Construction Supervision Consultant for

Jakarta Urgent Flood Mitigation Project (JUFMP)/


Jakarta Emergency Dredging Initiative (JEDI)
Ministry of Public Works and Housing Affair

World Bank

Prepared by
Korea Engineering Consultant Corp of Korea,
in association with

PT. Tetira International Consultants

PT. Puser Bumi Mekon

PT. Duta Cipta Mandiri Engineering Consultants


1
www.jufmp.com

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Table of Contents
1.
2.
3.
4.
5.

JUFMP/JEDI Information
Consultant Services
Executive Summary
Issues
Ongoing Construction Packages
Package 1
Package 2A
Package 2B
Package 3
Package 5
6. Photo Gallery
2

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Project Information
Project Name

: JUFMP/JEDI

Loan Agreement

: 8121 ID

Date of Loan Sign

: February 17, 2012

Effective Date

: August 8, 2012

Closing Date

: March 31, 2017

Loan Amount

: USD 139,640,000

Executing Agency

: 1. Directorate General Water Resources, MoPW


2. Directorate General Cipta Karya, MoPWHA
3. Provincial Government of DKI Jaya

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Project Development Objective (PDO)


1. Reduce the frequency and extend of flooding in Jakarta through
dredging, and rehabilitation and construction of embankment of key
waterways and flood retention basins;
2. Establishing institutional coordination between, and strengthening
their capacity of the three responsible agencies, to improve the
operations, maintenance and management of Jakartas flood
management system.
The project is intended to reduce the economic and social cost of
flooding by partially restoring the capacity of the citys flood control
system to its original design level.

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Project Components
1. Dredging and rehabilitation of selected key floodways, canals
and retention basins.: This component support the dredging and
rehabilitation of 11 floodways/canals and 4 retention basins which
have been identified as a priority sections of Jakarta flood
management system in the need of urgent rehabilitation and
improvement in flow capacities (USD 176.1 million)
2. Technical assistance for project management, social
safeguards, and capacity building: The component will support
contracts managemnt, engineering design review, construction
supervision engineers for dredging and rehabilitation works and
technical assistance for implementation of the project, including
Resettlement Policy Framework, Resettlement Plan and Grievance
Redress System (USD 13.4 million)
5

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Project Organization

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Project Location

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Subprojects and PIU

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Construction Supervision Consultant (CSC) for JUFMP/JEDI


Project Name
Source of Fund
Addendum No.1
Contract Amount
Engineer

:
:
:
:
:

Contractor

Contract No.
:
Notice to Proceed :
Time Period
:

Construction Supervision Consultant for JUFMP/JEDI


World Bank
1,784,300 USD + 38,494,770,000 IDR
2,072,400 USD + 38,153,170,999 IDR
Directorate of River and Coastal, Directorate General
Water Resources, Ministry of Public Work and
Housing
Korea Engineering Consultants Corporation with PT.
Puser Bumi Mekon joint venture and sub consultancy
PT. Tetira International Consultant and PT. Duta Cipta
Mandiri Engineering Consultant
06/KTR/PPK-Ad-Satker/X/2013 September 11, 2013
HI.0102-Ad/496 October 18, 2013
40.5 months Adendum No.1, originally 60 months
9

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Outline of Consultant Services


The main services of the Consultant for JUFMP/JEDI are:
Supervision of Dredging Work and Construction/Rehabilitation of
Embankment
Quality Assurances and Quality Control
Assist in Implementation of Environmental Management (RKL/RPL)
Assist in Implementation of Resettlement Plans (RPs)
Implementation of Grievance Redress System (GRS) and Complaint
Handling Mechanism
Monitoring, Reporting and Recording
Assist CPMU, CPIU and PIUs in Project Management

10

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Executive Summary
Figure 1. Budget Allocation for Component 1of JUFMP
(in million USD)
Total Budget 178.7

