General Submission Form (Other Than Material Submission)

Project

Venetian Macau in Cotai, Macau

Package No

7104 - CCMS

Name of Trade Contractor

Honeywell (Macau) Limited

Type of Service

CCMS

Submission Schedule Ref.

7104/PW/TRC002

A.

Submission Description

A.1

Desription:

Date of Submission :

26/01/2006

Testing and Commissioning Procedure (Format)

No. of Submission x1st 2nd 3rd 4th


A.2

Reason of Change
This is only the foramt for the Factory Acceptance Testing Procedure.

A.3

A.4

Details of Attachment

Method Statement

Working Programme

Testing and Commission Procedure

Others

Testing Certificate / Approval Letter

Remark

Authorized Signature of Contractor

Jimmy Lam
B.
B.1

Comment of Construction Manager / Consultant


A No adverse comment and shall work according to this submission
Comment
B No adverse comment and shall work according to comment
C Re-submit according to comment
D Rejected and shall re-submit the entire submission according to comment

Commented by:
Company:
Date:
B.2

Comment

Project: M138 Ventian Cotai, Macau


Document: Testing and Commissioning (format)
File reference: 7104_PW_TRC002-A.xls
Date: 1/27/2006
Produced by: Honewyell (Macau) Ltd.

(Please add separate sheet if needed)

Honeywell

Testing Procedure: Lighting Control

Testing & Commissioning Procedure


General Overview
The following procedure details the steps to be taken and the items of plant to be checked to
ensure that the unit is operating as specified in the associated Honeywell Optimal Solution
Functional Description.
Serious consideration is to be given to testing and checking the functionality of the software
program Off Site using the Honeywell Live CARE simulation tool for this purpose.
Ideally and where possible, the on site commissioning of the unit should be carried out from
the operators terminal of the Building Management System to the end or field device located
within the plant room or associated areas served by the unit.
Once the unit has been fully tested and commissioned a trend report can be set up to monitor
the zone temperature control system to ensure that the loop is correctly Tuned to provide
stable control within the zone or area served.

1. Lighting "Off" Mode Inspection / Individual Equipment Function Test


1.1 Lighting Off Mode
1) To disable the time program and exchange the lighting command point from auto
mode to manual mode.
2) It is recommended to off lighting.

2. Lighting "On" Mode Program Test


2.1 Lighting "Auto/Manual" Mode Operation
1) Auto/Manual mode is hardware point selection.
2) DDC program is enabled with lighting Auto mode selection.
2.2 Time Program Activiated
1) It is depended on the built-in time program to control the lighting.
2) It may be changed by operators in any times.

3. Reset All Points to Auto Mode


3.1 All Datapoints Reset to Auto Mode
After completion all the testing and commissioning, all the software and hardware points
must be return to auto mode from manual mode.

Honeywell Limited

Testing Procedure: Lighting-001


Revision: 1

Honeywell

Testing Procedure: Lighting Control

Revision History
Rev
1.0

Date
26-Jul-05

Honeywell Limited

Originator
XL Toolkits Team

Comments
Original Document

Testing Procedure: Lighting-001


Revision: 1