Al-Hajri Corporation
Kingdom of Saudi Arabia
METHOD STATEMENT
FOR
JUNCTION BOX INSTALLATION
Document No.: NSH-KBR-SKOP-PRO-E-007
Job No.: 6484-GC-021-SC-008 &
Job No.:6484-AB-012-SC-009
A
B
C
D
Code
Approved
Approved W/Comments
Rejected
Cancelled
Status ()
Legend
KBR
Name
Comments:
Signature
Date
22-Oct-08
For Approval
S. Augustin
Ponraj
Rev.
Date
Reason for
Issue
Prepared By
Name
Signature
Manoj
Sign
Checked
By
Date
D. Harikumar
Sign
Approved
By
Sign
Page 2 of 6
TABLE OF CONTENTS
1. SCOPE
2. PURPOSE
3. REFERENCE
4. DEFINITION
5. RESPONSIBILITIES
6. TOOLS AND EQUIPMENTS
7. MATERIAL STORAGE, HANDLING & INSPECTION
8. JUNCTION BOX INSTALLATION
9. SAFETY
10. ATTACHMENT
Page 3 of 6
1. SCOPE
This construction procedure covers requirements for the installation of Junction box
in Saudi Kayan Olefins Project. This procedure describes installation techniques and
different requirements to be adhere during execution of Junction box installation
work. It intents to co-relate and control all the tasks needed to be done in order to
get a satisfactory results.
2. PURPOSE
The purpose of this procedure is to ensure all the installation shall be carried out in a
neat, efficient and workmanlike manner, assuring satisfactory / proper operation.
The work shall be in accordance with the requirements of the project specifications,
and shall fulfill their true intent and meaning.
3. REFERENCE
IEC
IEEE
NACE
NEMA
NEC
000-65S-0001
000-65S-0002
000-65S-0057
SES-E05-E01
SES-E23-C01
4. DEFINITION
SKOP
KBR
NSH
Page 4 of 6
5. RESPONSIBILITIES
5.1
5.2
QA/QC Manager
QA/QC Manager is responsible for the implementation of all required quality
control activities and inspection for this particular job.
5.3
QA/QC Engineer
QA/QC Engineer is responsible for the proper carrying out of the inspection
respective to this procedure.
5.4
Electrical Manager
Electrical Manager will be coordinating with concerned personnel at site, plan
the daily work schedule, allocate the job to concerned supervisors, and
controlling the installation works in all the areas.
5.5
Electrical Supervisor
Electrical supervisor is responsible to monitor all day to day field activities,
assuring that implementation is as per this procedure and relevant referenced
standards and as per HSE policy manual.
5.6
The following necessary construction equipment / instrument, tools & tackles shall
be used to carry out the installation works.
Page 5 of 6
7.1
Upon receipt of junction box and accessories, it shall be checked with respect
to project specification, approved construction drawings, manufacturer
catalogue and delivery note.
7.2
Visual inspection shall be carried out to check condition and physical damage
of junction box and accessories.
7.3
7.4
7.5
Cable entry details including gland and gland plate provisions shall be
checked.
7.6
7.7
When outdoor storage is necessary, elevate well above ground and enclose
with durable, waterproof wrapping.
8.1
8.2
8.3
8.4
8.5
8.6
8.7
Any necessary field cuts or welding or any other damage to the galvanized
finish shall be repaired with an epoxy based zinc rich paint.
8.8
All conduit threads shall be fully engaged to the conduit fittings or hubs when
terminating to junction boxes.
Page 6 of 6
8.9
All junction boxes shall be tagged in accordance with the specification and
drawings.
9. SAFETY
9.1
All safety precautions will be taken care as required as per HSE Plan.
9.2
NSH Safety Supervisor shall carry out the safety site inspections to ensure
that safety requirements laid out in the safe work plan are followed during and
after the installation work. NSH Safety Manager / Supervisor shall review
Safety Action Plan and secure Work Permit if necessary prior to start of any
activities shall be strictly followed as per JSA.
9.3
10. ATTACHMENT
JSA
******EEnndd******