Vous êtes sur la page 1sur 9

Rozlina C23-227

15/11/2014

Operations
Management
Chapter 3
Project Management
PowerPoint presentation to accompany
Heizer/Render
Principles of Operations Management, 6e
Operations Management, 8e
2006
Prentice
Hall, Inc. Hall, Inc.

2006
Prentice

31

2006 Prentice Hall, Inc.

3 29

2006 Prentice Hall, Inc.

3 30

2006 Prentice Hall, Inc.

3 31

2006 Prentice Hall, Inc.

3 32

2006 Prentice Hall, Inc.

3 33

Rozlina C23-227

15/11/2014

Purposes of Project
Scheduling

Project Scheduling
Identifying precedence
relationships

1. Shows the relationship of each activity to


others and to the whole project

Sequencing activities

2. Identifies the precedence relationships


among activities

Determining activity times & costs

3. Encourages the setting of realistic time


and cost estimates for each activity

Estimating material and worker


requirements

4. Helps make better use of people, money,


and material resources by identifying
critical bottlenecks in the project

Determining critical activities


2006 Prentice Hall, Inc.

3 36

2006 Prentice Hall, Inc.

Project Management
Techniques

3 37

A Simple Gantt Chart

Gantt chart
Critical Path Method
(CPM)
Program Evaluation
and Review
Technique (PERT)

Time
M J

Design
Prototype
Test
Revise
Production

2006 Prentice Hall, Inc.

3 38

2006 Prentice Hall, Inc.

Service For A Delta Jet


Passengers
Baggage
Fueling
Cargo and mail
Galley servicing
Lavatory servicing
Drinking water
Cabin cleaning
Cargo and mail
Flight services
Operating crew
Baggage
Passengers

Figure 3.4
2006 Prentice Hall, Inc.

3 39

PERT and CPM

Deplaning
Baggage claim
Container offload
Pumping
Engine injection water
Container offload
Main cabin door
Aft cabin door
Aft, center, forward
Loading
First-class section
Economy section
Container/bulk loading
Galley/cabin check
Receive passengers
Aircraft check
Loading
Boarding

Network techniques
Developed in 1950s
CPM by DuPont for chemical plants (1957)
PERT by Booz, Allen & Hamilton with the
U.S. Navy, for Polaris missile (1958)

Consider precedence relationships and


interdependencies
Each uses a different estimate of
activity times
0

15

30
Minutes

45

60
3 40

2006 Prentice Hall, Inc.

3 42

Rozlina C23-227

15/11/2014

Six Steps PERT & CPM

Work Breakdown Structure

1. Define the project and prepare the


work breakdown structure

Level

2. Develop relationships among the


activities - decide which activities
must precede and which must follow
others

2.

1. Project
Major tasks in the project

3.

Subtasks in the major tasks

4.

Activities (or work packages)


to be completed

3. Draw the network connecting all of


the activities
2006 Prentice Hall, Inc.

3 43

2006 Prentice Hall, Inc.

Questions PERT & CPM


Can Answer

Six Steps PERT & CPM


4. Assign time and/or cost estimates
to each activity

1. When will the entire project be


completed?

5. Compute the longest time path


through the network this is called
the critical path

2. What are the critical activities or tasks in


the project?
3. Which are the noncritical activities?

6. Use the network to help plan,


schedule, monitor, and control the
project
2006 Prentice Hall, Inc.

4. What is the probability the project will be


completed by a specific date?

3 45

2006 Prentice Hall, Inc.

3 46

A Comparison of AON and


AOA Network Conventions

Questions PERT & CPM


Can Answer

Activity on
Node (AON)

5. Is the project on schedule, behind


schedule, or ahead of schedule?
6. Is the money spent equal to, less than, or
greater than the budget?

(a) A

B
A

7. Are there enough resources available to


finish the project on time?

(b)

C
B

8. If the project must be finished in a shorter


time, what is the way to accomplish this
at least cost?

B
(c)

Figure 3.5
2006 Prentice Hall, Inc.

3 44

3 47

2006 Prentice Hall, Inc.

Activity
Meaning
A comes before
B, which comes
before C
A and B must both
be completed
before C can start
B and C cannot
begin until A is
completed

Activity on
Arrow (AOA)

A
B

C
B
C
3 48

Rozlina C23-227

15/11/2014

A Comparison of AON and


AOA Network Conventions

A Comparison of AON and


AOA Network Conventions

Activity on
Node (AON)

Activity on
Node (AON)

(d)

(e)
Figure 3.5

Activity
Meaning

Activity on
Arrow (AOA)

C and D cannot
begin until A
and B have
both been
completed
C cannot begin
until both A and B
are completed; D
cannot begin until
B is completed. A
dummy activity is
introduced in AOA

(f)
C

C
Dummy activity

B and C cannot
begin until A is
completed. D
cannot begin
until both B and
C are completed.
A dummy
activity is again
introduced in
AOA.

