Académique Documents
Professionnel Documents
Culture Documents
CERTIFICATION
1
This work was carried out by UKOKOBILI, O.J in the Department of Civil
Engineering, Faculty of Engineering, University of Benin, Benin City and is hereby
certified.
SUPERVISOR:
Name: A.N ANIEKWU
Signature and Date: __________________________
HEAD OF DEPARTMENT
Name: ENGR. DR. C. IZINYON
Signature and Date: ____________________________
DEDICATION
This study is dedicated to Almighty God for the gift of life and His abundant grace
all this years, my parents Mr. and Mrs. A. UKOKOBILI for their parental love, care,
moral teachings and financial support, my siblings UKOKOBILI REBECCA
(Miss),
UKOKOBILI
DANIEL,
UKOKOBILI
PETER,
UKOKOBILI
OSEMUDIAMEN and the family of Hon. and Mrs B.O ASIKHIA for their moral
support.
ACKNOWLEDGEMENT
I am sincerely grateful to God Almighty for giving me the Grace to run and
complete this project successfully.
My gratitude goes to my supervisor A.N ANIEKWU for his fatherly care and
support throughout the period he supervised me, my H.O.D. ENGR. DR. C.
IZINYON, the entire academic staff and other members of staff of the Department,
other members of the University community.
Words are not enough to express my gratitude to my beloved friend PEACE
AMAKA AGHOLOR (Miss) for her support and encouragement especially when
my Laptop was stolen almost at the end of my project, also to Choristers of Gabriels
Catholic Church Choir, Urora for prayers.
TABLE OF CONTENTS
Content
Page
DEDICATION
ACKNOWLEDGEMENT
ii
ABTRACT
iii
TABLE OF CONTENTS
iv
LIST OF TABLES
LIST OF FIGURES
vi
LIST OF SYBMOLS
vii
CHAPTER ONE:
1.1
1.2
1.3
1.4
Introduction
Problem Definition
Aims and Objective
Scope of Study
CHAPTER TWO:
2.1
2.2
2.2
2.3
2.4
2.5
2.1.2
2.1.3
2.2.2
2.2.3
Teamwork...................................................................30
2.3.2
What is a team............................................................33
2.3.3
2.3.4
2.3.5
Implementation.....................................................................42
2.4.1
2.5.1
Team meeting..........................................................45
CHAPTER THREE:
3.0
Methodology.....................................................................50
3.1
Methodology.....................................................................51
CHAPTER FOUR:
4.0
Result...............................................................................53
4.1
Respondent profile......................................................... 53
4.2
Summary of results........................................................99
4.3
Discussion....................................................................101
CHAPTER FIVE:
5.0
Conclusion...................................................................103
5.1
Recommendation.........................................................103
REFERENCES................................................................................... 105
APPENDIX 1......................................................................................109
APPENDIX 2.....................................................................................117
REFERENCES
APPENDIX
ABSTRACT
The Nigeria construction industry is faced with increasing number of
complex and sophisticated design of structure, that requires the urgent need for a
more technical and technological method to improve the performance of project
development in the construction industry.
This study therefore assesses the feasibility of Concurrent Engineering to a
developing construction industry to make construction process less fragmented, to
improve project quality, to effectively keep construction project within deadline.
Thus, avoiding problems that might jeopardize the success of the whole construction
process.
KEYWORDS: Concurrent Engineering (CE) in the Nigeria construction industry.
CHAPTER ONE
1.1 INTRODUCTION
The Nigeria construction industry over the years has been faced with
continuously increasing demand and sophistication of clients, which calls for the
need for changes within the construction industry in its current practices and
project development which include design, procurement, construction, project
delivery etc.
Many of the services and parts of the structure of the modern facilities are
now so technically specialized that they have to be designed by many specialists.
8
10
CHAPTER TWO
2.0 LITERATURE REVIEW
Concurrent engineering which is sometimes called simultaneous engineering
or Integrated Product Development (IPD) is defined as a systematic approach to the
integrated, concurrent design of products and their related processes, including
manufacture and support. This approach is intended to cause the developers, from the
outset, to consider all elements of the product life cycle from conception through
disposal, including quality, cost, schedule, and user requirement.
Concurrent engineering is not a quick fix for a companys problems and its
not just a way to improve engineering performance. Its a business strategy that
addresses important company resources. The major objectives this business strategy
aim to achieve is improved project development performance. CE is a long-term
strategy, and it should be considered only by organisation willing to make up front
investment and the wait several years for long-term benefit. It involves major
organisation and cultural changes.
The problem with project with project development performance that CE
aims to overcome, those of the traditional serial project development process in
which people from different department work one after the other successive phase of
development. In traditional serial project development, the project is first completely
defined by the design team, after which the construction process is defined by the
construction team, etc. Usually this is slow, costly and low-quality approach, leading
to a lot of changes, projects delays and construction errors.
11
examples of very different practice. The modern need for concurrent engineering is
directly related to the increase of size and complexity of industry. The factors which
lead to the rebirth of CE over the past 20 years are not only increased competition,
accelerated development requirements, increased quality requirements, but also the
progress and growth of the post war period. This period of expansion is marked
with increasing over-management and compartmentalization in industry which
caused sequential engineering to develop. The benefits resulting from the
application of CE are the result of large complex entities function as many small, yet
integrated groups. The potential of this is great; by using the skills of many people it
creates a potential reservoir of skill, knowledge and experience far greater than any
individual could ever posses. The results of this approach are seen well before the
early 1980s when CE was rediscovered.
The Ford Motor Company historically utilized many of the ideas found in
modern CE, but lost them after the Second World War and then, over the last two
decades, expended a great deal of energy to reintroduce the same ideas in a
modernization and evolved form. The philosophy of CE is not entirely novel.
Pioneers of the automobile industry, like Henry Ford and Ransom Olds, practiced to
a certain extent the philosophy of what we now call concurrent engineering. During
Ford s early years, (1908-1927) it was by no means small single man operation, yet
they focused on designing a car easily and cheaply mass- produced, this car, the
Model T would be built for 19 years and revolutionize industry and culture around
the world. Designing a car to be easily manufactured and assembled sounds much
like DFA and DFM of modern theory. Not only did Ford use small-integrated teams,
but also as a mechanic, machinist and businessman, he possessed intimate knowledge
of the complete process. As businesses grew in size and complexity, it became much
13
more difficult for a single person to posses all the skills needed to understand the
entire process. The modern education system creates an intrinsic separation between
the people who will build the machines and those who design. In companies such as
Ford where they started with just a handful of people, each performing multiple
tasks, this sort of separation was not such an issue. Admittedly, given the
requirements of modern technology, this sort of educationally separation is largely
inescapable, although through sufficiently broad education and experience it may be
minimized. Following this trend, that compartmentalization is the result of greater
complexity, the subsequent evolution of SE along with the increase in complexity is
natural. As company expands, both in terms of size and interconnection with other
entities, the designer is prevented from taking an integrated approach unless they
enact some deliberate mechanism such as CE to preserve interaction among all the
parties involved.
Some of the best early demonstrations of Concurrent Engineering come out
of American industry during the Second World War. The United States developed not
only an immense production capacity of war material, but also designed and built the
necessary equipment in highly compressed timeframes with high quality results. At
this point Ford still possessed the qualities that had enabled it to development its
early successes. The peacetime engineering philosophy, a legacy of Henry Ford, of
using small, integrated, multidisciplinary teams similar to modern concurrent
engineering practices was extended to Ford s military production. Ford used these
techniques to develop and build trucks, tank engines, jeeps, B-24 bombers and other
important products for the war. A specific and rather impressive example is the
design of the P-51 fighter. The story of this airplanes design demonstrates what
could be done with the combination of CE, time pressure and the willingness to
14
utilize progressive technology. The design process used on the P-51 project was not
called by any special title; it was simply doing what needed to be done, presumably
the way the best of industry functioned at the mid century mark. The P-51 was
developed extremely quickly, although infinitely far from the complexity of modern
aircraft, designing and building a fighter for scratch to a flying prototype in a little
more than three months is truly an impressive feat. This remarkable aircraft was
designed and built in 102 days . . . Compared to a contemporary Spitfire with the
same engine, the Mustang climbed faster, had 50mph greater top speed and had a
much longer range, despite being 1600 pounds heavier. These examples demonstrate
that although very useful and perhaps necessary in the modern environment, it was
possible to rapidly develop complex designs without digital computers, CAD or all
of the modern tools now associated with CE. It cannot accurately be said that
intelligent design practices (such as CE) ever disappeared in a chronological sense, it
is more a matter of increasing limitations and constrains developing to overshadow
what fundamentally sound practice existed. The following is an example of a
company that managed to use fundamentally practices without the benefit of a
formally recognized methodology.
15
while the design was still fluid. We usually got some good ideas from the planners
and machinists when the time was tight and we were all working together at once.
When time wasn't so critical there wasn't so much motivation or the priorities were
on other projects where it was more critical. If vellum was replaced with CAD
system this quote could easily be coming from a contemporary account of applied
CE. Yet this quote is in reference to a company which closed down before the
widespread application of systematic concurrent engineering in the USA. This also
brings up an important change in corporate practice, the fact that Western Gear built
everything they designed is in stark contrast to the practice of most modern
companies, such as Boeing, who essentially design the overall structure and assemble
the parts built by suppliers.
This sort of structure requires more much effort to ensure proper
communication than when parts and being built in the same faculty by employees of
the same company who designed them and is going to do the final assembles. These
issues are now starting to be added with new Internet based tools such as IP Team
mentioned later in the paper, yet these sorts of tools are very new and still uncommon
in industry. The Western Gear example shows that although all industry was not
universally entrenched in a hopeless state of sequentially engineered disaster, the
level of the problem depended on other factors such as the level of outsourcing.
Western Gear was relatively small and specialized in low tech heavy machinery,
these factors helped to create the type of environment where it was possible to do
good design without a formal process. The major difference between what was done
in this example and theory is the lack of a formal plan; what they were doing worked,
but it is impossible to know if anyone knew why this was. Without the awareness of
their practices, there is no motivation to preserve their function as other factors
16
change. This lack of awareness may explain part of the evolution into sequential
engineering. Managers and designers didnt realize that small integrated teams were
an efficient and effective means of structuring design groups, so they adopted new,
and we now can say, less productive strategies as they evolved. An important, or at
least often neglected, point is that the ideas fundamental to concurrent engineering
have long been recognized by at least some portion of academia. These ideas were
not commonly identified within the entire community, but were still at least at times
recognized to some extent. Within the engineering literature there are numerous preW.W.II examples directly referring to the ideas fundamental to concurrent
engineering. The following is an example which dates for 1921, some sixty years
prior to the modern invention of concurrent engineering. It is plain that the
manufacturing designer must take into consideration every circumstance involved in
the production of the commodity.
cooperation with all who will be engaged in the development and operation of the
manufacturing equipment. This will include tool designers and the superintendents
and foremen of the various manufacturing and assembling departments.
It is clear that neither the ideas nor the practices that define CE are inventions
of the past couple of decades. It is however unclear why much of American industry
evolved in such a way that it would eventually require major reform and the
reintroduction of the very ideas and practices which had years before come naturally.
The history of Concurrent engineering, consists of three periods, the first is
the historical application of the ideas without recognition of a formal structure. This
typically took place before the Second World War. During the second phase, which
continued though the early 1980s, the ideas of CE were apparently lost, or were at
17
least prevented from being used by changes in the design environment. The third
period of CE s history, from the early 80 s through present, is characterized by the
resurrection of ideas from the first period along with new tools and methodology,
which were used to adapt to the contemporary design environment. It is fairly clear
what happened during CEs history, the question of why those things happened is not
so clear. In the next section of this paper it will examine this aspect of CE s history
and attempt to developed a plausible explanation for the development of the
environment which lead to the recent popularly of Concurrent Engineering.
