Vous êtes sur la page 1sur 30

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT


Pilar Street, Zamboanga City

Project
Location
Scope of Work

:
:
:

Cost of Project

PROPOSED FEEDER LINE AT ST. AGUSTINE DRIVE


Tetuan, Zamboanga City
A. NON ENGINEERING BASIC COST
I. CONSTRUCTION SAFETY AND HEALTH PROGRAM
II. SUPERVISION
B. ENGINEERING BASIC COST
I. MOBILIZATION
II. HAULING OF MATERIALS
III. FINAL STAKING/LAY-OUTING/LINE AND GRADE
IV. PIPELAYING WORKS
1. PIPE LAYING WITH PARTIAL BACKFILLING (LAYING OF 120.00 LINEAR METER P.E TUBING FEEDER LINE)
2. FITTINGS INSTALLATION AND INTERCONNECTION
V. HYDRO-TESTING & DISINFECTION WORKS
VI. FINAL BACKFILLING & COMPACTION
VII. DEMOBILIZATION
Php

158,134.00
BILL OF MATERIALS & COST ESTIMATES

Item Description
A. NON ENGINEERING BASIC COST
I. CONSTRUCTION SAFETY AND HEALTH PROGRAM
1. PROJECT SIGNAGE:
a. Materials:
1.20m x 2.40m Tarpaulin (Project Signage) Including Layout
6 - pcs. 2" x 2" x 10' Coco Lumber
10 - pcs. 2" x 3" x 10' Coco Lumber
12mm Thk x 1.20m x 2.40m Ordinary Plywood
3" C.W. Nail
4" C.W. Nail
2. BARRICADES:
A-Frame Barricade (24 pcs.)
a. Materials:
16 - pcs. 2"x 2"x 10' Coco Lumber
12mm Thk x 1.20m x 2.40m Ordinary Plywood
3" C.W. Nail
4" C.W. Nail
Gloss Latex Paint (Caterpillar Yellow)
Gloss Latex Paint (Black)
Baby Roller w/ Tray
2" Paint Brush
4" Paint Brush
3" Width Reflectorized Sticker
Pole Barricade (20 pcs.)
7 - pcs. 2" x 2" x 12' Coco Lumber
Portland Cement
Washed Sand
Gravel (G1)
Reflectorized Caution Tape, 3"W x 1000 ft./roll
b. Labor:
1 - Skilled Worker
4 - Contractual Laborers
TOTAL DIRECT COST OF CONSTRUCTION SAFETY AND HEALTH PROGRAM
II. SUPERVISION
Engineering Assistant
TOTAL DIRECT COST OF SUPERVISION
B. ENGINEERING BASIC COST
I. MOBILIZATION

Qty.

Unit

Unit Cost

1
20
50
1
1
1

unit
bd.ft.
bd.ft.
sht.
kg.
kg.

1,200.00
22.00
22.00
825.00
65.00
65.00

53
1
2
2
1
1
1
1
1
12

bd.ft.
sht.
kgs.
kgs.
gal.
gal.
pc.
pc.
pcs.
ln.ft.

22.00
825.00
65.00
65.00
600.00
600.00
110.00
28.00
40.00
39.00

28
1
2
3
1

bd.ft.
bag
bags
bags
roll

22.00
235.00
30.00
30.00
1,650.00

2
2

days
days

366.00
317.00

14

days

524.00

Page 1 of 30

lot

5,000.00

TOTAL COST OF MOBILIZATION


II. HAULING OF MATERIALS
a. Labor:
4 - Contractual Laborer
b. Equipment Rental/Fuel:
1 - Unit - Dump Truck w/ Operator
Diesel Fuel
TOTAL DIRECT COST OF HAULING OF MATERIALS
III. FINAL STAKING/LAY-OUTING/LINE AND GRADE
a. Labor:
1 - Skilled Worker
2 - Contractual Laborers
TOTAL DIRECT COST OF FINAL STAKING/LAY-OUTING/LINE AND GRADE

