Vous êtes sur la page 1sur 11

PT.

MEDCO ENERGI
KERAMASAN GAS RECEIVING FACILITY

DESIGN BASIS

02-05-2008

Approved for Construction

RHM

DNU

SAS

11-04-2008

Issued for Approval

RHM

DNU

SAS

REV.

DATE

DESCRIPTION

BY

CHKD

CHKD

KELSRI

APPVD

MEDCO ENERGI

STATUS CODE :
A= Issued for Approval ; B= Approved For Construction ; C= As Built ; I= Issued for Information ;
X= Document Cancelled
Total Or Partial Reproduction And / Or Utilization of This Document Are Forbidden Without Prior Written
Authorization of The Owner

ENGINEERING PROCUREMENT
CONSTRUCTION COMMISSIONING

KRS-R-RE-001

PT. KELSRI
0708-R-RE-001

SUBCONTRACT NO. : BF 2691

STATUS

REVISION

Page 1 of 11

TABULATION OF REVISED PAGES


SHEETREVISIONSSHEET
ABCD
REVISI
ONS
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50

X
X
X
X
X
X
X
X
X
X
X
X

X
X
X
X
X
X
X
X
X
X
X
X

51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100

Page 2 of 11

KELSRI

DESIGN BASIS
0708-R-RE-001

TABLE OF CONTENTS

INDEX

Pages

1. Introduction

2. Codes & Standard

3. Unit Measurement

4. Design Data

5. Facilities Description

5.1.

Process Facilities

5.2.

Utilities

6. Design Criteria

6.1.

Design Life

6.2.

Line Sizing

6.3.

Vessel

10

6.4.

Gas Filter

10

6.5.

Relief System

10

6.6.

Flare System

10

6.7.

Compressed Air System

10

6.8.

Utility Water

11

6.9.

Fire Safety System

11

7. Control & Shutdown System

11

8. Attachment

12

Page 3 of 11

KELSRI

DESIGN BASIS
0708-R-RE-001

1. INTRODUCTION
PT Medco E&P Indonesia is planning to supply gas to PLTG
Keramasan. The supplied gas will be tied in from existing 6 pipeline
from Simpang Keramasan to PLTG Keramasan. For future additional
gas supply, 8 pipeline will be installed parallel with the existing 6
pipeline by Pertamina. In order to achieve delivered gas minimum
specification, PT Medco E&P Indonesia is planning to install a receiving
facility in the downstream of the pipeline. This receiving facility will have
functions i.e. separate liquid (condensate and water) from the gas,
minimize liquid particle diameter and measure the supplied gas for
billing purpose. This receiving facility will be named as Keramasan Gas
Receiving Facilities.
This document provides information relevant to process design basis for
Keramasan Gas Receiving Facilities.
2. CODES & STANDARD
The following is a list of general recommended practices, codes and
standard shall be used in the detailed engineering design. In addition to
these codes and standards, all Indonesian governmental and regulatory
agency requirements and regulations shall be applied. The most current
version of these codes and standards shall be used.
MES

Medco Engineering Standard

ANSI

American National Standards Institute

ASME

American Society of Mechanical Engineers

SNI

Standard National Indonesia

NACE

National Association of Corrosion Engineers

API

American Petroleum Institute

NEC

National Electric Code

NFPA

National Fire Protection Association

3. UNIT MEASUREMENT
US Customary Unit shall be used for all design, drawing and
specification. Standard conditions for process calculation are 14.7 psia
Page 4 of 11

KELSRI

DESIGN BASIS
0708-R-RE-001

and 60F. In general, the following units and abbreviations shall be


used:

Application
Area
Density
Flow Rate (Mass)
Flow Rate (Volume)
Gas

Liquid

Unit
Square Feet
Pounds per Cubic Foot
Pounds per Hour

Abbreviations
ft2
lb/ft3
lb/hr

Million Standard Cubic Feet Per day


Standard Cubic Feet per Minutes
Barrels per Day
Barrels Fluid per Day (Well or Mixed

