FINAL REPORT Sheet

ROMANIA 2008
European Studies
ES 1
Traffic Information Systems - Study

MAIN ACHIEVEMENTS
Description of the situation before the project implementation:

In Romania there is no centralized information regarding the traffic and roads infrastructure status.
Different information exists at different Infrastructure Administrators or Authorities, but there is no system
gathering all the relevant information from one area and presenting it to the public.
Traffic Police have information regarding all the accidents and incidents on the motorways and national
roads and also inside cities. The information is gathered in a Traffic Info Centre and is presented to the
public in news bulletins on local radio stations and TV stations.

Description of the solution implemented:


OBJECTIVES
A. National and International state report on Traffic Information.
B. The elaboration of the technical Specification/tender documentation for the study and for the pilot
project

A. National and International study on Traffic Information


1) Market Analysis National and European State regarding Traffic Information
Actual analysis and definition of the evolution purposes at the National Level
InfoTransNet
Information subsystem for freight transport
Technical Road Data Bank
TRADB Traffic Road Accidents Data Base
Traffic monitoring subsystem for the national road network
InfoTraffic Road Police Center for information regarding accidents/incidents
Actual state analysis regarding Traffic Information
Potential service providers and products analysis

B. The elaboration of the technical specification/tender documentation for the study and for the pilot project.
1) The study regarding the National Traffic Information System - technical specification
2) Pilot Project - technical specification
Location
Structure and Functions
Testing
Possible architecture of the Road Traffic Information Center
General Requirements
Evaluation pilot system
Recommendations regarding system extend at the national level
3) Cost estimation of the contract
4) Motivation Criteria for tender procedure

Proposed system architecture


The system consists of the following parts:

Reliable data network

Server architecture

Dispatcher consoles

Display

KEY EVENTS EFFETTIVI


Description

Date (mm/yyyy)

Offers submission
Contract signature no.93/20685
Submission of report
Report Acceptance

09/2008
10/2008
12/2008
12/2008

COSTS SPENT (K)


EUR
Study
Planned
Internal
External
2008

600.000

TOTAL
600.000

Study
Spent
Internal
External
22.927

TOTAL
22.927

3,82%

ECB monthly accounting rate of the euro for December 2008 EUR/RON: 3,9227
DELIVERABLES
Title of deliverable
MONI-EasyWay_National and International Status Report
MONI-EasyWay_Technical Specification

Language
Deliverable
Romanian
Romanian

Summary