Académique Documents
Professionnel Documents
Culture Documents
MINISTRY OF SUSTAINABLE
DEVELOPMENT & TOURISM
JANUARY 2013.
GENERAL
No.
BOOK 1
GENERAL BOOK
BOOK 2
BOOK 3
BOOK 4
BOOK 5
Sveska 5.1
Process-technology design
Sveska 5.2
Hydrotechnical design
Sveska 5.3
Architectural design
Sveska 5.4
Mechanical design
Sveska 5.5.1
Sveska 5.5.2
Sveska 5.5.3
Sveska 5.6
TERMS OF REFERENCE
CONTENT
1. INTRODUCTION................................................................................. ERROR! BOOKMARK NOT DEFINED.
2. DESCRIPTION OF TECHNICAL SOLUTION ..................................... ERROR! BOOKMARK NOT DEFINED.
2.1. BASE ERROR! BOOKMARK NOT DEFINED.
2.2. PRECIPITATION ......................................................................................... ERROR! BOOKMARK NOT DEFINED.
2.3. DESIGN CRITERIA AND SELECTION OF THE PIPES ........................................ ERROR! BOOKMARK NOT DEFINED.
2.4. SOLUTION DISPLAY ................................................................................... ERROR! BOOKMARK NOT DEFINED.
2.5. SOFTWARE PACKAGE FOR HYDRAULIC CALCULATIONS ............................... ERROR! BOOKMARK NOT DEFINED.
STRANA 1
1. INTRODUCTION
The field of Cetinje is a karst field surrounded by mountains so there is no possibility of
direct outflow. The town of Cetinje was built in the field, and all the problems arising from
such a position, concern Cetinje too. When there was no settlement and when the
settlement was small, the water outflowed across many of the abysses. The most
important ones today are the abysses located in Donje Polje, which are still in use for
draining of all the water: used water, storm water originating from municipal sewage and
all external water.
With the development of Cetinje there came a process that made the situation less
favorable: there have been large amounts of dirty water, which, through the sewers,
brought suspended solids into the abyss where they deposited and reduced the capacity
of the abyss.
Since this has become the largest and heaviest utility problem of Cetinje, the municipality
has recently begun to take steps in finding a solution that would eliminated these
difficulties. The first significant attempt in this direction was the project done in 1982 by
"Geoinenjering" from Sarajevo. In this project, sewage of Cetinje and the wider problem
of draining all water from Cetinje were discussed at the level of conceptual solutions. The
main feature of the solution was a proposal to build a tunnel under the Belvedere, which
would have taken water towards Dobrsko selo. Longitudinal water was set at 12 m / sec
and during estimating the project, a remark was made that the amount of water had been
underestimated. The tunnel was designed as a purely hydroelectric facility, which would
be used to evacuate flood and to implement channel for the used water. No works have
been done under this project.
In February, 1986 Cetinje was affected by the floods and destructive high water that
flowed through the city area. Sinks were not able to accommodate all the water, which
caused the formation of significant accumulation in Donje Polje, in the zone of the abyss.
This flood (and not just flood that could be identified like the accumulated water), has
inflicted great damage and literally threaten the city In February in 1986. The Cetinje was
very affected by the floods and the elements of high water that flowed through the city
area. Sinks were not able to accommodate all the water, which caused the forimiranja
significant accumulation in the Lower Field, in the zone of the abyss. This flood (and not
just flooding that would be identified with the accumulated water) has inflicted great
damage and literally threaten the city of Cetinje.
The preliminary design of flood protection of Cetinje was done by Centroprojekt,
Belgrade, in 1988, after these great floods. This project included a solution of the water
removal from all areasof Cetinjes field outside the region, ie. taking these waters from the
field into the Crnojevia River.
The approach to solving these issues in the area Cetinje is more complex, because this is
not just a question of taking rainwater that fall into this area, but also the acceptance of
surface and groundwater gravitating towards Cetinjes field, waters that cracks here
through karstic springs and then outflow underground throug other located abysses. Due
to large differences in the amounts of water at extremely high rainfall (1/100 and 1/500
years) and the bandwidth of the existing abysses, with capacity reduced by urbanization
and lack of maintenance, while some are clogged, the emergence of flooding in the lower
parts of Cetinje field was inevitable. The derived solutions for the construction of a tunnel
to drain excess water from Cetinje came up because mentioned reasons.
IOV10-17/A1 IK KONSALTING I PROJEKTOVANJE JANUARY 2013
STRANA 2
In this preliminary design that we do 14 years later, having in mind a new plan documents
of development of this region done in the meantime, significant infrastructure facilities, as
well as new development plans of the city, we will give the solutions that are upgrading
and optimization of previously approved concept design. In addition, as part of solving
drainage of sewage and storm water from the City of Cetinje within the limits of Master
Plan, the separation of the two systems will be solved, with the urban waste water to be
purified at the plant for their treatment, and only after fused with atmospheric water and
discharged into the watercourse
STRANA 3
2.1. BASIS
Three types of basis: hydrological, topographical and geotechnical were used in creation
of this conceptual design.
Hydrologic basis are formed on the basis of existing hydrological documentation and are
primarily included in the analysis to determine the amount of water for the dimensioning
the individual elements of the system
Topographic basis. In addition to the existing situation R = 1:1000 for Cetinje, there is a
general map R = 1:2000. Since the projected basic hydrotechnical system reaches far out
of Cetinje, all to Skadar Lake, it is clear that the development of the project could not
possible be based on the available map of 1:2000. Dedicated recording was made at all
locations where key facilities of the system were predicted (intakes, etc.) and also along
the route of the sector beyond the existing maps of 1:1000.
Geotechnical backgrounds are also a significant problem. We have used existing data and
the basis, which were, in particular, prepared for the development of the mentioned
project from 1982. Starting from the current situation, the most necessary geotechnical
surfaces are appropriately arranged and provided with the solution. However, it is clear
that the development of higher stages of design can not be accessed until the required
program for geotechnical investigation is implemented.
The following investment and technical documentation related to the performed storm
sewer projects as well as projects that are planned to be realized was also used. List of
projects:
-
STRANA 4
Old
town
of
Cetinje,
done
by
Main project of the roadways in Cetinje: Vojvode Boa street, Sima Matavulja street,
Pavla Rovinskog street, Sava Buria street, X Crnogorska street, done by Simm
Inenjering, Podgorica, 2007-2009
Note that for projects that were carried out, we did not have the built design and we used
data from the above mentioned documents.
2.2. PRECIPITATIONS
Analysis of extreme rainfall and the possibillity of the return period and their values are
enclosed in the hydrological feasibility study. In the analysis and sizing storm sewers,
which includes removal of surface water from areas of the city, authoritative twenty minute
rain with a return period of 5 years was taken. Given the length of the basin and the main
sewer for the intense rain duration, it will begin to outflow into recipient, so we adopted it
for dimensioning. Other precipitation flowing into Cetinjes field were included in a special
drainage solution, taken from the "Preliminary design of Cetinjes flood protection " done
by Centroprojekat Belgrade, in 1988.
Design criteria:
Diameter
D (mm)
300
400
500
600
700
800
900
1000
Imin
(%)
0.33
0.23
0.18
0.14
0.12
0.10
0.085
0.075
Imax
(%)
13
9.1
6.9
5.4
4.5
3.8
3.3
2.9
STRANA 5
STRANA 6
Pipe
length
L(m)
Pipe type
PE/HDPE
PE/HDPE
PE/HDPE
Manholes
new
existing
total
10351.17
535.77
548.41
11435.35
No.
343
390
733
In the project done in 1982, and the other (tender supporting) solutions, the issue of the
water protection of Cetinje was taken very one-sided and simplistic. The problem was set
up as the only solution was to dig a tunnel in the Belvedere, to allow runoff from Cetinje.
However, the problems are much more complex. It was presented by a situation in
February, 1986. Cetinje does not tolerate (perhaps the least) only its inland waters, ie.
runoff formed on the city's territory, but it is also vulnerable by external water, that, when
appears, runs through the city.
The largest ammount of the overflow water is concentrated in a few places, the most in
the sites of Manastirske pecine and Bogdanov kraj. A small ammount of the water
appears at the site of Grude. The best proof of these quantities comes from 1986, when it
was estimated that sprang from Manstirske pecine was about 25 m / s of water (while in
the project from 1982 calculated ammount was 12m / sec).
As for the external surface waters threatening Cetinje, the situation is as follows:
northwest of the town of Cetinje there are constricted parts of Cetinjes field, towards
Bajice, and there are applied layers on limestone base even there. Under certain
conditions, significant amounts of water can be formed at this teritory flowing from the
surface towards Cetinje.
STRANA 7
The worst situation is as follows: when the high snow covers, when the soil is frozen,
when heavy rain falls and snow intensively melts at the same time, while the ground
remains frozen. Then the coefficient of swelling is large, and the outflow form the surface
great. In addition, on the southwest of Cetinje there is a basin of Borovik, situated in
impermeable rocks, and here is Borovik stream formed with water flowing into Cetinjes
field. The water from the direction of Bojica flows directly to Cetinje, Borovik stream water
flows in the field below, but not to the town of Cetinje in the narrow sense. However, there
is a large number of residential and commercial facilities in Donje Polje now, and the
water from Borovik threatens them in its way.
In the balance of surface waters, there is also water originating from the territory of the city
where there is (or will be) a sewer.
Both Manastirska peina and Bogdanov kraj with powerful sources (during extreme
rainfall periods) are places where large amounts of water appears in the city or on its
edge, which is defined in the conceptual design of flood protection Cetinje done by
Centroprojekt, Belgrade, in 1988.
There are five active abysses in Cetinjes field now, while there were many large and
small ones (9-17) before. They were buried when the houses were built on their sites.The
possibility of accepting the runoff of surface water underground was reduced in this way.
Abyss 1 is the main abyss now accepting municipal sewage, surface water and partially
stream water from Borovik, and excess water from sinks in Vladiina Basta. It consists of
the main sink and a number of smaller sinks. Due to the inflow of substantial pieces of
pure substances, either from sewage or storm water over a long period of time, this abyss
is partially clogged and it is estimated that it can receive not more than 22.7 m / s of
water (S.Prohaska). For these reasons, this sinks possibility of receiving in the future
should be evaluated with approx. 20m / sec.
Other sinks are smaller, 10-11 m deep, 18-30 m long, and have a very limited water
receiving capacity of 3-5 m / sec. Two active abyss No. 2 and No. 3 are located in the
dolomite in the eastern edge of Donje Polje, and water from the canal Borovik embarks
into them.
Abyss 4 is located south of the Monastery of Cetinje and it is better known as the "Abyss
in Vladiina Bata. In its vicinity there is a cave Ladnica, and further north, Cetinjes cave.
This sink is partially clogged, so, in terms of acceptance of significant amounts of water, it
should not be counted at.
Abyss 5 is located in the Obod factory and it accepts discharged wastewater of the
factory.
In the previous section we provided the estimated amount of water flowing into Cetinjes
field, taken from the voluminous documentation of the Preliminary Design of flood
protection of Cetinje done by Centroprojekt, Belgrade, in 1988. In addition, as part of
this project, we updated data referring to any of the objects, constructions or infrastructure
built in Cetinje in the meantime.
According to these data, amounts of water that should be evacuated from the area of
Cetinjes field are:
IOV10-17/A1 IK KONSALTING I PROJEKTOVANJE JANUARY 2013
STRANA 8
No
Area
1.
2.
3.
4.
5.
6.
7.
Bajice
Bogdanov kraj
Manastirska peina
Vladiina Bata
Donji kraj
Borovik
Podruje GUP
Cetinje
Total
Ammount
(m/s)
10
20
30
19
30
18
2
Data source
Preliminary
Design of flood
protection of
Cetinje
Centroprojekt,
Beograd, 1988
HMZ Crne Gore
129
Note: The volumes of water that appear on the edges in the border area GMP of Cetinje
are the sum of surface and groundwater gravitating towards Cetinjes field in the
designated areas (areas 1-7) caused by high rainfall with a return period of 1:0,05, while
for the area of the city within the Master Plan Cetinje authoritative rain was taken.
Solution of storm water flowing into Cetinjes field drainage
For the area outside of GMP of Cetinje earlier decision adopted by the Audit Commission,
so-called First codified variant Abyss", was taken over, on the part of the accepting water
from the area Bajica to the sink in Vladiina Basta. Thus, given that this gap is practically
clogged, water will be drained by a collector inlet to the channel Borovik, which will be
expanded and will flow into the existing shaft, which represents the first stage of
completed tunnel "Belvedere".
Therefore, the solution of the system of drainage water, from shoe factory Kouta to
Vladiina Bata, taken from the preliminary design of Centroprojekt, Belgrade, in 1988
consists of:
The collector from circular roadway of Kouta factory to the Monastery's cave,
which accepts 10 m / s of water from Bajica and of 22 m / s of water from
Bogdanov kraj, or a total of approximately 30.0 m / sec, and it has the following
dimensions:
rectangular reinforced concrete tank, BXH = 2.50 x 2.0 m clear aperture
total length L = 1 160 m
decrease of the level I = 8,7 (0,0087)
for a given flow velocity of the water in the collector is V = 5,9 m/sec
. Data are taken from Book 1, Volume 4, of mentioned project, where detailed
hydraulic calculations was carried out and on its bases the above dimensions of the
collector adopted.
The second section of the collector is a tunnel with a solution also given in the
same book of mentioned project, the area from Bogdanov kraj, with waters of the
surrounding abyss, to Monasterys cave (Cetinjes cave). It is envisaged that,
through this collector, besides the transit 30 m / sec of upstream water, there is
about 30 m / sec of water out from the Monastery's caves caverns, and the total
flow rate Q = 60 m / sec
The dimensions of this tunnel inlet were 3.0 x 3.0 m, with a free water flow in it.
