Académique Documents
Professionnel Documents
Culture Documents
Load
Model
Risk
Model
Generating Unit
Forced Outage Rate
If the hazard rate of a generating unit is constant
h(t ) =
f (t ) = h(t )e
h ( )d
= e
f (t ) = e
F (t ) = f ( )d = e
= e
=e
F (t ) = 1 e
d
0
= 1 1 e t
R(t ) = e
The mean-time-to-failure is
= e dt
0
[
e ]
1
= [e e ]
t
0
MTTF =
= m (mean up time)
the mean-time-to-repair is
MTTR =
The mean-time-between-failures
m
A=
=
m+r +
[up time]
A=
[down time] + [up time]
University of the Philippines
Department of Electrical and Electronics Engineering
r
U=
=
m+r +
[down time]
U=
[down time] + [up time]
Markov Models
of Generation System
Up
State
Generator
1
2
UP
DOWN
Rate of
Departure
Rate of
Entry
Down
1
State
Gen 1
Gen 2
1
2
3
4
UP
DOWN
UP
DOWN
UP
UP
DOWN
DOWN
2
3
Rate of
Departure
1 + 2
1 + 2
1 + 2
1 + 2
Rate of
Entry
1 + 2
1 + 2
1 + 2
1 + 2
A. IDENTICAL UNITS
For identical units, binomial distribution is applicable. The
probability of exactly r successes in n trials is
n!
nr
Pr =
p r (1 p )
r! (n r )!
p = 1 - 0.03 = 0.97
2!
(0.97 )0 (1 0.97 )20 = 0.0009
0! (2 0 )!
2!
(0.97 )1 (1 0.97 )2 1 = 0.0582
1! (2 1)!
2!
(0.97 )2 (1 0.97 )22 = 0.9409
2! (2 2 )!
Capacity Out
Capacity Available
Probability
0
1
2
0 MW
10 MW
20 MW
20 MW
10 MW
0 MW
0.9409
0.0582
0.0009
1.0000
n=3
p = 1 - 0.03 = 0.97
P0 =
3!
(0.97 )0 (1 0.97 )30 = 0.000027
0! (3 0 )!
P1 =
3!
(0.97 )1 (1 0.97 )31 = 0.002619
1! (3 1)!
P2 =
3!
(0.97 )2 (1 0.97 )32 = 0.084681
2! (3 2 )!
P3 =
3!
(0.97 )3 (1 0.97 )33 = 0.912673
3! (3 3)!
Capacity Out
Capacity Available
Probability
0
1
2
3
0 MW
5 MW
10 MW
15 MW
15 MW
10 MW
5 MW
0 MW
0.912673
0.084681
0.002619
0.000027
1.000000
For 4 - 3 1
Units Out
Capacity Out
Capacity Available
Probability
0
1
2
3
4
0.00 MW
3.33 MW
6.66 MW
10.00 MW
13.33 MW
13.33 MW
10.00 MW
6.66 MW
3.33 MW
0.00 MW
0.88529281
0.10952076
0.00508086
0.00010476
0.00000081
1.000000
B. NON-IDENTICAL UNITS
Binomial distribution is not applicable
Basic probability concepts can be applied
EXAMPLE:
A system consist of two 3 MW units and one 5 MW
unit each with forced outage rate of 0.02.
Markov Transition States (23 = 8)`
State
1
2
3
4
5
6
7
8
Gen. 1
Gen. 2
Gen. 3
UP
UP
UP
DOWN
UP
UP
UP
DOWN
UP
UP
UP
DOWN
DOWN
DOWN
UP
UP
DOWN
DOWN
DOWN
UP
DOWN
DOWN
DOWN
DOWN
Capacity In
3+3+5 = 11 MW
0+3+5 = 8 MW
3+0+5 = 8 MW
3+3+0 = 6 MW
0+0+5 = 5 MW
3+0+0 = 3 MW
0+3+0 = 3 MW
0+0+0 = 0 MW
Capacity Out
0 MW
3 MW
3 MW
5 MW
6 MW
8 MW
8 MW
11 MW
Prof. Rowaldo R. del Mundo
17
Capacity In
Capacity Out
Probability
1
2
3
4
5
6
11 MW
8 MW
6 MW
5 MW
3 MW
0 MW
0
3
5
6
8
11
P1
P2 + P3
P4
P5
P6 + P7
P8
Capacity In
6 MW
3 MW
0 MW
Probability
0.9604
0.0392
0.0004
1.0000
Pin service
= 0.98
Capacity In
6 + 5 = 11 MW
3 + 5 = 8 MW
0 + 5 = 5 MW
Probability
( 0.9604 ) ( 0.98 ) = 0.941192
( 0.0392 ) ( 0.98 ) = 0.038416
( 0.0004 ) ( 0.98 ) = 0.000392
0.980000
Capacity In
6 + 0 = 6 MW
3 + 0 = 3 MW
0 + 0 = 0 MW
Probability
( 0.9604 ) ( 0.02 ) = 0.019208
( 0.0392 ) ( 0.02 ) = 0.000784
( 0.0004 ) ( 0.02 ) = 0.000008
0.020000
Capacity In
11 MW
8 MW
6 MW
5 MW
3 MW
0 MW
Probability
0.941192
0.038416
0.019208
0.000392
0.000784
0.000008
1.000000
P(Ck ) =
Ci C j
Ck C j
P(Ci )
EXAMPLE:
Obtain the rounded probability table of the generation
system in the previous example rounded in 5 MW
increments.