2.1.1 THE EVOLUTION OF THE INTERNAL ENVIRONMENT
After the remarkable achievements of the period up through the Second
World War, American design entered into a period characterized by poor design
methodology and then suddenly, around 1980 began to adopt the practices and ideas
which are today called Concurrent Engineering. The literature suggests numerous
explanations for this phenomenon, despite the multitude of theories, no single one is
capable of providing a particularly satisfying explanation. Thus in order to
understand the background as well as is possible, the spectrum of theories will be
considered and appraised. The most common explanation for the transition to CE that
increasing complication of technology and heightened competition forced design
companies to make radical changes in design and management philosophy to remain
competitive. Yet this approach is difficult to support, both with the literature and
through solid reasoning. More importantly the competition theory does not9 explain
how industry came to be in such a state that they could no longer be viable after
years of successful or at least sufficient performance.
approaches to understand the origin of the problem. The first is that the environment
18
changed around industry that design was working fine until something external, such
as foreign competition came along and made the old system no longer viable. The
second is the idea that changes within in structure and organization of the design
environment caused it to become ineffective and unacceptable to both industry and
the end customer. The most probably explanation is a combination of both internal
and external factors combining at the right time to force a change.
2.1.2 CHANGES IN THE EXTERNAL ENVIRONMENT
There are a many potential influencing factors on the adopted of CE. These
include increased cooperation required by new manufacturing technologies, the
change in the availability/cost of communication and information technologies,
internal reluctance to restructuring out of the fear of losing power, the level and type
of training received by engineers and finally a widespread shift towards shortened
lead-times. The first explanation for the change in the design environment is that the
manufacturing processes developed recently require greater cooperation than those of
the earlier period and thus have increased the need for systems such as CE. We
observe the long-standing notion that new manufacturing technologies increase the
need for design-manufacturing integration.
Although its effect is characteristic of an overall increase in complexity,
manufacturing process alone is not responsible for this paradigm shift in design.
While there certainly have been new, complicated technologies developed over the
last decades, all technologies were new at one time and the design environment that
has undergone considerable change over time. There is little new about change in
technology, aside from the its rate. Although a general change in the degree of
cooperation required by new manufacturing technologies is not a major factor in the
19
creation of a need for a new design methodology, a change in the overall complexity
is. In the 1980s companies started to feel the influence of large multinational
organizations on markets, increased product complexities and new developments in
innovative technologies. This directly affected the organizations ability to develop
and introduce new products to the market.
This increase in complexity and technologies made it more difficult to
develop products and hence more difficult to compete. The differences between
companies may also have been increased; the new complex technologies made it
harder to other companies to catch up if a competitor had the advantage of years of
development time. Another factor that has in fact undergone a great deal of change is
the price and availability of the communication and information technologies. The
reinvention of CE and the development of computer technology took place over a
very similar timeframe. Advancements in CAD, CAM, and other computer tools
have greatly enhanced and simplified information storage and sharing, making the
implementation of CE much less expensive.
Although certainly important, the availability and cost of Information
Technology (IT) can only be part of the reason for CE s rebirth, as it shown
elsewhere in this paper there are plenty of examples of CE type practices before the
invention of the transistor. One point this argument does have in its favour is that as
the companies grew and decentralized, the computer tools greatly enhance
communication.
developed, 20+ years after the initial renewed interest in CE began. In the early
1980s CE developed along with CAD, but before the Internet and other tools which
help it to be practical for modern use. There is also an issue of the culture and
20
solution, yet it requires a greater wariness of process and methodology for training in
any sort of design methodology to take place. A final suggestion is that a widespread
trend towards shortened lead-time created a situation that had the potential to benefit
greatly from the application of CE and thus is encouraged its adoption. There have
been changes in the strategic environment that have led to an increased need for and
acceptance of concurrent engineering ideas in recent years
An increase in the
quality expected from the customer is often used to explain the need for CE
implementation. Yet the idea that there was a great deal more competition seems
unlikely. One justification given for the need for increased cooperation in the Product
development process is an increased level of competition. This justification is
21
22
23
quality and lower prices forcing American industry to change in order to compete. In
some industries the Japanese did play an influential role. In many cases the pace was
set by the Japanese, who progressively made inroads in North American and Europe
and in some cases dominated chosen markets. The list of these chosen markets
became longer year by year. The pressure applied by the Japanese would not have
been so important, except that American industry was not positioned to make
changes and did not act soon enough. Western companies attempted to meet this
pressure by applying computer tools without changing their basic structure. This
method did not work; the computer tools alone were insufficient to meet the
challenge.
it possible for some companies to create new successful products, which because of
the technological advantage over the competition placed enormous pressures on
those companies who fell behind.
The effect of forced design cycle reduced the possibility for input from
marketing and manufacturing which resulted in increasingly poor reflection of the
original engineering requirements. One effect of the changing design environment
was the increasing competitive demands and compressed design cycles. To compete
successfully, companies have to continuously keep reducing development times and
sustain improvements in their products and their quality. The need for better quality
and shorter product development lead times is now widely acknowledged and the
realization that the concurrent engineering approach offers the best way of achieving
these objectives has also became a necessary company strategy.
These pressures helped to trigger the change to new methods and attitudes
about design. Concurrent engineerings history may be considered from the premise
that it was introduced to combat internally sourced problems in the design
environment. This problem is characterized by the phenomenon, now identified as
Sequential Engineering (SE). It was not so much a theory, as a symptom of the ills
affecting industry. The alternative to concurrent engineering had strong
organizational separation between design, manufacturing and marketing, and/or to
separate the functional design of the product from production design and
manufacturing process design. There were, and continue to be many problems with
SE, one of the particularly weak areas is an inadequate understand of product
specifications, including not only those of the purchase customers, but also Design
for Manufacturing (DFM) and Design for Assembly (DFA). DFM and DFA are
25
ironically areas that were previously strong in American industry. Henry Ford in the
early 1900 s and Ford Motor Co through the 1940 have used DFM/DFA, yet they
were lost in the post-war expansion. (This is explored in depth earlier in the paper)
Concurrent Engineering offers simple, yet powerful instruments such as QFD to
combat some of SEs failures. QFD is a structured approach to defining customer
needs or requirements and translating them into specific plans to produce products to
meet those requirements which requires no computer technology or advanced
communications ability to implement only the knowledge of their existence. Despite
its appealing nature QFD was not first introduced in the USA until 1984. QFD also
combats SEs failure to perform accurate cost estimates, this is reflected in fire
fighting late stage design changes. These changes resulted from poor specification
understand and a lack of DFM. Yet these simple, low-tech tools were not adopted
initially Western companies, instead they attempted to meet the challenge of their
foreign competitors by using new computer technology within their existing systems.
These attempts can at best be called a Band-Aid solution that was largely
unsuccessful despite the expense and attractive nature of computer technology.
Without the proper structure, computer tools were used simply as a direct
replacement for older technology for such tasks as drafting and did very little to
alleviate the problems of SE. This expensive technology was largely ineffective,
because the new tools were used with existing structures, practices and attitudes.
Within the SE environment, application of the new computer technology did not help
the situation. Products continued to arrive in the market place at unsatisfactory
quality levels, and often too late to achieve sales and profit objectives.
Real
progress would require both the computer tools and the intentional adoption of
progressive design methodologies. All of the factors discussed played some role in
26
bringing about CEs modern development and popularly. It is not possible to choose
a single factor which was responsible, other than to say that a lack of historical
perspective, both in the modern and historical engineering communities caused them
to fail to understand what practices worked or if their new and improved practices
were actual an improvement. The design environment, both internal and external,
underwent a great deal of change in the past century and a half since the industrial
revolution began, and at least during the portion of the twentieth century, engineering
design philosophy did not always adapt along with the environment.
2.1.3 THE REINVENTION OF CE
The reinvention , reintroduction and adaptation of concurrent engineering
which has taken place over the past 20 years is one of the most ironic, almost
comical, aspects of CE s history. It is akin to European reintroduction of the Greek
classics from the Islamic Moors. The very ideas that had originally defined Western
throughout were lost for 500 years before being reintroduced from a foreign culture.
Although CE was lost for closer to 50 years, it might still be appropriate to call the
SE era the Dark Ages of design methodology.
Even
once
sequential
engineering was recognized as needing a replacement, the process of change was not
an easy one. It could be argued that many factors remain that17 inhibit the complete
adaptation of CE s principles. Ideas that were perceived as coming from Japan are
important in the re-creation process. At the beginning of the 1980 s American
corporations such as Ford set up programs to learn design from a group perceived as
being more skilled then could be found domestically: the Japanese. It has been
practiced by successful manufacturing managers, but no one has paid much attention
to applying it in a systematic way.
27
using its name, for some time. This is clearly illustrated by the studies done in the
automotive industry, comparing the time to market of Japanese and European
manufactures.
Although Japanese industry may certainly claim credit for further developing
the ideas and the creation of some tools for CE, it was ironically an American, Dr. W.
Edwards Deming who thirty years before had introduced CE to Japan after Second
World War. In 1981 the American Supplier Institute (ASI) and Ford (ASI was
previously called the Ford Supplier Institute) brought Deming back to the United
States to help them develop CE in the USA.
28
French aeronautical company started working with CADAM systems in 1975, when
they acquired one from Lockheed. This system proved inadequate so they began
developed an own proprietary software in 1977. IN 1985, CATIA V.2 was released
with fully integrated drafting, solid and robotics functions. It took a couple of more
years before IBM joined and CATIA was used in the USA.
In '87-'88 Boeing was beginning to focus on CATIA which had the capability
of being used by both engineering and manufacturing. At first it was being used
mostly as a drafting machine but gradually as people learned how to use it was used
for layouts (initial engineering) and we started to talk about eliminating the paper
drawings and only using data sets, both for design and planning.
CATIA is important because it was more than a computer system used to
generate drawings, but also provided tools which could be used to promote the
sharing of information and connecting manufacturing and design within the same
computer system. This paper has stressed that the ideas and concepts that define
concurrent engineering were well established in both industry and academia prior to
the 1950, yet there are some important differences that characterize the modern
incarnation. It could be argued that what is new about concurrent engineering
practice is not the adoption of any individual element of this package, but rather the
adoption of all of this approach, and its synthesis into a novel method for product
development.
Modern CE is not only using many of the different techniques, more
importantly it is the acknowledgment of a definite systematic strategy to overcome
the factors which create compartmentalization and poor cooperation and
communication. As has been demonstrated historically, CE can be practiced with
29
great success in certain special situations without the benefit of computers or even a
formal methodology. Yet such situations are a rarity in the modern world of bigger
companies, more complex products, shortened design cycles and dispersed
development teams. This [informal/unorganized] type of CE practice exists in very
small companies who have very skilled and experienced people in their
organizations. So while for the sake of argument CE is not new, it did not develop
until the early 80s because it did not make economic sense, the pressures were not
high enough and the tools were not yet available earlier to enable large corporations
to adopt CE. Future considerations one final historical note (further study). It strikes
the author that there must be some connection between the industrial atmosphere of
the Cold War period, and the nature of evolution away from concurrent engineering
practices. Although there must be some mention of it in the literature it is well hidden
and the author of this paper was not able to find anything about the effects of the
Cold War on design methodology. It does not seem, or perhaps it is still classified,
that there were the same great feats of engineering as during the Second World War.
Yet the movement back to concurrent engineering came from the military sector
which
2.2 BUILDING BLOCKS FOR CONCURRENT ENGINEERING
A feasible approach to part count reduction is to design multi-use or "building block"
parts that can be used interchangeably in a variety of different products, product
models, or applications. For example, with the right standardization scheme, the
same mounting plate can be used to mount a variety of different components. Multiuse parts reduce manufacturing information content by reducing the number of part
variations that need to be manufactured. They produce economies of scale because of
30
increased production volume of fewer parts and economies of scope because the
same part is being used in a variety of applications and products.