103.5
58%

22.3
12%

53.0
30%

Prov Gov of DKI


(37%) + IBRD (67%)
DG Water Resources (20%) + IBRD (80%)
DG Cipta Karya
(20%) + IBRD (80%)

11

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Executive Summary
Table 1. Budget Allocation for Component 1
Executing Agencies/ Packages
DKI Jakarta
Package 1
Package 4
Package 7
DGWR
Package 2A
Package 2B
Package 6
DGCK
Package 3
Package 5
TOTAL

Budget (Loan +
APBN/D)
USD
103,492,537
36,716,418
47,014,925
19,761,194
53,000,000
31,000,000
8,125,000
13,875,000
22,250,000
6,717,421
15,532,579
178,742,537

Loan Allocation
USD
69,340,000
24,600,000
31,500,000
13,240,000
42,400,000
24,800,000
6,500,000
11,100,000
17,800,000
5,373,937
12,426,063
129,540,000

APBD/N Sharing
USD
34,152,537
12,116,418
15,514,925
6,521,194
10,600,000
6,200,000
1,625,000
2,775,000
4,450,000
1,343,484
3,106,516
49,202,537
12

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Executive Summary
Table 2. Budget Allocation for Component 2

Items
Supervision Consultant
Flood Management Information
System
Panel of Experts
Resetlement Cost (DKI Jaya)
Total Component 2
Total Project Cost (Comp 1+2)

Total

USD
10,100,000
500,000
500,000
2,800,000
13,900,000
192,642,537

Loan IBRD

USD
10,100,000
10,100,000
139,640,000

APBD/N
Sharing
USD
500,000
2,800,000
3,300,000
52,502,537

Bilateral
Grant
USD
500,000
500,000
500,000

13

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Executive Summary
Table 3. Contract Amount by Packages (IDR)
Executing Agencies/
Packages
DKI Jakarta
Package 1
Package 4
Package 7
DGWR
Package 2A
Package 2B
Package 6
DGCK
Package 3
Package 5
TOTAL

Contract Amount
284,180,000,000
284,180,000,000
334,965,463,260
260,000,000,000
74,965,463,260
208,214,431,000
68,514,386,000
139,700,045,000
827,359,894,260

Loan
190,400,600,000
190,400,600,000
267,972,370,608
208,000,000,000
59,972,370,608
166,571,544,800
54,811,508,800
111,760,036,000
624,944,515,408

APBN/D Sharing
93,779,400,000
93,779,400,000
66,993,092,652
52,000,000,000
14,993,092,652
41,642,886,200
13,702,877,200
27,940,009,000
202,415,378,852

14

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Executive Summary
Figure 4. Financial Progress (in billion IDR)
284.2

300

260.0
250

208.7
200

201.5

163.6

148.6

139.7

150

75.0

100

54.0

54.9
33.9

50

68.5
22.2

19.8

32.9

Package 1

Package 2A
Disbursed

Package 2B

Disbursement + Un-disbursement

Package 3

Package 5

Contract Amount

15

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Executive Summary
Table 4. Volume of Dredge Material of On-going Packages
Volume (thousand m3)
Package

Sign Date

Notice to
Proceed

Package 1
Nov 26,2013 Dec 02,2013
Ciliwung-Gn. Sahari
Waduk Melati
Package 2A
Nov 11,2013 Nov 11,2013
Package 2B
Nov 11,2013 Nov 11,2013
Package 3
Nov 15,2013 Nov 15,2013
Package 5
Sep 3,2014 Sep 3,2014
Tanjungan Drain
Lower Angke Drain
TOTAL

Period
(days)
730

730
730
730
730

Garbage
(m3)
2.8
1.5
1.4
18.8
20.0
0.8
6.2
0.0
6.2
48.7

Sludge
(m3)
165.6
85.1
80.5
1,007.3
513.7
48.4
253.0
11.2
241.8
1,988.0

Garbage + Weight
Sludge
(m3)
168.4
86.6
81.9
1,026.1
533.7
49.2
259.2
11.2
248.0
2,036.7