MMscfd
SCFM
BPD

Fluid)
Barrels Water per Day (water)
Gallon per Minute
Feet
British Thermal Unit
Feet
Inch
Feet
Pound
Kilowatt
Horse Power
Pound per Square Inch
Pound per Square Inch Absolute
Pound per Square Inch Gauge
British Thermal Unit per ft per hour
Degrees Fahrenheit
Seconds
Minute
Hour
Feet per second
Barrels (Petroleum)
Cubic Feet
Gallons (US)
CentiPoise

Head
Heat
Elevation
Length
Mass
Power
Pressure
Radiation
Temperature
Time
Velocity
Volume
Viscosity

BFPD
BWPD
GPM
Ft
Btu
Ft
In
Ft
Lb
kW
HP
Psi
Psia
Psig
Btu/fr2/hr
F
Sec
Min
Hr
Fps
Bbl
ft3
Gal.
cP

4. DESIGN DATA
4.1.1.

Site Location
Keramasan Gas Receiving Facilities site location is planned at PLTG
Keramasan Companys area, Palembang, South Sumatera, Indonesia.

4.1.2.

Ambient Data
a. ambient pressure

: 14.7 psi (1 atm)


Page 5 of 11

KELSRI

DESIGN BASIS
0708-R-RE-001

b. ambient temperature
4.1.3.

: 75 100 F

Inlet Gas Data


Data of inlet gas for Keramasan Gas Receiving Facilities is referred to
PFD for Looping Pipeline Simpang Y Keramasan, supplied by
Pertamina, dated February 23, 2007 (see attachment) and listed bellow:
a. Pressure

: 450 psig

b. Temperature

: 73 F

c. Composition

: (dry basis)

COMPONENT
METHANE
ETHANE
PROPHANE
I-BUTANE
N-BUTANE
I-PENTANE
N-PENTANE
N-HEXANE
N-HEPTANE
N-OCTANE
NITROGEN
CARBON DIOXIDE
4.1.4.

UNIT
% MOL
% MOL
% MOL
% MOL
% MOL
% MOL
% MOL
% MOL
% MOL
% MOL
% MOL
% MOL

VALUE
85.36
5.64
2.81
0.38
0.45
0.18
0.13
0.03
0.00
0.00
0.00
5.00

Design Capacity
Based on Notulen Rapat Pembahasan Draft Amandemen PJBG Pusat
Listrik Keramasan dated April 19, 2007, committed gas deliverability is
22.3 BBTUD (see attachment).
Design capacity of Keramasan Gas Receiving Facilities is MMscfd of
Gas and 250 BPD of liquid.

4.1.5.

Sales Gas Specification


Specifications of sales gas for Keramasan Gas Receiving Facilities is
referred to Specifikasi Gas Bumi untuk Pusat Listrik Keramasan sesuai
PJBG (see attachment) and listed bellow:

COMPONENT
METHANE
ETHANE
PROPHANE
BUTANE
C5+
N2
CO2

UNIT
% MOL
% MOL
% MOL
% MOL
% MOL
% MOL
% MOL

VALUE
MINIMUM MAXIMUM
74
100
5
5
5
2
1
10
Page 6 of 11

KELSRI

DESIGN BASIS
0708-R-RE-001

H2S
KADAR AIR
TEMPERATURE
NILAI KALOR KOTOR
TEKANAN DI TITIK
PENYERAHAN

ppm
lb/MMSCFD
C
BTU/SCF
psig

20
950
280

2
10
40
1200
350

5. FACILITIES DESCRIPTION
5.1. Process Facilities
Keramasan process facilities consist of Gas Scrubber, Gas Filter, Metering
System, Condensate System and Flare System.
a. Gas Scrubber
Keramasan Gas Receiving Facilities receives gas from the existing 6
diameter and 3.3 km length Simpang Keramasan Keramasan pipeline
with incoming pressure of 450, approximately. The pressure of gas will be
reduced to 300 370 psig using pressure control valve before enter to gas
scrubber. Gas enters gas scrubber for gas-liquid separation process. The
function of this gas scrubber is to remove entrained liquid from the gas
stream. The gas product will pass through the top this vertical separator
with mist extractor and the design pressure is 700 psig and 160F.

