Vous êtes sur la page 1sur 91

EE 353 - Power System Reliability

Reliability of Generation System


Generating Capacity LOLE & LOEE
Prof. Rowaldo R. del Mundo
Department of Electrical and Electronics Engineering
University of the Philippines - Diliman

Conceptual Task & Generation


System Representation
Generation
Model

Load
Model

Risk
Model

Total System Generation

Total System Load

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


2

Generating Unit
Forced Outage Rate
If the hazard rate of a generating unit is constant
h(t ) =

The failure density function is exponential


t

f (t ) = h(t )e

h ( )d

= e

f (t ) = e

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


3

Generating Unit Forced Outage Rate

The cumulative failure distribution function is


t

F (t ) = f ( )d = e

= e

=e

F (t ) = 1 e

d
0

Then, the reliability function is


R(t ) = 1 F (t )

= 1 1 e t
R(t ) = e

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


4

Generating Unit Forced Outage Rate

The mean-time-to-failure is

MTTF = R(t )dt


0

= e dt
0

[
e ]

1
= [e e ]

t
0

MTTF =

= m (mean up time)

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


5

Generating Unit Forced Outage Rate

Also, if the repair rate function is constant


r (t ) =

the mean-time-to-repair is

MTTR =

= r (mean repair time)

The mean-time-between-failures

MTBF = mean uptime + mean repair time


= MTTF + MTTR
MTBF = m + r = T
and the cycle frequency is
1
f =
T
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


6

Generating Unit Forced Outage Rate

The Availability is the steady-state or long term


probability that the generating unit is in operating
condition (UP state)
mean up time
A=
cycle time
mean up time
A=
mean up time + mean repair time
m f
A= =
T

m
A=
=
m+r +

[up time]

A=
[down time] + [up time]
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


7

Generating Unit Forced Outage Rate

The Unavailability of a generating unit is the probability


of finding a unit on forced outage at some future time.
This is technically termed as Forced Outage Rate or
FOR.
U = 1 Availability
r f
U= =
T

r
U=
=
m+r +
[down time]

U=
[down time] + [up time]

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


8

Markov Models
of Generation System
Up

State

Generator

1
2

UP
DOWN

Rate of
Departure

Rate of
Entry

Down

Single Generating Unit

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


9

Markov Models of Generation System

1
State

Gen 1

Gen 2

1
2
3
4

UP
DOWN
UP
DOWN

UP
UP
DOWN
DOWN

2
3

Rate of
Departure
1 + 2
1 + 2
1 + 2
1 + 2

Rate of
Entry
1 + 2
1 + 2
1 + 2
1 + 2

Two Generating Units

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


10

Generating Capacity Model


(Capacity Outage Probability Table)

A. IDENTICAL UNITS
For identical units, binomial distribution is applicable. The
probability of exactly r successes in n trials is

n!
nr
Pr =
p r (1 p )
r! (n r )!

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


11

Generating Capacity Model


EXAMPLE 1:

2 10 MW units each with 0.03 forced outage rate


n=2
P0 =

p = 1 - 0.03 = 0.97

2!
(0.97 )0 (1 0.97 )20 = 0.0009
0! (2 0 )!

(probability that no generating unit is available)


P1 =

2!
(0.97 )1 (1 0.97 )2 1 = 0.0582
1! (2 1)!

(probability that exactly one generating unit is available)


P2 =

2!
(0.97 )2 (1 0.97 )22 = 0.9409
2! (2 2 )!

(probability that exactly two generating unit are available)


University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


12

Generating Capacity Model

The capacity outage table is summarized as follows:


Units Out

Capacity Out

Capacity Available

Probability

0
1
2

0 MW
10 MW
20 MW

20 MW
10 MW
0 MW

0.9409
0.0582
0.0009
1.0000

Note: The probability of all possible cases must sum


to unity

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


13

Generating Capacity Model


EXAMPLE 2:

3 5 MW units each with 0.03 forced outage rate

n=3

p = 1 - 0.03 = 0.97

P0 =

3!
(0.97 )0 (1 0.97 )30 = 0.000027
0! (3 0 )!

P1 =

3!
(0.97 )1 (1 0.97 )31 = 0.002619
1! (3 1)!

P2 =

3!
(0.97 )2 (1 0.97 )32 = 0.084681
2! (3 2 )!

P3 =

3!
(0.97 )3 (1 0.97 )33 = 0.912673
3! (3 3)!

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


14

Generating Capacity Model

The capacity outage table is summarized as follows:


Units Out

Capacity Out

Capacity Available

Probability

0
1
2
3

0 MW
5 MW
10 MW
15 MW

15 MW
10 MW
5 MW
0 MW

0.912673
0.084681
0.002619
0.000027
1.000000

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


15

Generating Capacity Model

For 4 - 3 1

units with 0.03 forced outage rate

Units Out

Capacity Out

Capacity Available

Probability

0
1
2
3
4

0.00 MW
3.33 MW
6.66 MW
10.00 MW
13.33 MW

13.33 MW
10.00 MW
6.66 MW
3.33 MW
0.00 MW

0.88529281
0.10952076
0.00508086
0.00010476
0.00000081
1.000000

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


16

Generating Capacity Model

B. NON-IDENTICAL UNITS
Binomial distribution is not applicable
Basic probability concepts can be applied
EXAMPLE:
A system consist of two 3 MW units and one 5 MW
unit each with forced outage rate of 0.02.
Markov Transition States (23 = 8)`
State
1
2
3
4
5
6
7
8

Gen. 1

Gen. 2

Gen. 3

UP

UP

UP

DOWN

UP

UP

UP

DOWN

UP

UP

UP

DOWN

DOWN

DOWN

UP

UP

DOWN

DOWN

DOWN

UP

DOWN

DOWN

DOWN

DOWN

Capacity In
3+3+5 = 11 MW
0+3+5 = 8 MW
3+0+5 = 8 MW
3+3+0 = 6 MW
0+0+5 = 5 MW
3+0+0 = 3 MW
0+3+0 = 3 MW
0+0+0 = 0 MW

University of the Philippines


Department of Electrical and Electronics Engineering

Capacity Out
0 MW
3 MW
3 MW
5 MW
6 MW
8 MW
8 MW
11 MW
Prof. Rowaldo R. del Mundo
17