(%)
8.3
4.2
4.0
50.4
26.2
2.4
12.7
0.6
12.2
100.0

16

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Executive Summary
Table 5. Progress of Dredging Works (On-going Packages)
Package
Package 1

Trip of
Truck

Volume (thousand m3)


Garbage

Sludge

Garbage + Sludge

8,765

160.5

160.5

95.3%

4,644

84.3

84.3

97.4%

76.2

76.2

93.0%

Package 2A

4,121
48,407

806.7

806.7

78.6%

Package 2B

21,968

376.6

376.6

70.6%

Package 3

209

3.6

3.6

7.3%

Package 5

144

2.4

2.4

0.9%

144

2.4

2.4

21.7%

79,493

1,349.8

1,349.8

66.3%

Ciliwung-Gn.Sahari
Waduk Melati

Tanjungan Drain
Lower Angke Drain
TOTAL

17

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Executive Summary
Figure 5. Schedule and Progress of Construction Works (%)
74.2

Package 1

75.8
82.3

Package 2A

69.6
78.7

Package 2B

78.5
82.7

Package 3

86.5
14.1

Package 5

16.9
0

10

20

30
Progress

40

50

60

70

80

90

Schedule

18

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Issues
1. Package 1 Ciliwung-Gunung Sahari and Waduk Melati
a) Waduk Melati: (i) construction schedule for Waduk Melati
pump station needs to be precisely managed to complete
within the contract period, and (ii) guard rail as an
additional work will be installed around the Waduk (fencing
in original contract was changed to guard rail in MC 0).
b) Gunung Sahari drain: remaining works such as gaps
between embankment edge and bridges, U-ditch along the
right bank and side walk along Jl. Gunung Sahari drain
should be completed as scheduled. DKI requested to
heighten the side walk.

19

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Issues
2.

Package 2A Cengkareng Floodway


a) Contractor proposed embankment work at both sides of the
floodway between bridges at STA 2+250 - STA 2+500 to use
stone masonry rather than piles for the reason of working space
limitation.
b) STA 3+400 - STA 5+050: several missing portion (gaps) on the
presence of road crossings and culverts.
c) Remedial works have not been started.

3. Package 2B Lower Sunter Floodway


a) Temporary disposal of dredge material at some places not
applied.

4. Package 3 Cideng-Thamrin Drain


20

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Issues
5. Package 4 Sentiong Sunter, Waduk Sunter Utara, Waduk

Sunter Selatan and Waduk Sunter Timur III


a) Bid opened on March 24, 2015. PT. Adhi Karya has the lowest
bidding price of 296.9 billion IDR

6. Package 5 Lower Angke and Tanjungan Drain


a) Not sufficient storage space available for CCSPs and heavy
equipment (such as crane) at Lower Angke Drain.

7. Package 6 Banjir Kanal Barat (BKB)and Upper Sunter


a) Dredge from Karet to river mouth proposed to add to Package 6.
b) Bidding is delayed due to LARAP.

21

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Issues
8. Package 7 Grogol Seketaris, Pakin, Kali Besar, Jelakeng
and Krukut.
a) Bid opened March 10, 2015. PT. Waskita Karya has the lowest
bidding price of 226.8 billion IDR.

9. LARAP
a) Houses and buildings along Upper Sunter Floodway (Package 6)
in Kayu Putih village of Pulo Gadung sub-district have been
demolished by DKI Jaya Government. PAPs of JUFMP/JEDI
located on Jatinegara Kaum were not affected by the demolition.
b) Due to problem at Lower Angke Muara, Dinas Tata Air DKI,
embankment work at Kel. Kapuk Muara modified to stone
masonry instead of concrete piles.
22

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Issues
c) LARAP reports for Sentiong Sunter, Waduk Sunter Utara and
Waduk Sunter Selatan were prepared and second socialization
is planned.
10. Construction Supervision Consultant
a) Staff of site offices have faced difficulties due to shortage of
transportation (mainly motor cycles).
b) Overtime payment for enumerators, surveyors and drivers not

yet settled.

