / Cash flow problems by consultant
3. Financial / Cash flow problems by contractors
4. Financial / Cash flow problems by subcontractors
5. Financial / Cash flow problems by suppliers
6. Delay of progress payment by owner to
consultants or to contractors
7. Delay of progress payment by main contractor to
sub-contractors or suppliers
8. Inaccurate estimate of budget
9. Devaluation and varying rates of exchange
4.2.6.6.
The sixth category of causes of delay is government and regulations related category
and it was referenced 12 out of 27 reports as shown in Table (4.10). This category describes
all causes of delay due to government permits and regulations, building codes, and
government tendering system to the select lowest bid. All other causes of delay that might
face projects team during construction are summarized in Table (4.16).
Table 4.16: Causes of Delay under Government and Regulations Related Category
Category Title
6. Government
Regulations - Related
Causes of Delay
and
61
4.2.6.7.
The seventh category of causes of delay is labour and equipment related category and it
was referenced 14 out of 27 reports as shown in Table (4.10). This category describes all
causes of delay due to shortage of manpower amounts or skills, shortage of equipment,
fluctuating of productivity rates. All other causes of delay that might face projects team
during construction are summarized in Table (4.17).
Table 4.17: Causes of Delay under Labour and Equipment Related Category
Category Title
7. Labour and Equipment
Related
1.
2.
3.
4.
5.
6.
4.2.6.8.
Causes of Delay
Shortage of labours numbers / skills
Shortage of equipment numbers, capacity, or
operators
Labours dispute and strike
Increase of labours salaries
Fluctuating of labours / equipment productivity
levels
Personal conflicts among labours
The eighth category of causes of delay is management, planning and scheduling related
category and it was referenced 14 out of 27 reports as shown in Table (4.10). This category
describes all causes of delay due to lack of management, planning or scheduling skills or
professional from contractors or consultants staff, inaccurate estimation of contract time by
the owner, slow decision making by the contractor or the owner, and poor contract
management by the owner or the contractor. All other causes of delay that might face
projects team during construction are summarized in Table (4.18).
62
Table 4.18: Causes of Delay under Management, Planning and Scheduling Related
Category
Category Title
8. Management,
Planning
Causes of Delay
1. Poor
coordination
or
communication
between
or
monitoring
improper
and
planning,
controlling
by
scheduling,
contractor,
of
administrative,
technical, managerial
63
4.2.6.9.
The ninth category of causes of delay is materials related category and it was
referenced 16 out of 27 reports as shown in Table (4.10). This category describes all causes
of delay due to shortage of materials, fluctuation of prices, or special requirements for
materials such as testing or storage precautions. All other causes of delay that might face
projects team during construction are summarized in Table (4.19).
1.
2.
3.
4.
5.
6.
Causes of Delay
Fluctuation of materials prices
Damage of sorted material
Increase wastage of material
Lack of materials on local market
Poor Quality of construction materials
Special testing required for construction materials
Site Related
Causes of Delay
1. Bad Weather or Environmental restrictions
2. Change or differing site condition
3. Unforeseen subsurface conditions
4. Inaccurate site investigations (soil composition,
high water table, etc.)
5. Problem with neighbours or existing buildings
6. Shortage of utilities (water, electricity, etc.)
7. Site limitations for storage, access, etc.
64
Causes of Delay
1. Natural disasters
2. Fires
3. Wars
4. Civil disorder
5. Revolution
On the other hand, a separate classification according to the involved parties
responsibility towards the causes of delay will be used. The responsibility towards the causes
of delay will be classified into four major parties:
1. Owner;
2. Contractor;
3. Consultant; and
4. others
65
et
by owner
delay
the
to
main
contractor,
payment
by owner
3. Lack of experience in construction law, and
management by project parties
4. Late supply of materials and equipment
5. Original contract duration imposed by owner
is too short
6. Improper pricing and budgeting
7. Excessive
bureaucracy
in
the
owner
administration
8. Subcontractors or Suppliers low credibility
9. Design defects
10. Ineffective planning and scheduling of the
project by the contractor or subcontractors
66
bureaucracy
in
the
owner
administration
6. Low competency of subcontractors or suppliers
7. Owners lack of experience in the construction
business
8. Improper planning and scheduling of the project
by the contractor or subcontractors
9. Inflation and sudden price changes
10. Strict application of quality control program
67
Mudlej,
are reviewed separately. The review of the five countries included 416 causes of delay with
similar meaning or even close to each other. By filtering the highest severity and impact of
causes of delay in each research, then in each country, then focus on the most predominant
causes of delay to extract the most significant causes that are finally summarized in Table
(4.25).
The overall review of these five countries outlined that the shortage of manpower,
shortage of equipment, shortage of materials, delay of preparation and approval of drawings,
change orders during construction, and lack of planning and management are the most
significant of delay in the Middle East as shown in Table (4.25).
Table 4.25: Top Ten Causes of Delay in the Middle East Countries
Country
UAE
Jordan
Research
(Faridi and El-Sayegh, 2006;
El-Sayegh, 2008; Motaleb
and Kishk, 2010)
(Al-Momani, 2000; Odeh and
Battaineh, 2002; Abu
Hammad et al., 2008)
Libya
Lebanon
On the other hand, El-Sayegh (2008) found that 55% of the risk shared between the
owner and contractor, while 38% of the risk is the contractors own risks. In addition,
Al-Momani (2000) studied the performance of construction projects in Jordan and found that
among 130 projects there was a delay in 106 projects (81.5%).
69
Research
(Ogwueleka, 2001; Aibinu and
Jagboro, 2002; Omoregie and
Radford, 2006; Aibinu, 2008;
Olupolola et al., 2010)
Ghana
South
Africa
Zambia
Uganda
Apolot et al.(2010)
70
research, then in each country, then focus on the most predominant causes of delay to extract
the most significant causes as summarized in Table (4.27).
The overall review of these seven countries outlined that the changes in design during the
construction stage, poor site management, shortage of equipment, shortage of materials,
ineffective planning, scheduling, delay contractors progress payments, inflation, and price
fluctuation are the most significant causes of delay in the Asia as shown in Table (4.27).
Indonesia
Pakistan
Research
(Sambasivan and Soon, 2007;
bin Yusof et al., 2007; Abdullah
et al., 2010; Wei, 2010)
(Alwi et al., 2002; Alwi and
Hampson, 2003; Soehodho et
al., 2003; Wiguna and Scott,
2005b; Wiguna, 2005a; Majid,
2006)
(Shaikh et al., 2010; Haseeb et
al., 2011)
(Afshari et al., 2011;
Mahdavinejad and Molaee,
2011; Pourrostam and Ismail,
2011)
Iran
Vietnam
China
Hong Kong
Korea
71
owners organisation are the most significant causes of delay in Europe and North America as
shown in Table (4.28).
Table 4.28: Top Ten Causes of Delay in Europe and North America
Country
UK
Research
Falqi(2004)
Portugal
USA
72
RII
..(4.2)
RII
category includes the causes of delay related to labour and equipment. The labour and
equipment related causes of delay represent 12% of the all causes of delay. Therefore, the
summation of causes of delay related to management, manpower represents about 41% of all
causes of delay in Africa.
On the other hand, classifying causes of delay according to responsibility shows that the
contractors are responsible for cause of delay by about 38% of all causes of delay in Africa as
shown in Figure (4.2). In addition, the second party responsible for the delay is the owner.
The owner responsibility represents about 26% of all causes of delay in Africa. It is worth
noting that the consultant is the lowest responsible for the delay in Africa with 15% of all
causes of delay.
35%
30%
29.0%
25%
20%
15%
12.3%
10.3%
10%
9.5%
5%
8.2%
7.8%
7.0%
5.9%
4.8%
4.2%
0%
Figure 4.1: Comparison among All Categories for Causes of Delay in Africa Average
of Nine Studies
74
40%
38%
35%
30%
26%
25%
20%
20%
15%
15%
10%
5%
0%
Contractor
Owner
External
Consultant
Figure 4.2: Comparison among Responsibilities for Causes of Delay in Africa - Average
of Nine Studies
75
35%
31.0%
30%
25%
20%
15%
13.3%
11.2% 11.2%
10%
6.4%
6.3%
6.2%
5%
5.2%
4.9%
4.2%
0.0%
0%
Figure 4.3: Comparison among All Categories for Causes of Delay in Asia - Average of
Nineteen Studies
60%
51%
50%
40%
30%
22%
20%
14%
13%
External
Consultant
10%
0%
Contractor
Owner
Figure 4.4: Comparison among Responsibilities for Causes of Delay in Asia -Average of
Nineteen Studies
76
Europe
60%
50%
49.0%
40%
30%
20%
10%
8.2%
8.0%
7.8%
7.0%
5.6%
5.3%
4.6%
2.5%
1.9%
0%
Figure 4.5: Comparison among All Categories for Causes of Delay in Europe - Average
of Two Studies
77
45%
42%
40%
35%
30%
27%
25%
20%
15%
15%
Consultant
External
15%
10%
5%
0%
Contractor
Owner
Figure 4.6: Comparison among Responsibilities for Causes of Delay in Europe Average of Two Studies
78
USA as shown in Figure (4.8). The external-related causes of delay appeared the most
significant in the USA due to causes of delay under force majeure category. Where, the
causes of delay related to force majeure category are the highest in all included countries in
our review. In addition, the second party responsible for the delay is the contractor. The
contractors responsibility represents about 32% of all causes of delay in the USA. It is worth
noting that the lowest responsible for delay in the USA is the owner with 15% of all causes of
delay as illustrated in Figure (4.8).
25%
N. America
21.8%
20%
20.3%
17.8%
15%
11.5%
10%
7.5%
7.4%
6.6%
5%
2.9%
2.3%
1.9%
0%
Figure 4.7: Comparison amongAll Categories for Causes of Delay in the USA
40%
35%
33%
32%
30%
25%
19%
20%
15%
15%
10%
5%
0%
External
Contractor
Consultant
Owner
40%
35%
30%
25%
20%
15%
10%
5%
0%
Middle East
36.2%
9.3%
9.3%
8.2%
7.5%
7.5%
6.2%
5.9%
5.3%
2.9%
1.8%
Figure 4.9: Comparison amongAll Categories for Causes of Delay in the Middle East
Countries - Average of 31 Studies
80
50%
45%
45%
40%
35%
30%
24%
25%
20%
20%
15%
11%
10%
5%
0%
Contractor
Owner
External
Consultant
Figure 4.10: Comparison among Responsibilities for Causes of Delay in the Middle East
Countries - Average of 31 Studies
A deep investigation of cause of delay in the Egypt, Kuwait and Kingdom of Saudi
Arabia show that the category of management, planning and scheduling related causes of
delay remains the most significant category in Egypt and KSA as manifested in Figure (4.11).
While, the category of suppliers and subcontractors related causes of delay is the most
significant in Kuwait as illustrated in Figure (4.11).
It is worth noting that the lowest significant category in KSA is the suppliers and
subcontractors related category, since KSA depends mostly on local materials. Nevertheless,
the suppliers and subcontractors category is the most significant category in Kuwait. This is
owed to that most of the construction materials are imported from abroad and hence need
a special coordination between numerous parties such as the owner, the main contractor, the
subcontractors and suppliers. The second significant category in Kuwait is the management,
planning, and scheduling related category that represent about 27% of all causes of delay as
shown in Figure (4.11).
On the other hand the analysis of the responsible party for delay in Egypt, KSA, and
Kuwait show that the contractor has the highest responsibility for the delay in the three
countries as shown in Figure (4.11). In addition, the contractors responsibility about the
delay in Kuwait is the highest among the three countries.
81
It is worth noting that, the owner is the second responsible for the delay in the three
countries. In addition, the owners responsibility for the delay in KSA is the highest in the
three countries as shown in Figure (4.11).
40%
35%
30%
25%
20%
15%
10%
5%
0%
a)
35.6%
10.3%
Management,
Planning &
Scheduling
9.7%
Contract
Construction
9.7%
9.6%
8.5%
Design &
Drawings
Approval
7.1%
6.4%
Financial &
Economical
Related
Labour &
Equipment
6.2%
Site
6.1%
5.3%
3.7%
1.2%
Materials
Egypt
50%
45%
40%
35%
30%
25%
20%
15%
10%
5%
0%
44.6%
Management,
Planning &
Scheduling
Labour &
Equipment
Financial &
Economical
Related
9.4%
Construction
6.1%
6.0%
5.4%
4.0%
3.5%
Design &
Drawings
Approval
Government &
Regulation
Site
Contract
Materials
1.8%
1.4%
1.0%
Materials
Financial &
Economical
Related
Site
1.7%
Suppliers & Sub
Contractors
b) KSA
50%
45%
40%
35%
30%
25%
20%
15%
10%
5%
0%
44.4%
27.3%
10.5%
4.8%
Suppliers & Management,
Sub
Planning &
Contractors Scheduling
c)
Contract
Labour &
Equipment
4.4%
Design &
Drawings
Approval
2.2%
2.1%
Government Construction
& Regulation
Kuwait
Figure 4.11: Comparison among All Categories for Causes of Delay in the Middle East
Countries: a) Egypt, b) KSA, and c) Kuwait
82
50%
45%
40%
35%
30%
25%
20%
15%
10%
5%
0%
45%
23%
21%
11%
Contractor
Owner
External
Consultant
14%
12%
External
Consultant
a) Egypt
50%
45%
40%
35%
30%
25%
20%
15%
10%
5%
0%
47%
27%
Contractor
Owner
b) KSA
70%
67%
60%
50%
40%
30%
18%
20%
11%
10%
4%
0%
Contractor
Owner
Consultant
External
a) Kuwait
Figure 4.12: Comparison among Responsibilities for Causes of Delay in the Middle East
Countries: a) Egypt, b) KSA, and c) Kuwait
83
84
On the other hand, comparing the ratio of delayed activities with respect to the total
activities number manifests that:
about 68% are delayed after their planned early start dates,
about 29.7% are delayed behind their planned late start dates,
about 79% are delayed after their planned early finish dates,
about40.9% are delayed behind their planned late finish dates and consequently cause
the delay of the whole project, and
about 65.7% have actual durations more than the planned estimated durations as
illustrated in Figure (4.13).
Therefore, about 65.7% of all activities have time overrun, while only 40.9% of all
activities may cause delay to the overall projects completion date. The activities that have
time overrun will be investigated to study the impact of different risks on the performance of
construction projects activities. As a general note: the numbers of delayed construction
activities are greater than those for engineering - procurement activities with respect to the
same case of delay as shown in Figure (4.13). The most influential element is the delay
behind planned late finish dates where they directly influence the projects planned
completion dates.
85
65.74%
54.36%
70%
64.07%
80%
68.02%
90%
75.07%
79.13%
Construction
Engineering
40.89%
60%
40%
16.76%
30%
24.94%
29.71%
50%
20%
10%
0%
(1) Early Start
(5) Duration
Figure 4.13: The Delayed Activities Percentages for Construction and Engineering Procurement Classified by Cases of Delay from Planned Dates: (1) Behind Early Start,
(2) Behind Late Start, (3) Behind Early Finish, (4) Behind Late Finish, and (5) Greater
Than the Estimated Duration
86
Table 4.29: Delayed Activities by: (1) Early Start, (2) Late Start, (3) Early Finish, (4) Late Finish, and (5) Increased Duration
Grouped by CSI Divisions for All Projects in the Middle East
No. of
Activities
Division
(2)
Late
Start
(3)
Early
Finish
(4)
Late
Finish
(5)
Duration
DIV (02)
4,451
2,539
1,332
3,122
1,864
2,986
57.04
29.93
70.14
41.88
67.09
DIV (03)
24,416
13,660
8,586
16,562
9,587
15,116
55.95
35.17
67.83
39.27
61.91
DIV (04)
2,705
1,588
472
2,215
868
2,202
58.71
17.45
81.89
32.09
81.40
DIV (05)
2,537
1,814
857
2,023
1,021
1,577
71.50
33.78
79.74
40.24
62.16
DIV (06)
293
286
125
291
168
211
97.61
42.66
99.32
57.34
72.01
DIV (07)
4,232
2,831
1,355
3,260
1,654
2,398
66.90
32.02
77.03
39.08
56.66
DIV (08)
4,069
3,407
1,484
3,634
2,188
3,022
83.73
36.47
89.31
53.77
74.27
DIV (09)
12,584
9,853
4,513
11,094
5,538
8,214
78.30
35.86
88.16
44.01
65.27
DIV (10)
1,829
1,410
414
1,724
897
1,444
77.09
22.64
94.26
49.04
78.95
DIV (14)
1,540
1,029
226
1,307
836
1,085
66.82
14.68
84.87
54.29
70.45
DIV (15)
19,187
14,186
4,131
16,013
6,562
13,177
73.94
21.53
83.46
34.20
68.68
DIV (16)
13,282
9,380
3,579
10,865
6,074
8,475
70.62
26.95
81.80
45.73
63.81
Total
91,125
61,983
27,074
72,110
37,257
59,907
68.02
29.71
79.13
40.89
65.74
87
88
Table 4.30: Number of Delayed Activities behind Late Start Dates and Their Recovery Status
No. of Activities
CSI
Divisions
All
Delayed
Fully
Not
Partially
Late Start
Recovered
Recovered
Recovered
(No. of Delayed
Late Start/
Total No.)
Not
Partially
Recovered
Recovered
Recovered
Division 02
4,451
1,332
77
813
442
29.93
5.78
61.04
33.18
Division 03
24,416
8,586
1,406
4,478
2,702
35.17
16.38
52.15
31.47
Division 04
2,705
472
42
339
91
17.45
8.90
71.82
19.28
Division 05
2,537
857
50
582
225
33.78
5.83
67.91
26.25
Division 06
293
125
101
23
42.66
0.80
80.80
18.40
Division 07
4,232
1,355
153
680
522
32.02
11.29
50.18
38.52
Division 08
4,069
1,484
58
1,150
276
36.47
3.91
77.49
18.60
Division 09
12,584
4,513
364
2,655
1,494
35.86
8.07
58.83
33.10
Division 10
1,829
414
322
86
22.64
1.45
77.78
20.77
Division 14
1,540
226
19
175
32
14.68
8.41
77.43
14.16
Division 15
19,187
4,131
459
2,232
1,440
21.53
11.11
54.03
34.86
Division 16
13,282
3,579
375
2,285
919
26.95
10.48
63.84
25.68
TOTAL
91,125
27,074
3,010
15,812
8,252
29.71
11.12
58.40
30.48
89
90
Activity Description
ED
MAD
Std.