Generating Capacity Model


Note: The probability of exactly 3 MW is out of service is
the sum of the probabilities of states 2 and 3.
Similarly, the probability of exactly 8 MW is out of
service is the sum of the probabilities of states 6
and 7. Therefore states 2 and 3 can be combined
and states 6 and 7 can be combined to come up
with the reduced states capacity probability table.
New State

Capacity In

Capacity Out

Probability

1
2
3
4
5
6

11 MW
8 MW
6 MW
5 MW
3 MW
0 MW

0
3
5
6
8
11

P1
P2 + P3
P4
P5
P6 + P7
P8

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


18

Generating Capacity Model


Step 1: Combine the two identical units
(binomial distribution may be applied)
Capacity Out
0 MW
3 MW
6 MW

Capacity In
6 MW
3 MW
0 MW

Probability
0.9604
0.0392
0.0004
1.0000

Step 2: Add the 5 MW units considering that it can exist in


two state (in service or out of service)

Pin service

= 0.98

Pout of service = 0.02


University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


19

Generating Capacity Model


Step 2a: 5 MW unit in service
Capacity Out
0 + 0 = 0 MW
3 + 0 = 3 MW
6 + 0 = 6 MW

Capacity In
6 + 5 = 11 MW
3 + 5 = 8 MW
0 + 5 = 5 MW

Probability
( 0.9604 ) ( 0.98 ) = 0.941192
( 0.0392 ) ( 0.98 ) = 0.038416
( 0.0004 ) ( 0.98 ) = 0.000392
0.980000

Step 2b: 5 MW unit out of service


Capacity Out
0 + 5 = 5 MW
3 + 5 = 8 MW
6 + 5 = 11 MW

Capacity In
6 + 0 = 6 MW
3 + 0 = 3 MW
0 + 0 = 0 MW

University of the Philippines


Department of Electrical and Electronics Engineering

Probability
( 0.9604 ) ( 0.02 ) = 0.019208
( 0.0392 ) ( 0.02 ) = 0.000784
( 0.0004 ) ( 0.02 ) = 0.000008
0.020000

Prof. Rowaldo R. del Mundo


20

Generating Capacity Model

Step 2c: Combine probability tables in steps 2a and 2b


Capacity Out
0 MW
3 MW
5 MW
6 MW
8 MW
11 MW

Capacity In
11 MW
8 MW
6 MW
5 MW
3 MW
0 MW

University of the Philippines


Department of Electrical and Electronics Engineering

Probability
0.941192
0.038416
0.019208
0.000392
0.000784
0.000008
1.000000

Prof. Rowaldo R. del Mundo


21

Generating Capacity Model

Cumulative Probability Table


An additional column can be added to the capacity
outage probability table which gives the cumulative
probability. This is the probability of finding a quantity of
capacity on outage equal or greater than the indicated
amount.
Capacity Out of Service Individual Probability Cumulative Probability
0 MW
0.941192
1.000000
3 MW
0.038416
0.058808
5 MW
0.019208
0.020392
6 MW
0.000392
0.001184
8 MW
0.000784
0.000792
11 MW
0.000008
0.000008
1.000000

P(cap out 3) = P3 + P5 + P6 + P8 + P11


P(cap out 5 ) = P5 + P6 + P8 + P11
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


22

Generating Capacity Model

Truncating the Probability Table


Theoretically, the capacity outage probability table
incorporates all the system capacity. The table, however,
can be truncated by omitting all capacity outages for
which the cumulative probability is less than a specified
amount, e.g., 10-8.

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


23

Generating Capacity Model

Capacity Rounding Probability Table


In a system containing a large number of units of different
capacities, the table will contain several hundred positive
discrete capacity outage levels. This number can be
greatly reduced by grouping the units into identical
capacity groups prior to combining or by rounding the
table to discrete levels after combining.
The rounding process is done by calculating
Ck Ci
P (C j ) =
P(Ci )
Ck C j

P(Ck ) =

Ci C j
Ck C j

P(Ci )

For all states i falling between the required rounding


states j and k.
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


24

Generating Capacity Model

EXAMPLE:
Obtain the rounded probability table of the generation
system in the previous example rounded in 5 MW
increments.
For Capacity
Out of Service
0 MW
3 MW
5 MW
6 MW
8 MW

Ci
0 MW
3 MW
5 MW
6 MW
8 MW

Cj

Ck

(Exact)
0 MW
5 MW
(Exact)
5 MW
10 MW
5 MW
10 MW

P(Ci)

P(Cj)

P(Ck)

0.941192
0.038416
0.019208
0.000392
0.000784

0.9411920
0.0153665
0.0192080
0.0003136
0.0003136

0.0000000
0.0230497
0.0000000
0.0000784
0.0004704

The final Rounded Probability Table is:


Capacity on
Outage (MW)
0 MW
5 MW
10 MW
15 MW

Individual Probability
0.941192 + 0.0153664
0.0230496 + 0.019208 + 2(0.0003136)
0.0000784 + 0.0004704 + 0.0000064
0.0000016

University of the Philippines


Department of Electrical and Electronics Engineering

=
=
=
=

0.9565584
0.0428848
0.0005552
0.0000016
1.0000000
Prof. Rowaldo R. del Mundo
25

Generating Capacity Model

Recursive Algorithm for Capacity Model Building


Addition in Probability Table one generating unit at a
time
Suitable for computerized computations
Cases
No Derated States
Derated States Included
Unit Removal

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


26

Generating Capacity Model

Case 1: No Derated States


The cumulative probability of a particular capacity outage
state of X MW after a unit of capacity C MW and forced
outage rate FOR is added is given by:
P( X ) = (1 FOR )P' ( X ) + (FOR )P' ( X C )
Where,

P (X)

P(X)

Cumulative Probability of X MW
or more on outage of new table
Probability of X MW or more on
outage of old table
Capacity of unit to be added

Initial Setting: P(X) = 1.0 for X 0,


P(X) = 0

otherwise

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


27

Generating Capacity Model


EXAMPLE 1:

UNIT RATING (MW)