23

Construction Supervision Consultant for


Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

City Gov of DKI

World Bank

PACKAGE 1
CILIWUNG-GUNUNG SAHARI DRAIN AND WADUK MELATI

Contractor:
PT. Brantas Abipraya (Persero)
24

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

General Information
PIU

: DPU - DKI

Contractor

: PT. Brantas Abipraya

No Objection Letter

: No. JUFMP 1

Letter of Acceptance

: No. 14705/-7.793.2

Contract No.

: 15380/-1.793.2 dated Nov 26, 2013

Contract Amount

: IDR 284,180,000,000 (incl. PPN)

Signed Date

: Nov 26, 2013

Notice to Proceed

: 15452/-1.793.2 dated Nov 26, 2013

Completion Day

: 730 Calendar days

Elapsed Days

: 514 days (70.4%)


25

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

General Information
Ciliwung Gunung Sahari Drain

SHEET PILE
4,832 m

LENGTH
OF DREDGING
5,100 m

Dredging Volume: 86,557 m3


Progress : 78,185 m3 or 90.3%
Embankment Repair : 4.600 m
ISTIQLAL MOSQUE

26

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Ciliwung Gunung Sahari Drain


a) Dredging Work: total = 86,557 m3, progress = 84,279 m3 (97.4%)
STA 0+500 - STA 5+100 (Martadinata Bridge - Istiqlal - Pasar Baru)

b) Concrete Work
volume = 2,681 m3 , length = 4,300 m
reinforcement bar, deformed = 91.04 ton

c) Pilling Work
Furnishing of CCSP W-450, total = 5,178 units

L 12 m = 2,442 units, L 14 m = 1,582 units, L 17 m = 1,154 units

Furnishing of square pile 40x40 cm, total = 392 units


Driving of CCSP W-450, total = 5,178 units
d)

Miscellaneous Works
Demolishing and disposal of existing concrete, total = 12.8 m3
Demolishing and disposal stone masonry,
total = 2,088 m3
27

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Waduk Melati
a) Dredging Works: total = 81,878 m3, progress = 76,167 m3 (93.0%)
b) Concrete Work
Total concrete = 570.25 m3, length = 1,229 m
Reinforcement bar, deformed = 30.95 ton
c) Pilling Works
Furnishing of CCSP W-450, total =1,208 units
10 m = 959 units, L 12 m = 249 units
Driving of CCSP W-450, total = 1,208 units
d) Miscellaneous Work

Demolishing and disposal of stone masonry, total = 1,021 m3

28

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 1: Progress of Dredging Works (thousand m3)


May 2014 Apr 2015
180

160.4
160

132.3

140

149.2

120

97.6

100
80

116.6

81.3
55.8

60
40

27.3

20
0

0.1 0.1

0.1
2.3

29

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 1: Schedule and Progress of Construction Work (%)


May 2014 Apr 2015
90
Schedule

Progress

77

80
72
70
62
58 58

60
53
50

69

76 74

51

4344
37 36

40

30 29

30
23
19 20

20
14
10
0
0

65 67

73
7172

4 6

15

6 10 9

30

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 1:

Financial Progress (billion IDR)


Apr 2015

163.6
58%

75.5
26%

45.1
16%

Contract Value = 284.2


Disbursed

Undisbursed

Remaining
31

Construction Supervision Consultant for


Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

BBWS CILCIS

World Bank

PACKAGE 2A - CENGKARENG FLOODWAY

Contractor:
Adhi Karya-Hutama Karya-Jaya Konstruksi JV
32

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

General Information
PIU
Contractor
No Objection Letter
Letter of Acceptance

:
:
:
:

BBWS Ciliwung-Cisadane, DGWR


Adhi Karya-Hutama Karya-Jaya Konstruksi (JV)
No. JUFMP/107 dated Sep 7, 2013
No.KU.03.01/PPK SP-SNVT PJSA CC/XI/310.1
dated Nov 6, 2013

Contract No.
Amendment IV

: HK.02.03/PPK SP-SNVT PJSA CC/XI/315.4


dated Nov 11, 2013
: IDR 260,000,000,000 incl. 10% tax

Amendment II

: IDR 234,627,368,750 incl. 10% tax

Original Contract

: IDR 209,808,000,000 incl. 10% tax

Signed Date

: Nov 11, 2013

Completion Day

: 730 Calendar days

Elapsed Days

: 535 days (73.3%)


33

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Location and Scope of Works


Cengkareng Floodway
DREDGING WORK
Target
Length =
8,380 m
Volume=1,026,125 m3
Finished
Length = 4+700 m
Volume= 711,684 m3

KAPUK
RAYA

Sta 3+750

Replacement
of Water Gates
PILLING WORK
Target
Length
= 2,100 m
CCSP W-325 = 2,100 units
Pile 30x30
= 525 units
Finished
Length
= 1,000 m
CCSP W-325 = 1,071 units
Pile 30x30 =
175 units

KEMBANGAN
BRIDGE

PILLING WORK
Target
Length
= 5,700 m
CCSP W-325 = 5,700 units
Pile 30x30
= 1,425 units
Finished
Length
= ... m
CCSP W-325 = 5,703 units
Pile 30x30
= 1,203 units

Sta 4+500
KAPUK
PULO
BRIDGE

Sta 5+000
Sta 5+875

Sta 6+750
Sta 7+800

PILLING WORK
Length
=
4,600 m
CCSP W-325 = 110,699 units
Pile 30x30
= 390,000 units

W : 325 ; B : 1000 L : 14 meter


34

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Cengkareng Floodway
a) Dredging Work: total = 1,026,125 m3, progress = 806,700 m3 (78.6%)
STA 0+500 - STA 7+800

b) Concrete Work
CCSP capping = 2,292.1 m3, backpile capping = 150.30 m3, walling = 86 m3

c) Pilling Work
Furnishing of CCSP W-325 and W-450, total = 8,057 units
L 12 m = 5,269 units, L 14 m = 2,948 units, L 15 m = 55 units, L 18 m = 237 units

Furnishing of square pile 40x40 cm, total = 2,064 units


L 10 m = 1,656 units, L 12 m = 408 units

Driving of CCSP W-450, total = 8,426 units


L 12 m = 5,268 units, L 14 m = 2,870 units, L 15 m = 55 units, L 18 m = 233 units

Driving of square pile total = 1,842 units


L 10 m = 1,513 units, L 12 m = 329 units
35

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 2A: Progress of Dredging Works (thousand m3)


May 2014 Apr 2015
880

806.7

800

720

711.7

640

605.5

560

457.5

480

530.1

400

377.4

320

246.7
240

134.7

160
80
0

182.5

92.8
13.7

29.4

123.4

67.1

36

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 2A.

Schedule and Progress of Construction Work (%)


May 2014 Apr 2015

90
Schedule

80

82

Progress

78

70

65

60

57

54
46

50

40

37

40

34

29
30

23

17
11
1

41

46

60

69
62

65

66

70

53

49

38
32

27

20
10

47

66

73

19

8
3

37

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 2A. Financial Progress (billion IDR)


Apr 2015

148.6
57%
58.5
23%

52.9
20%

Contract Value = 260.0


Disbursed

Undisbursed

Remaining
38

Construction Supervision Consultant for


Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

BBWS CILCIS

World Bank

PACKAGE 2B - LOWER SUNTER FLOODWAY

Contractor:
PT. Hutama Karya (Persero)
39

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

General Information
PIU

: BBWS Ciliwung-Cisadane, DGWR

Contractor

: PT. Hutama Karya

No Objection Letter

: No. JUFMP/1

Letter of Acceptance

: No.14705/-7.793.2

Contract No.