2.2.1 FACTORS OF GOOD PRODUCT DEVELOPMENT
The first step in achieving a simple design is to develop a systematized
product structure which standardizes the relationship between product function, form
and fabrication.What are product development tasks?
2.2.2
IMPORTANT
FACTORS
IN
CONCURRENT
ENGINEERING
PRACTICE
1. ORGANIZATIONAL FACTOR
a. Cross-functional Teams - Project team members gain a better
understanding of project priorities and process discipline, making risks and
compromises visible for better control. The design team is composed of
experts from engineering, production, marketing and any other functional
area which has a vested interest in the development project. The team is
formed to work on a specific project, and stays together throughout the
31
development of the product. This approach seems more recent, as it has been
discussed throughout the forties, fifties, and sixties as a viable mode of
accomplishing complex development work.
b. Liaison Personnel - Liaison personnel are not members of any
functional piece of an organization, but rather people who are capable and
prepared to address issues which span functional organizational
boundaries. Liaison Personnel have as their full-time job the coordination
of the disparate functions. Under this approach, they become the primary
modes of accomplishing information transfer between functional areas.
c. Job Rotation - Job Rotation means to rotate personnel between
functional categories. These personnel are assigned temporarily or
permanently outside of their accustomed functional specialty, which is a
manufacturing engineer will work with design engineers or vice versa.
Thus it is possible to integrate the
2.
3.
characteristics
interoperability,
such
as
simplified
35
Six hundred compressors were "life tested" by running them continuously for
two months under temperatures and pressures that were supposed to simulate five
years of actual use. Not a single compressor failed, and the good news was passed up
the management ladder. During testing, technicians noticed that many of the motor
windings were discoloured from heat, bearing surfaces appeared worn, and the sealed
lubricating oil seemed to be breaking down. This bad news was not passed up the
management ladder!
GE offered a five year warranty on the refrigerators, but they could not wait
five years before beginning full-scale manufacturing. Evaluating a five -year life
span based on two months of testing is tricky, so the original test plan was to fieldtest some refrigerators for two years before full-scale manufacturing began. Pressure
to stay on schedule reduced this test time to nine months.
By the end of 1986, GE had produced over one million new compressors.
Everyone was ecstatic over the new refrigerators; however, in July of 1987 the first
refrigerator failed. Quickly thereafter came an avalanche of failures, and the
engineers could not fix the problems. In December of 1987, GE started buying
foreign compressors for the refrigerators. Finally, in the summer of 1988 the
engineers made their report. The two powdered-metal parts were wearing
excessively, increasing friction, burning up the oil, and causing the compressors to
fail. GE management decided to redesign the compressor without the powderedmetal parts, and in 1989 they voluntarily replaced over one million defective
compressors.
36
about the technical paper. In the test (100 points) one makes 70 points and the other
one gets 50 points.
When discussion begins, they can neutralize each other and they will be
confused about the situation, the data and the logic necessary to make a good
decision. The media can be reducing to 60 or 50 at the end of the discussion. It
means that they are going to be in an incomprehension state. Thats not impressive.
In other hand, they can joy their knowledge and get in comprehension levels.
In this case, the action represents a 60: above the decision that could take the team
mate less prepare, but below the decision of the best prepare of them. Thats not
impressive too.
Exist a third possibility: if each of them put his knowledge to the disposition
to the other they can resolve the situation using the free and sincere dialogue. The
final point is going to be 99. Thats impressive.
Synergy Team Work is an intelligent group working together. Team Work
brings impressive results if the members of the group give all their dedication, effort,
information and recommendations to get the goals.
The project team approach has been proven to be the most successful
organizational structure used to implement new product development. One of the
most important factor in the future success of the concurrent engineering effort is the
acquired knowledge of ilities in the design and development of engineering team.
The goal of concurrent engineering is the interactive work of different
disciplines that affect a product to make it better.
38
Team work
managerial support
A team will constitute and develop with expert care. It could adopt a lot more
of the sum of individual as an entity. Some teams will pass an unknown barrier and
will reach to a phase of super execution.
An important aspect when the team development stated and its success is the
fact that they should count with a support structure so much from the administration
as internal and external counsellors.
The four fundamentally different types of teams we just looked at are based
on two defining characteristics: the need for coordination of actions among team
members and the degree of specialized or discrete skills needed within the team to
perform. Regardless of the type of team, there are common characteristics all team
configurations have that clearly differentiate them from groups or collections of
individuals. This is an important distinction. Many companies are using the bowling
or home-care model to form groups, but in no way have they created a fully
functioning team.
A team has a common:
Purpose
Awareness of the customer needs that the teams efforts are addressing
40
Regardless of the type of team, these factors remain common- they are the
defining qualities of teaming. Without them, there is no team, merely a collection of
individuals.
2.3.3 MULTIFUNCTIONAL PRODUCT DEVELOPMENT TEAM
In the best form of basic concurrent engineering, each product is developed
by a multifunctional product development team (PDT). The PDT makes all decisions
about the product design, production system, and field-support system. Although the
PDT must grow and then later shrink in size and, in so doing, change its composition
somewhat, there is never any sudden change. In particular, at the transitions in
process phases, there are not any sudden changes in the PDT. Continuity is
maintained; throwing results over the wall is avoided. All decisions are made with
the full participation of the people who have all of the relevant knowledge.
Basic concurrent engineering is best carried out by a multifunctional product
development team (PDT) led by a strong product manager. All functions of the
corporation should participate. People who are doing significant work for the specific
product development program should be part of the PDT while they are doing the
programs work. There is a vast psychological difference between performing a task
within a support group and performing it as a member of the PDT. As a PDT
member, the contributor will:
All three of these benefits are much less likely to materialize if the
contributor remains outside the PDT. It is important that the people on the PDT from
each function be able to:
gain the commitment of that function to the decisions that are made.
42
44
A further development was the pyramid structure. Cadillac has adopted the
pyramid as the symbol Simultaneous Engineering. At the base or foundation,
is the Cadillac executive staff who supports and nurtures the process with the
ultimate objective of satisfying our customers-at the top of the pyramid.
The role of top management in the simultaneous engineering environment is
to:
flourish
Any time an organization sets out to make a significant change in the way it
does business, it is going to take a great deal of time and education for all employees
to make it work. But, without top managements leadership, support, patience, and
commitment nothing will be accomplished. Next on the pyramid is the steering
committee whose job is to:
45
Next are vehicle teams that are responsible for managing all steps of product
development in their vehicle program. Each vehicle team comprises members
representing all staffs of the organization. The roles of the vehicle team are to:
Develop the vehicle strategy including defining the target market and
specific demographics. This vehicle strategy must be consistent with the
overall divisional strategy.
Assure the needs and expectations of the customers are met or exceeded.
As Cadillac developed the structure for simultaneous engineering, the car was
sectioned into specific vehicle systems and created six corresponding vehicle system
management teams. These were the exterior component/body mechanical,
chassis/power train application, seats and interior trim, electric/electronic, body-inwhite, instrument panel/heating, and air-conditioning systems. The role of each one
46
of these vehicle system management teams was to manage their vehicle system in
order to optimize the business decisions that are made in that area of the vehicle.
The vehicle system management teams and the vehicle teams are in the same
layer of the pyramid. This symbolized their partnership and interdependence to
accomplish the task.
The product development and improvement teams (PDITs) are responsible
for the actual design of components that are part of the six vehicle systems. Each
PDIT has varying core memberships, depending on its purpose, but can draw
members from any area of the organization and suppliers. One hundred percent of the
vehicle is covered by these simultaneous engineering teams.
In some companies the simultaneous engineering approach calls for product
development teams (PDTs). These teams include process and product engineers in
the development phase of products, and then disband when the particular product
goes into production. Unlike these PDTs, Cadillacs PDITs have cradle to grave
responsibility for the productions and continuous quality improvement of that
component or part. Cadillac PDITs focus on all business aspects of their assigned
portion of the vehicle: quality, cost, timing, technology, reliability, and profitability.
It is as if they are running their own business. Cadillac eventually created 66 PDITs
with an average of eight team members.
The structure of the pyramid is similar to a matrix organization structure
although Cadillac has formally maintained its centralized functional structure. Each
team member still reports to a staff area and has other assignments as well. With the
exception of the vehicle teams, all other simultaneous engineering teams elect their
47
own chairpersons and do not have a manager as in typical matrix structure. The
teams receive expectations and leadership from the next team down in the pyramid.
Each of the vehicle systems management teams is responsible for business
decisions concerning its systems, as well as determining what vehicle subsystems
require the formation of PDITs. Each PDIT, in turn, has similar business decisionmaking responsibilities at a component or subsystem level.
The vision was developed and the structure was determined. Roles and
responsibilities were defined and the strategy for simultaneous engineering was
ready for the next stage of implementation. The new expectations of team members
would require them to learn about other part of the business. In addition, most team
members were familiar with planning and decision-making in the context of their
individual staff, but not with cross-staff teams. Normally this type of decisionmaking is not experienced in a centralized organization except at the executive staff
level. The need to develop consensus decision-making skills and teamwork was
acknowledged. A great need existed to provide education and training.
2.4 IMPLEMENTATION
Change takes time and education. In November of 1985, an organization
event was held to communicate the plan. It was considered important to
communicate the design for simultaneous engineering to those who had originally
met in January as a follow-up since they had empowered the steering committee. It
was also considered important to communicate to significant others who would
eventually be called upon to staff the simultaneous engineering teams. The meeting
was designed to be interactive. All questions were documented and a response was
48
Cultural Change
3.
4.
Planning
5.
Esprit de Corps
49
similar to those for VSMTs but included more emphasis on problem solving
techniques. They, unlike the four day VSMT kick off, were delivered in three phases:
Phase 1: Simultaneous engineering, business, and systems information.
Phase 2: Team building and planning
Phase 3: Problem solving (applied to product quality).
2.5 PROJECT TEAM STRUCTURE
Project team structure consists of an autonomous project team, existing
independently of the rest of the organization. The project team is assembled for a
specific project under the action of the product manager. The team is thus temporary
and will be disbanded when its project is complete.
Sometimes we can find design or products with special requirements that are
not encompassed within one or more of the functions. This will lead to cooperative
efforts of marketing, production, engineering, and others as appropriate; as well as
assistance from the accounting legal, and contracting staffs. When it is an important
new effort, a dynamic and capable person from the upper levels of middle
management is selected to take responsibility for this unique activity. A project is
organized around this project manager, and then a few specialized assistants are
provided and a project team is formed. The project manager exercises direct and
autonomous control over the various discipline groups and is responsible for the
coordination and monitoring of the effort of the team. Since most major
organizational functions will be affected by this team, it is typically removed from
the functional organizations structure.
50
Flexibility
The actual organizational power and authority of the team manager may
be a delicate issue.
51
Be specific.
Consider the needs from all the involve individuals during the
action.
A different point of view should stand out when the person receive a critic:
Maintain the calm, breathing deeply during the time the critics
will be done.
53
2.6 BENEFITS OF CE
Concurrent Engineering is a system of practices that companies can employ so that
their engineering and production departments work together in the most streamlined
manner possible.
When the processes between the two groups are organized correctly through a
systematic methodology, the work flow and exchange of information is extremely
efficient and problems that would otherwise slow down the processes are avoided.
Potential benefits of Concurrent Engineering include a shorter cycle to get
new product to market, a quicker turnaround time for issues with product quality that
require engineering time and a smaller number of changes made to a product or its
process during its life cycle. Another benefit is that employees then require less time
learning how to produce new or improved products, thereby enabling engineers to
have higher visibility when it comes to knowing exactly what is going on in the shop
floor operations. Concurrent engineering also produces a continual streamlining of
processes so they can continue to be consistently duplicated. Concurrent Engineering
focuses on the process by which a product is manufactured.