1
3
2
3
3
5

FOR
0.02
0.02
0.02

Using the Recursive Algorithm, the system capacity outage


probability table is created sequentially as follows:
STEP 1: Add Unit No.1

C = 3 MW

P (0 ) = (1 FOR )P' (0 ) + (FOR )P' (0 3)


= (1 0.02 )(1.0 ) + (0.02 )(1.0 )

= 1.0

P (1) = (1 0.02 )P' (1) + (0.02 )P' (1 3)


= (0.98 )(0 ) + (0.02 )(1.0 )

= 0.02

P (2 ) = (1 0.02 )P' (2 ) + (0.02 )P' (2 3)


= (0.98)(0 ) + (0.02 )(1.0)

= 0.02

P (3) = (1 0.02 )P' (3) + (0.02 )P' (3 3 )


= (0.98 )(0 ) + (0.02 )(1.0 )

= 0.02

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


28

Generating Capacity Model


STEP 2: Add Unit No. 2

C = 3 MW

P (0 ) = (1 0.02 )P' (0 ) + (0.02 )P' (0 3 )


= (0.98 )(1.0 ) + (0.02 )(1.0 )

= 1.0

P (1) = (1 0.02 )P' (1) + (0.02 )P' (1 3)


= (0.98 )(0.02 ) + (0.02 )(1.0 )

= 0.0396

P (2 ) = (1 0.02 )P' (2 ) + (0.02 )P' (2 3)


= (0.98 )(0.02 ) + (0.02 )(1.0 )

= 0.0396

P (3) = (1 0.02 )P' (3) + (0.02 )P' (3 3 )


= (0.98 )(0.02 ) + (0.02 )(1.0 )
P (4 ) = (1 0.02 )P' (4 ) + (0.02 )P' (4 3)
= (0.98 )(0 ) + (0.02 )(0.02 )

= 0.0004

P (5 ) = (1 0.02 )P' (5 ) + (0.02 )P' (5 3 )


= (0.98 )(0 ) + (0.02 )(0.02 )

= 0.0004

P (6 ) = (1 0.02 )P' (6 ) + (0.02 )P' (6 3 )


= (0.98 )(0 ) + (0.02 )(0.02 )

= 0.0004

University of the Philippines


Department of Electrical and Electronics Engineering

= 0.0396

Prof. Rowaldo R. del Mundo


29

Generating Capacity Model


STEP 3: Add Unit No. 3

C = 5 MW

P (0 ) = (1 0.02 )P' (0 ) + (0.02 )P' (0 5 )


= (0.98 )(1.0 ) + (0.02 )(1.0 )

= 1.0

P (3) = (1 0.02 )P' (3) + (0.02 )P' (3 5 )


= (0.98 )(0.0396 ) + (0.02 )(1.0 )

= 0.058808

P (5 ) = (1 0.02 )P' (5 ) + (0.02 )P' (5 5 )


= (0.98 )(0.0004 ) + (0.02 )(1.0 )

= 0.020392

P (6 ) = (1 0.02 )P' (6 ) + (0.02 )P' (6 5 )


= (0.98 )(0.0004 ) + (0.02 )(0.0396 )
P (8 ) = (1 0.02 )P' (8 ) + (0.02 )P' (8 5 )
= (0.98 )(0 ) + (0.02 )(0.0396 )

= 0.000792

P (11) = (1 0.02 )P' (11) + (0.02 )P' (11 5 )


= (0.98 )(0 ) + (0.02 )(0.0004 )

= 0.000008

University of the Philippines


Department of Electrical and Electronics Engineering

= 0.001184

Prof. Rowaldo R. del Mundo


30

Generating Capacity Model


EXAMPLE 2:
Using the Recursive Algorithm, prepare the
generating capacity outage probability table of the
system with three (3) generating units:

STEPS
UNIT RATING (MW)
A
100
B
150
C
200

FOR
0.01
0.02
0.03

No. of states = 23

1. Initialize Table
2. Enter Unit A
3. Enter Unit B
4. Enter Unit C

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


31

Generating Capacity Model


STEP 1: Initialize the outage table
STATE
1
2
3
4
5
6
7
8
9
10

X MW or more on Outage Cumulative Probability


0
1.000000
50
0.000000
100
0.000000
150
0.000000
200
0.000000
250
0.000000
300
0.000000
350
0.000000
400
0.000000
450
0.000000

Probability when no unit yet is added into


the generation system
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


32

Generating Capacity Model

STEP 2: Add unit A : C = 100, FOR = 0.01, 1-FOR = 0.99


STATE

X MW

P'(X)

(X - C) MW

P'(X-C)

P(X)

1
2
3
4
5
6
7
8
9
10

0
50
100
150
200
250
300
350
400
450

1.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000

-100
-50
0
50
100
150
200
250
300
350

1.000000
1.000000
1.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000

1.000000
0.010000
0.010000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


33

Generating Capacity Model

STEP 3: Add unit B: C = 150, FOR = 0.02, 1-FOR = 0.98


STATE
1
2
3
4
5
6
7
8
9
10

X MW
0
50
100
150
200
250
300
350
400
450

P'(X)
(X - C) MW
1.000000
-150
0.010000
-100
0.010000
-50
0.000000
0
0.000000
50
0.000000
100
0.000000
150
0.000000
200
0.000000
250
0.000000
300

University of the Philippines


Department of Electrical and Electronics Engineering

P'(X-C)
1.000000
1.000000
1.000000
1.000000
0.010000
0.010000
0.000000
0.000000
0.000000
0.000000

P(X)
1.000000
0.029800
0.029800
0.020000
0.000200
0.000200
0.000000
0.000000
0.000000
0.000000

Prof. Rowaldo R. del Mundo


34

Generating Capacity Model

STEP 4: Add unit C : C = 200, FOR = 0.03, 1-FOR = 0.97


STATE
1
2
3
4
5
6
7
8
9
10

X MW
0
50
100
150
200
250
300
350
400
450

P'(X)
1.000000
0.029800
0.029800
0.020000
0.000200
0.000200
0.000000
0.000000
0.000000
0.000000

(X - C) MW
-200
-150
-100
-50
0
50
100
150
200
250

University of the Philippines


Department of Electrical and Electronics Engineering

P'(X-C)
1.000000
1.000000
1.000000
1.000000
1.000000
0.029800
0.029800
0.020000
0.000200
0.000200

P(X)
1.000000
0.058906
0.058906
0.049400
0.030194
0.001088
0.000894
0.000600
0.000006
0.000006

Prof. Rowaldo R. del Mundo


35

Generating Capacity Model

Case 2: Derated States Included


To include the multi-state unit representations, the
recursive equation is modified as follows:
n