IOV10-17/A1 IK KONSALTING I PROJEKTOVANJE JANUARY 2013
STRANA 9
From Vladiina Bata, at in advance given high waters, there is an outflow of the
estimated additional 19 m / s of water, which makes the total flow rate of 79 m /
sec. Water should be drained through open trapezoidal channel to the existing
channel of Borovik. This route and this solution is the substitution of the last
section derived from three main reasons:
1. Large abyss cannot hold all of these atmospheric waters, so they must be
transferred via the sink overflow to a special collector at current entrance
portal of the tunnel "Belvedere" (existing constructed shafts along the route of
the projected tunnel "Belvedere").
2. Since the detailed urban designs for Donje Polje havent been completed yet,
and that there is urbanization of the neighborhood planned, the construction of
the tunnel inlet through this area would be very expensive and it could not be
possible to define the urban requirements as previous documentation (DUP's )
is not done.
3. With redirecting the water from the canal Borovik into the tunnel "Belvedere",
the most effective solution is to transport storm waters collected from the
hinterland of Cetinje and brought to Vladiina Bata into the canal Borovik and
deliver them to the entrance to the tunnel.
Given the level of development of planning documents for Donje Polje , the approximate
channel route Vladiina Bata - connection to Borovik channel will be proposed with the
required dimensions for the given amount of water transport and estimates of investment
costs the same. Also, we will calculate and dimension the part of the canal Borovik which
now must accept these additional amounts of water, which require significant additional
capacity or reconstruction.
2.4.2.3. SOLUTION FOR THE ATMOSPHERIC WATER DRAINAGE FLOWING INTO CETINJE FIELD
All waters falling within the urban part of Cetinje and the part which is, according to
the Master Plan, going to be urbanized, will be collected and taken to the city area
over part of the existing system and the extension of the storm water drainage.
Drainage water flowing from the surrounding watersheds, or water that can occur at
high rainfall out of many cracks and sinks, ie. the area outside the master plan or in
the border area has been soluted as in earlier solutions maintained in the
Preliminary design of flood protection of Cetinje. This project was developed by
company Centroprojekt - Belgrade, in 1988.
According to the decision given in the project the system accepts the following
amounts of water (with a probability of occurrence of 0,002 or phenomena 1:500
year) as was estimated occurrence of heavy rainfall in 1984. Evaluation of high
water flows was as follows:
From the area Bajica
10 m/sec
20 m/sec
30 m/sec
STRANA 10
Ukupno:
From south edge
Chanel Borovik inflow
79 m/sec
30 m/sec
18 m/sec
_____________________
Total:
127 m/sec
This is the total amount of storm water to be carried out from Cetinje. About 2.0 m /
sec should be added to this amount that will be collected by surface drainage from
the area of Cetinje, so the total amount of water would be about 130 m / sec.
Through the existing large abyss approximately 22.0 m / s of water can be
evacuated, and all other amounts should be taken through the existing shaft, or the
future tunnel Belvedere in the direction of Dobrskos field and futher to The
Crnojevia River.
According to the decision given in the Preliminary Design (Centroprojekt, Belgrade,
1988) the input structure would be in the region Bogdanov kraj where waters
collected from the collector accepting waters from the direction of the area and the
area of Bajice. From here, water will be transported to Cetinjes cave by a tunnel of
horseshoe cross-section 2.5 x 2.5 m, L = 720 m long. Throughput of this collector is
R = 30 m / sec, at a flow rate V = 6.77 m / sec.
2.4.2.4. SUB-SECTION FOR TAKING STORM WATER FROM BELVEDERE TUNNEL TO THE RIJEKA
CRNOJEVICA
Due to the rapid terrain decrease after leaving the tunnel Belvedere into Dobrsko
field, before releasing of water through this field, in order to calm the water and take
it into an open channel that runs through this field, it was decided to build the facility
- dam on the location of the quarry. With this solution, the water would be accepted
in front of the dam and its power calmed, and then though overflow (type Kruger
profile) taken to the projected channel. This solution is given in the Preliminary
design of flood protection Cetinje - Centroprojekt, in 1988, book 1, volume 4 Constructive building solution with bill of works. This solution was accepted as part
of a unique decision of taking extreme flood from the area of Cetinjes field.
The route of the sewer from Belvedere to Dobrsko field, water will flow away freely
and there is no need for additional work. Through Dobrsko field a channel is
designed for controlled water flow. The route of the collector is placed closer to the
hill, in areas that are less processed. Here the canal fall is caused by the natural
decline of the terrain. So adopted falls from 6.4 to 7.33 , except for two brief
sections that have 2.2% and 4.3% declines. A trapezoidal channel is designed b =
7.0 m wide with the parties in the fall 1:1,50 representing minor trough for flow rates
up to 30 m / sec and the fall i = 6,4 . The water level in the canal is about 1.5 m
and a height of side - channel depth is l = 2.0 m. For maximum flow rates of over
100 m / sec in a solution with expanded channel, ie. Beside the minor riverbed is
the same on both sides of the extended depth of 1.50 m from the 5.0 we increased
1:1,15 embankment height of 1.5 m. This solution of extended cross section of
channel ensures the flow of 138,95 m / s water.
It is anticipated that the treated water from the WWTP located near Dobrsko polje
engage in drainage channel at 321.50 elevation. Detail of discharge solution is
given on a separate drawing.
IOV10-17/A1 IK KONSALTING I PROJEKTOVANJE JANUARY 2013
STRANA 11
Further water discharge into the Crnojevia River is given the mentioned project of
Centoprojekt - Belgrade, in 1988, and will not be repeated here
STRANA 12
Terrain
Bottom
Terrain
Bottom
elevation of elevation of
elevation of
Pipe
elevation of Pipe
Upstream
the
the pipe of Downstream
the
Pipe length
the pipe of descent
diameter
manhole upstream upstream
manhole downstream
(m)
downstream
(%)
(mm)
manhole manhole
manhole
manhole
(m)
(m)
(m
P-401
P-402
P-403
P-404
P-405
P-406
P-407
P-408
P-409
P-410
P-411
P-412
P-413
P-414
P-415
P-416
P-417
P-418
MH-406
MH-407
MH-408
MH-409
MH-410
MH-411
MH-412
MH-413
MH-414
MH-415
MH-416
MH-417
MH-418
MH-419
MH-420
MH-421
MH-422
MH-423
701.60
701.00
700.65
700.45
700.30
700.00
699.85
699.45
698.96
698.71
698.51
697.97
697.70
696.90
696.00
695.35
695.00
694.00
700.00
699.48
699.15
698.78
698.60
698.08
697.77
697.25
696.73
696.21
695.69
695.17
694.65
694.13
693.61
692.85
692.05
691.37
MH-407
MH-408
MH-409
MH-410
MH-411
MH-412
MH-413
MH-414
MH-415
MH-416
MH-417
MH-418
MH-419
MH-420
MH-421
MH-422
MH-423
MH-387
701.00
700.65
700.45
700.30
700.00
699.85
699.45
698.96
698.71
698.51
697.97
697.70
696.90
696.00
695.35
695.00
694.00
692.70
699.48
699.15
698.78
698.60
698.08
697.77
697.25
696.73
696.21
695.69
695.17
694.65
694.13
693.61
692.85
692.05
691.37
689.80
1.30
1.30
1.32
1.25
1.30
1.31
1.30
1.30
1.30
1.30
1.30
1.30
1.30
1.30
1.99
2.00
2.02
1.98
40.00
25.46
28.03
14.38
40.00
23.72
40.00
40.00
40.00
40.00
40.00
40.00
40.00
40.00
38.17
40.00
33.67
39.37
STRANA 13
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
Total flow
(l/s)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Average Average
d/D (pipe
speed pipe cover
fillings) (%)
(m/s)
(m)
0.31
0.41
0.47
0.52
0.56
0.59
0.62
0.65
0.67
0.70
0.72
0.74
0.76
0.77
0.79
0.80
0.82
1.13
1.26
1.21
1.28
1.38
1.51
1.70
1.84
1.91
2.06
2.36
2.51
2.62
2.61
2.28
2.14
2.42
2.49
2.07
9.20
12.00
14.30
16.30
18.10
19.70
21.20
22.60
23.90
25.10
26.30
27.50
28.60
29.70
30.70
31.70
32.70
28.10
Designed
capacity
(l/s)
124.608
124.424
125.564
122.273
124.608
124.939
124.608
115.023
124.608
124.608
124.608
124.608
124.608
124.608
154.213
154.558
155.313
153.83
Pipe fillings
Pipe fillings
at the
at the exit
entrance
(m)
(m)
0.020
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.090
0.090
0.100
0.100
0.100
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.090
0.090
0.100
0.100
0.100
0.070
PROFILE 2
Pipe
label
P-363
P-364
P-365
P-366
P-367
P-368
P-369
P-370
P-371
P-372
P-373
P-374
P-375
P-376
P-377
P-378
P-379
P-380
P-381
P-382
P-383
P-384
P-385
P-386
P-387
Terrain
Bottom
Bottom
Terrain
elevation of elevation of
elevation of elevation of
Pipe
Downstrea
Pipe
the
the pipe of Downstream
the
the pipe of
Pipe length
m
descent
diameter
upstream upstream
manhole downstream downstream
(m)
(%)
(mm)
manhole
manhole manhole
manhole
manhole
(m)
(m))
(m)
(m))
MH-368
MH-369
MH-370
MH-371
MH-372
MH-373
MH-374
MH-375
MH-376
MH-377
MH-378
MH-379
MH-380
MH-381
MH-382
MH-383
MH-384
MH-385
MH-386
MH-387
MH-388
MH-389
MH-390
MH-391
MH-392
717.05
716.20
714.90
714.50
713.80
713.00
712.20
710.35
708.40
707.00
705.75
704.80
702.60
700.72
698.81
697.40
696.19
694.83
693.78
692.70
692.00
690.41
689.32
687.90
687.25
715.00
714.20
713.40
712.70
712.27
711.07
709.87
707.40
705.00
703.80
702.60
701.66
699.50
697.00
695.80
694.60
693.40
692.20
691.00
689.80
688.60
687.52
686.32
685.12
683.92
MH-369
MH-370
MH-371
MH-372
MH-373
MH-374
MH-375
MH-376
MH-377
MH-378
MH-379
MH-380
MH-381
MH-382
MH-383
MH-384
MH-385
MH-386
MH-387
MH-388
MH-389
MH-390
MH-391
MH-392
MH-393
716.20
714.90
714.50
713.80
713.00
712.20
710.35
708.40
707.00
705.75
704.80
702.60
700.72
698.81
697.40
696.19
694.83
693.78
692.70
692.00
690.41
689.32
687.90
687.25
685.80
714.20
713.40
712.70
712.27
711.07
709.87
707.40
705.00
703.80
702.60
701.66
699.50
697.00
695.80
694.60
693.40
692.20
691.00
689.80
688.60
687.52
686.32
685.12
683.92
682.72
2.00
2.00
2.00
2.97
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
40.00
40.00
34.96
14.48
40.00
40.00
40.00
40.00
40.00
40.00
31.33
40.00
40.00
40.00
40.00
40.00
40.00
40.00
40.00
40.00
36.03
40.00
40.00
40.00
40.00
STRANA 14
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
400 mm
400 mm
400 mm
400 mm
400 mm
400 mm
Total flow
(l/s)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
38
39
40
41
42
43
Average Average
d/D (pipe
speed pipe cover
fillings) (%)
(m/s)
(m)
0.31
0.41
0.47
0.52
0.56
0.59
0.94
0.98
0.67
0.70
0.72
1.10
1.13
0.77
0.79
0.80
0.82
0.83
0.72
1.00
1.01
1.02
1.02
1.03
1.04
1.72
1.45
1.35
1.36
1.43
1.83
1.70
2.27
3.00
2.87
2.84
2.34
2.46
3.06
2.60
2.49
2.41
2.40
2.54
2.78
2.77
2.57
2.52
2.68
2.83
9.20
12.00
14.30
16.30
18.10
19.70
16.80
18.00
23.90
25.10
26.30
22.00
22.90
29.70
30.70
31.70
32.70
33.70
40.10
37.60
38.10
38.60
39.10
39.60
40.10
154.558
154.558
154.646
188.333
189.294
189.294
189.294
189.294
189.294
189.294
189.304
189.294
189.294
189.294
189.294
189.294
189.294
189.294
189.294
328.988
328.851
328.988
328.988
328.988
328.988
0.020
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.090
0.090
0.100
0.100
0.100
0.100
0.140
0.140
0.140
0.150
0.150
0.150
0.030
0.040
0.050
0.050
0.060
0.060
0.040
0.040
0.070
0.080
0.080
0.050
0.050
0.090
0.100
0.100
0.100
0.100
0.140
0.140
0.140
0.150
0.150
0.150
0.150
P-388
P-389
P-390
P-391
P-392
P-393
P-394
P-395
P-396
P-397
P-398
P-399
P-400
MH-393
MH-394
MH-395
MH-396
MH-397
MH-398
MH-399
MH-400
MH-401
MH-402
MH-403
MH-404