AER
Std/MAD
Dev
Percentiles
Min
25
50
75
80
85
90
95
Max
MER
MAR
D01
Excavation up to FDL
1,271
39
46
433
119
17
54
72
85
106
130
268
30
D06
1,271
15
42
37
280
89
19
29
51
57
70
85
131
270
18
D10
1,271
15
19
53
243
13
21
309
21
39
D19
1,271
11
42
37
382
89
19
29
51
57
70
85
131
270
25
D23
1,253
11
20
73
245
13
21
309
28
39
ED = Estimated Duration, MAD = Mean Actual Duration, AER = (Mean Actual Duration / Estimated Duration) Ratio, Std. Dev. = Standard Deviation, Min = Minimum,
Max= Maximum, MER = (Maximum / Estimated) Duration Ratio, and MAR = (Maximum / Mean Actual Duration) Ratio
Activity Description
ED
MAD
D02
1,271
10
Std.
Dev
16
AER
%
111
Std/MAD
%
160
Min
D03
Isolated footings
1,271
13
89
167
11
14
17
25
275
31
34
D08
1,271
15
11
15
73
136
14
16
18
21
32
315
21
29
D11
1,271
15
33
159
11
18
77
15
D12
1,271
25
24
16
96
66
12
20
31
33
37
42
54
116
D13
1,271
29
21
14
72
69
11
17
26
29
32
38
48
104
D16
1,271
13
114
167
11
14
17
25
275
39
34
D17
1,271
10
16
143
155
10
13
16
23
37
132
19
13
D20
1,271
11
11
21
100
187
11
15
22
29
42
308
28
28
D21
1,271
11
11
15
100
136
14
16
18
21
32
315
29
29
D24
1,054
30
136
95
453
70
57
131
195
211
238
277
322
386
13
D25
1,271
11
18
45
350
11
18
393
36
79
91
25
2
50
4
75
10
Percentiles
80
85
14
19
90
24
95
33
Max
MER
MAR
311
35
31
Table 4.33: Statistics of Divisions (04): Masonry Works Activities, (05): Metal Works Activities, (07): Thermal and Moisture Protection
Activities, and (08): Doors and Windows Activities
Division
ID
Activity Description
AER
%
Std/
MAD
%
ED
MAD
Std.
Dev
1,226
48
74
54
154
73
1,023
47
43
79
91
Percentiles
Min
Max
MER
MAR
191
348
181
218
372
25
50
75
80
85
90
95
37
57
92
108
127
150
184
34
76
120
D42
Block)
DIV 05
D58
DIV 05
D60
891
47
21
17
264
16
33
200
25
DIV 05
D66
905
14
17
50
241
44
208
15
30
DIV 07
D05
1,271
16
56
325
275
31
55
DIV 07
D09
1,271
15
13
27
321
319
21
80
DIV 07
D18
1,271
16
71
325
275
39
55
DIV 07
D22
1,268
11
13
36
322
319
29
80
DIV 07
D50
932
47
43
46
91
107
17
26
46
61
82
109
161
246
DIV 07
D51
923
47
46
49
98
107
14
27
56
67
95
124
167
265
DIV 08
D43
1,166
29
14
32
48
232
11
14
18
26
56
309
11
22
D57
671
47
74
56
157
76
34
63
99
109
123
147
178
399
DIV 08
D59
588
21
46
104
219
226
18
46
100
159
315
637
30
14
DIV 08
D62
904
47
42
60
89
142
19
61
71
82
100
136
655
14
16
92
Activity Description
ED
MAD
Std.
Dev
AER
Std/MAD
Min
25
50
75
80
85
90
95
Max
MER
MAR
D44
1,126
50
75
51
150
68
43
61
94
103
117
142
190
332
D45
1,045
50
21
31
42
147
14
25
29
35
42
65
372
18
918
47
17
37
36
220
12
16
22
44
81
597
13
35
1,072
34
24
26
264
11
17
32
252
28
898
47
13
35
28
271
14
24
35
52
390
30
831
47
10
28
21
281
11
22
39
385
39
D48
skirting
D49
D52
1,153
86
49
37
57
76
27
40
59
66
74
87
124
342
D53
1,022
58
65
65
112
100
17
40
96
108
126
179
213
461
D54
982
47
28
43
60
154
14
30
35
44
63
103
341
12
D55
873
47
13
20
28
158
15
20
26
34
46
171
13
D56
836
47
98
84
209
85
30
73
153
169
199
221
276
413
D63
520
30
130
108
433
83
42
89
198
222
245
290
343
470
16
D65
918
14
13
22
93
168
13
15
18
22
36
279
20
21
93
Division (16)
Division (15)
Divisions
Table 4.35: Statistics of Divisions (15): Mechanical Works Activities and (16): Electrical Works Activities
ID
Activity Description
ED
Std.
MAD
Dev
AER
Std/
MAD
Percentiles
Min
50
75
80
85
90
95
D26
1,253
12
21
23
175
110
10
15
24
27
30
35
52
210
18
10
D27
1,205
10
80
49
12
12
12
12
14
62
D28
1,202
47
18
19
203
10
10
14
591
13
66
D29
1,057
28
12
33
43
279
10
10
11
14
15
309
11
26
D30
1,054
11
64
62
10
10
10
11
14
62
D31
880
10
10
100
64
14
14
14
14
17
50
D32
869
11
13
183
123
14
14
14
17
19
198
33
18
D33
679
15
40
188
267
10
14
14
14
14
17
463
58
31
D34
611
12
240
73
14
14
14
14
14
73
15
D64
1,147
23
15
22
290
23
397
17
79
D35
999
35
74
89
211
120
10
45
110
118
135
181
241
701
20
D36
915
18
11
18
61
166
11
12
15
21
34
314
17
29
D37
605
23
20
32
87
162
11
17
21
81
101
243
11
12
D38
Install of DBs
896
23
11
20
48
179
10
11
11
14
21
175
16
D39
444
14
280
43
12
20
20
20
20
20
22
D40
627
23
19
32
83
169
11
17
21
79
101
243
11
13
D41
675
20
12
286
59
25
29
29
29
29
29
118
17
94
The statistical analysis for electro-mechanical works under divisions (15) mechanical
works and (16) electrical works show that the ratios AER for division (15) activities range
between 19% and 240% as shown in Table (4.35). Besides, the ratios AER for division (16)
activities range between 48% and 286%. Nevertheless, the MAR ratios for division (15)
activities vary from 5 to 79 times the MAD values. Meanwhile, the MAR ratios for division
(16) activities range between 2 and 29 times the MAD values.
The maximum durations are further investigated deeply to discover the relationship
between the percentile durations and the maximum duration of each activity. The value (95
Percentile = 130 days) mean that about 95 % of activities have actual duration equal to or less
than 130 days. The ratio (Percentile to Maximum Ratio PMR) represents the relationship
between different percentile durations and the maximum duration for the same activity are
summarized in Table (4.36) and illustrated in Figure (4.14). It is clearly observed that, the
increase rates of the ratios PMR have gradual increase till 85 percentile, and then these rates
suddenly converted to rapid increase as shown in Figure (4.14) and Table (4.36). Therefore,
these excessive increment values of activities' durations (after 85 percentiles) can be
disregarded from the next analyses.
In order to analyse the performance of construction activities and to quantify the impact
of different causes of delay on the activities durations, we selected seven activities that
represent different divisions in the project such as follows:
1. (D01 - Excavation up to foundation level (FDL)) to represent division (02) site works,
2. (D14 - Columns & slab for medium roof & parapet) to represent division (03) concrete
works,
3. (D51 Water Proof (WP) membrane screed & foam conc. for wet areas) to represent
division (07) thermal and moisture protection works,
4. (D57 - Fixing of aluminium doors & windows) to represent division (08) doors and
windows works,
5. (D56 - Interior painting works (putty & 1 st coat)) to represent division (09) finishes
works,
6. (D26 - External manhole & Ground Floor drainage) to represent division (15) mechanical
works, and
7. (D35 - Install of elec. pipes & Back Boxes for walls) to represent division (16) electrical
works.
95
Table 4.36: Relationship between the Actual Durations Percentiles and the Maximum Durations of Activities
Division
ID
ED
Mean
AD
Maximum
(Max / AD)
DIV 02
D10
15
309
DIV 02
D19
11
42
(Percentiles / Maximum) %
10
20
25
30
40
50
60
70
75
80
85
90
95
38.6
270
6.4
11
13
16
19
21
26
31
49
DIV 03
D25
11
393
78.6
DIV 03
D11
15
77
15.4
10
14
23
DIV 03
D24
30
136
386
2.8
13
15
17
26
34
40
47
51
55
62
72
83
10
11
11
14
16
19
22
26
31
36
43
55
DIV 04
D42
48
74
348
4.7
DIV 05
D60
47
200
25.0
17
DIV 05
D58
47
43
372
8.7
21
32
49
59
DIV 07
D09
15
319
79.8
11
13
15
19
25
33
44
66
DIV 07
D50
47
43
246
5.7
DIV 08
D43
29
14
309
22.1
18
DIV 08
D59
21
46
637
13.8
16
25
49
DIV 09
D49
47
10
385
38.5
10
12
17
21
23
27
39
46
DIV 09
D53
58
65
461
7.1
DIV 09
D63
30
130
470
3.6
10
13
19
32
38
42
47
52
62
73
DIV 15
D28
47
591
65.7
DIV 15
D34
12
73
6.1
12
12
12
12
12
12
12
19
19
19
19
19
19
10
10
18
18
18
18
20
20
28
28
28
28
34
DIV 15
D31
10
10
50
5.0
DIV 16
D36
18
11
314
28.5
11
DIV 16
D35
35
74
701
9.5
14
16
17
19
26
34
DIV 16
D39
14
22
38.6
27
36
41
45
45
55
86
91
91
91
91
91
91
96
120%
D01 Excavation UP TO FDL
D51 W.P. membrane screed & foam conc. for wet areas
25%
20%
14%
0%
0
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
Figure 4.14: Relationship between the Actual Durations Percentiles (among 1271 Buildings Construction) and the Absolute Maximum
Durations of the Selected Activities
97
It is found that the ratio of percentile values to maximum values (PMR) ranges between
7% and 49% of the maximum durations for divisions (02) activities. Also, the ratio PMR for
division (03) ranges between 17% and 83% of the maximum durations. In addition, the ratio
PMR ranges between 2% and 66% of the activities maximum durations for division (07) as
illustrated in Table (4.36). Therefore, it can be concluded that the ratio PMR for civil works
ranges between 2% and 83% as shown in Table (4.36).
Moreover, it is found that the ratio PMR for mechanical works division (15) ranges
between 2% and 34% of the maximum durations. In addition, PMR ratio for division (16)
electrical works range between 11% and 91% of the maximum durations as illustrated in
Table (4.36). Therefore, the recorded ratio PMR for electro-mechanical works ranges
between 2% and 91% of the maximum durations as manifested in Table (4.36).
98
Table 4.37: Relationship between the Actual Durations Percentiles and the Estimated
Duration of Activities
(Percentile Maximum Duration / ED) %
Division
ID
ED
10
20
25 30
40
50
60
70
75
80
85
90
95
100
2978
DIV 02
D01
44
67
78 100
133
189
333
500
600
800
944
1178
1444
DIV 03
D14
10
70
90
110 120
160
190
260
375
480
560
630
800
1000
2440
DIV 07
D51
47
13
26
30
32
45
57
74
106
119
143
202
263
355
564
DIV 08
D57
47
37
64
72
87
109
134
160
194
211
232
262
313
379
849
DIV 09
D56
47
26
52
64
79
113
154
213
285
326
360
424
470
588
879
DIV 15
D26
12
50
75
83
92
108
125
150
183
200
225
250
292
436
1750
DIV 16
D35
35
14
26
29
31
60
129
186
283
314
337
386
517
689
2003
Table 4.38: Relationship between the Actual Durations Percentiles and the Mean Values
of the Actual Durations of Activities
Division
ID
Mean
AD
10
20
25
30
40
50
60
70
75
80
85
90
95
100
DIV 02
D01
39
10
15
18
23
31
44
77
115
138
185
218
272
333
687
DIV 03
D14
33
21
27
33
36
48
58
79
114
145
170
191
242
303
739
DIV 07
D51
46
13
26
30
33
46
59
76
109
122
146
206
269
363
576
DIV 08
D57
74
23
41
46
55
69
85
102
123
134
147
166
199
241
539
DIV 09
D56
98
12
25
31
38
54
74
102
137
156
172
204
226
282
421
DIV 15
D26
21
29
43
48
52
62
71
86
105
114
129
143
167
249
1000
DIV 16
D35
74
12
14
15
28
61
88
134
149
159
182
245
326
947
The potential risks in Kuwait were extracted from a research conducted by Al-Tabtabai
(2002) on housing projects as summarized in Table (4.39). The associated risks of the seven
activities were allocated during many interviews with the planning and management teams in
the project. The contractors planning and management teams in the project allocated risks
percentages according the risks contribution in the delay for each activity in each building as
shown in Table (4.40). Then we calculated the contribution of the risk in the delay for each
activity in each building as illustrated in Table (4.40). The summation of all risks contribution
percentages for an activitys delay should equal to 100% as shown in Table (4.40).
99
Risk Title
Index Rank
0.870
0.860
0.840
0.830
1
2
3
4
0.820
0.810
0.800
RSK019
0.760
RSK032
RSK040
RSK041
RSK049
0.760
0.740
0.740
0.730
9
10
11
12
RSK001
RSK024
RSK038
RSK014
RSK030
0.730
0.720
0.720
0.720
0.720
13
14
15
16
17
RSK022
RSK006
RSK016
RSK054
RSK018
0.720
0.710
0.700
0.690
0.690
18
19
20
21
22
RSK023
RSK044
RSK045
RSK031
0.690
0.660
0.660
0.660
23
24
25
26
RSK005
RSK043
RSK002
RSK042
RSK017
0.650
0.650
0.640
0.640
0.630
27
28
29
30
31
0.630
0.630
0.610
32
33
34
RSK036
RSK015
RSK034
100
0.600
0.590
0.590
35
36
37
RSK012
RSK027
RSK048
RSK050
0.570
0.570
0.570
0.560
38
39
40
41
RSK053
RSK047
RSK051
RSK026
RSK007
0.560
0.560
0.550
0.530
0.530
42
43
44
45
46
RSK025
RSK028
RSK052
RSK003
RSK010
0.520
0.500
0.500
0.500
0.460
47
48
49
50
51
0.450
0.450
0.440
52
53
54
The quantitative analysis for the amount of delayed days for any risk is calculated according
to Equation
Delay (days) =Risk Contribution Percentage Activitys Delay ...... (4.3)
Where,
Activitys Delay = Actual Duration Estimated Duration..... (4.4)
Then we extracted the statistical properties for risks contribution in delay through using
IBM Statistics SPSS Ver. 22 software. The statistical properties of risks contribution of delay
were studied and evaluated as summarized in Table (4.41). As shown in Table (4.41), the
seven selected activities were exposed to only thirteen risks, while the investigation included
fifty four distinct risks as included in (Al-Tabtabai, 2002). The total number of completed
activities in all buildings is 6908 activities as illustrated in Table (4.41).It is found that the
risk slow financial and payment procedures has the highest influence on the activities by
101
number as it had influence on about 82% of the total number of the studied activities, as
illustrated in Table (4.41) and Figure (4.15). Then, the lack of planning and scheduling as it
affected about 58% of the total number of the studied activities, as manifested in Table (4.41)
and Figure (4.15). Whilst the lowest effect on the number of activities is observed for
contractors shop drawings errors, as illustrated in Table (4.41) and Figure (4.15).
The quantitative analysis of risk showed that the total amount of delays for the seven
activities in all buildings is 168,407 days as illustrated in Table (4.41). It is found that the
highest delay contributions was observed for the lack of planning and scheduling, then for
slow financial and payment procedures, as they contributed by about 27.7% and 23.1% of the
total delay of the seven activities in all buildings dues to the thirteen risks as illustrated in
Table (4.41) and Figure (4.15). It is worth noting that these two risks are included in the top
ten risks evaluated by Al-Tabtabai (2002) as shown in Table (4.42). The summation of these
two risks represents about 51% of the total delay. Therefore, the highest attention should be
directed to reduce or control the delays due to planning and slow payment procedures. In
addition, the lowest contribution in the total delay for the seven activities in all buildings is
observed for the unavailability of construction material as illustrated in Table (4.41) and
Figure (4.16).
102
Table 4.40: Example of Risks Contribution in the Delays Amounts and Percentages of One Activity in All Buildings
38
38
31
31
31
31
38
38
38
15
15
25
25
25
25
15
15
15
15
15
31
31
31
31
15
15
15
100
100
100
100
100
100
100
100
100
5
5
3
4
5
5
5
5
5
6
6
8
10
12
13
6
6
6
2
2
6
8
9
10
2
2
2
2
2
8
10
12
13
2
2
2
0
0
0
0
0
0
0
0
0
25-Dec-10
25-Dec-10
27-Dec-10
27-Dec-10
12
12
10
10
3
3
1
1
31
31
31
31
38
38
38
38
15
15
15
15
15
15
15
15
100
100
100
100
1
1
0
0
1
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
06-Jan-11
06-Jan-11
06-Jan-11
06-Jan-11
103
31
31
13
13
13
13
31
31
31
Total
RSK ..