P( X ) = pi P' ( X Ci )
i =1

Where,

Number of unit states

Ci

pi

Capacity outage of state i for


the unit being added
Probability of existence of the
unit state i

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


36

Generating Capacity Model


EXAMPLE 1:

5 MW unit 3-state representation


State
1
2
3

Capacity Out
0
2
5

State Probability
0.960
0.033
0.007

Replacing the 2-state 5 MW unit in the previous example


by the new 3-state unit,
n = 1;

C1 = 0 MW

n = 2;

C2 = 2 MW

n = 3;

C3 = 5 MW

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


37

Generating Capacity Model


P(0 ) = p1P' (0 0 ) + p2 P' (0 2 ) + p3 P' (0 5 )
= (0.960 )(1.0 ) + (0.033)(1.0 ) + (0.007 )(1.0 )

= 1.0

P(2 ) = (0.960 )P' (2 0 ) + (0.033)P' (2 2 ) + (0.007 )P' (2 5 )


= (0.960 )(0.0396 ) + (0.033 )(1.0 ) + (0.007 )(1.0 )

= 0.078016

P(3) = (0.960 )P' (3 0 ) + (0.033 )P' (3 2 ) + (0.007 )P' (3 5 )


= (0.960 )(0.0396 ) + (0.033 )(0.0396 ) + (0.007 )(1.0 )

= 0.0463228

P(5 ) = (0.960 )P' (5 0 ) + (0.033 )P' (5 2 ) + (0.007 )P' (5 5 )


= (0.960 )(0.0004 ) + (0.033 )(0.0396 ) + (0.007 )(1.0 )

= 0.0086908

P(6 ) = (0.960 )P' (6 0 ) + (0.033 )P' (6 2 ) + (0.007 )P' (6 5 )


= (0.960 )(0.0004 ) + (0.033 )(0.0004 ) + (0.007 )(0.0396 )

= 0.0006744

P(8 ) = (0.960 )P' (8 0 ) + (0.033 )P' (8 2 ) + (0.007 )P' (8 5 )


= (0.960 )(0 ) + (0.033)(0.0001184 ) + (0.007 )(0.0396 )

= 0.000283272

P(11) = (0.960 )P' (11 0 ) + (0.033 )P' (11 2 ) + (0.007 )P' (11 5 )
= (0.960 )(0 ) + (0.033 )(0 ) + (0.007 )(0.0004 )
= 0.000002

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


38

Generating Capacity Model

Case 3: Unit Removal


From the recursive algorithm for capacity model building,
P( X ) = (1 FOR )P' ( X ) + (FOR )P' ( X C )

The modified capacity model after a unit removal can be


obtained by working on the algorithm in reverse. Thus,

P( X ) (FOR )P' ( X C )
(
)
P' X =
1 FOR

Where: P(X-C) = 1.0 for X C

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


39

Generating Capacity Model

EXAMPLE:
Using the obtained capacity outage probability table
for the 100 MW system (2 - 25 MW and 1 - 50 MW).
Remove the 50MW Unit with FOR = 0.02
Capacity Out of Service (MW)
0
25
50
75
100

Cumulative Probability
1.000000
0.058808
0.020392
0.000792
0.000008

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


40

Generating Capacity Model


Removing the unit from the capacity outage probability
tables that gives the following modified capacity model:
P(0 ) (0.02 )P' (0 50 )
(1 0.02 )
1.0 (0.02 )(1.0 )
=
0.98

P(0 ) =

P(25 ) =
=

= 1.0

P(25 ) (0.02 )P' (25 50 )


(1 0.02 )
0.058808 (0.02 )(1.0 )
0.98

P(50 ) (0.02 )P' (50 50 )


(1 0.02 )
0.020392 (0.02 )(1.0 )
=
0.98

= 0.0396

P(50 ) =

University of the Philippines


Department of Electrical and Electronics Engineering

= 0.0004

Prof. Rowaldo R. del Mundo


41

Comparison of Deterministic and


Probabilistic Criteria
Consider the following four systems which are very
similar but not identical
SYSTEM 1 - 24 x 10 MW Units each having a FOR of 0.01
SYSTEM 2 12 x 20 MW Units each having a FOR of 0.01
SYSTEM 3 - 12 x 20 MW Units each having a FOR of 0.03
SYSTEM 4 - 22 x 10 MW Units each having a FOR of 0.01

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


42

Comparison of Deterministic and


Probabilistic Criteria
SYSTEM 1: Capacity Outage Probability Table
Capacity
Out (MW)

Capacity In
(MW)

Individual
Probability

Cumulative
Probability

240

0.785678

1.000000

10

230

0.190467

0.214322

20

220

0.022125

0.023855

30

210

0.001639

0.001730

40

200

0.000087

0.000091

50

190

0.000004

0.000004

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


43

Comparison of Deterministic and


Probabilistic Criteria
SYSTEM 2: Capacity Outage Probability Table
Capacity
Out (MW)

Capacity In
(MW)

Individual
Probability

Cumulative
Probability

240

0.886384

1.000000

20

220

0.107441

0.113616

40

200

0.005969

0.006175

60

180

0.000201

0.000206

80

160

0.000005

0.000005

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


44

Comparison of Deterministic and


Probabilistic Criteria
SYSTEM 3: Capacity Outage Probability Table
Capacity
Out (MW)

Capacity In
(MW)

Individual
Probability

Cumulative
Probability

240

0.693841

1.000000

20

220

0.257509

0.306159

40

200

0.043803

0.048650

60

180

0.004516

0.004847

80

160

0.000314

0.000331

100

140

0.000016

0.000017

120

120

0.000001

0.000001

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


45

Comparison of Deterministic and


Probabilistic Criteria
SYSTEM 4: Capacity Outage Probability Table
Capacity
Out (MW)