MH-405
685.80
683.83
683.26
682.40
680.71
679.45
678.40
677.10
676.31
675.34
674.43
673.40
672.60
682.72
681.52
680.32
679.12
677.92
676.72
675.52
674.32
673.12
671.92
670.72
669.52
668.35
MH-394
MH-395
MH-396
MH-397
MH-398
MH-399
MH-400
MH-401
MH-402
MH-403
MH-404
MH-405
MH-322
683.83
683.26
682.40
680.71
679.45
678.40
677.10
676.31
675.34
674.43
673.40
672.60
671.91
681.52
680.32
679.12
677.92
676.72
675.52
674.32
673.12
671.92
670.72
669.52
668.35
667.54
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
2.99
3.01
40.00
40.00
40.00
40.00
40.00
40.00
40.00
40.00
40.00
40.00
40.00
39.09
26.95
400 mm
400 mm
400 mm
400 mm
500 mm
500 mm
500 mm
500 mm
500 mm
500 mm
500 mm
500 mm
500 mm
44
45
46
47
48
49
50
51
52
53
54
55
56
1.05
1.05
1.06
1.59
1.00
1.01
1.02
1.02
1.03
1.03
1.04
1.05
1.61
2.32
2.25
2.74
2.66
2.26
2.30
2.33
2.48
2.80
3.06
3.29
3.56
3.81
40.60
41.00
41.50
33.60
29.20
29.50
29.80
30.10
30.40
30.70
31.00
31.30
25.20
328.988
328.988
328.988
328.988
708.516
708.516
708.516
708.516
708.516
708.516
708.516
707.699
709.173
0.150
0.150
0.150
0.160
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.160
0.160
0.150
0.150
0.160
0.100
0.150
0.150
0.150
0.150
0.150
0.150
0.160
0.160
0.090
PROFILE 3
Pipe
label
P-708
P-709
P-710
P-711
P-712
P-713
P-714
P-715
P-716
P-717
P-718
Terrain
Terrain
Bottom
Terrain
elevation of
elevation of elevation of
elevation of
the
Pipe
the
the pipe of Downstream
the
Upstream
Pipe
descent
downstream
manhole
downstream
manhole upstream upstream
length(m)
(%)
manhole
manhole manhole
manhole
(m))
(m))
(m))
(m))
Pipe
Average Average
d/D Pipe
Total flow
diameteri
spped pipe cover
filling) (%)
(l/s)
(mm)
(m/s)
(m)
MH-715
MH-716
MH-717
MH-718
MH-719
MH-720
MH-721
MH-722
MH-723
MH-724
MH-725
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
400 mm
400 mm
154.558
154.558
154.558
154.558
155.063
172.801
172.801
172.801
171.95
301.878
299.223
677.81
677.29
676.58
675.23
674.48
673.65
672.73
672.09
671.00
670.29
669.71
676.00
675.20
674.40
673.60
672.80
672.37
671.37
670.37
669.37
668.79
668.06
MH-716
MH-717
MH-718
MH-719
MH-720
MH-721
MH-722
MH-723
MH-724
MH-725
MH-726
677.29
676.58
675.23
674.48
673.65
672.73
672.09
671.00
670.29
669.71
668.61
675.20
674.40
673.60
672.80
672.37
671.37
670.37
669.37
668.79
668.06
667.11
2.00
2.00
2.00
2.00
2.01
2.50
2.50
2.50
2.48
2.53
2.48
40.00
40.00
40.00
40.00
21.36
40.00
40.00
40.00
23.43
28.90
38.28
STRANA 15
1
2
3
4
5
6
7
8
9
10
11
0.31
0.41
0.47
0.52
0.56
0.59
0.62
0.65
0.97
0.67
0.69
1.65
1.83
1.60
1.35
1.18
1.02
1.24
1.37
1.26
1.20
1.20
9.20
12.00
14.30
16.30
18.10
19.70
21.20
22.60
19.40
19.30
20.20
0.020
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.070
0.070
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.050
0.070
0.080
P-719
P-720
P-707
MH-726
MH-727
MH-714
668.61
667.90
667.51
667.11
665.19
664.97
MH-727
MH-714
MH-703
667.90
667.51
667.16
665.19
664.97
664.73
2.49
0.99
1.01
26.49
22.19
23.85
400 mm
400 mm
400 mm
12
13
14
1.03
0.73
0.74
Total flow
(l/s)
Average
speed
(m/s)
1
2
3
4
9
10
0.31
0.41
0.47
0.81
0.67
0.94
1.10
2.25
2.11
17.20
21.90
22.70
299.813
189.126
190.537
0.080
0.080
0.080
0.050
0.080
0.090
PROFILE 4
Pipe
label
P-526
P-527
P-528
P-529
P-539
P-540
Bottom
Terrain
Terrain
elevation of elevation of
elevation of
Kota terena
Pipe
Pipe
Upstream
the
the pipe of Downstream
the
Pipe length
nizvodnog
diameter
descent
manhole upstream upstream
manhole
downstream
(m)
ahta (m)
(mm)
(%)
manhole manhole
manhole
(m))
(m))
(m))
MH-527
MH-528
MH-529
MH-530
MH-531
MH-543
668.32
667.90
667.00
666.05
665.17
664.50
667.00
666.50
666.00
665.00
663.67
662.95
MH-528
MH-529
MH-530
MH-531
MH-543
MH-541
667.90
667.00
666.05
665.17
664.50
663.50
666.50
666.00
665.00
663.67
662.95
662.12
1.25
1.25
2.50
3.08
1.80
1.80
40.00
40.00
40.00
26.91
40.00
37.17
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
Prosena
Pipe filling
pokrivka
Pipe fillings
d/D (pipe Designed
at entrance
cevi
fillings) (%) capacity(l/s)
at exit (m)
(m)
(m)
1.06
0.90
0.72
0.72
1.22
1.08
9.20
12.00
14.30
12.70
23.90
21.10
122.189
122.189
172.801
191.936
146.626
146.729
0.020
0.030
0.040
0.050
0.070
0.070
0.030
0.040
0.050
0.030
0.070
0.050
PROFILE 5
Pipe
label
P-530
P-531
P-532
P-533
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-532
MH-533
MH-534
MH-535
MH-533
MH-534
MH-535
MH-531
665.35
665.25
665.40
665.43
664.30
664.14
663.98
663.82
Kota dna
Kota terena
cevi
Pad cevi
nizvodnog
nizvodnog
(%)
ahta (m)
ahta (m)
665.25
665.40
665.43
665.17
664.14
663.98
663.82
663.67
0.40
0.40
0.40
0.44
Duina
cevi (m)
40.00
40.00
40.00
34.39
STRANA 16
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
1
2
3
4
Prosena
brzina
(m/s)
0.28
0.37
0.44
0.42
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.78
0.96
1.21
1.25
10.00
13.00
15.10
19.60
69.12
69.12
69.12
72.178
0.030
0.040
0.040
0.050
0.040
0.040
0.050
0.070
PROFILE 6
Pipe
label
P-534
P-535
P-536
P-537
P-538
P-541
P-542
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-537
MH-538
MH-539
MH-540
MH-541
MH-542
MH-544
MH-538
MH-539
MH-540
MH-541
MH-542
MH-544
MH-330
663.90
663.70
663.75
663.60
663.50
663.00
663.06
662.90
662.70
662.50
662.30
662.12
661.68
661.39
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
663.70
663.75
663.60
663.50
663.00
663.06
663.12
662.70
662.50
662.30
662.12
661.68
661.39
659.42
Pad cevi
(%)
Duina
cevi (m)
0.50
0.50
0.50
0.55
1.10
1.12
1.11
40.00
40.00
40.00
32.92
40.00
25.84
39.71
Pad cevi
(%)
Duina
cevi (m)
1.00
1.00
1.00
1.00
1.00
0.99
0.99
40.00
40.00
40.00
40.00
40.00
30.39
13.12
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
15
16
17
Prosena
brzina
(m/s)
0.30
0.40
0.47
0.39
0.79
0.80
0.98
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.70
0.82
0.97
1.04
1.05
1.19
1.62
9.50
12.30
14.40
22.80
30.70
31.70
29.10
77.279
77.279
77.279
80.813
114.623
115.779
115.041
0.020
0.030
0.040
0.050
0.090
0.100
0.100
0.030
0.040
0.050
0.090
0.100
0.100
0.080
PROFILE 7
Pipe
label
P-747
P-748
P-749
P-750
P-751
P-752
P-753
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-753
MH-754
MH-755
MH-756
MH-757
MH-758
MH-759
MH-754
MH-755
MH-756
MH-757
MH-758
MH-759
MH-17
659.82
659.71
659.00
658.89
658.77
658.70
658.64
658.80
658.40
658.00
657.60
657.20
656.80
656.50
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
659.71
659.00
658.89
658.77
658.70
658.64
658.57
658.40
658.00
657.60
657.20
656.80
656.50
656.23
STRANA 17
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
7
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.56
0.59
0.75
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.86
0.85
0.84
1.13
1.43
1.72
1.87
9.20
12.00
14.30
16.30
18.10
19.70
18.80
109.289
109.289
109.289
109.289
109.289
108.585
108.788
0.020
0.030
0.040
0.050
0.050
0.060
0.060
0.030
0.040
0.050
0.050
0.060
0.060
0.050
PROFILE 8
Pipe
label
P-742
P-743
P-744
P-745
P-746
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-748
MH-749
MH-750
MH-751
MH-752
MH-749
MH-750
MH-751
MH-752
MH-344
657.20
657.00
657.36
657.65
657.60
656.16
656.00
655.84
655.71
655.60
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
657.00
657.36
657.65
657.60
657.30
656.00
655.84
655.71
655.60
655.51
Pad cevi
(%)
Duina
cevi (m)
0.95
0.40
0.40
0.39
0.43
16.83
40.00
32.73
28.17
11.58
Pad cevi
(%)
Duina
cevi (m)
1.50
1.50
1.50
1.51
40.00
40.00
40.00
23.87
Pad cevi
(%)
Duina
cevi (m)
0.50
0.50
0.50
0.50
0.52
0.52
40.00
40.00
40.00
40.00
13.43
24.87
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
Prosena
brzina
(m/s)
0.30
0.37
0.43
0.48
0.58
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.72
0.96
1.43
1.67
1.57
9.70
13.00
15.30
17.10
17.50
106.56
69.12
68.877
68.293
71.813
0.020
0.040
0.040
0.050
0.050
0.040
0.040
0.050
0.050
0.050
PROFILE 9
Pipe
label
P-503
P-504
P-505
P-506
Kota
Kota dna
Upstream
terena
cevi
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-504
MH-505
MH-506
MH-507
MH-505
MH-506
MH-507
MH-333
658.20
657.83
657.86
657.78
657.20
656.60
656.00
655.40
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
657.83
657.86
657.78
657.53
656.60
656.00
655.40
654.17
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
1
2
3
4
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.69
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.81
1.24
1.82
2.13
9.20
12.00
14.30
13.60
133.851
133.851
133.851
134.215
0.020
0.030
0.040
0.050
0.030
0.040
0.050
0.040
PROFILE 10
Pipe
label
P-497
P-498
P-499
P-500
P-501
P-502
Kota
Kota dna
Upstream
terena
cevi
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-498
MH-499
MH-500
MH-501
MH-502
MH-503
MH-499
MH-500
MH-501
MH-502
MH-503
MH-333
657.20
657.42
657.37
657.60
657.61
657.76
656.20
656.00
655.80
655.60
655.40
655.33
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
657.42
657.37
657.60
657.61
657.76
657.53
656.00
655.80
655.60
655.40
655.33
654.17
STRANA 18
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
Prosena
brzina
(m/s)
0.30
0.40
0.46
0.52
0.56
0.63
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.91
1.19
1.48
1.80
2.02
2.08
9.50
12.30
14.50
16.30
18.10
18.80
77.279
77.279
77.279
77.279
78.902
79.015
0.020
0.030
0.040
0.050
0.050
0.060
0.030
0.040
0.050
0.050
0.060
0.060
PROFILE 11
Pipe
label
P-507
P-508
P-509
P-510
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-508
MH-509
MH-510
MH-511
MH-509
MH-510
MH-511
MH-335
656.15
656.12
656.10
655.92
655.10
654.70
654.30
653.97
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
656.12
656.10
655.92
655.64
654.70
654.30
653.97
652.78
Pad cevi
(%)
Duina
cevi (m)
1.00
1.00
1.01
1.03
40.00
40.00
32.77
21.45
Pad cevi
(%)
Duina
cevi (m)
0.40
0.40
0.40
0.40
0.39
40.00
40.00
40.00
40.00
25.41
Pad cevi
(%)
Duina
cevi (m)
0.50
0.49
0.52
40.00
28.42
21.24
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
1
2
3
4
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.64
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.93
1.31
1.57
1.62
9.20
12.00
14.30
14.20
109.289
109.289
109.672
110.681
0.020
0.030
0.040
0.050
0.030
0.040
0.050
0.040
PROFILE 12
Pipe
label
P-511
P-512
P-513
P-514
P-515
Kota dna
Kota
cevi
Upstream
terena
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-512
MH-513
MH-514
MH-515
MH-516
MH-513
MH-514
MH-515
MH-516
MH-335
655.40
655.60
655.78
656.10
655.87
654.40
654.24
654.08
653.92
653.76
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
655.60
655.78
656.10
655.87
655.64
654.24
654.08
653.92
653.76
652.78
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
Prosena
brzina
(m/s)
0.28
0.37
0.43
0.48
0.57
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.88
1.23
1.64
1.84
1.74
10.00
13.00
15.30
17.30
17.70
69.12
69.12
69.12
69.12
68.56
0.030
0.040
0.040
0.050
0.060
0.040
0.040
0.050
0.060
0.050
PROFILE 13
Pipe
label
P-520
P-521
P-522
Kota
Kota dna
Upstream
terena
cevi
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-521
MH-522
MH-523
MH-522
MH-523
MH-338
653.61
653.84
653.91
652.60
652.40
652.26
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
653.84
653.91
653.50
652.40
652.26
650.67
STRANA 19
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
1
2
3
Prosena
brzina
(m/s)
0.30
0.40
0.52
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.92
1.24
1.20
9.50
12.20
13.30
77.279
76.706
78.649
0.020
0.030
0.040
0.030
0.040
0.040
PROFILE 14
Pipe
label
P-516
P-517
P-518
P-519
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-517
MH-518
MH-519
MH-520
MH-518
MH-519
MH-520
MH-338
653.40
653.80
653.87
653.94
652.40
652.20
652.00
651.80
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