For Capacity
Out of Service
0 MW
3 MW
5 MW
6 MW
8 MW
Ci
0 MW
3 MW
5 MW
6 MW
8 MW
Cj
Ck
(Exact)
0 MW
5 MW
(Exact)
5 MW
10 MW
5 MW
10 MW
P(Ci)
P(Cj)
P(Ck)
0.941192
0.038416
0.019208
0.000392
0.000784
0.9411920
0.0153665
0.0192080
0.0003136
0.0003136
0.0000000
0.0230497
0.0000000
0.0000784
0.0004704
Individual Probability
0.941192 + 0.0153664
0.0230496 + 0.019208 + 2(0.0003136)
0.0000784 + 0.0004704 + 0.0000064
0.0000016
=
=
=
=
0.9565584
0.0428848
0.0005552
0.0000016
1.0000000
Prof. Rowaldo R. del Mundo
25
P (X)
P(X)
Cumulative Probability of X MW
or more on outage of new table
Probability of X MW or more on
outage of old table
Capacity of unit to be added
otherwise
FOR
0.02
0.02
0.02
C = 3 MW
= 1.0
= 0.02
= 0.02
= 0.02
C = 3 MW
= 1.0
= 0.0396
= 0.0396
= 0.0004
= 0.0004
= 0.0004
= 0.0396
C = 5 MW
= 1.0
= 0.058808
= 0.020392
= 0.000792
= 0.000008
= 0.001184
STEPS
UNIT RATING (MW)
A
100
B
150
C
200
FOR
0.01
0.02
0.03
No. of states = 23
1. Initialize Table
2. Enter Unit A
3. Enter Unit B
4. Enter Unit C
X MW
P'(X)
(X - C) MW
P'(X-C)
P(X)
1
2
3
4
5
6
7
8
9
10
0
50
100
150
200
250
300
350
400
450
1.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
-100
-50
0
50
100
150
200
250
300
350
1.000000
1.000000
1.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
1.000000
0.010000
0.010000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
X MW
0
50
100
150
200
250
300
350
400
450
P'(X)
(X - C) MW
1.000000
-150
0.010000
-100
0.010000
-50
0.000000
0
0.000000
50
0.000000
100
0.000000
150
0.000000
200
0.000000
250
0.000000
300
P'(X-C)
1.000000
1.000000
1.000000
1.000000
0.010000
0.010000
0.000000
0.000000
0.000000
0.000000
P(X)
1.000000
0.029800
0.029800
0.020000
0.000200
0.000200
0.000000
0.000000
0.000000
0.000000
X MW
0
50
100
150
200
250
300
350
400
450
P'(X)
1.000000
0.029800
0.029800
0.020000
0.000200
0.000200
0.000000
0.000000
0.000000
0.000000
(X - C) MW
-200
-150
-100
-50
0
50
100
150
200
250
P'(X-C)
1.000000
1.000000
1.000000
1.000000
1.000000
0.029800
0.029800
0.020000
0.000200
0.000200
P(X)
1.000000
0.058906
0.058906
0.049400
0.030194
0.001088
0.000894
0.000600
0.000006
0.000006
P( X ) = pi P' ( X Ci )
i =1
Where,
Ci
pi
Capacity Out
0
2
5
State Probability
0.960
0.033
0.007
C1 = 0 MW
n = 2;
C2 = 2 MW
n = 3;
C3 = 5 MW
= 1.0
= 0.078016
= 0.0463228
= 0.0086908
= 0.0006744
= 0.000283272
P(11) = (0.960 )P' (11 0 ) + (0.033 )P' (11 2 ) + (0.007 )P' (11 5 )
= (0.960 )(0 ) + (0.033 )(0 ) + (0.007 )(0.0004 )
= 0.000002
P( X ) (FOR )P' ( X C )
(
)
P' X =
1 FOR
EXAMPLE:
Using the obtained capacity outage probability table
for the 100 MW system (2 - 25 MW and 1 - 50 MW).