16
16
24
31
37
40
16
16
16
25
25
33
40
46
49
25
25
25
RSK ..
18-Jun-11 13-Jul-11
18-Jun-11 13-Jul-11
10-Jun-11 13-Jul-11
03-Jun-11 13-Jul-11
28-May-11 13-Jul-11
25-May-11 13-Jul-11
03-May-11 28-May-11
03-May-11 28-May-11
03-May-11 28-May-11
1268
1269
1270
1271
Actual Duration
1
2
3
4
5
6
8
9
10
House No.
Table 4.41: Statistics of Risks Contribution in the Delay of the Selected Seven Activities in a Single Housing Project in Kuwait
Maximum
Contribution of
Delay
50 60 70
1,266
18.3
4,976
3.0
44
6 8
10 13 15
42
8 12 14 19 23 30 36
3,212
46.5
3,304
2.0
38
2 2
10
31
13 21 33
5,663
82.0
38,869
23.1
19
287
1 11 14 20 28 41
256
670
9.7
3,730
2.2
11
83
3 11 13 16 20 27
73
8 12 14 17 21 27 37
2,500
36.2
14,621
8.7
65
9 11 14 18 24
63
5 11 15 18 23 29 39
835
12.1
15,813
9.4
19
31
158
9 38 47 55 65 79
140
14 23 27 33 39 47 56
4,016
58.1
46,574
27.7
12
21
190
2 17 24 30 41 56
172
10 14 18 24 33
1,056
15.3
1,690
1.0
47
3 4
43
10 12 15 19
1,592
23.0
2,134
1.3
12
75
-1
6 8
12 17 26
62
-2
12 18 27 42
2,156
31.2
2,948
1.8
10
75
4 5
7 11 20
62
1,904
27.6
8,996
5.3
66
8 10 12 15 20
59
7 11 14 16 20 25 34
1,952
28.3
24,820
14.7
13
39
431
9 18 37 49 81
410
922
13.3
-69
0.0
27
-2
1 2
12
21
-10 -6
22 37 59
6,908
100.0
168,407
100.0
24
58
712
6 42 55 75 97 138
666
11 15 21
Risk
Affected Activities
Number
Mean
104
Percentiles
Std.
Range
Deviation
50 75 80 85 90 95
(Percentiles / Maximum) %
75
80
85
90
95
11 16
11 17 31
12 20
5.0
105
1.8
1.3
1.0
15.3
10.0
0.0
12.1
9.7
13.3
RSK045 - Unavailability of
Construction material
18.3
20.0
2.0
0.0
2.2
3.0
28.3
31.2
30.0
9.4
10.0
RSK024 - Lack of design drawings
coordination
40.0
25.0
RSK010 - Inspection procedures
50.0
30.0
RSK032 - Lack of planning and
scheduling
60.0
90.0
80.0
82.0
70.0
58.1
46.5
36.2
27.6
23.0
27.7
23.1
20.0
15.0
14.7
8.7
5.3
Figure 4.16: Percentage of Risk Contribution of the Total Delay of the Seven Activities
in a Single Housing Project in Kuwait
The comparisons between the delays percentiles due to each risk were concluded as
shown in Table (4.41) and Figure (4.17). It is found that there is gradual increase of the ratio
of delay percentiles to the maximum delay (DPM) relevant to all risks till 95 percentile, and
then a sudden increase occurs after 95 percentile. Therefore, the delay after 95 percentiles can
be considered extreme delays due to extraordinary or unjustified reasons.
120
100
All Risks
80
60
40
37
21
20
8
100
95
90
85
80
75
70
65
60
55
50
45
40
0
Percentiles
Figure 4.17: Relationship between the Delays Percentiles to the Maximum Delay (DPM)
of the Seven Activities Due to Different Risks
The summation of risks contributions in activities delay was calculated for each activity
as illustrated in Table (4.42). It is found that the greatest impact or delay was observed for
Activities: (1) D56 - Interior painting works (putty & 1 st coat); (2) D35 - Install of elec. pipes
&back boxes for walls; and (3) D01 - Excavation up to foundation level (FDL) as the sum of
delays occurred for these three activities in all buildings are 42,651, 38,212, and 37,684 days
respectively that represented 25%, 23% and 22% of all delays.
106
Table 4.42: Risks Contribution to the Delay in the Selected Seven Activities in a Single Housing Project in Kuwait
4,976
7,592
3,224
-182
st
11,080
4,418
262
16,989
6,493
9,256
3,730
3,351
3,304
-403
-69
4,571
14,621
107
15,813
46,574
2,498
3,038
1,690
3,730
28,284
15,758
831
38,869
5,959
15,221
4,976
37,684
-364
15,813
-273
Associated Risks
Activity Description
Delays (days)
1,690
2,134
2,948
8,996
18,255
1,829
4,612
22,991
38,212
24,820 -69
168,407
The quantitative impact of risks on activities was investigated on different types of work
such as civil works or electro-mechanical works. It is found that out of the thirteen risks only
ten risks affected the civil works as shown in Figure (4.18). Whilst, the electro-mechanical
activities are influenced by only four different risks out of the thirteen risks included in our
investigation as shown in Figure (4.18). In addition, it is found that the lack of planning and
scheduling has an impact of 37% of the total delay relevant to civil works (five activities) in
all buildings. Moreover, the slow financial and payment procedures had contributed to the
delay of civil works by 18%. Hence, the contribution of lack of planning and slow payment is
about 55% of the total delay occurred on the civil works activities (five activities) in all
buildings as shown in Figure (4.18).
On the other hand, it is found that the fluctuation of productivity level had the maximum
influence on the delay of electro-mechanical works. The fluctuation of productivity
contributed the total delays of electrical activities (two activities) in all buildings by
approximately 58% as illustrated in Figure (4.18). Also, it is found that the slow financial and
the payment procedures had the second rank in influencing activities of both electromechanical as well as civil works. However the contribution of slow payment procedures on
electro-mechanical works delay was greater than civil works delay as shown in Figure (4.18).
Consequently, adding more planning and enhancing scheduling techniques, expediting the
payment procedures, and improving the productivity rates can help in controlling and
managing about 65% of the total delays encountered in housing projects in Kuwait as shown
in Figures (4.16), and (4.18).
108
60%
40%
10%
50%
37%
30%
20%
4%
0%
RSK010 - Inspection procedures
0%
0%
0%
0%
0%
0%
0%
0%
RSK045 - Unavailability of
Construction material
0%
5%
10%
1%
58%
RSK040 - Poor manpower skills
70%
a)
RSK024 - Lack of design drawings
coordination
13%
15%
-5%
RSK032 - Lack of planning and
scheduling
20%
40%
37%
35%
30%
25%
18%
12%
7%
4%
3%
109
2%
2%
2%
0%
0%
0%
0%
b)
Figure 4.18: Risks Contribution of Delay for the Selected Seven Activities in a Single
Housing Project in Kuwait: a) Civil Works, and b) Electro-mechanical Works
110
High Rise Buildings, Commercial Malls, Hotels, Hospitals, Stadiums, Banks, Administration,
Residential, Infrastructure and Highway Projects as summarized in Table (5.1).
Project
TNT-HOS
MOI-JED
MSLH
Al-Salam
Avenues
CBK
CEG-GIRLS
HASAWI
KTC
PIFFS
PIFSS
SABAH
SLMH
STAD
SUBY
TNT
TVIG
Salalah
18
Complex
Barwa
19
Avenue
20 TWN-TWR
All
Projects
Estimated
Budget
(USD)
46,944,591
344,500,000
44,978,829
24,752,000
438,287,200
392,908,181
142,022,765
4,950,400
61,175,816
35,706,528
22,950,542
Number
of
Activities
17-Jun-2001
17-Feb-2013
11-Feb-2013
3-Feb-2013
31-Mar-2012
25-Apr-2011
20-Nov-2010
31-Dec-2010
31-May-2008
24-Dec-2013
7-Jan-2013
Contractua
l Duration
(Days)
915
720
885
505
899
1,095
1,219
518
1,177
738
730
15-Jun-2010
1-Apr-2011
14-Sep-2004
3-May-2009
25-Jul-2007
4-Jul-2010
27-Jun-2013
29-Mar-2013
12-Dec-2006
1-May-2012
1-Apr-2009
1-Jul-2012
1,109
729
820
1,095
617
729
469,865,505
27,667,107
195,364,244
146,203,059
12,984,270
47,596,395
20,075
2,974
6,108
1,816
1,885
6,541
Oman
1-Sep-2008
5-Sep-2010
735
9,156,040
3,870
Qatar
2-Feb-2008
12-Sep-2011
1,319
102,315,500
2,856
UAE
Middle
East
25-Oct-2009
30-Nov-2012
1,133
76,820,703
7,490
16-Dec-1998
24-Dec-2013
17,687
2,647,149,674
126,310
Country
Contractual
Start
Estimated
Finish
Egypt
KSA
KSA
Kuwait
Kuwait
Kuwait
Kuwait
Kuwait
Kuwait
Kuwait
Kuwait
16-Dec-1998
1-Mar-2011
11-Sep-2010
18-Sep-2011
15-Oct-2009
26-Apr-2008
21-Jul-2007
1-Aug-2009
12-Mar-2005
18-Dec-2011
9-Jan-2011
Kuwait
Kuwait
Kuwait
Kuwait
Kuwait
Kuwait
1,563
5,731
7,729
6,024
22,019
4,546
8,583
841
6,111
5,043
4,505
The study included a huge amount of various activities that exceeded 125,000 activities,
including engineering, procurement and construction (EPC) activities. The engineering and
procurement activities within the studied projects constitute a portion ranges from 6% to 68%
of relevant number of activities in each project. While, the overall of engineeringprocurement activities represent approximately 17% of the total number of activities in all
projects, as shown in Table (5.2).
111
PROJECT
Al-Salam
Avenues
CEG-GIRLS
HASAWI
KTC
MOI-JEDDA
MSLH
PIFFS
PIFSS
SABAH
SLMH
STAD
SUBY
TNT
CBK
TWN-TWR
Barwa Avenue
Salalah Complex
TNT-HOS
TVIG
TOTAL
No. of Activities
Engineering
Construction
Total
Procurement
(A)
(B)
(C)=(A)+(B)
3,249
2,775
6,024
18,006
4,013
22,019
7,010
1,573
8,583
269
572
841
4,454
1,657
6,111
5,119
612
5,731
7,057
672
7,729
2,694
2,349
5,043
3,841
664
4,505
19,010
1,065
20,075
2,617
357
2,974
4,783
1,325
6,108
1,709
107
1,816
1,405
480
1,885
3,957
589
4,546
6,922
568
7,490
2,506
350
2,856
3,090
780
3,870
1,103
460
1,563
5,832
709
6,541
104,633
21,677
126,310
Engineering -
(A)/(C) %
53.9
81.8
81.7
32
72.9
89.3
91.3
53.4
85.3
94.7
88
78.3
94.1
74.5
87
92.4
87.7
79.8
70.6
89.2
82.8
Procurement
(B)/(C) %
46
18
18
68
27
11
9
47
15
5
12
22
6
26
13
8
12
20
29
11
17.2
112
Table 5.3: Mean and Standard Deviation Values for Engineering - Procurement and
Construction Activities for All Projects in the Middle East
Engineering Procurement
Activities
Estimated
Number of Readings
Mean (days)
17,438
27.32
Actual
Estimated
Actual
66,546
85.20
312%
39.69
Construction
Activities
12.82
94.12
All Activities
Estimat
Actual
ed
83,984
15.83
734%
113.68
15.72
92.26
583%
130.27
23.61
127.05
829%
538%
Deviation Estimated)
Coefficient of Variation (COV %)
145%
133%
113
123%
138%
149%
138%
Figure 5.1: Case Studies of Evaluating the Best Probability Density Function to Represent Activities in Construction Projects
114
Following the same analysis for all projects, illustrate that the standard deviation of
engineering - procurement and construction activities actual durations represent about 3 and 8
times the same for the estimated values respectively. In general, the standard deviation for
actual durations represents about 5 times that for estimated durations as illustrated in Table
(5.3). It is worth noting that, the coefficient of variation (COV) for
estimated durations in
Table 5.4: Chi Square Test Results for Curve Fitting of Construction Projects
Activities in the Middle East
Case of Analysis
Beta
Gamma
Lognormal
Normal
Weibull
1,604
734
629
1,990
770
2,448
282
357
N/A
N/A
N/A
365
251
3,858
516
N/A
637
448
N/A
N/A
N/A
604
37
N/A
1,528
N/A
1,517
1,008
N/A
4,221
115
a)
b)
Figure 5.2: Probability Density Function PDF and Curve Fitting for Construction
Activities Durations for All Projects: a) Estimated Durations, and b) Actual Durations
116
a)
b)
Figure 5.3 Probability Density Function PDF and Curve Fitting for Engineering Procurement Activities Durations for All Projects: a) Estimated Durations, and
b) Actual Durations
117
a)
b)
Figure 5.4: Probability Density Function PDF and Curve Fitting for All Construction
and Engineering - Procurement Activities Durations for All Projects: a) Estimated
Durations, and b) Actual Durations
118
119
Table 5.5: Mean and Standard Deviation Values for Divisions (03), (09), (15), and (16)
Division (03) Activities
Division (09)
Division (15)
Division (16)
Activities
Activities
Activities
Estimated
Actual
Estimated
- Number of Readings
21,272
19,200
- Mean (days)
14.64
49.89
Actual
Estimated
Actual
11,119
10,529
16,937
15,622
10,962
9,531
17.32
73.38
15.65
117.88
16.35
133.67
341%
estimated)
- Std. Deviation (days)
Actual Estimated
25.06
74.05
424%
21.60
87.51
753%
25.33
132.02
818%
23.987
144.76
295%
405%
521%
604%
Figures (5.7) and (5.8) represent the behaviour of the estimated and the actual durations
for electro-mechanical works as well as the most popular curve fitting for both. It is very
clear in Figures (5.7) and (5.8) that the frequencies of the estimated and the actual durations
are not steady along the whole sample size. However, the actual durations are smoother and
more homogenous. In addition, it is found that the lognormal PDF is the best to describe the
electro-mechanical activities as illustrated in Figure (5.6) and (5.7) as well as the values of
Chi square tests as summarized in Table (5.6). On the other hand, it is apparent that using
normal PDF represents the lowest confidence choice as shown in Table (5.6).
120
Table 5.6 Chi Square Test Results for Curve Fitting of CSI Divisions Activities in the
Middle East
Division
Beta
Gamma
Lognormal
Normal
Weibull
N/A
544
484
677
1,184
358
324
222
3,593
2,212
N/A
311
255
N/A
791
1,099
805
980
1,460
N/A
805
83
76
360
1,517
367
157
58
N/A
2,243
1,060
202
214
1,118
232
358
324
222
3,593
2,212
N/A
177
114
233
294
47
77
37
140
605
N/A
86
78
4,462
220
285
288
300
4,173
3,181
N/A
314
239
796
1,157
N/A
405
384
570
3,038
771
981
833
N/A
N/A
N/A
840
714
1,026
2,635
N/A
1,197
1,067
386
3,753
316
79
91
4,086
719
N/A
43
25
67
94
230
137
51
1,419
1,429
N/A
1,574
1,065
2,030
5,365
N/A
2,084
2,714
N/A
3,325
N/A
2,292
2,100
3,776
8,903
7,954
860
874
N/A
5,304
121
a)
b)
Figure 5.5: Probability Density Function PDF and Curve Fitting for Division
(03 - Concrete Works) Activities Durations for All Projects: a) Estimated Durations,
and b) Actual Durations
122
a)
b)
Figure 5.6: Probability Density Function PDF and Curve Fitting for Division
(09 - Finishes Works) Activities for All Projects: a) Estimated Durations, and b) Actual
Durations
123
a)
b)
Figure 5.7: Probability Density Function PDF and Curve Fitting for Division
(15 - Mechanical Works) Activities for All Projects: a) Estimated Durations, and
b) Actual Durations
124
a)
b)
Figure 5.8: Probability Density Function PDF and Curve Fitting for Division
(16 - Electrical Works) Activities for All Projects: a) Estimated Durations, and
b) Actual Durations
125
126
Table 5.7: Statistics for a Single Projects Activities Classified by CSI Divisions
No. of
Activities
Mean
4,797
11
4,797
31
19,173
12
19,173
15
883
48
883
53
1,460
29
1,458
13
5,721
17
5,719
1,390
38
1,386
29
7,169
48
7,155
27
5,151
18
5,147
10
1,873
26
1,866
35
Division
(Mean Actual
/ Estimated)
%
269
127
111
45
50
75
55
58
136
Percentiles
Std.
Deviation
Range
15
36
308
22
30
Minimum
Maximum
Sum
25
50
75
85
90
95
55,093
11
15
15
15
15
309
148,366
20
39
57
72
109
29
233,118
11
15
15
25
29
369
370
295,117
15
23
32
56
48
48
42,384
48
48
48
48
48
48
29
197
202
47,202
33
48
66
78
92
117
14
33
14
47
42,028
14
23
47
47
47
47
29
396
397
19,015
21
41
85
14
40
47
98,399
11
15
47
47
47
16
182
183
49,413
15
23
35
18
29
47
53,324
29
47
47
47
47
47
38
236
237
39,876
10
41
70
83
111
16
72
14
86
345,559
47
47
50
58
58
86
35
372
372
191,251
12
37
55
69
100
13
41
47
93,007
10
11
28
28
47
47
21
462
463
53,910
10
14
18
26
17
18
35
48,648
23
23
35
35
35
35
47
244
244
65,878
54
95
111
131
127
The Graphical statistical study and tests of goodness of fit for construction activities
show that, the probability density function of the actual durations for each activity tends to be
represented by the Lognormal distribution as illustrated in Figures from Figures (5.9) to
(5.15) and Table (5.8). The Figures from (5.9) to (5.15) represent activities for the divisions
(02) Site works, (03) concrete works, (07) thermal and moisture protection works, (08) doors
and windows works, (09) finishes works, (15) mechanical works, and (16) electrical works
respectively. As a general note, the lognormal distribution is recorded as the best distribution
to represent activities in a single project in Kuwait, then the second best fit is the gamma
distribution as shown in Table (5.9). The results of Chi square test for the 66 activities show
that, there are 28 activities that are best represented by the lognormal distribution and 22
activities are best represented by the gamma distribution as shown in Table (5.9).