653.80
653.87
653.94
653.50
652.20
652.00
651.80
650.67
Pad cevi
(%)
Duina
cevi (m)
0.50
0.50
0.50
0.50
40.00
40.00
40.00
21.95
Pad cevi
(%)
Duina
cevi (m)
0.70
0.71
0.72
40.00
36.62
13.95
Pad cevi
(%)
Duina
cevi (m)
0.50
0.51
0.50
39.86
33.24
13.97
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
1
2
3
4
Prosena
brzina
(m/s)
0.30
0.40
0.46
0.56
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
1.00
1.43
1.70
1.67
9.50
12.30
14.50
15.40
77.279
77.279
77.279
77.367
0.020
0.030
0.040
0.050
0.030
0.040
0.050
0.050
PROFILE 15
Pipe
label
P-491
P-492
P-493
Kota
Kota dna
Upstream
terena
cevi
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-492
MH-493
MH-494
MH-493
MH-494
MH-351
652.60
652.60
652.70
651.58
651.30
651.04
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
652.60
652.70
652.85
651.30
651.04
650.94
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
1
2
3
Prosena
brzina
(m/s)
0.31
0.41
0.34
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.86
1.18
1.48
9.20
12.00
22.50
91.438
92.088
92.531
0.020
0.030
0.040
0.030
0.040
0.100
PROFILE 16
Pipe
label
P-523
P-524
P-525
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-524
MH-525
MH-526
MH-525
MH-526
MH-353
651.87
651.60
651.70
650.80
650.60
650.43
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
651.60
651.70
651.13
650.60
650.43
649.20
STRANA 20
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
1
2
3
Prosena
brzina
(m/s)
0.30
0.40
0.52
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.73
0.83
0.72
9.50
12.20
13.40
77.414
78.157
77.362
0.020
0.030
0.040
0.030
0.040
0.040
PROFILE 17
Pipe
label
P-494
P-495
P-496
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-495
MH-496
MH-497
MH-496
MH-497
MH-353
650.94
651.02
651.10
649.84
649.56
649.30
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
651.02
651.10
651.13
649.56
649.30
649.20
Pad cevi
(%)
Duina
cevi (m)
0.70
0.70
0.70
40.00
37.22
14.36
Pad cevi
(%)
Duina
cevi (m)
2.50
2.50
2.50
2.50
2.51
0.49
0.48
0.53
0.48
0.50
0.51
0.47
0.52
40.00
40.00
40.00
40.00
37.83
14.37
35.38
28.22
14.61
40.00
27.42
29.78
32.93
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
1
2
3
Prosena
brzina
(m/s)
0.31
0.41
0.32
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.98
1.33
1.56
9.20
12.00
24.70
91.438
91.343
91.201
0.020
0.030
0.040
0.030
0.040
0.110
PROFILE 18
Pipe
label
P-419
P-420
P-421
P-422
P-423
P-424
P-425
P-426
P-427
P-428
P-429
P-430
P-431
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-424
MH-425
MH-426
MH-427
MH-428
MH-429
MH-430
MH-431
MH-432
MH-433
MH-434
MH-435
MH-436
MH-425
MH-426
MH-427
MH-428
MH-429
MH-430
MH-431
MH-432
MH-433
MH-434
MH-435
MH-436
MH-1
672.30
672.45
670.60
669.43
669.00
667.30
667.00
668.00
667.80
667.55
667.00
666.72
666.25
670.00
669.00
668.00
667.00
666.00
665.05
664.98
664.81
664.66
664.59
664.39
664.25
664.11
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
672.45
670.60
669.43
669.00
667.30
667.00
668.00
667.80
667.55
667.00
666.72
666.25
666.15
669.00
668.00
667.00
666.00
665.05
664.98
664.81
664.66
664.59
664.39
664.25
664.11
663.49
STRANA 21
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
7
8
9
10
11
12
13
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.56
0.59
0.62
0.65
0.67
0.70
0.71
0.73
0.79
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
2.57
2.72
2.21
2.41
2.32
1.83
2.30
2.86
2.75
2.48
2.24
2.00
1.87
9.20
12.00
14.30
16.30
18.10
19.70
21.20
22.60
23.90
25.10
26.40
27.60
27.80
172.801
172.801
172.801
172.801
173.188
76.277
75.757
79.679
75.648
77.279
78.092
74.934
78.524
0.020
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.080
PROFILE 19
Pipe
label
P-432
P-433
P-434
P-435
P-436
P-437
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-437
MH-438
MH-439
MH-440
MH-441
MH-442
MH-438
MH-439
MH-440
MH-441
MH-442
MH-3
667.30
665.90
665.35
665.67
665.05
665.20
664.00
663.80
663.60
663.40
663.20
663.00
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
665.90
665.35
665.67
665.05
665.20
665.29
663.80
663.60
663.40
663.20
663.00
662.63
Pad cevi
(%)
Duina
cevi (m)
0.50
0.50
0.50
0.50
0.50
0.51
40.00
40.00
40.00
40.00
40.00
23.69
Pad cevi
(%)
Duina
cevi (m)
1.80
1.80
1.30
1.29
1.30
35.50
40.00
40.00
29.39
13.08
Pad cevi
(%)
Duina
cevi (m)
0.40
0.40
0.39
40.00
40.00
12.77
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
Prosena
brzina
(m/s)
0.30
0.40
0.46
0.52
0.56
0.63
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
2.40
1.62
1.71
1.76
1.72
2.00
9.50
12.30
14.50
16.40
18.10
18.80
77.279
77.279
77.279
77.279
77.279
77.783
0.020
0.030
0.040
0.050
0.050
0.060
0.030
0.040
0.050
0.050
0.060
0.060
PROFILE 20
Pipe
label
P-438
P-439
P-440
P-441
P-442
Kota
Kota dna
Upstream
terena
cevi
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-443
MH-444
MH-445
MH-446
MH-447
MH-444
MH-445
MH-446
MH-447
MH-7
665.50
664.80
663.80
663.75
663.67
663.50
662.86
662.14
661.62
661.24
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
664.80
663.80
663.75
663.67
663.57
662.86
662.14
661.62
661.24
661.00
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.71
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
1.67
1.50
1.59
1.98
2.16
9.20
12.00
14.30
16.30
15.40
146.741
146.626
124.608
124.27
124.594
0.020
0.030
0.040
0.050
0.050
0.030
0.040
0.050
0.050
0.040
PROFILE 21
Pipe
label
P-443
P-444
P-445
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-448
MH-449
MH-450
MH-449
MH-450
MH-10
661.10
661.60
661.85
660.00
659.84
659.68
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
661.60
661.85
661.99
659.84
659.68
659.42
STRANA 22
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
1
2
3
Prosena
brzina
(m/s)
0.28
0.37
0.50
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
1.13
1.66
1.96
10.00
13.00
13.80
69.12
69.12
68.386
0.030
0.040
0.040
0.040
0.040
0.040
PROFILE 22
Pipe
label
P-446
P-447
P-448
P-449
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-451
MH-452
MH-453
MH-454
MH-452
MH-453
MH-454
MH-17
657.80
658.00
658.00
658.31
656.80
656.65
656.50
656.35
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
658.00
658.00
658.31
658.57
656.65
656.50
656.35
656.23
Pad cevi
(%)
Duina
cevi (m)
0.37
0.37
0.37
0.30
40.00
40.00
40.00
40.00
Pad cevi
(%)
Duina
cevi (m)
1.00
1.00
1.00
0.99
1.06
40.00
40.00
40.00
19.21
10.35
Pad cevi
(%)
Duina
cevi (m)
2.00
1.99
40.00
31.14
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
1
2
3
4
Prosena
brzina
(m/s)
0.27
0.36
0.41
0.29
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.87
1.12
1.43
1.85
10.20
13.10
16.00
32.70
66.925
66.925
66.925
59.86
0.030
0.040
0.040
0.050
0.040
0.040
0.050
0.150
PROFILE 23
Pipe
label
P-450
P-451
P-452
P-453
P-454
Kota dna
Kota
cevi
Upstream
terena
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-455
MH-456
MH-457
MH-458
MH-459
MH-456
MH-457
MH-458
MH-459
MH-19
658.85
658.40
658.00
657.70
657.51
657.70
657.30
656.90
656.50
656.31
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
658.40
658.00
657.70
657.51
657.65
657.30
656.90
656.50
656.31
655.39
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.69
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.82
0.80
0.85
0.90
1.02
9.20
12.00
14.30
16.30
15.80
109.289
109.289
109.289
108.69
112.668
0.020
0.030
0.040
0.050
0.050
0.030
0.040
0.050
0.050
0.040
PROFILE 24
Pipe
label
P-455
P-456
Kota
Kota dna
Upstream
terena
cevi
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-460
MH-461
MH-461
MH-22
656.80
656.00
655.80
655.00
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
656.00
656.13
655.00
654.10
STRANA 23
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
1
2
Prosena
brzina
(m/s)
0.31
0.60
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.70
1.07
9.20
9.40
154.558
154.21
0.020
0.030
0.030
0.020
PROFILE 25
Pipe
label
P-543
P-544
P-545
P-546
P-547
P-548
P-549
P-550
P-551
P-552
P-553
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-545
MH-546
MH-547
MH-548
MH-549
MH-550
MH-551
MH-552
MH-553
MH-554
MH-555
MH-546
MH-547
MH-548
MH-549
MH-550
MH-551
MH-552
MH-553
MH-554
MH-555
MH-26
662.54
660.81
660.00
660.10
660.00
658.50
656.20
656.10
655.89
655.80
655.58
659.80
659.00
658.45
657.98
657.60
655.80
654.27
654.03
653.77
653.45
652.82
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
660.81
660.00
660.10
660.00
658.50
656.20
656.10
655.89
655.80
655.58
654.18
659.00
658.45
657.98
657.60
655.80
654.27
654.03
653.77
653.45
652.82
652.44
Pad cevi
(%)
Duina
cevi (m)
2.00
2.00
1.99
2.05
2.03
2.02
1.99
2.05
2.02
1.99
2.02
40.00
27.46
23.57
18.56
15.29
29.75
12.06
12.71
15.81
31.60
18.78
Pad cevi
(%)
Duina
cevi (m)
0.39
0.39
0.42
28.03
35.60
11.85
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
7
8
9
10
11
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.79
0.83
0.62
0.65
0.67
0.70
0.49
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
1.97
1.38
1.53
1.96
1.50
1.55
1.70
1.79
1.93
2.25
1.95
9.20
12.00
14.30
16.30
14.80
16.20
21.20
22.60
23.90
25.10
42.60
154.558
154.67
154.328
156.379
155.615
155.206
154.173
156.311
155.484
154.313
155.46
0.020
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.030
0.040
0.050
0.050
0.040
0.040
0.070
0.070
0.070
0.080
0.180
PROFILE 26
Pipe
label
P-461
P-462
P-463
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-466
MH-467
MH-468
MH-467
MH-468
MH-31
651.80
651.64
651.90
650.75
650.64
650.50
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
651.64
651.90
652.02
650.64
650.50
650.45
STRANA 24
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
1
2
3
Prosena
brzina
(m/s)
0.27
0.24
0.08
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.72
0.90
1.18
10.10
28.90
54.20
68.464
68.535
70.991
0.030
0.040
0.140
0.040
0.140
0.190
PROFILE 27
Pipe
label
P-457
P-460
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-462
MH-463
MH-463
MH-33
651.00
651.10
649.80
649.64
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
651.10
651.34
649.64
649.59
Pad cevi
(%)
Duina
cevi (m)
0.40
0.40
40.00
12.51
Pad cevi
(%)
Duina
cevi (m)
0.35
0.40
0.42
40.00
40.00
21.49
Pad cevi
(%)
Duina
cevi (m)
0.71
0.70
0.65
0.66
0.64
0.64
0.66
29.41
40.00
39.95
27.32
39.03
33.01
10.53
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
1
2
Prosena
brzina
(m/s)
0.19
0.05
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
1.03
1.30
27.90
55.60
69.12
69.093
0.030
0.140
0.140
0.190
PROFILE 28
Pipe
label
P-465
P-459
P-458
Kota
Kota dna
Upstream
terena
cevi
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-469
MH-464
MH-465
MH-464
MH-465
MH-35
650.12
650.25
650.40
649.12
648.98
648.82
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
650.25
650.40
650.76
648.98
648.82
648.73
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
1
2
3
Prosena
brzina
(m/s)
0.27
0.25
0.09
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.83
1.12
1.50
10.20
23.90
50.70
64.656
69.12
70.726
0.030
0.040
0.110
0.040
0.110
0.200
PROFILE 29
Pipe
label
P-466
P-467
P-468
P-469
P-470
P-471
P-472
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-470
MH-471
MH-472
MH-473
MH-474
MH-475
MH-476
MH-471
MH-472
MH-473
MH-474
MH-475
MH-476
MH-40
650.60
649.70
649.25
648.90
648.80
649.20
649.28
648.71
648.50
648.22
647.96
647.78
647.53
647.32
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
649.70
649.25
648.90
648.80
649.20
649.28
649.25
648.50
648.22
647.96
647.78
647.53
647.32
647.22
STRANA 25
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
7
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.56
0.37
0.11
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
1.24
0.81
0.68
0.68
1.04
1.51
1.68
9.20
12.00
14.30
16.30
18.10
45.40
83.40
92.35
91.438
88.167
88.71
87.467
87.169
89.107
0.020
0.030
0.040
0.050
0.050
0.060
0.220
0.030
0.040
0.050
0.050
0.060
0.220
0.290
PROFILE 30
Pipe
label
P-476
P-477
P-478
P-479
P-480
P-481
P-482
P-483
P-484
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-134
MH-478
MH-479
MH-480
MH-481
MH-482
MH-483
MH-484
MH-485
MH-478
MH-479
MH-480
MH-481
MH-482
MH-483
MH-484
MH-485
MH-42
650.27
649.93
649.65
649.30
648.95
649.10
649.19
649.30
649.40
649.00
648.80
648.40
648.22
648.05
647.63
647.33
647.20
647.05
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
649.93
649.65
649.30
648.95
649.10
649.19
649.30
649.40
648.81
648.80
648.40
648.22
648.05
647.63
647.33
647.20
647.05
646.92
Pad cevi
(%)
Duina
cevi (m)
0.95
1.00
1.04
1.34
1.05
0.99
0.98
1.03
0.97
20.99
40.00
17.29
12.73
39.88
30.27
13.27
14.55
13.39
Pad cevi
(%)
Duina
cevi (m)
1.60
1.20
1.20
1.20
1.24
1.25
50.00
50.00
50.00
50.00
36.22
10.42
Prenik
Ukupni
cevi (mm) protok (l/s)
500 mm
500 mm
500 mm
500 mm
500 mm
500 mm
500 mm
500 mm
500 mm
12
13
14
15
16
17
18
19
20
Prosena
brzina
(m/s)
0.68
0.69
0.71
0.72
0.73
0.75
0.76
0.51
0.19
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.70
0.69
0.66
0.49
0.68
1.16
1.48
1.72
1.62
14.60
15.20
15.80
16.30
16.80
17.40
17.80
31.00
57.00
399.298
409.062
417.376
472.715
419.794
407.233
404.879
415.339
403.06
0.070
0.070
0.080
0.080
0.080
0.090
0.090
0.090
0.220
0.070
0.080
0.080
0.080
0.090
0.090
0.090
0.220
0.350
PROFILE 31
Pipe
label
P-485
P-486
P-487
P-488
P-489
P-490
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-486
MH-487
MH-488
MH-489
MH-490
MH-491
MH-487
MH-488
MH-489
MH-490
MH-491
MH-52
650.00
649.20
648.60
648.22
647.70
647.51
649.00
648.20
647.60
647.00
646.40
645.95
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
649.20
648.60
648.22
647.70
647.51
647.42
648.20
647.60
647.00
646.40
645.95
645.52
STRANA 26
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.45
0.23
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.70
0.70
0.81
0.96
1.13
1.28
9.20
12.00
14.30
16.30
22.60
49.80
138.241
119.72
119.72
119.72
121.817
122.071
0.020
0.030
0.040
0.050
0.050
0.090
0.030
0.040
0.050
0.050
0.090
0.220
PROFILE 32
Pipe
label
P-687
P-688
P-689
P-690
P-691
P-692
P-693
P-694
P-695
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-694
MH-695
MH-696
MH-697
MH-698
MH-699
MH-700
MH-701
MH-702
MH-695
MH-696
MH-697
MH-698
MH-699
MH-700
MH-701
MH-702
MH-316
642.26
641.10
640.95
639.73
639.30
638.93
638.66
638.45
638.04
640.50
639.90
639.30
638.70
638.11
637.83
637.55
637.23
636.83
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
641.10
640.95
639.73
639.30
638.93
638.66
638.45
638.04
637.10
639.90
639.30
638.70
638.11
637.83
637.55
637.23
636.83
635.03
Pad cevi
(%)
Duina
cevi (m)
1.50
1.50
1.50
1.51
1.54
1.49
1.52
1.51
1.52
40.00
40.00
40.00
39.15
18.20
18.82
21.00
26.49
28.36
Pad cevi
(%)
Duina
cevi (m)
2.02
1.97
2.12
1.99
0.60
0.60
0.58
0.61
0.61
0.60
0.59
0.63
23.79
26.35
40.00
20.11
40.00
41.89
25.89
32.93
28.05
40.00
35.51
14.27
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
7
8
9
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.56
0.59
0.62
0.65
0.87
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
1.18
1.12
1.04
0.81
0.84
0.80
0.86
0.91
0.65
9.20
12.00
14.30
16.30
18.10
19.70
21.20
22.60
20.40
133.851
133.851
133.851
134.164
135.556
133.304
134.909
134.296
134.573
0.020
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.050
PROFILE 33
Pipe
label
P-626
P-627
P-628
P-629
P-630
P-631
P-632
P-633
P-634
P-635
P-636
P-639
Kota
Kota dna
Upstream
terena
cevi
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-633
MH-634
MH-632
MH-635
MH-636
MH-637
MH-638
MH-639
MH-640
MH-641
MH-642
MH-643
MH-634
MH-632
MH-635
MH-636
MH-637
MH-638
MH-639
MH-640
MH-641
MH-642
MH-643
MH-644
645.70
645.20
644.60
642.95
642.60
643.10
643.30
643.00
642.60
642.35
641.95
641.50
643.80
643.32
642.80
641.95
641.55
641.31
641.06
640.91
640.71
640.54
640.30
640.09
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
645.20
644.60
642.95
642.60
643.10
643.30
643.00
642.60
642.35
641.95
641.50
641.07
643.32
642.80
641.95
641.55
641.31
641.06
640.91
640.71
640.54
640.30
640.09
639.63
STRANA 27
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
5
6
7
8
9
10
11
12
13
14
Prosena
brzina
(m/s)
0.31
0.35
0.56
0.59
0.62
0.65
0.67
0.70
0.72
0.74
0.76
0.83
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
1.59
1.54
1.10
0.72
1.12
1.71
1.86
1.69
1.55
1.43
1.23
0.94
9.20
14.00
18.10
19.70
21.20
22.60
23.90
25.10
26.30
27.50
28.60
28.20
155.238
153.528
159.314
154.134
84.655
84.429
83.187
85.172
85.081
84.655
84.045
86.793
0.020
0.030
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.090
0.030
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.090
0.080
PROFILE 34
Pipe
label
P-624
P-625
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-630
MH-631
MH-631
MH-632
645.10
645.30
644.00
643.43
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
645.30
644.60
643.43
642.80
Pad cevi
(%)
Duina
cevi (m)
1.45
1.44
39.25
29.95
Pad cevi
(%)
Duina
cevi (m)
1.00
1.00
1.04
1.51
1.63
1.54
2.05
2.01
1.50
1.53
1.00
1.00
1.00
0.98
1.00
40.00
40.00
17.28
19.25
14.12
9.71
21.97
30.90
40.00
19.00
40.00
40.00
40.00
40.00
40.00
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
1
2
Prosena
brzina
(m/s)
0.31
0.56
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
1.18
1.43
9.20
9.70
131.702
130.952
0.020
0.030
0.030
0.030
PROFILE 35
Pipe
label
P-590
P-591
P-592
P-593
P-594
P-595
P-596
P-597
P-598
P-599
P-600
P-601
P-602
P-603
P-604
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-596
MH-597
MH-598
MH-599
MH-600
MH-601
MH-602
MH-603
MH-604
MH-605
MH-606
MH-607
MH-608
MH-609
MH-610
MH-597
MH-598
MH-599
MH-600
MH-601
MH-602
MH-603
MH-604
MH-605
MH-606
MH-607
MH-608
MH-609
MH-610
MH-611
650.30
649.60
649.50
649.10
648.70
648.45
647.80
646.90
646.30
646.15
646.09
646.29
645.92
645.28
644.30
648.00
647.60
647.20
647.02
646.73
646.50
646.35
645.90
645.28
644.68
644.39
643.99
643.59
643.19
642.80
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
649.60
649.50
649.10
648.70
648.45
647.80
646.90
646.30
646.15
646.09
646.29
645.92
645.28
644.30
643.65
647.60
647.20
647.02
646.73
646.50
646.35
645.90
645.28
644.68
644.39
643.99
643.59
643.19
642.80
642.40
STRANA 28
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
7
8
9
10
11
12
13
14
22
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.56
0.59
0.62
0.65
0.67
0.70
0.72
0.74
0.76
0.68
0.83
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
1.85
1.85
1.89
1.72
1.66
1.40
0.92
0.71
0.94
1.28
1.70
2.01
1.91
1.49
1.07
9.20
12.00
14.30
16.30
18.10
19.70
21.20
22.60
23.90
25.10
26.30
27.50
28.60
33.00
39.30
109.289
109.289
111.542
134.14
139.483
135.835
156.411
154.807
133.851
135.02
109.289
109.289
109.289
107.914
109.289
0.020
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.090
0.110
0.030
0.040
0.050
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.090
0.110
0.130
PROFILE 36
Pipe
label
P-605
P-606
P-607
P-608
P-609
P-610
P-611
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-612
MH-613
MH-614
MH-615
MH-616
MH-617
MH-618
MH-613
MH-614
MH-615
MH-616
MH-617
MH-618
MH-610
646.10
645.65
645.55
645.80
645.50
645.15
644.35
644.80
644.60
644.30
643.99
643.62
643.26
642.92
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
645.65
645.55
645.80
645.50
645.15
644.35
644.30
644.60
644.30
643.99
643.62
643.26
642.92
642.80
Pad cevi
(%)
Duina
cevi (m)
1.54
1.53
1.00
1.00
1.01
1.00
1.04
13.00
19.60
30.87
37.12
35.58
34.11
11.49
Pad cevi
(%)
Duina
cevi (m)
0.50
0.50
0.50
0.51
0.51
1.00
1.00
1.50
1.50
1.50
1.49
1.51
1.50
40.00
40.00
40.00
39.59
19.50
40.00
40.00
40.00
40.00
40.00
11.43
28.57
33.25
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
7
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.56
0.59
0.47
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.87
0.85
1.23
1.54
1.58
1.36
1.16
9.20
12.00
14.30
16.30
18.10
19.70
28.60
135.556
135.21
109.519
109.112
109.932
109.112
111.688
0.020
0.030
0.040
0.050
0.050
0.060
0.060
0.030
0.040
0.050
0.050
0.060
0.060
0.110
PROFILE 37
Pipe
label
P-612
P-613
P-614
P-615
P-616
P-617
P-618
P-619
P-620
P-621
P-637
P-638
P-623
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-619
MH-620
MH-621
MH-622
MH-623
MH-611
MH-624
MH-625
MH-626
MH-627
MH-628
MH-644
MH-629
MH-620
MH-621
MH-622
MH-623
MH-611
MH-624
MH-625
MH-626
MH-627
MH-628
MH-644
MH-629
MH-319
644.50
644.20
644.20
643.70
643.60
643.65
643.00
642.60
642.00
641.70
641.15
641.07
640.20
643.30
643.10
642.90
642.70
642.50
642.40
642.00
641.60
641.00
640.40
639.80
639.63
639.20
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
644.20
644.20
643.70
643.60
643.65
643.00
642.60
642.00
641.70
641.15
641.07
640.20
640.13
643.10
642.90
642.70
642.50
642.40
642.00
641.60
641.00
640.40
639.80
639.63
639.20
638.20
STRANA 29
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
28
29
30
31
32
33
48
49
Prosena
brzina
(m/s)
0.30
0.40
0.47
0.52
0.39
0.96
0.97
0.98
0.99
1.00
0.91
1.15
1.43
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.85
0.90
0.85
0.75
0.87
0.82
0.70
0.70
0.85
1.02
1.09
0.92
0.91
9.50
12.30
14.40
16.30
29.50
42.10
42.90
43.70
44.40
45.10
50.40
55.60
48.90
77.279
77.279
77.279
77.678
78.263
109.289
109.289
133.851
133.851
133.851
133.284
134.077
134.018
0.020
0.030
0.040
0.050
0.050
0.130
0.130
0.130
0.130
0.140
0.140
0.170
0.170
0.030
0.040
0.050
0.050
0.130
0.130
0.130
0.130
0.140
0.140
0.170
0.170
0.130
PROFILE 38
Pipe
label
P-575
P-576
P-577
P-578
P-579
P-580
P-581
P-582
P-583
P-584
P-585
P-586
P-587
P-754
P-653
P-654
P-647
P-648
P-649
P-650
P-651
P-652
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-581
MH-582
MH-580
MH-583
MH-584
MH-585
MH-586
MH-587
MH-588
MH-589
MH-590
MH-591
MH-592
MH-593
MH-659
MH-660
MH-652
MH-653
MH-654
MH-655
MH-656
MH-657
MH-582
MH-580
MH-583
MH-584
MH-585
MH-586
MH-587
MH-588
MH-589
MH-590
MH-591
MH-592
MH-593
MH-659
MH-660
MH-652
MH-653
MH-654
MH-655
MH-656
MH-657
O-8
650.30
649.70
649.10
648.70
647.80
647.60
647.30
646.43
645.42
644.81
644.40
644.00
643.25
642.70
642.20
641.80
641.61
641.20
640.43
640.30
640.15
640.00
649.30
648.70
647.20
646.60
646.00
645.78
645.52
644.92
644.32
643.72
643.36
642.95
642.25
641.55
640.73
640.34
639.21
639.01
638.86
638.66
638.50
638.31
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
649.70
649.10
648.70
647.80
647.60
647.30
646.43
645.42
644.81
644.40
644.00
643.25
642.70
642.20
641.80
641.61
641.20
640.43
640.30
640.15
640.00
640.00
648.70
647.20
646.60
646.00
645.78
645.52
644.92
644.32
643.72
643.36
642.95
642.25
641.55
640.73
640.34
639.21
639.01
638.86
638.66
638.50
638.31
638.21
Pad cevi
(%)
Duina
cevi (m)
1.61
1.60
1.50
1.50
1.51
1.48
1.50
1.50
1.50
1.50
1.50
1.75
1.75
1.75
1.00
1.01
0.50
0.49
0.50
0.51
0.50
0.48
37.19
37.49
40.00
40.00
14.61
17.55
40.00
40.00
40.00
24.07
27.33
40.00
40.00
32.66
39.10
33.62
40.00
30.35
40.00
31.22
38.04
20.75
STRANA 30
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
5
6
7
8
9
10
11
12
13
14
15
16
17
18
26
27
28
29
30
31
Prosena
brzina
(m/s)
0.31
0.58
0.56
0.59
0.62
0.65
0.67
0.70
0.72
0.74
0.76
0.77
0.79
1.06
0.82
0.98
0.94
0.95
0.96
0.97
0.97
0.99
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.70
0.70
1.70
1.65
1.51
1.50
1.34
1.00
0.79
0.76
0.74
0.72
0.77
0.88
1.16
1.23
1.99
1.58
1.30
1.34
1.37
1.44
9.20
9.60
18.10
19.70
21.20