Capacity In
(MW)

Individual
Probability

Cumulative
Probability

220

0.801631

1.000000

10

210

0.178140

0.198369

20

200

0.018894

0.020229

30

190

0.001272

0.111335

40

180

0.000061

0.000063

50

170

0.000002

0.000002

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


46

Comparison of Deterministic and


Probabilistic Criteria
Percentage Reserve Margin Criteria
System

Total
Capacity

Load

% Reserve

Probabilistic Risk

System 1

240 MW

200 MW

20%

0.000004

System 2

240 MW

200 MW

20%

0.000206

System 3

240 MW

200 MW

20%

0.004847

System 4

220 MW

183 1/3 MW

20%

0.000063

Note that the risk in system 3 is more than 1000 times greater than that in system 1
Analysis of the four systems shows that the variation in true risk depends upon FOR,
number of units and load demand
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


47

Comparison of Deterministic and


Probabilistic Criteria
Largest Unit Reserve Criteria
System

Cap/
Unit

Units

Reserve Probabilistic Risk

System 1

10 MW

24

230 MW

10 MW

0.023855

System 2

20 MW

12

220 MW

20 MW

0.006175

System 3

20 MW

12

220 MW

20 MW

0.048650

System 4

10 MW

22

210 MW

10 MW

0.020229

Load

It is seen from the above comparison that deterministic approaches in power reserve
margin planning are inconsistent, unreliable and subjective.

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


48

Loss of Load Expectation


Loss of Load Expectation (LOLE)
The expected number of days in the specified period in
which the daily peak load will exceed the available
capacity.
Notes:
LOLE is known in the power industry as the LOLP.
LOLP is not a probability index but an expectation.

The expected risk of loss of load is determined by


convolving the system capacity outage table and the
system load characteristic.
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


49

Loss of Load Expectation

Daily Peak Demand


January 1
to
December 31

Daily Peak, MW

Load Models

365

Day

Actual Load Curve

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


50

Loss of Load Expectation


Load Models

Daily Peak Demand


Arrange in Descending Order

Load Variation Curve

Linearized LVC

The load is represented by its daily peak arranged in descending


order to form a cumulative load model called load variation curve.

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


51

Loss of Load Expectation


n

LOLP = pk t k
k =1
n

LOLP = (t k t k 1 )Pk
k =1
n

= Tk Pk
k =1

Magnitude of the kth outage in the system


capacity outage probability table
- Number of time units in the study interval that
an outage magnitude Ok would result in a loss
of load
- Individual probability of the capacity outage Ok.
- Cumulative outage probability for capacity state Ok.

Where, Ok tk

pk
Pk

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


52

Loss of Load Expectation


EXAMPLE 1:
Consider a system
containing 5 - 40 MW
units each with a FOR of
0.01. The capacity
outage probability table
is shown on the right.

Capacity
Individual Cumulative
Out of
Probability Probability
Service
0
0.950991
1.000000
40
0.048029
0.049009
80
0.000971
0.000980
120
0.000009
0.000009
Note: Probability values less than
10-8 have been deleted.

The system load model


is represented by the
daily peak load variation
curve in the figure on the
right.

Daily Peak Load (MW)

Installed Capacity = 200 MW


02 = 40MW

03 = 80MW

04 = 120 MW

160
T4 = 41.7%

120
t3 = T3 = 41.7%
80
64

t4 = 83.4%

Time (%)

64

100

Time periods during which loss of load occurs


University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


53

Loss of Load Expectation


LOLP using Individual Probabilities
Capacity Out of
Service (MW)
0
40
80
120

Capacity In
Service (MW)
200
160
120
80

Total Time, tk
Individual
Probability, pk
(% )
0.950991
0.0
0.048029
0.0
0.000971
41.7
0.000009
83.4

LOLP
pk tk
0.0000000
0.0000000
0.0404907
0.0007506
0.0412413

LOLP using the Cumulative Probabilities


Capacity Out of
Service (MW)
0
40
80
120

Capacity In
Service (MW)
200
160
120
80

Cumulative Total Time, Tk


Probability, Pk
(% )
1.000000
0.0
0.049009
0.0
0.000980
41.7
0.000009
41.7

LOLP
P k Tk
0.0000000
0.0000000
0.0408660
0.0003753
0.0412413

If the time considered is 365 days per year then,


LOLP = 365(0.0412413 100 ) = 0.1505307 days year
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


54

Loss of Load Expectation


It should be realized that there is difference between the
terms capacity outage and loss of load. The term
capacity outage indicates a loss of generation which
may or may not result in a loss of load.
n

LOLP = Pi (Ci Li )

days/period

i =1

Where,

Ci

- Available capacity on day i

Li

- Forecast peak load on day i

Pi(Ci Li) - Probability of loss of load on day i. This


value is obtained directly from the capacity
outage cumulative probability table.

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


55

Loss of Load Expectation


EXAMPLE 2:
What is the LOLP of the 450 MW system in a 5-day
period?

Generator and Demand Data


Unit Rating (MW) FOR
A
100
0.01
B
150
0.02
C
200
0.03

University of the Philippines


Department of Electrical and Electronics Engineering

Day
1
2
3
4
5

MW
95
120
160
110
90

Prof. Rowaldo R. del Mundo


56

Loss of Load Expectation


Generation Model
STATE
1
2
3
4
5
6
7
8

G1
100
0
100
100
0
0
100
0

G2
150
150
0
150
0
150
0
0

G3
200
200
200
0
200
0
0
0

CAP IN CAP OUT


450
0
350
100
300
150
250
200
200
250
150
300
100
350
0
450

IND
CUMULATIVE
0.941094
1.000000
0.009506
0.058906
0.019206
0.049400
0.029106
0.030194
0.000194
0.001088
0.000294
0.000894
0.000594
0.000600
0.000006
0.000006