b. Gas Filter
Gas from the top of gas scrubber will enter gas filter. The function of this
filter is to achieve the diameter requirement. The filtration efficiency is 99%
removal droplet @ 0.5-micron maximum solid & liquid. The gas outlet gas
filter is sent to the metering system for further handling. Design pressure
of gas filter is 700 psig @ 160F.
c. Metering System
The gas outlet filter is then measured at a gas metering system before
transferred to PLTG Keramasan. The metering system used for this
measurement is custody metering system type complete with gas
chromatography and moisture analyzer. The metering installation shall
follow AGA-3 requirement and the gas chromatography shall follow AGA-8
requirement. Design pressure of Gas Metering is 700 psig @ 160F.
d. Condensate System
Page 7 of 11

KELSRI

DESIGN BASIS
0708-R-RE-001

This system consists of condensate drum and recovery pump. Liquid


product from gas scrubber, gas filters and others will be sent to KO Drum
before transferred and stored to condensate drum. After the liquid
maintain a specific level at condensate drum, the liquid is then pumped to
an unloading truck using recovery pump.
e. Drain System
Closed drain system shall be provided to collect the entire hydrocarbon
inventory for disposal. Low point drain connections are provided at Gas
Scrubber, Filter, and Condensate Tank. Closed drain system consist of
closed drain line, header and pond.
An open drain system is also provided to collect the wash water in the
facilities areas. These are routed to the rainwater collection that completed
with control box.
f.

Flare System
Flare system is provided for safe disposal of waste hydrocarbon vapour
which are generated during plant upset, emergency and shut down
condition. Flare system consist of a flare header, flare KO drum (horizontal
type, without mist extractor), flare KO drum pump, and multiple-jet
enclosed flare complete with a flare ignition system. Flare gas is released
to flare header through Pressure Control Valve (PCV), or blow down
during emergency.

Flare gas is then sent to flare K.O. drum for liquid-gas separation. Liquid
product, drain, is transferred to condensate system using flare KO drum
pump.

5.2. Utilities
Utilities for Keramasan Receving Facilities consist of compressed air system,
electricity power, fresh water and fire safety system.
a. Compressed Air System
Compressed air system is used to produce clean, oil free and dry air for
instrument air, utility air and diaphragm pump driven. This system consists
of air compressors, air dryers and air receiver. Ambient air is compressed
using air compressor to produce compressed air. The compressed air is
then dehydrated in the air dryer. The air dryer is used to separate
Page 8 of 11

KELSRI

DESIGN BASIS
0708-R-RE-001

condensed moisture from the compressed air. Dry air is then stored at air
receiver for instrument air, utility air and air pump driver purpose.
b. Electric Power
Main electric power will be provided by PT. PLN (Persero). Emergency
electric power will be provided by the power plant contractor, PT. Asta
Keramasan Energy. UPS shall be provided for temporary power supply to
the metering system in case of power loss.
c. Utility Water
Water is used for utility purpose. A deep well be used for fresh water
source and shall be provided with water tank and plumbing system.
d. Fire Safety System
Fire safety system shall be provided for both light and heavy fire fighting.
Fire safety system for light fire case is provided by portable gas fire
extinguishers. Fire safety system for heavy fire case is provided by fusible
loop. This loop is connected with ESD system. When heavy fire case
occurs in Keramasan Gas Receiving Facilities, fusible loop will trigger
ESD system to shut down the facility.