22.60
23.90
25.10
26.30
27.50
28.60
29.70
30.70
26.90
32.70
30.30
40.60
41.30
42.10
42.90
43.90
44.30
138.815
138.259
133.851
133.851
134.11
133.022
133.851
133.851
133.851
133.656
133.859
144.575
144.575
144.379
109.149
109.905
77.279
76.832
77.279
78.238
77.238
75.869
0.020
0.030
0.050
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.090
0.090
0.100
0.100
0.100
0.120
0.120
0.130
0.130
0.130
0.140
0.030
0.030
0.060
0.060
0.070
0.070
0.070
0.080
0.080
0.090
0.090
0.090
0.100
0.070
0.100
0.080
0.120
0.130
0.130
0.130
0.140
0.130
PROFILE 39
Pipe
label
P-573
P-574
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-578
MH-579
MH-579
MH-580
649.40
648.80
648.40
647.80
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
648.80
649.10
647.80
647.20
Pad cevi
(%)
Duina
cevi (m)
1.50
1.50
40.00
40.00
Pad cevi
(%)
Duina
cevi (m)
1.00
1.00
1.00
1.00
1.00
0.49
0.51
40.00
40.00
40.00
40.00
40.00
34.44
23.53
Pad cevi
(%)
Duina
cevi (m)
1.00
1.00
1.00
1.01
1.02
1.01
40.00
31.93
35.84
36.79
40.00
39.77
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
1
2
Prosena
brzina
(m/s)
0.31
0.35
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.70
1.15
9.20
14.00
133.851
133.851
0.020
0.030
0.030
0.050
PROFILE 40
Pipe
label
P-640
P-641
P-642
P-643
P-644
P-645
P-646
Kota
Kota dna
Upstream
terena
cevi
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-645
MH-646
MH-647
MH-648
MH-649
MH-650
MH-651
MH-646
MH-647
MH-648
MH-649
MH-650
MH-651
MH-652
643.00
642.15
641.73
641.42
641.08
641.10
641.30
641.50
641.10
640.70
640.30
639.90
639.50
639.33
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
642.15
641.73
641.42
641.08
641.10
641.30
641.61
641.10
640.70
640.30
639.90
639.50
639.33
639.21
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
7
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.56
0.59
0.45
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.97
0.74
0.77
0.85
1.09
1.48
1.88
9.20
12.00
14.30
16.30
18.10
19.70
30.30
109.289
109.289
109.289
109.289
109.289
76.784
78.047
0.020
0.030
0.040
0.050
0.050
0.060
0.060
0.030
0.040
0.050
0.050
0.060
0.060
0.120
PROFILE 41
Pipe
label
P-681
P-682
P-683
P-684
P-685
P-686
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-688
MH-689
MH-690
MH-691
MH-692
MH-693
MH-689
MH-690
MH-691
MH-692
MH-693
MH-666
640.00
639.20
638.80
638.82
638.45
638.40
638.60
638.20
637.88
637.52
637.15
636.74
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
639.20
638.80
638.82
638.45
638.40
639.57
638.20
637.88
637.52
637.15
636.74
635.78
STRANA 31
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.56
0.72
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.90
0.66
0.81
1.00
1.18
2.14
9.20
12.00
14.30
16.30
18.10
17.40
109.289
109.408
109.532
109.6
110.646
109.604
0.020
0.030
0.040
0.050
0.050
0.060
0.030
0.040
0.050
0.050
0.060
0.050
PROFILE 42
Pipe
label
P-677
P-678
P-679
P-680
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-684
MH-685
MH-686
MH-687
MH-685
MH-686
MH-687
MH-664
639.70
639.40
639.10
638.60
638.70
638.30
637.90
637.50
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
639.40
639.10
638.60
639.74
638.30
637.90
637.50
636.10
Pad cevi
(%)
Duina
cevi (m)
1.00
1.00
1.00
1.01
40.00
40.00
40.00
39.60
Pad cevi
(%)
Duina
cevi (m)
0.50
0.49
0.50
0.50
0.52
0.54
40.00
34.74
40.00
12.11
23.07
16.71
Pad cevi
(%)
Duina
cevi (m)
1.00
1.00
1.00
1.00
40.00
40.00
40.00
38.00
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
1
2
3
4
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.64
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.75
0.85
0.85
1.57
9.20
12.00
14.30
14.20
109.289
109.289
109.289
109.839
0.020
0.030
0.040
0.050
0.030
0.040
0.050
0.040
PROFILE 43
Pipe
label
P-667
P-668
P-669
P-670
P-671
P-672
Kota dna
Kota
cevi
Upstream
terena
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-674
MH-675
MH-676
MH-677
MH-678
MH-679
MH-675
MH-676
MH-677
MH-678
MH-679
MH-665
638.56
638.67
639.00
639.16
639.25
639.37
637.50
637.30
637.13
636.93
636.87
636.75
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
638.67
639.00
639.16
639.25
639.37
639.60
637.30
637.13
636.93
636.87
636.75
635.97
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
6
Prosena
brzina
(m/s)
0.30
0.40
0.46
0.52
0.56
0.64
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.91
1.32
1.75
2.00
2.20
2.48
9.50
12.30
14.50
16.40
18.10
18.70
77.279
76.451
77.279
76.927
78.821
80.206
0.020
0.030
0.040
0.050
0.050
0.060
0.030
0.040
0.050
0.050
0.060
0.060
PROFILE 44
Pipe
label
P-673
P-674
P-675
P-676
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-680
MH-681
MH-682
MH-683
MH-681
MH-682
MH-683
MH-667
638.90
638.50
639.10
638.82
637.90
637.50
637.10
636.70
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
638.50
639.10
638.82
639.60
637.50
637.10
636.70
635.72
PROFILE 45
STRANA 32
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
1
2
3
4
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.64
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
0.70
1.20
1.76
2.40
9.20
12.00
14.30
14.20
109.289
109.289
109.289
109.289
0.020
0.030
0.040
0.050
0.030
0.040
0.050
0.040
Pipe
label
P-655
P-656
P-657
P-658
P-659
P-660
P-661
P-662
P-663
P-664
P-665
P-666
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-661
MH-662
MH-663
MH-664
MH-665
MH-666
MH-667
MH-668
MH-669
MH-670
MH-671
MH-672
MH-662
MH-663
MH-664
MH-665
MH-666
MH-667
MH-668
MH-669
MH-670
MH-671
MH-672
O-5
637.70
638.64
639.85
639.74
639.60
639.57
639.60
639.60
639.40
639.30
637.30
636.00
636.70
636.50
636.30
636.10
635.97
635.78
635.72
635.52
635.32
635.23
634.93
634.63
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
638.64
639.85
639.74
639.60
639.57
639.60
639.60
639.40
639.30
637.30
636.00
635.67
636.50
636.30
636.10
635.97
635.78
635.72
635.52
635.32
635.23
634.93
634.63
634.50
Pad cevi
(%)
Duina
cevi (m)
0.50
0.50
0.50
0.49
0.49
0.51
0.50
0.50
0.54
0.75
0.75
0.99
40.00
40.00
40.00
26.63
38.85
11.86
40.00
40.00
16.53
40.00
40.00
13.15
Pad cevi
(%)
Duina
cevi (m)
1.00
1.00
1.04
0.99
1.02
40.00
40.00
27.00
27.20
11.81
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
8
15
22
27
28
29
30
31
32
Prosena
brzina
(m/s)
0.30
0.40
0.38
0.55
0.71
0.84
0.95
0.96
0.97
0.98
0.99
1.15
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
(l/s)
ulazu (m) izlazu (m)
cevi) (%)
(m)
1.27
2.54
3.29
3.33
3.41
3.53
3.68
3.78
3.77
2.92
1.57
0.97
9.50
12.30
17.70
26.00
33.50
38.90
41.30
42.10
42.90
43.70
44.40
41.00
77.279
77.279
77.279
76.359
76.429
77.734
77.279
77.279
80.642
94.647
94.647
108.664
0.020
0.030
0.040
0.070
0.090
0.110
0.120
0.130
0.130
0.130
0.130
0.140
0.030
0.040
0.070
0.090
0.110
0.120
0.130
0.130
0.130
0.130
0.140
0.110
PROFILE 46
Pipe
label
P-554
P-555
P-556
P-557
P-558
Kota
Kota dna
terena
cevi
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-556
MH-557
MH-558
MH-559
MH-560
MH-557
MH-558
MH-559
MH-560
O-11
645.40
645.70
645.80
645.30
644.10
644.40
644.00
643.60
643.32
643.05
Kota
Kota dna
terena
cevi
nizvodnog nizvodnog
ahta (m) ahta (m)
645.70
645.80
645.30
644.10
643.65
644.00
643.60
643.32
643.05
642.93
STRANA 33
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
300 mm
1
2
3
4
5
Prosena
brzina
(m/s)
0.31
0.41
0.47
0.52
0.68
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
1.05
1.65
1.79
1.21
0.58
9.20
12.00
14.30
16.30
15.90
109.289
109.289
111.294
108.886
110.164
0.020
0.030
0.040
0.050
0.050
0.030
0.040
0.050
0.050
0.040
PROFILE 47
Pipe
label
P-563
P-564
P-565
P-566
Kota dna
Kota
cevi
terena
Upstream
manhole uzvodnog uzvodnog
ahta (m) ahta (m)
Nizvodni
aht
MH-566
MH-567
MH-568
MH-569
MH-567
MH-568
MH-569
O-10
642.53
642.60
643.10
642.30
641.53
641.40
641.27
641.13
Kota dna
Kota
cevi
terena
nizvodnog nizvodnog
ahta (m) ahta (m)
642.60
643.10
642.30
641.77
641.40
641.27
641.13
641.00
Pad cevi
(%)
Duina
cevi (m)
0.34
0.36
0.35
0.34
38.75
36.36
39.96
37.81
Prenik
Ukupni
cevi (mm) protok (l/s)
300 mm
300 mm
300 mm
300 mm
1
2
3
4
Prosena
brzina
(m/s)
0.26
0.35
0.41
0.53
Prosena
d/D
Projektovani Ispunjenost Ispunjenost
pokrivka
(ispunjenost kapacitet
cevi na
cevi na
cevi
cevi) (%)
(l/s)
ulazu (m) izlazu (m)
(m)
0.80
1.21
1.20
0.67
10.40
13.30
15.80
16.10
63.301
65.348
64.688
64.083
0.030
0.040
0.040
0.050
0.040
0.040
0.050
0.050
Responsible Designer
STRANA 34
4.1.2. STANDARDS
The Contractor is obliged to comply with EN standards or JUS standards according to the
latest edition of "Catalogue of the Yugoslav standard JUS. If there are no corresponding
JUS standards for any of the individual works, products or materials, the contractor will
apply international, national or an industry standard which is basically in accordance with
EN standards or JUS.
4.1.3. REGULATIONS
The Contractor should follow all regulations relating to the works and the products and
materials that will be implemented during construction, which are the subject of these
technical requirements.
STRANA 35
STRANA 36
The Contractor should carry out temporary works, and build temporary facilities including:
access roads to the construction site, embankments, temporary sanitation facilities,
premises, offices on the site, storage for products and materials, storage for tools and
construction equipment, first aid station, and temporary protective fences, connecting
signs, barricades, restricting access to the site, a room for the guards, concrete base, fire
equipment and the like, in a word - all that is normally required to build in such and similar
works for quick and safe flow of contracted work. The Contractor shall also provide supply
the electricity supply for motor and lighting, heating workrooms and installation of the
water supply at his own expense .
STRANA 37
STRANA 38
STRANA 39
STRANA 40
All the works required for the construction or repair of water facilities under
public spaces, streets, footpaths, roads, road shoulders, parks and other public
spaces in the city, regardless of who performs such works, can be done only with
prior approval of the competent authority .
Such works may be carried out from 1 April 1 November, and only in exceptional
cases outside this period.
The approval mentioned in the previous paragraf determines the start and
completion of the work, surface and places where the digging was approved, as well
as other conditions related to works that are prescribed by these terms.
The approval for the digging of public land may be issued only by labor
organization registered for such activities.
STRANA 41
The request for such approval must be submitted inwritten form, and the
construction can not begin prior to written approval.
Approval for digging can be issued only at the request of the Contractor. In exceptional
cases accidental damages of water facilities which prevent handling of the city or its
parts, communal organization with a damaged installation can begin to work on the
reconstruction of the verbal permission of the head of the competent authority, but it is
obliged to require a written approval within 48 hours.
The authority mentioned in Article 1.1. of these conditions is obliged to deliver a copy of its
given approval to a referent adequate community organization which maintains particular
public area.
Beside the application for approval to dig, the Contractor shall also submit:
Lay-out survey (in two copies) which defines following elevations: the
position of objects, digging belt, the position and type of previously placed objects in
the closest neighbourhood, mutual crossings, opposite passings and collisions.
