Project Specification
SECTION 11 66 00
PLAYGROUND EQUIPMENT
PART 1 - GENERAL
1.01
A.
1.02
SUMMARY
The work included in this Section comprises the performance requirements for materials and
workmanship for the installation of playground equipment, sand surfaces and other
miscellaneous equipment associated with the project playgrounds.
RELATED SECTIONS
A.
B.
C.
D.
E.
F.
1.03
A.
REFERENCES
Product manufacture, testing and installation shall comply with the following references,
unless otherwise specified or unless otherwise approved by the Engineer.
1.
B.
All items of playground equipment are to be tested and certified standard compliant by TUV
testing institute.
C.
Materials that have not been individually specified in this document will be of international
standard. Any differences between their requirements and this specification shall be
submitted by the Contractor.
1.04
A.
GENERAL REQUIREMENTS
Product manufacturer, testing and installation shall comply with the following requirements,
unless otherwise approved by the Engineer.
1.
Play Equipment shall conform to the locations and levels on the drawings unless
otherwise approved by the Engineer.
2.
All materials for use in construction shall be obtained only from sources approved by
the Engineer.
PLAYGROUND EQUIPMENT
SECTION 11 66 00 - 1
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
1.05
A.
3.
The specific source of materials shall not be changed without prior written approval of
the Engineer.
4.
If the grading and quality of material delivered to the site does not conform to the
grading and quality as previously inspected and tested or does not comply with the
specifications, the Engineer may reject such material at the site of the work.
5.
Sufficient materials must be stored in stockpiles to allow for testing and approval of
such materials prior to use in works.
SUBMITTALS
Product Approval
1.
B.
Project Specification
The Contractor shall submit sufficient information to the Engineer, prior to purchase,
according to Section 013000, in order to verify compliance with the plans and
specifications. Such information shall include at least the following, unless otherwise
required by the Engineer.
a.
Manufacturers name.
b.
Suppliers name.
c.
d.
Product description.
e.
f.
Storage instructions.
g.
h.
i.
Samples
1.
Samples (applied) shall be supplied for at least the following products or as requested
by the Engineer.
a. Playground Equipment.
b. 200mm length of typical structural members (post) from each source.
c. 200mm length, 200mm width panels from each source.
i.
ii.
iii.
2.
C.
Method Statement
1.
The Contractor shall provide separate method statements meeting the requirements of
Section 01400, for at least the following activities or as requested by the Engineer.
PLAYGROUND EQUIPMENT
SECTION 11 66 00 - 2
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
Project Specification
Shop Drawings
1.
The Contractor shall submit shop drawings according to Section 01300 for at least the
following items.
a. Playground Equipment.
E.
Mock-up
1.
The Contractor shall prepare a mock-up meeting the requirements of Section 01400 for
at least the following installations or as requested by the Engineer.
a. Playground Equipment.
b. Provide mockup of layout where directed by the Engineer.
c. 1 No. mock-up per item specified (site furniture to be fixed as per final
arrangement).
d. Show range of shades, color, texture and line marking.
e. Accepted mockup may become part of the work.
1.06
A.
QUALITY CONTROL
Prior to dispatch from the factory, the Contractor shall notify the Engineer, in sufficient time
to allow the Engineer or his representatives to inspect and test the products, if so desired.
1.
2.
B.
Inspection Requests shall be submitted to the Engineer during the on site installation work
prior to proceeding with at least the following activities. Minimum notification time shall be
24 hours. They shall include but not be limited to;
1.
2.
PLAYGROUND EQUIPMENT
SECTION 11 66 00 - 3
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
C.
3.
4.
Project Specification
Testing Laboratory
1.
Testing of all materials shall be carried out by a suitably equipped site laboratory or in
an independent laboratory as described in Section 01400 and approved by the
Engineer.
a. Routine materials testing and site testing shall always be conducted in the site
laboratory, unless otherwise agreed by the Engineer.
b. All sampling shall be witnessed by the Engineer, unless otherwise directed by the
Engineer.
D.
2.
During the course of the work, all required tests shall be carried out under the
supervision of the Engineer, to ascertain the suitability of materials according to this
specification.
3.
The Contractor shall maintain a daily log of all tests carried out for the Engineers
review.
Manufacturer Qualifications:
1.
2.
E.
The contractor shall record the batch number of each product used on the site and maintain it
through the warranty period.
F.
The contractor shall provide the inspector, upon request, an estimate of the volume of each
product to be used on the site.
1.07
A.
2.
Only nylon slings shall be allowed for lifting products. Steel chains, clamps or cables
shall not be allowed for lifting purposes, unless approved by the Engineer.
a. Steel chains or cables may be allowed for securing products during transport or
storage provided protective padding or timber blocking is utilized.