Remove the 50MW Unit with FOR = 0.02
Capacity Out of Service (MW)
0
25
50
75
100
Cumulative Probability
1.000000
0.058808
0.020392
0.000792
0.000008
P(0 ) =
P(25 ) =
=
= 1.0
= 0.0396
P(50 ) =
= 0.0004
Capacity In
(MW)
Individual
Probability
Cumulative
Probability
240
0.785678
1.000000
10
230
0.190467
0.214322
20
220
0.022125
0.023855
30
210
0.001639
0.001730
40
200
0.000087
0.000091
50
190
0.000004
0.000004
Capacity In
(MW)
Individual
Probability
Cumulative
Probability
240
0.886384
1.000000
20
220
0.107441
0.113616
40
200
0.005969
0.006175
60
180
0.000201
0.000206
80
160
0.000005
0.000005
Capacity In
(MW)
Individual
Probability
Cumulative
Probability
240
0.693841
1.000000
20
220
0.257509
0.306159
40
200
0.043803
0.048650
60
180
0.004516
0.004847
80
160
0.000314
0.000331
100
140
0.000016
0.000017
120
120
0.000001
0.000001
Capacity In
(MW)
Individual
Probability
Cumulative
Probability
220
0.801631
1.000000
10
210
0.178140
0.198369
20
200
0.018894
0.020229
30
190
0.001272
0.111335
40
180
0.000061
0.000063
50
170
0.000002
0.000002
Total
Capacity
Load
% Reserve
Probabilistic Risk
System 1
240 MW
200 MW
20%
0.000004
System 2
240 MW
200 MW
20%
0.000206
System 3
240 MW
200 MW
20%
0.004847
System 4
220 MW
183 1/3 MW
20%
0.000063
Note that the risk in system 3 is more than 1000 times greater than that in system 1
Analysis of the four systems shows that the variation in true risk depends upon FOR,
number of units and load demand
University of the Philippines
Department of Electrical and Electronics Engineering
Cap/
Unit
Units
System 1
10 MW
24
230 MW
10 MW
0.023855
System 2
20 MW
12
220 MW
20 MW
0.006175
System 3
20 MW
12
220 MW
20 MW
0.048650
System 4
10 MW
22
210 MW
10 MW
0.020229
Load
It is seen from the above comparison that deterministic approaches in power reserve
margin planning are inconsistent, unreliable and subjective.
Daily Peak, MW
Load Models
365
Day
Linearized LVC
LOLP = pk t k
k =1
n
LOLP = (t k t k 1 )Pk
k =1
n
= Tk Pk
k =1
Where, Ok tk
pk
Pk
Capacity
Individual Cumulative
Out of
Probability Probability
Service
0
0.950991
1.000000
40
0.048029
0.049009
80
0.000971
0.000980
120
0.000009
0.000009
Note: Probability values less than
10-8 have been deleted.