Page 2 of 30

days

317.00

2
53

days
liters

10,816.00
49.00

1
1

day
day

366.00
317.00

IV. PIPELAYING WORKS


1. PIPE LAYING WITH PARTIAL BACKFILLING (LAYING OF 120.00 LINEAR METER P.E TUBING FEEDER LINE)
a. Materials:
50mm x 60.0m P.E Tubing, SDR 11
50mm C.I Sleeve Type Flexible Coupling, (Std.)
Sand Envelop
Washed Sand
Concrete Thrust Block and Concrete Pad
Portland Cement
Washed Sand
Gravel (GI)
12mm x 6.00m Deformed Rein. Steel Bar (Grade 20)
b. Labor:
1 - Pipe Fitter
6 - Contractual Laborers
TOTAL DIRECT COST FOR PIPELAYING W/ PARTIAL BACKFILLING
2. FITTINGS INSTALLATION AND INTERCONNECTION
a. Material:
150mm x 6.00m PVC Pipe, Class 150, B/S, w/ R.R.
150mm C.I. Valve Cover
50mm C.I Body Gate Valve, PN16, NRS, F/F, Flanged End Dimension
in accordance w/ ANSI B16.1 Class 125
50mm x 50mm C.I Tee, M/F, Flange End Dimension in accordance
w/ ANSI B16.1 Class 125
50mm C.I Adaptor, F/P, Flange End Dimension in accordance
w/ ANSI B16.1 Class 125
50mm C.I Sleeve Type Flexible Coupling, (Std.)
16mm x 75mm Hex. Head Stainless Bolt w/ Nut & Washer
6mm thk. Rubber Gasket
b. Labor:
1 - Pipefitter
4 - Contractual Laborers
TOTAL DIRECT COST FOR FITTINGS INSTALLATION & INTERCONNECTION
V. HYDRO-TESTING & DISINFECTION WORKS
a. Materials:
Chlorine Granules
Potable Water
50mm C.I Mechanical End Cap
50mm x 19mm Saddle Clamp w/ Stainless Bolt, Nut & Washer & Rubber
19mm Brass Corporation Cock, (ISO)
19mm G.I Plug
25mm Teflon Tape
b. Labor:
1 - Pipe Fitter
4 - Contractual Laborers
c. Equipment Rental/Fuel:
1 - Unit - Hydro Machine
Premium Gasoline
Engine Oil
TOTAL DIRECT COST HYDRO-TESTING & DISINFECTION WORKS
VI. FINAL BACKFILLING & COMPACTION
a. Labor:
1 - Skilled Worker
4 - Contractual Laborers
b. Equipment Rental/Fuel:
1 - Unit - Tamper Rammer Machine
Premium Gasoline
TOTAL DIRECT COST OF FINAL BACKFILLING & COMPACTION
VII. DEMOBILIZATION
TOTAL DIRECT COST OF DEMOBILIZATION

2
2

rolls
pcs.

8,316.00
732.00

19

cu.m

1,000.00

5
0
1
1

bags
cu.m
cu.m
pc.

235.00
1,000.00
1,000.00
243.00

12
14

days
days

341.00
317.00

1
1

pc.
pc.

2,778.00
990.00

pc.

3,422.00

pc.

1,416.00

1
1
12
1

pc.
pc.
pcs.
kg.

1,120.00
732.00
110.00
75.00

1
1

day
day

341.00
317.00

kg.
cu.m
pcs.
sets
pcs.
pcs.
pcs.

250.00
54.00
650.00
243.00
494.00
25.00
30.00

1
1

day
day

341.00
317.00

1
3
1

day
ltrs.
ltr.

500.00
60.00
120.00

11
8

days
days

366.00
317.00

3
18

days
ltrs.

1,000.00
60.00

lot

5,000.00

0.10
1
2
2
2
2
2

Page 3 of 30

Page 4 of 30

SUMMARY
A. NON ENGINEERING BASIC COST
I. CONSTRUCTION SAFETY AND HEALTH PROGRAM
II. SUPERVISION
B. ENGINEERING BASIC COST
I. MOBILIZATION
II. HAULING OF MATERIALS
III. FINAL STAKING/LAY-OUTING/LINE AND GRADE
IV. PIPELAYING WORKS
1. PIPE LAYING WITH PARTIAL BACKFILLING (LAYING OF 120.00 LINEAR METER P.E TUBING FEEDER LINE)
2. FITTINGS INSTALLATION AND INTERCONNECTION
V. HYDRO-TESTING & DISINFECTION WORKS
VI. FINAL BACKFILLING & COMPACTION
VII. DEMOBILIZATION
SUB TOTAL
OVERHEAD EXPENSES
PRICE & PHYSICAL CONTINGENCIES
MISCELLANEOUS
TOTAL PROJECT COST

Php

Php

Prepared by:

Checked & Reviewed by:

Approved by:

MICHAELO T. MENDOZA
Researcher/Analyst A (J.O.)
Planning & Development Section

MARIE CLAIRE C. BONGO


Principal Engineer C
Planning & Development Section

MARLI P. ACOSTA-D
Officer-In-Charge
Planning & Design Div

Recomending Project Implementation:

Approved for Project Implementa

ARNULFO A. ALFONSO
Department Manager C
Maintenance Department

LEONARDO REY D. VASQUEZ


General Manager

Page 5 of 30

public of the Philippines


NGA CITY WATER DISTRICT
Street, Zamboanga City

G (LAYING OF 120.00 LINEAR METER P.E TUBING FEEDER LINE)

& COST ESTIMATES


Total Cost

1,200.00
440.00
1,100.00
825.00
65.00
65.00

3,695.00

1,166.00
825.00
130.00
130.00
600.00
600.00
110.00
28.00
40.00
468.00

4,097.00

616.00
235.00
60.00
90.00
1,650.00

2,651.00

732.00
2,536.00
Php

3,268.00
13,711.00

7,336.00
Php

7,336.00
7,336.00

5,000.00

5,000.00

Page 6 of 30

Php

5,000.00

2,536.00

2,536.00

21,632.00
2,597.00
Php

24,229.00
26,765.00

366.00
634.00
Php

1,000.00
1,000.00

Page 7 of 30

16,632.00
1,464.00

18,096.00

19,000.00

19,000.00

1,175.00
250.00
500.00
243.00

2,168.00

4,092.00
26,628.00
Php

30,720.00
51,888.00

2,778.00
990.00
3,422.00
1,416.00
1,120.00
732.00
1,320.00
75.00

11,853.00

341.00
1,268.00
Php

1,609.00
13,462.00

25.00
54.00
1,300.00
486.00
988.00
50.00
60.00

2,963.00

341.00
1,268.00

1,609.00

500.00
180.00
120.00
Php

800.00
5,372.00

4,026.00
10,144.00

10,144.00

3,000.00
1,080.00
Php

4,080.00
14,224.00

5,000.00
Php

5,000.00
5,000.00

Page 8 of 30

Page 9 of 30

SUMMARY

13,711.00
7,336.00
5,000.00
26,765.00
1,000.00
51,888.00
13,462.00
5,372.00
14,224.00
5,000.00
143,758.00
7,187.90
5,750.32
1,437.58
158,134.00

Php

Approved by:

MARLI P. ACOSTA-DE FIESTA


Officer-In-Charge
Planning & Design Division

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ

Page 10 of 30

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT


Pilar St., Zamboanga City

GANTT CHART
Project
Location
Project Cost
Project Duration
Manpower Requirements

:
:
:
:
:

PROPOSED FEEDER LINE AT ST. AGUSTINE DRIVE


Tetuan, Zamboanga City

Php158,134.00
Fourteen (14) CALENDAR DAYS
13 MANPOWER (10 - Laborers, 1- Engineering Assistant, 1 - Pipe Fitter, 1 - Skilled Worker)

Particulars

Amounts

A. NON ENGINEERING BASIC COST


I. CONSTRUCTION SAFETY AND HEALTH PROGRAM
II. SUPERVISION
B. ENGINEERING BASIC COST
I. MOBILIZATION
II. HAULING OF MATERIALS
III. FINAL STAKING/LAY-OUTING/LINE AND GRADE
IV. PIPELAYING WORKS
1. PIPE LAYING WITH PARTIAL BACKFILLING (LAYING OF 120.00 LINEAR METER P.E TUBING FEEDER LINE)
2. FITTINGS INSTALLATION AND INTERCONNECTION
V. HYDRO-TESTING & DISINFECTION WORKS
VI. FINAL BACKFILLING & COMPACTION
VII. DEMOBILIZATION
OVERHEAD EXPENSES
PRICE & PHYSICAL CONTINGENCIES
MISCELLANEOUS

13,711.00
7,336.00

Php
Php
Php

5,000.00
26,765.00
1,000.00

Php
Php
Php
Php
Php
Php
Php
Php

51,888.00
13,462.00
5,372.00
14,224.00
5,000.00
7,187.90
5,750.32
1,437.58

Php

TOTAL PROJECT COST


CASH OUTLAY REQUIREMENT
TARGETED COMPLETION THIS PERIOD
COMMULATIVE COMPLETION TO DATE
Prepared by:

Php
Php

Checked and Reviewed by:

Approved by:

MARLI P. ACOSTA - DE FIESTA

158,134.00

Recommending Project Implemen

MICHAELO T. MENDOZA

MARIE CLAIRE C. BONGO

Researcher/Analyst A, (J.O.)