Load Model
DAY
1
2
3
4
5

MW
95
120
160
110
90

DAY
1
2
3
4
5

University of the Philippines


Department of Electrical and Electronics Engineering

MW
160
120
110
95
90
Prof. Rowaldo R. del Mundo
57

Loss of Load Expectation

System Reliability
SYSTEM
PEAK LOAD
DAY
CAPACITY (MW)
(MW)
1
2
3
4
5

450
450
450
450
450

160
120
110
95
90

RESERVE
(MW)
290
330
340
355
360
LOLP

PROB. OF
LOSS-OFLOAD
0.000894
0.000600
0.000600
0.000006
0.000006
0.002106

LOLP = 0.002106 Days/5-Days


Annual LOLP

365 days period

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


58

Loss of Load Expectation


EXAMPLE 3:

100 MW system with annual peak load of 57 MW


System Capacity Data
Unit No.
1
2
3

Capacity (MW)
25
25
50

FOR
0.02
0.02
0.02

System Load Data


Daily Peak Load

57

52

46

41

34

No. of Occurences

12

83

107

116

47

University of the Philippines


Department of Electrical and Electronics Engineering

= 365 days

Prof. Rowaldo R. del Mundo


59

Loss of Load Expectation


Using the recursive algorithm, the capacity outage
cumulative probability table is
Capacity Out of Service (MW)
0
25
50
75
100

Cumulative Probability
1.000000
0.058808
0.020392
0.000792
0.000008

LOLP = 12 P(100 57 ) + 83 P(100 52 ) + 107 P(100 46 )


+ 116 P(100 41) + 47 P(100 34 )
= 12 P(43 ) + 83 P(48 ) + 107 P(54 ) + 116 P(59 ) + 47 P(66 )
= 12(0.020392 ) + 83(0.020392 ) + 107 (0.000792 )
+ 116 (0.000792 ) + 47 (0.000792 )
LOLP = 2.15108 days year
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


60

Loss of Load Expectation


LOLP Vs. Peak Load

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


61

Loss of Load Expectation

Scheduled Outages
The system capacity evaluation examples previously
considered assumed that the load model applied to the entire
period and that the capacity model was also applicable for the
entire period. This will not be the case if the units are removed
from services for periodic inspection and maintenance in
accordance with the planned program. During this period, the
capacity available is not constant and therefore a single
capacity outage probability table is not applicable.
System Daily Peak Load

Total Installed Capacity

Units on
maintenance

Reserve

Typical Annual Load


& Capacity Model
January 1

December 31

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


62

Loss of Load Expectation


Considering scheduled maintenance, the annual LOLPa can
be obtained by dividing the year into periods and calculating
the period LOLPP values using the modified capacity model
and the appropriate period load model.
The annual risk index is given by
n

LOLPa = LOLPp
p =1

System Daily Peak Load

Total Installed Capacity


R2
R3

R1

P1

P2

P3

Subdivision of Period
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


63

Loss of Load Expectation


Approximate methods may also be used to take into account
scheduled maintenance while using the original capacity
outage probability table such as shown in the following figures:

Load

Installed Capacity
Reserve Capacity
Peak Load

Modified Load
Characteristic
Original Load
Characteristic

Capacity on
Maintenance
0 Time load exceeded the indicated value
Installed Capacity

Load

Reserve Capacity
Capacity on Maintenance

Peak Load

0 Time load exceeded the indicated value


University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


64

LOLE with Load Forecast Uncertainty


The calculation of reliability indices presented so far assumes
that the actual peak load will differ from the forecast value
with zero probability. But some uncertainties exists in load
forecasting arising from the historical data considered, the
methodology used and the assumptions made. There is,
therefore, a need to improve the risks calculation by including
these uncertainties in building the system load model.
Studies made in the past had shown that the uncertainty in the
load forecasts can be reasonably described by a normal
distribution with the peak load value as the distribution mean
parameter. The distribution can be divided into a discrete
number of class intervals. The load representing the class
interval midpoint is assigned the probability for that class
interval. A seven-step distribution is considered reasonable in
the subdivision.
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


65

Load Forecast Uncertainty

Probability given by indicated area

0.382
0.061

0.242

0.242

0.061

0.006
-3

0.006
-2

-1

No. of standard deviations


from the mean

+1

+2

+3

Mean = forecast load (MW)

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


66

Load Forecast Uncertainty

Example:
The capacity model of a system consisting of twelve 5 MW units,
each with forced outage rate of 0.01 is shown below.

Capacity Outage
(MW)

Cumulative
Probability

1.00000000

0.11361513

10

0.00617454

15

0.00020562

20

0.00000464

25

0.00000007

(probability values less than 10-B are neglected)


University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


67

Load Forecast Uncertainty


Using a seven-step normal distribution approximation of the load
forecast with peak load of 50MW, 2% S.D., 70% load factor and
straightline load variation curve, calculate the annual LOLP of the
system in days/year.
Standard Deviation = (0.02)(50) = 1 MW

Mean = 50 MW

Number of
S. D.
(1)

Load
(MW)
(2)

Probability of
the Load (3)

LOLP (days/year)
(4)

(3) x (4)

-3

47

0.006

0.00562781

0.000033766

-2

48

0.061

0.00811645

0.000495103

-1

49

0.242

0.01050352

0.002541851

50

0.382

0.01279510

0.004887728

+1

51

0.242

0.08619473

0.020859125

+2

52

0.061

0.15677132

0.009563050

+3

53

0.006

0.22468462

0.001348107

Annual LOLP = 0.03972873 days/year


University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


68

Application in Generation System


Expansion Analysis
Alternative 2

Peak megawatt
demand

Megawatts

Alternative 1

MW0

Years

Note: MW0 = capacity of existing generating plant

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


69

Application in Generation System


Expansion Analysis

Percentage of days the daily peak load


exceeded the indicated value

Daily peak load variation curve

Load Growth at 10% p.a.