The practices also prioritize the time spent putting together a manufacturing
process which works to bring a quality product to market quickly and at a reasonable
54
cost. The process is considered as important as the product design itself. For
example, even if you have the blueprint for the next iphone in your head, what value
is it if you do not take the time to detail the process of bringing your idea to fruition?
So without a validated plan, essentially you plan to fail. The main ingredients
of Concurrent Engineering are integrated tools and data. Though engineering and
manufacturing are closely related, each department's tools and data are often
managed separately, which can lead to inefficiencies. With Concurrent Engineering,
the manufacturing data models are created directly from their engineering
predecessors with tightly integrated change management.
Integrated processes for managing changes and digital validation of the product and
process streamline shop floor changes.
Previously, the manufacturing shop floor would have to basically work
around engineering. Often, changes would be tested on the shop floor, only to have
to be redone and reworked on later. Integrating the processes eliminates this. Having
a collaborative culture and environment also allows product engineers to spend a lot
of time on the shop floor effectively evaluating the success of their designs. When
the value in the corporate culture changes to emphasize reducing the number of
changes in the process rather than being able to pump changes out more quickly, then
Concurrent Engineering strategies works at their best.
So, as complex as the technology and methodology might sound, it basically
circles around one idea, that of working together.
55
CHAPTER THREE
3.0 METHODOLGY
The purpose of this study is to determine the level of awareness, factors,
benefits, constraints and readiness of CE in Nigeria as a developing construction
industry. This chapter therefore explains the method and mode used for collecting
datas.
In order to access CE in the Nigeria construction industry, a case was carried
out by using questionnaires which was administrated to Consultancy firms,
Contracting firms, Materials suppliers, and Clients. One of the reason for carrying
out this case study is the fact that, it will help to solve current problem through an
examination of what happened in the past and which is happening now, and this will
save a lot of time.
In this study, questionnaires were designed to sample relevant information
needed to access the feasibility of CE in the Nigeria construction industry.
The five-point Linker-type scale was used to measure a range of
opinions from Strongly Agree to Strongly Disagree in the designed
questionnaires. The significant agreement or otherwise with the notion being tested
was determined by adopting the mid-point value of the index (that is 3) as the
hypothesized mean (Coakes and Steed, 2001). This implies that any result
significantly different from this uncommitted or unsure value was assumed to be
either positive or negative to the notion being tested (Pullin and Haidar, 2003).
A
56
57
deviation is small enough that chance alone accounts for it. A p value of 0.6,
for example, means that there is a 60% probability that any deviation from
expected is due to chance only. This is within the range of acceptable
deviation.
conclude that some factor other than chance is operating for the deviation to
be so great. For example, a p value of 0.01 means that there is only a 1%
chance that this deviation is due to chance alone. Therefore, other factors
must be involved.
CHAPTER FOUR
4.0 RESULTS
The result of this study are presented and discussed in this chapter. The major
purpose of this was to examine:
58
1.
2.
3.
4.
From the total 65 respondents received, 22 (33%) were contractors, 18 (27.7%) were
consultants, 10 (10%) were client, 11 (17%) were material suppliers and while the
other 4 (6.2%) were suc-contractors.
59
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
1
12
0
0
fo
strongly Disagr
row
D
ee
total
2
0
3
18
0
4
6
10
11
10
21
12
11
25
60
fe
fo-fe
(fo-fe)
(fo-fe)2
/fe
60
0.04
0.0333
33
0.44444
44
0.6666
67
0.53777
78
0.16
0.7333
33
1.8285
71
19.6
2
2.2
4.2
0.0666
67
1.77777
78
1.3333
33
2.15111
11
1.4666
67
3.6571
43
3.3
2.5606
06
4.4133
61
0.8889
61
2.7
0.8066
67
0.4378
79
0.1785
71
53.071
76
1.2
0.6666
67
0.7333
33
-0.2
0.666666
7
0.733333
3
3
12
0
0
0
1.4
3.6
2
2.2
4.2
1.6
8.4
-2
-2.2
-4.2
2.56
70.56
4
4.84
17.64
2.4
1.3333
33
1.4666
67
-0.4
1.333333
3
1.466666
7
2.8
3.3
1.8333
33
2.0166
67
3.2
-3.3
2.166666
67
2.983333
33
10.24
10.89
4.69444
44
8.90027
78
3.85
7.5
4.1666
67
4.5833
33
-1.85
-4.5
1.833333
33
1.416666
67
3.4225
20.25
3.36111
11
2.00694
44
10
8.75
1.25
1.5625
6
0
4
5
2
3
6
Since our x2 statistic value (53.07176) exceed the critical value for 0.05 probability
level, we can reject the null hypothesis that the professionals in the industry are not
aware of CE.
RESEARCH QUESTION 2: I participated in its usage;
61
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
0
10
0
3
strongly Disagr
row
D
ee
total
5
3
0
18
1
4
2
10
11
13
22
22
19
61
fo
fe
0
0
2
0.8852
46
0.4918
03
0.5409
84
10
1.0819
67
6.4918
03
3.6065
57
3.9672
13
7.9344
26
5.6065
57
3.1147
54
0
13
3
4
2
0
3.4262
3
6.8524
59
2.6557
38
1.4754
1
1.6229
51
3.2459
02
fo-fe
0.885245
9
0.491803
3
1.459016
39
0.081967
2
3.508196
72
0.606557
4
2.967213
1
0.065573
77
0.606557
4
2.114754
1
3.426229
5
6.147540
98
0.344262
3
2.524590
16
0.377049
18
3.245901
(fo-fe)
(fo-fe)2
/fe
0.78366
03
0.8852
46
0.24187
05
2.12872
88
0.4918
03
3.9349
23
0.00671
86
12.3074
44
0.0062
1
1.8958
44
0.36791
19
0.1020
12
8.80435
37
0.00429
99
2.2192
79
0.0005
42
0.36791
19
0.0656
22
4.47218
49
1.4358
07
11.7390
49
37.7922
6
0.11851
65
6.37355
55
0.14216
61
10.5358
77
3.4262
3
5.5151
38
0.0446
27
4.3198
54
0.0875
97
3.2459
02
62
2.3606
56
1.3114
75
1.4426
23
2.8852
46
0
2
6
2.360655
7
0.688524
59
4.557377
05
2.885245
9
5.57269
55
0.47406
61
20.7696
86
2.3606
56
0.3614
75
14.397
17
8.32464
39
2.8852
46
47.681
18
Since our x2 statistic value (47.68118) exceed the critical value for 0.05 probability
level, we can reject the null hypothesis that the professionals in the industry are not
aware if they have participated in it usage.
RESEARCH QUESTION 3: Government new policies will raise cost of project
execution
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
5
8
5
3
strongly Disagr
row
D
ee
total
0
3
2
18
1
1
0
10
11
10
10
22
26
25
61
fo
fe
5
5
6
10
8
3
7.6721
31
4.2622
95
4.6885
25
9.3770
49
7.3770
49
4.0983
fo-fe
(fo-fe)
2.672131
1
0.737704
92
1.311475
41
0.622950
82
0.622950
82
-
7.14028
49
0.54420
85
1.71996
78
0.38806
77
0.38806
77
1.20639
(fo-fe)2
/fe
0.9306
78
0.1276
8
0.3668
46
0.0413
85
0.0526
05
0.2943
63
61
4.5081
97
9.0163
93
0.2950
82
0.1639
34
0.1803
28
4
10
0
0.3606
56
2.0655
74
1.1475
41
1.2622
95
0
3
2.5245
9
0.5901
64
0.3278
69
0.3606
56
0.7213
11
1.098360
7
0.508196
7
0.983606
56
0.295082
0.836065
57
0.180327
9
0.360655
7
0.934426
23
0.147541
0.262295
1
0.524590
2
1.409836
07
0.327868
9
0.360655
7
0.721311
5
61
61
0.25826
39
0.96748
19
0.08707
34
0.69900
56
0.0572
88
0.1073
03
0.2950
82
4.2639
34
0.03251
81
0.1803
28
0.13007
26
0.87315
24
0.02176
83
0.3606
56
0.4227
17
0.0189
7
0.06879
87
0.0545
03
0.27519
48
1.98763
77
0.1090
06
3.3679
42
0.10749
8
0.3278
69
0.13007
26
0.3606
56
0.52029
02
0.7213
11
12.461
12
Since our x2 statistic value (12.46112) did not exceed the critical value for 0.05
probability level, we can accept the null hypothesis that the Government new
policies will raise cost of project execution.
RESEARCH QUESTION 4: The approval and licensing polices of the government
are favourable.
64
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
5
8
4
1
fo
strongly Disagr
row
D
ee
total
0
5
0
18
2
2
1
10
11
22
14
12
11
17
61
fe
fo-fe
(fo-fe)
4.1311 0.868852 0.75490
5
48
46
46
2.2950 1.704918 2.90674
4
82
03
55
2.5245 1.524590 2.32437
1
9
2
52
5.0491 1.049180 1.10077
4
8
3
94
3.5409 4.459016 19.8828
8
84
39
27
1.9672 0.967213 0.93550
1
13
1
12
2.1639 1.163934 1.35474
1
34
4
33
4.3278 2.327868 5.41897
2
69
9
34
3.2459 3.245901 10.5358
0
02
6
77
1.8032 0.196721 0.03869
2
79
31
93
1.9836 1.983606 3.93469
0
07
6
5
3.9672 5.032786 25.3289
9
13
89
44
5.0163 0.016393 0.00026
5
93
4
87
2.7868 0.786885 0.61918
2
85
2
84
3.0655 1.934426 3.74200
5
74
23
48
5 6.1311
- 1.27949
(fo-fe)2
/fe
0.1827
35
1.2665
11
0.9206
94
0.2180
11
5.6150
58
0.4755
46
0.6260
56
1.2521
11
3.2459
02
0.0214
61
1.9836
07
6.3845
68
5.36E05
0.2221
79
1.2206
54
0.2086
65
48
2.0655
74
1.1475
41
1.2622
95
2.5245
9
0
1
1.131147
5
2.065573
8
0.147541
2.737704
92
0.524590
2
48
88
4.26659
5
0.02176
83
7.49502
82
2.0655
74
0.0189
7
5.9376
2
0.27519
48
0.1090
06
31.975
Since our x2 statistic value (31.975) exceed the critical value for 0.05 probability
level, we can reject the null hypothesis that the approval and licensing of the
government are not favourable.
RESEARCH QUESTION 5: Plant/equipment would be fundamental for success.