Principal Engineer C

Officer-In-Charge

Department Manager C

Planning and Development Section

Planning and Development Section

Planning and Design Division

Maintenance Departmen

Page 1 of 1

ARNULFO A. ALFONS

ublic of the Philippines

GA CITY WATER DISTRICT

ar St., Zamboanga City

CALENDAR DAYS

%
Perfected

15

8.67%
4.64%

###

3.16%
16.93%
0.63%

###

32.81%
8.51%
3.40%
8.99%
3.16%
4.55%
3.64%
0.91%

###

###
###
###
###
###
###
###
###
###
###

100%
Php158,133.80
100.00%
100.00%
Recommending Project Implementation:

ARNULFO A. ALFONSO
Department Manager C

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ


General Manager

Maintenance Department

Page 1 of 1

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
Project
Location
Scope of Work

:
:
:

PROPOSED PIPE EXTENSION AT BUENAGATAS


Zone III and Zone IV, Boalan, Zamboanga City
A. NON ENGINEERING BASIC COST
I. CONSTRUCTION AND PUBLIC SAFETY
II. SUPERVISION
B. ENGINEERING BASIC COST
I. MOBILIZATION
II. HAULING OF MATERIALS
III. FINAL STAKING/LAY-OUTING/LINE AND GRADE
IV. CONCRETE CUTTING & CONCRETE BREAKING (225.00 Linear meters of Concrete Cutting & Breaking)
V. PIPELAYING WORKS
1. Pipe Laying w/ Partial Backfilling (Laying of 950.00 linear meter PVC Pipeline)
2. Fittings Installation & Interconnection
3. Installation of One (1) unit 75mm Fire Hydrants w/ Concrete Barricade
VI. HYDRO-TESTING & DISINFECTION WORKS
VII. FINAL BACKFILLING & COMPACTION
VIII. RESTORATION WORKS
IX. DEMOBILIZATION

Cost of Project

Php

1,338,193.00
BILL OF MATERIALS & COST ESTIMATES

Item Description
A. NON ENGINEERING BASIC COST
I. CONSTRUCTION AND PUBLIC SAFETY
1. PROJECT SIGNAGE:
a. Materials:
1.20m x 2.40m Tarpaulin (Project Signage) Including Layout
6 - pcs. 2" x 2" x 10' Coco Lumber
10 - pcs. 2" x 3" x 10' Coco Lumber
12mm Thk x 1.20m x 2.40m Ordinary Plywood
3" C.W. Nail
4" C.W. Nail
b. Labor:
1 - Carpenter
2 - Contractual Laborer

Qty.

Unit

1
20
50
1
1
1

unit
bd.ft.
bd.ft.
sht.
kg.
kg.

1 day
1 day

2. BARRICADES:
A-Frame Barricade (24 pcs.)
a. Materials:
32 - pcs. 2"x 2"x 10' Coco Lumber
12mm Thk x 1.20m x 2.40m Ordinary Plywood
3" C.W. Nail
4" C.W. Nail
Gloss Latex Paint (Caterpillar Yellow)
Gloss Latex Paint (Lamp Black)
Baby Roller w/ Tray
2" Paint Brush
3" Paint Brush
3" Width Reflectorized Sticker
Pole Barricade (40 pcs.)
Portland Cement
Washed Sand
Gravel (G1)
Caution Tape, 3"W x 1000 ft./roll
14 - pcs. 2" x 2" x 12' Coco Lumber
b. Labor:
1 - Carpenter
1 - Painter
2 - Contractual Laborer

Page 13 of 30

Unit Cost

1,200.00
20.00
20.00
750.00
65.00
65.00

366.00
317.00

128
2
2
2
1
1
1
2
1
24

bd.ft.
shts.
kgs.
kgs.
gal.
gal.
pc.
pcs.
pcs.
ln.ft.

20.00
750.00
65.00
65.00
600.00
600.00
98.00
20.00
40.00
35.00

2
4
6
1
56

bags
bags
bags
roll
bd.ft.