A
Dummy
activity

D
C

Figure 3.5
3 49

2006 Prentice Hall, Inc.

3 50

AON Example

AON Network for


Milwaukee Paper

Milwaukee Paper Manufacturing's


Activities and Predecessors
Description
Build internal components

Activity on
Arrow (AOA)

2006 Prentice Hall, Inc.

Activity
A

Activity
Meaning

Immediate
Predecessors

Modify roof and floor

Construct collection stack

Pour concrete and install frame

A, B

Build high-temperature burner

Activity A
(Build Internal Components)

Activity B
(Modify Roof and Floor)

Install pollution control system

Install air pollution device

D, E

Inspect and test

F, G

Start

Start
Activity

Figure 3.6

Table 3.1
2006 Prentice Hall, Inc.

3 51

2006 Prentice Hall, Inc.

3 52

AON Network for


Milwaukee Paper

AON Network for


Milwaukee Paper

Activity A Precedes Activity C


F
A

Start

Start

D
Activities A and B
Precede Activity D

2006 Prentice Hall, Inc.

H
G

Arrows Show Precedence


Relationships

Figure 3.7
3 53

2006 Prentice Hall, Inc.

Figure 3.8

3 54

Rozlina C23-227

15/11/2014

AOA Network for


Milwaukee Paper

Perform a Critical Path Analysis

C
4
(Construct
Stack)

The critical path is the longest path


through the network

Dummy
Activity

Determining the Project


Schedule

H
(Inspect/
Test)

D
5
(Pour
Concrete/
Install Frame)

The critical path is the shortest time in


which the project can be completed

Any delay in critical path activities


delays the project
Critical path activities have no slack
time

Figure 3.9

2006 Prentice Hall, Inc.

3 55

2006 Prentice Hall, Inc.

AON Example

Determining the Project


Schedule

Milwaukee Paper Manufacturing's


Activities and Predecessors
Acti
vity
A

Description
Build internal components

Immediate
Predecessor
s

Time
(week
s)
2

Modify roof and floor

Construct collection stack

Pour concrete and install frame

A, B

Build high-temperature burner

Install pollution control system

Install air pollution device

D, E

Inspect and test

F, G

Perform a Critical Path Analysis


Earliest start (ES) = earliest time at which an activity can
Activity Description
Time (weeks)
start, assuming all predecessors
have
A
Build internal
components
2
been completed
Modify
roof and
floor
3
EarliestBfinish (EF)
= earliest
time
at which an activity can
be finished
C
Construct
collection stack
2
D start (LS)
Pour=concrete
and
Latest
latest time
atinstall
which frame
an activity can4
start so as to not delay
E
Build high-temperature
burnerthe completion
4
of thecontrol
entire project
F
Install time
pollution
system
3
LatestGfinish (LF)
=
latest
time
by
which
an
activity
has
Install air pollution device
5 to
be finished so as to not delay the
H
Inspect and test
2
completion time of the entire project
Table
Total Time (weeks)
25 3.2

2
26

Total time (weeks)

Table 3.1
2006 Prentice Hall, Inc.

3 57

2006 Prentice Hall, Inc.

Determining the Project


Schedule

Begin at starting event and work forward


Earliest Start Time Rule:

Activity Name
or Symbol
A
ES

Latest
Start

LS

EF
LF
2

3 59

Forward Pass

Perform a Critical Path Analysis

Earliest
Start

3 56

If an activity has only one immediate


predecessor, its ES equals the EF of the
predecessor
If an activity has multiple immediate
predecessors, its ES is the maximum of
all the EF values of its predecessors

Earliest
Finish

Latest
Finish

ES = Max (EF of all immediate predecessors)


Figure 3.10
2006 Prentice Hall, Inc.

Activity Duration
3 60

2006 Prentice Hall, Inc.

3 61

Rozlina C23-227

15/11/2014

ES/EF Network for


Milwaukee Paper

Forward Pass
Begin at starting event and work forward
ES

Earliest Finish Time Rule:

EF = ES + Activity time

The earliest finish time (EF) of an activity


is the sum of its earliest start time (ES)
and its activity time

Start

EF = ES + Activity time

2006 Prentice Hall, Inc.

3 62

2006 Prentice Hall, Inc.

3 63

ES/EF Network for


Milwaukee Paper

Start

ES/EF Network for


Milwaukee Paper

EF of A =
ES of A + 2

ES
of A

Start

EF of B =
ES of B + 3

ES
of B

2
3
2006 Prentice Hall, Inc.

