Académique Documents
Professionnel Documents
Culture Documents
REPORT
Located at
Lopez Jaena Street,
Ormoc City, Leyte
Owner:
Mr. Ruvinieu Mendola
Submitted by:
ENGR. BENEDICT B. BANQUIL, BSC, MEngg IPM
The
proposed
construction
of
an
additional
third
floor
of
Originally, the natural ground level (NGL) is about the same level as the existing road.
Site drainage is mainly by gravity to the existing open drainage facilities located along
the main road.
acceleration of the location is between 4.0 to 4.8 m/s2 (or 0.5 g) with a ten percent
(10%) probability of exceedance in 50 years as shown in Figure 7.
Even if the structural engineers provides designs in accordance with the applicable
codes for seismic design, the possibility of damage occurring cannot be ruled out if
moderate-to-strong ground shaking occurs as result of a violent earthquake. Based on
this condition, the structure should be designed in accordance with the latest National
Structural Code of the Philippines (NSCP) criteria for seismic design parameters as
follows:
Near Source Factor - Type A
(Table 208-4 and 208-5, p2-39, Figure 208-2C, NSCP)
Seismic Zone - 4 use Z Factor = 0.40
(Figure 208-1, NSCP)
Soil Investigation
Mr. Ruvinieu Mendola
4. SOIL INVESTIGATION
The site investigation included subsurface investigation of the site soil condition and
laboratory testing. The subsurface exploration consisted of one deep excavation or
borehole. The approximate location of the excavation is shown in Fig 8. The purpose of
the excavations was to delineate the subsurface conditions in the area of the proposed
improvements.
Soil and rock conditions encountered in the test pit excavation were
recovered from test pit were placed in moisture resistant containers and transported to
the laboratory for testing. Excavation was then backfilled upon completion.
They were tested in the laboratory for particle size gradation (ASTM D422-63),
Atterberg limits (ASTM D4318-05), and natural moisture content (ASTM D2216-05) for
the purposes of classifying according to the Unified Soil Classification System (USCS).
The layer formations of the soil at the site from the ground surface, as observed,
consist of 0.0m to 2.0m thick of silty soil layer and sand and gravel layer thereafter.
Groundwater was encountered 3.0 meter below the natural ground level.
5. RECOMMENDATIONS
The following are the recommendations for the proposed additional third floor of the
existing commercial/residential building with respect to geotechnical condition of the site:
a. The columns should be connected with tie beams at the ground level.
b. The structural engineer should check the existing size of the footings based on the
given design parameters and increase its sizes if necessary.
c. Allowable bearing pressure: 200 kPa or based on the presumptive load-bearing
values (see Table 304-1 NSCP 2010).
d. Depth of the footing: 2.0 meters below the natural ground level (NGL). Water
accumulating at the bottom of the excavation, if found, should be pump out prior to
pouring of concrete.
e. The foundation concrete should be at least Type I with a maximum water/cement
ratio of 0.50 by weight. Minimum unconfined compressive strength and reinforcement
condition should be in accordance with structural engineering requirements. In addition,
Soil Investigation
Mr. Ruvinieu Mendola
6. OTHERS CONSIDERATIONS
Other design considerations are as follows:
Surface drainage. Provision shall be made for the control and drainage of the water
around the building and ensure that scour will not threaten such structures through
adequate embedment. It is recommended that appositive drainage be provided so that
water flows away from the foundations. Two percent drainage away from the foundation is
recommended. Surface water should be directed to street canals.
Sidewalks/Flatworks.
geotechnical services during construction. This office should be contacted for review of
finals plans for improvements. In addition, the soil engineer should be involved during
construction to monitor the geotechnical aspects of the development (i.e., foundation
excavations). During construction, it is recommended that this office verify site
geotechnical conditions and conformance with the intentions of the recommendations for
construction. Although not all possible geotechnical observation and testing services are
required by the government agencies, the more reviews performed, the lower the risk of
future problems.
Site safety. The contractor is the party responsible for providing a safe site. The
geotechnical engineer will not direct the contractors operations and cannot be
responsible for the safety of personnel other than his own representatives on-site. The
contractor should notify the owner if unsafe conditions are anticipated. At the time of
construction, if the geotechnical consultant considers condition unsafe, the contractors,
as well as the owners representative, will be notified.
Soil Investigation
Mr. Ruvinieu Mendola
7. CLOSURE
The geotechnical investigation was performed using the degree of care and skill
ordinarily exercised, under similar circumstances, by geotechnical engineers practicing in
this or similar localities.
Submitted by
PRC NO.
VALID UNTIL
PTR N0./Date
CTC No./Date
TIN NO.
Soil Investigation
Mr. Ruvinieu Mendola
Soil Investigation
Mr. Ruvinieu Mendola