Académique Documents
Professionnel Documents
Culture Documents
Author:
Agenda
Initial planning
p
g
Project evaluation
C
Conclusions
l i
Francisco-Javier Rodrguez
It permits a quick evaluation of the status of projects with regards to execution timelines,
costs and tasks.
It is a unique and simple system which integrates multiple evaluations into a unique reporting
system.
e g
Being:
Francisco-Javier Rodrguez
Being:
9
Francisco-Javier Rodrguez
Project scope:
9 Full turnkeyy deployment
p y
of a number of base stations to p
provide cellular coverage
g to
rural areas in a certain country.
9 Integration of those new base stations in the existing customer network.
9 For everyone of those base stations
stations, scope includes:
Civil works.
works
Equipment installation.
Francisco-Javier Rodrguez
Time:
9 Whole project: 1 year (2012).
9 Assume 3 months as average to build (from site acquisition to customer acceptance)
ONE SINGLE base station.
Cost:
9 Contract won with a sales value of 36,000,000 (customer project budget).
9 C
Customer
t
estimates
ti t that
th t thi
this b
budget
d t could
ld cover th
the iinstallation
t ll ti off around
d 600 new
base stations (with different configurations or types):
If customer project budget is spent with less than 600 base stations, project is
considered as finished.
If 600 new base stations are built and customer project budget has not been
totallyy spent,
p , then project
p j
will continue with the installation of new base stations
till complete spending of customer project budget ( 36,000,000).
Francisco-Javier Rodrguez
So, in order to plan the project (needed if we want to apply EVM) we could assume:
9 Contract won with a sales value of 36,000,000 (customer project budget).
9 Customer estimates that this budget could cover the installation of around 600 new
base stations.
9 Simply dividing previous values, they would give an average sales value of 60,000
per base station.
9 Based on our experience, and considering the mix of the different types or
configurations for the base stations,
stations we could use an average cost of a new base
station around 45,000.
9 This would give us an acceptable 25% gross margin.
9 Our
O totall project
j
cost would
ld then
h b
be around
d 27,000,000.
2 000 000
Francisco-Javier Rodrguez
8%
22%
70%
Jan12
Feb'12
Mar'12
Apr'12
May'12
Jun'12
Jul'12
Aug'12
Aug
12
Sep'12
Oct'12
Nov'12
Dec'12
Nokia Siemens Networks
TOTAL
30
60
30
30
90
90
30
90
90
60
0
0
600
Engineering
Civil w orks,
equip. Install. &
integr.
0
0
30
0
60
30
30
60
30
30
90
30
90
90
30
90
90
30
90
90
60
90
0
60
Francisco-Javier Rodrguez
600
600
INITIAL PLANN
NING
Site acquisition
TOTAL
(Planned cost of the planned
d base stations))
(Planned n
number of new b
base stations)
INITIAL PLANN
NING
TOTAL
Jan12
Feb'12
Mar'12
Apr'12
May'12
Jun'12
Jul'12
Aug'12
Aug
12
Sep'12
Oct'12
Nov'12
Dec'12
TOTAL
Site acquisition
Engineering
Civil w orks,
equip. Install. &
integr.
TOTAL
108,000
216,000
108,000
108,000
324,000
324,000
108,000
324,000
324,000
216,000
0
0
2,160,000
0
297,000
594,000
297,000
297,000
891,000
891,000
297,000
891,000
891,000
594,000
0
5,940,000
0
0
945,000
1,890,000
945,000
945,000
2,835,000
2,835,000
945,000
2,835,000
2,835,000
1,890,000
18,900,000
108,000
513,000
1,647,000
2,295,000
1,566,000
2,160,000
3,834,000
3,456,000
2,160,000
3,942,000
3,429,000
1,890,000
27,000,000
700
90
Number of new b
base stations
500
70
60
400
50
300
40
30
200
Numb
ber of new base sta
ations (cumulative))
600
80
20
100
10
Site acquisition
Engineering
Francisco-Javier Rodrguez
Site acquisition
Engineering
BAC
25,000,000
20,000,000
15,000,000
10,000,000
5,000,000
0
Jan12
Feb'12
Mar'12
Apr'12
May'12
Jun'12
Jul'12
InitialPlanning
10
Francisco-Javier Rodrguez
Aug'12
Sep'12
Oct'12
Nov'12
Dec'12
P j t evaluation
Project
l ti
on 31
31stt J
July,
l 2012
2012:
9
11
Site acquisition
Engineering
Civil w orks,
equip. Install.
equip
Install &
integr.
30
60
30
30
90
90
30
0
30
60
30
30
90
90
0
0
30
60
30
30
90
360
330
240
Jan12
Feb'12
Mar'12
p
Apr'12
May'12
Jun'12
Jul'12
Aug'12
Sep'12
O t'12
Oct'12
Nov'12
Dec'12
TOTAL
Francisco-Javier Rodrguez
TOTAL
PLANNED VALUE
(Planned number of n
new base station
ns)
PLANNED
D VALUE
TOTAL
Jan12
Feb'12
Mar'12
Apr'12
Apr
12
May'12
Jun'12
Jul'12
Aug'12
Sep'12
O t'12
Oct'12
Nov'12
Dec'12
TOTAL
Site acquisition
Engineering
Civil w orks,
equip. Install.
equip
Install &
integr.
