Académique Documents
Professionnel Documents
Culture Documents
Mendoza, Vincent
Morada, Roberto Carlo
TEANECK COMPANY
For strategic reasons, it is very important for Teaneck Company to submit the most competitive bid.
Winning the bid not only means that the company will get the sewer system project but it can also
edge out the other competitors in obtaining a contract amounting to P50 million later that year.
Precedence Table
Before coming up with the bid price, we have laid out the activities required in constructing the
sewer system in the precedence table below.
Table 1. Precedence Table
A
B
C
D
E
F
G
H
J
K
L
M
ACTIVITY
Move in machinery/equipment
Excavate primary shaft
Excavate secondary shafts
Excavate trenches
Excavate tunnel
Backfill (trenches only)
Pipelaying in trenches
Pipelaying in tunnel
Pour concrete in trenches
Pour concrete in tunnel
Landscape
Move out
Precedence
A
B
A
B
J
D
C,E
G
H
F
L
After the machinery/equipment has been settled at the construction site, the excavation of the
primary shaft and trenches will begin immediately. These will be followed by the excavation of the
secondary shafts and the tunnel. After all the excavation procedures, the pipes will then be laid both
in the trenches and in the tunnel. After pipelaying, concrete will be poured to fill the excavation.
Once the concrete has set, the construction team can begin backfilling the holes in the trenches to
make the foundations sturdier. Lastly, the construction should be properly leveled or landscaped
before moving out the machinery/equipment.
Page 1 of 1
supporting these calculations are shown in the Appendix Section. The project cost and bid prices
are summarized in Table 2a.
In this scenario, we have observed that the direct cost increases as the company increases its
number of shifts. However, increasing the number of shifts dramatically reduces the number of
days required to complete the project, consequently cutting down total indirect costs. As the
number of shifts increases, the reduction in indirect costs more than offsets the increase in direct
costs, thus decreasing the overall cost and making our bid price more competitive. By comparing
absolutely 1, 2 or 3 shifts, we can see that the optimal shift seems to be the last one as this has the
lowest total cost and shortest project period.
Table 2a. Bid Price Per Shift No Strike Scenario
Direct cost
Indirect cost
Total direct & indirect cost
General and administrative expense
Total cost
Mark-up
Bid price
One shift
Two shifts
6,247,500
7,020,000
3,479,000
2,016,000
9,726,500
9,036,000
3,890,600
3,614,400
13,617,100 12,650,400
1,361,710
1,265,040
14,978,810 13,915,440
Days
Cost/day
Three shifts
7,337,000
1,539,000
8,876,000
3,550,400
12,426,400
1,242,640
13,669,040
497
252
171
27,399
50,200
72,669
B. With Strike
Unfortunately, an Excavators Union strike is expected to occur on the projects inception date. This
is expected to stretch the completion date of the project by the weighted average number of days,
i.e. summation of the product of length of strike days and probability. We can expect the sewer
systems project completion date to be extended by approximately 32.5 days
Length of strike days
20
30
40
Total
Probability
.25
.25
0.5
Although the strike will not affect direct costs, the group expects the cost of the strike to be charged
with the indirect cost per day for the corresponding shift. The cost is then multiplied by the
probability of occurrence which is 80%. The bid prices for the absolute shift scenarios that
incorporate the strike are shown in Table 2b. Based on this, the most competitive bid still utilizes
three shifts.
Page 2 of 2
One shift
Two shifts
6,247,500
7,020,000
3,479,000
2,016,000
182,000
208,000
9,908,500
9,244,000
3,963,400
3,697,600
13,871,900 12,941,600
1,387,190
1,294,160
15,259,090 14,235,760
Days
Cost/day
Three shifts
7,337,000
1,539,000
234,000
9,110,000
3,644,000
12,754,400
1,275,400
14,029,400
529.5
284.5
203.5
28,818
50,038
68,941
Page 3 of 3
One shift
Two shifts
Indirect
Cost
84,000
Total
Cost
234,000
Three shifts
Indirect
Cost
48,000
Total
Cost
213,000
180,000
Indirect
Cost
36,000
Total
Cost
216,000
455,500
Move in machinery/equipment
12
Direct
Cost
150,000
12
347,500
84,000
