Vous êtes sur la page 1sur 35

Project ID: IAD-HC13/14C076G.

Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

SEWER EXTENS
EXTENSION & HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVIS
PRELIMINARIES

Finish

Total Pocess
Delays

394 25-May-14 A 22-Jun-15 A

-184

394 25-May-14 A 22-Jun-15 A

-184

P1000

Project start

0 25-May-14 A

P1020

Project documentation

15 25-May-14 A 10-Jun-14 A

P1030

Accommodation for Engineer's Staff

15 25-May-14 A 10-Jun-14 A

P1090

Mobilisation

30 25-May-14 A 28-Jun-14 A

-15

P1021

Performance bond & insurance

30 25-May-14 A 28-Jun-14 A

P1022

Government permits/Authori approval

30 25-May-14 A 28-Jun-14 A

P1100

Surveying work

150 26-May-14 A 23-Nov-14 A

P1110

Dewatering

203 29-Jun-14 A

01-Mar-15 A

-62

P1120

Other general maintenance & facilities

215 29-Jun-14 A

15-Mar-15 A

-74

P1130

Revised Programme 02

P1080

Safety measures

285 25-May-14 A 30-Apr-15 A

-114

P1040

Engineering site facilities

271 11-Jun-14 A

02-May-15 A

-115

P1050

Contractor's site facilities

271 11-Jun-14 A

02-May-15 A

-115

P1060

Testing of work

271 11-Jun-14 A

02-May-15 A

-115

P1070

Testing of materials

271 11-Jun-14 A

02-May-15 A

-115

P1010

Project finish

22-Jun-15 A

-183

0 12-Jul-14 A

12-Jul-14 A

Total Float SI-1

SI-2

2015
Feb

Jun

Jul

0 12-Jul-14 A

SI-1

RC.1010

Changing VC pipe dia for 62% of scope (453 lm) from 200 mm to 300 mm

0 12-Jul-14 A

SI-1

00 mm

RC.1020

Additional work by adding 18% of pipe length (136 lm)

0 12-Jul-14 A

SI-1

RC.1030

Changing VC pipe dia for for all scope (105 lm) from 150 mm to 200 mm

0 12-Jul-14 A

SI-1

167 15-Jul-14 A

29-Dec-14 A

167 15-Jul-14 A

29-Dec-14 A

0 mm

RC.1040

Issuance of Excavation Permit for (15/1/28/12/6 to 15/1/28/12/5)

0 15-Jul-14 A

Ps

RC.1050

Issuance of Excavation Permit for (15/1/28/12/5 to 15/1/28/12/4)

0 15-Jul-14 A

Ps

RC.1060

Issuance of Excavation Permit for (15/1/28/12/4 to 15/1/28/12/3)

0 16-Nov-14 A

Ps

Permit for (15/1/28/12/4 to 15/1/28/12/3)

RC.1070

Issuance of Excavation Permit for (15/1/28/12/3 to 15/1/28/12/2)

0 26-Nov-14 A

Ps

on Permit for (15/1/28/12/3 to 15/1/28/12/2)

RC.1080

Issuance of Excavation Permit for (15/1/28/12/2 to 15/1/28/12/1)

0 16-Dec-14 A

Ps

xcavation Permit for (15/1/28/12/2 to 15/1/28/12/1)

RC.1090

Issuance of Excavation Permit for (Not Yet Issuued)

0 29-Dec-14 A

Ps

of Excavation Permit for (Not Yet Issuued)

135 16-Aug-14 A

SEWER IN TRENCH
TRENC PHASE-2

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Aug

Project finish

Changing RC pipe dia for all scope (618 lm) from 200 mm to 300 mm

SEWER IN TRENCH
TRENC PHASE-1

May

Revised Programme 02

RC.1000

ISSUANCE OF PER
PERMITS

Apr

0 31-Mar-15 A

CHANGE ORDER IN
INSTRUCTION NO.01

Mar

29-Dec-14 A

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 1 of 35
Data Date: 22-Jun-15

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

Total Float SI-1

SI-2

2015
Feb

Mar

Apr

May

Jun

Jul

RC.1110

Issuance of Excavation Permit for (15/1/28/15 to 15/1/28/14)

0 16-Aug-14 A

Ps

8/14)

RC.1100

Issuance of Excavation Permit for (15/1/28/16 to 15/1/28/15)

0 16-Sep-14 A

Ps

6 to 15/1/28/15)

RC.1120

Issuance of Excavation Permit for (15/1/28/14 to 15/1/28/13)

0 20-Dec-14 A

Ps

Excavation Permit for (15/1/28/14 to 15/1/28/13)

RC.1130

Issuance of Excavation Permit for (Not Yet Issued)

0 29-Dec-14 A

Ps

of Excavation Permit for (Not Yet Issued)

Ps

of Excavation Permit for Whole Phase (Not Yet Issued)

0 29-Dec-14 A

SEWER IN TRENCH
TRENC PHASE-3
RC.1140

Issuance of Excavation Permit for Whole Phase (Not Yet Issued)

0 29-Dec-14 A

TIME IMPLICATED FOR


EOT3.1000

Procession of Site (Should have been poccessed on 12.April.2015)

SI2.1010

Site Instruction No 2

29-Dec-14 A

46 12-Apr-15 A

28-May-15 A

39 12-Apr-15 A

21-May-15 A

Ps

0 28-May-15 A

SI-2

99 25-May-14 A 31-Aug-14 A

ENGINEERING
SUBCONTRACTORS' PRE-QUALIFICATION
SUBCONTRACTOR
SUBMITTAL OF S
SUBCONTRACTORS' PRE-QUALIFICATION

-18

43 25-May-14 A 06-Jul-14 A

14 25-May-14 A 07-Jun-14 A

EN.S/A.SB1020

Submittal subconractor for Reinstatement

14 25-May-14 A 07-Jun-14 A

EN.S/A.SB1000

Submittal subconractor for Micro Tunneling

14 25-May-14 A 07-Jun-14 A

21 08-Jun-14 A

06-Jul-14 A

APPROVAL OF S
SUBCONTRACTORS' PRE-QUALIFICATI ON
EN.S/A.SB1030

Aproval subconractor for Micro Tunneling

21 08-Jun-14 A

06-Jul-14 A

EN.S/A.SB1010

Aproval subconractor for Reinstatement

21 08-Jun-14 A

06-Jul-14 A

METHOD STATEMENT/GENERAL
STATEM
PLANS

43 25-May-14 A 06-Jul-14 A

SUBMITTAL OF METHOD
M
STATEMENT

14 25-May-14 A 07-Jun-14 A

14 25-May-14 A 07-Jun-14 A

21 08-Jun-14 A

06-Jul-14 A

21 08-Jun-14 A

06-Jul-14 A

43 25-May-14 A 06-Jul-14 A

14 25-May-14 A 07-Jun-14 A

EN.S.M1000

Submittal of method statement

APPROVAL OF M
METHOD STATEMENT
EN.A.M1000

Approval of method statement

GENERAL PLANS
SUBMITTAL OF GENERAL
G
PLANS
EN.S.GP1000

Submittal of QA/QC plans

14 25-May-14 A 07-Jun-14 A

EN.S.GP1010

Submittal of health & safety plans

14 25-May-14 A 07-Jun-14 A

EN.S.GP1020

Submittal of Environmental plans

14 25-May-14 A 07-Jun-14 A

21 08-Jun-14 A

06-Jul-14 A

APPROVAL OF G
GENERAL PLANS
E.A.GP1000

Approval of QA/QC plans

21 08-Jun-14 A

06-Jul-14 A

E.A.GP1010

Approval of health & safety plans

21 08-Jun-14 A

06-Jul-14 A

E.A.GP1020

Approval of Environmental plans

21 08-Jun-14 A

06-Jul-14 A

64 29-Jun-14 A

31-Aug-14 A

SHOP DRAWING S
SUBMITTAL AND APPROVAL

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Site Instruction No 2

-18

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 2 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

ENSDSA1000

Shop drawing submittal

30 29-Jun-14 A

31-Jul-14 A

-18

ENSDSA1010

Shop drawing approval

21 03-Aug-14 A

31-Aug-14 A

-12

280 25-May-14 A 28-Feb-15 A

-81

55 25-May-14 A 18-Jul-14 A

-41

PROCUREMENT
MATERIAL SUBMITTAL
SUBMI

Total Float SI-1

Readymix concrete

7 25-May-14 A 31-May-14 A

EMS1010

Steel reinforcement

7 25-May-14 A 31-May-14 A

EMS10100

Pipe bedding

7 25-May-14 A 31-May-14 A

EMS1070

Epoxy Products

7 01-Jun-14 A

07-Jun-14 A

EMS1080

Tanking

7 01-Jun-14 A

07-Jun-14 A

EMS1090

Bitumen Primer

7 01-Jun-14 A

07-Jun-14 A

EMS1120

DI Manhole Cover & Frame

7 01-Jun-14 A

07-Jun-14 A

EMS1130

Surface Box

7 01-Jun-14 A

07-Jun-14 A

EMS10600

Marker/warning tape

7 01-Jun-14 A

07-Jun-14 A

EMS1100

6mm Plywood

7 01-Jun-14 A

07-Jun-14 A

EMS1040

VC Pipe & Fittings

7 12-Jul-14 A

18-Jul-14 A

-48

SI-1

EMS1050

GRP Lined RC Jacking Pipes

7 12-Jul-14 A

18-Jul-14 A

-48

SI-1

EMS1060

GRP Products

7 12-Jul-14 A

18-Jul-14 A

-48

SI-1

56 01-Jun-14 A

20-Aug-14 A

-30

EMA1000

Readymix concrete

21 01-Jun-14 A

29-Jun-14 A

EMA1010

Steel reinforcement

21 01-Jun-14 A

29-Jun-14 A

EMA10100

Pipe bedding

21 01-Jun-14 A

29-Jun-14 A

EMA1070

Epoxy Products

21 08-Jun-14 A

06-Jul-14 A

EMA1080

Tanking

21 08-Jun-14 A

06-Jul-14 A

EMA1090

Bitumen Primer

21 08-Jun-14 A

06-Jul-14 A

EMA1100

6mm Plywood

21 08-Jun-14 A

06-Jul-14 A

EMA1120

DI Manhole Cover & Frame

21 08-Jun-14 A

06-Jul-14 A

EMA1130

Surface Box

21 08-Jun-14 A

06-Jul-14 A

EMA10600

Marker/warning tape

21 08-Jun-14 A

06-Jul-14 A

EMA1050

GRP Lined RC Jacking Pipes

21 20-Jul-14 A

20-Aug-14 A

-35

SI-1

EMA1060

GRP Products

21 20-Jul-14 A

20-Aug-14 A

-35

SI-1

EMA1040

VC Pipe & Fittings

21 20-Jul-14 A

20-Aug-14 A

-35

SI-1

63 30-Jun-14 A

03-Sep-14 A

-42

PROCURE MATER
MATERIAL

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

2015
Feb

EMS1000

MATERIAL APPROVAL
APPRO

SI-2

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 3 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

Total Float SI-1

Readymix concrete

14 30-Jun-14 A

13-Jul-14 A

PMP1010

Steel reinforcement & Formwork

14 30-Jun-14 A

13-Jul-14 A

PMP10100

Pipe bedding

14 30-Jun-14 A

13-Jul-14 A

PMP1070

Epoxy Products

14 07-Jul-14 A

20-Jul-14 A

PMP1080

Tanking

14 07-Jul-14 A

20-Jul-14 A

PMP1090

Bitumen Primer

14 07-Jul-14 A

20-Jul-14 A

PMP1100

6mm Plywood

14 07-Jul-14 A

20-Jul-14 A

PMP1120

DI Manhole Cover & Frame

14 07-Jul-14 A

20-Jul-14 A

PMP1130

Surface Box

14 07-Jul-14 A

20-Jul-14 A

PMP10600

Marker/warning tape

14 07-Jul-14 A

20-Jul-14 A

PMP1040

VC Pipe & Fittings

14 21-Aug-14 A

03-Sep-14 A

-49

SI-1

PMP1060

GRP Products

14 21-Aug-14 A

03-Sep-14 A

-49

SI-1

PMP1050

GRP Lined RC Jacking Pipes

14 21-Aug-14 A

03-Sep-14 A

-49

236 30-Jun-14 A

28-Feb-15 A

-79

PMD1000

Readymix concrete

157 30-Jun-14 A

09-Dec-14 A

PMD1050

GRP Lined RC Jacking Pipes

141 21-Aug-14 A

12-Jan-15 A

-50

PMD1010

Steel reinforcement

236 30-Jun-14 A

28-Feb-15 A

-86

PMD1040

VC Pipe & Fittings

187 21-Aug-14 A

28-Feb-15 A

-91

SI-1

PMD1060

GRP Products

187 21-Aug-14 A

28-Feb-15 A

-124

SI-1

PMD1070

Epoxy Products

229 07-Jul-14 A

28-Feb-15 A

-204

PMD1080

Tanking

229 07-Jul-14 A

28-Feb-15 A

-128

PMD1090

Bitumen Primer

229 07-Jul-14 A

28-Feb-15 A

-175

PMD1100

6mm Plywood

229 07-Jul-14 A

28-Feb-15 A

-182

PMD10100

Pipe bedding

236 30-Jun-14 A

28-Feb-15 A

-222

PMD1120

DI Manhole Cover & Frame

229 07-Jul-14 A

28-Feb-15 A

-215

PMD1130

Surface Box

229 07-Jul-14 A

28-Feb-15 A

-215

PMD10600

Marker/warning tape

229 07-Jul-14 A

28-Feb-15 A

-124

359 29-Jun-14 A

22-Jun-15 A

-184

359 29-Jun-14 A

22-Jun-15 A

-196

287 29-Jun-14 A

11-Apr-15 A

-216

283 29-Jun-14 A

07-Apr-15 A

-238

219 29-Jun-14 A

19-Mar-15 A

-198

CONSTRUCTION
SEWER IN TRENCH
TRENC
PHASE 1: FROM MH 15/1/28/12/6 TO MH 15/1/28/12
VC PIPE WORKS
WORKS: FROM MH 15/1/28/12/6 TO MH 15/1/28/12
200mm NOMINAL
NOMINA BORE 33.88m: From MH 15/1/28/12/6 to MH 15/1/28/12/5

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

2015
Feb

PMP1000

MATERIAL DELIVERY
DELIVE
TO SITE

SI-2
Mar

Apr

May

Jun

Jul

SI-1

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 4 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CST1010