Table 5.8: Chi Square Test Results for Curve Fittings of Activities in a Single Project in
Kuwait
Activity
D01- Excavation up to Foundation
D03- Isolated Footings
D05- Bituminous Paint to Surfaces
D06 Backfill to till Ground Beams
D08- Casting of Ground Beams
D26- External Manhole and Drainage
D29- Water Supply Pipes
D35- Electrical Pipes for Walls
D36- Pulling Electrical Wiring
D43- Frames for Doors and Windows
D51- WP for Wet Areas
D52- External Facade Works
D54- Ceramic Tiles - Walls and Floors
D62- Wooden Doors
Beta
71
N/A
N/A
105
33
34
30
9
18
N/A
42
17
362
N/A
Gamma
42
32
55
82
25
40
39
28
14
13
14
11
31
22
Lognormal
24
22
14
78
8
26
14
5
4
9
10
5
10
17
Normal
4,73
9,547
1,510
1,201
16,61
498
212
7
721
272
452
143
1,600
142
Weibull
158
8,441
1,185
2,381
5,388
206
4,914
100
1,420
2,338
101
370
1,004
33
Table 5.9: Ranks of Curve Fitting for Each Probability Distribution Function According
to Chi Square Test Results
Probability Density Function
Beta
Gamma
Lognormal
Normal
Weibull
1
5
22
28
3
2
128
2
9
27
17
0
7
Rank of Distribution
3
4
5
17
8
0
9
0
2
9
5
1
12
31
14
13
16
22
N/A
27
6
6
6
6
a)
b)
Figure 5.9: Probability Density Function PDF and Curve Fitting for Division (02 - Site
Works) Activities Actual Durations for One Project: a) Excavation up to Foundation,
and b) Backfill till Ground Beams
129
a)
b)
Figure 5.10: Probability Density Function and Curve Fitting for Division (03 - Concrete
Works) Activities Actual Durations for One Project: a) Isolated Footings, and
b) Casting of Ground Beams
130
a)
b)
Figure 5.11: Probability Density Function and Curve Fitting for Division (07 - Thermal
and Moisture Protection Works) Activities Actual Durations for One Project:
a) Bituminous Paint to Surfaces, and b) WP for Wet Areas
131
a)
b)
Figure 5.12: Probability Density Function and Curve Fitting for Division (08 - Doors
and Windows Works) Activities Actual Durations for One Project: a) Frames for Doors
and Windows, and b) Wooden Doors
132
a)
b)
Figure 5.13: Probability Density Function and Curve Fitting for Division (09 - Finishes
Works) Activities Actual Durations for One Project: a) External Facade Works, and
b) Ceramic Tiles - Walls and Floors
133
a)
b)
Figure 5.14: Probability Density Function and Curve Fitting for Division
(15 - Mechanical Works) Activities Actual Durations for One Project: a) External
Manhole and Drainage, and b) Water Supply Pipes
134
a)
b)
Figure 5.15: Probability Density Function and Curve Fitting for Division
(16 - Electrical Works) Activities Actual Durations for One Project: a) Electrical Pipes
for Walls, and b) Pulling Electrical Wiring
135
require fast completion, a thorough study must be made to determine the contract duration.
Where unrealistic contract duration is imposed, this will obviously represent an inevitable
risk to the performance of the contractor and may force the contractor either to accelerate the
progress of the works and neglect the desired quality, or to perform the works as required but
not on time (Falqi, 2004). On the other hand, the successful execution of construction
projects and keeping them within budgeted cost and defined schedules depend on
a methodology that requires sound engineering judgment (Hancher and Rowing, 1981; Falqi,
2004).
The conventional estimation of activities duration used in Critical Path Method (CPM)
technique depends on the resulted deterministic value from the average productivity rates of
all resources assigned to the activity. Using this approach does not guarantee that the project
would finish on time (Lana, 2006). Nevertheless, the Program Evaluation and Review
Technique (PERT) uses three-point estimate instead of the traditional single-point estimate
for each activitys duration (Uher, 2003). All classic techniques impoverished considering
the effects of the potential risks that the construction project may encounter. Therefore, the
traditional scheduling technique stands powerless in front of numerous degrees of
uncertainties and risks that the construction projects may experience. Consequently, the
involved parties in the construction industries might inevitably be jeopardized to
unexpectedly immense losses.
The major objective of the current study is to provide a reliable technique for estimating
the duration of activities in the construction projects. This technique considers the actual
behaviour and performance of the similar real activities in large construction projects, which
are exposed to real risks that affect the performance of these activities. A variety of distinct
regression models were generated to delineate the relationship between the estimated
136
deterministic durations or budgets and their actual durations. The generated models provide
practical and easy tool for estimating the activity duration stochastically. This derivation
expands the previously reported studies and evaluates the actual results from currently
running projects or completed before this study.
137
stochastically. The statistical properties of activities will be used for preparing stochastic time
schedules for construction projects in the Middle East countries.
138
Figure 6.1: Cases of Analysis of Regression Models for the Estimated Durations or Budgets and the Actual Durations in Construction
Projects
139
6.3.1.
The generated regression models are classified according to the type of activities as: (1)
Engineering - Procurement activities and (2) Construction activities. The descriptive
statistical analysis for 66,500 construction activities and 17,500 engineering - procurement
activities grouped by the estimated duration value is summarized in Table (6.1). Comparing
the values of activities durations over 90 days in the current study with similar ones in
Al-Momanis (2000) study has proved that they are close to each other.
As clearly illustrated in Table (6.1) the smaller the estimated duration, the higher
duration slippage is. The ratio (Z) defines the relationship between the mean values of the
actual durations and the estimated duration. Z-values are high for small estimated durations.
Meanwhile, Z-values are smaller for high values of estimated durations. This unexpected
ratio might be attributed to the explanation by (Willis, 1986; Callahan et al., 1992) as there is
no time margin to compensate the improperly estimated small durations. On the other hand,
for the case of higher values of estimated durations, there is plenty of time to recover the
delays internally on the level of every activity. This result leads to the recommendation for
contractors to prepare the work breakdown structure for no less than about 15 days.
Table (6.1), also shows that for estimated durations less than four days, the Z-values for
engineering - procurement activities are higher than those for construction activities. Then
Z-values for engineering - procurement activities become smaller than construction activities
for all values of estimated durations. The deduced coefficient of variation (COV) for actual
duration values from Table (6.1) shows that the COV for construction activities ranges
between 0.72and 2.1, while COV for engineering - procurement ranges between 0.65 and
2.65. Furthermore, the values of COV for engineering - procurement activities are not always
higher than construction activities for similar values of estimated duration.
Planners and projects managers can utilize the mean and standard deviation values from
Table (6.1) as well as the probability density function resulted in the previous chapters to
forecast the projects overall duration. Notwithstanding, forecasting projects overall duration
based on the proposed regression models utilizing the lognormal distribution tends to be
greater than that calculated using conventionally estimated activities. But, the validation tests
showed that the forecasted projects durations are more realistic. Consequently, these
forecasted projects durations could oblige the contractors to implement different
methodologies and alternative plans to reduce the projects duration.
140
Table 6.1: Statistics of Actual Duration Values for Construction Activities and
Engineering- Procurement Activities
Engineering Procurement Activities
Mode
Std. Deviation
(days)
COV = Std / AD
Z = Mean AD /
ED
Number of
Activities
(AD)
Mean Actual
Duration (days)
Median
Mode
Std. Deviation
(days)
COV = Std / AD
Z = Mean AD /
ED
1
2
3
4
5
6
7
8
9
1,059
4,413
3,987
3,638
4,086
4,591
3,340
4,033
1,120
44
82
62
73
83
98
93
70
80
20
28
8
17
17
41
31
24
25
1
1
2
3
5
6
7
8
9
59.1
110.3
107.2
108.2
158.0
122.2
140.0
100.6
114.2
1.3
1.3
1.7
1.5
1.9
1.2
1.5
1.4
1.4
44.1
41.1
20.7
18.1
16.6
16.3
13.3
8.7
8.9
1,927
39
56
19
75
128
285
96
4
86
88
35
94
75
22
36
44
66
55
70
6
27
39
6
10
30
15
7
1
6
3
4
6
6
30
4
105.6
99.7
92.9
152.5
85.9
43.0
65.1
45.5
109.2
1.2
1.1
2.6
1.6
1.1
2.0
1.8
1.0
1.7
85.6
44.2
11.7
23.6
15.0
3.7
5.2
5.4
7.3
10
11
12
7,858
590
5,757
71
111
118
22
61
58
10
8
7
109.0
124.6
138.4
1.5
1.1
1.2
7.1
10.1
9.9
374
7
1,277
42
120
58
19
42
20
12
12
12
57.7
118.0
79.3
1.4
1.0
1.4
4.2
10.9
4.8
13
2,602
36
18
10
75.7
2.1
2.8
43
46
43
43.7
0.9
3.6
14
3,809
109
60
14
125.5
1.1
7.8
5,516
65
25
13
90.9
1.4
4.6
15
2,945
135
79
14
159.5
1.2
9.0
599
54
23
16
67.2
1.3
3.6
20
829
141
105
19
137.2
1.0
7.0
159
91
48
22
100.4
1.1
4.5
25
30
40
50
60
90
120
150
615
604
165
1,778
144
119
10
4
111
161
127
76
130
152
380
274
61
116
90
53
97
115
355
151
4
34
46
4
61
19
50
5
138.7
160.8
127.8
90.0
108.6
123.9
318.4
351.7
1.2
1.0
1.0
1.2
0.8
0.8
0.8
1.3
4.4
5.4
3.2
1.5
2.2
1.7
3.2
1.8
258
917
108
54
547
347
324
144
77
92
84
145
126
149
188
218
29
45
49
105
98
120
170
197
28
29
11
9
47
36
47
196
116.9
95.2
90.9
148.5
113.6
116.6
123.9
141.7
1.5
1.0
1.1
1.0
0.9
0.8
0.7
0.6
3.1
3.1
2.1
2.9
2.1
1.7
1.6
1.5
87
208
186
33
153.5
0.7
1.2
(ED)
Estimated
Duration
(days)
Number of
Activities
Median
Construction Activities
(AD)
Mean
Actual
Duration
(days)
180
6.3.2.
The regression models for construction activities were generated from the three countries
in our study to provide a regional model in the Middle East countries. The investigation
comprised 66,500 distinct construction activities to develop a regression model describing the
relationship between activities estimated durations and their relevant mean actual durations
as well as the relationship between the estimated durations and the standard deviation for
actual activities. These regression models can be utilized to estimate the mean value and the
standard deviation for activities based on their initially estimated durations through
traditional techniques and average productivity rates for resources loaded on each activity.
The extracted mean and standard deviation values for each activity will then be used in any
simulation process to predict a more reliable projects overall duration. These regression
models can be utilized to predict the average actual duration and standard deviation for any
141
activity based on its relevant estimated duration extracted by activitys scope and productivity
rate.
The general model that represents the construction activities in the three countries is
described by Table (6.2) and Equations (6.1) and (6.2) for mean values and standard
deviation values respectively.
y = a + b. ln(x) .... (6.1)
y = a + b. x 2 ...... (6.2)
Where y is the average value of actual duration, x is the estimated duration value
and a, b are constants summarized in Table (6.2).
As shown in Figure (6. 2) there is a rapid increasing slope of the average actual duration
against estimated duration until the estimated duration reaches about 30 days, then the
increasing rate remains constant with moderate slope. While, the standard deviation for actual
durations increased slowly till the estimated durations reaches 40 days then the slope
increases rapidly.
142
200
150
100
50
0
0
20
40
60
80
100
120
a) Mean Value
250
200
150
100
50
0
0
20
40
60
80
100
120
140
160
180
b) Standard Deviation
Figure 6.2: Regression Models for Estimated Durations of Construction Activities in the
Three Countries and Actual Durations Statistics: a) Mean, and b) Standard Deviation
143
Another analysis on the construction activities was conducted for each individual country
in order to estimate the impact of potential risks and uncertainty level specific to each
country. The regression models extracted for construction activities in Egypt are illustrated in
Figure (6.3). The relationship between the estimated durations and the actual durations
statistics (Mean and standard duration values) and are best represented by Equations (6.2) and
Table (6.2). As shown in Figure (6.3) the slope of average actual duration is very high until
the estimated duration of about ten days. Then the slope slowly decreases until the estimated
duration of 30 days.
The extracted regression models for construction activities in Kuwait are illustrated in
Figure (6.4). The relationship between the estimated durations and the mean values of the
actual durations is best represented by Equations (6.1) and Table (6.2). Meanwhile, the
relationship between estimated durations and standard deviation values of actual durations is
best represented by Equation (6.3) ant Table (6.2).
As shown in Figure (6.4) the average actual durations in Kuwait are rapidly increased
until the estimated durations reach about 20 days. Then the slope slowly decreases until the
estimated duration of 30 days, and then the curve seems to be a straight line with fixed slope.
Besides, the slope of standard deviation for the actual durations is very high until the
estimated duration of about ten days. Then the standard deviation curve becomes horizontal
for all estimated durations as shown in Figure (6.3b).
y = a + b/x....(6.3)
In general, the values of average actual durations relevant to estimated durations less
than 20 days are higher in the Egypt and Kuwait. Furthermore, the highest values for this
range are observed in Kuwait due to fluctuated level of productivity rates, the strict
application of quality control programs, the lack of manpower in local market, and lack of
planning and control by the subcontractors (Koushki et al., 2005).
144
250
200
150
100
50
0
0
10
15
20
25
30
a) Mean
300
250
200
150
100
50
0
0
10
15
20
Estimated Duration (days)
25
30
35
b) Standard Deviation
Figure 6.3: Regression Models for Estimated Durations of Construction Activities in
Egypt and Actual Durations Statistics: a) Mean, and b) Standard Deviation
145
250
200
150
100
50
0
0
20
40
60
80
100
120
140
a) Mean
180
160
140
120
100
80
60
40
20
0
0
20
40
60
80
100
120
140
160
b) Standard Deviation
Figure 6.4: Regression Models for Estimated Durations of Construction Activities in
Kuwait and Actual Durations Statistics: a) Mean, and b) Standard Deviation
146
The extracted regression models for construction activities in the Kingdom of Saudi
Arabia are illustrated in Figure (6.5). The relationship between the estimated durations and
mean values of actual durations is best represented by Equations (6.4) and Table (6.2).
Meanwhile, the relationship between the estimated durations and standard deviation values of
actual durations is best represented by Equation (6.1) ant Table (6.2).
As shown in Figure (6.5) the relation between average actual and estimated durations in
the KSA is a linear with a quiet high rate of slope from the beginning till the end. While, the
standard deviation values of actual durations in Saudi Arabia are rapidly increased until the
estimated durations reach about 20 days. Then the curve seems to be a straight line with fixed
slope till the end.
y = a + b. x.....(6.4)
350
300
250
200
150
100
50
0
0
20
40
60
a) Mean
147
80
100
120
100
80
60
40
20
0
0
10
20
30
40
50
60
b) Standard Deviation
Figure 6.5: Regression Models for Estimated Durations of Construction Activities in
KSA and Actual Durations Statistics: a) Mean, and b) Standard Deviation
6.3.3.
148
600
500
400
300
200
100
0
0
100
200
300
400
500
600
500
600
a) Mean
200
150
100
50
0
0
100
200
300
400
b) Standard Deviation
Figure 6.6: Regression Models for Estimated Durations of (Engineering-Procurement
Activities) Three Countries and Actual Durations Statistics: a) Mean, and b) Standard
Deviation
149
6.3.4.
The study of the actual behaviour of critical activities included approximately 12,900
critical activities representing about 15.4% of a sample size that equals about 84,500
activities. The construction critical activities represent about 14% percentage of the total
construction activities, while the critical engineering - procurement activities represent about
20% percentage of the total engineering procurement activities.
Equation (6.1) and Table (6.2) represent the regression models for critical activities in all
phases. Besides, Equation (6.1) and Table (6.2) represent the regression models for
construction critical activities. While, the engineering - procurement critical activities are
represented by Equation (6.4) and Table (6.2).As clearly shown in Figure (6.7) the ratio (RD)
in construction activities is higher than engineering procurement activities till the estimated
duration of 20 days due to the fluctuated levels of productivity and shortage of manpower.
While, the ratio (RD) alters higher for engineering procurement than construction for the
estimated durations greater than 80 days due to delays in material delivery and poor
coordination between main contractors and international suppliers [Al-Khalil & Al-Ghafly,
1999; Abdul Rashid and Bakarman, 2005; Koushki et al., 2005]. The r2 coefficient and
constant values for regression models of critical activities are summarized in Table (6.2).
160
140
120
100
80
60
40
20
0
0
20
40
60
80
a) All Phases
150
100
120
140
160
140
120
100
80
60
40
20
0
0
20
40
60
80
100
120
140
b) Construction
200
180
160
140
120
100
80
60
40
20
0
0
20
40
60
80
100
120
c) Engineering - Procurement
Figure 6.7: Regression Models for Actual Durations of Critical Activities in the Three
Countries Grouped by Phase of Work: a) All Phases, b) Construction, and
c) Engineering Procurement
151
152
250
200
150
100
50
0
0
20
40
60
80
a) Mean
120
100
80
60
40
20
0
0
20
40
60
80
100
120
140
160
180
200
b) Standard Deviation
Figure 6.8: Regression Model for Estimated Durations for Construction Activities in All
Projects in Kuwait under Division (02 Site Works) and Actual Durations Statistics:
a) Mean, and b) Standard Deviation
153
200
180
160
140
120
100
80
60
40
20
0
0
20
40
60
80
100
120
100
120
a) Mean
180
160
140
120
100
80
60
40
20
0
0
20
40
60
80
b) Standard Deviation
Figure 6.9: Regression Model for Estimated Durations for Construction Activities in All
Projects in Kuwait under Division (03 Concrete Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation
154
The third analysis was carried out on masonry construction activities in all projects in
Kuwait. The analysis shows that division (04 masonry works) is best represented by Equation
(6.1) and Table (6.-2) for both the mean values and the standard deviation values of the actual
durations. Figure (6.10a) shows that the slope between the mean values of the actual
durations and the estimated durations starts with a rapid increase till an estimated duration of
about 10 days. Then the slope increases moderately till an estimated duration of about 25
days. Finally, the slope seems to be a straight line with fixed slope. In addition, Figure
(6.10b) shows that the slope between the standard deviation values of the actual durations and
the estimated durations starts with a high increase till an estimated duration of about 20 days.