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
16
1
8
1
fo
strongly Disagr
row
D
ee
total
0
1
0
18
0
1
0
10
11
13
20
40
11
59
fe
fo-fe
(fo-fe)2
12.203 3.796610 14.4142
16
39
17
49
6.7796 1.220338 1.48922
8
61
98
72
7.4576 4.457627 19.8704
3
27
1
4
13.559
- 0.31284
13
32 0.559322
11
3.3559 2.355932 5.55041
1
32
2
65
1 1.8644
- 0.74719
(fo-fe)2
/fe
1.1811
68
0.2196
61
2.6644
45
0.0230
72
1.6539
12
0.4007
66
07
2.0508
47
3.7288
14
0.6101
69
0.3389
83
0.3728
81
0.6779
66
1.5254
24
0.8474
58
0.9322
03
1.6949
15
0.3050
85
0.1694
92
1
1
0
1
0.1864
41
0.3389
83
0.864406
8
1.949152
54
1.271186
44
0.610169
5
0.338983
1
1.627118
64
0.677966
1
0.525423
7
0.152542
37
1.067796
61
0.694915
3
0.305084
7
0.169491
5
0.186440
7
0.661016
95
91
3.79919
56
1.61591
5
7
1.8525
0.4333
59
0.37230
68
0.6101
69
0.11490
95
2.64751
51
0.3389
83
7.1001
54
0.45963
8
0.6779
66
0.27607
01
0.02326
92
1.14018
96
0.1809
79
0.0274
58
1.2231
12
0.48290
72
0.2849
15
0.09307
67
0.3050
85
0.02872
74
0.1694
92
0.03476
01
0.43694
34
0.1864
41
1.2889
83
20.822
63
Since our x2 statistic value (20.82263) did not exceed the critical value for 0.05
probability level, we can accept the null hypothesis that the Plant/equipment will be
fundamental for success
67
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
1
1
6
3
strongly Disagr
row
D
ee
total
2
5
9
18
0
0
1
10
22
11
12
12
13
16
61
fo
fe
1
6
1
4
3.5409
84
1.9672
13
4.3278
69
2.1639
34
3.5409
84
1.9672
13
4.3278
69
2.1639
34
2.3606
56
1
3
5
0
4
2
5
0
7
1.3114
75
2.8852
46
1.4426
23
3.8360
66
2.1311
48
4.6885
25
fo-fe
2.540983
6
4.032786
89
3.327868
9
1.836065
57
2.540983
6
1.032786
89
0.672131
15
0.836065
57
0.360655
7
1.311475
4
1.114754
1
0.557377
05
1.163934
43
2.131147
5
2.311475
41
(fo-fe)
(fo-fe)2
/fe
6.45659
77
16.2633
7
1.8233
91
8.2672
13
11.0747
11
3.37113
68
2.5589
29
1.5578
74
6.45659
77
1.06664
88
0.45176
03
0.69900
56
1.8233
91
0.5422
13
0.1043
84
0.3230
25
0.13007
26
0.0551
1.71996
78
1.24267
67
0.31066
92
1.35474
33
1.3114
75
4.54178
98
5.34291
86
2.1311
48
1.1395
74
0.4307
0.2153
5
0.3531
6
68
2.3442
62
4.7213
11
2.6229
51
5.7704
92
2.8852
46
1.344262
3
4.278688
52
1.622950
8
0.770491
8
1.885245
9
1.80704
11
18.3071
75
0.7708
36
3.8775
61
2.63396
94
1.0042
01
0.59365
76
0.1028
78
3.55415
21
1.2318
37
29.624
24
Since our x2 statistic value (29.62424) exceed the critical value for 0.05 probability
level, we can reject the null hypothesis that CE is for smaller small firms and
younger person.
RESEARCH QUESTION 7: It will improve productivity
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
13
5
4
4
fo
strongly Disagr
row
D
ee
total
0
0
0
18
0
1
1
10
11
10
10
22
30
23
61
fe
fo-fe
(fo-fe)2
8.8524 4.147540 17.2020
13
59
98
96
4.9180 0.918032 0.84278
4
33
8
42
5.4098 2.409836 5.80730
3
36
1
99
10 10.819
- 0.67186
67 0.819672
24
(fo-fe)2
/fe
1.9432
0.1713
66
1.0734
72
0.0620
96
69
10
6.7868
85
3.7704
92
4.1475
41
8.2950
82
0.5901
64
5
4
4
0
1
1
0.3278
69
0.3606
56
0.7213
11
0.8852
46
0.4918
03
0.5409
84
1.0819
67
0
1
0.8852
46
0.4918
03
0.5409
84
1.0819
67
0
1
1
1.786885
2
0.229508
2
0.147541
1.704918
03
0.590163
9
0.327868
9
0.639344
26
0.278688
52
0.885245
9
0.508196
72
0.459016
39
0.081967
2
0.885245
9
0.508196
72
1.459016
39
1.081967
2
3.19295
89
0.05267
4
0.02176
83
2.90674
55
0.4704
6
0.0139
7
0.0052
48
0.3504
18
0.34829
35
0.5901
64
0.10749
8
0.40876
11
0.07766
73
0.3278
69
1.1333
83
0.1076
75
0.78366
03
0.25826
39
0.21069
6
0.8852
46
0.5251
37
0.3894
68
0.00671
86
0.0062
1
0.78366
03
0.25826
39
2.12872
88
0.8852
46
0.5251
37
3.9349
23
1.17065
31
1.0819
67
14.482
66
Since our x2 statistic value (14.48266) did not exceed the critical value for 0.05
probability level, we can accept the null hypothesis, it will improve productivity.
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
2
13
1
1
strongly Disagr
row
D
ee
total
2
0
1
18
5
0
3
10
11
22
13
25
10
61
fo
fe
2
3.8360
66
2.1311
48
13
2.3442
62
4.6885
25
7.3770
49
4.0983
61
4.5081
97
9.0163
93
2
8
2.9508
2
1.6393
44
1.8032
79
3.6065
57
1.7704
92
2
5
0
2
0.9836
07
1.0819
67
fo-fe
1.836065
6
1.131147
5
0.344262
3
3.311475
41
5.622950
82
3.098360
7
2.508196
7
0.016393
4
0.950819
7
3.360655
74
0.196721
31
2.606557
4
1.770491
8
0.983606
6
0.918032
79
(fo-fe)
(fo-fe)2
/fe
3.37113
68
0.8788
01
1.27949
48
0.6003
78
0.11851
65
10.9658
69
31.6175
76
0.0505
56
2.3388
74
4.2859
38
9.59983
88
2.3423
61
6.29105
08
1.3954
69
0.00026
87
2.98E05
0.90405
8
11.2940
07
0.03869
93
0.3063
75
6.8893
44
0.0214
61
6.79414
14
1.8838
3
3.13464
12
1.7704
92
0.96748
19
0.84278
42
0.9836
07
0.7789
37
71
2.1639
34
2.0655
74
1.1475
41
1.2622
95
2.5245
9
1
3
1.836065
57
1.065573
8
1.852459
02
1.737704
92
2.524590
2
3.37113
68
1.5578
74
1.13544
75
3.43160
44
3.01961
84
0.5497
01
2.9903
98
2.3921
65
6.37355
55
2.5245
9
34.541
18
Since our x2 statistic value (34.54118) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that the system cannot be
controlled.
strongly
No
A
Agree
option
2
6
3
1
strongly Disagr
row
D
ee
total
3
1
6
18
1
2
3
10
11
22
12
16
10
15
61
fo
fe
3.5409
84
1.9672
13
2.1639
34
fo-fe
1.540983
6
1.032786
89
2.163934
4
(fo-fe)
(fo-fe)2
/fe
2.37463
05
1.06664
88
0.6706
13
0.5422
13
4.68261
22
2.1639
34
72
4.3278
69
4.7213
11
2.6229
51
0
9
3
2.8852
46
5.7704
92
2.3606
56
1.3114
75
1.4426
23
2.8852
46
1
2
4
2.9508
2
1.6393
44
1.8032
79
3.6065
57
4.4262
3
2.4590
16
2.7049
18
5.4098
36
3
6
3
2.672131
15
1.278688
52
1.622950
8
2.885245
9
3.229508
2
0.639344
26
0.311475
4
0.557377
05
0.885245
9
1.950819
7
0.360655
74
2.196721
31
0.606557
4
1.573770
49
0.540983
61
2.295081
97
4.409836
1
7.14028
49
1.63504
43
1.6498
39
0.3463
11
2.63396
94
1.0042
01
8.32464
39
10.4297
23
0.40876
11
2.8852
46
1.8074
24
0.1731
56
0.09701
69
0.31066
92
0.0739
75
0.2153
5
0.78366
03
0.2716
1
3.80569
74
0.13007
26
4.82558
45
1.2897
09
0.0793
44
2.6760
06
0.36791
19
2.47675
36
0.29266
33
5.26740
12
0.1020
12
0.5595
63
0.1190
16
1.9473
42
19.4466
54
3.5946
85
22.171
55
Since our x2 statistic value (22.17155) exceed the critical value for 0.05
probability level, we can reject the null hypothesis.
73
RESEARCH QUESTION 10: Bank and credit facilities are readily available to
sustain Concurrent Engineering
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
1
4
0
1
strongly Disagr
row
D
ee
total
4
8
1
18
0
3
6
10
11
22
11
15
19
12
61
fo
fe
1
1.1803
28
0.6557
38
0.7213
11
1.4426
23
3.2459
02
1.8032
79
0
3
1.9836
07
3.9672
13
4.4262
3
0
2
9
8
3
2.4590
16
2.7049
18
5.4098
36
5.6065
57
3.1147
fo-fe
0.180327
9
0.655737
7
0.721311
5
1.557377
05
0.754098
36
0.803278
7
1.983606
6
2.032786
89
0.426229
5
2.459016
4
0.704918
3.590163
93
2.393442
62
-
(fo-fe)
(fo-fe)2
/fe
0.03251
81
0.0275
5
0.42999
19
0.6557
38
0.52029
02
2.42542
33
0.56866
43
0.7213
11
1.6812
59
0.1751
95
0.64525
67
0.3578
24
3.93469
5
4.13222
25
1.9836
07
1.0415
93
0.18167
16
0.0410
44
6.04676
16
0.49690
94
12.8892
77
5.72856
76
0.01316
2.4590
16
0.1837
06
2.3825
63
1.0217
62
0.0042
74
4
4
54
3.4262
3
6.8524
59
3.5409
84
1.9672
13
2.1639
34
4.3278
69
1
6
0.114754
1
0.573770
49
2.852459
2.540983
6
4.032786
89
2.836065
57
4.327868
9
85
0.32921
26
8.13652
24
28
0.0960
86
1.1873
87
6.45659
77
16.2633
7
8.04326
79
1.8233
91
8.2672
13
3.7169
65
18.7304
49
4.3278
69
32.155
31
Since our x2 statistic value (32.15531) exceed the critical value for 0.05
probability level, we can accept the null hypothesis that the bank and credits facilities
are not adequate to sustain this process.
RESEARCH QUESTION 11: Import and export policies will favour the
implementation of Concurrent Engineering
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
2
4
1
2
fo
strongly Disagr
row
D
ee
total
4
7
1
18
1
2
4
10
11
10
11
22
17
17
13
11
61
fe
fo-fe
(fo-fe)
0.8852 1.114754 1.24267
2
46
1
67
0.4918 0.508196 0.25826
1
03
72
39
0.5409 0.540983 0.29266
0
84
6
33
0 1.0819
- 1.17065
67 1.081967
31
(fo-fe)2
/fe
1.4037
64
0.5251
37
0.5409
84
1.0819
67
75
5.0163
93
2.7868
85
10
3.0655
74
6.1311
48
5.0163
93
2.7868
85
1
11
7
3.0655
74
6.1311
48
3.8360
66
2.1311
48
2.3442
62
4.6885
25
3.2459
02
1.8032
79
1.9836
07
3.9672
13
1
4
2
1.016393
4
0.786885
2
2.065573
8
3.868852
46
1.016393
4
1.786885
2
2.065573
8
4.868852
46
3.163934
43
0.131147
5
0.655737
7
3.688524
6
2.245901
6
2.196721
31
4.016393
44
3.967213
1
1.03305
56
0.2059
36
0.61918
84
0.2221
79
4.26659
5
14.9680
19
1.3917
77
2.4413
08
1.03305
56
0.2059
36
3.19295
89
1.1457
09
4.26659
5
23.7057
24
10.0104
81
1.3917
77
3.8664
42
2.6095
7
0.01719
97
0.42999
19
0.0080
71
0.1834
23
13.6052
14
2.9018
11
5.04407
42
4.82558
45
16.1314
16
1.5539
82
2.6760
06
8.1323
67
15.7387
8
3.9672
13
36.455
36
Since our x2 statistic value (36.45536) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that the import and export policies
will not be favourable.