Excavation & disposal of materials

5 29-Jun-14 A

03-Jul-14 A

CST1020

Bedding preparation prior to VC pipe laying

2 05-Jul-14 A

06-Jul-14 A

CST1030

Laying VC pipes & fittings and pre-testing

2 12-Jul-14 A

13-Jul-14 A

CST1040

Granular & concrete surrounds

2 14-Jul-14 A

15-Jul-14 A

CST1050

Backfilling

3 16-Jul-14 A

19-Jul-14 A

CST1060

SRC 20 concrete backfill

2 20-Jul-14 A

21-Jul-14 A

CST1070

Marker tape installation

2 18-Mar-15 A

19-Mar-15 A

205 15-Jul-14 A

200mm NOMINAL
NOMINA BORE 90.09m: From MH 15/1/28/12/5 to MH 15/1/28/12/4

9 15-Jul-14 A

24-Jul-14 A

CST1940

Bedding preparation prior to VC pipe laying

2 26-Jul-14 A

27-Jul-14 A

CST1950

Laying VC pipes & fittings and pre-testing

2 31-Jul-14 A

02-Aug-14 A

CST1960

Granular & concrete surrounds

2 03-Aug-14 A

04-Aug-14 A

CST1970

Backfilling

3 05-Aug-14 A

07-Aug-14 A

CST1980

SRC 20 concrete backfill

2 09-Aug-14 A

10-Aug-14 A

CST1990

Marker tape installation

2 18-Mar-15 A

19-Mar-15 A

185 11-Aug-14 A

19-Mar-15 A

-198

CST1080

Excavation & disposal of materials

9 11-Aug-14 A

20-Aug-14 A

-34

CST1090

Bedding preparation prior to VC pipe laying

2 21-Aug-14 A

23-Aug-14 A

-34

CST1100

Laying VC pipes & fittings and pre-testing

2 24-Aug-14 A

25-Aug-14 A

-34

CST1110

Granular & concrete surrounds

2 26-Aug-14 A

27-Aug-14 A

-34

CST1120

Backfilling

3 28-Aug-14 A

31-Aug-14 A

-34

CST1130

SRC 20 concrete backfill

2 01-Sep-14 A

02-Sep-14 A

-34

CST1210

Marker tape installation

2 18-Mar-15 A

19-Mar-15 A

-198

185 11-Aug-14 A

19-Mar-15 A

-193

CST1150

Excavation & disposal of materials

5 11-Aug-14 A

16-Aug-14 A

-25

CST1160

Bedding preparation prior to VC pipe laying

2 24-Aug-14 A

25-Aug-14 A

-31

CST1170

Laying VC pipes & fittings and pre-testing

2 26-Aug-14 A

27-Aug-14 A

-31

CST1180

Granular & concrete surrounds

2 28-Aug-14 A

30-Aug-14 A

-31

CST1190

Backfilling

3 01-Sep-14 A

03-Sep-14 A

-32

CST1200

SRC 20 concrete backfill

2 04-Sep-14 A

06-Sep-14 A

-32

CST1280

Marker tape installation

2 18-Mar-15 A

19-Mar-15 A

-193

100 22-Nov-14 A

19-Mar-15 A

-183

300mm NOMINAL
NOMINA BORE 34.48m: From MH 15/1/28/12/2 to MH 15/1/28/12/1

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

2015
Feb

Mar

Apr

May

Jun

Jul

19-Mar-15 A

Excavation & disposal of materials

300mm NOMINAL
NOMINA BORE 42.20m: From MH 15/1/28/12/3 to MH 15/1/28/12/2

SI-2

-198

CST1930

300mm NOMINAL
NOMINA BORE 50.37m: From MH 15/1/28/12/4 to MH 15/1/28/12/3

Total Float SI-1

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 5 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CST1220

Excavation & disposal of materials

4 22-Nov-14 A

25-Nov-14 A

-99

CST1230

Bedding preparation prior to VC pipe laying

3 27-Nov-14 A

30-Nov-14 A

-101

CST1240

Laying VC pipes & fittings and pre-testing

2 04-Dec-14 A

06-Dec-14 A

-104

CST1250

Granular & concrete surrounds

2 09-Dec-14 A

10-Dec-14 A

-106

CST1260

Backfilling

4 10-Dec-14 A

14-Dec-14 A

-106

CST1270

SRC 20 concrete backfill

2 17-Dec-14 A

20-Dec-14 A

-108

CST1350

Marker tape installation

2 18-Mar-15 A

19-Mar-15 A

-183

88 10-Jan-15 A

07-Apr-15 A

-238

300mm NOMINAL
NOMINA BORE 59.46m: From MH 15/1/28/12/1 to MH 15/1/28/12
Recovery

0 10-Jan-15 A

CST1290

Excavation & disposal of materials

2 01-Mar-15 A

02-Mar-15 A

CST129.10

Delay: Issuance of Excavation permit

75 10-Jan-15 A

25-Mar-15 A

CST1300

Bedding preparation prior to VC pipe laying

4 28-Mar-15 A

31-Mar-15 A

-203

CST1310

Laying VC pipes & fittings and pre-testing

5 28-Mar-15 A

01-Apr-15 A

-202

CST1320

Granular & concrete surrounds

6 28-Mar-15 A

02-Apr-15 A

-201

CST1330

Backfilling

7 28-Mar-15 A

04-Apr-15 A

-199

CST1340

SRC 20 concrete backfill

8 29-Mar-15 A

06-Apr-15 A

-199

CST1420

Marker tape installation

1 07-Apr-15 A

07-Apr-15 A

-199

46 16-Feb-15 A

09-Apr-15 A

46 16-Feb-15 A

09-Apr-15 A

1 16-Mar-15 A

16-Mar-15 A

FC-01
CST2330

SRC 20 concrete backfill

CST2280

Excavation & disposal of materials

42 16-Feb-15 A

05-Apr-15 A

CST2290

Bedding preparation prior to VC pipe laying

40 18-Feb-15 A

05-Apr-15 A

CST2300

Laying VC pipes & fittings and pre-testing

39 19-Feb-15 A

05-Apr-15 A

CST2310

Granular & concrete surrounds

38 21-Feb-15 A

05-Apr-15 A

CST2320

Backfilling

38 22-Feb-15 A

06-Apr-15 A

CST2340

Marker tape installation

2 08-Apr-15 A

09-Apr-15 A

MANHOLE CONSTRUCTION
CONS
MANHOLE: 15/1/28/12/6
15/1

204 26-Jul-14 A

29-Mar-15 A

-178

25 26-Jul-14 A

26-Aug-14 A

-14

Excavation & disposal of materials

4 26-Jul-14 A

02-Aug-14 A

-14

CSTM1020

Blinding

1 03-Aug-14 A

03-Aug-14 A

-14

CSTM1030

Reinforcement, shuttering, concreting

4 04-Aug-14 A

07-Aug-14 A

-14

CSTM1040

Pipe connection to manhole & pre-testing of section

2 09-Aug-14 A

10-Aug-14 A

-14

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

2015
Feb

Mar

Apr

May

Jun

Jul

-180

CSTM1010

Remaining Level of Effort

SI-2

very

CST129

FUTURE CONNE
CONNECTION

Total Float SI-1

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 6 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSTM10400

Benching work

2 11-Aug-14 A

12-Aug-14 A

-14

CSTM1050

Bitumen primer

1 13-Aug-14 A

13-Aug-14 A

-14

CSTM1060

Tanking membrane

1 14-Aug-14 A

14-Aug-14 A

-14

CSTM1070

Epoxy mortor & sealant

2 16-Aug-14 A

17-Aug-14 A

-14

CSTM1080

GRP accessories

2 18-Aug-14 A

19-Aug-14 A

-14

CSTM1090

DI Manhole Cover & Frame

2 20-Aug-14 A

21-Aug-14 A

-14

CSTM1100

Backfilling

3 23-Aug-14 A

25-Aug-14 A

-14

CSTM1330

SRC 20 concrete backfill

1 26-Aug-14 A

26-Aug-14 A

-14

25 03-Aug-14 A

31-Aug-14 A

MANHOLE: 15/1/28/12/5
15/1
CSTM28210

Excavation & disposal of materials

4 03-Aug-14 A

06-Aug-14 A

CSTM28220

Blinding

1 07-Aug-14 A

07-Aug-14 A

CSTM28230

Reinforcement, shuttering, concreting

4 09-Aug-14 A

12-Aug-14 A

CSTM28240

Pipe connection to manhole & pre-testing of section

2 13-Aug-14 A

14-Aug-14 A

CSTM28250

Benching work

2 16-Aug-14 A

17-Aug-14 A

CSTM28260

Bitumen primer

1 18-Aug-14 A

18-Aug-14 A

CSTM28270

Tanking membrane

1 19-Aug-14 A

19-Aug-14 A

CSTM28280

Epoxy mortor & sealant

2 20-Aug-14 A

21-Aug-14 A

CSTM28290

GRP accessories

2 23-Aug-14 A

24-Aug-14 A

CSTM28300

DI Manhole Cover & Frame

2 25-Aug-14 A

26-Aug-14 A

CSTM28310

Backfilling

3 27-Aug-14 A

30-Aug-14 A

CSTM28320

SRC 20 concrete backfill

1 31-Aug-14 A

31-Aug-14 A

24 21-Aug-14 A

17-Sep-14 A

-32

MANHOLE: 15/1/28/12/4
15/1
CSTM1350

Excavation & disposal of materials

4 21-Aug-14 A

25-Aug-14 A

-34

CSTM1360

Blinding

1 26-Aug-14 A

26-Aug-14 A

-34

CSTM1370

Reinforcement, shuttering, concreting

4 27-Aug-14 A

31-Aug-14 A

-34

CSTM1380

Pipe connection to manhole & pre-testing of section

2 01-Sep-14 A

02-Sep-14 A

-32

CSTM13800

Benching work

2 03-Sep-14 A

04-Sep-14 A

-32

CSTM1390

Bitumen primer

1 06-Sep-14 A

06-Sep-14 A

-32

CSTM1400

Tanking membrane

1 07-Sep-14 A

07-Sep-14 A

-32

CSTM1410

Epoxy mortor & sealant

1 08-Sep-14 A

08-Sep-14 A

-32

CSTM1420

GRP accessories

2 09-Sep-14 A

10-Sep-14 A

-32

CSTM1430

DI Manhole Cover & Frame

2 11-Sep-14 A

13-Sep-14 A

-32

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 7 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSTM1440

Backfilling

3 14-Sep-14 A

16-Sep-14 A

-32

CSTM1450

SRC 20 concrete backfill

1 17-Sep-14 A

17-Sep-14 A

-32

32 17-Aug-14 A

22-Sep-14 A

-32

MANHOLE: 15/1/28/12/3
15/1
CSTM1470

Excavation & disposal of materials

4 17-Aug-14 A

20-Aug-14 A

-25

CSTM1480

Blinding

1 28-Aug-14 A

28-Aug-14 A

-31

CSTM1490

Reinforcement, shuttering, concreting

4 01-Sep-14 A

04-Sep-14 A

-33

CSTM1500

Pipe connection to manhole & pre-testing of section

2 06-Sep-14 A

07-Sep-14 A

-32

CSTM15000

Benching work

2 08-Sep-14 A

09-Sep-14 A

-32

CSTM1510

Bitumen primer

1 10-Sep-14 A

10-Sep-14 A

-32

CSTM1520

Tanking membrane

1 11-Sep-14 A

11-Sep-14 A

-32

CSTM1530

Epoxy mortor & sealant

1 13-Sep-14 A

13-Sep-14 A

-32

CSTM1540

GRP accessories

2 14-Sep-14 A

15-Sep-14 A

-32

CSTM1550

DI Manhole Cover & Frame

2 16-Sep-14 A

17-Sep-14 A

-32

CSTM1560

Backfilling

3 18-Sep-14 A

21-Sep-14 A

-32

CSTM1570

SRC 20 concrete backfill

1 22-Sep-14 A

22-Sep-14 A

-32

27 21-Dec-14 A

20-Jan-15 A

-122

MANHOLE: 15/1/28/12/2
15/1
CSTM1690

SRC 20 concrete backfill

1 21-Dec-14 A

21-Dec-14 A

-96

CSTM1590

Excavation & disposal of materials

4 25-Dec-14 A

29-Dec-14 A

-123

CSTM1600

Blinding

1 30-Dec-14 A

30-Dec-14 A

-123

CSTM1610

Reinforcement, shuttering, concreting

4 31-Dec-14 A

04-Jan-15 A

-123

CSTM1620

Pipe connection to manhole & pre-testing of section

2 05-Jan-15 A

06-Jan-15 A

-123

CSTM16200

Benching work

2 07-Jan-15 A

08-Jan-15 A

-123

CSTM1630

Bitumen primer

1 10-Jan-15 A

10-Jan-15 A

-123

CSTM1640

Tanking membrane

1 11-Jan-15 A

11-Jan-15 A

-123

CSTM1650

Epoxy mortor & sealant

1 12-Jan-15 A

12-Jan-15 A

-123

CSTM1660

GRP accessories

2 13-Jan-15 A

14-Jan-15 A

-123

CSTM1670

DI Manhole Cover & Frame

2 15-Jan-15 A

17-Jan-15 A

-123

CSTM1680

Backfilling

3 18-Jan-15 A

20-Jan-15 A

-123

81 24-Dec-14 A

29-Mar-15 A

-178

MANHOLE: 15/1/28/12/1
15/1
CSTM1710

Excavation & disposal of materials

4 24-Dec-14 A

28-Dec-14 A

-122

CSTM1720

Blinding

2 28-Dec-14 A

29-Dec-14 A

-122

CSTM1730

Reinforcement, shuttering, concreting

4 31-Dec-14 A

04-Jan-15 A

-123

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 8 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSTM1740

Pipe connection to manhole & pre-testing of section

3 05-Jan-15 A

07-Jan-15 A

-124

CSTM17400

Benching work

2 08-Jan-15 A

10-Jan-15 A

-124

CSTM1750

Bitumen primer

1 13-Jan-15 A

13-Jan-15 A

-126

CSTM1760

Tanking membrane

1 29-Jan-15 A

29-Jan-15 A

-139

CSTM1770

Epoxy mortor & sealant

1 25-Feb-15 A

25-Feb-15 A

-160

CSTM1780

GRP accessories

2 26-Feb-15 A

28-Feb-15 A

-160

CSTM1800

Backfilling

4 24-Feb-15 A

28-Feb-15 A

-155

CSTM1790

DI Manhole Cover & Frame

3 21-Mar-15 A

23-Mar-15 A

-178

CSTM1810

SRC 20 concrete backfill

3 26-Mar-15 A

29-Mar-15 A

-178

79 25-Dec-14 A

28-Mar-15 A

MANHOLE: 15/1/28/12
15/1
CSTM28330

Excavation & disposal of materials

5 25-Dec-14 A

30-Dec-14 A

CSTM28340

Blinding

1 01-Jan-15 A

01-Jan-15 A

CSTM28350

Reinforcement, shuttering, concreting

4 03-Jan-15 A

06-Jan-15 A

CSTM28360

Pipe connection to manhole & pre-testing of section

2 07-Jan-15 A

08-Jan-15 A

CSTM28370

Benching work

2 10-Jan-15 A

11-Jan-15 A

CSTM28380

Bitumen primer

1 12-Jan-15 A

12-Jan-15 A

CSTM28390

Tanking membrane

1 13-Jan-15 A

13-Jan-15 A

CSTM28400

Epoxy mortor & sealant

2 19-Mar-15 A

21-Mar-15 A

CSTM28410

GRP accessories

3 21-Mar-15 A

23-Mar-15 A

CSTM28420

DI Manhole Cover & Frame

3 23-Mar-15 A

25-Mar-15 A

CSTM28430

Backfilling

4 24-Mar-15 A

28-Mar-15 A

CSTM28440

SRC 20 concrete backfill

2 26-Mar-15 A

28-Mar-15 A

41 23-Feb-15 A

11-Apr-15 A

-180

39 23-Feb-15 A

08-Apr-15 A

-182

REINSTATEMENT
ASPHALT
CSTR1110

90mm Base course

38 23-Feb-15 A

07-Apr-15 A

-186

CSTR1120

70mm Wearing course

27 09-Mar-15 A

08-Apr-15 A

-182

18 22-Mar-15 A

11-Apr-15 A

-186

KERBSTONE
CSTR1130

Excavation & concrete foundation for kerbs

16 22-Mar-15 A

08-Apr-15 A

-186

CSTR1140

Kerbs installation

17 22-Mar-15 A

09-Apr-15 A

-186

CSTR1150

Backing concrete

18 22-Mar-15 A

11-Apr-15 A

-186

2 18-Mar-15 A

19-Mar-15 A

-163

2 18-Mar-15 A

19-Mar-15 A

-165

PAVING/CONCRETE PAVING
PAVING/CONCR
CSTR1160

Formation preparation

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 9 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