Year Number

Forecast Peak Load (MW)

1
2
3
4
5
6
7
8

160.0
176.0
193.6
213.0
234.3
257.5
283.1
311.4

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


70

Loss of Load Expectation


Consider a system containing five 40 MW units each with
a forced outage rate of 0.01.
Generation model for the
five-unit system.
Capacity out
of service
0 MW
40 MW
80 MW
120 MW

Individual
Probability
0.950991
0.048029
0.000971
0.000009
1.000000

Cumulative
Probability
1.000000
0.049009
0.000980
0.000009

Daily Peak Load (MW)

Sytem installed capacity = 200 MW

Installed Capacity = 200 MW


03 = 40MW

02 = 40MW

04 = 40 MW

160
T4 = 41.7%

120
t3 = T3 = 41.7%
80
64

University of the Philippines


Department of Electrical and Electronics Engineering

t4 = 83.4%

64

Time (%)
100
Time periods during which loss of load occurs

Prof. Rowaldo R. del Mundo


71

Loss of Load Expectation


LOLE using individual probabilities
Capacity Out
of Service (MW)
0
40
80
120

Capacity In
Service (MW)
200
160
120
80

Individual
Probability
0.950991
0.048029
0.000971
0.000009
1.000000

Total Time
tk (% )
0.0
0.0
41.7
83.4

LOLE
(% )
0.0404907
0.0007506
0.0412413

LOLE using cumulative probabilities


Capacity Out
of Service (MW)
0
40
80
120

Capacity In
Service (MW)
200
160
120
80

Cumulative
Probability
1.000000
0.049009
0.000980
0.000009

University of the Philippines


Department of Electrical and Electronics Engineering

Total Time
tk (% )
0.0
0.0
41.7
41.7

LOLE
(% )
0.040866
0.0003753
0.0412413

Prof. Rowaldo R. del Mundo


72

Loss of Load Expectation

System Peak
Load (MW)
100
120
140
160
180
200
220
240
250
260
280
300
320
340
350

LOLE (days/year)
200 MW
Capacity
0.001210
0.002005
0.086860
0.150600
3.447000
6.083000
-

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


73

Loss of Load Expectation

System Peak
Load (MW)
100
120
140
160
180
200
220
240
250
260
280
300
320
340
350

LOLE (days/year)
200 MW 250 MW
Capacity Capacity
0.001210
0.002005
0.086860 0.001301
0.150600 0.002625
3.447000 0.068650
6.083000 0.150500
2.058000
4.853000
6.083000
-

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


74

Loss of Load Expectation

LOLE (days/year)
System Peak 200 MW 250 MW 300 MW
Load (MW) Capacity Capacity Capacity
100
0.001210
120
0.002005
140
0.086860 0.001301
160
0.150600 0.002625
180
3.447000 0.068650
200
6.083000 0.150500 0.002996
220
2.058000 0.036100
240
4.853000 0.180000
250
6.083000 0.661000
260
3.566000
280
6.082000
300
320
340
350
-

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


75

Loss of Load Expectation

System
Peak
Load (MW)
100
120
140
160
180
200
220
240
250
260
280
300
320
340
350

200 MW
Capacity
0.001210
0.002005
0.086860
0.150600
3.447000
6.083000
-

LOLE (days/year)
250 MW 300 MW
Capacity Capacity
0.001301
0.002625
0.068650
0.150500 0.002996
2.058000 0.036100
4.853000 0.180000
6.083000 0.661000
3.566000
6.082000
-

350 MW
Capacity
0.002980
0.004034
0.011750
0.107500
0.290400
2.248000
4.880000
6.083000

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


76

Loss of Energy Indices


Let, Ok - Magnitude of the
capacity outage
Pk - Probability of the
capacity outage
equal to Ok
Ek - Energy curtailed by
capacity outage
equal to Ok.

Load Model: Load Duration Curve (LDC)


Individual hourly load values arranged in
decreasing orders
The area under the curve represents the energy
required in the given period
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


77

Loss of Energy Expectation

Load Models
HOUR
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24

LOAD
1452
1422
1446
1405
1440
1464
1417
1455
1547
1498
1574
1535
1501
1499
1504
1487
1504
1659
2051
1960
1830
1718
1598
1661

P.U. LOAD
0.71
0.69
0.71
0.69
0.70
0.71
0.69
0.71
0.75
0.73
0.77
0.75
0.73
0.73
0.73
0.73
0.73
0.81
1.00
0.96
0.89
0.84
0.78
0.81

Hourly Load Curve


(Luzon Grid)

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


78

Loss of Energy Expectation

Load Models
HOUR
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24

P.U. LOAD
1.00
0.96
0.89
0.84
0.81
0.81
0.78
0.77
0.75
0.75
0.73
0.73
0.73
0.73
0.73
0.73
0.71
0.71
0.71
0.71
0.70
0.69
0.69
0.69

Load Duration Curve


(Hourly Peak arrange in descending order)

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


79

Loss of Energy Indices


The probability energy curtailed by a capacity outage
equal to Ok is Ekpk.
Loss of Energy Expectation is the total energy curtailment
because of capacity outages.
n

LOEE = Ek pk
k =1

The per unit LOEE value represents the ratio between the
probable load energy curtailed due to deficiencies in
available generating capacity and the total energy
required to served the system demand.

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


80

Loss of Energy Indices


Example:
Generating Capacity Model
STATE CAP IN CAP OUT INDIVIDUAL CUMULATIVE
1
450
0
0.941094
1.000000
2
350
100
0.009506
0.058906
3
300
150
0.019206
0.049400
4
250
200
0.029106
0.030194
5
200
250
0.000194
0.001088
6
150
300
0.000294
0.000894
7
100
350
0.000594
0.000600
8
0
450
0.000006
0.000006

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


81

Loss of Energy Indices


Hourly Load
1
2
3
4
5
6
7
8
9
10
11
12

160.00
152.90
142.76
134.02
129.58
129.42
124.66
122.79
120.68
119.75
117.33
117.33

13
14
15
16
17
18
19
20
21
22
23
24

University of the Philippines


Department of Electrical and Electronics Engineering

117.09
116.94
116.86
116.00
114.21
113.51
113.27
112.80
112.34
110.93
110.54
109.61
Prof. Rowaldo R. del Mundo
82

Loss of Energy Indices


Loss of Energy Expectation (LOEE)
CAP IN = 150
HOUR
LOAD
1
160.00
2
152.90
3
142.76
4
134.02
5
129.58
6
129.42
7
124.66
8
122.79
9
120.68
10
119.75
11
117.33
12
117.33
13
117.09
14
116.94
15
116.86
16
116.00
17
114.21
18
113.51
19
113.27
20
112.80
21
112.34
22
110.93
23
110.54
24
109.61
SUBTOTAL