STRANA 42
STRANA 43
When the width of the pavement dug (trenches and extensions for reinforcement) is
greater than 1/3 of the roadway, the first layer consists of bituminous surface. The layer
thickness must be equal to thickness the basic structure, but not less than 16 cm, and it is
applied to the level of the roadway. The trench closed in such way is left to the traffic for 46 months period of time. Then eventual depressions are filled, and wearing layer of
minimum 4 cm thickness is applied to the entire street
Transversaly digging through city streets, digging in the area of crossings, digging for
repairs on existing installations and closing the trench.
Transversaly digging through city streets means digging a trench with an axle that
intersects the axle of the roadway at an angle equal or greater than 45o.
Canals may be done only in sections geared to the demands of traffic organization.
All excavated material is immediately transported to the landfill.
Mounted (constructed) installation (object) must be protected with material upon the
request of the base material installation and equipment (construction) supplier and the
applicable regulations.
Overlaying the protected installation (object) is done by the top layer of pavement. The
amount of overburden is conditioned by the thickness of the existing pavement and the
minimum may be 20 cm from the road surface if it is asphalted roadway. Filling material
must meet the prescribed technical requirements for subbase. Quality control is done
according to prescribed conditions for the subbase
Upon completion of compaction the trench, associated roadway structures are excavated
for another 30 cm on each side of the edge of the trench, if the average depth of the
trench is less than 1.5 m, and for another 60 cm on both sides of the trench if the average
depth is equal to or greater than 1.5 m. The excavated material is transported to the
landfill, and the entire surface shall be cleaned, aligned and compacted to the required
density. Quality control is carried out according to the prescribed technical requirements
for subbase.
Closed trench must make monolithic entity with the existing roadway (cube, concrete
roadway, flatness, flagstone, paving stone, etc.) and fulfill the aesthetic and technical
requirements (slope of roadway, dress ups, contacts in the level, drainage, preventing the
frost - joints, fugues, etc.).
If it is asphalt construction, new asphalt is applied in two layers. The first layer consists of
bituminous substrates (bituminous gravel, bituminous rubble). The layer thickness must
be equal to the basic structure, but not less than 16 cm. Wearing layer must match the
type and thickness of the wearing layer of the basic construction, with minimum thickness
of 4 cm. If the roadway is to be asphalted, it must be done in two layers: BNS 16 of 6 cm
and AB 11 of 4 cm.
4.3.1.3. DIGGING IN THE AREAS PLANNED TRAFFIC AND CLOSING THE TRENCHES
Mounted (built) installation (object) is protected with the material at the request of the
supplier of materials and equipment (construction) and the applicable regulations.
STRANA 44
Overlaying the protected installation (object) is done by the top layer of existing terrain
using excavated material with required compaction. If a road is planned to be built on such
a surface within two years, installation should be burried up to the terrains surface, with
materials and methods that correspond to prescribed technical requirements for subgrade.
4.3.1.4. LONGITUDINAL EXCAVATION OF SIDEWALKS AND TRENCH BACKFILLING
Longitudinal digging of footpaths (sidewalks) means to dig for a trench with an axle
parallel to the axle of the sidewalk, or with an axle that intersects the sidewalk under the
angle less than 30o.
Canals may be done in sections adapted to the demands of the traffic.
Mounted (constructed) installation (object) must be protected with material requested by
materials and equipment (construction) supplier and the applicable regulations.
The overlay above the protected installation (object) is done up to 30 cm under the
sidewalk (footpath) surface, with materials corresponding to prescribed technical
requirements for subgrade.
If the material from the excavation does not meet the prescribed conditions, it should be
stabilized to required quality or completely replaced.
Material i quality control of subgrades, must correspond to prescribed technical
requirements for subgrade.
The construction of the bottom layer of pedestrian paths is carried out in all upon the
required technical conditions for the subbase.
The existing construction of pedestrian paths conditions conditions the height of the
existing sidewalk.
Upon completion of compaction the trench, associated roadway structures are excavated
for another 30 cm on each side of the edge of the trench, if the average depth of the
trench is less than 1.5 m, and for another 60 cm on both sides of the trench if the average
depth is equal to or greater than 1.5 m. The excavated material is transported to the
landfill, and the entire surface shall be cleaned, aligned and compacted to the required
density. Quality control is carried out according to the prescribed technical requirements
for subbase.
Final construction of the sidewalk must make monolithic entity with the existing roadway
(cube, concrete roadway, flatness, flagstone, paving stone, etc.) and fulfill the aesthetic
and technical requirements (slope of roadway, dress ups, contacts in the level, drainage,
preventing the frost - joints, fugues, etc.).
If it is an usual construction of concrete and wearing layer, final closing of the trench is
done in a way to produce a layer of concrete of minimum thickness of 10 cm at the level of
2 cm below the surface of footpaths.
When the width of a dug footpath (trenches and extensions for reinforcement) is equal to
or less than 1/3 of thesidewalk, asphalt wearing layer is applied over concrete substrates.
The quality and type of asphalt must meet the basic asphalt of the sidewalk. Contact with
the existing asphalt layer is performed by heating up the existing layer and then merges
hot with a flap of at least 2 cm thickness.
STRANA 45
When the width of a dug footpath (trenches and expansion for reinforcement) is greater
than 1/3 of the sidewalk, old asphalt is removed and the entire footpath is applied with
new asphalt of 2 cm thickness .
Transversaly digging through sidewalks means digging a trench with an axle that
intersects the axle of the sidewalk at an angle equal or greater than 30o.
All excavated material is immediately transported to the landfill.
Mounted (constructed) installation (object) must be protected with material requested by
materials and equipment (construction) supplier and the applicable regulations.
The overlay above the protected installation (object) is done up to the sidewalk (footpath)
surface, with materials corresponding to prescribed technical requirements for subgrade.
Filling is done with with materials corresponding to prescribed technical requirements for
subgrade.
Quality control is carried out according to the prescribed technical requirements for
subbase.
Upon completion of compaction the trench, associated roadway structures are excavated
for another 30 cm on each side of the edge of the trench, if the average depth of the
trench is less than 1.5 m, and for another 60 cm on both sides of the trench if the average
depth is equal to or greater than 1.5 m. The excavated material is transported to the
landfill, and the entire surface shall be cleaned, aligned and compacted to the required
density. Quality control is carried out according to the prescribed technical requirements
for subbase.
Final construction of the sidewalk must make monolithic entity with the existing roadway
(cube, concrete roadway, flatness, flagstone, paving stone, etc.) and fulfill the aesthetic
and technical requirements (slope of roadway, dress ups, contacts in the level, drainage,
preventing the frost - joints, fugues, etc.).
If it is an usual construction of concrete and wearing layer, final closing of the trench is
done in a way to produce a layer of concrete of minimum thickness of 10 cm at the level of
2 cm below the surface of footpaths. Contact with the existing asphalt layer is performed
by heating up the existing layer and then merges hot with a flap of at least 2 cm thickness.
4.3.1.6. EXCAVATION IN PARKS AND TRENCH BACKFILLING
Digging that must be done close to the trees is done manually with an obligation to protect
the vital parts of the roots (thickness diameter above 5 cm).
Protection of roots consists of careful excavation and wrapping the roots in corrugated
cardboard tape, kraft paper or other suitable coating (carboar or other material with
bituminous coatings as well as binding with wire are not allowed).
Protective covering must be removed before backfilling the trench.
If the root lies on the mounted installation (object), it must be provided by a protective
layer at the place of contact.
STRANA 46
Backfilling of the trench in a place where there are roots must be done manually by hand
tamping compactor. The roots themselves are coated with topsoil without admixture of
stone and clay and compacted by hand plugger in order to prevent deformity that would
cause material subsidence .
The entire trench is backfilled in layers with the required degree of compaction, which
guarantees that there will be no subsidence of the material.
Excess material is transported to the landfill.
Reconstruction of grasslands and low crops must cover not only a narrow strip directly
above and along the trench, but the entire land crossed by the installation.
Demolished or damaged trees must be reimbursed by an adequate number of seedlings,
selected and ordered by a horticultural expert.
4.3.1.7. EXCAVATIONS
Excavation performed may be seizing and excavation of trenches for pipelines, canals
and other that may occur during construction. After removing all that is necessary,
clearing land and setting out the route, excavation can start according to measures and
elevations in the project or in the draft, as well as to other possible instructions given in
writing by the Supervisory Council. At locations of inappropriate land that is considered
unsuitable, excavation will be carried out under the elevations specified in the project, and
dug area will be sealed with a suitable material as directed by Supervisory Body.
Excavated material that a Supervisor declares ineligible as well as surplus of excavated
material that remains after backfilling the trenches and other similar works will be marked
as surplus excavation. Contractor shall load into vehicles any surplus of excavation and
drive it to the designated landfill.
As a rule, the excavations will be carried out with adequate construction machinery
wherever possible.
While excavating trenches, the Contractor shall take care of mowing down the sides to
avoid unnecessary collapsing into already excavated area. Mowing the sides should be in
accordance with the geotechnical characteristics and the type of soil in which excavation
is performed and regulations on hygienic and technical safety when performing such work.
During ground and other works Contractor shall protect them against ground and surface
waters that may occur by building temporary facilities, pumping water or other suitable
ways. All the works performed in order to defence from water will not be separately paid if
they are not specifically stated in the bill of quantities for each water management facility.
The bill of quantities contains all specified types of grounds and positions where the
excavations should be done.
Certain types and categories of the excavations are presented based on data from the
project, while the calculation and payment will be made based on actual identified
categories of land during construction. Establishing categories of land where the
excavations will be carried is done by a supervisor after completion of excavation on the
specified object.
STRANA 47
In all the places where pedestrian traffic goes simultaneously with the construction, which
are determined by competent authority, there should a temporary protective barrier at one
side of the trench. The Contractor will submit a draft of temporary protective fences for
approval to the investor and to the competent authorities. Only after obtaining the consent
and approval, the fence can be built. The fence should be sufficiently strong and high to
protect pedestrians from falling or sliding into the trench. At the completion of the works,
with the consent and approval of the Supervisory Council and the competent authorities, a
temporary fence must be removed and the surrounding area brought back to its original
condition.
Calculation and payment will be made by 1 m of placed and removed temporary
protective fence. The Contractor will be paid 50% of the unit price after installing fences,
and the remaining 50% upon completion of the works when the fence is removed. Special
price includes all other works and costs that normally occur in the construction of such
facilities.
4.3.1.7.3. ALLOWANCE FOR DIFFICULT WORKING CONDITIONS
During the excavation of trenches and seizing on the routes of objects, at some parts of
the route difficult conditions for the work may appear. These are cases of wet and soggy
soil in parts of the route when it encounters an underground installation, where the normal
excavation is difficult because of the struts, and similar cases. In such cases the
contractor is entitled to the allowance for difficult working conditions during excavation. All
of these cases is determined and approved by the Supervisory Authority at written request
of the Contractor.
Calculation and payment will be made per 1 m3 of excavation or trench seizing regardless
of the width and depth of the trench and regardless of the group of land on which the
excavation was made under difficult circumstances, based on the review and approval of
the Supervisory Council. Unit price for difficult conditions during the excavation of
trenches and seizing covers all costs and work related to these cases and are not
specifically mentioned in the bill of quantities.
STRANA 48
Upon completion of the trench and channel excavations, but before concreting works and
installation of facilities start, trench bottommust be planned, according to measures of the
longitudinal profile of the project. The excavated material should be removed from the
trench at a certain distance and then, if it is the excess excavation, taken to the dump. It
is anticipated to plan trench bottom up to 1 m and over 1 m width.
Billing and payment will be made per 1 m of planned trench bottom to 1m over 1 m wide,
depending on the case. Unit price includes all other works and costs that normally occur
during execution of such facilities.
4.3.1.7.5. TRENCH SUPPORTING
During the excavation and seizing of trenches on the routes of water facilities, in some
parts of the route, due to poor geological composition of the soil, a need for shoring up the
sides of the trench may occur. If such a case occurs, the Contractor will inform the
Supervisory Council in written form. When the supervisor reviews reported case and
approves shoring, the Contractor is obliged to perform shoring with appropriate means
and materials. Shoring should be carried out so that the struts do not interfere with normal
work operations. Upon completion of the trench, during backfilling, struts should be
gradually removed and removed along with the progress of backfilling, in order to prevent
a sudden collapse of the soil in a trench and damages on the executed objects.
Disassembled and removed struts should be removed from the site where they were
used.
Billing and payment will be made per 1 m2 of trench shoring, regardless of the depth of the
trench. Each side of the trench is separatelly calculated. Contractor will be paid 50% of
the unit price for bracing when installing bracing and the rest of 50% after their removal
after completion and after the approval of the Supervisory Council that struts can be
removed. Unit price for shoring trenches coveres all costs of the works related to these
cases and they are not specifically mentioned in the bill of quantities.
STRANA 49
During excavation and seizing trenches and other works on the routes of water facilities,
groundwater in some parts of the route may occur. It should be appropriately removed by
pumping to allow undisturbed work at the site. If such a case occurs, the Contractor must
inform the supervisory. After the supervisor reviews reported case and approves pumping,
Contractor will place device or equipment for pumping with all the necessary wirings. A
device for pumping water should have a minimum capacity of 25 liters / sec and 1500 l /
min regardless of the depth or height of pumping. Pumping should be run so that drained
water cannot come back to the place where it is pumped from or outflows to other parts of
the route. Contractor should place enough pumping devices for successful lowering the
water level and to remove the water from the place where it appears, so that the works in
progress can normally run.
Contractor may remove the device or devices for pumping water at the end of the work or
upon the approval of the Supervisory when there is no more need for pumping.