CSTR1170

Original Start
Duration

Paving interlock

PLANT AND GRASS


GR

Finish

Total Pocess
Delays

2 18-Mar-15 A

19-Mar-15 A

-163

2 18-Mar-15 A

19-Mar-15 A

-161

CSTR1180

Excavation for plants

2 18-Mar-15 A

19-Mar-15 A

-163

CSTR1190

Planting/grass

2 18-Mar-15 A

19-Mar-15 A

-161

PHASE 2: FROM MH 15/1/18/12 TO 15/1/28/16

225 16-Aug-14 A

10-May-15 A

-162

VC PIPE WORKS:
WORKS 15/1/18/12 TO 15/1/28/16

180 16-Aug-14 A

18-Mar-15 A

-145

29 25-Jan-15 A

28-Feb-15 A

300mm NOMINAL
NOMINA BORE 56.99m: From MH 15/1/28/12 to MH 15/1/28/13
CST2030

Granular & concrete surrounds

2 29-Jan-15 A

31-Jan-15 A

CST2040

Backfilling

3 28-Jan-15 A

31-Jan-15 A

CST2050

SRC 20 concrete backfill

2 29-Jan-15 A

31-Jan-15 A

CST2000

Excavation & disposal of materials

9 25-Jan-15 A

03-Feb-15 A

CST2010

Bedding preparation prior to VC pipe laying

9 03-Feb-15 A

14-Feb-15 A

CST2020

Laying VC pipes & fittings and pre-testing

9 05-Feb-15 A

16-Feb-15 A

CST2060

Marker tape installation

25 29-Jan-15 A

28-Feb-15 A

52 01-Dec-14 A

31-Jan-15 A

300mm NOMINAL
NOMINA BORE 55.00m: From MH 15/1/28/13 to MH 15/1/28/14
CST2070

Excavation & disposal of materials

8 01-Dec-14 A

09-Dec-14 A

CST2080

Bedding preparation prior to VC pipe laying

2 10-Dec-14 A

11-Dec-14 A

CST2090

Laying VC pipes & fittings and pre-testing

3 13-Dec-14 A

15-Dec-14 A

CST2100

Granular & concrete surrounds

2 17-Dec-14 A

20-Dec-14 A

CST2110

Backfilling

4 22-Dec-14 A

25-Dec-14 A

CST2120

SRC 20 concrete backfill

2 27-Dec-14 A

28-Dec-14 A

CST2130

Marker tape installation

2 29-Jan-15 A

31-Jan-15 A

29 25-Jan-15 A

28-Feb-15 A

9 25-Jan-15 A

03-Feb-15 A

200mm NOMINAL
NOMINA BORE 36.30m: From MH 15/1/28/14 to MH 15/1/28/14/1
CST2140

Excavation & disposal of materials

CST2190

SRC 20 concrete backfill

10 14-Feb-15 A

24-Feb-15 A

CST2150

Bedding preparation prior to VC pipe laying

11 11-Feb-15 A

24-Feb-15 A

CST2160

Laying VC pipes & fittings and pre-testing

11 11-Feb-15 A

24-Feb-15 A

CST2170

Granular & concrete surrounds

11 11-Feb-15 A

24-Feb-15 A

CST2180

Backfilling

10 14-Feb-15 A

24-Feb-15 A

CST2200

Marker tape installation

2 26-Feb-15 A

28-Feb-15 A

45 25-Jan-15 A

18-Mar-15 A

9 25-Jan-15 A

03-Feb-15 A

200mm NOMINAL
NOMINA BORE 41.20m: From MH 15/1/28/14/1 to MH 15/1/28/14/2
CST2210

Excavation & disposal of materials

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 10 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CST2220

Bedding preparation prior to VC pipe laying

11 11-Feb-15 A

24-Feb-15 A

CST2230

Laying VC pipes & fittings and pre-testing

11 11-Feb-15 A

24-Feb-15 A

CST2240

Granular & concrete surrounds

11 11-Feb-15 A

24-Feb-15 A

CST2250

Backfilling

11 11-Feb-15 A

24-Feb-15 A

CST2260

SRC 20 concrete backfill

10 14-Feb-15 A

24-Feb-15 A

CST2270

Marker tape installation

2 17-Mar-15 A

18-Mar-15 A

180 16-Aug-14 A

18-Mar-15 A

-148

300mm NOMINAL
NOMINA BORE 71.5m: From MH 15/1/28/14 to MH 15/1/28/15
CST1360

Excavation & disposal of materials

5 16-Aug-14 A

20-Aug-14 A

15

CST1370

Bedding preparation prior to VC pipe laying

5 26-Aug-14 A

31-Aug-14 A

CST1380

Laying VC pipes & fittings and pre-testing

3 28-Aug-14 A

31-Aug-14 A

10

CST1390

Granular & concrete surrounds

2 31-Aug-14 A

01-Sep-14 A

11

CST1400

Backfilling

3 02-Sep-14 A

04-Sep-14 A

11

CST1410

SRC 20 concrete backfill

3 06-Sep-14 A

08-Sep-14 A

10

CST1490

Marker tape installation

2 17-Mar-15 A

18-Mar-15 A

-148

153 16-Sep-14 A

18-Mar-15 A

-145

300mm NOMINAL
NOMINA BORE 60m: From MH 15/1/28/15 to MH 15/1/28/16
CST1430

Excavation & disposal of materials

134 16-Sep-14 A

24-Feb-15 A

-141

CST1440

Bedding preparation prior to VC pipe laying

130 21-Sep-14 A

24-Feb-15 A

-139

CST1450

Laying VC pipes & fittings and pre-testing

131 23-Sep-14 A

28-Feb-15 A

-140

CST1460

Granular & concrete surrounds

129 25-Sep-14 A

28-Feb-15 A

-136

CST1470

Backfilling

127 28-Sep-14 A

28-Feb-15 A

-132

CST1480

SRC 20 concrete backfill

124 01-Oct-14 A

28-Feb-15 A

-130

CST1560

Marker tape installation

2 17-Mar-15 A

18-Mar-15 A

-145

70 18-Feb-15 A

10-May-15 A

46 18-Feb-15 A

12-Apr-15 A

FUTURE CONNE
CONNECTION
FC-02
CST2350

Excavation & disposal of materials

14 18-Feb-15 A

05-Mar-15 A

CST2360

Bedding preparation prior to VC pipe laying

12 21-Feb-15 A

06-Mar-15 A

CST2370

Laying VC pipes & fittings and pre-testing

11 22-Feb-15 A

06-Mar-15 A

CST2380

Granular & concrete surrounds

11 23-Feb-15 A

07-Mar-15 A

CST2390

Backfilling

10 24-Feb-15 A

07-Mar-15 A

CST2400

SRC 20 concrete backfill

1 09-Apr-15 A

09-Apr-15 A

CST2410

Marker tape installation

2 11-Apr-15 A

12-Apr-15 A

45 21-Feb-15 A

13-Apr-15 A

FC-03

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 11 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

CST2420

Excavation & disposal of materials

12 21-Feb-15 A

06-Mar-15 A

CST2430

Bedding preparation prior to VC pipe laying

11 23-Feb-15 A

07-Mar-15 A

CST2440

Laying VC pipes & fittings and pre-testing

10 24-Feb-15 A

07-Mar-15 A

CST2450

Granular & concrete surrounds

10 25-Feb-15 A

08-Mar-15 A

CST2460

Backfilling

9 26-Feb-15 A

08-Mar-15 A

CST2470

SRC 20 concrete backfill

1 11-Apr-15 A

11-Apr-15 A

CST2480

Marker tape installation

1 12-Apr-15 A

13-Apr-15 A

66 23-Feb-15 A

10-May-15 A

FC-04
CST2490

Excavation & disposal of materials

36 23-Feb-15 A

05-Apr-15 A

CST2500

Bedding preparation prior to VC pipe laying

34 25-Feb-15 A

05-Apr-15 A

CST2510

Laying VC pipes & fittings and pre-testing

34 26-Feb-15 A

06-Apr-15 A

CST2520

Granular & concrete surrounds

33 28-Feb-15 A

06-Apr-15 A

CST2530

Backfilling

33 28-Feb-15 A

06-Apr-15 A

CST2540

SRC 20 concrete backfill

24 12-Apr-15 A

09-May-15 A

CST2550

Marker tape installation

24 13-Apr-15 A

10-May-15 A

29 08-Mar-15 A

09-Apr-15 A

FC-05
CST2560

Excavation & disposal of materials

26 08-Mar-15 A

06-Apr-15 A

CST2570

Bedding preparation prior to VC pipe laying

23 11-Mar-15 A

06-Apr-15 A

CST2580

Laying VC pipes & fittings and pre-testing

22 12-Mar-15 A

06-Apr-15 A

CST2590

Granular & concrete surrounds

21 14-Mar-15 A

06-Apr-15 A

CST2600

Backfilling

21 14-Mar-15 A

06-Apr-15 A

CST2610

SRC 20 concrete backfill

21 16-Mar-15 A

08-Apr-15 A

CST2620

Marker tape installation

20 18-Mar-15 A

09-Apr-15 A

98 01-Dec-14 A

26-Mar-15 A

73 03-Dec-14 A

28-Feb-15 A

MANHOLE CONSTRUCTION
CONS
MANHOLE: 15/1/28/13
15/1
CSTM28450

Excavation & disposal of materials

4 03-Dec-14 A

07-Dec-14 A

CSTM28460

Blinding

2 08-Dec-14 A

09-Dec-14 A

CSTM28470

Reinforcement, shuttering, concreting

5 08-Dec-14 A

13-Dec-14 A

CSTM28480

Pipe connection to manhole & pre-testing of section

3 15-Dec-14 A

17-Dec-14 A

CSTM28490

Benching work

3 20-Dec-14 A

22-Dec-14 A

CSTM28500

Bitumen primer

2 23-Dec-14 A

24-Dec-14 A

CSTM28510

Tanking membrane

1 02-Feb-15 A

02-Feb-15 A

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Pocess
Delays

Total Float SI-1

SI-2

2015
Feb

Mar

Apr

May

Jun

Jul

-140

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 12 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

CSTM28520

Epoxy mortor & sealant

1 03-Feb-15 A

03-Feb-15 A

CSTM28530

GRP accessories

2 04-Feb-15 A

05-Feb-15 A

CSTM28550

Backfilling

3 09-Feb-15 A

11-Feb-15 A

CSTM28560

SRC 20 concrete backfill

2 18-Feb-15 A

19-Feb-15 A

CSTM28540

DI Manhole Cover & Frame

2 26-Feb-15 A

28-Feb-15 A

71 04-Dec-14 A

26-Feb-15 A

MANHOLE: 15/1/28/14
15/1
CSTM28570

Excavation & disposal of materials

4 04-Dec-14 A

08-Dec-14 A

CSTM28580

Blinding

2 11-Dec-14 A

13-Dec-14 A

CSTM28590

Reinforcement, shuttering, concreting

4 14-Dec-14 A

17-Dec-14 A

CSTM28600

Pipe connection to manhole & pre-testing of section

2 17-Dec-14 A

20-Dec-14 A

CSTM28610

Benching work

3 21-Dec-14 A

23-Dec-14 A

CSTM28620

Bitumen primer

2 08-Jan-15 A

10-Jan-15 A

CSTM28630

Tanking membrane

2 12-Jan-15 A

13-Jan-15 A

CSTM28640

Epoxy mortor & sealant

1 14-Jan-15 A

14-Jan-15 A

CSTM28650

GRP accessories

2 15-Jan-15 A

17-Jan-15 A

CSTM28670

Backfilling

3 04-Feb-15 A

07-Feb-15 A

CSTM28680

SRC 20 concrete backfill

2 19-Feb-15 A

21-Feb-15 A

CSTM28660

DI Manhole Cover & Frame

2 25-Feb-15 A

26-Feb-15 A

31 22-Jan-15 A

28-Feb-15 A

MANHOLE: 15/1/28/14/1
15/1
CSTM28690

Excavation & disposal of materials

4 22-Jan-15 A

26-Jan-15 A

CSTM28700

Blinding

1 02-Feb-15 A

02-Feb-15 A

CSTM28710

Reinforcement, shuttering, concreting

4 03-Feb-15 A

07-Feb-15 A

CSTM28720

Pipe connection to manhole & pre-testing of section

2 08-Feb-15 A

09-Feb-15 A

CSTM28730

Benching work

2 10-Feb-15 A

11-Feb-15 A

CSTM28740

Bitumen primer

1 14-Feb-15 A

14-Feb-15 A

CSTM28750

Tanking membrane

1 15-Feb-15 A

15-Feb-15 A

CSTM28760

Epoxy mortor & sealant

1 16-Feb-15 A

16-Feb-15 A

CSTM28770

GRP accessories

2 17-Feb-15 A

18-Feb-15 A

CSTM28790

Backfilling

3 22-Feb-15 A

24-Feb-15 A

CSTM28800

SRC 20 concrete backfill

1 25-Feb-15 A

25-Feb-15 A

CSTM28780

DI Manhole Cover & Frame

1 27-Feb-15 A

28-Feb-15 A

32 21-Jan-15 A

28-Feb-15 A

MANHOLE: 15/1/28/14/2
15/1

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Pocess
Delays

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 13 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSTM28810