76
RESEACH QUESTION 12: There is nothing wrong with the traditional system of
project delivery
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
11
10
20
11
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)2
1.55227
09
0.4782
25
3.2459
02
1.245901
6
1.8032
79
0.196721
31
0.03869
93
0.0214
61
1.9836
07
1.983606
6
3.93469
5
1.9836
07
3.9672
13
3.032786
89
9.19779
63
2.3184
53
2.9508
2
1.049180
33
1.10077
94
0.3730
42
1.6393
44
0.639344
3
0.40876
11
0.2493
44
1.8032
79
0.803278
7
0.64525
67
0.3578
24
3.6065
57
0.393442
62
0.15479
71
0.0429
21
77
2.6557
38
1.344262
3
1.80704
11
0.6804
29
1.4754
1
1.475409
8
2.17683
42
1.4754
1
1.6229
51
0.622950
8
0.38806
77
0.2391
12
3.2459
02
0.754098
36
0.56866
43
0.1751
95
5.9016
39
1.098360
66
1.20639
61
0.2044
17
3.2786
89
0.278688
5
0.07766
73
0.0236
89
3.6065
57
0.606557
4
0.36791
19
0.1020
12
7.2131
15
0.213114
8
0.04541
79
0.0062
97
3.2459
02
2.245901
6
5.04407
42
1.5539
82
1.8032
79
2.196721
31
4.82558
45
2.6760
06
1.9836
07
4.016393
44
16.1314
16
8.1323
67
3.9672
13
3.967213
1
15.7387
8
3.9672
13
25.061
Since our x2 statistic value (25.061) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that there is nothing wrong with
the old system of project delivery.
78
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
11
18
client
10
mat
&
supplier
11
contractor
s
13
22
column
total
28
10
61
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)2
0.42999
19
0.1619
11
2.6557
38
0.655737
7
1.4754
1
1.524590
16
2.32437
52
1.5754
1
1.6229
51
0.622950
8
0.38806
77
0.2391
12
3.2459
02
0.245901
6
0.06046
76
0.0186
29
11
8.2622
95
2.737704
92
7.49502
82
0.9071
36
4.5901
64
2.590163
9
6.70894
92
1.4615
93
5.0491
8
3.049180
3
9.29750
07
1.8413
88
13
10.098
2.901639
8.41951
0.8337
79
36
34
09
2.6557
38
1.655737
7
2.74146
73
1.0322
81
1.4754
1
0.524590
16
0.27519
48
0.1865
21
1.6229
51
0.622950
8
0.38806
77
0.2391
12
3.2459
02
1.754098
36
3.07686
11
0.9479
22
2.9508
2
1.049180
33
1.10077
94
0.3730
42
1.6393
44
0.360655
74
0.13007
26
0.0793
44
1.8032
79
1.196721
31
1.43214
19
0.7941
88
3.6065
57
2.606557
4
6.79414
14
1.8838
3
1.4754
1
1.475409
8
2.17683
42
1.4754
1
0.8196
72
0.180327
87
0.03251
81
0.0396
72
0.9016
39
3.098360
66
9.59983
88
10.647
09
1.8032
79
1.803278
7
3.25181
4
1.8032
79
26.540
62
Since our x2 statistic value (26.54062) exceed the critical value for 0.05
80
probability level, we can reject the null hypothesis that insurance will not be well
implemented.
RESEARCH QUESTION 14: The client is too uniformed for this concept
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
10
22
column
total
16
20
12
61
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
2.0655
74
0.065573
8
0.00429
99
0.0020
82
1.1475
41
3.852459
02
14.8414
4
12.933
26
1.2622
95
1.262295
1
1.59338
89
1.2622
95
2.5245
9
2.524590
2
6.37355
55
2.5245
9
4.7213
11
2.278688
52
5.19242
14
1.0997
84
2.6229
51
0.622950
8
0.38806
77
0.1479
51
2.8852
3.55415
1.2318
81
46
1.885245
9
21
37
5.7704
92
0.229508
2
0.05267
4
0.0091
28
5.9016
39
0.098360
66
0.00967
48
0.0016
39
3.2786
89
2.278688
5
5.19242
14
1.5836
89
3.6065
57
0.606557
4
0.36791
19
0.1020
12
10
7.2131
15
2.786885
25
7.76672
94
1.0767
51
3.5409
84
0.540983
6
0.29266
33
0.0826
5
1.9672
13
0.967213
1
0.93550
12
0.4755
46
2.1639
34
0.163934
4
0.02687
45
0.0124
19
4.3278
69
1.672131
15
2.79602
26
0.6460
51
1.7704
92
1.770491
8
3.13464
12
1.7704
92
0.9836
07
0.016393
44
0.00026
87
0.0002
73
1.0819
67
3.918032
79
15.3509
81
14.188
03
2.1639
34
2.163934
4
4.68261
22
2.1639
34
41.314
41
82
Since our x2 statistic value (41.31441) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that the client is uninformed.
RESEARCH QUESTION 15: Corruption will not let this system work
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
10
18
client
10
mat
&
supplier
11
contractor
s
12
22
14
18
15
10
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
4.1311
48
1.131147
5
1.27949
48
0.3097
19
2.2950
82
5.704918
03
32.5460
9
14.180
8
2.5245
9
2.524590
2
6.37355
55
2.5245
9
5.0491
8
2.049180
3
4.19914
0.8316
48
5.3114
75
1.311475
4
1.71996
78
0.3238
21
2.9508
2
0.950819
7
0.90405
8
0.3063
75
83
3.2459
02
3.245901
6
12
6.4918
03
5.508196
72
30.3402
31
4.6736
21
1.1803
28
1.180327
9
1.39317
39
1.1803
28
0.6557
38
0.655737
7
0.42999
19
0.6557
38
0.7213
11
0.721311
5
0.52029
02
0.7213
11
1.4426
23
2.557377
05
6.54017
74
4.5335
32
10
4.4262
3
5.573770
49
31.0669
17
7.0188
22
2.4590
16
2.459016
4
6.04676
16
2.4590
16
2.7049
18
0.295081
97
0.08707
34
0.0321
91
5.4098
36
3.409836
1
11.6269
82
2.1492
3
2.9508
2
1.950819
7
3.80569
74
1.2897
09
1.6393
44
1.639344
3
2.68744
96
1.6393
44
1.8032
79
6.196721
31
38.3993
55
21.294
19
3.6065
57
2.606557
4
6.79414
14
1.8838
3
10.5358
77
3.2459
02
84
71.253
71
Since our x2 statistic value (71.25371) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that the system fail due to high of
corruption.
RESEARCH QUESTION 16: The supply market is too informal and undeveloped
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
11
18
client
10
mat
&
supplier
11
contractor
s
22
11
11
23
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
0.06046
76
0.0186
29
3.2459
02
0.245901
6
1.8032
79
4.196721
31
17.6124
7
9.7669
15
1.9836
07
1.983606
6
3.93469
5
1.9836
07
3.9672
13
1.967213
1
3.86992
74
0.9754
78
85
2.3606
56
0.360655
7
1.3114
75
1.688524
59
2.85111
53
2.1739
75
1.4426
23
1.442623
2.08116
1
1.4426
23
2.8852
46
0.114754
1
0.01316
85
0.0045
64
3.2459
02
1.245901
6
1.55227
09
0.4782
25
1.8032
79
1.803278
7
3.25181
4
1.8032
79
1.9836
07
1.983606
6
3.93469
5
1.9836
07
3.9672
13
5.032786
89
25.3289
44
6.3845
68
11
6.7868
85
4.213114
75
17.7503
36
2.6153
88
3.7704
92
3.770491
8
14.2166
08
3.7704
92
4.1475
41
0.147541
0.02176
83
0.0052
48
8.2950
82
0.295082
0.08707
34
0.0104
97
2.3606
56
2.360655
7
5.57269
55
2.3606
56
1.3114
75
0.311475
4
0.09701
69
0.0739
75
1.4426
23
5.557377
05
30.8844
4
21.408
53
0.13007
26
0.0551
86
2.8852
46
2.885245
9
8.32464
39
2.8852
46
60.200
6
Since our x2 statistic value (60.2006) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that the supply market will not
sustain this process.
RESEARCH QUESTION 17: It will be difficult to integrate the supply chain in the
concurrent engineering system
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
column
total
13
10
19
11
61
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)2
1.85138
4
0.7842
67
2.3606
56
1.360655
7
1.3114
75
2.688524
59
7.22816
45
5.5114
75
1.4426
23
0.557377
05
0.31066
92
0.2153
5
87
2.8852
46
1.885245
9
3.8360
66
0.836065
6
0.69900
56
0.1822
19
2.1311
48
0.868852
46
0.75490
46
0.3542
24
2.3442
62
1.344262
3
1.80704
11
0.7708
36
4.6885
25
1.311475
41
1.71996
78
0.3668
46
2.9508
2
2.950819
7
8.70733
67
2.9508
2
1.6393
44
0.360655
74
0.13007
26
0.0793
44
1.8032
79
0.803278
7
0.64525
67
0.3578
24
3.6065
57
3.393442
62
11.5154
53
3.1929
21
5.6065
57
1.393442
62
1.94168
23
0.3463
23
3.1147
54
3.114754
1
9.70169
31
3.1147
54
3.4262
3
0.573770
49
0.32921
26
0.0960
86
6.8524
59
1.147540
98
1.31685
03
0.1921
72
3.2459
02
3.754098
36
14.0932
55
4.3418
61
1.8032
79
0.803278
7
0.64525
67
0.3578
24
3.55415
21
1.2318
37
88
1.9836
07
1.016393
44
1.03305
56
0.5207
97
3.9672
13
3.967213
1
15.7387
8
3.9672
13
28.934
99
Since our x2 statistic value (28.93499) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that it will be difficult to integrate.
RESEARCH QUESTION 18: Project schedule are strictly adhered to
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
13
18
18
61
column
total
fo
fe
fo-fe
(fo-fe)
(fo-fe)2
/fe
3.8360
66
0.163934
43
0.02687
45
0.0070
06
2.1311
48
2.868852
46
8.23031
44
3.8619
17
2.3442
62
2.344262
3
5.49556
57
2.3442
62
89
4.6885
25
0.688524
6
5.3114
75
1.688524
59
2.85111
53
0.5367
84
2.9508
2
1.049180
33
1.10077
94
0.3730
42
3.2459
02
2.245901
6
5.04407
42
1.5539
82
6.4918
03
0.491803
3
0.24187
05
0.0372
58
1.4754
1
0.475409
8
0.22601
45
0.1531
88
0.8196
72
0.819672
1
0.67186
24
0.8196
72
0.9016
39
1.098360
66
1.20639
61
1.3380
03
1.8032
79
0.196721
31
0.03869
93
0.0214
61
5.3114
75
0.688524
59
0.47406
61
0.0892
53
2.9508
2
2.950819
7
8.70733
67
2.9508
2
3.2459
02
0.754098
36
0.56866
43
0.1751
95
6.4918
03
1.508196
72
2.27465
74
0.3503
89
2.0655
74
2.065573
8
4.26659
5
2.0655
74
1.1475
41
0.147541
0.02176
83
0.0189
7
0.47406
61
0.1011
12
90
1.2622
95
2.737704
92
7.49502
82
5.9376
2
2.5245
9
0.524590
2
0.27519
48
0.1090
06
22.844
51
Since our x2 statistic value (22.84451) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that the schedule cannot be
strictly adhere to.