Then the slope becomes a straight line with fixed slope till the end.
The forth analysis was carried out on doors and windows construction activities in all
projects in Kuwait. The analysis shows that division (08 doors and windows works) is best
represented by Equation (6.4) and Table (6.2) for both the mean values and the standard
deviation values of actual durations. Figure (6.11) show that the slope between the mean
values of the actual durations and the estimated durations is higher than the slope between the
standard deviation values of the actual durations and the estimated durations.
The fifth analysis was carried out on finishes construction activities in all projects in
Kuwait. The analysis shows that division (09finishes works) is best represented by Equation
(6.3) and Table (6.2) for the mean values of actual durations. In addition, the relationship
between the standard deviation values of actual durations and the estimated durations is best
represented by Equation (6.6) and Table (6.2).Figure (6.12) shows that the slope between the
mean values of the actual durations and the estimated durations starts with a high slope till an
estimated duration of about 20 days then the slope becomes horizontal till the end.
Furthermore, the slope between the standard deviation values of the actual durations and
estimated durations can be considered horizontal from an estimated duration of about 10 days
till the end as shown in Figure (6.12).
y = a + b/x 2 .(6.6)
155
300
250
200
150
100
50
0
0
10
20
30
40
50
60
70
50
60
70
a) Mean
160
140
120
100
80
60
40
20
0
0
10
20
30
40
b) Standard Deviation
Figure 6.10: Regression Models for Estimated Durations of Construction Activities in
All Projects in Kuwait under Division (04 Masonry Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation
156
350
300
250
200
150
100
50
0
0
20
40
60
80
100
120
140
a) Mean
180
160
140
120
100
80
60
40
20
0
0
20
40
60
80
100
120
140
160
180
200
b) Standard Deviation
Figure 6.11: Regression Models for Estimated Durations of Construction Activities in
All Projects in Kuwait under Division (08 Doors and Windows Works) and Actual
Durations Statistics: a) Mean, and b) Standard Deviation
157
100
80
60
40
20
0
0
20
40
60
80
60
80
a) Mean
100
80
60
40
20
0
0
20
40
Estimated Duration (days)
b) Standard Deviation
Figure 6.12: Regression Models for Estimated Durations of Construction Activities in
All Projects in Kuwait under Division (09 Finishes Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation
158
The sixth and the seventh studies are relevant to divisions (15 mechanical works) and
(16 electrical works) respectively. The sixth analysis was carried out on mechanical
construction activities that include plumbing, firefighting and HVAC works in all projects in
Kuwait. The analysis shows that division (15 mechanical works) is best represented by
Equation (6.1) and Table (6.2) for the mean values of the actual durations. In addition, the
relationship between the standard deviation values of actual durations and the estimated
durations is best represented by Equation (6-3) and Table (6.2). Figure(6.13) shows that the
slope between the mean values of the actual durations and the estimated durations starts with
high slope till an estimated duration of about 20 days then the slope increases moderately till
the end. Furthermore, the slope between the standard deviation values of the actual durations
and the estimated durations starts with very rapid increase till estimated duration of 10 days,
and then tends to become horizontal till the end as shown in Figure (6.12).
y = a + b/..(6.7)
The seventh analysis was carried out on electrical construction activities that include
power, fire alarm and telecommunication works in all projects in Kuwait. The analysis shows
that division (16 electrical works) is best represented by Equation (6.7) and Table (6.2) for
the mean values of the actual durations. In addition, the relationship between the standard
deviation values of the actual durations and the estimated durations is best represented by
Equation (6.5) and Table (6.2). Figure (6.14) shows that the slope between the mean values
of the actual durations and the estimated durations starts with a high slope till an estimated
duration of about 15 days then the slope increases moderately till the end. Furthermore, the
slope between the standard deviation values of the actual durations and the estimated
durations tends to become a linear with a moderate slope till the end as shown in Figure
(6.14).
As a general note, all regression models for the construction activities considered in our
study in Kuwait follow nonlinear models except division (08 doors and windows works)
activities. Furthermore, most regression models for the construction activities in Kuwait start
with rapid increasing slopes till estimated duration up to about 15 days. Then most models
slopes are slowly increased except for division (09 finishes works) that tends to become
horizontal.
159
250
200
150
100
50
0
0
20
40
60
80
a) Mean
125
120
115
110
105
100
95
90
85
0
10
20
30
40
50
60
70
b) Standard Deviation
Figure 6.13: Regression Models for Estimated Durations of Construction Activities in
All Projects in Kuwait under Division (15 Mechanical Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation
160
250
200
150
100
50
0
0
10
20
30
40
50
60
a) Mean 16
180
160
140
120
100
80
60
40
20
0
0
10
20
30
40
50
60
70
b) Standard Deviation
Figure 6.14: Regression Models for Estimated Durations of Construction Activities in
All Projects in Kuwait under Division (16Electrical Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation
161
162
250
200
150
100
50
0
0
10
20
30
40
50
60
70
100
120
140
a) Mean
100
80
60
40
20
0
0
20
40
60
80
b) Standard Deviation
Figure 6.15: Regression Models for Estimated Durations of All Construction Activities
in a Single Project in Kuwait and Actual Durations Statistics: a) Mean, and
b) Standard Deviation
163
The analysis of division (02 site works) activities in a single project in Kuwait shows
that, the regression model is best represented by Equations (6.5) and Table (6.2) for the case
of mean values of the actual durations. Also, it is found that the case of the standard deviation
values of the actual durations is best represented by Equation (6.1) and Table (6.2). Besides,
the slope between mean values of the actual durations and the estimated durations starts with
a moderate slope and continues till the end as shown in Figure (6.16). In addition, the slope
between the standard deviation values of the actual durations and the estimated durations
starts with a rapid increase till an estimated duration of about 10 days. Then the slope
increases moderately between the estimated durations 10 and 25 days. Then the slope
increases with a slow fixed slope till the end as shown in Figure (6.16).
Furthermore, the analysis of division (03 concrete works) activities in a single project in
Kuwait shows that, the regression model is best represented by Equations (6.2) and Table
(6.2) for the case of the mean values of the actual durations. Also, it is found that the case of
the standard deviation values of actual durations is best represented by Equation (6.5) and
Table (6.2). Besides, the slope between the mean values of the actual durations and the
estimated durations starts with a slow slope till an estimated duration of about 30 days. Then
the slope of the actual durations increases rapidly till the end as shown in Figure (6.17). In
addition, the slope between the standard deviation values of the actual durations and the
estimated durations starts with a moderate increase till an estimated duration of about 10
days. Then the slope increases slowly from an estimated durations 10 days till the end as
shown in Figure (6.17).
The analysis of division (15 mechanical works) activities in a single project in Kuwait
shows that, the regression models are best represented by Equations (6.5) and Table (6.2) for
the case of the mean values of the actual durations and by Equation (6.3) and Table (6.2) for
the case of the standard deviation values of actual durations. Besides, the curve of the mean
values start with a rapid slope till an estimated duration of about 10 days, and continues with
a moderate slope till the end as shown in Figure (6.18). In addition, the slope of the standard
deviation values increases rapidly till an estimated duration of about 10 days. Then the slope
becomes horizontal till the end as shown in Figure (6.18).
164
250
200
150
100
50
0
0
10
20
30
40
Estimated Duration (days)
50
60
70
a) Mean
100
80
60
40
20
0
0
20
40
60
80
b) Standard Deviation
Figure 6.16: Regression Models for Estimated Durations of Construction Activities in
a Single Project in Kuwait under Division (02 Site Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation
165
180
160
140
120
100
80
60
40
20
0
0
10
20
30
40
50
60
50
60
a) Mean
80
60
40
20
0
0
10
20
30
40
b) Standard Deviation
Figure 6.17: Regression Models for Estimated Durations of Construction Activities in
a Single Project in Kuwait under Division (03 Concrete Works) and Actual Durations
Statistics: a) Mean, and b) Standard Deviation
166
180
160
140
120
100
80
60
40
20
0
0
10
20
30
40
50
60
70
50
60
70
a) Mean
70
60
50
40
30
20
10
0
0
10
20
30
40
b) Standard Deviation
Figure 6.18: Regression Models for Estimated Durations of Construction Activities in
a Single Project in Kuwait under Division (15 Mechanical Works) and Actual
Durations Statistics: a) Mean, and b) Standard Deviation
167
Table 6.2: Regression Models, Model Constants, and r2 Coefficients for All Cases for the Relationship between the Estimated Durations
and the Statistics of the Actual Durations
Case of
Analysis
Equation
Equation
No.
Construction activities grouped by country
Mean Value
Constant
a
b
r
Coefficient
Equation
No.
Standard Deviation
Constant
Equation
a
b
43.152146
25.791774
0.722268
6-2
y = a + bx2
6-1
y = a + b. ln(x)
y = a + b. ln(x)
-31.315662
57.501272
0.637207
6-1
y = a + b. ln(x)
Kuwait
6-1
y = a + b. ln(x)
39.278186
28.153913
0.716789
6-3
y = a + b/x
KSA
6-4
y = a + b. x
25.808561
2.660858
0.760414
6-1
52.247198
0.935995
0.941770
All Countries
6-1
Egypt
r2
Coefficient
108.582178
0.004425
0.759478
-17.1794
79.36755
0.955573
144.093000
-86.754800
0.757840
y = a + b. ln(x)
-7.696580
24.762040
0.578467
6-1
y = a + b. ln(x)
13.408429
23.270368
0.660946
6-4
y = a + b. x
6-1
y = a + b. ln(x)
-6.546497
28.374720
0.845170
6-1
y = a + b. ln(x)
-8.330252
29.038051
0.809375
6-4
y = a + b. x
2.923219
1.662299
0.933647
44.141265
0.844100
6-3
y = a + b/x
102.822900
-62.393000
0.863192
6-5
y = a + b. ln(x)
y = a + b
-10.956444
17.486019
0.945975
6-4
y = a + b. x
51.878760
0.866990
0.762841
DIV 04
DIV 08
6-1
6-4
y = a + b. ln(x)
y = a + b. x
-71.293389
42.765386
76.259028
2.332210
0.860520
0.857364
6-1
6-4
y = a + b. ln(x)
y = a + b. x
36.929980
70.447588
23.249090
0.522886
0.530186
0.553331
DIV 09
6-3
y = a + b/x
75.103390
-91.726218
0.731517
6-6
y = a + b/x2
85.586425
-53.609215
0.714495
DIV 15
6-1
72.249936
27.216517
0.757291
6-3
y = a + b/x
118.022700
-25.080000
0.660659
DIV 16
6-7
y = a + b. ln(x)
y = a + b
232.291363
-235.85607
0.838533
6-5
y = a + b
109.363947
5.971599
0.775508
DIV 02
6-1
DIV 03
6-5
y = a + b
14.575190
20.443443
0.861593
6-3
y = a + b/x
79.636910
-61.103100
0.726438
DIV 02
6-5
y = a + b
-36.682006
30.708906
0.983824
6-1
y = a + b. ln(x)
19.967720
15.125640
0.776989
DIV 03
6-2
57.499591
0.031131
0.924581
6-5
y = a + b
21.624833
6.033689
0.696109
DIV 15
6-5
= + . 2
y = a + b
4.876508
19.171406
0.942550
6-3
y = a + b/x
49.294920
-32.024708
0.612711
168
6.3.7. Influence of the Total Float of Activities on the Ratio of the Actual
Duration to the Estimated Duration
Another key analysis has been conducted to investigate the relationship between the
originally estimated total float and the duration overrun. This study illustrates that there is no
direct relationship between the total float and the actual duration of activities as shown in
Figure (6.19). However, it could be assumed that preparing a schedule with a higher total
float would lead to a higher time overrun. Also, it could be concluded that the duration ratio
(RD) between the mean values of the actual durations and the estimated durations for various
activities with total float range between zero and 30 days doesn't follow a steady behaviour.
Whilst, the ratio (RD) seems more stable for the activities with a total float ranges between
30 and 200 days. Another major note is that the ratio (RD) is almost small for critical
activities which have zero total float (TF), since most planning teams and managers pay more
attention for activities with a zero total float.
Estimated Duration 30
Estimated Duration 120
Estimated Duration 60
800%
700%
600%
500%
400%
300%
200%
100%
401-500
301-400
201-300
151-200
91-150
101-200
61-90
31-60
21-30
10-20
0-10
0%
Estimated Duration 15
Estimated Duration 90
Total Float
Figure 6.19: Relationship between the Total Float and the Increment in Ratio of Mean
Actual Duration to Estimated Duration
169
Percent Completion
80
70
60
50
40
30
20
10
A1
A7
A12
A16
1/Apr/2013
1/Mar/2013
1/Feb/2013
1/Jan/2013
1/Dec/2012
1/Nov/2012
1/Oct/2012
1/Sep/2012
1/Aug/2012
1/Jul/2012
1/Jun/2012
1/May/2012
1/Apr/2012
1/Mar/2012
1/Feb/2012
1/Jan/2012
1/Dec/2011
1/Nov/2011
A11
Figure 6.20: The Actual Periodical Progress for Construction Activities in Different CSI
Divisionsin a Single Project in Kuwait
170
Table 6.3: The Periodical Actual Progress for Construction Activities of Different CSI Divisions in a Single Project in Kuwait
Estimated
Actual
Start
1/Nov/2011
1/Dec/2011
1/Feb/2012
1/Apr/2012
1/Jun/2012
30/Jun/2012
31/Jul/2012
31/Aug/2012
31/Oct/2012
30/Nov/2012
31/Dec/2012
31/Jan/2013
28/Feb/2013
31/Mar/2013
30/Apr/2013
Activity ID
Actual Dates
CSI Division
Duration
03
A1
142
14-Nov-11
03-Apr-12
70
70
70
100
100
100
100
100
100
100
100
100
100
100
03
A2
145
16-Nov-11
06-Apr-12
70
70
70
100
100
100
100
100
100
100
100
100
100
100
03
A3
144
10-Nov-11
01-Apr-12
70
70
70
100
100
100
100
100
100
100
100
100
100
100
03
A4
152
02-Nov-11
01-Apr-12
70
70
70
100
100
100
100
100
100
100
100
100
100
100
03
A5
10
153
14-Nov-11
14-Apr-12
70
70
70
100
100
100
100
100
100
100
100
100
100
100
21
165
21-Aug-12
01-Feb-13
90
90
90
90
90
100
100
100
21
140
15-Sep-12
01-Feb-13
70
70
70
70
70
100
100
100
21
125
30-Jun-12
01-Nov-12
50
90
90
100
100
100
100
100
100
21
113
12-Jul-12
01-Nov-12
50
95
95
100
100
100
100
100
100
21
57
06-Oct-12
01-Dec-12
30
30
100
100
100
100
100
04
04
04
04
A6
A7
A8
A9
Activity Name
Level, 1st
Level, 2
Finish
nd
st
Level, 1
Level, 1
Level, 1
st
st
04
A10
08
A11
35
70
22-Jan-13
01-Apr-13
85
85
90
100
09
A12
30
151
01-Oct-12
28-Feb-13
70
70
70
100
100
100
100
st
30
144
01-Oct-12
21-Feb-13
70
70
70
70
100
100
100
st
30
130
12-Sep-12
19-Jan-13
30
95
95
100
100
100
100
30
123
26-Sep-12
26-Jan-13
95
95
100
100
100
100
09
09
A13
A14
09
A15
Plaster Work 2
Layer
15
A16
150
05-Sep-12
01-Feb-13
50
50
50
50
100
100
100
15
A17
12
108
16-Aug-12
01-Dec-12
50
50
50
100
100
100
100
100
171
Table 6.4: Budget per the Estimated and the Actual Durations in Kuwait Classified by
CSI Divisions
Division
Budget/ Estimated
Budget/ Actual
Budget
Duration
Duration
(KD/day)
(KD/day)
10.94
946.3
153.5
40.91
694.5
203.5
2.59
462.1
95.5
7.44
1,057.5
234.7
0.12
476.9
74.9
2.89
293.8
73.7
3.08
383.3
70.3
6.6
185.1
40.9
0.81
447.2
51.6
11.3
284.7
33.9
11.65
504.7
45.3
492.1
83.7
CSI DIVISION
All Divisions
172
The regression models that describe the relationship between the average values of the
actual duration and their budget assigned to all construction activities are best represented by
Equation (6.3) and Table (6.5). The developed regression model is valid for construction
activities with assigned budgeted values greater than 2,500 KD. The regression model starts
with approximately a fixed increase as illustrated in Figure (6.21).
140
120
100
80
60
40
20
0
0
10
12
14
16
Figure 6.21: Relationship between Activities Average Budget (1000 KD) and the Mean
Values of the Actual Durations
Another analysis was conducted to describe the relationship between the budget assigned
to the construction activities and their relevant actual durations. The objective of this study is
to derive estimated durations for activities of construction projects with higher degrees of
reliability by utilizing the activitys budgeted value. It is found that all divisions together as
well as division (15) follow the same regression model that is represented by Equation (6.3)
and Table (6.5). While, divisions (03), (09), and (16) follow regression models represented by
Equation (6.1) and Table (6.5). In addition, division (02) follows Equation (6.2) and Table
(6.5).