431,500
12
347,500
96,000
443,500
12
347,500
108,000
60
312,500
420,000
732,500
24
330,000
192,000
522,000
12
347,000
108,000
455,000
ACTIVITY
Days
Days
Direct
165,000
Days
Direct
Excavate trenches
300
1,685,000
2,100,000
3,785,000
150
2,125,000
1,200,000
3,325,000
100
2,250,000
900,000
3,150,000
Excavate tunnel
305
1,807,500
2,135,000
3,942,500
155
1,955,000
1,240,000
3,195,000
105
2,000,000
945,000
2,945,000
50
50,000
350,000
400,000
25
75,000
200,000
275,000
17
100,000
153,000
253,000
Pipelaying in trenches
50
375,000
350,000
725,000
25
410,000
200,000
610,000
17
445,000
153,000
598,000
Pipelaying in tunnel
50
275,000
350,000
625,000
25
285,000
200,000
485,000
15
300,000
135,000
435,000
70
570,000
490,000
1,060,000
35
582,500
280,000
862,500
25
592,500
225,000
817,500
60
550,000
420,000
970,000
30
562,500
240,000
802,500
20
575,000
180,000
755,000
Landscape
10
100,000
70,000
170,000
145,000
64,000
209,000
150,000
54,000
204,000
Move out
25,000
35,000
60,000
37,500
24,000
61,500
50,000
18,000
68,000
Page 4 of 4
Shift
Days
Move in machinery/equipment
213,000
431,500
12
455,000
12
Excavate trenches
3,150,000
100
Excavate tunnel
2,945,000
105
253,000
17
17
Pipelaying in trenches
598,000
17
17
Pipelaying in tunnel
435,000
15
817,500
35
755,000
20
Landscape
170,000
10
10
60,000
5
190
M Move out
TOTAL
100
35
ACTIVITY
Move in machinery/equipment
Excavate primary shaft
Excavate secondary shafts
Excavate trenches
Excavate tunnel
Backfill (trenches only)
Pipelaying in trenches
Pipelaying in tunnel
Pour concrete in trenches
Pour concrete in tunnel
Landscape
Move out
Shift
2
1
3
3
3
3
3
3
2
3
1
1
Days
6
12
12
100
105
17
17
15
35
20
10
5
Direct
P 165,000
347,500
347,000
2,250,000
2,000,000
100,000
445,000
300,000
582,500
575,000
100,000
25,000
Indirect
P 48,000
P 7,237,000
P 1,639,000
900,000
153,000
153,000
280,000
70,000
35,000
No Strike
P 7,237,000
1,639,000
With Strike
P 7,237,000
1,639,000
182,000
P 8,876,000
3,550,400
P 12,426,400
1,242,640
P 13,669,040
P 9,058,500
3,623,200
P 12,681,200
1,268,120
(at P7,000/day, with 80% prob. of occurrence = P7000 x 32.5 days x 80%)
P 13,949,320
Page 5 of 5
ACTIVITY
Move in machinery/equipment
Excavate primary shaft
Excavate secondary shafts
Excavate trenches
Excavate tunnel
Backfill (trenches only)
Pipelaying in trenches
Pipelaying in tunnel
Pour concrete in trenches
Pour concrete in tunnel
Landscape
Move out
Shift
2
1
1
3
3
3
3
2
2
3
1
1
Days
6
12
60
100
105
17
17
25
35
20
10
5
Direct
165,000
347,500
312,500
2,250,000
2,000,000
100,000
445,000
285,000
582,500
575,000
100,000
25,000
Indirect
48,000
P 7,187,500
1,639,000
900,000
153,000
153,000
280,000
70,000
35,000
No Strike
P 7,187,500
1,639,000
With Strike
P 7,187,500
1,639,000
182,000
P 8,826,500
3,530,600
P 12,357,100
1,235,710
P 13,592,810
P 9,008,500
3,603,400
P 12,611,900
1,261,190
P 13,873,090
Page 6 of 6
D
300
12
12
G
50
312 362
312 362
J
70
F
50
strike
0
0
0
0
0
A
12
0
0
12
12
312
312
B
12
E
305
24
67
12
55
24
67
329
372
C
60
362 432
362 432
H
50
329 379
372 422
432 482
432 482
K
60
379 439
422 482
L
10
482 492
482 492
M
5
492 497
492 497
24
84
312 372
END
Page 7 of 7
2 shifts
START
D
150
6
6
strike
0
0
0
0
0
A
6
0
0
6
6
156
156
G
17
156 181
156 181
J
25
F
17
B
12
E
155
18
31
6
19
18
31
173
186
C
24
181 216
181 216
H
25
173 198
186 211
216 241
216 241
K
30
198 228
211 241
L
8
241 249
241 249
M
3
249 252
249 252
18
42
162 186
END
Page 8 of 8
3 shifts
START
D
100
4
4
strike
0
0
0
0
0
A
4
0
0
4
4
104
104
G
17
104 121
104 121
J
25
F
17
B
12
E
105
16
23
4
11
16
23
121
128
C
12
121 146
121 146
H
15
121 136
128 143
146 163
146 163
K
20
136 156
143 163
L
6
163 169
163 169
M
2
169 171
169 171
16
28
116 128
END
Page 9 of 9
B. Combination of shifts
The strike is expected to occur on the project inception date, pushing the start of moving in the
machinery/equipment by the expected length of strike.
START
strike
32.5
0
0
32.5
32.5
A
6
32.5
32.5
38.5
38.5
D
100
38.5
38.5
138.5
138.5
B
12
G
17
138.5 155.5
138.5 155.5
J
35
155.5 190.5
155.5 190.5
H
25
155.5 180.5
162.5 187.5
F
17
190.5 207.5
190.5 207.5
K
20
180.5 200.5
187.5 207.5
E
105
50.5
57.5
L
10
207.5 217.5
207.5 217.5
M
5
217.5 222.5
217.5 222.5
155.5
162.5
38.5
45.5
50.5
57.5
C
60
50.5 110.5
102.5 162.5
END
Page 10 of 10