Calculation and payment will be made per an 1 hour of a effective work of pumping device
capacity from 5 to 25 liters / sec and 1500 l / min regardless of the height or depth of the
water pumping. Unit price for pumping water covers the delivery and installation of
pumping equipment, with all necessary wirings, operation of the device during the
pumping with the operator, dismantling and shipping of the device with installation after
completion or supervisory approval, as well as all costs and works related to this kind of
work, but not specifically mentioned in the bill of quantities.
4.3.1.8. BACKFILLING AND DISPOSAL
Backfilling trenches on the route of distribution pipelines should be done after the pipes
are laid and facilities inspected, tested, and after labeling of pipelines and terminals.
Backfill material must be prescribed depending on the place where the backfill is to be
performed in accordance with the requirements for the digging of public land for the
construction and repair of underground installations and units in the city, which are listed
in the Technical Requirements in Section 1.
The excavated material is temporarily deposited on the trench side or on certain
temporary landfills if the material will be used for backfilling trenches. Surplus of
excavated material remained after backfilling, must be loaded into vehicles and taken
away to a particular landfill.
4.3.1.8.1. SAND BACKFILING
After the pipes are laid on prepared bedding and testing of pipelines done, pipes are
flooded in the sand layer of corresponding thickness above their vertices. Clean sand free
from harmful impurities, debris, rock fragments must be used. Poured sand should be
compacted to the required density by a light beater.
Billing and payment will be made per 1 m3 of purchased, delivered, outspreaded and
compacted sand. Unit price includes all works and costs related to the purchase and
spreading of sand and are not specifically mentioned in the bill of quantities.
STRANA 50
Backfilling trenches with excavated ground material will be performed in accordance with
the requirements for the digging of public land for the construction of underground
installations and city units, which means at all those places where subbase is not
required. Excavated soil, approved by the appropriate Supervisory, should be used in
backfilling the trenches.
While trenches backfilling, finer excavated material should be outspread and sticked first.
Backfilling continues in a layers of 15 to 30 cm thickness over the entire width of the
trench until envisaged height of fill is reached.
Gravel should be compacted to achieve 95% of the parts of the trenches with the lower
bearing layers and 85% in the trenches without supporting layers, with the maximum
density of the optimum moisture content according to JUS U. B. 1 045.
Mechanical compaction is achieved by pneumatic plugger except in the first part of the
trench around placed pipes. Here compaction should be performed by manual
compactors.
Compaction testing should prove whether backfilling trenches by excavated ground
material meets requirements and it should be done at the place designated by the
supervisor. If the test results do not meet the standards, the Contractor must excavate the
buried material and re-compact the trench until the required density is achieved.
Billing and payment will be made by 1 m3 of bacfilled trench with excavated soil to proper
compaction.
Unit price includes all works and costs related to this type of work and are not specifically
provided for in the cost of works.
4.3.1.8.3. LOADING AND TRANSPORT TO A LANDFILL
Each surplus of excavated material that remained after backfilling the trench or from other
works. should be loaded on the vehicle and transported to the landfill determined by the
Supervisory Authority.
Billing and payment will be made per m3 of loaded, transported and disposed excavated
surplus regardless of the soil type. This surplus is determined by the difference between
amount of excavated material measured in the fused state from which the amount of the
same material used for backfilling trenches and other works is deducted, also measured
the fused state. Unit price includes all other works and costs that normally occur in this
type of work.
STRANA 51
STRANA 52
STRANA 53
Calculation and payment will be done by 1 m1 of installed steel water pipe of specific
nominal diameter with all above described acts. Unit price include and all other works and
costs that appears normally at construction structures like this is.
4.5.4. ASSEMBLING OF AIR VALVES, MUD OUTLETS AND HYDRANTS
This work includes purchase of particular fittings and reinforcements that should install on
places of air valves, mud outlets and hydrants. With this is comprised transport,
dispatching, lowering, assembling, sealing, testing on the test pressure, rinsing and
disinfection.
Calculation and payment will be done by piece of installed air valve, mud outlet and
hydrant. Unit price include and all other works and costs that appears normally at
construction structures like this is, and they are not mentioned in bill of quantities.
4.5.5. STANDARDS FOR PIPE MATERIALS AND PIPES JOINTS
4.5.5.1. POLYPROPYLENE PIPES
Purchase, transport, dispatching along the trench and assembling of two layer corrugated
sewage pipes of polypropylene (PP) with integrated coupling, type SN 8, into the trench.
Pipes should be manufactured according to EN 13 476-3, in orange color, and inner side
in white, due to easier inspection, in all according to designed diameters and specification.
Pipes carefully lay on prepared sand bed, and watching out that during the laying and
assembling of pipes the same be laid in designed descent without horizontal and vertical
breaking. Descent control should be done with surveying instrument with supervisors
presence. Works should be done all in accordance with technical regulation for particular
type of pipes, or in accordance with requirements EN 1610, in the manner, which was
precise by pipe manufacturer, and all in accordance to Supervisors direction.
4.5.5.2. PVC RIGID PIPES
Purchase, transport, dispatching along the trench and assembling of three layer PVC
sewage pipes with integrated coupling, type SN 8. The pipes should be producted
according to EN 13 476-2, all in accordance with designed diameters and specification.
Pipes carefully lay on prepared sand bed, and watching out that during the laying and
assembling of pipes the same be laid in designed descent without horizontal and vertical
breaking. Descent control should be done with surveying instrument with supervisors
presence. Works should be done all in accordance with technical regulation for particular
type of pipes, or in accordance with requirements EN 1610, in the manner, which was
precise by pipe manufacturer, and all in accordance to Supervisors direction.
4.5.5.3. POLYETHYLENE PIPES
High Density Polyethylene pipes can be with or without steel reinforcement (rings) which
enables them to provide a high ring stiffness. These pipes should meet DIN EN 13476th
Stiffness of the external pressure should be consistent with the standard DIN EN ISO
9969 SN8. Watertight in accordance with DIN EN 1277 and DIN EN in 1610.
4.5.5.4. POLYESTER PIPES
Pipes specification
STRANA 54
Sewage pipes with nominal diameter DN (mm), nominal rigidness SN (N/m2) and nominal
pressure PN (bar), from polyester, manufactured according to EN 14364:2007. The pipes
should meet requirements from TV standard MUC-KSP-A 2000. Single pipe length is 6
m, and at one end of the pipe is fitted polyester joint with sealing of EPDM. The sealing of
EPDM must in complete, with entire surface, cover the inner side of polyester joint. Inner
protective layer of polyester, without filling and fiberglass must have a thickness of
minimum 1 mm, due to increased resistance to abrasion and chemical attack.
Specification of pre-cast manholes from polyester
The standard inspection chamber with vertical pipe DN (mm) from polyester,
manufactured according to EN 14364:2007, with steps from incorrodible material, with
shaped gutter of polyester, with connections defined in inspection chambers( diameter
and high of vertical pipe, diameter, position, high and type of material of connections). In
item, it is included and standard steps. The pipe from which is performed inspection
chamber must have inner protective layer of polyester, without filling and fiberglass, with
thickness of minimum 1 mm, due to increased resistance to abrasion and chemical attack,
and it should meet requirements from TV standard MUC-KSP-A 2000.
STRANA 55
4.7. FINAL TESTING (AND/OR TESTING OF PIPELINE AND MANHOLES AFTER THE FILLING)
After completion of works on pipes laying, it is necessary to do some testing, as follows:
4.7.1. VISUAL TESTING
Visual testing include:
Position by route and altitude
joints
damages or evenly deformation
connections
4.7.2. SEALING
Sealing of the pipeline altogether with connections, manholes and inspection chambers
must be tested according the item 7.4.
4.7.3. PIPELINE AREA AND MAIN FILLING
STRANA 56
4.7.3.1. COMPATION
If it is required, it is necessary to: test the degree of bed compactness, side filling, and
cover of mail filling.
4.7.3.2. PIPE DEFORMATION
Test pressure
Test pressure is the pressure, from filling of tested part to level of terrain elevation, and
subject to standard, upstream or downstream placed manholes, given pressure from
exceeding 50kPa and at least 10 kPa, measured at the back of the pipe head. Higher test
pressures can be prescribed for pipelines which are laid and which always or from time to
time are under higher pressure (to see NORM EN 805).
Time for preparation
After pipeline and/or manhole filling and reaching necessary test pressure, may be
needed preparatory time (usually enough 1 hour).
Testing time
Testing time must be 301 min.
Testing requirements
The pressure must be maintained within a certain 1k of certain test pressure with water
recharging .
The total volume of water, which was added to achieve these requirements during the
test, as well as the respective amount of pressure required test pressure must be
measured and written.
Requirements of filling are accomplished if water volume is not higher than:
0.15 l/m2 for 30 min for pipelines
0.20 l/m2 for 30 min for pipelines including manholes
0.15 l/m2 for 30 min for manholes and inspection chamber
IOV10-17/A1 IK KONSALTING I PROJEKTOVANJE JANUARY 2013
STRANA 57
5. BILL OF QUANTITIES
Item
Description
Unit
measure
PRELIMINARY WORKS
ROUTE MARKING
Quantity
Price per
unit
measure
EUR
Total
EUR
11,436.00
1.50
17,154.00
5.00
60.00
300.00
Calculation per m .
ASSURANCE OF EXISTING
INSTALATION
To do assurance and, eventually
replacement of existing underground
instalations.
Calculation per piece
DEMOLITION OF ASPHALT ROADWAY
Demolition of asphalt roadway for 20 cm
wider from provided width of trench and
removing of material from part of route on
which will be temporary storage
excavated material.
2
Calculation per m .
RESTORING OF ROADWAY TO
ORIGINAL CONDITION
piece
15,030.00
7.00
105,210.00
15,030.00
45.00
676,350.00
Calculation per m .
799,014.00
STRANA 58
II
EARTH WORKS
22,018.00
5,505.00
6.00
18.00
132,108.00
99,090.00
168.00
18.00
3,024.00
12,742.00
2.00
25,484.00
8,220.00
20.00
164,400.00
m
3
m
STRANA 59
Calculation per m .
TRANSPORT OF SURPLUS MATERIAL
Transport of surplus material from
excavation on the dump, far to 5 km,
defined by Supervisor. Position Unit price
includes loading, transport, unloading and
coarse spreading of loaded materials on
the dump. Quantity of excavated materials
for transport should be increased for 2025%, due to material bulking.
3
Calculation per m .
II
III
CARPENTRY WORKS
TRENCH SUPPORTING
Supporting of the trench at greater depth
with metal supporting, type "KRINGS
VERBAU". Supporting should be placed
parallel with trench excavation. Price
includes assembling and disassembling of
formwork.
2
Calculation per m .
III
IV
CONCRETE WORKS
INSPECTION CHAMBER
18,397.00
25.00
27,523.00
15.00
459,925.00
412,845.00
1,296,876.00
3,660.00
7.00
25,620.00
25,620.00
piece
343
290.00
STRANA 60
99,470.00
WATER GULLYS
Purchase, transport and assembling of
street water gullies with cast iron
450/150mm grating as well and pipes
150 mm length 3 m for connecting on
sewage collector. Unit price includes all
material for water gully.
Calculation per piece.
IV
piece
686
200.00
ASSEMBLING WORKS
137,200.00
236,670.00
Calculation per m .
DN 300 mm
DN 400 mm
DN 500 mm
LG COVERS
m
1
m
1
m
10,352.00
536.00
549.00
55.00
75.00
115.00
569,360.00
40,200.00
63,135.00
piece
343.00
320.00
109,760.00
piece
2,565.00
7.00
17,955.00
800,410.00
STRANA 61
VI
OTHER WORKS
HYDRAULIC TESTING
Upon completion of the installation of
certain sections of sewer, carry out their
testing of water resistance, in the
presence of the Supervisory
Council,under all the conditions of the
utility and the applicable regulations for
this type of work. Remove all possible
defects before backfilling the trench.
The calculation of the m1.
1
Calculation per m .
SEWAGE RINSING
Flushing sewage before hydraulic testing
in order to remove any material brought
into the sewage system during installation.
Calculation per m .
AS BUILD SURVEYING FOR
CADASTER
Upon completion of the installation of
storm sewer sections, the Contractor is
required to perform geodetic survey of
executed situation and convey all
amendments of the state and the
corresponding longitudinal profiles and
details to the situation.
The calculation of the m1.
1
Calculation per m .
PERFORMANCE OF AS BUILD DESIGN
After receiving the data of executed
sewage surveyed, draw the situation and
the longitudinal profile with other
necessary data in the situation. Study
should be prepared in six copies, which
will be signed by the contractor and
supervision, and submit it to the investor.
1
Calculation per m .
SUPERVISION COSTS
It involves the provision of appropriate
supervisions costs made by supervision
institutions (power, communication, public
utilities) during the execution of work in
order to make timely provision of all
underground utilities.
Calculation by the job
11,436.00
2.00
22,872.00
11,436.00
2.00
22,872.00
11,436.00
2.00
22,872.00
1.00
6,000.00
6,000.00
1.00
5,000.00
5,000.00
By the
job
STRANA 62
VI
By the
job
3,000.00
3,000.00
By the
job
300,000.00
382,616.00
Summary recapitulation
Position
I Preliminary works
II Earth works:
Amount (EUR)
799,014.00
1,296,876.00
25,620.00
IV Concrete works
236,670.00
V Assembling works
800,410.00
VI Other works
382,616.00
TOTAL (EUR) :
3,541,206.00
Responsible designer
STRANA 63
Drawing
number
Drawing title
001
Lay-out
002
Lay-out
003
Lay-out
004
Profile 1
005
Profile 2
006
Profile 2
007
Profiles 3, 4, 5
008
Profiles 6, 7, 8, 9, 10
009
010
011
012
013
014
015
016
PRILOG 1
PRILOG 2
PRILOG 3
PRILOG 4
PRILOG 5
PRILOG 6
STRANA 64