173
Table 6.5: Regression Models, Model Constants, and r2 Coefficients for the Average
Budget of Construction Activities and the Actual Durations Classified by
CSI Divisions
Division
Equation
No.
r2
Constant
Equation
Coefficient
All Divisions
6-5
y = a + bx
-106.8500419
63.91129224
0.90151434
Division (02)
6-4
y = a + b. x
63.92006073
2.148396907
0.524244605
Division (03)
6-1
y = a + b. ln(x)
-100.7569902
70.90250967
0.873196646
Division (09)
6-1
y = a + b. ln(x)
-5.451089338
54.77628786
0.880309629
Division (15)
6-5
y = a + bx
-35.28792636
70.05992049
0.849104483
Division (16)
6-1
y = a + b. ln(x)
40.44178744
34.93124258
0.571360974
As shown in Figure (6.22) the curves for divisions classified as civil works such as
division (02), (03) and (04) start with quite moderate increasing rates. Meanwhile, the curves
for divisions (15) and (16) that represent electro-mechanical works start with a rapid increase.
This rapid increase can be attributed to the distribution of items budget over their relevant
construction activities. Where, the electro-mechanical first fix activities always have smaller
budgets than second or third fix activities. Also, the first fix activities often have
interdependencies with various disciplines that always cause time slippage and duration
overrun. Meanwhile, the third fix activities are always installed in a short time and during
one session. Therefore, contractors should plan and make the necessary coordination for
electro-mechanical first fix activities at earlier stages. On the other hand, the same
equipment from different vendors or brands may increase the assigned budget, but will not
have a tangible impact on the installation time.
174
400
300
200
100
0
0
20
40
60
80
100
120
140
250
200
150
100
50
0
0
10
20
30
175
40
50
180
160
140
120
100
80
60
40
20
0
0
10
12
14
16
600
500
400
300
200
100
0
0
10
20
30
40
176
50
60
70
180
160
140
120
100
80
60
40
20
0
0
10
12
14
16
Figure 6.22: Regression Models for the Relationship between Construction Activities
Budgets and Actual Durations in Kuwait Classified by CSI Divisions: a) Division 02,
b) Division 03, c) Division 09, d) Division 15, and e) Division 16
177
178
The process of collecting and organizing risks and their references data is divided into
three steps through three interfaces as shown in Figure (7.1). The first step is the preparation
of research data such as country, researcher, year of publishing, and institute. The second step
is to prepare risks categories or classifications according to the published in their relevant
researches. The third step is the preparation of risks characteristics such as risk severity and
frequency.
Figure 7.1: Data Entry Interfaces for Researches and Risks Data
In addition, the preparation process for projects and activities data is also divided into
three steps through three interfaces as shown in Figure (7.2). The first step is the preparation
of projects data such as title, owner, contractual start and finish dates, and location of the
project. The second step is to prepare projects activities and their characteristics such as title,
estimated duration, predecessors and their relevant CSI divisions. The third step is assigning
risks for each activity and the ratio of impact according to the contractors risk plan.
On the other hand, the program calculates the relative risks values on the level of the
project. The normalized risks values on each activity are then accumulated in order to
evaluate the activities that are exposed to higher levels of risk as shown in Figure (7.3). This
process assists projects managers and planning teams to focus on risky activities practically
based on reliable quantitative analysis. In addition, the program evaluates the most affecting
risks according to their contribution in the projects total risks as shown in Figure (7.4). This
process assists the planning teams and managers to continue monitoring the risks with highest
impacts from the beginning of the project till the end.
179
Figure 7.4: Example for a Report of Risks Contribution to the Overall Values of
Projects Risks
181
182
START
t=task+1
No
No of Act. = All
Selected for Export
Yes
END
183
START
No
Read ED, PDF, and Extracted
No
No of Act. = All
Activitie
Yes
Call Subroutine for Generating Random
Variable
Calculate Scheduling
No of Runs = No of
Iterations (n)
Yes
END
Figure 7.6: Flowchart for Detailed Process of Simulation and Scheduling Using
Microsoft Project Software
184
Figure 7.7: Sample of Graphical Analysis and Curve Fitting by Automating MATLAB
Software
integrity over different scenarios or conditions. The validation process will help in assessing
the usage limitations and considerations that should be considered for future prediction of
projects. In addition, the model should be periodically reviewed against future practices and
technical literature to confirm that the model is still appropriate for the latest conditions and
is up to date with construction industry practices. Consequently, the concluded probability
distribution functions as well as the predictive regression models for representing activities
durations should be tested through real completed projects. The projects that will be used for
testing and validating our study models and proposed values or probability distribution
functions shall include a variety of projects with different categories such as size of the
project, location, type of work, owners degree, and contractors classification. Furthermore,
contracting, and real estate companies need to validate their own models to keep pace with
changes in construction industry dynamics and variation.
The predictive durations based on our suggested regression models were extracted and
implemented on about two projects in Kuwait, one project in Saudi Arabia, and two projects
in Oman as illustrated in Table (7.1). Through the validation process included five steps as
follows
1. Extracting the estimated durations for all activities from primavera software.
2. Modifying the durations for all activities based on suggested regression models in
chapter six.
3. Reload the modified durations into the Primavera software.
4. Run the scheduling process for the project in Primavera and extract the projects
overall duration.
5. Compare the extracted duration from step four with the actual duration of the project.
The review of the results shows that the models could be implemented successfully and
accurately in Kuwait for conventionally estimated durations greater than 25 days. Meanwhile,
the estimated durations less than25 days could be modified by multiplying them by (1.5) as
shown in Table (7.1). In addition, the studied projects in Saudi Arabia and Oman show that
the regression models are valid for application on all conventionally estimated activities
greater than 15 days. Meanwhile, the estimated durations less than 15 days can be modified
by multiplying them by (1.5) as shown in Table (7.1).
The actual and the predicted overall durations for construction projects used during the
validation process are summarized in Table (7.1) As shown in Table (7.1), the variance
between the projects' actual durations and the predicted ones that are calculated based on the
extracted durations of activities from the proposed regression models, range between +5%.
186
01 Wataniya
Headquarter
Modification
Factor
(A)
Estimated
Duration
(days)
(B)
(C)
(D) =(C)-(A) (E) =(C)-(B) Predicted / Predicted
Actual Predicted Variance from Variance
Estimated / Actual
Duration Duration
Estimated
from Actual
(C)/(A)
(C)/(B)
(days)
(days)
(days)
(days)
%
%
Kuwait
627
1295
1260
-633
-35
201
97
900
1513
2254
-1354
741
250
149
900
1513
1881
-981
368
209
124
900
1513
1653
-753
140
184
109
900
1513
1544
-644
31
172
102
03 Shinkhar
Palace
03 Shinkhar
Palace
KSA
530
1111
1241
-711
130
234
112
KSA
530
1111
1085
-555
-26
205
98
1611
2147
2352
-741
205
146
110
1611
2147
2259
-648
112
140
105
700
1702
1718
-1018
16
245
101
700
1702
1626
-926
-76
232
96
04 HasikOMAN
Shuwaymiyah
04 HasikOMAN LT15 Days 1.5
Shuwaymiyah
05 Slalah
OMAN LT10 Days 1.5
Complex
05 Slalah
Complex
187
projects, and the percentage of delay from the projects estimated durations in
which the respondent has participated.
2. The second section includes the list of 41 methods of minimizing construction
delays. Five scales were identified to determine the effectiveness of each method.
Keeping the questionnaire short (two pages only), but comprehensive enough, so
that it could be completed within 15 to 20 minutes.
Received Questionnaires
Consultant
Contractor
2
2
9
2
8
13
1
1
0
4
20
22
Client
1
0
9
1
0
11
Total
5
11
30
3
4
53
[=5
=1 ]
..(7.1)
Table 7.3: The Effectiveness Index for Methods of Minimizing Construction Delays in
the Middle East Ranked by All Respondents
Effectiveness
Rank
Index *
ID
Question Description
Q14
Q06
Q08
Q13
Q35
Q40
Q02
3.636
3.591
3.455
3.386
3.296
3.295
3.250
1
2
3
4
5
6
7
3.115
Q21
Q24
Q05
Q12
Q03
Q30
Q15
Q38
Q11
Q34
Q26
Q16
Q37
Q09
Q20
Q27
Q17
Q18
Q22
Q29
Q31
Q25
3.114
3.023
2.955
2.932
2.887
2.886
2.841
2.795
2.773
2.752
2.750
2.794
2.727
2.659
2.616
2.614
2.569
2.567
2.545
2.477
2.432
2.386
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Q36
2.364
31
Q23
2.318
32
2.259
33
2.250
2.185
34
35
2.182
36
2.068
2.045
1.955
1.818
1.795
37
38
39
40
41
Q10
Q04
Q32
Q19
Q01
Q41
Q07
Q39
Q28
Q33
190
It is clear that ensuring the adequate and available source of finance until the completion
of the project has the highest rank between the methods of minimizing the construction
delays in the Middle East as shown in Table (7.3). This result coincided with the results of
the quantitative analysis accomplished in chapter 4 of this study. Where, it was concluded
that the most effective cause of delay was the slow financial and payment procedures for the
main contractor and subsequently for the subcontractors and suppliers. The second and the
third ranked methods of minimizing the construction delays are providing competent project
manager and ensure effective strategic planning. This result coincide with the results
concluded form the analytical comparisons of causes of delay in the Middle East. The most
important category for causes of delay was the management, planning and scheduling.
191
192
engineering, procurement and construction (EPC) activities for most trades of works. The
analysis included the curve fittings and goodness of fit for the estimated and the actual
durations of activities to evaluate the best probability density function for representing
activities durations within the simulation process.
The third study included developing various regression models by using real data from
thirteen large construction projects in Egypt, Kuwait and KSA including approximately
84,000 EPC activities representing most trades of works. The regression models delineate the
relationship between the estimated and the statistics of the actual durations of activities. The
regression models can be used to predict the expected durations based on the conventionally
estimated duration through conventional estimation techniques. Another set or regression
models were developed by utilizing 35,000 construction activities in Kuwait to predict the
activities durations based on their budgets.
Throughout the course of the study, many Software Packages such as Microsoft Access
2010, Primavera Project Planner 3.1, Primavera Enterprise 6.7, Microsoft Project 2010,
MATLAB 2010b, STATISTICA 10.0, Easy Fit 5.5 and IBM Statistics SPSS 22, have been
utilized in order to collect, sort, analyse and derive the statistical parameters for durations of
activities, checking goodness of fit, and developing regression models. In addition, the fast
and the efficient accomplishment of the study urged the author to design and develop
a comprehensive database and a special program to
organizing and allocating risks to the activities of construction projects to prepare detailed
time schedule loaded with risks; (2) automating Microsoft project software to perform
simulation for the scheduling process; (3) evaluating the statistical parameters of the projects
overall durations; (4) quantifying the most effective risks with the highest potential impacts,
and (5) automating MATLAB 2010b software package to create curve fitting.
The overall thesis results and conclusions urged to investigate the practical solutions and
methods of minimizing the causes of delay. For this purpose, a questionnaire was designed to
collect, analyze and evaluate the opinion of construction experts and professionals. The
questionnaire included 41 factors and was distributed among three types of practitioners:
owners, consultants and contractors working in the Middle East and South Korea. The
questionnaire was sent to 411 of construction practitioners in Egypt, Kingdom of Saudi
Arabia, Kuwait, United Arab Emirates, and South Korea. The total collected number of
questionnaires was 53 questionnaires distributed as follows: 11 from clients, 20 from
consultants and 22 from contractors.
193
8.2. Conclusions
The accomplished three studies concluded that in the construction industry, uncertainty
implementation and risk are very significant parameters and have to be considered when
a project is planned and scheduled. It provides a disciplined framework for proactive projects
managers to assess incessantly the impacts from surrounding conditions; determine risk
priorities; and implement the most suitable actions to deal with those risks. The following
conclusions can be deduced from the results of the three subsidiary studies:
194
195
14. There is no proof of a direct relationship between the total float and the actual
duration slippage of activities. Notwithstanding, the ratio RD is almost small for
critical activities which have a zero total float.
15. The highest budget rate per actual duration is observed for division (05): Metal works,
and then for division (03): concrete works. However the lowest budget rates per actual
duration are divisions (15): Mechanical works and (16): Electrical works.
16. The regression models for electro-mechanical works start with a rapid increase
because the first fix activities always have smaller budgets than second or third fix
activities. Meanwhile, the first fix activities often have time slippage and duration
overrun. Therefore, contractors should plan and coordinate more accurately for
electro-mechanical first fix activities at early stages.
196
REFERENCES
Abd El-Razek, M., Bassioni, H. and Mobarak, A., 2008, Causes of Delay in Building
Construction Projects in Egypt, Journal of Construction Engineering and
Management, ASCE, Vol. 134, No. 11, pp.831-41.
AbdMajid, M. and McCaffer, R., 1998, Factors of Non-Excusable Delays that Influence
Contractors' Performance, Journal of Management in Engineering, ASCE, Vol.
14,No. 3, pp.42-49.
AbdAllah, E., 2008, Dynamic Simulation for Optimal-Cost Scheduling of Construction
Projects, PhD Thesis, Faculty of Engineering, Cairo University, Giza, Egypt.
Abdel-Gawad, M., Georgy, M. and Ibrahim, M.,2005, Sources of Project Risks Under Joint
Ventures in Egypt, Proceedings of the Eleventh International Colloquium on
Structural and Geotechnical Engineering, ICSGE. Cairo, Egypt.
Abdul Rashid, I. and Bakarman, B., 2005, Risk Assessment and Analysis for Construction
Contractors in Egypt, Proceedings of the Eleventh International Colloquium on
Structural and Geotechnical Engineering, ICSGE. Cairo, Egypt.
Abdullah, M., Abdul Rahman, I. and Abdul Azis, A., 2010, Causes of Delay in MARA
Management Procurement Construction Projects, Journal of Surveying, Construction
and Property, Vol. 1, No. 1, pp.12338.
Abdul-Malak, M., El-Saadi, M., and Abou-Zeid, M., 2002, Process Model for
Administrating Construction Claims, Journal of Management in Engineering, ASCE,
Vol. 18, No. 2, pp.84-94.
AbouRizk, S. and Halpin, D., 1992, Statistical Properties of Construction Duration Data,
Journal of Construction Engineering and Management, ASCE, Vol. 118,No. 3,
pp.525-44.
AbouRizk, S., Halpin, D. and Wilson, J., 1991, Visual Interactive Fitting of Beta
Distributions, Journal of Construction Engineering and Management, ASCE, Vol.
117, No. 4, pp.589-605.
Abu Hammad, A., Alhaj Ali, S., Sweis, G., and Bashir, A., 2008, Prediction Model for
Construction Cost and Duration in Jordan, Jordan Journal of Civil Engineering, Vol.
2, No. 3, pp.250-66.
Abu Hammad, A., Alhaj Ali, S., Sweis, G., and Sweis, R., 2010, Statistical Analysis on the
Cost and Duration of Public Building Projects, Journal of Management in
Engineering, ASCE, Vol. 26, No. 2, pp.105-12.
197
Acharya, N., Lee, Y., Kim, S., and Lee, J., 2006, Analysis of Construction Delay Factor:
A Korean Perspective, Proceedings of the 7th Asia Pacific Industrial Engineering and
Management Systems Conference, Bangkok, Thailand.
Afshar, A., 2008, A fuzzy-Based Model for Unbalanced Bidding in Construction,
Proceedings of the 1st International Conference on Construction in Developing
Countries (ICCIDCI), Karachi, Pakistan.
Afshari, H., Khosravi, S., Ghorbanali, A., Borzabadi, M., and Valipour, M., 2011,
Identification of Causes of Non-Excusable Delays of Construction Projects,
Proceedings of the 2010 International Conference on E-business, Management and
Economics, IACSIT Press, Hong Kong.
Agbulos, A. and Abou Rizk, S., 2003, An Application of Lean Concepts and Simulation for
Drainage Operations Maintenance Crews, Proceedings of the 35thWinter Simulation
Conference, New Orleans, Louisiana, USA.
Ahmed, S., Azhar, S. and Castillo, M., 2002, Construction Delays in Florida: An Empirical
Study, Final Report Submitted to the Department of Community Affairs (DCA),
Florida, Miami, USA.
AI-Mudlej, K., 1984, Causes of Delays and Overruns of Construction Projects in Saudi
Arabia, MSc. Thesis, Faculty of the College of Graduate Studies, King Fahd
University of Petroleum and Minerals, KFUPM, Dhahran, Saudi Arabia.
AI-Hazmi, M., 1987, Causes of Delay in Large Building Construction Projects, MSc.
Thesis, Faculty of the College of Graduate Studies, King Fahd University of
Petroleum and Minerals, KFUPM, Dhahran, Saudi Arabia.
Aibinu, A., 2008, Managing Projects to Reduce Delivery Schedule, Proceedings of the
International Conference on Building Education and Research (BEAR), University of
Salford, UK.
Aibinu, A., and Jagboro, G., 2002, The Effects of Construction Delays on Project Delivery
in Nigerian Construction Industry, International Journal of Project Management,
Vol. 20, pp.593-99.
Al-Salman, A., 2004, Assessment of Risk Management Perceptions and Practices of
Construction Contractors in Saudi Arabia, MSc. Thesis, Faculty of the College of
Graduate Studies, King Fahd University of Petroleum and Minerals, KFUPM,
Dhahran, Saudi Arabia.
Al-Bahar, J., and Crandall, K., 1990, Systematic Risk Management Approach for
Construction Projects, Journal of Construction Engineering and Management,
ASCE, Vol. 116, No. 3, pp.533-47.
198
Al-Ghafly, M., 1995, Delay in the Construction of Public Utility Projects in Saudi Arabia,
MSc. Thesis, Faculty of the College of Graduate Studies, King Fahd University of
Petroleum and Minerals, KFUPM, Dhahran, Saudi Arabia.