: HK.02.03/PPK SP-SNVT CC/XI/315.4

Contract Amount

: IDR 65,258,477,570

Amendment I No.

: HK.02.03/AMD/PPK SP-SNVT/PJSA CC/II/38.5

Amendment I Amount

: IDR 74,965,463,260

Signed Date

: Nov 11, 2013

Notice to Proceed

: Nov 11, 2013

Completion Day

: 730 Calendar days

Elapsed Days

: 535 days (73.3%)


40

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Location and Scope of Works


Lower Sunter Floodway

Concrete wall
1,000 m
Concrete Wall
400 m
Concrete Wall
400 m

41

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Lower Sunter Drain


a) Dredging Work: total = 533,689 m3, progress = 376,624 m3 (70.6%)

STA 0+025 - STA 7+350

b) Concrete Work

Type-A (K-225), total = 1,998 m3


Formwork type A2 = 4,083 m2
Reinforcement bar, deformed = 87,305 kg
Lean concrete, t = 10 cm, total = 149 m3
Graded sand fill, t = 10 cm, total = 149 m3
Stone masonry,
total = 278 m3

c) Pilling Work
Furnishing of concrete pile 20x20x400, total = 3,600 units
Driving of concrete pile 20x20x400,
total = 2,961 units
42

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 2B.

Progress of Dredging Works (thousand m3)


May 2014 Apr 2015

400

376.6

350

314.2
334.2

300

282.7

306.5

250

243.6
200

185.0

150

126.8
100

47.6

81.3

50

3.0

57.3
16.8

43

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 2B.

Schedule and Progress of Construction Work (%)


Dec 2014 Apr 2015

90
80

74 73

70

64

65

79 79

68 68

56 58 59

60

51
47
44 44

50

42
37 37 37

40

31
30

24

20

13

13

10

18

14
5

13

27

29

23

17

44

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 2B.

Financial Progress (billion IDR)


Apr 2015

21.0
28%

20.0
27%
33.9
45%

Contract Amount = 75.0


Disbursed

Undisbursed

Remaining

45

Construction Supervision Consultant for


Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

DG Cipta Karya

World Bank

PACKAGE 3 CIDENG THAMRIN DRAIN

Contractor:

PT. Dutaraya Dinametro


46

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

General Information
PIU

: Directorate of Environmental Sanitation Development,


Directorate General Human Settlement, Ministry of Public
Work and Housing

Contractor
No Objection Letter

: PT. Dutaraya Dinametro


: No. JUFMP-3

Contract No.

: HK.02.03/JUFMP-FSK/XI/1

Contract Amount

: IDR 62,324,785,000 (Addendum 2)

Signed Date
Notice to Proceed

IDR 48,747,011,000 (Original Contract)


: Nov 15, 2013
: Nov 15, 2013

Completion Day
Elapsed Days

: 730 Calendar days


: 531 days (72.7%)
47

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Location and Scope of Works


Cideng Thamrin Drain

EXISTING

SHEETPILES

Reinforced Concrete Block


NEW
SHEETPILES

48

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Cideng-Thamrin Drain
a) Dredging Work: total = 49,224 m3, progress = 3,598 m3 (7.3%)
STA 0CT-4 - STA CT-31

b) Concrete Work
Type-A (K-225), total = 998.8 m3

c) Pilling Work
Furnishing of CCSP W-325 L = 14 m, total =

602 units

Furnishing of CCSP W-350 L = 16 m, total = 1,538 units

Driving of CCSP W-325

L = 14 m, total =

Driving of CCSP W-350

L = 16 m, total = 1,524 units

602 units

Driving of 6 Pipe L = 10 m under Bridges


target = 18,960 m, progress = 12,110 m (63.9%)
49

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 3.

