Overview
Numerous submittals and other contract requirements must be managed and tracked for a successful
project. Managing this process requires working in front of the curve, taking a proactive approach to
securing completion of these items. The Submittal Process is an important part of the construction
schedule. Submittals that are not approved on time can jeopardize the overall schedule by delaying
material ordering and delivery.
Use this procedure to create a submittal item.
Prerequisites
You must have necessary permissions to create submittal items.
Navigation
Follow these steps to access the task:
Project Home | Engineering | Submittal Items | Create
Tips and Tricks
Grayed out submittal package information listed on the Submittal Item form cannot be
entered into this form. It will be auto populated from the Submittal Package form only when
the item is linked to a package.
Printed material may be outdated. Please check TKN for the most current version.
Published On: 5/10/2012
1/9
Printed material may be outdated. Please check TKN for the most current version.
Published On: 5/10/2012
2/9
Procedure
1.
Start the transaction using the navigation path as listed in the Overview section.
2.
R/O/C
Description
Required
Example:
00133
Type in a unique submittal item number or
click
to auto populate the next
available submittal item number for the project.
Printed material may be outdated. Please check TKN for the most current version.
Published On: 5/10/2012
3/9
Field
R/O/C
Revision
Description
Required
Example:
0
Type in zero (0) the first time the item is
entered to indicate that there have been no
revisions for the item. When revisions are created
in Submittal Packages this field will autopopulate with the next available revision number
for the item.
Description
Required
3.
4.
R/O/C
Specification Section
Description
Required
Example:
08110
Type in the applicable specification section
number from the project specifications manual for
the submittal item.
Optional
Example:
2.01
Type in the applicable specification sub
section number from the project specifications
manual for the submittal item.
Printed material may be outdated. Please check TKN for the most current version.
Published On: 5/10/2012
4/9
Field
R/O/C
Responsible Company
Description
Conditional
Supplier
Optional
Example:
Enter Supplier
Type in the name of any additional company
working with the responsible company to supply
the item, if applicable.
5.
6.
Action should be left blank. It will be auto-populated from the Submittal Packages module when
reviewed by the architect.
7.
R/O/C
Description
Required
Example:
Kim Warf
Converge will auto populate this field with
the current user's name but will be overwritten by
the user that logs the Action of the item.
Notes
Optional
8.
9.
if applicable.
10. Converge will auto populate Task Date if a scheduled activity ID is present.
Printed material may be outdated. Please check TKN for the most current version.
Published On: 5/10/2012
5/9
R/O/C
Description
Optional
Example:
0
Type in the number of calendar days
required to approve the submittal item, including
time for any revisions that may be required.
Fab
Optional
Example:
0
Type in the number of calendar days
required for fabrication.
Delivery
Optional
Example:
0
Type the number of calendar days required
for delivery of the itme.
Delivery
Optional
Example:
0
Type the number of calendar days required
for delivery of the itme.
Printed material may be outdated. Please check TKN for the most current version.
Published On: 5/10/2012
6/9
Field
R/O/C
Description
Conditional
Example:
3/1/2011
Type in the date by which the subcontractor
is to have the item to the project for review. This
field will be auto-populated if the Use Lead Time
to Get Due Date box is checked.
Optional
Example:
2/15/2011
Type in the date the responsible company
submitted the item. This information can be filled
in by Turner or the responsible company when
they submit an item for review.
Optional
Example:
Printed material may be outdated. Please check TKN for the most current version.
Published On: 5/10/2012
7/9
Field
R/O/C
Back to Sub
Description
Optional
Example:
2/15/2011
Type the date you returned the item to the
responsible company after review or Converge
will auto-populate this field with the date the item
was returned to the responsible company (after
review), based on the information entered in the
linked submittal item package.
Scheduled Delivery
Optional
Example:
3/1/2011
Type in the date the item is set to arrive on
the project.
Actual Delivery
Optional
Example:
2/28/2011
Type in the date the item arrived on the
project.
Optional
Example:
13.
Click
Printed material may be outdated. Please check TKN for the most current version.
Published On: 5/10/2012
8/9
Do not reply via the notification emails as the mail box they are sent from is not monitored, it is
used for outgoing mail only.
Troubleshooting
If you cannot resolve issues using this document, please contact the designated support person in your
Business Unit or the Help Desk.
Printed material may be outdated. Please check TKN for the most current version.
Published On: 5/10/2012
9/9