Excavation & disposal of materials

4 21-Jan-15 A

25-Jan-15 A

CSTM28820

Blinding

1 02-Feb-15 A

02-Feb-15 A

CSTM28830

Reinforcement, shuttering, concreting

4 03-Feb-15 A

07-Feb-15 A

CSTM28840

Pipe connection to manhole & pre-testing of section

2 08-Feb-15 A

09-Feb-15 A

CSTM28850

Benching work

2 10-Feb-15 A

11-Feb-15 A

CSTM28860

Bitumen primer

1 14-Feb-15 A

14-Feb-15 A

CSTM28870

Tanking membrane

1 15-Feb-15 A

15-Feb-15 A

CSTM28880

Epoxy mortor & sealant

1 16-Feb-15 A

16-Feb-15 A

CSTM28890

GRP accessories

2 17-Feb-15 A

18-Feb-15 A

CSTM28910

Backfilling

3 22-Feb-15 A

24-Feb-15 A

CSTM28920

SRC 20 concrete backfill

1 26-Feb-15 A

26-Feb-15 A

CSTM28900

DI Manhole Cover & Frame

2 26-Feb-15 A

28-Feb-15 A

75 01-Dec-14 A

28-Feb-15 A

-121

MANHOLE: 15/1/28/15
15/1
CSTM1950

Excavation & disposal of materials

4 01-Dec-14 A

04-Dec-14 A

-70

CSTM1960

Blinding

2 06-Dec-14 A

07-Dec-14 A

-71

CSTM1970

Reinforcement, shuttering, concreting

5 09-Dec-14 A

14-Dec-14 A

-73

CSTM1980

Pipe connection to manhole & pre-testing of section

3 15-Dec-14 A

17-Dec-14 A

-74

CSTM19800

Benching work

3 17-Dec-14 A

21-Dec-14 A

-74

CSTM1990

Bitumen primer

2 24-Dec-14 A

25-Dec-14 A

-77

CSTM2000

Tanking membrane

2 27-Dec-14 A

28-Dec-14 A

-78

CSTM2010

Epoxy mortor & sealant

1 08-Feb-15 A

08-Feb-15 A

-113

CSTM2020

GRP accessories

2 09-Feb-15 A

10-Feb-15 A

-113

CSTM2040

Backfilling

3 15-Feb-15 A

17-Feb-15 A

-113

CSTM2030

DI Manhole Cover & Frame

2 26-Feb-15 A

28-Feb-15 A

-125

CSTM2050

SRC 20 concrete backfill

1 28-Feb-15 A

28-Feb-15 A

-121

45 02-Feb-15 A

26-Mar-15 A

-140

MANHOLE: 15/1/28/16
15/1
CSTM2070

Excavation & disposal of materials

3 02-Feb-15 A

04-Feb-15 A

-122

CSTM2080

Blinding

1 05-Feb-15 A

05-Feb-15 A

-122

CSTM2090

Reinforcement, shuttering, concreting

4 07-Feb-15 A

10-Feb-15 A

-122

CSTM2100

Pipe connection to manhole & pre-testing of section

2 11-Feb-15 A

14-Feb-15 A

-118

CSTM21000

Benching work

2 15-Feb-15 A

16-Feb-15 A

-118

CSTM2110

Bitumen primer

1 17-Feb-15 A

17-Feb-15 A

-118

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 14 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSTM2120

Tanking membrane

1 18-Feb-15 A

18-Feb-15 A

-118

CSTM2130

Epoxy mortor & sealant

1 19-Feb-15 A

19-Feb-15 A

-118

CSTM2140

GRP accessories

2 21-Feb-15 A

22-Feb-15 A

-118

CSTM2160

Backfilling

3 25-Feb-15 A

28-Feb-15 A

-118

CSTM2170

SRC 20 concrete backfill

3 25-Feb-15 A

28-Feb-15 A

-117

CSTM2150

DI Manhole Cover & Frame

2 25-Mar-15 A

26-Mar-15 A

-144

54 11-Feb-15 A

15-Apr-15 A

-141

54 11-Feb-15 A

15-Apr-15 A

-147

49 11-Feb-15 A

09-Apr-15 A

-147

6 09-Apr-15 A

15-Apr-15 A

-147

2 09-Apr-15 A

11-Apr-15 A

-145

REINSTATEMENT
ASPHALT
CSTR1010

90mm Base course

CSTR1020

70mm Wearing course

KERBSTONE
CSTR1030

Excavation & concrete foundation for kerbs

2 09-Apr-15 A

11-Apr-15 A

-147

CSTR1040

Kerbs installation

2 09-Apr-15 A

11-Apr-15 A

-146

CSTR1050

Backing concrete

2 09-Apr-15 A

11-Apr-15 A

-145

3 09-Apr-15 A

12-Apr-15 A

-142

PAVING/CONCRETE PAVING
PAVING/CONCR
CSTR1060

Formation preparation

3 09-Apr-15 A

12-Apr-15 A

-144

CSTR1070

Paving interlock

3 09-Apr-15 A

12-Apr-15 A

-142

5 09-Apr-15 A

14-Apr-15 A

-140

PLANT AND GRASS


GR
CSTR1080

Excavation for plants

3 09-Apr-15 A

12-Apr-15 A

-140

CSTR1090

Planting/grass

3 12-Apr-15 A

14-Apr-15 A

-140

PHASE 3: FROM MH 15/1/28/17 TO 15/1/28/25

155 19-Jan-15 A

22-Jun-15 A

-196

VC PIPE WORKS:
WORKS 15/1/28/17 TO 15/1/28/21

127 16-Feb-15 A

22-Jun-15 A

-217

55 19-Feb-15 A

14-Apr-15 A

-195

10 19-Feb-15 A

02-Mar-15 A

-137

300mm NOMINAL
NOMINA BORE 70m: From MH 15/1/28/16 to MH 15/1/28/17
CST1500

Excavation & disposal of materials

CST1510

Bedding preparation prior to VC pipe laying

1 28-Mar-15 A

28-Mar-15 A

-157

CST1520

Laying VC pipes & fittings and pre-testing

1 28-Mar-15 A

28-Mar-15 A

-155

CST1530

Granular & concrete surrounds

1 28-Mar-15 A

28-Mar-15 A

-153

CST1540

Backfilling

1 12-Apr-15 A

12-Apr-15 A

-191

CST1550

SRC 20 concrete backfill

1 13-Apr-15 A

13-Apr-15 A

-190

CST1630

Marker tape installation

1 14-Apr-15 A

14-Apr-15 A

-190

39 12-Apr-15 A

30-May-15 A

-198

200mm NOMINAL
NOMINA BORE 45.93m: From MH 15/1/28/17 to MH 15/1/28/18
0000.30

As per Al Jazeera, TCTC shall be allowed to work

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Total Float SI-1

Revision

Checked

2015
Feb

Mar

Apr

May

Jun

Jul

Aug

As per Al Jazeera, TCTC shall be allowed

0 12-Apr-15 A

Date

SI-2

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 15 of 35
Data Date: 22-Jun-15

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CST1570

Excavation & disposal of materials

39 12-Apr-15 A

21-May-15 A

-203 Ps

CST1580

Bedding preparation prior to VC pipe laying

34 17-Apr-15 A

22-May-15 A

-202 Ps

CST1590

Laying VC pipes & fittings and pre-testing

33 18-Apr-15 A

23-May-15 A

-200 Ps

CST1600

Pipe Connection to MH

32 19-Apr-15 A

25-May-15 A

-200 Ps

CST1610

Granular surrounds and Air Test

30 21-Apr-15 A

26-May-15 A

-197 Ps

CST1620

Backfill and SRC 20 concrete backfill

28 23-Apr-15 A

29-May-15 A

-198 Ps

CST1700

Marker tape installation

24 27-Apr-15 A

30-May-15 A

-198 Ps

29 12-Apr-15 A

10-May-15 A

200mm NOMINAL
NOMINA BORE 20.00m: From MH 15/1/28/18 to MH 15/1/28/19

Total Float SI-1

SI-2

As per Al Jazeera, TCTC shall be allowed to work

0 12-Apr-15 A

CST2840

Excavation & disposal of materials

6 12-Apr-15 A

17-Apr-15 A

CST2850

Bedding preparation prior to VC pipe laying

1 18-Apr-15 A

18-Apr-15 A

CST2860

Laying VC pipes & fittings and pre-testing

1 19-Apr-15 A

19-Apr-15 A

CST2880

Granular surrounds and Air Test

2 22-Apr-15 A

23-Apr-15 A

CST2870

Pipe Connection to MH

15 20-Apr-15 A

04-May-15 A

CST2890

Backfill and SRC 20 concrete backfill

4 06-May-15 A 09-May-15 A

CST2900

Marker tape installation

1 10-May-15 A 10-May-15 A

CST2910

Excavation & disposal of materials

7 28-May-15 A 03-Jun-15 A

SI-2

CST2920

Bedding preparation prior to VC pipe laying

2 04-Jun-15 A

05-Jun-15 A

SI-2

CST2930

Laying VC pipes & fittings and pre-testing

2 06-Jun-15 A

07-Jun-15 A

SI-2

CST2940

Pipe Connection to MH

2 08-Jun-15 A

09-Jun-15 A

SI-2

CST2950

Granular surrounds and Air Test

2 10-Jun-15 A

11-Jun-15 A

SI-2

CST2960

Backfill and SRC 20 concrete backfill

5 12-Jun-15 A

16-Jun-15 A

SI-2

CST2970

Marker tape installation

1 17-Jun-15 A

17-Jun-15 A

SI-2

CST3050

Reinstatement

5 18-Jun-15 A

22-Jun-15 A

43 16-Feb-15 A

30-Mar-15 A

-135

200mm NOMINAL
NOMINA BORE 29.58m: From MH 15/1/28/19 to MH 15/1/28/20
CST1710

Excavation & disposal of materials

11 16-Feb-15 A

28-Feb-15 A

-98

CST1720

Bedding preparation prior to VC pipe laying

11 19-Feb-15 A

03-Mar-15 A

-100

CST1730

Laying VC pipes & fittings and pre-testing

1 17-Mar-15 A

17-Mar-15 A

-110

CST1740

Granular & concrete surrounds

2 17-Mar-15 A

18-Mar-15 A

-110

CST1750

Backfilling

2 17-Mar-15 A

18-Mar-15 A

-107

CST1760

SRC 20 concrete backfill

2 17-Mar-15 A

18-Mar-15 A

-106

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Apr

May

Jun

Jul

26 28-May-15 A 22-Jun-15 A

200mm NOMINAL
NOMINA BORE 20.00m: From MH 15/1/28/19 to MH 15/1/28/19/1

Second Baseline

Mar

Revision

Checked

Aug

As per Al Jazeera, TCTC shall be allowed

0000.40

Remaining Level of Effort

2015
Feb

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 16 of 35
Data Date: 22-Jun-15

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

CST1840

Original Start
Duration

Marker tape installation

200mm NOMINAL
NOMINA BORE 14.68m: From MH 15/1/28/20 to MH 15/1/28/21

Finish

Total Pocess
Delays

2 29-Mar-15 A

30-Mar-15 A

-133

27 22-Feb-15 A

24-Mar-15 A

-107

CST1780

Excavation & disposal of materials

11 22-Feb-15 A

05-Mar-15 A

-100

CST1790

Bedding preparation prior to VC pipe laying

11 24-Feb-15 A

08-Mar-15 A

-101

CST1800

Laying VC pipes & fittings and pre-testing

1 14-Mar-15 A

14-Mar-15 A

-104

CST1810

Granular & concrete surrounds

1 15-Mar-15 A

15-Mar-15 A

-104

CST1820

Backfilling

1 24-Mar-15 A

24-Mar-15 A

-109

CST1910

Marker tape installation

1 24-Mar-15 A

24-Mar-15 A

-107

CST1830

SRC 20 concrete backfill

1 24-Mar-15 A

24-Mar-15 A

-108

11 04-Apr-15 A

14-Apr-15 A

11 04-Apr-15 A

14-Apr-15 A

FUTURE CONNE
CONNECTION
FC-06
CST2980

Excavation & disposal of materials

2 04-Apr-15 A

05-Apr-15 A

CST2990

Bedding preparation prior to VC pipe laying

1 06-Apr-15 A

06-Apr-15 A

CST3000

Laying VC pipes & fittings and pre-testing

1 07-Apr-15 A

07-Apr-15 A

CST3010

Granular & concrete surrounds

1 09-Apr-15 A

09-Apr-15 A

CST3020

Backfilling

1 11-Apr-15 A

11-Apr-15 A

CST3030

SRC 20 concrete backfill

1 12-Apr-15 A

12-Apr-15 A

CST3040

Marker tape installation

2 13-Apr-15 A

14-Apr-15 A

152 19-Jan-15 A

19-Jun-15 A

-197

38 09-Mar-15 A

15-Apr-15 A

-179

MANHOLE CONSTRUCTION
CONS
MANHOLE: 15/1/28/17
15/1
CSTM2190

Excavation & disposal of materials

1 09-Mar-15 A

09-Mar-15 A

-140

CSTM2200

Blinding

1 10-Mar-15 A

10-Mar-15 A

-140

CSTM2210

Reinforcement, shuttering, concreting

1 11-Mar-15 A

11-Mar-15 A

-137

CSTM2220

Pipe connection to manhole & pre-testing of section

1 12-Mar-15 A

12-Mar-15 A

-136

CSTM22200

Benching work

1 12-Mar-15 A

12-Mar-15 A

-134

CSTM2230

Bitumen primer

1 14-Mar-15 A

14-Mar-15 A

-134

CSTM2240

Tanking membrane

1 14-Mar-15 A

14-Mar-15 A

-133

CSTM2250

Epoxy mortor & sealant

1 14-Mar-15 A

14-Mar-15 A

-132

CSTM2260

GRP accessories

1 12-Apr-15 A

12-Apr-15 A

-181

CSTM2270

DI Manhole Cover & Frame

1 13-Apr-15 A

13-Apr-15 A

-180

CSTM2280

Backfilling

1 14-Apr-15 A

14-Apr-15 A

-178

CSTM2290

SRC 20 concrete backfill

1 15-Apr-15 A

15-Apr-15 A

-177

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 17 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

MANHOLE: 15/1/28/18
15/1

Finish

120 19-Jan-15 A

18-May-15 A

Total Pocess
Delays

Delay: Issuance of Excavation permit

35 19-Jan-15 A

22-Feb-15 A

0000.20

Delay: Al Jazeera Stopped the Work

37 23-Feb-15 A

31-Mar-15 A

CSTM2310

Excavation & disposal of materials

2 12-Apr-15 A

13-Apr-15 A

-161

CSTM2320

Blinding/Tanking & Screeding

3 14-Apr-15 A

16-Apr-15 A

-163

CSTM2330

Reinforcement, shuttering, concreting (Base & Wall)

4 01-May-15 A 04-May-15 A

-177

CSTM2340

Pipe connection to manhole & Backdrob

4 05-May-15 A 08-May-15 A

-178

CSTM23400

Bitumen primer

1 09-May-15 A 09-May-15 A

-177

CSTM2350

Tanking membrane

1 10-May-15 A 10-May-15 A

-177

CSTM2360

Backfilling

4 11-May-15 A

14-May-15 A

-180

CSTM2370

DI Manhole Cover & Frame

1 15-May-15 A 15-May-15 A

-179

CSTM2380

SRC 20 concrete backfill

1 16-May-15 A 16-May-15 A

-178

CSTM2390

Benching work

1 17-May-15 A 17-May-15 A

-177

CSTM2410

GRP accessories

1 18-May-15 A 18-May-15 A

-173

19 12-Apr-15 A

30-Apr-15 A

CSTM29290

Excavation & disposal of materials

2 12-Apr-15 A

13-Apr-15 A

CSTM29300

Blinding/Tanking & Screeding

3 14-Apr-15 A

16-Apr-15 A

CSTM29310

Reinforcement, shuttering, concreting (Base & Wall)

