Académique Documents
Professionnel Documents
Culture Documents
Complete a Valuation
Issued August 2011
How
Do I Complete a Valuation?
Introduction
A Valuation is where, in a given Valuation Period, you decide how much
you are going to pay your subcontractor the internal costs - and apply
to the client for payment for the value of the project - the external
value - according to the percentage of work accomplished.
The Projectsheet is calculated based on the current Valuation Period that
has been set for the Projectbook.
Much of what you can do in Valuations depends on the way your
Projectbook has been set up. For example, the percentage over
certification permitted and whether retention is applied before discount.
These are setup on the Module configuration screen.
Module Configuration
Internal Valuations
This is where the Main Contractor values and certifies the Trade Contract
items and certifies any Subcontract Applications that have been made in
the current Valuation Period.
The amount of the submitted application is shown in the Projectsheet in
the Application to Date column.
The amount that is agreed to be paid certified is shown in the
Certified to Date column.
If the Subcontractor does not have access to Commercial Management,
the applications can be made offline to the Main Contractor who then has
2 options:
enter the amounts and certify them directly from the Internal
Valuations screen.
Copyright conject
Project Control by conject v6.0
Page 1
button
button.
The applications on the Internal Valuations listing screen may have one of
these statuses:
Submitted the contract has been valued and saved, but not yet
certified
Click on the link in the Status column to view the details of the
application.
edit
>
The Trade Contract selection box contains only the orders placed with
the company you selected. Then click on
.
Copyright conject
Project Control by conject v6.0
Page 2
General details about the application are shown at the top of the next
screen, followed by a summary detailing the previous and current values
of the certificates, for example:
This table describes each of the fields in the summary and how they are
calculated:
Column Name Description
Formula
Gross Total
Retention
Discount
Net Total
The net amount after the deduction of Sum of the Net To Date column on all
any retention and discount
the line items in the application
This
Certificate
You may enter values directly against individual line items, or you may
enter a summary amount to be applied to ALL the line items.
Copyright conject
Project Control by conject v6.0
Page 3
At the top of the Order List, above the first Line Item, are three
summary fields. If you enter any values here, they are applied to ALL
the line items:
The following description assumes you are entering values for individual
line items:
the amount for which you are applying in the Certified Amount
To Date field
Copyright conject
Project Control by conject v6.0
Page 4
You may certify this application immediately or save it so you can return
and make any changes.
the valuation is listed with a status of Submitted and
If you click
the value is entered into the Projectsheet in the Applications to Date
column.
the valuation is listed with a status of Certified
If you click on
and you cannot edit it. The value is entered into the Projectsheet in the
Certified to Date column.
If you move to the next Valuation Period before you Certify the
application, the application does not appear in the Internal Valuation
listing unless you use the filters to view the applications made in the
previous valuation period.
Once you have found the application, you can click on it, and edit it and
certify it, in the previous valuation period.
Copyright conject
Project Control by conject v6.0
Page 5
>
.
Using the same example as shown above, in the next valuation period
you may want to make an application for 20% of the Phase 2 Demolition
which is in Line Item 2:
Click on
or
Again, if you have External Values setup for the Projectsheet, you may
go directly to the External Application screen to submit an application to
the Client:
Page 6
The Trade Contract is for 10,000 and represents the finished brickwork.
Although no construction work has been done in this valuation period,
you can value and certify the value of the bricks that have been
delivered to site so far for example 2,000.
When the above example is created, the following is shown in the
Material On/Off Site List:
Now you can certify this amount by entering the amount in the Certified
Amount to Date box:
and click on
Page 7
You can certify payment for these items by entering amounts for
Quantity, Percentage and Amount in the same way as for Orders
described above.
The amount entered against Change Items is added to the amounts
entered for Materials On/Off Site and Orders. The totals are shown in
the Summary at the top of the screen.
External Applications
If your Projectbook is set up to track External Value, this is where the
Main Contractor can make applications for payment to the Client.
The process whereby you click on a button from the Internal Valuation
screen to create an External Application:
Copyright conject
Project Control by conject v6.0
Page 8
From here you can list, view and edit existing Open applications and view
any Submitted Applications for the current Valuation Period. Use the
button to view Applications from other Valuation Periods.
The method of entering amount for the application is the same as
described for Internal Valuations with the exception that you are
applying to the Client for payment for the value of the work completed
instead of certifying payment to the subcontractor for the cost of work
completed.
External Certifications
This is where the Client can certify the application for payment made by
the Main Contractor by accessing the External Certification screen.
If the Client does not have access to conject Commercial Management,
the Main Contractor provides the Client with submitted applications
outside of Commercial Management. Once certified, the Main Contractor
records the certified amounts on the External Certification screen in
Commercial Management.
>
>
From the navigation panel select
to view the Submitted External Applications made in the current
Valuation Period. Click on the status link of the submitted application
you want to Certify.
The External Certification Details screen displays a summary showing the
values of the Current and Previous Certificates and the total amount
Certified to Date.
The method of entering amounts for the certification is the same as
described for Internal Valuations with the exception that you are
recording the amounts the Client has certified to pay the Main Contractor
for the value of the work completed instead of certifying payment to the
subcontractor for the cost of work completed.
Valuation Reports
There are a number of reports available to help you manage and monitor
the valuation process. These are found under the
option in
the navigation bar:
Page 9
A report title
Paper size
Depending on the report you are running, you may also be able to specify
combinations of options such as:
Valuation Period
Trade Contract
More Information
How Do I?
Setup Valuations
Copyright conject
Project Control by conject v6.0
User Guides
Change Management
Page 10