Académique Documents
Professionnel Documents
Culture Documents
Abstract
This paper describes new methods to economically improve
production levels in one of the mature fields of Petroleum
Development Oman. This field had been developed by infill
drilling programs, which were suspended in early 2001 to
review the development strategy. A reservoir management
team set a challenge to effectively conduct logging operations
and quickly utilize the data collected to identify and avail of
optimization opportunities, thus maximizing the production of
the wells whilst lowering overall costs. The optimization
activity consisted of clean-out, saturation logging, perforation
and stimulation. These activities were carried out either with
coiled tubing only utilizing conventional practises and e-line
coiled tubing, or with the combination of coiled tubing and
hoist through multiple well entries. Both of these methods
were successfull in that they resulted in incremental net oil
production but at relatively high costs.
This paper presents a methodology which enables clean-out,
logging, stimulation and perforation with one coiled tubing
intervention, which includes a plastic coated e-line coiled
tubing, coiled tubing perforating head and new perforation
technology. All systems are in complete compliance with the
most stringent safety criteria. The new method has a
considerable time and cost savings impact, and this is fully
illustrated in this paper with field trial case histories, in which
a multi-disciplinary team effectively targeted the most suitable
zones for perforation and stimulation using a state of the art
self diverting, non damaging, acid system. Technical and
economic comparisons are made with conventional practices.
The methodology is currently being employed in this field and
is potentially applicable to other fields.
Introduction
One of the matured fields of Petroleum Development Oman,
situated in North Oman and is mainly producing from the
Lower Cretaceous Shuaiba formation which is heavily faulted
and consists of intrashelf basin floor carbonate muds. Porosity
ranges from 30 to 35% while permeability ranges from 1 md
at the base of the Shuaiba to 200 md in thief zones. Average
matrix permeability is approximately 10 md. Permeabilities in
fault and fracture zones are believed to be orders of magnitude
higher than the average matrix permeability. Most of the
production comes from horizontal wells with 4 cemented
liner and perforated. The average current water cut from this
field is 93%. The high water cut presents longer term concerns
and Petroleum Development Oman has implemented a multidisciplinary effort with the ultimate goal of improving
production through a concerted CT and Hoist operations. A
very thorough evaluation of candidate selection is conducted
utilizing appropriate reservoir evaluation techniques, with
strong consideration to geology.
The development activities in this field traditionally have been
targeted by infill drilling with vertical wells until 1994
followed by horizontal wells. The infill well drilling was
suspended in early 2001. An integrated field review was
initiated to design the next era of this field development to
maximize the remaining value through effective well and
reservoir management. The well and reservoir management
team identified the need for data gathering through recording
reservoir saturations by running pulse neutron capture tools
(PNC) for identifying additional perforation opportunities. In
gas lifted wells the PNC logging was run on a coiled tubing
and in ESP (Electrical Submersible Pump) wells by pumping
the PNC tool inside the work string during hoist operations.
Based on the PNC logs, additional perforations were made in
many wells and the additional perforations improved the net
oil production from them. Hence, through PNC logging,
additional perforation and stimulation were given prime
importance in this field during the year 2004 in order to
maintain production levels. Various cost reduction measures
were applied to reduce the operating cost per barrel. One of
them is the novel idea of utilising coiled tubing for cleanout,
logging, mechanical water shut-off, perforation and
stimulation in one go. This paper describes the single rig-up
coiled tubing process that has eliminated multiple entries and
resulted in both cost reduction and less turn around time.
www.petroman.ir
SPE 94761
Challenge Definition
More than 90% of the wells are horizontal with 4
cemented and perforated liner with either gas lift or ESP
artificial lift completions. Most of the wells are producing at
more than 90% water cut. Typically the drawdown from these
wells ranges from 30 to 60% of the reservoir pressure. Also
the water is saturated with calcium carbonate (CaCO3) and the
gas contains approximately 3% carbon dioxide (CO2). Due to
the saturated nature of the water and high drawdown there is
often scales formation inside the tubing walls which required
cleaning out to enable entry to the perforations. In this
situation, any optimization activities require the following:
a. Clean-out
b. Logging
c. Water shut-off if any
d. Perforation if any
e. Stimulation
There are many ways of carrying out these activities.
However, cost effectiveness and a reduction in turn around
time were the challenges to the well and reservoir
management team and the service companies for carrying out
these jobs 1,2,3. Hence, we are comparing the single rig-up
coiled tubing solution with the two well proven technologies
of multiple entry coiled tubing operations and using the
combinations of coiled tubing and workover rig / hoist for the
gas lift wells.
Multiple Entry Coiled Tubing Operations
This method requires four three interventions but using only
coiled tubing units ie rigless or without a hoist. The sequence
of operations conducted is described below:
A) Cleanout of the horizontal cemented liner with
conventional coiled tubing.
B) PNC reservoir saturation logging with e-line coiled
tubing.
C) Perforating using conventional coiled tubing with
hydraulic firing head followed with stimulation treatment
across new perforations executed by running in and
retrieving a series of perforating gun strings under live
well pressure (RPGSP).
Table-1 shows the approximate well cost and the time frame
required for the full project from cleaning the well through
PNC saturation logging, placing additional perforations to
stimulating. The overall turnaround time for these operations
required was at least 3 months in cases where execution
proceeded without significant problems
Combination of Coiled tubing and Hoist operations
In this method there are three interventions, two coiled tubing
and one hoist operation. The sequence of operations is as
follows:
A) Cleanout of scale in the horizontal cemented liner with
normal interventions with normal coiled tubing
B) PNC logging with e-line coiled tubing.
C) Perforation and stimulation with a workover rig or hoist
unit.