4 17-Apr-15 A

20-Apr-15 A

CSTM29320

Pipe connection to manhole & Backdrob

4 21-Apr-15 A

24-Apr-15 A

CSTM29330

Bitumen primer

1 25-Apr-15 A

25-Apr-15 A

CSTM29340

Tanking membrane

1 26-Apr-15 A

26-Apr-15 A

CSTM29350

Backfilling

4 27-Apr-15 A

30-Apr-15 A

CSTM29360

DI Manhole Cover & Frame

1 30-Apr-15 A

30-Apr-15 A

CSTM29370

SRC 20 concrete backfill

1 30-Apr-15 A

30-Apr-15 A

CSTM29380

Benching work

1 30-Apr-15 A

30-Apr-15 A

CSTM29390

GRP accessories

1 30-Apr-15 A

30-Apr-15 A

SI-2

2015
Feb

Mar

Apr

May

Jun

Jul

-175

0000.10

MANHOLE: 15/1/28/19
15/1

Total Float SI-1

23 28-May-15 A 19-Jun-15 A

MANHOLE: 15/1/28/19/1
15/1
CSTM29410

Excavation & disposal of materials

2 28-May-15 A 29-May-15 A

SI-2

CSTM29420

Blinding/Tanking & Screeding

3 30-May-15 A 01-Jun-15 A

SI-2

CSTM29430

Reinforcement, shuttering, concreting (Base & Wall)

4 02-Jun-15 A

05-Jun-15 A

SI-2

CSTM29440

Pipe connection to manhole & Backdrob

4 06-Jun-15 A

09-Jun-15 A

SI-2

CSTM29450

Bitumen primer

1 10-Jun-15 A

10-Jun-15 A

SI-2

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 18 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

Total Float SI-1

SI-2

CSTM29460

Tanking membrane

1 11-Jun-15 A

11-Jun-15 A

SI-2

CSTM29470

Backfilling

4 12-Jun-15 A

15-Jun-15 A

SI-2

CSTM29480

DI Manhole Cover & Frame

1 16-Jun-15 A

16-Jun-15 A

SI-2

CSTM29490

SRC 20 concrete backfill

1 17-Jun-15 A

17-Jun-15 A

SI-2

CSTM29500

Benching work

1 18-Jun-15 A

18-Jun-15 A

SI-2

CSTM29510

GRP accessories

1 19-Jun-15 A

19-Jun-15 A

SI-2

63 16-Feb-15 A

19-Apr-15 A

-139

MANHOLE: 15/1/28/20
15/1
CSTM2550

Excavation & disposal of materials

2 16-Feb-15 A

17-Feb-15 A

-85

CSTM2560

Blinding

2 24-Mar-15 A

25-Mar-15 A

-115

CSTM2570

Reinforcement, shuttering, concreting

1 25-Mar-15 A

25-Mar-15 A

-111

CSTM2580

Pipe connection to manhole & pre-testing of section

2 28-Mar-15 A

29-Mar-15 A

-112

CSTM25800

Benching work

1 12-Apr-15 A

12-Apr-15 A

-143

CSTM2590

Bitumen primer

1 13-Apr-15 A

13-Apr-15 A

-143

CSTM2600

Tanking membrane

1 14-Apr-15 A

14-Apr-15 A

-143

CSTM2610

Epoxy mortor & sealant

1 15-Apr-15 A

15-Apr-15 A

-142

CSTM2620

GRP accessories

1 16-Apr-15 A

16-Apr-15 A

-141

CSTM2630

DI Manhole Cover & Frame

1 17-Apr-15 A

17-Apr-15 A

-140

CSTM2640

Backfilling

1 18-Apr-15 A

18-Apr-15 A

-137

CSTM2650

SRC 20 concrete backfill

1 19-Apr-15 A

19-Apr-15 A

-137

66 14-Feb-15 A

20-Apr-15 A

-137

13 14-Feb-15 A

28-Feb-15 A

-91

MANHOLE: 15/1/28/21
15/1
CSTM2670

Excavation & disposal of materials

CSTM2680

Blinding

1 12-Mar-15 A

12-Mar-15 A

-101

CSTM2690

Reinforcement, shuttering, concreting

2 15-Mar-15 A

16-Mar-15 A

-100

CSTM2700

Pipe connection to manhole & pre-testing of section

1 26-Mar-15 A

26-Mar-15 A

-107

CSTM27000

Benching work

1 13-Apr-15 A

13-Apr-15 A

-140

CSTM2710

Bitumen primer

1 14-Apr-15 A

14-Apr-15 A

-140

CSTM2720

Tanking membrane

1 15-Apr-15 A

15-Apr-15 A

-140

CSTM2730

Epoxy mortor & sealant

1 16-Apr-15 A

16-Apr-15 A

-140

CSTM2740

GRP accessories

1 17-Apr-15 A

17-Apr-15 A

-139

CSTM2750

DI Manhole Cover & Frame

1 18-Apr-15 A

18-Apr-15 A

-137

CSTM2760

Backfilling

1 19-Apr-15 A

19-Apr-15 A

-135

CSTM2770

SRC 20 concrete backfill

1 20-Apr-15 A

20-Apr-15 A

-135

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 19 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

REINSTATEMENT
ASPHALT

Finish

Total Pocess
Delays

45 19-Apr-15 A

02-Jun-15 A

-174

32 19-Apr-15 A

01-Jun-15 A

-178

CSTA1010

90mm Base course

32 19-Apr-15 A

01-Jun-15 A

-179 Ps

CSTA1020

70mm Wearing course

32 19-Apr-15 A

01-Jun-15 A

-178 Ps

1 01-Jun-15 A

01-Jun-15 A

-180

KERBSTONE
CSTC1000

Excavation & concrete foundation for kerbs

1 01-Jun-15 A

01-Jun-15 A

-182 Ps

CSTC1010

Kerbs installation

1 01-Jun-15 A

01-Jun-15 A

-181 Ps

CSTC1020

Backing concrete

1 01-Jun-15 A

01-Jun-15 A

-180 Ps

2 01-Jun-15 A

02-Jun-15 A

-176

PAVING/CONCRETE PAVING
PAVING/CONCR
CSTP1010

Paving interlock

2 01-Jun-15 A

02-Jun-15 A

-176 Ps

CSTP1000

Formation preparation

2 01-Jun-15 A

02-Jun-15 A

-179 Ps

2 01-Jun-15 A

02-Jun-15 A

-174

PLANT AND GRASS


GR
CSTPG1000

Excavation for plants

2 01-Jun-15 A

02-Jun-15 A

-176 Ps

CSTPG1010

Planting/grass

2 01-Jun-15 A

02-Jun-15 A

-174 Ps

262 12-Jul-14 A

30-Mar-15 A

-104

262 12-Jul-14 A

30-Mar-15 A

-160

82 12-Jul-14 A

21-Oct-14 A

-44

43 12-Jul-14 A

02-Sep-14 A

-36

SEWER IN MICTROTUNNEL
MICTR
PHASE 1: FROM MH 15/1/28 TO 15/1/28/4
JACKING PIPES
PIPES: FROM MH 15/1/28 TO 15/1/28/4
L-300mm NOMINAL
NOMI
BORE IN M.TUNNEL 59.26m: From MH 15/1/28/1 to MH Ex.15/1/28
CSMJ1010

Excavation for launch shaft & material disposal

7 12-Jul-14 A

19-Jul-14 A

-13

CSMJ1020

Concrete for platform & trust wall

3 20-Jul-14 A

22-Jul-14 A

-13

CSMJ1030

Jacking GRP lined RC pipe

9 21-Aug-14 A

31-Aug-14 A

-36

CSMJ10300

Testing Prior to Annulus Grouting

1 01-Sep-14 A

01-Sep-14 A

-36

CSMJ1040

Annulus grouting

1 02-Sep-14 A

02-Sep-14 A

-36

19 24-Aug-14 A

14-Sep-14 A

-37

300mm NOMINAL
NOMINA BORE IN M.TUNNEL 60m: From MH 15/1/28/1 to MH 15/1/28/2
CSMJ1070

Excavation for receiver shaft

7 24-Aug-14 A

31-Aug-14 A

-36

CSMJ1080

Concrete for platform & trust wall

1 01-Sep-14 A

01-Sep-14 A

-36

CSMJ1090

Jacking GRP lined RC pipe

9 02-Sep-14 A

11-Sep-14 A

-37

CSMJ10900

Testing Prior to Annulus Grouting

1 13-Sep-14 A

13-Sep-14 A

-37

CSMJ1100

Annulus grouting

1 14-Sep-14 A

14-Sep-14 A

-37

21 01-Sep-14 A

24-Sep-14 A

-38

L-300mm NOMINAL
NOMI
BORE IN M.TUNNEL 60m: From MH 15/1/28/3 to MH 15/1/28/2
CSMJ1130

Excavation for launch shaft & material disposal

7 01-Sep-14 A

08-Sep-14 A

-38

CSMJ1140

Concrete for platform & trust wall

3 09-Sep-14 A

11-Sep-14 A

-37

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 20 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSMJ1150

Jacking GRP lined RC pipe

9 13-Sep-14 A

22-Sep-14 A

-38

CSMJ11500

Testing Prior to Annulus Grouting

1 23-Sep-14 A

23-Sep-14 A

-38

CSMJ1160

Annulus grouting

1 24-Sep-14 A

24-Sep-14 A

-38

22 23-Sep-14 A

21-Oct-14 A

-44

300mm NOMINAL
NOMINA BORE IN M.TUNNEL70m: From MH 15/1/28/3 to MH 15/1/28/4
CSMJ1190

Excavation for receiver shaft

9 23-Sep-14 A

02-Oct-14 A

-44

CSMJ1200

Concrete for platform & trust wall

1 07-Oct-14 A

07-Oct-14 A

-44

CSMJ1210

Jacking GRP lined RC pipe

10 08-Oct-14 A

19-Oct-14 A

-44

CSMJ12100

Testing Prior to Annulus Grouting

1 20-Oct-14 A

20-Oct-14 A

-44

CSMJ1220

Annulus grouting

1 21-Oct-14 A

21-Oct-14 A

-44

187 25-Sep-14 A

30-Mar-15 A

-182

123 27-Nov-14 A

29-Mar-15 A

-222

MANHOLE CONSTRUCTION
CONS
MANHOLE: 15/1/28/1
15/1
CSMM1840

Preparing shaft for MH construction

2 27-Nov-14 A

29-Nov-14 A

-107

CSMM1850

Blinding

1 30-Nov-14 A

30-Nov-14 A

-107

CSMM184

Recovery

0 10-Jan-15 A

CSMM1860

Reinforcement, shuttering, concreting

CSMM1870

21-Jan-15 A

-147

Pipe connection to manhole & pre-testing of section

3 21-Jan-15 A

24-Jan-15 A

-146

CSMM18700

Benching work

2 31-Jan-15 A

01-Feb-15 A

-151

CSMM1880

Bitumen primer

1 02-Feb-15 A

02-Feb-15 A

-151

CSMM1890

Tanking membrane

1 03-Feb-15 A

03-Feb-15 A

-151

CSMM1900

Epoxy mortor & sealant

1 04-Feb-15 A

04-Feb-15 A

-151

CSMM1930

Backfilling

3 23-Feb-15 A

25-Feb-15 A

-159

CSMM1910

GRP accessories

2 25-Feb-15 A

26-Feb-15 A

-167

CSMM1920

DI Manhole Cover & Frame

3 23-Mar-15 A

25-Mar-15 A

-188

CSMM1940

SRC 20 concrete backfill

3 26-Mar-15 A

29-Mar-15 A

-185

122 25-Sep-14 A

19-Feb-15 A

-137

CSMM1950

Preparing shaft for MH construction

1 25-Sep-14 A

25-Sep-14 A

-38

CSMM1960

Blinding

1 27-Sep-14 A

27-Sep-14 A

-38

CSMM1970

Reinforcement, shuttering, concreting

96 28-Sep-14 A

21-Jan-15 A

-130

CSMM1980

Pipe connection to manhole & pre-testing of section

3 26-Jan-15 A

28-Jan-15 A

-134

CSMM19800

Benching work

2 02-Feb-15 A

03-Feb-15 A

-137

CSMM1990

Bitumen primer

1 04-Feb-15 A

04-Feb-15 A

-137

CSMM2000

Tanking membrane

1 05-Feb-15 A

05-Feb-15 A

-137

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

SI-2

2015
Feb

Mar

Apr

May

Jun

Jul

very

44 01-Dec-14 A

MANHOLE: 15/1/28/2
15/1

Total Float SI-1

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 21 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSMM2010

Epoxy mortor & sealant

1 07-Feb-15 A

07-Feb-15 A

-137

CSMM2020

GRP accessories

2 08-Feb-15 A

09-Feb-15 A

-137

CSMM2030

DI Manhole Cover & Frame

2 10-Feb-15 A

11-Feb-15 A

-137

CSMM2040

Backfilling

5 14-Feb-15 A

18-Feb-15 A

-137

CSMM2050

SRC 20 concrete backfill

1 19-Feb-15 A

19-Feb-15 A

-137

103 22-Oct-14 A

21-Feb-15 A

-125

MANHOLE: 15/1/28/3
15/1
CSMJ1840

Preparing shaft for MH construction

1 22-Oct-14 A

22-Oct-14 A

-44

CSMJ1850

Blinding

1 23-Oct-14 A

23-Oct-14 A

-44

CSMJ1860

Reinforcement, shuttering, concreting

76 25-Oct-14 A

21-Jan-15 A

-116

CSMJ1870

Pipe connection to manhole & pre-testing of section

3 31-Jan-15 A

02-Feb-15 A

-124

CSMJ18700

Benching work

2 04-Feb-15 A

05-Feb-15 A

-125

CSMJ1880

Bitumen primer

1 07-Feb-15 A

07-Feb-15 A

-125

CSMJ1890

Tanking membrane

1 08-Feb-15 A

08-Feb-15 A

-125

CSMJ1900

Epoxy mortor & sealant

1 09-Feb-15 A

09-Feb-15 A

-125

CSMJ1910

GRP accessories

1 10-Feb-15 A

10-Feb-15 A

-125

CSMJ1920

DI Manhole Cover & Frame

2 11-Feb-15 A

14-Feb-15 A

-125

CSMJ1930

Backfilling

5 15-Feb-15 A

19-Feb-15 A

-125

CSMJ1940

SRC 20 concrete backfill

1 21-Feb-15 A

21-Feb-15 A

-125

72 05-Jan-15 A

30-Mar-15 A

-151

MANHOLE: 15/1/28/4
15/1
CSMJ1950

Preparing shaft for MH construction

2 05-Jan-15 A

06-Jan-15 A

-102

CSMJ1960

Blinding

2 18-Jan-15 A

19-Jan-15 A

-112

CSMJ1970

Reinforcement, shuttering, concreting

4 04-Feb-15 A

08-Feb-15 A

-125

CSMJ1980

Pipe connection to manhole & pre-testing of section

2 09-Feb-15 A

10-Feb-15 A

-125

CSMJ19800

Benching work

2 11-Feb-15 A

14-Feb-15 A

-125

CSMJ1990

Bitumen primer

1 15-Feb-15 A

15-Feb-15 A

-125

CSMJ2000

Tanking membrane

1 16-Feb-15 A

16-Feb-15 A

-125

CSMJ2010

Epoxy mortor & sealant

1 17-Feb-15 A

17-Feb-15 A

-125

CSMJ2020

GRP accessories

1 25-Feb-15 A

25-Feb-15 A

-131

CSMJ2040

Backfilling

4 24-Feb-15 A

28-Feb-15 A

-126

CSMJ2030

DI Manhole Cover & Frame

3 26-Mar-15 A

29-Mar-15 A

-156

CSMJ2050

SRC 20 concrete backfill

3 28-Mar-15 A

30-Mar-15 A

-151

12 16-Mar-15 A

29-Mar-15 A

-134

REINSTATEMENT

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 22 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

ASPHALT

Finish

Total Pocess
Delays

5 24-Mar-15 A

29-Mar-15 A

-146

CSMTR1510

90mm Base course

3 24-Mar-15 A

26-Mar-15 A

-146

CSMTR1520

70mm Wearing course

3 26-Mar-15 A

29-Mar-15 A

-146

2 16-Mar-15 A

17-Mar-15 A

-130

KERBSTONE
CSMTR1530

Excavation & concrete foundation for kerbs

2 16-Mar-15 A

17-Mar-15 A

-134

CSMTR1540

Kerbs installation

2 16-Mar-15 A

17-Mar-15 A

-132

CSMTR1550

Backing concrete

2 16-Mar-15 A

17-Mar-15 A

-130

2 16-Mar-15 A

17-Mar-15 A

-126

PAVING/CONCRETE PAVING
PAVING/CONCR
CSMTR1560

Formation preparation

2 16-Mar-15 A

17-Mar-15 A

-128

CSMTR1570

Paving interlock

2 16-Mar-15 A

17-Mar-15 A

-126

1 16-Mar-15 A

16-Mar-15 A

-123

PLANT AND GRASS


GR
CSMTR1580

Excavation for plants

1 16-Mar-15 A

16-Mar-15 A

-124

CSMTR1590

Planting/grass

1 16-Mar-15 A

16-Mar-15 A

-123

221 21-Aug-14 A

29-Mar-15 A

-103

183 21-Aug-14 A

19-Feb-15 A

-110

26 15-Dec-14 A

10-Jan-15 A

-128

PHASE 2: FROM MH 15/1/28/4 TO 15/1/28/12


JACKING PIPE F
FROM MH 15/1/28/4 TO 15/1/28/12
L300mm NOMINAL
NOMIN
BORE IN M.TUNNEL 45.35m: From MH 15/1/28/5 to MH 15/1/28/4
CSMJ1250

Excavation for launch shaft & material disposal

6 15-Dec-14 A

22-Dec-14 A

-104

CSMJ1260

Concrete for platform & trust wall

4 23-Dec-14 A

27-Dec-14 A

-100

CSMJ1270

Jacking GRP lined RC pipe

4 29-Dec-14 A

01-Jan-15 A

-101

CSMJ12700

Testing Prior to Annulus Grouting

1 03-Jan-15 A

03-Jan-15 A

-101

CSMJ1280

Annulus grouting

2 06-Jan-15 A

07-Jan-15 A

-104

CSMJ125

Recovery

0 10-Jan-15 A

300mm NOMINAL
NOMINA BORE IN M.TUNNEL 30.43m: From MH 15/1/28/5 to MH 15/1/28/6

22 04-Jan-15 A

28-Jan-15 A

-116

Excavation for receiver shaft

4 04-Jan-15 A

07-Jan-15 A

-106

CSMJ1320

Concrete for platform & trust wall

2 10-Jan-15 A

11-Jan-15 A

-108

CSMJ1330

Jacking GRP lined RC pipe

8 18-Jan-15 A

26-Jan-15 A

-116

CSMJ1340

Annulus grouting

2 27-Jan-15 A

28-Jan-15 A

-116

CSMJ13300

Testing Prior to Annulus Grouting

2 27-Jan-15 A

28-Jan-15 A

-117

19 06-Jan-15 A

27-Jan-15 A

-108

CSMJ1370

Excavation for launch shaft & material disposal

8 06-Jan-15 A

14-Jan-15 A

-107

CSMJ1380

Concrete for platform & trust wall

4 11-Jan-15 A

14-Jan-15 A

-104

CSMJ1390

Jacking GRP lined RC pipe

10 14-Jan-15 A

25-Jan-15 A

-108

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

SI-2

2015
Feb

Mar

Apr

May

Jun

Jul

very

CSMJ1310

L-300mm NOMINAL
NOMI
BORE IN M.TUNNEL 61.78m: From MH 15/1/28/7 to MH 15/1/28/6

Total Float SI-1

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 23 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSMJ13900

Testing Prior to Annulus Grouting

2 25-Jan-15 A

26-Jan-15 A

-108

CSMJ1400

Annulus grouting

2 26-Jan-15 A

27-Jan-15 A

-108

106 21-Aug-14 A

27-Dec-14 A

-75

300mm NOMINAL
NOMINA BORE IN M.TUNNEL 55.74m: From MH 15/1/28/7 to MH 15/1/28/8
CSMJ1430

Excavation for receiver shaft

6 21-Aug-14 A

27-Aug-14 A

17

CSMJ1440

Concrete for platform & trust wall

1 28-Aug-14 A

28-Aug-14 A

17

CSMJ1450

Jacking GRP lined RC pipe

8 30-Aug-14 A

07-Sep-14 A

14

CSMJ14500

Testing Prior to Annulus Grouting

1 08-Sep-14 A

08-Sep-14 A

14

CSMJ1460

Annulus grouting

2 25-Dec-14 A

27-Dec-14 A

-75

102 28-Aug-14 A

29-Dec-14 A

-71

L-300mm NOMINAL
NOMI
BORE IN M.TUNNEL 35.13m: From MH 15/1/28/9 to MH 15/1/28/8
CSMJ1490

Excavation for launch shaft & material disposal

3 28-Aug-14 A

31-Aug-14 A

19

CSMJ1500

Concrete for platform & trust wall

3 04-Sep-14 A

07-Sep-14 A

16

CSMJ1510

Jacking GRP lined RC pipe

4 08-Sep-14 A

11-Sep-14 A

16

CSMJ15100

Testing Prior to Annulus Grouting

1 13-Sep-14 A

13-Sep-14 A

16

CSMJ1520

Annulus grouting

2 28-Dec-14 A

29-Dec-14 A

-71

95 09-Sep-14 A

01-Jan-15 A

-68

300mm NOMINAL
NOMINA BORE IN M.TUNNEL 32.74m: From MH 15/1/28/9 to MH 15/1/28/10
CSMJ1550

Excavation for receiver shaft

3 09-Sep-14 A

11-Sep-14 A

16

CSMJ1560

Concrete for platform & trust wall

1 13-Sep-14 A

13-Sep-14 A

16

CSMJ1570

Jacking GRP lined RC pipe

5 14-Sep-14 A

18-Sep-14 A

16

CSMJ15700

Testing Prior to Annulus Grouting

1 20-Sep-14 A

20-Sep-14 A

16

CSMJ1580

Annulus grouting

2 31-Dec-14 A

01-Jan-15 A

-68

93 13-Sep-14 A

03-Jan-15 A

-62

L-300mm NOMINAL
NOMI
BORE IN M.TUNNEL 50.23m: From MH 15/1/28/11 to MH 15/1/28/10
CSMJ1610

Excavation for launch shaft & material disposal

7 13-Sep-14 A

20-Sep-14 A

14

CSMJ1620

Concrete for platform & trust wall

3 21-Sep-14 A

23-Sep-14 A

14

CSMJ1630

Jacking GRP lined RC pipe

7 24-Sep-14 A

01-Oct-14 A

12

CSMJ16300

Testing Prior to Annulus Grouting

1 02-Oct-14 A

02-Oct-14 A

12

CSMJ1640

Annulus grouting

2 01-Jan-15 A

03-Jan-15 A

-62

123 24-Sep-14 A

19-Feb-15 A

-93

300mm NOMINAL
NOMINA BORE IN M.TUNNEL 54.53m: From MH 15/1/28/11 to MH 15/1/28/12
CSMJ1670

Excavation for receiver shaft

7 24-Sep-14 A

01-Oct-14 A

12

CSMJ1680

Concrete for platform & trust wall

1 02-Oct-14 A

02-Oct-14 A

12

CSMJ1690

Jacking GRP lined RC pipe

8 07-Oct-14 A

15-Oct-14 A

12

CSMJ16900

Testing Prior to Annulus Grouting

1 16-Oct-14 A

16-Oct-14 A

12

CSMJ1700

Annulus grouting

1 19-Feb-15 A

19-Feb-15 A

-93

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 24 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

MANHOLE CONSTRUCTION
CONS
MANHOLE: 15/1/28/5
15/1

Finish

Total Pocess
Delays

86 17-Dec-14 A

29-Mar-15 A

-103

79 27-Dec-14 A

29-Mar-15 A

-144

CSMJ2060

Preparing shaft for MH construction

2 27-Dec-14 A

28-Dec-14 A

-88

CSMJ2070

Blinding

1 20-Jan-15 A

20-Jan-15 A

-107

CSMJ2080

Reinforcement, shuttering, concreting

4 31-Jan-15 A

03-Feb-15 A

-115

CSMJ2090

Pipe connection to manhole & pre-testing of section

2 15-Feb-15 A

16-Feb-15 A

-123

CSMJ20900

Benching work

2 17-Feb-15 A

18-Feb-15 A

-123

CSMJ2100

Bitumen primer

1 19-Feb-15 A

19-Feb-15 A

-123

CSMJ2110

Tanking membrane

1 21-Feb-15 A

21-Feb-15 A

-123

CSMJ2120

Epoxy mortor & sealant

1 22-Feb-15 A

22-Feb-15 A

-123

CSMJ2130

GRP accessories

1 25-Feb-15 A

25-Feb-15 A

-125

CSMJ2150

Backfilling

6 22-Feb-15 A

28-Feb-15 A

-120

CSMJ2160

SRC 20 concrete backfill

3 25-Mar-15 A

28-Mar-15 A

-143

CSMJ2140

DI Manhole Cover & Frame

3 26-Mar-15 A

29-Mar-15 A

-150

72 04-Jan-15 A

29-Mar-15 A

-137

MANHOLE: 15/1/28/6
15/1
CSMJ2170

Preparing shaft for MH construction

2 04-Jan-15 A

05-Jan-15 A

-88

CSMJ2180

Blinding

2 27-Jan-15 A

28-Jan-15 A

-107

CSMJ2190

Reinforcement, shuttering, concreting

4 31-Jan-15 A

03-Feb-15 A

-108

CSMJ2200

Pipe connection to manhole & pre-testing of section

2 04-Feb-15 A

05-Feb-15 A

-108

CSMJ22000

Benching work

2 07-Feb-15 A

08-Feb-15 A

-108

CSMJ2210

Bitumen primer

1 09-Feb-15 A

09-Feb-15 A

-108

CSMJ2220

Tanking membrane

1 10-Feb-15 A

10-Feb-15 A

-108

CSMJ2230

Epoxy mortor & sealant

1 11-Feb-15 A

11-Feb-15 A

-108

CSMJ2240

GRP accessories

1 25-Feb-15 A

25-Feb-15 A

-118

CSMJ2260

Backfilling

6 22-Feb-15 A

28-Feb-15 A

-113

CSMJ2250

DI Manhole Cover & Frame

3 25-Mar-15 A

28-Mar-15 A

-142

CSMJ2270

SRC 20 concrete backfill

3 26-Mar-15 A

29-Mar-15 A

-137

75 31-Dec-14 A

29-Mar-15 A

-131

MANHOLE: 15/1/28/7
15/1
CSMJ2300

Reinforcement, shuttering, concreting

4 31-Dec-14 A

04-Jan-15 A

-76

CSMJ2310

Pipe connection to manhole & pre-testing of section

3 05-Jan-15 A

07-Jan-15 A

-77

CSMJ23100

Benching work

2 08-Jan-15 A

10-Jan-15 A

-77

CSMJ2280

Preparing shaft for MH construction

2 12-Jan-15 A

13-Jan-15 A

-89

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 25 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSMJ2320

Bitumen primer

2 13-Jan-15 A

14-Jan-15 A

-80

CSMJ2290

Blinding

2 27-Jan-15 A

28-Jan-15 A

-101

CSMJ2330

Tanking membrane

1 31-Jan-15 A

31-Jan-15 A

-93

CSMJ2340

Epoxy mortor & sealant

1 01-Feb-15 A

01-Feb-15 A

-93

CSMJ2350

GRP accessories

1 25-Feb-15 A

25-Feb-15 A

-112

CSMJ2370

Backfilling

5 23-Feb-15 A

28-Feb-15 A

-107

CSMJ2360

DI Manhole Cover & Frame

3 26-Mar-15 A

29-Mar-15 A

-137

CSMJ2380

SRC 20 concrete backfill

3 26-Mar-15 A

29-Mar-15 A

-131

74 01-Jan-15 A

29-Mar-15 A

-125

MANHOLE: 15/1/28/8
15/1
CSMJ2400

Blinding

2 01-Jan-15 A

03-Jan-15 A

-73

CSMJ2410

Reinforcement, shuttering, concreting

4 04-Jan-15 A

07-Jan-15 A

-73

CSMJ2390

Preparing shaft for MH construction

2 08-Jan-15 A

10-Jan-15 A

-80

CSMJ2420

Pipe connection to manhole & pre-testing of section

3 07-Jan-15 A

10-Jan-15 A

-73

CSMJ24200

Benching work

2 10-Jan-15 A

11-Jan-15 A

-72

CSMJ2430

Bitumen primer

2 11-Jan-15 A

12-Jan-15 A

-72

CSMJ2440

Tanking membrane

1 31-Jan-15 A

31-Jan-15 A

-87

CSMJ2450

Epoxy mortor & sealant

1 01-Feb-15 A

01-Feb-15 A

-87

CSMJ2460

GRP accessories

1 25-Feb-15 A

25-Feb-15 A

-106

CSMJ2480

Backfilling

6 22-Feb-15 A

28-Feb-15 A

-101

CSMJ2470

DI Manhole Cover & Frame

3 26-Mar-15 A

29-Mar-15 A

-131

CSMJ2490

SRC 20 concrete backfill

3 26-Mar-15 A

29-Mar-15 A

-125

86 17-Dec-14 A

29-Mar-15 A

-119

MANHOLE: 15/1/28/9
15/1
CSMJ2510

Blinding

2 17-Dec-14 A

20-Dec-14 A

-55

CSMJ2520

Reinforcement, shuttering, concreting

5 22-Dec-14 A

27-Dec-14 A

-57

CSMJ2530

Pipe connection to manhole & pre-testing of section

2 29-Dec-14 A

30-Dec-14 A

-58

CSMJ25300

Benching work

2 01-Jan-15 A

03-Jan-15 A

-59

CSMJ2500

Preparing shaft for MH construction

2 04-Jan-15 A

05-Jan-15 A

-70

CSMJ2540

Bitumen primer

2 05-Jan-15 A

06-Jan-15 A

-61

CSMJ2550

Tanking membrane

1 31-Jan-15 A

31-Jan-15 A

-81

CSMJ2560

Epoxy mortor & sealant

1 01-Feb-15 A

01-Feb-15 A

-81

CSMJ2570

GRP accessories

1 25-Feb-15 A

25-Feb-15 A

-100

CSMJ2590

Backfilling

6 23-Feb-15 A

01-Mar-15 A

-96

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 26 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSMJ2580