PROB = 0.000294
CURTAILED EXPECTATION
10.00
2.90
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
12.901024

University of the Philippines


Department of Electrical and Electronics Engineering

0.002940
0.000853
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.000000
0.003793

Prof. Rowaldo R. del Mundo


83

Loss of Energy Indices


Loss of Energy Expectation (LOEE)
CAP IN = 100
HOUR
LOAD
1
160.00
2
152.90
3
142.76
4
134.02
5
129.58
6
129.42
7
124.66
8
122.79
9
120.68
10
119.75
11
117.33
12
117.33
13
117.09
14
116.94
15
116.86
16
116.00
17
114.21
18
113.51
19
113.27
20
112.80
21
112.34
22
110.93
23
110.54
24
109.61
SUBTOTAL

PROB = 0.000594
CURTAILED EXPECTATION
60.00
52.90
42.76
34.02
29.58
29.42
24.66
22.79
20.68
19.75
17.33
17.33
17.09
16.94
16.86
16.00
14.21
13.51
13.27
12.80
12.34
10.93
10.54
9.61
535.309605

University of the Philippines


Department of Electrical and Electronics Engineering

0.035640
0.031423
0.025399
0.020209
0.017568
0.017475
0.014649
0.013537
0.012285
0.011729
0.010293
0.010293
0.010154
0.010061
0.010015
0.009505
0.008439
0.008022
0.007883
0.007605
0.007327
0.006493
0.006261
0.005705
0.317974

Prof. Rowaldo R. del Mundo


84

Loss of Energy Indices


Loss of Energy Expectation (LOEE)
CAP IN = 0
HOUR
LOAD
1
160.00
2
152.90
3
142.76
4
134.02
5
129.58
6
129.42
7
124.66
8
122.79
9
120.68
10
119.75
11
117.33
12
117.33
13
117.09
14
116.94
15
116.86
16
116.00
17
114.21
18
113.51
19
113.27
20
112.80
21
112.34
22
110.93
23
110.54
24
109.61
SUBTOTAL

PROB = 0.000006
CURTAILED EXPECTATION
160.00
152.90
142.76
134.02
129.58
129.42
124.66
122.79
120.68
119.75
117.33
117.33
117.09
116.94
116.86
116.00
114.21
113.51
113.27
112.80
112.34
110.93
110.54
109.61
2935.309605

University of the Philippines


Department of Electrical and Electronics Engineering

0.000960
0.000917
0.000857
0.000804
0.000777
0.000777
0.000748
0.000737
0.000724
0.000718
0.000704
0.000704
0.000703
0.000702
0.000701
0.000696
0.000685
0.000681
0.000680
0.000677
0.000674
0.000666
0.000663
0.000658
0.017612

Prof. Rowaldo R. del Mundo


85

Loss of Energy Indices

Loss of Energy Expectation (LOEE)


STATE CAP IN CAP OUT
PROB
1
450
0
0.941094
2
350
100
0.009506
3
300
150
0.019206
4
250
200
0.029106
5
200
250
0.000194
6
150
300
0.000294
7
100
350
0.000594
8
0
450
0.000006
LOEE (MWH)

University of the Philippines


Department of Electrical and Electronics Engineering

CURTAILED EXPECTATION
0.00
0.00000
0.00
0.00000
0.00
0.00000
0.00
0.00000
0.00
0.00000
12.90
0.00379
535.31
0.31797
2935.31
0.01761
0.33938

Prof. Rowaldo R. del Mundo


86

Loss of Energy Indices


Applications in Probabilistic Production Simulations

Consider the LDC below

Load (MW)

75.0

52.5
30.0

20

100

Duration (hours)

University of the Philippines


Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


87

Loss of Energy Indices


and the generating units capacity data
Unit No.
1

2
3

Capacity (MW)
0
15
25
0
30
0
20

Probability
0.05
0.30
0.65
0.03
0.97
0.04
0.96

Assume that the economic loading order is units 1, 2 & 3.


Total Required Energy = 4575.0 MWh (area under the curve)

If there were no units in the system, the expected energy


not supplied would be
EENS0 = 4575.0 MWh
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


88

Loss of Energy Indices


If the system contained only Unit 1, the EENS can be
calculated as follows:
Capacity Out of Capacity in
Energy Curtailed Expectation
Probability
Service (MW) Service (MW)
(MWh)
(MWh)
0
25
0.65
2075.0
1348.75
10
15
0.30
3075.0
922.50
25
0
0.05
4575.0
228.75
EENS1
2500.00

The expected energy produced by Unit 1

= EENS0 - EENS1
= 4575.0 - 2500.0
= 2075.0 MWh
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


89

Loss of Energy Indices

EENS with Units 1 and 2


Capacity Out of Capacity in
Energy Curtailed Expectation
Probability
Service (MW) Service (MW)
(MWh)
(MWh)
0
55
0.6305
177.8
112.09
10
45
0.2910
475.0
138.23
25
30
0.0485
1575.0
76.39
30
25
0.0195
2075.0
40.46
40
15
0.0090
3075.0
27.68
55
0
0.0015
4575.0
6.86
401.70
EENS 2

The expected energy produced by Unit 2

= EENS1 - EENS2
= 2500.0 - 401.7
= 2098.3 MWh
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


90

Loss of Energy Indices

EENS with Units 1, 2 and 3


Capacity Out of Capacity in
Energy Curtailed Expectation
Probability
Service (MW) Service (MW)
(MWh)
(MWh)
0
75
0.60528
0.0
0.00
10
65
0.27936
44.4
12.42
20
55
0.02522
177.8
4.48
25
50
0.04656
286.1
13.32
30
45
0.03036
475.0
14.42
40
35
0.00864
1119.4
9.67
45
30
0.00194
1575.0
3.06
50
25
0.00078
2075.0
1.62
55
20
0.00144
2575.0
3.71
60
15
0.00036
3075.0
1.11
75
0
0.00006
4575.0
0.27
EENS 3
64.08

The expected energy produced by Unit 3

= EENS2 - EENS3
= 401.7 - 64.08 = 337.6 MWh
University of the Philippines
Department of Electrical and Electronics Engineering

Prof. Rowaldo R. del Mundo


91

Vous aimerez peut-être aussi