03 = 80MW
04 = 120 MW
160
T4 = 41.7%
120
t3 = T3 = 41.7%
80
64
t4 = 83.4%
Time (%)
64
100
Capacity In
Service (MW)
200
160
120
80
Total Time, tk
Individual
Probability, pk
(% )
0.950991
0.0
0.048029
0.0
0.000971
41.7
0.000009
83.4
LOLP
pk tk
0.0000000
0.0000000
0.0404907
0.0007506
0.0412413
Capacity In
Service (MW)
200
160
120
80
LOLP
P k Tk
0.0000000
0.0000000
0.0408660
0.0003753
0.0412413
LOLP = Pi (Ci Li )
days/period
i =1
Where,
Ci
Li
Day
1
2
3
4
5
MW
95
120
160
110
90
G1
100
0
100
100
0
0
100
0
G2
150
150
0
150
0
150
0
0
G3
200
200
200
0
200
0
0
0
IND
CUMULATIVE
0.941094
1.000000
0.009506
0.058906
0.019206
0.049400
0.029106
0.030194
0.000194
0.001088
0.000294
0.000894
0.000594
0.000600
0.000006
0.000006
Load Model
DAY
1
2
3
4
5
MW
95
120
160
110
90
DAY
1
2
3
4
5
MW
160
120
110
95
90
Prof. Rowaldo R. del Mundo
57
System Reliability
SYSTEM
PEAK LOAD
DAY
CAPACITY (MW)
(MW)
1
2
3
4
5
450
450
450
450
450
160
120
110
95
90
RESERVE
(MW)
290
330
340
355
360
LOLP
PROB. OF
LOSS-OFLOAD
0.000894
0.000600
0.000600
0.000006
0.000006
0.002106
Capacity (MW)
25
25
50
FOR
0.02
0.02
0.02
57
52
46
41
34
No. of Occurences
12
83
107
116
47
= 365 days
Cumulative Probability
1.000000
0.058808
0.020392
0.000792
0.000008
Scheduled Outages
The system capacity evaluation examples previously
considered assumed that the load model applied to the entire
period and that the capacity model was also applicable for the
entire period. This will not be the case if the units are removed
from services for periodic inspection and maintenance in
accordance with the planned program. During this period, the
capacity available is not constant and therefore a single
capacity outage probability table is not applicable.
System Daily Peak Load
Units on
maintenance
Reserve
December 31
LOLPa = LOLPp
p =1
R1
P1
P2
P3
Subdivision of Period
University of the Philippines
Department of Electrical and Electronics Engineering
Load
Installed Capacity
Reserve Capacity
Peak Load
Modified Load
Characteristic
Original Load
Characteristic
Capacity on
Maintenance
0 Time load exceeded the indicated value
Installed Capacity
Load
Reserve Capacity
Capacity on Maintenance
Peak Load
0.382
0.061
0.242
0.242
0.061
0.006
-3
0.006
-2
-1
+1
+2
+3
Example:
The capacity model of a system consisting of twelve 5 MW units,
each with forced outage rate of 0.01 is shown below.
Capacity Outage
(MW)
Cumulative
Probability
1.00000000
0.11361513
10
0.00617454
15
0.00020562
20
0.00000464
25
0.00000007
Mean = 50 MW
Number of
S. D.
(1)
Load
(MW)
(2)
Probability of
the Load (3)
LOLP (days/year)
(4)
(3) x (4)
-3
47
0.006
0.00562781
0.000033766
-2
48
0.061
0.00811645
0.000495103
-1
49
0.242
0.01050352
0.002541851
50
0.382
0.01279510
0.004887728
+1
51
0.242
0.08619473
0.020859125
+2
52
0.061
0.15677132
0.009563050
+3
53
0.006
0.22468462
0.001348107
Peak megawatt
demand
Megawatts
Alternative 1
MW0
Years
1
2
3
4
5
6
7
8
160.0
176.0
193.6
213.0
234.3
257.5
283.1
311.4
Individual
Probability
0.950991
0.048029
0.000971
0.000009
1.000000
Cumulative
Probability
1.000000
0.049009
0.000980
0.000009
02 = 40MW
04 = 40 MW
160
T4 = 41.7%
120
t3 = T3 = 41.7%
80
64
t4 = 83.4%
64
Time (%)
100
Time periods during which loss of load occurs
Capacity In
Service (MW)
200
160
120
80
Individual
Probability
0.950991
0.048029
0.000971
0.000009
1.000000
Total Time
tk (% )
0.0
0.0
41.7
83.4
LOLE
(% )
0.0404907
0.0007506
0.0412413
Capacity In
Service (MW)
200
160
120
80
Cumulative
Probability
1.000000
0.049009
0.000980
0.000009
Total Time
tk (% )
0.0
0.0
41.7
41.7
LOLE
(% )
0.040866
0.0003753
0.0412413
System Peak
Load (MW)
100
120
140
160
180
200
220
240
250
260
280
300
320
340
350
LOLE (days/year)
200 MW
Capacity
0.001210
0.002005
0.086860