Schedule and Progress of Construction Work (%)


Dec 2014 Apr 2015

100

Schedule

90

Progress
82
79

80
70

63

87
83

71 72
64 64
62 62 62

60

48

50

41

41
40

34
26

30

21
20
10

3 5

5
0

11 10

15 13

16

47

33
25

20

50

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 3. Financial Progress (billion IDR)


Apr 2015

14.5
21%

34.2
50%
19.8
29%

Contract Amount = 68.5


Disbursed

Undisbursed

Remaining

51

Construction Supervision Consultant for


Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

DG Cipta Karya

World Bank

PACKAGE 5
TANJUNGAN DRAIN AND LOWER ANGKE DRAIN

Contractor:
PT. SAC Nusantara and

PT. Penata Karya Utama (JO)


52

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

General Information
PIU

: Directorate of Environmental Sanitation Development, DGHS, MoPW

Contractor

: PT. SAC Nusantara and PT. Penata Karya Keluarga Utama (JO)

No Objection Letter

: -

Letter of Acceptance

: No.KU.03.01/JUFMP/02/VIII/2014

Contract No.

: HK.02.03/JUFMP-FSK/IX/2

Contract Amount

: IDR 139,700,045,000 (incl. Tax)

Signed Date

: Sep 3, 2014

Notice to Proceed

: -

Completion Day

: 730 Calendar days

Elapsed Days

: 239 days (32.7%)


53

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Location and Scope of Works


TANJUNGAN
DRAIN

LENGTH
OF DREDGING
600 m

SHEET PILE
1,092 m

Dredging : 11,210 m3
Embankment Repair: 1,092 m
54

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Location and Scope of Works


LOWER ANGKE
DRAIN

SHEET PILE
248 m

LENGTH
OF DREDGING
4,050 m

RETAINING WALL
573 m

Dredging : 241,800 m3
Embankment Repair : 821 m
55

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Tanjungan Drain
a) Dredging Works: total = 11,500 m3, progress = 4,468 m3 (38.9%)
b) Concrete Work
Total concrete = 228.3 m3
Formwork type-A2 = 182.6 m2
c) Pilling Works
Furnishing of CCSP W-500, total = 1,000 units
14 m = 600 units, L 16 m = 400 units

Furnishing of square pile 0.3x0.3x10 m, total = 50 units

Driving of CCSP W-500, total = 935 units


14 m = 559 units, L 16 m = 376 units

56

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 5. Schedule and Progress of Construction Work (%)


Oct 2014 Apr 2015
20
Schedule

Progress

16.9

15
13.0
10.1

10

9.0

13.6
13.0

14.1

9.3

5.5
5
2.3
0.6

3.1

3.5

0.4

0
Oct 14

Nov 14

Dec 14

Jan 15

Feb 15

Mar 15

Apr 15

57

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 5. Financial Progress (billion IDR)


Apr 2015
10.7
8%

22.2
16%

106.8
76%

Contract Value = 139.7


Disbursed

Undisbursed

Remaining
58

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 1
Check list reinforcement bar STA 3 + 200
Ciliwung Gunung Sahari Drain

Result of Concrete Work STA 3 + 350


Ciliwung Gunung Sahari Drain

59

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 1
Activities of Dredging pump STA 0 + 850 at
Ciliwung Gunung Sahari Drain

Excavation for foundation of pump station at


Waduk Melati

60

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 1
Concrete Work for the foundation of pump
station at Waduk Melati

Dredging Work at STA 0+050 Waduk Melati

61

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 2A

62

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 2A

63

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 2B

64

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 3

65

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 3

66

MoPW&HA

World Bank
Construction Supervision Consultant for
Jakarta Urgent Flood Mitigation Project (JUFMP)/
Jakarta Emergency Dredging Initiative (JEDI)

Package 5
Mr. President, Ministry of PWHA and
Governor of DKI visited Tanjungan Drain

Dredging work at Tanjungan Drain

67