230.00
30.00
30.00
1,400.00
20.00

4 days
4 days
4 days

366.00
317.00
317.00

TOTAL DIRECT COST OF CONSTRUCTION AND PUBLIC SAFETY


II. SUPERVISION
Engineering Assistant
TOTAL DIRECT COST OF SUPERVISION

40 days

B. ENGINEERING BASIC COST


I. MOBILIZATION
TOTAL COST OF MOBILIZATION

1 lot

II. HAULING OF MATERIALS


a. Labor:
4 - Contractual Laborer

12 days

Page 14 of 30

524.00

10,000.00

317.00

b. Equipment Rental/Fuel:
1 - Unit - Boom Truck w/ Driver
1 - Unit - Dump Truck w/ Driver
Diesel Fuel
TOTAL DIRECT COST OF HAULING OF MATERIALS
III. FINAL STAKING/LAY-OUTING/LINE AND GRADE
a. Labor:
1 - Pipe fitter
2 - Contractual Laborers
TOTAL DIRECT COST OF FINAL STAKING/LAY-OUTING/LINE AND GRADE
IV. CONCRETE CUTTING & CONCRETE BREAKING (225.00 Linear meters of Concrete Cutting & Breaking)
1. Concrete Cutting (450.00 Linear Meter)
a. Labor:
1 - Operator
2 - Contractual Laborers
b. Equipment Rental/Fuel:
1 - Unit Concrete Cutter
Premium Gasoline
TOTAL DIRECT COST FOR CONCRETE CUTTING
2. Concrete Breaking (92.00 Sq. Mtrs.)
a. Labor:
1 - Operator
2 - Contractual Laborers
b. Equipment Rental/Fuel:
1 - Unit Jack Hammer w/ Compressor
Diesel Fuel
TOTAL DIRECT COST FOR CONCRETE BREAKING
TOTAL DIRECT COST OF CONCRETE CUTTING & CONCRETE BREAKING
V. PIPELAYING WORKS
1. Pipe Laying w/ Partial Backfilling (Laying of 950.00 linear meter PVC Pipeline)
a. Materials:
100mm x 6.00m PVC Pipe Class 150, B/S w/ R.R.
100mm x 11.25 PVC Bend, Class 150, B/S, w/ R.R.
100mm x 45 PVC Bend, Class 150, B/S, w/ R.R.
Margarine
Sand Envelop
Washed Sand

2 days
10 days
400 liters

10,000.00
10,000.00
49.00

2 days
2 days

341.00
317.00

10 days
10 days

366.00
317.00

10 days
40 ltrs.

2,000.00
60.00

15 days
15 days

366.00
317.00

15 days
270 ltrs.

5,000.00
49.00

159
6
8
8

1,590.00
550.00
741.00
85.00

Pcs.
Pcs.
Pcs.
kgs.

180 cu.m

Concrete Thrust Block and Pad


Portland Cement
Washed Sand
Gravel (GI)
12mm x 6.00m Deformed Rein. Steel Bar

5
0.25
0.5
1

b. Labor:
1 - Pipe Fitter
30 - Contractual Laborers
TOTAL DIRECT COST FOR PIPELAYING W/ PARTIAL BACKFILLING
2. Fittings Installation & Interconnection
a. Material:
150mm x 6.00m PVC Pipe, Class 150, B/S, w/ R.R.
150mm C.I. Valve Cover
100mm C.I Body Gate Valve, PN16, NRS, F/F, Flanged End Dimension
in accordance w/ ANSI B16.1 Class 125
100mm C.I Adaptor, F/P, Flange End Dimension in accordance
w/ ANSI B16.1 Class 125
100mm C.I Sleeve Type Flexible Coupling, (C.I.-PVC)
16mm x 75mm Hex. Head Stainless Bolt w/ Nut & Washer

Page 15 of 30

1,000.00

bags
cu.m
cu.m
pc.

230.00
1,000.00
1,000.00
240.00

15 days
15 days

341.00
317.00

1 pc.
1 pc.

3,686.00
1,055.00

1 pc.

7,532.00

2 pcs.
2 pcs.
16 pcs.

2,760.00
4,051.00
85.00

6mm thk. Rubber Gasket


b. Labor:
1 - Pipefitter
2 - Contractual Laborers
TOTAL DIRECT COST FOR FITTINGS INSTALLATION & INTERCONNECTION

2 kgs.

75.00

1 day
1 day

341.00
317.00

3. Installation of One (1) unit 75mm Fire Hydrants w/ Concrete Barricade


a. Materials:
100mm x 75mm C.I. Tee, F/F , Flanged End Dimension
in accordance w/ ANSI B16.1 Class 125 w/ 1-75mm Ring Flange,
Flange End Dimension in accordance w/ ANSI B16.50 Class 150
100mm C.I Adaptor, F/P, Flange End Dimension in accordance
w/ ANSI B16.1 Class 125
Flanged End Dimension in accordance w/ AWWA C207 Class D (Std.)

