QC PROCEDURE - BORED PILE WORK


CHECK
RANDOM CHECK
S SURVEYOR

Flow of Activities

Check item

Method of measure

Check Frequency

Position

Theodolite

All

As per drawing

Bore location sequence

Casting record

All

Radius 3m from casted bore pile which


less then 2 days strength

Embankment

Visual

All

To retain the water flow to adjacent

Collection pit

Visual

All

To pump back to collection pit

Rebar fabrication

Visual

All

As per drawing

Concrete cover

Visual

Random

Sufficient spacer and cover i.e.75mm

Tremie Pipe

Visual

Random

Clean condition

Casing

Reference peg

All

Verticality 1/100. Final position + 75mm

Water in bore hole

Visual

Random

Water level min. 2m above ground water


level i.e.RL -3m or up to ground level to
control

Drilling bar

Spirit Level

Random

Verticality 1/500

Drilling depth

Tape

All

As per design requirement

Sediment

Time

All

Toe depth

Record

Length

Pre - Installation

Specification/Criteria

Record

Check list

SV SUPERVISOR
S SURVEYOR

QC

SV

REMARK

Check list

Check list

Check list

Bore piling

Check Sheet

Allow min.30min for sediment to settle


before final bore hole cleaning

Check list

All

min.200 above bore hole toe

Check list

Record

All

As per specification

Check list

Lapping

Measure

All

As per specification i.e. 40D

Check list

Joint

Visual

Random

Spot weld

Install tremie pipe

Nos. of pipe

All

max. 200mm above toe level

Water plunger

Visual

All

Before casting

Concrete

Slump

Random

Slump 16 + 2

Travel time

Batching record

Random

Max. 2hrs

Tremie pipe

Tape

Random

Min.1.5m below concrete upper surface

Casting height

Tape

All

Cut of level + 1m

Extract casing

Visual

Random

Remove soon after complete casting

Cleaning tremie pipe

Visual

Random

Soon after remove from concrete

Curing

Casting record

All

Min.7 days strength before allow for


excavation

Back fill blind hole

Visual

All

After concrete age >12 hrs

Rebar installation

Check Sheet

Concreting

Cleaning & Curing

Excavation & pile head


treatment

Check Sheet

Check Sheet

INSPECTION CHECKLIST - BOREPILING WORK

PROJECT : SENAYAN SQUARE OFFICE TOWER 3

DATE :

SUB-CONTRACTOR :
PILE NO.

NO.

ITEMS TO BE CHECKED

Pre-Installation
a) Peg position
b) Bore location 6m from new casted pile
c) Collection pit
d) Rebar cage
e) Concrete cover ; 75mm
Bore piling
a) Casing position
b) Kelly bar verticality
c) Toe Level ; RL -30m
d) Base cleaning min.30min after
e)

Rebar Installation

Acceptable

CRITERIA /
CH'K METHOD

YES

Theodolite
Record
Visual
Dwg
Measure

NO

DATE

Sign :

Sign :

Offset line
Spirit Level

Actual :

Measure
Record

Actual :

Measure

Cage 1 : 12m

Cage 2 : 12m

Cage 3 :
f)

g)

Tremie pipe
- Cleanliness
- Top level
- Tremie total length
- Toe depth max.200mm above toe
Bore hole water level
min. 2m above ground water level

Visual
Measure
Record
Calculate
Measure

Sign :
3

Concreting G30N
a) Concrete Slump ; 18 + 2
b) Time
c) Top level ; min.1 x above cut off level
d) Concrete Volume

Actual :
Actual :
Actual :
Water level : 3m
Bore hole water level :

Sign :

Slump test
Time
Measure
Record

Actual :
Start :
Actual :
Dwg :
Differences % :

OTHER COMMENT IF ANY ;

Page 1 of 2

KI/FORM/QC/BP Rev.1

Page 1 of 2

KI/FORM/QC/BP Rev.1

ORK
Form Ref. : KI/FORM/QC/BP/01

REMARKS

( STS )

( KI )

Time :
Time :
Lapping 1 :

mm

Lapping 2 :

mm

hole water level :

Finish :
Actual

Page 1 of 2

KI/FORM/QC/BP Rev.1

Page 1 of 2

KI/FORM/QC/BP Rev.1