3.
PLAYGROUND EQUIPMENT
SECTION 11 66 00 - 4
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
Project Specification
5.
6.
B.
C.
The Contractor shall visually inspect all products upon delivery and report any damage
to the Engineer.
a. Any products damaged during delivery, storage or installation shall be marked by
the Contractor and set aside.
Delivery
1.
Deliver materials and products in factory labeled packages indicating name, brand,
type, size, color, production date and expiry date where applicable.
2.
Sequence deliveries to avoid project delays and to permit proper co-ordination of the
work.
Storage
1.
2.
Deliver product to the site in original unopened containers with proper labels attached.
PART 2 - PRODUCTS
2.01
GENERAL
A.
All products supplied to be used with the contract area shall meet current (ISO) international
standards for design and manufacturing. These shall be suitable for use in extreme climatic
conditions with UV protection and other surface protection to international standards. All
items will be reviewed and approved on a case by case basis.
B.
The finish and color of all products shall match the drawings as directed by the Engineer.
2.02
A.
PLAYGROUND EQUIPMENT
SECTION 11 66 00 - 5
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
Project Specification
PLAYGROUND EQUIPMENT
SECTION 11 66 00 - 6
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
Project Specification
2. Metal. All metal components shall be brass, stainless steel, anodized aluminum, hot
dipped galvanized or electric galvanized powder coated steel.
3. Plastic. All plastic based components in the architectural and landscaping works shall be
suitable and appropriate for the local climatic conditions.
a. The physical and mechanical properties, along with the durability and stability, of the
plastics shall not show signs of distress, degradation, change of shape, degradability,
stress or stain when exposed to the local environmental conditions. The plastic shall
have a high UV-resistant rating and product warranty that the plastic elements do not
fade in colour within 10 years of fixing.
b. For proprietary items, the Contractor and/or manufacturer/supplier shall provide all
the necessary information to the Engineer regarding the properties of any plastic
components. For any items or members, the Engineer may request the Contractor to
undertake in-house or independent testing to verify the properties and quality. Any
such testing shall be at the Contractors expense.
c. The Contractor or manufacturer/supplier shall provide testing certificates, project
references, and examples of existing similar items in service, as required by the
Engineer.
d. Screws, nuts, washers, bolts, and other hardware shall be of austenitic stainless steel,
or galvanized steel, or as directed by the approved manufacturer or supplier.
e. Final approval of the component will be based on the Engineers satisfaction that the
materials proposed are reputable, structurally sound and that all materials are of a
high quality suitable for the local environment.
4. Nets and Ropes. All ropes shall be pre- stretched and steel reinforced, with an ultimate
tensile strength not less than 2200 kg. The minimum diameter of the rope shall be 12mm.
Nets shall be made of 16mm diameter rope, assembled with stainless steel couplers. All
rope ends shall be looped with aluminum couplers.
5. Hardware. All hardware shall be either stainless steel, cast aluminum, anodized
aluminum, hot-dip galvanized, or electric galvanized, and powder coated steel and tamper
proof.
6. Rubber. Rubber elements shall be made from vulcanized UV resistant rubber, with the
addition of fire retardant and weather proofing material.
2.04
PLAY EQUIPMENT
A.
Specific Play Equipment for all playgrounds shall be as identified in the plans and details.
B.
Play Equipment and playgrounds are developed based on the ages of the intended users.
Playgrounds shall include different combinations of equipment within any one project site.
PART 3 - EXECUTION
3.01
A.
GENERAL
All operations shall be performed in accordance with the specification, and in conformity
with the lines, grades, thickness and typical cross Section shown on the plans or established
by the Engineer. Only approved material shall be used in the construction. The embankment
and subgrade in fill shall be constructed utilizing only suitable material obtained from
PLAYGROUND EQUIPMENT
SECTION 11 66 00 - 7
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
Project Specification
roadway excavation or imported fill material from sources previously approved by the
competent authority.
3.02
A.
Site preparation and clearing shall comply with Section 02200, unless otherwise approved by
the Engineer.
B.
Verify that substrates are stable and capable of supporting the weight of items covered under
this section.
C.
Verify that substrates have been adequately prepared to securely anchor those items that will
be surface mounted.
3.03
INSTALLATION
A.
B.
3.04
PROTECTION
A.
Erect temporary barriers to protect site furniture during drying and curing.
B.
3.05
CLEAN UP
A.
Remove all containers, surplus materials and debris. Dispose of materials in accordance with
local, state and Federal regulations.
B.
END OF SECTION
PLAYGROUND EQUIPMENT
SECTION 11 66 00 - 8