1 set

3,913.00

2 pcs.

2,760.00

1 pc.

1,490.00

and 1-75mm. Ring Flange


100mm Blind Flange, Flanged End Dimension
in accordance w/ AWWA C207 Class D (Std.)

Page 16 of 30

75mm C.I. Body Gate Valve, F/F, Flanged End Dimension


in accordance w/ ANSI B16.1 Class 125

2 pcs.

4,940.00

75mm MS Ring Flange, Flanged End Dimension


in accordance w/ ANSI B16.50 Class 150
75mm Fire Hydrant Head w/ 63mm Hose Connector

6 pcs.
2 sets

1,490.00
17,000.00

75mm x 6.00m G.I. Pipe, ASTM A53-90A Heavy Gauge


75mm x 90 G.I. Elbow, ANSI B16.3 Class 150

1 pc.
2 pcs.

5,200.00
570.00

100mm C.I. Sleeve Type Flexible Coupling, (C.I - PVC)


75mm C.I. Adaptor, F/P

3 pcs.
4 pcs.
2 pcs.

1,065.00
1,475.00

20 rolls

22.00

80 pcs.
4 kgs.

85.00
75.00

150mm C.I. Telescopic Valve Cover


25mm x 10m Teflon Tape
16mm x 75mm Hex Head Stainless Bolt w/ Nut & Washer
6mm thk Rubber Gasket
Portland Cement
Washed Sand

850.00

5 bags
0.25 cu.m.

245.00
1,000.00

Grave G1
16mm x 6.00m Deformed Rein. Steel Bar

0.5 cu.m.
8 pcs.

1,000.00
450.00

12mm x 6.00m Deformed Rein. Steel Bar


10mm x 6.00m Deformed Rein. Steel Bar
Hacksaw Blade

1 pc.
4 pcs.
4 pcs.

240.00
165.00
60.00

#16 G.I. Tie-wire


Concrete Neutralizer

2 kgs.
1 gal.

86.00
300.00

Flat Latex Paint


Gloss Latex Paint (Black)

1 gal.
1 gal.

600.00
600.00

Gloss Latex Paint (Caterpillar Yellow)


Red Lead Paint

1 gal.
1 gal.

600.00
450.00

QDE Paint International Red


Paint Thinner

1 gal.
1 gal.

860.00
350.00

2" Paint Brush


1" Paint Brush

2 pcs.
2 pcs.

28.00
10.00

25mm Masking Tape


12mm thk x 1.20m x 2.40m Ordinary Plywood

2 rolls
1 sht.

25.00
750.00

3pcs. - 2" x 2" x 8' Coco Lumber


1" C.W. Nail
3" C.W. Nail

8 bd.ft.
2 kgs.
2 kgs.

20.00
65.00
65.00

4 days
4 days

341.00
317.00

b. Labor:
1 - Pipefitter
4 - Contractual Laborers
TOTAL DIRECT COST FOR ITEM 3
TOTAL DIRECT COST OF PIPE LAYING WORKS

Page 17 of 30

4. Installation of One (1) unit - Air-ReleaseE Assembly w/ Concrete Barricade


a. Materials :
100mm x 25mm Saddle Clamp w/ Stainless Bolt, Nut & Washer
25mm C.I. Air-Release Pressure Valve
150mm x 100mm G.I. Bell Reducer, Sch. 40
100mm x 6.00m G.I. Pipe, Sch. 40 (ASTM 53 - Standard)
25mm x 6.00m G.I. Pipe, Sch. 40 (ASTM 53 - Standard)
25mm x 90o G.I. Elbow, Sch. (ASTM 53 - Standard)
25mm Teflon Tape
Portland Cement (Type 1P)
Washed Sand
Gravel (G1)
Fine Sand (For Plastering)
12mm x 6.00m Deformed Rein. Steel Bars (Grade 20)
16mm x 6.00m Deformed Rein. Steel Bars (Grade 20)
#16 G.I. Tie Wire
Hacksaw Blade
Concrete Neutralizer
Flat Latex Paint (Primer)
Latex Paint Top Coat Gloss (Caterpillar Yellow)
Latex Paint Top Coat Gloss (Lamp Black)
Red Lead Paint
Quick Dry Enamel (Blue)
Paint Thinner
2" Paint Brush
25mm Masking Tape
12mm thk x 1.20m x 2.40m Ordinary Plywood
40pcs. - 2" x 2" x 8' Coco Lumber
1-1/2 C.W. Nail
2" C.W. Nail
4" C.W. Nail
b. Labor:
1 - Pipefitter
4 - Contractual Laborers
TOTAL DIRECT COST FOR ITEM 4
TOTAL DIRECT COST OF PIPE LAYING WORKS
VI. HYDRO-TESTING & DISINFECTION WORKS
a. Materials:
Chlorine Granules
Potable Water
100mm C.I Mechanical End Cap
1000mm x 19mm C.I Saddle Clamp
w/ Stainless Bolts, Nuts & Waher, w/ Rubber
19mm Brass Corporation Cock, (ISO)
19mm G.I Plug
25mm Teflon Tape
b. Labor:
1 - Pipe Fitter
4 - Contractual Laborers
c. Equipment Rental/Fuel:
1 - Unit Hydro Machine
Premium Gasoline
Engine Oil
TOTAL DIRECT COST HYDRO-TESTING & DISINFECTION WORKS
VII. FINAL BACKFILLING & COMPACTION
a. Labor:
6 - Contractual Laborers
b. Equipment Rental/Fuel:
2 - Units- Tamper Rammer Machine
Premium Gasoline
TOTAL DIRECT COST OF FINAL BACKFILLING & COMPACTION

Page 18 of 30

1
1
1
1
1
2
2
5
0.25
0.5
0.5
2
4
1
6
2
1
1
1
1
1
1
2
10
6
107
2
4
4

set
set
pcs.
pcs.
pcs.
pcs.
rolls
bags
cu.m.
cu.m.
cu.m.
pcs.
pcs.
kgs.
pcs.
qrts.
gal.
gal.
gal.
gal.
gal.
gal.
pcs.
pcs.
shts.
bd.ft.
kgs.
kgs.
kgs.

435.00
16,400.00
2,160.48
3,400.00
578.00
35.00
25.00
226.00
900.00
900.00
1,200.00
240.00
410.00
60.00
60.00
85.00
470.00
600.00
600.00
440.00
416.00
360.00
28.00
25.00
750.00
20.00
65.00
65.00
65.00

1 day
1 day

341.00
317.00

0.7 kgs.
14 cu.m
2 pcs.

250.00
54.00
949.00

2 pcs.

586.00

2 pcs.
2 pcs.
2 pcs.

350.00
25.00
27.00

2 days
2 days

341.00
317.00

1 day
3 ltrs.
1 ltr.

500.00
60.00
120.00

9 days

317.00

9 days
108 ltrs.

500.00
60.00

VIII. RESTORATION WORKS


a. Materials:
23 - pcs. 1" x 6" x 8' Coco Lumber
12 - pcs. 2" x 3" x 8' Coco Lumber
3" C.W. Nail

92 bd.ft.
48 bd.ft.
2 kgs.

Portland Cement
Washed Sand
Gravel 311A

140 bags
7 cu.m.
14 cu.m.

Page 19 of 30

20.00
20.00
60.00
230.00
1,000.00
1,000.00

b. Labor:
1 - Mason
6 - Contractual Laborers
c. Equipment Rental/Fuel:
1 - Unit Bagger Mixer
Premium Gasoline
TOTAL COST OF RESTORATION WORKS

7 days
7 days

366.00
317.00

7 days
140 liters

2,000.00
60.00

IX. DEMOBILIZATION
TOTAL DIRECT COST OF DEMOBILIZATION

1 lot

10,000.00

SUMMARY
A. NON ENGINEERING BASIC COST
I. CONSTRUCTION AND PUBLIC SAFETY
II. SUPERVISION
B. ENGINEERING BASIC COST
I. MOBILIZATION
II. HAULING OF MATERIALS
III. FINAL STAKING/LAY-OUTING/LINE AND GRADE
IV. CONCRETE CUTTING & CONCRETE BREAKING (225.00 Linear meters of Concrete Cutting & Breaking)
1. Concrete Cutting (450.00 Linear Meter)
2. Concrete Breaking (92.00 Sq. Mtrs.)
V. PIPELAYING WORKS
1. Pipe Laying w/ Partial Backfilling (Laying of 950.00 linear meter PVC Pipeline)
2. Fittings Installation & Interconnection
3. Installation of One (1) unit 75mm Fire Hydrants w/ Concrete Barricade
VI. HYDRO-TESTING & DISINFECTION WORKS
VII. FINAL BACKFILLING & COMPACTION
VIII. RESTORATION WORKS
IX. DEMOBILIZATION
SUB TOTAL
OVERHEAD EXPENSES
PRICE & PHYSICAL CONTINGENCIES
MISCELLANEOUS
TOTAL PROJECT COST

Prepared by:

Php

Php

Reviewed & Checked by:

MICHAELO T. MENDOZA
Researcher/Analyst A (J.O.)