DI Manhole Cover & Frame

3 26-Mar-15 A

29-Mar-15 A

-125

CSMJ2600

SRC 20 concrete backfill

3 26-Mar-15 A

29-Mar-15 A

-119

70 06-Jan-15 A

29-Mar-15 A

-112

MANHOLE: 15/1/28/10
15/1
CSMJ2610

Preparing shaft for MH construction

2 06-Jan-15 A

07-Jan-15 A

-65

CSMJ2620

Blinding

2 27-Jan-15 A

28-Jan-15 A

-82

CSMJ2630

Reinforcement, shuttering, concreting

4 31-Jan-15 A

03-Feb-15 A

-83

CSMJ2640

Pipe connection to manhole & pre-testing of section

2 04-Feb-15 A

05-Feb-15 A

-83

CSMJ26400

Benching work

2 07-Feb-15 A

08-Feb-15 A

-83

CSMJ2650

Bitumen primer

1 09-Feb-15 A

09-Feb-15 A

-83

CSMJ2660

Tanking membrane

1 10-Feb-15 A

10-Feb-15 A

-83

CSMJ2670

Epoxy mortor & sealant

1 11-Feb-15 A

11-Feb-15 A

-83

CSMJ2680

GRP accessories

1 25-Feb-15 A

25-Feb-15 A

-93

CSMJ2700

Backfilling

6 22-Feb-15 A

28-Feb-15 A

-88

CSMJ2690

DI Manhole Cover & Frame

3 26-Mar-15 A

29-Mar-15 A

-118

CSMJ2710

SRC 20 concrete backfill

3 26-Mar-15 A

29-Mar-15 A

-112

33 13-Jan-15 A

21-Feb-15 A

-72

MANHOLE: 15/1/28/11
15/1
CSMJ2720

Preparing shaft for MH construction

2 13-Jan-15 A

14-Jan-15 A

-62

CSMJ2730

Blinding

2 27-Jan-15 A

28-Jan-15 A

-73

CSMJ2750

Pipe connection to manhole & pre-testing of section

2 31-Jan-15 A

01-Feb-15 A

-70

CSMJ2740

Reinforcement, shuttering, concreting

5 28-Jan-15 A

02-Feb-15 A

-73

CSMJ27500

Benching work

2 02-Feb-15 A

03-Feb-15 A

-70

CSMJ2760

Bitumen primer

1 04-Feb-15 A

04-Feb-15 A

-70

CSMJ2770

Tanking membrane

1 05-Feb-15 A

05-Feb-15 A

-70

CSMJ2780

Epoxy mortor & sealant

1 07-Feb-15 A

07-Feb-15 A

-70

CSMJ2790

GRP accessories

1 08-Feb-15 A

08-Feb-15 A

-70

CSMJ2800

DI Manhole Cover & Frame

2 09-Feb-15 A

10-Feb-15 A

-70

CSMJ2810

Backfilling

5 11-Feb-15 A

17-Feb-15 A

-70

CSMJ2820

SRC 20 concrete backfill

2 19-Feb-15 A

21-Feb-15 A

-72

3 16-Mar-15 A

18-Mar-15 A

-109

3 16-Mar-15 A

18-Mar-15 A

-109

11 16-Mar-15 A

28-Mar-15 A

-85

3 25-Mar-15 A

28-Mar-15 A

-89

MANHOLE: 15/1/28/12
15/1
CSMJ2830

Beaking MH and Pipe connection

REINSTATEMENT
ASPHALT

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 27 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSMTR1360

90mm Base course

3 25-Mar-15 A

28-Mar-15 A

-91

CSMTR1370

70mm Wearing course

3 25-Mar-15 A

28-Mar-15 A

-89

2 16-Mar-15 A

17-Mar-15 A

-76

PAVING/CONCRETE PAVING
PAVING/CONCR
CSMTR1410

Formation preparation

2 16-Mar-15 A

17-Mar-15 A

-77

CSMTR1420

Paving interlock

2 16-Mar-15 A

17-Mar-15 A

-76

1 16-Mar-15 A

16-Mar-15 A

-76

KERBSTONE
CSMTR1380

Excavation & concrete foundation for kerbs

1 16-Mar-15 A

16-Mar-15 A

-78

CSMTR1400

Backing concrete

1 16-Mar-15 A

16-Mar-15 A

-76

CSMTR1390

Kerbs installation

1 16-Mar-15 A

16-Mar-15 A

-77

2 16-Mar-15 A

17-Mar-15 A

-76

PLANT AND GRASS


GR
CSMTR1430

Excavation for plants

2 16-Mar-15 A

17-Mar-15 A

-76

CSMTR1440

Planting/grass

2 16-Mar-15 A

17-Mar-15 A

-76

162 08-Jan-15 A

18-Jun-15 A

-184

159 11-Jan-15 A

18-Jun-15 A

-184

144 11-Jan-15 A

03-Jun-15 A

-170

54 11-Jan-15 A

15-Mar-15 A

-87

HOUSE CONNECTION
CONNECT
SEWER IN TRENCH
TRENC (AREA)
HOUSE CONNECTION
CONNEC
PHASE 1
SURVEY AND DEMOLISH
D
CHG1000

Plot survey

2 11-Jan-15 A

12-Jan-15 A

-37

CHG1010

Demolition of ext. underground structures

3 12-Mar-15 A

15-Mar-15 A

-87

67 24-Feb-15 A

01-May-15 A

-242

PIPE WORK IN TRENCH-HC 01


CSHCP1010

Excavation & disposal of materials

43 24-Feb-15 A

07-Apr-15 A

-232

CSHCP1020

Bedding preparation prior to pipe laying

43 26-Feb-15 A

09-Apr-15 A

-231

CSHCP1030

Laying pipe & connecting to new manhole

42 28-Feb-15 A

10-Apr-15 A

-228

CSHCP1040

Granular & concrete surrounds

44 28-Feb-15 A

12-Apr-15 A

-227

CSHCP1050

Backfilling

46 28-Feb-15 A

14-Apr-15 A

-227

CSHCP1060

Concrete backfill

63 28-Feb-15 A

01-May-15 A

-242

70 28-Feb-15 A

08-May-15 A

PIPE WORK IN TRENCH-HC 02


CSHCP1070

Excavation & disposal of materials

30 28-Feb-15 A

29-Mar-15 A

CSHCP1080

Bedding preparation prior to pipe laying

43 28-Feb-15 A

11-Apr-15 A

CSHCP1090

Laying pipe & connecting to new manhole

50 28-Feb-15 A

18-Apr-15 A

CSHCP1100

Granular & concrete surrounds

52 28-Feb-15 A

20-Apr-15 A

CSHCP1110

Backfilling

54 28-Feb-15 A

22-Apr-15 A

CSHCP1120

Concrete backfill

70 28-Feb-15 A

08-May-15 A

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 28 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

PIPE WORK IN TRENCH-HC 03

Finish

98 24-Feb-15 A

01-Jun-15 A

Total Pocess
Delays

CSHCP1130

Excavation & disposal of materials

86 24-Feb-15 A

22-May-15 A

Ps

CSHCP1140

Bedding preparation prior to pipe laying

84 26-Feb-15 A

24-May-15 A

Ps

CSHCP1150

Laying pipe & connecting to new manhole

84 26-Feb-15 A

26-May-15 A

Ps

CSHCP1160

Granular & concrete surrounds

84 26-Feb-15 A

28-May-15 A

Ps

CSHCP1170

Backfilling

50 07-Apr-15 A

30-May-15 A

Ps

CSHCP1180

Concrete backfill

2 31-May-15 A 01-Jun-15 A

PIPE WORK IN TRENCH-HC 04

99 25-Feb-15 A

03-Jun-15 A

Excavation & disposal of materials

48 25-Feb-15 A

13-Apr-15 A

CSHCP1200

Bedding preparation prior to pipe laying

49 26-Feb-15 A

15-Apr-15 A

CSHCP1210

Laying pipe & connecting to new manhole

51 26-Feb-15 A

17-Apr-15 A

CSHCP1220

Granular & concrete surrounds

53 26-Feb-15 A

19-Apr-15 A

CSHCP1230

Backfilling

53 28-Feb-15 A

21-Apr-15 A

CSHCP1240

Concrete backfill

2 02-Jun-15 A

03-Jun-15 A

21 14-Apr-15 A

04-May-15 A

-139

Excavation & disposal of materials

1 14-Apr-15 A

14-Apr-15 A

-133

CHCC1020

Blinding

1 15-Apr-15 A

15-Apr-15 A

-133

CHCC1030

Reinforcement, shuttering, concreting

1 16-Apr-15 A

16-Apr-15 A

-132

CHCC1040

Pipe connection to manhole & pre-testing of section

1 17-Apr-15 A

17-Apr-15 A

-132

CHCC10400

Benching work

1 18-Apr-15 A

18-Apr-15 A

-130

CHCC1050

Bitumen primer

1 19-Apr-15 A

19-Apr-15 A

-130

CHCC1060

Tanking membrane

1 20-Apr-15 A

20-Apr-15 A

-130

CHCC1070

Epoxy mortor & sealant

1 21-Apr-15 A

21-Apr-15 A

-130

CHCC1080

GRP accessories

1 22-Apr-15 A

22-Apr-15 A

-130

CHCC1090

DI Manhole Cover & Frame

1 03-May-15 A 03-May-15 A

-139

CHCC1100

Backfilling

1 04-May-15 A 04-May-15 A

-139

44 15-Apr-15 A

28-May-15 A

-163

CHCC1120

Excavation & disposal of materials

1 15-Apr-15 A

15-Apr-15 A

-134

CHCC1130

Blinding

1 16-Apr-15 A

16-Apr-15 A

-134

CHCC1140

Reinforcement, shuttering, concreting

1 17-Apr-15 A

17-Apr-15 A

-133

CHCC1150

Pipe connection to manhole & pre-testing of section

1 18-Apr-15 A

18-Apr-15 A

-133

CHCC11500

Benching work

1 03-May-15 A 03-May-15 A

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

2015
Feb

Mar

Apr

May

Jun

Jul

Ps

CHCC1010

INSPECTION CHAMBER
CH
2

SI-2

Ps

CSHCP1190

INSPECTION CHAMBER
CH
1

Total Float SI-1

-145

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 29 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CHCC1160

Bitumen primer

1 23-May-15 A 23-May-15 A

-164 Ps

CHCC1170

Tanking membrane

1 24-May-15 A 24-May-15 A

-164 Ps

CHCC1180

Epoxy mortor & sealant

1 25-May-15 A 25-May-15 A

-164 Ps

CHCC1190

GRP accessories

1 26-May-15 A 26-May-15 A

-164 Ps

CHCC1200

DI Manhole Cover & Frame

1 27-May-15 A 27-May-15 A

-163 Ps

CHCC1210

Backfilling

1 28-May-15 A 28-May-15 A

-163 Ps

SI-2

2015
Feb

Mar

Apr

May

Jun

Jul

11 03-May-15 A 13-May-15 A

INSPECTION CHAMBER
CH
3
CHCC11510

Excavation & disposal of materials

1 03-May-15 A 03-May-15 A

CHCC11520

Blinding

1 04-May-15 A 04-May-15 A

CHCC11530

Reinforcement, shuttering, concreting

1 05-May-15 A 05-May-15 A

CHCC11540

Pipe connection to manhole & pre-testing of section

1 06-May-15 A 06-May-15 A

CHCC11550

Benching work

1 07-May-15 A 07-May-15 A

CHCC11560

Bitumen primer

1 08-May-15 A 08-May-15 A

CHCC11570

Tanking membrane

1 09-May-15 A 09-May-15 A

CHCC11580

Epoxy mortor & sealant

1 10-May-15 A 10-May-15 A

CHCC11590

GRP accessories

1 11-May-15 A

CHCC11600

DI Manhole Cover & Frame

1 12-May-15 A 12-May-15 A

CHCC11610

Backfilling

1 13-May-15 A 13-May-15 A

INSPECTION CHAMBER
CH
4

11-May-15 A

28 17-Apr-15 A

14-May-15 A

CHCC11620

Excavation & disposal of materials

1 17-Apr-15 A

17-Apr-15 A

CHCC11630

Blinding

1 18-Apr-15 A

18-Apr-15 A

CHCC11640

Reinforcement, shuttering, concreting

1 04-May-15 A 04-May-15 A

CHCC11650

Pipe connection to manhole & pre-testing of section

1 05-May-15 A 05-May-15 A

CHCC11660

Benching work

1 06-May-15 A 06-May-15 A

CHCC11670

Bitumen primer

1 07-May-15 A 07-May-15 A

CHCC11680

Tanking membrane

1 08-May-15 A 08-May-15 A

CHCC11690

Epoxy mortor & sealant

1 09-May-15 A 09-May-15 A

CHCC11700

GRP accessories

1 10-May-15 A 10-May-15 A

CHCC11710

DI Manhole Cover & Frame

1 11-May-15 A

CHCC11720

Backfilling

1 14-May-15 A 14-May-15 A

REINSTATEMENT FOR CHAMBERS


REINSTATEMEN
CHCC1220

Total Float SI-1

Reinstatement around constructed chamber

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

11-May-15 A

1 31-May-15 A 31-May-15 A

-165

1 31-May-15 A 31-May-15 A

-165

Checked

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 30 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

HOUSE CONNECTION
CONNEC
PHASE 2
SURVEY AND DEMOLISH
D

Finish

128 21-Jan-15 A

28-May-15 A

125 21-Jan-15 A

25-May-15 A

C.HC.P221000

Plot survey

3 21-Jan-15 A

C.HC.P221010

Demolition of ext. underground structures

3 23-May-15 A 25-May-15 A

PIPE WORK IN TRENCH-HC 05

94 24-Feb-15 A

28-May-15 A

Excavation & disposal of materials

75 24-Feb-15 A

09-May-15 A

CSHCP1260

Bedding preparation prior to pipe laying

76 25-Feb-15 A

11-May-15 A

CSHCP1270

Laying pipe & connecting to new manhole

79 24-Feb-15 A

13-May-15 A

CSHCP1280

Granular & concrete surrounds

81 24-Feb-15 A

15-May-15 A

CSHCP1290

Backfilling

82 25-Feb-15 A

17-May-15 A

CSHCP1300

Concrete backfill

93 25-Feb-15 A

28-May-15 A

INSPECTION CHAMBER
CH
5

REINSTATEMENT FOR CHAMBERS


REINSTATEMEN

2 25-May-15 A 26-May-15 A

Reinstatement around constructed chamber

Total Float SI-1

SI-2

2015
Feb

Mar

Apr

May

Jun

Jul

24-Jan-15 A

CSHCP1250

C.HC.P221020

Total Pocess
Delays

2 25-May-15 A 26-May-15 A

HOUSE CONNECTION
CONNEC
PHASE 3
SURVEY AND DEMOLISH
D

148 22-Jan-15 A

18-Jun-15 A

-184

108 22-Jan-15 A

09-May-15 A

-157

24-Jan-15 A

-45

CSTH1070

Plot survey

2 22-Jan-15 A

CSTH1080

Demolition of ext. underground structures

3 07-May-15 A 09-May-15 A
13 26-May-15 A 07-Jun-15 A

PIPE WORK IN TRENCH-HC 06

-155
-177

CSTH1010

Excavation & disposal of materials

5 26-May-15 A 30-May-15 A

-183

CSTH1020

Bedding preparation prior to pipe laying

2 31-May-15 A 01-Jun-15 A

-182

CSTH1030

Laying pipe & connecting to new manhole

4 02-Jun-15 A

05-Jun-15 A

-182

CSTH1050

Backfilling

2 06-Jun-15 A

07-Jun-15 A

-179

CSTH1060

Concrete backfill

2 06-Jun-15 A

07-Jun-15 A

-177

CSTH1040

Granular & concrete surrounds

2 06-Jun-15 A

07-Jun-15 A

-181

11 31-May-15 A 10-Jun-15 A

PIPE WORK IN TRENCH-HC 07 (SI 2)