The first two operations are not combined with the workover
rig/hoist operation because reservoir saturation logging under
flowing conditions is a requirement in order to avoid any
flushing, i.e water flowing back ino the formation showing
higher saturation against the high permeability zone under
static conditions as wells are producing more than 90% water
cut. Also it was observed that the stimulation was not effective
even with a polymer based diverting system in combination
with wash cups or straddle packer systems with minimal
spacing of 3 m due to the highly fractured environment.
Table-2 shows the approximate well intervention cost and
time required for these jobs. The turn around time in this case
is around 2 months.
One Rig-up Coiled Tubing solution- New Intervention
Method
This method calls for only one intervention with plastic coated
cable inside the coil tubing eliminating the multiple
interventions. This set up is capable of completing all four
objectives: well clean out, saturation logging, multiple zone
perforation and stimulation.
This method was possible with the development of technology
in the field of coiled tubing perforation, e-coil, and the
perforation gun systems. The following are the components of
the system:
A plastic coated logging cable. The logging cable provides
the electrical connection between the downhole tools and
the surface processing equipment. In conventional wireline
applications, the cable is always kept under tension, with
operating techniques and practices applied to maintain the
correct degree of cable tension and mechanical stability.
However, when installed in a CT string, there are
conditions under which a significant portion of the cable
may experience compression forces near the bottom end of
the string. If severe or sudden compression forces are
applied, the cable armor may distort. This will almost
certainly result in the loss of conductivity or insulation in
one or all of the conductors. To counteract such unstable
conditions encountered by cables installed in the CT string,
a jacked armored cable was developed specifically for CT
logging operations. An outer sheath or jacket is applied to
the cable during the manufacturing process to provide
several benefits. The coating and modified armor
construction for CT logging cables provides a more stable
cable structure under the varying forces experienced within
the CT string. In addition, the coating provides protection
from treatment fluids pumped through the CT string which
may degrade the mechanical or electrical performance of
the cable.
Coiled tubing logging/perforation head, which consists of
electrical quick connector with mechanical weak point for
electric line and dual flapper valve to prevent wellbore
fluid flow within coiled tubing. This logging/perforating
head has dual release mechanism (exceed flow limit and
overpull simultaneously), which will prevent unintentional
releases during logging and perforation.
CT deployment bar- is used to make up a long tool when
the tool string or bottom hole assembly can not be rigged
www.petroman.ir
SPE 94761
www.petroman.ir
SPE 94761
www.petroman.ir
SPE 94761
Item
Cost
Days
17,000
60,000
210,000
287,000
2
2
6
10
Cost
Days
17,000
60,000
250,000
327,000
2
2
7
11
Item
CT Cleanout (w/ conventional CT)
PNC logging (w/ E-line CT)
Additional Perforation and Stimulation (w/ Hoist)
Total
Table-2:- Proven Technology Using Combined Coiled Tubing and Workover Rig / Hoist Entries
Cost
Days
17,000
50,000
133,000
28,000
2
1
2
1
Total
228,000
Item
Sl. No
Well No.
Well-A
Well-B
Well-C
Well-D
Well-E
Well-F
Well-G
Well-H
Well-I
10
Well-J
Actual
Oil Gain,
m3/d
Expected
Oil Gain,
m3/d
34
Before
After
Gross
Net
%
Water
Cut
Gross
Net
%
Water
Cut
30
458
29
93.7
556
63
88.7
23
24
570
99.6
523
25
95.2
-3
23
567
30
94.7
611
27
95.6
11
50
507
32
93.7
646
43
93.3
214
105
1221
31
97.5
1580
245
84.5
31
30
1106
100.0
460
31
93.3
57
26
343
22
93.6
1022
79
92.3
26
15
582
30
94.8
662
56
91.5
88
36
1237
33.5
97.3
950
121
87.3
23
181
43
76.2
245
51
79.2
489
362
Table-4 Comparision of Actual oil gains with expected gains from the wells where single rig-up coil tubing technology was implemented
www.petroman.ir
SPE 94761
CT Connector
Logging/
Perforating Head
In je c t o r
H ead
S w ivel
L u b r ic a to r
Deploym ent Bar
S h e a r S e a l/
Com bi BO P
CCL
Q uad B O P
W e ll H e a d
Firing Head
P erforation G un
www.petroman.ir
SPE 94761
Well - B
750
100
Axis 1
Calendar Day Oil Rate ( m3/d )
Calendar Day Liquid Rate ( m3/d )
Test Liquid Rate (m3/d)
600
80
Axis 2
Water Cut ( % )
Test.Bsw ( % )
Average Days of Prodn ( Date )
Lift Gas ( Kscm/d )
450
60
300
40
150
20
1997
98
99
750
01
02
03
100
Nearby Well
Axis 1
Calendar Day Oil Rate ( m3/d )
Calendar Day Liquid Rate ( m3/d )
Test Liquid Rate (m3/d)
600
2000
80
Axis 2
Water Cut ( % )
Test.Bsw ( % )
Average Days of Prodn ( Date )
Lift Gas ( Kscm/d )
450
60
300
40
150
20
1
1997
98
99
2 3
2000
www.petroman.ir
01
02
4
03
SPE 94761
Ideas
High Value / Difficult:
High Value / Easy:
1. Combine the last two perforating runs (3rd 1. Hold a kick-off meeting prior to commencement of operations
2.
Preview the job activities.
& 4th 60m) using RPGSP
3.
Confirm accommodations for the unit crew.
2. Investigate chemical shutoff instead of
4.
Mobilization
5.
Field supervisor travels to the field one to two days prior to ensure
bridge plug for water shutoff
that site is prepared, ready and safe for operations and that the
3. Reduce log interpretation turn around time.
permit is signed.
6.
7.
V
A
L
U
E
8.
9.
10.
11.
12.
1.
Ease of imImplementation
www.petroman.ir