RESEARCH QUESTION 19: Failure of a member in the team will be very
expensive
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
13
18
client
10
mat
&
supplier
11
contractor
s
22
18
26
10
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
5.3114
75
0.311475
4
0.09701
69
0.0182
66
2.9508
2
0.049180
33
0.00241
87
0.0008
2
91
3.2459
02
1.754098
36
3.07686
11
0.9479
22
6.4918
03
1.491803
3
2.22547
7
0.3428
13
13
7.6721
31
5.327868
85
28.3861
87
3.6999
09
4.2622
95
2.262295
1
5.11797
9
1.2007
57
4.6885
25
2.688524
6
7.22816
45
1.5416
71
9.3770
49
0.377049
2
0.14216
61
0.0151
61
1.7704
92
1.770491
8
3.13464
12
1.7704
92
0.9836
07
3.016393
44
9.09862
94
9.2502
73
1.0819
67
0.081967
2
0.00671
86
0.0062
1
2.1639
34
1.163934
4
1.35474
33
0.6260
56
2.9508
2
2.950819
7
8.70733
67
2.9508
2
1.6393
44
0.639344
3
0.40876
11
0.2493
44
1.8032
79
0.196721
31
0.03869
93
0.0214
61
3.6065
57
3.393442
62
11.5154
53
3.1929
21
92
0.2950
82
0.295082
0.08707
34
0.2950
82
0.1639
34
0.163934
4
0.02687
45
0.1639
34
0.1803
28
0.819672
13
0.67186
24
3.7257
82
0.3606
56
0.360655
7
0.13007
26
0.3606
56
20.013
5
Since our x2 statistic value (20.0135) did not exceed the critical value for 0.05
probability level, we can accept the null hypothesis that failure of team member will
be detrimental to the process.
RESEARCH QUESTION 20: Delayed payments of valuation will frustrate the
concept
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
10
18
client
10
mat
&
supplier
11
contractor
s
22
29
23
61
column
total
fo
fe
fo-fe
(fo-fe)
(fo-fe)2
/fe
93
8.5573
77
0.557377
0.31066
92
0.0363
04
4.7540
98
1.245901
64
1.55227
09
0.3265
12
5.2295
08
0.770491
8
0.59365
76
0.1135
21
10.459
02
1.459016
4
2.12872
88
0.2035
31
10
6.7868
85
3.213114
75
10.3241
06
1.5211
85
3.7704
92
0.770491
8
0.59365
76
0.1574
48
4.1475
41
0.147541
0.02176
83
0.0052
48
8.2950
82
2.295082
5.26740
12
0.6350
03
1.1803
28
1.180327
9
1.39317
39
1.1803
28
0.6557
38
0.655737
7
0.42999
19
0.6557
38
0.7213
11
0.721311
5
0.52029
02
0.7213
11
1.4426
23
2.557377
05
6.54017
74
4.5335
32
1.1803
28
1.180327
9
1.39317
39
1.1803
28
0.6557
38
0.344262
3
0.11851
65
0.1807
38
0.7213
11
0.721311
5
0.52029
02
0.7213
11
94
1.4426
23
1.557377
05
2.42542
33
1.6812
59
0.2950
82
0.295082
0.08707
34
0.2950
82
0.1639
34
0.163934
4
0.02687
45
0.1639
34
0.1803
28
0.819672
13
0.67186
24
3.7257
82
0.3606
56
0.360655
7
0.13007
26
0.3606
56
18.398
75
Since our x2 statistic value (18.39875) did not exceed the critical value for 0.05
probability level, we can accept the null hypothesis that it will frustrate the concept.
RESEARCH QUESTION 21: Avenues of manpower development is very limited
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
11
18
client
10
mat
&
supplier
11
contractor
s
14
22
21
30
61
column
total
fo
fe
fo-fe
(fo-fe)
(fo-fe)2
/fe
95
6.1967
21
0.803278
69
0.64525
67
0.1041
29
3.4426
23
3.557377
05
12.6549
31
3.6759
56
3.7868
85
3.213114
75
10.3241
06
2.7262
79
7.5737
7
7.573770
5
57.3619
99
7.5737
7
11
8.8524
59
2.147540
98
4.61193
23
0.5209
78
4.9180
33
1.918032
8
3.67884
98
0.7480
33
5.4098
36
3.409836
1
11.6269
82
2.1492
3
14
10.819
67
3.180327
87
10.1144
85
0.9348
24
0.8852
46
0.885245
9
0.78366
03
0.8852
46
0.4918
03
0.491803
3
0.24187
05
0.4918
03
0.5409
84
0.540983
6
0.29266
33
0.5409
84
1.0819
67
1.918032
79
3.67884
98
3.4001
49
1.1803
28
1.180327
9
1.39317
39
1.1803
28
0.6557
38
0.655737
7
0.42999
19
0.6557
38
0.7213
0.278688
0.07766
0.1076
96
11
52
73
75
1.4426
23
1.557377
05
2.42542
33
1.6812
59
0.8852
46
0.885245
9
0.78366
03
0.8852
46
0.4918
03
0.491803
3
0.24187
05
0.4918
03
0.5409
84
0.459016
39
0.21069
6
0.3894
68
1.0819
67
0.918032
79
0.84278
42
0.7789
37
29.921
84
Since our x2 statistic value (29.92184) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that manpower development is
limited.
RESEARCH QUESTION 22: The level of manpower skills will not meet up the
needed requirements of Concurrent engineering
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
14
22
13
26
12
61
column
97
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
3.8360
66
0.836065
6
0.69900
56
0.1822
19
2.1311
48
2.868852
46
8.23031
44
3.8619
17
2.3442
62
2.655737
7
7.05294
28
3.0085
98
4.6885
25
4.688524
6
21.9822
63
4.6885
25
7.6721
31
3.672131
1
13.4845
47
1.7576
01
4.2622
95
0.262295
1
0.06879
87
0.0161
41
4.6885
25
0.688524
6
0.47406
61
0.1011
12
14
9.3770
49
4.622950
82
21.3716
74
2.2791
47
1.1803
28
1.180327
9
1.39317
39
1.1803
28
0.6557
38
0.655737
7
0.42999
19
0.6557
38
0.7213
11
0.278688
52
0.07766
73
0.1076
75
1.4426
23
1.557377
05
2.42542
33
1.6812
59
3.5409
3.459016
11.9647
3.3789
98
84
39
94
47
1.9672
13
0.967213
1
0.93550
12
0.4755
46
2.1639
34
1.163934
4
1.35474
33
0.6260
56
4.3278
69
1.327868
9
1.76323
57
0.4074
14
1.7704
92
2.229508
2
4.97070
68
2.8075
29
0.9836
07
0.983606
6
0.96748
19
0.9836
07
1.0819
67
1.081967
2
1.17065
31
1.0819
67
2.1639
34
0.163934
4
0.02687
45
0.0124
19
29.293
75
Since our x2 statistic value (29.29375) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that the level of man power skill
is limited.
RESEARCH QUESTION 23: Concurrent engineering involves a team formation of
some key persons of different personality and character
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
10
18
client
10
99
mat
&
supplier
11
contractor
s
11
22
17
27
10
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
1.03305
56
0.2059
36
5.0163
93
1.016393
4
2.7868
85
1.213114
75
1.47164
74
0.5280
62
3.0655
74
0.934426
23
0.87315
24
0.2848
25
6.1311
48
1.131147
5
1.27949
48
0.2086
88
10
7.9672
13
2.032786
89
4.13222
25
0.5186
53
4.4262
3
1.426229
5
2.03413
06
0.4595
63
4.8688
52
1.868852
5
3.49260
95
0.7173
37
11
9.7377
05
1.262295
08
1.59338
89
0.1636
31
2.9508
2
1.950819
7
3.80569
74
1.2897
09
1.6393
44
0.360655
74
0.13007
26
0.0793
44
1.8032
79
2.196721
31
4.82558
45
2.6760
06
100
3.6065
57
0.606557
4
1.7704
92
0.229508
2
0.05267
4
0.0297
51
0.9836
07
0.016393
44
0.00026
87
0.0002
73
1.0819
67
1.081967
2
1.17065
31
1.0819
67
2.1639
34
0.836065
57
0.69900
56
0.3230
25
0.2950
82
0.704918
03
0.49690
94
1.6839
71
0.1639
34
0.163934
4
0.02687
45
0.1639
34
0.1803
28
0.180327
9
0.03251
81
0.1803
28
0.3606
56
0.360655
7
0.13007
26
0.3606
56
0.36791
19
0.1020
12
11.057
67
Since our x2 statistic value (11.05767) did not exceed the critical value for 0.05
probability level, we can accept the null hypothesis that it involves team formatiom.
RESEARCH QUESTION 24: This system of practice involves shifting of
responsibility
options
consultant
strongly
A
9
No
option
Agree
8
strongly
D
0
Disagr
ee
1
row
total
18
101
client
10
mat
&
supplier
11
contractor
s
11
22
column
total
22
17
12
61
fo
fe
fo-fe
(fo-fe)
(fo-fe)2
/fe
6.4918
03
2.508196
72
6.29105
08
0.9690
76
3.6065
57
2.606557
4
6.79414
14
1.8838
3
3.9672
13
2.967213
1
8.80435
37
2.2192
79
11
7.9344
26
3.065573
77
9.39774
25
1.1844
26
5.0163
93
2.983606
56
8.90190
81
1.7745
63
2.7868
85
0.786885
2
0.61918
84
0.2221
79
3.0655
74
1.065573
8
1.13544
75
0.3703
87
6.1311
48
1.131147
5
1.27949
48
0.2086
88
3.5409
84
3.540983
6
12.5385
65
3.5409
84
1.9672
13
1.032786
89
1.06664
88
0.5422
13
102
2.1639
34
2.836065
57
8.04326
79
3.7169
65
4.3278
69
0.327868
9
0.10749
8
0.0248
39
1.4754
1
1.475409
8
2.17683
42
1.4754
1
0.8196
72
1.180327
87
1.39317
39
1.6996
72
0.9016
39
0.098360
66
0.00967
48
0.0107
3
1.8032
79
0.196721
31
0.03869
93
0.0214
61
1.4754
1
0.475409
8
0.22601
45
0.1531
88
0.8196
72
1.180327
87
1.39317
39
1.6996
72
0.9016
39
1.098360
66
1.20639
61
1.3380
03
1.8032
79
1.803278
7
3.25181
4
1.8032
79
24.858
84
Since our x2 statistic value (24.85884) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that it does not involves shifting
of responsibility.
RESEARCH QUESTION 25: Compliance with conditions of contract is low
options
strongly
A
Agree
No
option
strongly
D
Disagr
ee
row
total
103
consultant
10
18
client
10
mat
&
supplier
11
contractor
s
22
13
18
21
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
3.8360
66
1.836065
6
3.37113
68
0.8788
01
2.1311
48
3.868852
46
14.9680
19
7.0234
55
2.3442
62
0.655737
7
0.42999
19
0.1834
23
4.6885
25
2.688524
6
7.22816
45
1.5416
71
5.3114
75
1.311475
4
1.71996
78
0.3238
21
2.9508
2
0.950819
7
0.90405
8
0.3063
75
3.2459
02
0.754098
36
0.56866
43
0.1751
95
6.4918
03
1.508196
72
2.27465
74
0.3503
89
2.0655
74
1.065573
8
1.13544
75
0.5497
01
1.1475
1.31685
1.1475
104
41
1.147541
03
41
1.2622
95
0.262295
1
0.06879
87
0.0545
03
2.5245
9
2.475409
84
6.12765
39
2.4271
88
10
6.1967
21
3.803278
69
14.4649
29
2.3342
87
3.4426
23
1.442623
2.08116
1
0.6045
28
3.7868
85
1.786885
2
3.19295
89
0.8431
62
7.5737
7
0.573770
5
0.32921
26
0.0434
67
0.5901
64
0.409836
07
0.16796
56
0.2846
08
0.3278
69
0.327868
9
0.10749
8
0.3278
69
0.3606
56
0.639344
26
0.40876
11
1.1333
83
0.7213
11
0.721311
5
0.52029
02
0.7213
11
21.254
68
Since our x2 statistic value (21.25468) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that compliance level is
satisfactory.