MARIE CLAIRE C. BONGO


Officer-In-Charge
Planning & Development Section

Recomending Project Implementation:

ARNULFO A. ALFONSO
Department Manager C
Maintenance Department

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ


General Manager

Page 20 of 30

1,33

Page 21 of 30

Republic of the Philippines


MBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

IALS & COST ESTIMATES


Total Cost

1,200.00
400.00
1,000.00
750.00
65.00
65.00

3,480.00

366.00
634.00

1,000.00

2,560.00
1,500.00
130.00
130.00
600.00
600.00
98.00
40.00
40.00
840.00

6,538.00

460.00
120.00
180.00
1,400.00
1,120.00

3,280.00

1,464.00
1,268.00
2,536.00

5,268.00

Page 22 of 30

Php

19,566.00

20,960.00

20,960.00
20,960.00

10,000.00

10,000.00
10,000.00

15,216.00

15,216.00

Php

Php

Page 23 of 30

20,000.00
100,000.00
19,600.00
Php

682.00
1,268.00
Php

3,660.00
6,340.00

20,000.00
2,400.00
Php

5,490.00
9,510.00

75,000.00
13,230.00
Php
Php

139,600.00
154,816.00

1,950.00
1,950.00

10,000.00

22,400.00
32,400.00

15,000.00

88,230.00
103,230.00
135,630.00

252,810.00
3,300.00
5,928.00
680.00

262,718.00

180,000.00

180,000.00

1,150.00
250.00
500.00
240.00

2,140.00

5,115.00
142,650.00
Php

3,686.00
1,055.00
7,532.00
5,520.00
8,102.00
1,360.00

Page 24 of 30

147,765.00
592,623.00

150.00

341.00
634.00
Php

3,913.00

5,520.00

1,490.00

Page 25 of 30

27,405.00

975.00
28,380.00

9,880.00
8,940.00
34,000.00
5,200.00
1,140.00
3,195.00
5,900.00
1,700.00
440.00
6,800.00
300.00
1,225.00
250.00
500.00
3,600.00
240.00
660.00
240.00
172.00
300.00
600.00
600.00
600.00
450.00
860.00
350.00
56.00
20.00
50.00
750.00
160.00
130.00
130.00

1,364.00
5,072.00

100,361.00

6,436.00
106,797.00
727,800.00

Php

Page 26 of 30

435.00
16,400.00
2,160.48
3,400.00
578.00
70.00
50.00
1,130.00
225.00
450.00
600.00
480.00
1,640.00
60.00
360.00
170.00
470.00
600.00
600.00
440.00
416.00
360.00
56.00
250.00
4,500.00
2,140.00
130.00
260.00
260.00

38,690.48

341.00
1,268.00

1,609.00
40,299.48
40,299.48

Php

175.00
756.00
1,898.00
1,172.00
700.00
50.00
54.00

4,805.00

682.00
2,536.00

3,218.00

500.00
180.00
120.00

800.00
8,823.00

Php

17,118.00

17,118.00

9,000.00
6,480.00
Php

15,480.00
32,598.00

Page 27 of 30

1,840.00
960.00
120.00
32,200.00
7,000.00
14,000.00

Page 28 of 30

56,120.00

2,562.00
13,314.00

15,876.00

14,000.00
8,400.00
Php

22,400.00
94,396.00

10,000.00
Php

10,000.00
10,000.00

SUMMARY

19,566.00
20,960.00
10,000.00
154,816.00
1,950.00
32,400.00
103,230.00
592,623.00
28,380.00
106,797.00
8,823.00
32,598.00
94,396.00
10,000.00
1,216,539.00
60,826.95
48,661.56
12,165.39
Php

1,338,193.00

Approved by:

MARLI P. ACOSTA-DE FIESTA


Officer-In-Charge
Planning & Design Division

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ

Page 29 of 30

Page 30 of 30

Vous aimerez peut-être aussi