3 64

2006 Prentice Hall, Inc.

3 65

ES/EF Network for


Milwaukee Paper
0

2
0

Start

ES/EF Network for


Milwaukee Paper
0

Start

2006 Prentice Hall, Inc.

D
3

B
3

3 66

= Max (2, 3)
0

0
0

2006 Prentice Hall, Inc.

4
3 67

Rozlina C23-227

15/11/2014

ES/EF Network for


Milwaukee Paper
0

2
0

Start

ES/EF Network for


Milwaukee Paper
0

Start

C
2

0
0

13

15

2
8

13

5
Figure 3.11

2006 Prentice Hall, Inc.

3 68

2006 Prentice Hall, Inc.

3 69

Backward Pass

Backward Pass

Begin with the last event and work backwards

Begin with the last event and work backwards

Latest Finish Time Rule:

Latest Start Time Rule:

If an activity is an immediate predecessor


for just a single activity, its LF equals the
LS of the activity that immediately follows it
If an activity is an immediate predecessor
to more than one activity, its LF is the
minimum of all LS values of all activities
that immediately follow it

The latest start time (LS) of an activity is


the difference of its latest finish time (LF)
and its activity time

LS = LF Activity time

LF = Min (LS of all immediate following activities)


2006 Prentice Hall, Inc.

3 70

2006 Prentice Hall, Inc.

3 71

LS/LF Times for


Milwaukee Paper
0

2
0

Start

C
2

B
3

13
13

LS = LF
D Activity time
G
3

4
0

Figure 3.12

F
3

2006 Prentice Hall, Inc.

LS/LF Times for


Milwaukee Paper

H
2

15
15

Start

10

F
3

7
13

8 of
LF =4 Min(LS
following activity)

13
13

LF = EF
of Project

13

B
3

D
4

H
2

15
15

13

Figure 3.12
3 72

2006 Prentice Hall, Inc.

3 73

Rozlina C23-227

15/11/2014

LS/LF Times for


LF = Min(4, 10)
Milwaukee
Paper
0

2
0

Start

C
2

10

4
4

0
0

E
4

F
3

LS/LF Times for


Milwaukee Paper
7

13

13

13

8
8

G
5

H
2

15

15

Start

C
2

10

13

13

Figure 3.12

B
3

D
4

E
4

7
13

13

13

H
2

15
15

13
13

Figure 3.12

2006 Prentice Hall, Inc.

3 74

2006 Prentice Hall, Inc.

Computing Slack Time

Computing Slack Time

After computing the ES, EF, LS, and LF times


for all activities, compute the slack or free
time for each activity

Activity

A
B
C
D
E
F
G
H

Slack is the length of time an activity can


be delayed without delaying the entire
project
Slack = LS ES

or

3 75

Slack = LF EF

Earliest Earliest
Start
Finish
ES
EF

0
0
2
3
4
4
8
13

2
3
4
7
8
7
13
15

Latest
Start
LS

Latest
Finish
LF

Slack
LS ES

On
Critical
Path

0
1
2
4
4
10
8
13

2
4
4
8
8
13
13
15

0
1
0
1
0
6
0
0

Yes
No
Yes
No
Yes
No
Yes
Yes
Table 3.3

2006 Prentice Hall, Inc.

3 76

2006 Prentice Hall, Inc.

Critical Path for


Milwaukee Paper
0
0
0
0

Start

A
2

C
2

10

0
1

B
3

D
4

E
4

F
3

ES EF Gantt Chart
for Milwaukee Paper
1

7
13

13

10

11 12 13 14 15 16

C Construct collection
stack

15

D Pour concrete and


install frame

15

E Build hightemperature burner

13

F Install pollution
control system

13

G Install air pollution


device
H Inspect and test

Figure 3.13
2006 Prentice Hall, Inc.

B Modify roof and floor

13

A Build internal
components

3 77

3 78

2006 Prentice Hall, Inc.

3 79

Rozlina C23-227

15/11/2014

LS LF Gantt Chart
for Milwaukee Paper
1

10

Variability in Activity Times

11 12 13 14 15 16

CPM assumes we know a fixed time


estimate for each activity and there
is no variability in activity times

A Build internal
components
B Modify roof and floor
C Construct collection
stack

PERT uses a probability distribution


for activity times to allow for
variability

D Pour concrete and


install frame
E Build hightemperature burner
F Install pollution
control system
G Install air pollution
device
H Inspect and test
2006 Prentice Hall, Inc.

3 80

Activity Preceding

Time

2006 Prentice Hall, Inc.

3 81

Activity

Preceding

--

Duration

12

--

--

A, B

C, F

G, I

E, J

2006 Prentice Hall, Inc.

3 114

2006 Prentice Hall, Inc.

3 116

2006 Prentice Hall, Inc.

3 115

Vous aimerez peut-être aussi