0.150600
3.447000
6.083000
-
System Peak
Load (MW)
100
120
140
160
180
200
220
240
250
260
280
300
320
340
350
LOLE (days/year)
200 MW 250 MW
Capacity Capacity
0.001210
0.002005
0.086860 0.001301
0.150600 0.002625
3.447000 0.068650
6.083000 0.150500
2.058000
4.853000
6.083000
-
LOLE (days/year)
System Peak 200 MW 250 MW 300 MW
Load (MW) Capacity Capacity Capacity
100
0.001210
120
0.002005
140
0.086860 0.001301
160
0.150600 0.002625
180
3.447000 0.068650
200
6.083000 0.150500 0.002996
220
2.058000 0.036100
240
4.853000 0.180000
250
6.083000 0.661000
260
3.566000
280
6.082000
300
320
340
350
-
System
Peak
Load (MW)
100
120
140
160
180
200
220
240
250
260
280
300
320
340
350
200 MW
Capacity
0.001210
0.002005
0.086860
0.150600
3.447000
6.083000
-
LOLE (days/year)
250 MW 300 MW
Capacity Capacity
0.001301
0.002625
0.068650
0.150500 0.002996
2.058000 0.036100
4.853000 0.180000
6.083000 0.661000
3.566000
6.082000
-
350 MW
Capacity
0.002980
0.004034
0.011750
0.107500
0.290400
2.248000
4.880000
6.083000
Load Models
HOUR
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
LOAD
1452
1422
1446
1405
1440
1464
1417
1455
1547
1498
1574
1535
1501
1499
1504
1487
1504
1659
2051
1960
1830
1718
1598
1661
P.U. LOAD
0.71
0.69
0.71
0.69
0.70
0.71
0.69
0.71
0.75
0.73
0.77
0.75
0.73
0.73
0.73
0.73
0.73
0.81
1.00
0.96
0.89
0.84
0.78
0.81
Load Models
HOUR
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
P.U. LOAD
1.00
0.96
0.89
0.84
0.81
0.81
0.78
0.77
0.75
0.75
0.73
0.73
0.73
0.73
0.73
0.73
0.71
0.71
0.71
0.71
0.70
0.69
0.69
0.69
LOEE = Ek pk
k =1
The per unit LOEE value represents the ratio between the
probable load energy curtailed due to deficiencies in
available generating capacity and the total energy
required to served the system demand.
160.00
152.90
142.76
134.02
129.58
129.42
124.66
122.79
120.68
119.75
117.33
117.33
13
14
15
16
17
18
19
20
21
22
23
24
117.09
116.94
116.86
116.00
114.21
113.51
113.27
112.80
112.34
110.93
110.54
109.61
Prof. Rowaldo R. del Mundo
82
PROB = 0.000294
CURTAILED EXPECTATION
10.00
2.90
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
12.901024
0.002940
0.000853
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.003793
PROB = 0.000594
CURTAILED EXPECTATION
60.00
52.90
42.76
34.02
29.58
29.42
24.66
22.79
20.68
19.75
17.33
17.33
17.09
16.94
16.86
16.00
14.21
13.51
13.27
12.80
12.34
10.93
10.54
9.61
535.309605
0.035640
0.031423
0.025399
0.020209
0.017568
0.017475
0.014649
0.013537
0.012285
0.011729
0.010293
0.010293
0.010154
0.010061
0.010015
0.009505
0.008439
0.008022
0.007883
0.007605
0.007327
0.006493
0.006261
0.005705
0.317974
PROB = 0.000006
CURTAILED EXPECTATION
160.00
152.90
142.76
134.02
129.58
129.42
124.66
122.79
120.68
119.75
117.33
117.33
117.09
116.94
116.86
116.00
114.21
113.51
113.27
112.80
112.34
110.93
110.54
109.61
2935.309605
0.000960
0.000917
0.000857
0.000804
0.000777
0.000777
0.000748
0.000737
0.000724
0.000718
0.000704
0.000704
0.000703
0.000702
0.000701
0.000696
0.000685
0.000681
0.000680
0.000677
0.000674
0.000666
0.000663
0.000658
0.017612
CURTAILED EXPECTATION
0.00
0.00000
0.00
0.00000
0.00
0.00000
0.00
0.00000
0.00
0.00000
12.90
0.00379
535.31
0.31797
2935.31
0.01761
0.33938
Load (MW)
75.0
52.5
30.0
20
100
Duration (hours)
2
3
Capacity (MW)
0
15
25
0
30
0
20
Probability
0.05
0.30
0.65
0.03
0.97
0.04
0.96
= EENS0 - EENS1
= 4575.0 - 2500.0
= 2075.0 MWh
University of the Philippines
Department of Electrical and Electronics Engineering
= EENS1 - EENS2
= 2500.0 - 401.7
= 2098.3 MWh
University of the Philippines
Department of Electrical and Electronics Engineering
= EENS2 - EENS3
= 401.7 - 64.08 = 337.6 MWh
University of the Philippines
Department of Electrical and Electronics Engineering