CSTH12410

Excavation & disposal of materials

5 31-May-15 A 04-Jun-15 A

SI-2

CSTH12420

Bedding preparation prior to pipe laying

2 05-Jun-15 A

06-Jun-15 A

SI-2

CSTH12430

Laying pipe & connecting to new manhole

2 07-Jun-15 A

08-Jun-15 A

SI-2

CSTH12440

Granular & concrete surrounds

2 07-Jun-15 A

08-Jun-15 A

SI-2

CSTH12460

Concrete backfill

2 09-Jun-15 A

10-Jun-15 A

SI-2

CSTH12450

Backfilling

2 09-Jun-15 A

10-Jun-15 A

SI-2

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 31 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

INSPECTION CH
CHAMBER 1 (SI 2)

Finish

Total Pocess
Delays

13 05-Jun-15 A

17-Jun-15 A

-181

Total Float SI-1

SI-2

CSTH1100

Excavation & disposal of materials

1 05-Jun-15 A

05-Jun-15 A

-183

SI-2

CSTH1110

Blinding

1 06-Jun-15 A

06-Jun-15 A

-183

SI-2

CSTH1120

Reinforcement, shuttering, concreting

2 07-Jun-15 A

08-Jun-15 A

-182

SI-2

CSTH1130

Pipe connection to manhole & pre-testing of section

1 09-Jun-15 A

09-Jun-15 A

-182

SI-2

CSTH11300

Benching work

2 10-Jun-15 A

11-Jun-15 A

-182

SI-2

CSTH1140

Bitumen primer

1 12-Jun-15 A

12-Jun-15 A

-182

SI-2

CSTH1150

Tanking membrane

1 13-Jun-15 A

13-Jun-15 A

-182

SI-2

CSTH1160

Epoxy mortor & sealant

1 14-Jun-15 A

14-Jun-15 A

-181

SI-2

CSTH1170

GRP accessories

1 15-Jun-15 A

15-Jun-15 A

-181

SI-2

CSTH1180

DI Manhole Cover & Frame

1 16-Jun-15 A

16-Jun-15 A

-181

SI-2

CSTH1190

Backfilling

1 17-Jun-15 A

17-Jun-15 A

-181

SI-2

13 06-Jun-15 A

18-Jun-15 A

-182

INSPECTION CH
CHAMBER 2 (SI 2)
CSTH1210

Excavation & disposal of materials

1 06-Jun-15 A

06-Jun-15 A

-184

SI-2

CSTH1220

Blinding

1 07-Jun-15 A

07-Jun-15 A

-184

SI-2

CSTH1230

Reinforcement, shuttering, concreting

2 08-Jun-15 A

09-Jun-15 A

-183

SI-2

CSTH1240

Pipe connection to manhole & pre-testing of section

1 10-Jun-15 A

10-Jun-15 A

-183

SI-2

CSTH12400

Benching work

2 11-Jun-15 A

12-Jun-15 A

-183

SI-2

CSTH1250

Bitumen primer

1 13-Jun-15 A

13-Jun-15 A

-183

SI-2

CSTH1260

Tanking membrane

1 14-Jun-15 A

14-Jun-15 A

-183

SI-2

CSTH1270

Epoxy mortor & sealant

1 15-Jun-15 A

15-Jun-15 A

-182

SI-2

CSTH1280

GRP accessories

1 16-Jun-15 A

16-Jun-15 A

-182

SI-2

CSTH1290

DI Manhole Cover & Frame

1 17-Jun-15 A

17-Jun-15 A

-182

SI-2

CSTH1300

Backfilling

1 18-Jun-15 A

18-Jun-15 A

-182

SI-2

5 14-Jun-15 A

18-Jun-15 A

-182

5 14-Jun-15 A

18-Jun-15 A

-182

141 08-Jan-15 A

28-May-15 A

-163

141 08-Jan-15 A

28-May-15 A

-163

97 08-Jan-15 A

14-Apr-15 A

-132

REINSTATEMENT FOR CHAMBERS (SI 2)


REINSTATEMEN
CSTH1310

Reinstatement around constructed chamber

SEWER IN MICTROTUNNEL
MICTR
HOUSE CONNECTION
CONNEC
PHASE 2
SURVEY AND DEMOLISH
D
CSMTHC1390

Plot survey

2 08-Jan-15 A

10-Jan-15 A

-33

CSMTHC1400

Demolition of ext. underground structures

3 12-Apr-15 A

14-Apr-15 A

-130

88 22-Feb-15 A

22-May-15 A

-158

PIPE WORK IN TRENCH-HC 12/13

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

2015
Feb

Mar

Apr

May

Jun

Jul

SI-2

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 32 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

CSMTHC1330

Excavation & disposal of materials

56 22-Feb-15 A

18-Apr-15 A

-138

CSMTHC1340

Bedding preparation prior to pipe laying

54 24-Feb-15 A

18-Apr-15 A

-136

CSMTHC1350

Laying pipe & connecting to new manhole

55 24-Feb-15 A

19-Apr-15 A

-132

CSMTHC1360

Granular & concrete surrounds

54 25-Feb-15 A

19-Apr-15 A

-130

CSMTHC1370

Backfilling

54 25-Feb-15 A

19-Apr-15 A

-128

CSMTHC1380

Concrete backfill

84 26-Feb-15 A

22-May-15 A

-158

31 20-Apr-15 A

25-May-15 A

-158

INSPECTION CHAMBER
CH
1
CSMTHC1420

Excavation & disposal of materials

2 20-Apr-15 A

21-Apr-15 A

-138

CSMTHC1430

Blinding

2 21-Apr-15 A

22-Apr-15 A

-138

CSMTHC1440

Reinforcement, shuttering, concreting

3 22-Apr-15 A

24-Apr-15 A

-137

CSMTHC1450

Pipe connection to manhole & pre-testing of section

2 24-Apr-15 A

25-Apr-15 A

-137

CSMTHC14500 Benching work

3 25-Apr-15 A

27-Apr-15 A

-137

CSMTHC1460

Bitumen primer

2 27-Apr-15 A

29-Apr-15 A

-137

CSMTHC1470

Tanking membrane

2 28-Apr-15 A

29-Apr-15 A

-137

CSMTHC1480

Epoxy mortor & sealant

2 29-Apr-15 A

30-Apr-15 A

-136

CSMTHC1490

GRP accessories

2 30-Apr-15 A

01-May-15 A

-136

CSMTHC1500

DI Manhole Cover & Frame

2 01-May-15 A 02-May-15 A

-136

CSMTHC1510

Backfilling

19 02-May-15 A 25-May-15 A

-158

INSPECTION CHAMBER
CH
2

REINSTATEMENT FOR CHAMBERS


REINSTATEMEN

3 26-May-15 A 28-May-15 A

-161

3 26-May-15 A 28-May-15 A

-161

CSMTHC1630

Reinstatement around constructed chamber

PIPE CONNECTIO
CONNECTION TO EXISTING MH
MANHOLE: Existing
Existi
15/1/28

5 16-Mar-15 A

21-Mar-15 A

-77

5 16-Mar-15 A

21-Mar-15 A

-77

Excavation & breaking existing MH

2 16-Mar-15 A

17-Mar-15 A

-77

CSMM2770

Pripe connection, Epoxy mortor & sealant

2 18-Mar-15 A

19-Mar-15 A

-78

CSMM2780

Backfilling

2 19-Mar-15 A

21-Mar-15 A

-77

233 22-Jul-14 A

22-Jun-15 A

-131

233 22-Jul-14 A

22-Jun-15 A

-132

145 22-Jul-14 A

18-Feb-15 A

-131

SEWER IN TRENCH
TRENC
FINAL TESTING PHASE
P
1
TC.ST.P1.00

Final testing 73m: From MH 15/1/28/14/5 to MH 15/1/28/14/4

1 22-Jul-14 A

22-Jul-14 A

TC.ST.P1.10

Final testing 29m: From MH 15/1/28/14/4 to MH 15/1/28/14/3

1 03-Sep-14 A

03-Sep-14 A

-27

TC.ST.P1.20

Final testing 39m: From MH 15/1/28/14/3 to MH 15/1/28/14/2

1 07-Sep-14 A

07-Sep-14 A

-26

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

SI-2

2015
Feb

Mar

Apr

May

Jun

Jul

CSMM2750

TESTING & COMM


COMMISSIONING

Total Float SI-1

Checked

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 33 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

TC.ST.P1.30

Final testing 80m: From MH 15/1/28/14/2 to MH 15/1/28/14/1

1 05-Feb-15 A

05-Feb-15 A

-124

TC.ST.P1.40

Final testing 68.6m: From MH 15/1/28/14/1 to MH 15/1/28/14

1 18-Feb-15 A

18-Feb-15 A

-131

22 19-Feb-15 A

22-Mar-15 A

-118

FINAL TESTING PHASE


P
2
TC.ST.P2.00

Final testing 71.5m: From MH 15/1/28/14 to MH 15/1/28/15

1 19-Feb-15 A

19-Feb-15 A

-105

TC.ST.P2.20

Final testing 70m: From MH 15/1/28/16 to MH 15/1/28/17

2 19-Mar-15 A

22-Mar-15 A

-118

TC.ST.P2.10

Final testing 60m: From MH 15/1/28/15 to MH 15/1/28/16

2 19-Mar-15 A

22-Mar-15 A

-123

47 15-Apr-15 A

18-Jun-15 A

-143

FINAL TESTING PHASE


P
3
TC.ST.P3.30

Final testing 37m: From MH 15/1/28/19 to MH 15/1/28/20

2 15-Apr-15 A

16-Apr-15 A

-106

TC.ST.P3.40

Final testing 60m: From MH 15/1/28/20 to MH 15/1/28/21

2 16-Apr-15 A

19-Apr-15 A

-99

TC.ST.P3.00

Final testing 70m: From MH 15/1/28/17 to MH 15/1/28/18

1 18-May-15 A 18-May-15 A

-132

TC.ST.P3.20

Final testing 32m: From MH 15/1/28/18 to MH 15/1/28/18/2

1 18-May-15 A 18-May-15 A

-130

TC.ST.P3.10

Final testing 20m: From MH 15/1/28/18 to MH 15/1/28/19

1 27-May-15 A 27-May-15 A

-138

TC.ST.P3.50

Final testing 60m: From MH 15/1/28/919 to MH 15/1/28/19/1

2 17-Jun-15 A

18-Jun-15 A

63 26-Mar-15 A

22-Jun-15 A

-132

COMMISIONING
Commissioning phase 2 (in trench)

13 26-Mar-15 A

13-Apr-15 A

-82

TC.ST.C.10

Commissioning phase 1 (in trench)

17 26-Mar-15 A

19-Apr-15 A

-87

TC.ST.C.30

Commissioning phase 3 (in trench)

4 17-Jun-15 A

22-Jun-15 A

SEWER IN MICRO TUNNEL

38 04-Feb-15 A

30-Mar-15 A

-71

FINAL TESTING PHASE


P
1

16 04-Feb-15 A

28-Feb-15 A

-102

Final Testing 60m: From MH Ex.15/1/28 to MH 15/1/28/1

2 04-Feb-15 A

05-Feb-15 A

-117

TC.SMT.P1.20

Testing 60m: From MH 15/1/28/2 to MH 15/1/28/3

1 10-Feb-15 A

10-Feb-15 A

-96

TC.SMT.P1.30

Testing 60m: From MH 15/1/28/3 to MH 15/1/28/4

1 15-Feb-15 A

15-Feb-15 A

-93

TC.SMT.P1.10

Testing 60m: From MH 15/1/28/1 to MH 15/1/28/2

1 26-Feb-15 A

28-Feb-15 A

-118

12 11-Feb-15 A

01-Mar-15 A

-51

TC.SMT.P2.70

Final Testing 60m: From MH 15/1/28/11 to MH 15/1/28/12

1 11-Feb-15 A

11-Feb-15 A

-47

TC.SMT.P2.10

Final Testing 60m: From MH 15/1/28/5 to MH 15/1/28/6

1 17-Feb-15 A

17-Feb-15 A

-84

TC.SMT.P2.20

Final Testing 60m: From MH 15/1/28/6 to MH 15/1/28/7

1 18-Feb-15 A

18-Feb-15 A

-80

TC.SMT.P2.00

Final Testing 60m: From MH 15/1/28/4 to MH 15/1/28/5

1 19-Feb-15 A

19-Feb-15 A

-91

TC.SMT.P2.30

Final Testing 60m: From MH 15/1/28/7 to MH 15/1/28/8

1 19-Feb-15 A

19-Feb-15 A

-76

TC.SMT.P2.40

Final Testing 60m: From MH 15/1/28/8 to MH 15/1/28/9

1 22-Feb-15 A

22-Feb-15 A

-72

TC.SMT.P2.50

Final Testing 60m: From MH 15/1/28/9 to MH 15/1/28/10

1 23-Feb-15 A

23-Feb-15 A

-67

TC.SMT.P2.60

Final Testing 60m: From MH 15/1/28/10 to MH 15/1/28/11

1 24-Feb-15 A

24-Feb-15 A

-60

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

2015
Feb

Mar

Apr

May

Jun

Jul

-132 Ps

TC.SMT.P1.00

Remaining Level of Effort

SI-2

SI-2

TC.ST.C.20

FINAL TESTING PHASE


P
2

Total Float SI-1

Approved

Document Tittle: Progress Update as per Revised Programme 02


Page 34 of 35
Data Date: 22-Jun-15

Aug

Project ID: IAD-HC13/14C076G.


Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)

Activity ID

Activity Name

Original Start
Duration

Finish

Total Pocess
Delays

TC.SMT.P2.80

Final Testing 60m: From MH 15/1/28/12 to MH 15/1/28/13

1 25-Feb-15 A

25-Feb-15 A

-53

TC.SMT.P2.90

Final Testing 60m: From MH 15/1/28/13 to MH 15/1/28/14

1 01-Mar-15 A

01-Mar-15 A

-51

9 18-Mar-15 A

30-Mar-15 A

-71

COMMISIONING
TC.SNT.C.20

Commissioning phase 2 (in micro tunnel)

9 18-Mar-15 A

30-Mar-15 A

-71

TC.SNT.C.10

Ccommissioning phase 1 (in micro tunnel)

9 18-Mar-15 A

30-Mar-15 A

-72

85 10-Feb-15 A

22-Jun-15 A

-157

CLOSE OUT
A1030

Demobilisation

73 25-Feb-15 A

22-Jun-15 A

-157

A1010

As built data submission & approval

85 10-Feb-15 A

22-Jun-15 A

-157

A1020

Snagging

55 18-Mar-15 A

22-Jun-15 A

-157

Remaining Level of Effort

Second Baseline

Criti...

Actual Level of Effort

Actual Work

Mile...

Primary Baseline

Remaining Work

Date

Revision

Checked

Total Float SI-1

SI-2

2015
Feb

Approved

Mar

Apr

May

Jun

Jul

Document Tittle: Progress Update as per Revised Programme 02


Page 35 of 35
Data Date: 22-Jun-15

Aug

Vous aimerez peut-être aussi