TOTAL
108,000
216,000
108,000
108 000
108,000
324,000
324,000
108,000
0
0
0
0
0
1,296,000
0
297,000
594,000
297 000
297,000
297,000
891,000
891,000
0
0
0
0
0
3,267,000
0
0
945,000
1 890 000
1,890,000
945,000
945,000
2,835,000
0
0
0
0
0
7,560,000
108,000
513,000
1,647,000
2 295 000
2,295,000
1,566,000
2,160,000
3,834,000
0
0
0
0
0
12,123,000
12
TOTAL
TOTAL
Site acquisition
Engineering
Civil w orks,
equip. Install.
equip
Install &
integr.
26
53
15
36
81
93
26
0
26
53
15
36
81
93
0
0
26
53
15
36
81
330
304
211
Jan12
Feb'12
Mar'12
Apr'12
Apr
12
May'12
Jun'12
Jul'12
Aug'12
Sep'12
O t'12
Oct'12
Nov'12
Dec'12
TOTAL
Francisco-Javier Rodrguez
(Budg
geted value of the completed bas
se
stations)
EARNED V
VALUE
EARNED V
VALUE
Jan12
Feb'12
Mar'12
Apr'12
Apr
12
May'12
Jun'12
Jul'12
Aug'12
Sep'12
O t'12
Oct'12
Nov'12
Dec'12
TOTAL
Site acquisition
Engineering
Civil w orks,
equip. Install.
equip
Install &
integr.
TOTAL
93,600
190,800
54,000
129 600
129,600
291,600
334,800
93,600
0
0
0
0
0
1,188,000
0
257,400
524,700
148 500
148,500
356,400
801,900
920,700
0
0
0
0
0
3,009,600
0
0
819,000
1 669 500
1,669,500
472,500
1,134,000
2,551,500
0
0
0
0
0
6,646,500
93,600
448,200
1,397,700
1 947 600
1,947,600
1,120,500
2,270,700
3,565,800
0
0
0
0
0
10,844,100
13
TOTAL
TOTAL
Site acquisition
Engineering
Civil w orks,
equip. Install.
equip
Install &
integr.
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Jan12
Feb'12
Mar'12
Apr'12
Apr
12
May'12
Jun'12
Jul'12
Aug'12
Sep'12
O t'12
Oct'12
Nov'12
Dec'12
TOTAL
Francisco-Javier Rodrguez
(Actual c
cost of the comp
pleted base statiions)
ACTUAL COST
ACTUAL COST
Jan12
Feb'12
Mar'12
Apr'12
Apr
12
May'12
Jun'12
Jul'12
Aug'12
Sep'12
O t'12
Oct'12
Nov'12
Dec'12
TOTAL
Site acquisition
Engineering
Civil w orks,
equip. Install.
equip
Install &
integr.
TOTAL
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
85,468
433,445
1,184,209
1 974 302
1,974,302
870,898
2,101,607
3,241,904
9,891,833
25 000 000
25,000,000
20,000,000
15,000,000
10,000,000
5,000,000
Initial Planning
14
Francisco-Javier Rodrguez
PLANNED VALUE
EARNED VALUE
ACTUAL COST
15
1.5
0.5
Red-Low
15
Francisco-Javier Rodrguez
Green-High
Green-Low
Red-High
CPI
SPI
Whatt if,
Wh
if once completed
l t d a project
j t evaluation,
l ti
we realice
li that
th t the
th final
fi l number
b off
completed sites is going to be, lets say 500 (instead of the 600 initially planned) ?
In order to keep
p on using
g EVM indicators,, we could rebaseline the p
project
j
with an
updated average planned cost per site and with the new number of planned
sites.
If doing that,
that we would guarantee that SPI,
SPI upon project completion,
completion will continue
tending to 1.
Upon project
completion
l ti
16
Francisco-Javier Rodrguez
Butt we could
B
ld also
l decide
d id to
t keep
k
(for
(f reporting
ti purposes)) the
th initial
i iti l number
b off
planned sites with the initial average planned cost per site.
If doing that, we should use the new average planned cost per site from the
rebaseline date onwards and only in the upper part of the SPI equation.
By doing it in this way, we would still guarantee that SPI, upon project
completion,
p
, will continue tending
g to 1.
Upon project
completion
17
Francisco-Javier Rodrguez
Conclusions
18
Introduces an objective
objective measure about the status of projects.
projects
It is a unique and simple system which integrates multiple evaluations into a unique
reporting
p
g system.
y
If the Project Manager is going to use the data provided by the Finance Department
about project costs, he / she must take into account that those costs are recognized
costs (according to the agreed revenue recognition method)
method).
So, during the planning of project costs (planning phase), the Project Manager should
know (and take into account) the method that will be used to recognize those project
costs
t during
d i th
the executing
ti phase.
h
Calculation of EVM indexes (mainly CPI and SPI) will depend on the way to measure
and track the degree of project progress.
If scope is not totally defined at the beginning of the project, and we want to use EVM
in the monitoring and control phase, some assumptions should be made about the
scope,
p for instance, making
g use of average
g values for the number and type
yp of
deliverables.
Nokia Siemens Networks
Francisco-Javier Rodrguez
Author: