Académique Documents
Professionnel Documents
Culture Documents
Date: 2010-01-26
File / dossier : 6.02.04
Edocs 3490675
____________________________________ ____________________________________
C8use(s): Activated corrosion products in the feeders in Bruce A Unit 1 became dislodged during
feeder grinding activities.
How affected:
Environment None
Other None
implications
e-docs #3489957
UCENSEE ACTIONS
Taken or in progress: An oral notification was provided to CNSC staff on January 5, 2010 once it
was determined that an action level may be exceeded, which is a licence reporting requirement. A
Preliminary Report was submitted to the CNSC on January 7, 2010.
Work in the Unit 1 vault was stopped until clean-up of the alpha contamination was complete. Workers
potentially affected by the incident have been removed from other radioactive work until additional
information regarding the exposures is obtained.
Analysis is currently underway at Chalk River Laboratories to determine the actual doses received by
the workers. This should be complete by the first week of February. In the meantime, Bruce Power
has placed alpha-sensitive monitors at strategic locations in Units 1 and 2 in order to identify any
further potential contamination.
Planned: Bruce Power will continue to update CNSC staff with new information as its obtained and
will submit a Detailed Report as per regulatory reporting requirements.
An additional alpha-sensitive monitor has been ordered for the West End Complex as an additional
barrier for monitoring.
CNSC ACTIONS
Taken or in progress: CNSC staff has been monitoring the situation, ensuring that the licensee is
aware of the extent of condition of cause of the event and that they are taking the appropriate
corrective actions.
Planned: CNSC staff will continue to monitor the situation, including the conduct of enhanced
inspection activities as well as review of the Detailed Report when submitted.
Further reporting: No
NAME SIGNATURE
PA~
Directorate- Bruce Regulatory program
Division - Director - Ken Lafreniere
,ru~ J Director General
4.1.2 Bruce Power: 10-M13 4.1.2 Bruce Power :
Bruce A Unit 4 Unanticipated Déclenchement imprévu du SAU2
SDS2 Trip de la tranche 4 de Bruce-A
e-docs #3489726
cause(s): The event was a result of the unantidpated Ch J trip while Ch G was tripped for testing.
The root cause of the Ch J trip is unknown at this time.
How affected
Environment No impact
security No impact
Other no impact
implications
UCENSEE ACTIONS
Taken or in progress:
Bruce Power staff followed procedures
• At the time of the event the Unit transient tone was sounded.
• A Power Reduction Action Guide for 5052 was completed
• 5051 was manually tripped as per procedure.
• Turbine was tripped and monitored as per procedure.
There were no human performance issues identified. Crew demonstrated very good response to the
transient. Bruce Power also determined that the operability of other units was not affected.
Due to the shutdown of the unit, Bruce Power decided at this time to complete a design change that
had just been completed in Unit 3.
CNSC ACTlONS
Taken or in progress: CNSC Site Staff reviewed Bruce Power's actions after the event and verified
that there were no unforeseen issues that occurred as a result of the trip (i.e. the station operated as
expected on initiation of 5052 trip).
Planned: Review the detailed report and root cause investigation report when they become available
to verify that the assigned Bruce Power corrective actions are appropriate.
Further reporting: The detailed report which will indude the root cause will be submitted
to the CNSC as per 5-99 procedures.
NAME SIGNATURE
Directorate - Bruce Regulatory Program Ad,'~ ::kTl 0 0, 1-f
Division - Director - Ken Lafreniere Direetor General Date