6. DESIGN CRITERIA
6.1. Design Life
The facility is designed for a 15-year design life.
6.2. Line Sizing
Process line sizing and criteria shall refer to International API Standards, RP
14E, Recommended Practice for Design and Installation of Offshore
Production Platform Piping Systems and PT. Medco E&P Indonesia
Engineering Standard MEP-P-ES-001, Standard Specification for Piping
Material Specification.
6.3. Vessel

Page 9 of 11

KELSRI

DESIGN BASIS
0708-R-RE-001

Vessel Sizing and design criteria shall refer to International API Standards, RP
12J, Specification for Oil and Gas Separator. Vessel sizing and criteria shall
also refer to PT. Medco E&P Indonesia Engineering Standard MEP-R-ES-001,
Standard Specification for Vapor Liquid Separator. For special case, K.O.
Drum sizing shall also refer to API 521, Guide for Pressure-Relieving and
Depressuring Systems.
6.4. Gas Filter
Gas filter sizing and criteria shall refer to PT. Medco E&P Indonesia
Engineering Standard MEP-R-ES-003, Standard Specification for Fuel Gas
Separator and Filter.
6.5. Relief System
Relief gas system including relief valve and blow down calculation and criteria
shall refer to International API Standards RP 520, Sizing, Selection, and
Installation of Pressure-Relieving Devices in Refineries; Part I Sizing and
RP 521, Guide for Pressure-Relieving and Depressuring Systems.
6.6. Flare System
Flare system criteria including the ignition system shall refer to international
API STD 521, Guide for Pressure-Relieving and Depressuring Systems. Flare
system and API STD 537, Flare Details for General Refunery and
Petrochemical Service.

6.7. Compressed Air System


Criteria of all equipments included in instrument air system such as air
compressor, air filter, air dryer and air receiver shall refer to standards as
follow:
a. API STD 618, Reciprocating Compressors for Petroleum, Chemical, and
Gas Industry Services.
b. API STD 619, Rotary Type Positive Displacement Compressors for
Petroleum, Chemical, and Gas Industry Services.
c. MEP-M-ES-004, Standard Specification for Instrument Air Compressor
Package.
d. MEP-I-ES-001, Standard Specification for Engineering and Design of
Instrument System.
Page 10 of 11

KELSRI

DESIGN BASIS
0708-R-RE-001

e. API 550 & Vendor Catalogue for Air Demand Calculation.


f.

ANSI/ISA 7.0.01 1996, Quality Standard for Instrument Air.

6.8. Utility Water


Utility water criteria shall refer to local standard, i.e. PDAM Standard.
6.9. Fire Safety System
Fire safety system and fire fighting equipment shall refer to PT. Medco E&P
Indonesia Engineering Standard MEP-F-ES-001, Standard Specification for
General Fire and safety and MEP-F-ES-003, Standard Specification for
Portable & Auxiliary Fire Fighting Equipment.
7. CONTROL & SHUTDOWN SYSTEM
Control, alarm and shutdown system will use pneumatic system. New pneumatic
panel will be provided for alarm and shutdown system.
Shutdown level shall developed with initial outline of the expected hierarchy:

Unit Shutdown

Process Shutdown (PSD), which will shut off process inflow and outflow of
the facility and initiate gas inventory depressurizing.

Emergency Shutdown (ESD), which will intake process shutdown and


blowdown gas from system to annunciate fire/emergency alarm.

PSD will be triggered by push/pull button. ESD will be triggered by ESD push/pull
Button and fusible loop.

8. ATTACHMENT
A.

PFD for Looping Pipeline Simpang Y Keramasan

B.

Notulen Rapat Pembahasan Draft Amandemen PJBG Pusat Listrik


Keramasan dated April 19, 2007.

C.

Spesifikasi Gas Bumi untuk Pusat Listrik Keramasan sesuai PJBG.

Page 11 of 11

Vous aimerez peut-être aussi