Aliabadizadeh, Y., 2009, Evaluation of Ways to Recover Late Construction Projects, MSc.
Thesis, Faculty of the Graduate School of the University of Maryland, College Park,
USA.
Al-Khalil, M. and Al-Ghafly, M., 1999, Important Causes of Delay in Public Utility
Projects, Journal of Construction Management and Economics, Vol. 17, No. 5,
pp.647-55.
Al-Kharashi, A. and Skitmore, M., 2009, Causes of Delays in Saudi Arabian Public Sector
Construction Projects, Journal of Construction Management and Economics, Vol.
27, No. 1, pp.3-23.
Al-Momani, A., 2000, Construction Delay: A Quantitative Analysis, International Journal
of Project Management, Vol. 188, pp.51-59.
Al-Najjar, J., 2008, Factors Influencing Time and Cost Overruns on Construction Projects in
the Gaza Strip, MSc. Thesis, Civil Engineering Construction Management, The
Islamic University of Gaza, Gaza, Palestine.
Al-Sultan, A., 1989, Determination of Construction Contract Duration for Public Projects in
Saudi Arabia, MSc. Thesis, Faculty of the College of Graduate Studies, King Fahd
University of Petroleum and Minerals, KFUPM, Dhahran, Saudi Arabia.
Al-Tabtabai, H., 2002, Causes for Delays in Construction Projects in Kuwait, Engineering
Journal of the University of Qatar, Vol. 15, pp.19-37..
Alwi, S., Hampson, K. and Mohamed, S., 2002, Factors Influencing Contractor Performance
in Indonesia: A Study of Non Value-Adding Activities, Proceedings of the
International Conference on Advancement in Design, Construction, Construction
Management and Maintenance of Building Structure, Bali, Indonesia.
Alwi, S. and Hampson, K., 2003, Identifying the Important Causes of Delays in Building
Construction Projects, Proceedings of The 9th East Asia-Pacific Conference on
Structural Engineering and Construction, Bali, Indonesia.
Ammar, M., Elsamdony, A., and Rabie, A., 2009, Risk Allocation and Mitigation in The
Egyptian Barrage Projects, Proceedings of the Thirteenth International Conference
on Structural and Geotechnical Engineering, ICSGE. Cairo, Egypt.
199
Apolot, R., Alinaitwe, H. and Tindiwensi, D., 2010, An Investigation into the Causes of
Delay and Cost Overrun in Ugandas Public Sector Construction Projects,
Proceedings of the Second International Conference on Advances in Engineering and
Technology.
Asif, M., 2003, Critical Success Factor for Different Project Objectives, MSc. Thesis,
Faculty of the College of Graduate Studies, King Fahd University of Petroleum and
Minerals, KFUPM, Dhahran, Saudi Arabia.
Assaf, S., Al-Khalil, M. and A-Hazmi, M., 1995, Causes of Delay in Large Building
Construction Projects, Journal of Management in Engineering, ASCE, Vol. 11, No.
2, pp. 45-50.
Assaf, S., and Al-Hejji, S., 2006, Causes of Delay in Large Construction Projects,
International Journal of Project Management, Vol. 24, No. 4, pp.34957.
Awawdeh, S., 1985, An Investigation into Delays and Cost Overrun in Saudi Arabia, MSc.
Thesis, Faculty of the College of Graduate Studies, King Fahd University of
Petroleum and Minerals, KFUPM, Dhahran, Saudi Arabia.
Balci, O., 1990, Guidelines for Successful Simulation Studies, Proceedings of the 22nd
Winter Simulation Conference, New Orleans, Louisiana, USA.
Ballard, G., 1999, Improving Work Flow Reliability, Proceedings of the 7th Conference of
the International Group for Lean Construction, Berkeley, California, USA.
Benjamin, J. and Cornell, C., 1970, Probability, Statistics, and Decision, McGraw-Hill Book
Company, New York, USA.
bin-Yusof, M., binti Mohammad, N. and bin Mat Derus, Z., 2007, Excusable and
Compensable Delays in the Construction of Building Project - A Study in the States
of Selangor and Wilayah Persekutuan Kuala Lumpur, Malaysia, The Institution of
Engineers Journal, Malaysia, Vol. 68, No. 4, pp.21-26.
Biruk, S. and Jaskowski, P., 2010, On the Problems of Modelling and Reliability
Assessment of Construction Projects Duration, Journal of International Group on
Reliability, Vol. 4, No. 19, pp.6-14.
Bonke, S. and Olsen, I., 2010, Introducing Partnering in Denmark Lessons Learned
Applying Public Private Partnerships as an Innovation Platform, Proceedings of the
18th CIB World Building Congress, The Lowry, Salford Quays, United Kingdom.
Braimah, N., 2008,An Investigation into the Use of Construction Delay and Disruption
Analysis Methodologies, PhD Thesis, University of Wolverhampton,
Wolverhampton, United Kingdom.
200
201
202
Fang, D., Li, M., Fong, P., and Shen, L., 2004, Risks in Chinese Construction Market
Contractors Perspective, Journal of Construction Engineering and Management,
ASCE, Vol. 130, No. 6, pp.853-61.
Faridi, A.,and El-Sayegh, S., 2006, Significant Factors Causing Delay in the UAE
Construction Industry, Journal of Construction Management and Economics, Vol.
24, pp.11671176.
Flyvbjerg, B., Holm, K., and Buhl, S., 2003, How Common and How Large Are Cost
Overruns in Transport Infrastructure Projects?, Journal of Transport Reviews, Vol.
23, No. 1, pp.71-88.
Fugar, F., and Agyakwah-Baah, A., 2010, Delays in Building Construction Projects in
Ghana, Australasian Journal of Construction Economics and Building, Vol. 10,
pp.103-16.
Global Insight, I., 2010, Construction Spending Analysis and Forecast for Egypt. [Online]
Global Insight, Inc. Available at:
HYPERLINK "http://www.constructionint.com/article/construction-spending-analysis-and-forecast-for-egypt.html"
http://www.construction-int.com/article/construction-spending-analysis-and-forecastfor-egypt.html [Accessed 26 Mar 2013].
Graham, D., Smith, S. and Crapper, M., 2004, Improving Concrete Placement Simulation
With A Case-Based Reasoning Input, Journal of Civil Engineering and
Environmental Systems, Vol. 21, No. 02, pp.137-50.
Guo, W., 2004,Development of a Framework for Preliminary Risk Analysis in
Transportation Projects, MSc. Thesis, Civil Engineering, Faculty of Worcester
Polytechnic Institute, Worcester, USA.
Halpin, D., 1977, CYCLONE - Method for Modelling Job Site Processes, Journal of the
Construction Division, ASCE, Vol. 103, No. 3, pp.48999.
Hancher, D., and Rowing, R., 1981, Sitting Highway Construction Contract Duration,
Journal of the Construction Division, ASCE, Vol. 107, No. 2, pp.169-79.
Harmelink, D., and Bernal, M., 1998, Simulating Haul Durations for Linear Scheduling,
Proceedings of the 30thWinter Simulation Conference, Washington, DC, USA.
Haseeb, M., Xinhai-L., Bibi, A., Maloof-ud, D., and Rabbani, W., 2011, Problems of
Projects and Effects of Delays in the Construction Industry of Pakistan, Australian
Journal of Business and Management Research, Vol. 1, No. 5, pp.41-50.
Hendrickson, C., Martinelli, D. and Rehak, D., 1987, Hierarchical Rule-Based Activity
Duration Estimation, Journal of Construction Engineering and Management, ASCE,
Vol. 113, No. 2, pp.288-301.
203
Jaafari, A., 1990, Surviving Failures: The Lessons from a Field Study, Journal of
Construction Engineering and Management, ASCE, Vol. 116, No. 1, pp.68-86.
Jacinto, C., 2002, Discrete Event Simulation for the Risk of Development of an Oil Field,
Proceedings of the 34th Winter Simulation Conference. San Diego, California, USA.
Kaliba, C., Muya, M. and Mumba, K., 2009, Cost Escalation and Schedule Delays in Road
Construction Projects in Zambia, International Journal of Project Management, Vol.
27, No. 5, pp.522-31.
Kannan, G., Schmitz, L. and Larsen, C., 2000, An Industry Perspective on the Role of
Equipment-Based Earthmoving Simulation, Proceedings of the 32nd Winter
Simulation Conference. Orlando, USA.
Kartam, N. and Kartam, S., 2001, Risk and its Management in the Kuwaiti Construction
Industry: Contractors Perspective, International Journal of Project Management,
Vol. 19, No. 6, pp.325-35.
Kelleher, A., 2004, An Investigation of the Expanding Role of the Critical Path Method by
ENR's Top 400 Contractors, MSc. Thesis, Faculty of Virginia Polytechnic Institute
and State University, Blacksburg, USA.
Kohler, N. and Moffatt, S., 2003, Life-Cycle Analysis of the Built Environment, Journal of
Industry and Environment, (Sustainable building and construction), pp.04-94.
Koushki, P., Al-Rashid, K. and Kartam, N., 2005, Delays and Cost Increases in the
Construction of Private Residential Projects in Kuwait, Journal of Construction
Management and Economics, Vol. 23, pp.285-94.
Lana, E., 2006, Stochastic Critical Path, Proceedings of the 2006 Crystal Ball User
Conference.
Laufer, A. and Tucker, R., 1987, Is Construction Project Planning Really Doing Its Job?
A Critical Examination of Focus, Role and Process, Journal of Construction
Management and Economics, Vol. 5, pp.243-66.
Lee, D., 2005, Probability of Project Completion Using Stochastic Project Scheduling
Simulation, Journal of Construction Engineering and Management, ASCE, Vol. 131,
No. 3, pp.310-18.
Lee, D., Arditi, D., and Son, C., 2013, The Probability Distribution of Project Completion
Times in Simulation-Based Scheduling, KSCE Journal of Civil Engineering, Vol. 17,
No. 4, pp.638-45.
Leemis, L., Duggan, M., Drew, J., Mallozzi, J., and Connell, K., 2006, Algorithms to
Calculate the Distribution of the Longest Path Length of a Stochastic Activity
Network with Continuous Activity Durations, www.interscience.wiley, pp.14365.
204
Le-Hoai, L., Lee, D., and Lee, J., 2008, Delay and Cost Overruns in Vietnam Large
Construction Projects: A Comparison with Other Selected Countries, KSCE Journal
of Civil Engineering, Vol. 12, No. 6, pp.367-77.
Long, N., Ogunlana, O., Quang T., and Lam, C., 2004, Large Construction Projects in
Developing Countries, a Case Study from Vietnam, International Journal of Project
Management, Vol. 22, pp.553-61.
Lucko, G., Swaminathan, K., Benjamin, P.. and Madden, M.G., 2009, Rapid Deployment of
Simulation Models for Building Construction Applications, Proceedings of the 41st
Winter Simulation Conference. Austin, USA.
Lyer, K., and Jha, K., 2006, Critical Factors Affecting Schedule Performance: Evidence
from Indian Construction Projects, Journal of Construction Engineering and
Management, ASCE, Vol. 132,No. 8, pp.871-81.
Mahdavinejad, M. and Molaee, M., 2011, The Result of Delayed Projects on Publics
Satisfaction in Tehran, Proceedings of the 2nd International Conference on
Construction and Project Management, Singapore.
Majid, I., 2006, Causes and Effects of Delays in Aceh Construction Industry, MSc. Thesis,
Faculty of Engineering, Universiti Teknologi Malaysia, Skudai, Johor Bahru,
Malaysia.
Martin, J., Burrows, T., and Pegg, I., 2006, Predicting Construction Duration of Building
Projects, Proceedings of the XXIII International FIG Congress, Munich, Germany.
Marzouk, M., Zein El-Dein, H., and El-Said, M., 2006, Bridge_ Sim: Framework For
Planning and Optimizing Bridge Deck Construction Using Computer Simulation,
Proceedings of the 38th Winter Simulation Conference. Monterey, California, USA.
Marzouk, M., Zein El-Dein, H., and El-Said, M., 2007, Application of Computer Simulation
to Construction of Incremental Launching Bridges, Journal of Civil Engineering and
Management, Vol. XIII, pp.2736.
Marzouk, M., El-Mesteckawi, L., and Ibrahim, M., 2007, Construction Disputes in Egypt:
Causes and Methodologies for Resolution, Proceedings of the Twelfth International
Colloquium on Structural and Geotechnical Engineering, ICSGE. Cairo, Egypt.
Marzouk, M., and El-Rasas, T., 2014, Analysing Delay Causes in Egyptian Construction
Projects, Journal of Advanced Research, Vol. 5, pp.49-55.
McCabe, B., 2003, Monte Carlo Simulation for Schedule Risks, Proceedings of the 35th
Winter Simulation Conference. New Orleans, Louisiana, USA.
205
Menesi, W., 2007, Construction Delay Analysis under Multiple Baseline Updates, Master
of Applied Science Thesis, Civil Engineering, University of Waterloo, Waterloo,
Ontario, Canada.
Mezher, T., and Tawil, W., 1998, Factors of Non-excusable Delays that Influence
Contractors Performance, Journal of Engineering, Construction and Architectural
Management, Vol. 5,No. 3, pp.252 - 260.
Moavenzadeh, F., and Rossow, J., 1975, The Construction Industry in Developing
Countries, Report for Technology Adaptation Program, Massachusetts Institute of
Technology, Cambridge, USA.
Mojahed, S., 2005, A Project Improvement System for Effective Management of
Construction Projects, PhD Thesis, Graduate Faculty of the Louisiana State
University and Agricultural and Mechanical College, Baton Rouge, USA.
Molak, V., 1997, Fundamentals of Risk Analysis and Risk Management, Lewis Publishers,
Cincinnati, Ohio, USA.
Montgomery, D., and Runger, G., 2003, Applied Statistics and Probability for Engineers,
Third Edition, John Wiley and Sons, Inc., USA.
Moosavi, S., 2012, Assessment and Evaluation of Detailed Schedules in Building
Construction, Master of Applied Science, Building, Civil and Environmental
Engineering, School of Graduate Studies, Concordia University, Montreal, Quebec,
Canada.
Morris, P., 1994, The Management of Projects, Thomas Telford Services Ltd., London, UK.
Motaleb, O. and Kishk, M., 2010, An Investigation into Causes and Effects of Construction
Delays in UAE, Proceedings of the 26th Annual ARCOM Conference, Leeds, UK.
Mulholland, B. and Christian, J., 1999, Risk Assessment in Construction Schedules,
Journal of Construction Engineering and Management, ASCE, Vol. 125, No. 1, pp.815.
Nasir, D., McCabe, B. and Hartono, L., 2003, Evaluating Risk in ConstructionSchedule
Model ERICS: Construction Schedule Risk Model, Journal of Construction
Engineering and Management, ASCE, Vol. 129, No. 5, pp.518-827.
Ng, S., Mak, M., Skitmore, R., Lam, K., and Varnam, M., 2001, The Predictive Ability of
Bromilows Time-Cost Model, Journal of Construction Management and
Economics, Vol. 19, No. 2, pp.165-73.
Oberkampf, L., DeLand, M., Rutherford, M., Diegert, V., and Alvin, F., 2000, Estimation of
Total Uncertainty in Modelling and Simulation, Report for U.S. Department of
Energy, Sandia National Laboratories, California, USA.
206
Odabai, E., 2009, Models for Estimating Construction Duration: An Application for
Selected Buildings on the METU Campus, MSc. Thesis, Graduate School of Natural
and Applied Sciences, Middle East Technical University, Ankara, Turkey.
Odeh, A., and Battaineh, H., 2002, Causes of Construction Delay: Traditional Contracts,
International Journal of Project Management, Vol. 20, No. 1, pp.67-73.
Ogunlana, S., Promkuntong, K., and Jearkjirm, V., 1996, Construction Delays in a FastGrowing Economy: Comparing Thailand with Other Economies, International
Journal of Project Management, Vol. 14, No. 1, pp.3745.
Ogunsemi, D., and Jagboro, G., 2006, Time-Cost Model for Building Projects in Nigeria,
Journal of Construction Management and Economics, Vol. 24, No. 3, pp.253-58.
Ogwueleka, A., 2001, The Critical Success Factors Influencing Project Performance in
Nigeria, International Journal of Management Science and Engineering
Management, Vol. 6, No. 5, pp.343-49.
Okumbe, J., and Verster, J., 2008, Construction Industry Perspective on Causes and Effects
of Delays in South Africa, Proceedings of The Construction and Building Research
Conference of the Royal Institution of Chartered Surveyors, Dublin Institute of
Technology.
Olupolola, F., Emmanuel, O., Adeniyi, M., and Kamaldeen, A., 2010, Factors Affecting the
Time Performance of Building Projects, Proceedings of the Construction, Building
and Real Estate Research Conference of The Royal Institution of Chartered
Surveyors. Dauphine Universit, Paris, France.
Omoregie, A., and Radford, D., 2006, Infrastructure Delays and Cost Escalation: Causes and
Effects in Nigeria, [Online] Rotterdam (Netherlands) Available at: HYPERLINK
"http://www.irb.fraunhofer.de/CIBlibrary/search-quick-resultlist.jsp?A&idSuche=CIB+DC8999" http://www.irb.fraunhofer.de/CIBlibrary/searchquick-result-list.jsp?AandidSuche=CIB+DC8999 [Accessed 2010].
Panthi, K., 2007, Prioritizing and Estimating Hydropower Project Construction Risks:
A Case Study of Nyadi Hydropower Project, Proceedings of the 2nd Annual
Himalayan Policy Research Conference, Madison, Wisconsin, USA.
Pham, H., 2006, Springer Handbook of Engineering Statistics, Springer-Verlag London
Limited, London, UK.
PMI., 2012, A Guide to The Project Management Body of Knowledge (PMBOK 5 th
Guide), Fifth Edition, Project Management Institute, Inc., Pennsylvania, USA.
Ponce de Leon, G., 1987, Theories of Concurrent Delays, AACE Transactions.
207
Pourrostam, T. and Ismail, A., 2011, Significant Factors Causing and Effects of Delay in
Iranian Construction Projects, Australian Journal of Basic and Applied Sciences,
Vol. 7, No. 5, pp.450-56.
Prateapusanond, A., 2003, A Comprehensive Practice of Total Float Pre-Allocation and
Management for the Application of a CPM-Based Construction Contract, PhD
Thesis, Faculty of the Virginia Polytechnic Institute and State University, Blacksburg,
USA.
Sakka, Z., and El-Sayegh, S., 2007, Float Consumption Impact on Cost and Schedule in the
Construction Industry, Journal of Construction Engineering and Management,
ASCE, Vol. 133,No. 2, pp.124-30.
Sambasivan, M., and Soon, Y., 2007, Causes and Effects of Delays in Malaysian
Construction Industry, International Journal of Project Management, Vol. 25,No. 5,
pp.51726.
Schexnayder, C., Knutson, K. and Fente, J., 2005, Describing a Beta Probability
Distribution Function for Construction Simulation, Journal of Construction
Engineering and Management, ASCE, Vol. 131,No. 2, pp.221-29.
Shaikh, A., Muree, M., and Soomro, A., 2010, Identification of Critical Delay Factors in
Construction, Sindh University Research Journal (Science Series), Vol. 42,No. 2,
pp.11-14.
Shen, Y. and Rowlinson, S., 2010, Study On The Risk Appraisal Framework Of PPP In
Yangtze River Delta Region, Proceedings of the 18th CIB World Building Congress,
The Lowry, Salford Quays, UK.
Shi, J., 1997, A Conceptual Activity Cycle-Based Simulation Modelling Method,
Proceedings of the 29th Winter Simulation Conference. Atlanta, USA.
Soehodho, S., Susantono, B. and Prasetya, S., 2003, Infrisk Simulation in Risk Influence of
Investing Toll Road Projects, Proceedings of the Eastern Asia Society for
Transportation Studies.
Song, L., Al-Battaineh, H., and Abou Rizk, S., 2005, Modelling Uncertainty with an
Integrated Simulation System, Canadian Journal of Civil Engineering, Vol. 32,
pp.533-42.
Soong, T., 2004, Fundamentals of Probability and Statistics for Engineers, John Wiley and
Sons Ltd., Buffalo, New York, USA.
208
Strong, K., Kandil, A., and Maze, T., 2007, Flexible Start / Fixed Duration Contracting for
Construction of Transportation Projects: A Case Study of the Paseo Bridge
Maintenance Project, Report for Centre of Transportation Research and Education,
Iowa State University, Ames, USA.
Tumi,.H., Omran, A. and Pakir, K., 2009, Causes of Delay in Construction Industry in
Libya, Proceedings of the International Conference on Administration and Business.
Bucharest, Romania.
Uher, T., 2003, Programming and Scheduling Techniques, 1st edition, University of New
South Wales Press Ltd., Sydney, Australia.
Walewski, J. and Gibson, G., 2003, International Project Risk Assessment: Methods,
Procedures, and Critical Factors, Centre Construction Industry Studies (CCIS) and
Construction Industry Institute (CII), the University of Texas at Austin, Austin, USA.
Walpole, R., Myers, R., Myers, S., and Ye, K., 2012, Probability and Statistics for Engineers
and Scientists, Ninth Edition, Prentice Hall Inc., Boston, USA.
Wei, K., 2010, Causes, Effects and Methods of Minimizing Delays in Construction
Projects, BSc. Report, Faculty of Civil Engineering, Universiti Teknologi Malaysia,
Skudai, Malaysia.
Wiguna, I., and Scott, S., 2005a, Analysing the Risks Affecting Construction Delay and
Cost Overruns in Indonesia Building Projects, Proceedings of the 3rd International
Conference on Innovation in Architecture, Engineering and Construction. Rotterdam,
Netherlands.
Wiguna, I. and Scott, S., 2005b, Nature of the Critical Risk Factors Affecting Project
Performance in Indonesian Building Contracts, Proceedings of the 21st Annual
ARCOM Conference. London, UK.
Willis, E., 1986, Scheduling construction projects, John Wiley and Sons, Inc., Canada.
Wu, J., and Soibelman, L., 2006, Advanced Scheduling Data Preparation, Representation,
and Analysis in Support of Construction Planning and Scheduling, Proceedings of
the Joint International Conference on Computing and Decision Making in Civil and
Building Engineering. Montral, Canada.
Yoe, C., 2009, Risk Analysis Framework for Cost Estimation, Report for U.S. Army Corps
of Engineers, Institute for Water Resources, Alexandria, USA.
Youssef, W., 2005, Effect of Spatial Variability of Soil Properties on Safety Factors of
Cantilever Retaining Walls, MSc. Thesis, Faculty of Engineering, Cairo University,
Giza, Egypt.
209
Zaneldin, E., 2005, AOA - Based Modelling and Simulation of Construction Operations,
International Journal of Simulation Modelling, Vol. 4, No. 4, pp.184-95.
Zayed, T., and Halpin, D., 2000, Simulation as a Tool for Resource Management,
Proceedings of the 32nd Winter Simulation Conference, Orlando, USA.
Zayed, T., and Halpin, D., 2001, Simulation of Bored Pile Construction, Proceedings of the
33rd Winter Simulation Conference, Arlington, USA.
Zayed, T., and Halpin, D., 2004, Simulation as a Tool for Pile Productivity Assessment,
Journal of Construction Engineering and Management, ASCE, Vol. 130, No. 3,
pp.394 -404.
Zhang, H., Tam, C., and Li, H., 2005, Modelling Uncertain Activity Duration by Fuzzy
Number and Discrete - Event Simulation, European Journal of Operational Research,
Vol. 164, No. 3, pp.71529.
210
211
Duration
(Days)
0
90
120
30
1SS+14 days
2SS+30 days
1SS+14 days
45
1SS+20 days
45
1SS+40 days
60
1SS+60 days
8
9
10
11
12
30
26
25
25
30
13
21
1SS+8 days
8,4SS+14 days,2SS+14 days
9,5SS+14 days
9,5SS+14 days
11SS+5 days,10SS+5
days,5SS+14 days
12FS+14 days
14
30
13
15
16
17
18
19
40
30
30
35
21
20
25
14,18FF
14,15
13,14FF-14 days
17,14
18,15,16,5FF+7 days,3FF+7
days
12,6SS+14 days
21
30
20,6SS+14 days
22
30
21FS+14 days
23
40
22
24
25
26
45
30
30
23,27FF
23,24
22,23FF-14 days
27
35
26,23
28
21
29
30
27,24,25,6FF+7 days,3FF+7
days
21,7SS+14 days
30
31
32
33
35
30
40
50
29
30FS+14 days
31
32,36FF
34
35
36
40
30
40
32,33SS
31,32FF-14 days
35,32
37
21
38
21
36,33,34,7FF+7 days,3FF+7
days
30FF+14 days,37FF
39
40
41
60
45
0
1
2
3
4
5
6
Task Name
ACT001 - Project Start Date
ACT002 - Materials Submittals & Approvals
ACT003 - Materials Procurements
ACT004 - Shop Drawings Sub & Approvals For
Foundation
ACT005 - Shop drawings Sub & Approvals Basement
212
Predecessors
30FF+14 days,34SS,25SS
39SS+14 days
23,25,24,26,27,28,29,30,31,32,34,
33,35,36,37,38,39,40
02
03
04
05
06
07
08
09
10
Activity Title
Risk Title
213
Risk Index
Relative
Risk Index
%
0.88
0.71
0.76
0.51
0.74
0.15
0.12
0.13
0.09
0.13
0.7
0.73
0.86
0.12
0.12
0.15
0.86
0.15
0.54
0.09
0
0.2
0.63
0.00
0.03
0.11
0.58
8.7
8.7
8.7
8.7
8.7
8.7
8.75
15.24
0.71
0.67
0.64
0.58
0.51
0.10
1.49
1.49
1.49
1.49
1.49
1.49
1.49
2.60
0.12
0.11
0.11
0.10
0.09
0.56
0.61
0.76
0.10
0.10
0.13
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
214
0.7
0.74
0.12
0.13
0.55
0.51
0.48
0.54
0.09
0.09
0.08
0.09
0.72
0.12
0.7
0.88
0.8
0.12
0.15
0.14
0.67
0.77
0.75
0.74
14.59
14.59
14.59
8.64
17.6
17.6
17.6
19.78
19.13
19.13
14.59
14.59
8.64
17.6
17.6
17.6
19.78
19.13
19.13
14.59
14.59
8.64
17.6
17.6
17.6
19.78
19.13
19.13
13.46
17.79
17.79
0.11
0.13
0.13
0.13
2.49
2.49
2.49
1.47
3.00
3.00
3.00
3.38
3.27
3.27
2.49
2.49
1.47
3.00
3.00
3.00
3.38
3.27
3.27
2.49
2.49
1.47
3.00
3.00
3.00
3.38
3.27
3.27
2.30
3.04
3.04
585.8
100
Table A.3: Values of Risks Relative Indices Calculated on the Overall Project
Risk ID
1503
1487
627
726
892
1504
1061
1488
1060
1482
1486
1495
1492
468
1499
1500
1494
465
1497
893
626
1489
1505
1059
1481
1498
1501
459
2029
2030
1491
95
1496
1493
92
2136
460
1502
462
1490
91
1484
94
264
1483
1485
93
Risk Title
Design Changes by owner's
Poor coordination with regulatory agencies
Poor scheduling of subcontractors
Slow financial and payment procedures
Difficulty of working during Summer & Ramadan
Lack of planning and scheduling
Fluctuating productivity levels
Lack of planning & control on the side of the subcontractors
Manpower shortage in the Market
Slow decision-making process
Lack of professional construction
Inspection procedures
Unrealistic contractor program.
Inflexibility toward alternatives
Poor site management and planning
Lack of field / project experience
Late construction mobilization
Apprehensive towards contractor's favouritism
Inaccurate project estimate
Manpower Visas difficulty
Lack of competent specialty subcontractors
Over-design practice by client
Unfamiliarity with new methods
Poor manpower skills
Limited authority among supervision staff
Selection of incompetent sub-contractors
Uncooperative management
Miss-interpretation of drawings and specifications
Testing of construction materials
Unavailability of Construction material
unrealistic project duration estimate
Design drawings errors
Under staffed project personnel
Lack of construction management training
Lack of design drawings coordination
Differing site conditions
Risk allocation mainly on the contractor.
Inadequate contractor experience
Week Contract clauses
Lack of site attendance control
Design drawings and specifications do not match
Short time extensions for variation orders
Lack of constructability applications
Contractors shop drawings errors
Strict application of quality control program
Lack of Contractors staff training on construction management techniques
Inefficient Shop drawings approval
Total Risks assigned to all Activities in the Project
215
Relative Risk
Index %
4.93
4.80
4.66
4.51
4.37
4.24
4.10
4.06
3.94
3.61
3.54
3.50
3.20
3.12
2.77
2.63
2.62
2.50
2.48
2.29
2.19
2.18
2.08
1.67
1.65
1.56
1.39
1.38
1.33
1.31
1.19
1.17
1.02
1.01
0.99
0.89
0.88
0.81
0.70
0.66
0.65
0.64
0.23
0.20
0.13
0.12
0.10
100.00
Based on the activities CSI values, the phase of work, the program will use the
regressions models to extract the predicted mean and standard deviations values that will be
used in Monte Carlo Simulation for each activity.
The program will apply Monte Carlo Simulation on the schedule and evaluate the overall
project durations. Then the program will make the necessary statistical analysis to extract the
overall project durations at different percentiles as well as the graphical curve fitting for the
projects durations as illustrated in Figure (A.1).
Figure A.1: Probability Density Function (PDF) and Curve Fitting for Overall Project
Durations
The program will present some of the possible solutions or methods that could help in
minimizing or reducing the impact of risks on the activities durations as summarized in Table
(A.4).
The Residual Risk = Initial Relative Risk * (1- Effectiveness factor)
216
Table A.4: Risks and their Relevant Methods of Reducing Risks Impact
Initial
Relative
Risk %
Ser
Risk
ID
1503
4.92
1487
4.80
627
4.66
726
4.51
892
4.37
1504
4.24
1061
4.10
1488
4.06
1060
3.94
10
1482
3.61
11
1486
3.54
12
1495
Inspection procedures
3.50
13
1492
3.20
14
468
3.12
15
1499
2.77
16
1500
2.63
17
1494
2.62
18
19
465
1497
2.50
2.48
Risk Title
217
Effectiveness
Factor %
Residual
Risk %
65.0
1.7
54.5
2.2
49.5
2.4
51.4
2.2
39.1
2.7
49.5
2.1
58.6
1.7
47.3
2.1
51.4
1.9
54.5
1.6
65.9
1.2
60.5
1.4
47.3
1.7
55.0
1.4
48.6
1.4
58.6
1.1
35.9
1.7
53.2
46.4
1.2
1.3
20
893
2.29
21
626
2.19
22
1489
2.18
23
1505
2.08
24
1059
1.67
25
1481
1.65
26
1498
1.57
27
2030
1.41
28
1501
Uncooperative management
1.39
29
459
1.38
30
2029
1.33
31
1491
1.19
32
95
1.17
33
1496
1.02
34
1493
1.00
35
92
0.99
36
37
38
39
2136
460
1502
462
0.89
0.88
0.81
0.70
218
51.4
1.1
43.6
1.2
40.9
1.3
58.6
0.9
58.6
0.7
52.3
0.8
65.9
0.5
35.9
0.9
50.9
0.7
52.3
0.7
45.0
0.7
35.9
0.8
55.0
0.5
56.8
0.4
47.3
0.5
55.0
0.4
48.6
53.2
65.9
53.2
0.5
0.4
0.3
0.3
40
1490
0.66
41
91
0.65
42
1484
0.64
43
94
0.23
44
264
0.21
45
1483
0.13
46
1485
0.12
100.00
219
55.5
0.3
55.0
0.3
45.0
0.4
41.4
0.1
65.9
0.1
62.3
0.0
47.3
0.1
47.9
Based on the added enhancements to the risk control and project overall performance, the
extracted project durations will be reduced by the remaining risk values assigned to each
activity. The program will recalculate the values of assigned risks to each activity as shown in
Table (A.5).
Table A.5: Initial and Residual Relative Index of Risks Assigned to each Activity
Activity
ID
Activity Title
Initial
Risk
Factor
Modified
Risk
Factor
Residual
Risk
%
02
8.70
4.04
46.4
03
8.70
4.04
46.4
04
8.70
4.04
46.4
05
8.70
4.04
46.4
06
8.70
4.04
46.4
07
8.70
4.04
46.4
08
8.75
4.28
48.9
09
15.24
7.22
47.4
10
14.59
6.89
47.2
11
14.59
6.89
47.2
12
14.59
6.89
47.2
13
8.64
4.20
48.6
14
17.60
8.57
48.7
15
17.60
8.57
48.7
16
17.60
8.57
48.7
17
19.78
9.44
47.7
18
19.13
9.11
47.6
19
19.13
9.11
47.6
20
14.59
6.89
47.2
21
14.59
6.89
47.2
22
8.64
4.20
48.6
23
17.60
8.57
48.7
24
17.60
8.57
48.7
25
17.60
8.57
48.7
26
19.78
9.44
47.7
220
27
19.13
9.11
47.6
28
19.13
9.11
47.6
29
14.59
6.89
47.2
31
23.23
11.09
47.7
32
17.60
8.57
48.7
33
17.60
8.57
48.7
34
17.60
8.57
48.7
35
19.78
9.44
47.7
36
19.13
9.11
47.6
37
19.13
9.11
47.6
38
13.46
6.42
47.7
39
17.79
8.88
49.9
40
17.79
8.88
49.9
585.80
280.81
47.9
The program will consider the residual risk factor as the modification factor of the
regression models and will calculate the modified mean and standard deviation values for
each activity. Based on the modified activities durations, the program will recalculate the
overall projects durations. Then the program will also make the necessary statistical analysis
to extract the overall project durations at different percentiles as well as the graphical curve
fitting for the projects durations as illustrated in Figure (A.2) and Table (A.6).
221
Figure A.2: Probability Density Function (PDF) and Curve Fitting for Modified Overall
Project Durations
Table A.6: Initial ad Modified Projects Durations at Different Percentiles
Percentile
P20
P25
P30
P35
P40
P45
P50
P55
P60
P65
P70
P75
P80
P85
P90
P95
375
398
424
447
472
497
528
557
590
626
670
726
787
867
1,002
1,285
365
378
394
408
423
439
455
473
493
517
540
569
604
646
705
829
222
The target project durations can be achieved at 75 percentiles; however the modified
projects durations will enhance the degree of reliability to about 92 percentile. On the other
hand, the owner is opted to carry out the project in about 569 days with 75 percentile.
223
.
%01 .
01
0111 . %7
%02 .
.
.
.
0007
0771 0722 %71
%01 %21 .
%71
0110
. 002
%71 .
.
%71
. %01
.
010
01 %11
.
%022 .
.
%001
%00 .
.
.
( :)
( )
.
.
.
.
0710
% 01 .
. .
.
) (CPM
) .(PERT
111 ) (ENR
) (CPM %71 %72 0771 .0112
.
()
.
.
.
.
.
.
) (PERT .
.
.
.
.
.
. 01
000,111 .
).(CSI
. 0070
.
. 01
000,111 .
:
.0
.0
.2
.1 .
) (CSI
.
.
.
.
:
( )0
.
( )0
.
( )2
( ).
.
( )1
.
:
.0
0070 . 02
01
7 .
.0 )0( :
; ( )2
; ( )2
.
%00
.
.2 %70
%00 %27 %0
.
.1
.
. .
.
.0
.
.0
021 ( )0.7 ()0.2
.
.7
( )0.00 .
.2
.
.
.
-
-
2109
. /
-
-
2109
-
-
2109