RESEARCH QUESTION 26: Sabotage of the concurrent engineering system is easy
105
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
22
17
12
61
column
total
fo
fe
fo-fe
(fo-fe)
(fo-fe)2
/fe
6.4918
03
1.508196
72
2.27465
74
0.3503
89
3.6065
57
2.393442
62
5.72856
76
1.5883
76
3.9672
13
1.032786
89
1.06664
88
0.2688
66
7.9344
26
4.934426
2
24.3485
62
3.0687
24
5.0163
93
0.983606
56
0.96748
19
0.1928
64
2.7868
85
0.786885
2
0.61918
84
0.2221
79
3.0655
74
0.934426
23
0.87315
24
0.2848
25
6.1311
48
1.131147
5
1.27949
48
0.2086
88
3.5409
84
0.540983
6
0.29266
33
0.0826
5
106
1.9672
13
1.967213
1
2.1639
34
2.163934
4
4.68261
22
2.1639
34
4.3278
69
4.672131
15
21.8288
09
5.0437
78
2.6557
38
1.655737
7
2.74146
73
1.0322
81
1.4754
1
0.524590
16
0.27519
48
0.1865
21
1.6229
51
0.622950
8
0.38806
77
0.2391
12
3.2459
02
1.754098
36
3.07686
11
0.9479
22
0.2950
82
0.295082
0.08707
34
0.2950
82
0.1639
34
0.163934
4
0.02687
45
0.1639
34
0.1803
28
0.819672
13
0.67186
24
3.7257
82
0.3606
56
0.360655
7
0.13007
26
0.3606
56
3.86992
74
1.9672
13
22.393
78
Since our x2 statistic value (22.39378) exceed the critical value for 0.05
probability level, we can reject the null hypothesis sabotage will be rare.
RESEARCH QUESTION 27: Compliance/cooperation of team members is not
guaranteed without sanction
107
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
24
15
11
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
7.0819
67
1.081967
2
1.17065
31
0.1653
01
3.9344
26
4.065573
77
16.5288
9
4.2010
93
4.3278
69
2.672131
15
7.14028
49
1.6498
39
8.6557
38
5.655737
7
31.9873
69
3.6955
1
4.4262
3
1.573770
49
2.47675
36
0.5595
63
2.4590
16
0.459016
4
0.21069
6
0.0856
83
2.7049
18
0.704918
0.49690
94
0.1837
06
5.4098
36
0.409836
1
0.16796
56
0.0310
48
3.2459
02
1.245901
1.55227
09
0.4782
25
108
6
1.8032
79
1.803278
7
3.25181
4
1.8032
79
1.9836
07
1.983606
6
3.93469
5
1.9836
07
3.9672
13
5.032786
89
25.3289
44
6.3845
68
2.6557
38
0.344262
3
0.11851
65
0.0446
27
1.4754
1
1.475409
8
2.17683
42
1.4754
1
1.6229
51
0.622950
8
0.38806
77
0.2391
12
3.2459
02
1.754098
36
3.07686
11
0.9479
22
0.5901
64
0.409836
07
0.16796
56
0.2846
08
0.3278
69
0.327868
9
0.10749
8
0.3278
69
0.3606
56
0.639344
26
0.40876
11
1.1333
83
0.7213
11
0.721311
5
0.52029
02
0.7213
11
26.395
66
Since our x2 statistic value (26.39566) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that compliance of team members
is will guaranteed.
109
options
strongly
A
consultant
No
option
Agree
strongly
D
Disagr
ee
row
total
10
18
client
10
mat
&
supplier
11
contractor
s
10
22
26
25
61
column
total
(fo-fe)2
/fe
fo-fe
(fo-fe)2
10
7.6721
31
2.327868
85
5.41897
34
0.7063
19
4.2622
95
2.737704
92
7.49502
82
1.7584
49
4.6885
25
1.311475
41
1.71996
78
0.3668
46
9.3770
49
6.377049
2
40.6667
56
4.3368
39
7.3770
49
0.622950
82
0.38806
77
0.0526
05
4.0983
61
2.098360
7
4.40311
74
1.0743
61
4.5081
97
0.491803
28
0.24187
05
0.0536
51
10
9.0163
93
0.983606
56
0.96748
19
0.1073
03
0.2950
0.08707
0.2950
fo
fe
110
82
0.295082
34
82
0.1639
34
0.163934
4
0.02687
45
0.1639
34
0.1803
28
0.180327
9
0.03251
81
0.1803
28
0.3606
56
0.639344
26
0.40876
11
1.1333
83
2.0655
74
2.065573
8
4.26659
5
2.0655
74
1.1475
41
0.147541
0.02176
83
0.0189
7
1.2622
95
1.262295
1
1.59338
89
1.2622
95
2.5245
9
3.475409
84
12.0784
74
4.7843
3
0.5901
64
0.590163
9
0.34829
35
0.5901
64
0.3278
69
0.327868
9
0.10749
8
0.3278
69
0.3606
56
0.360655
7
0.13007
26
0.3606
56
0.7213
11
1.278688
52
1.63504
43
2.2667
66
21.905
72
Since our x2 statistic value (21.90572) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that dependence on imported
materials and technology will be favourable.
111
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
18
20
17
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
5.3114
75
4.311475
4
18.5888
2
3.4997
47
2.9508
2
6.049180
33
36.5925
83
12.400
82
3.2459
02
3.754098
36
14.0932
55
4.3418
61
6.4918
03
5.491803
3
30.1599
03
4.6458
44
5.9016
39
1.098360
66
1.20639
61
0.2044
17
3.2786
89
2.278688
5
5.19242
14
1.5836
89
3.6065
57
0.393442
62
0.15479
71
0.0429
21
7.2131
15
0.786885
25
0.61918
84
0.0858
42
1.1803
1.39317
1.1803
112
28
1.180327
9
39
28
0.6557
38
0.655737
7
0.42999
19
0.6557
38
0.7213
11
0.721311
5
0.52029
02
0.7213
11
1.4426
23
2.557377
05
6.54017
74
4.5335
32
5.0163
93
2.983606
56
8.90190
81
1.7745
63
2.7868
85
2.786885
2
7.76672
94
2.7868
85
3.0655
74
3.065573
8
9.39774
25
3.0655
74
6.1311
48
2.868852
46
8.23031
44
1.3423
77
0.5901
64
1.409836
07
1.98763
77
3.3679
42
0.3278
69
0.327868
9
0.10749
8
0.3278
69
0.3606
56
0.360655
7
0.13007
26
0.3606
56
0.7213
11
0.721311
5
0.52029
02
0.7213
11
47.643
23
Since our x2 statistic value (47.64323) exceed the critical value for 0.05
113
probability level, we can reject the null hypothesis that facilities for professional
teaming is adequate.
RESEARCH QUESTION 30: The local penetration of information communication
technology (ICT) is shallow
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
20
20
61
column
total
fo
fe
fo-fe
(fo-fe)
(fo-fe)2
/fe
5.9016
39
3.098360
66
9.59983
88
1.6266
39
3.2786
89
1.278688
5
1.63504
43
0.4986
89
3.6065
57
1.393442
62
1.94168
23
0.5383
76
7.2131
15
3.213114
8
10.3241
06
1.4312
97
5.9016
39
1.098360
66
1.20639
61
0.2044
17
3.2786
89
1.278688
5
1.63504
43
0.4986
89
3.6065
0.36791
0.1020
114
57
0.606557
4
19
12
7.2131
15
0.786885
25
0.61918
84
0.0858
42
1.4754
1
1.475409
8
2.17683
42
1.4754
1
0.8196
72
0.819672
1
0.67186
24
0.8196
72
0.9016
39
0.901639
3
0.81295
35
0.9016
39
1.8032
79
3.196721
31
10.2190
27
5.6669
15
2.3606
56
1.360655
7
1.85138
4
0.7842
67
1.3114
75
0.688524
59
0.47406
61
0.3614
75
1.4426
23
1.442623
2.08116
1
1.4426
23
2.8852
46
2.114754
1
4.47218
49
1.5500
19
2.3606
56
1.360655
7
1.85138
4
0.7842
67
1.3114
75
2.688524
59
7.22816
45
5.5114
75
1.4426
23
1.557377
05
2.42542
33
1.6812
59
2.8852
46
2.885245
9
8.32464
39
2.8852
46
28.850
23
115
Since our x2 statistic value (28.85023) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that the ICT facilities adequate.
RESEARCH QUESTION 31: Dependence of Concurrent Engineering on
communication will create problems for the effectiveness of the concept
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
column
total
20
17
10
61
fo
fe
fo-fe
(fo-fe)
(fo-fe)2
/fe
2.3606
56
1.639344
26
2.68744
96
1.1384
34
1.3114
75
0.311475
4
0.09701
69
0.0739
75
1.4426
23
1.442623
2.08116
1
1.4426
23
2.8852
46
0.114754
1
0.01316
85
0.0045
64
5.9016
39
0.098360
66
0.00967
48
0.0016
39
3.2786
89
2.278688
5
5.19242
14
1.5836
89
116
3.6065
57
4.393442
62
19.3023
38
5.3520
12
7.2131
15
2.213114
8
4.89787
69
0.6790
24
1.7704
92
1.770491
8
3.13464
12
1.7704
92
0.9836
07
0.983606
6
0.96748
19
0.9836
07
1.0819
67
1.081967
2
1.17065
31
1.0819
67
2.1639
34
3.836065
57
14.7153
99
6.8002
98
5.0163
93
2.983606
56
8.90190
81
1.7745
63
2.7868
85
0.213114
75
0.04541
79
0.0162
97
3.0655
74
3.065573
8
9.39774
25
3.0655
74
6.1311
48
0.131147
5
0.01719
97
0.0028
05
2.9508
2
2.950819
7
8.70733
67
2.9508
2
1.6393
44
3.360655
74
11.2940
07
6.8893
44
1.8032
79
1.196721
31
1.43214
19
0.7941
88
3.6065
57
1.606557
4
2.58102
66
0.7156
48
37.121
117
56
Since our x2 statistic value (37.12156) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that communication would not be
a problem.
RESEARCH QUESTION 32: The IT infrastructure to support Concurrent
Engineering is adequate
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
10
18
client
10
mat
&
supplier
11
contractor
s
12
22
column
total
24
15
61
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)2
3.13464
12
1.7704
92
1.7704
92
1.770491
8
0.9836
07
3.016393
44
9.09862
94
9.2502
73
1.0819
67
1.081967
2
1.17065
31
1.0819
67
2.1639
34
0.163934
0.02687
45
0.0124
19
118
4
10
7.0819
67
2.918032
79
8.51491
53
1.2023
38
3.9344
26
1.934426
2
3.74200
48
0.9510
93
4.3278
69
4.327868
9
18.7304
49
4.3278
69
12
8.6557
38
3.344262
3
11.1840
9
1.2921
01
2.6557
38
0.344262
3
0.11851
65
0.0446
27
1.4754
1
1.475409
8
2.17683
42
1.4754
1
1.6229
51
0.377049
18
0.14216
61
0.0875
97
3.2459
02
0.754098
36
0.56866
43
0.1751
95
4.4262
3
0.573770
49
0.32921
26
0.0743
78
2.4590
16
1.459016
4
2.12872
88
0.8656
83
2.7049
18
2.295081
97
5.26740
12
1.9473
42
5.4098
36
1.409836
1
1.98763
77
0.3674
12
2.0655
74
2.065573
8
4.26659
5
2.0655
74
1.1475
41
1.852459
02
3.43160
44
2.9903
98
1.2622
2.737704
7.49502
5.9376
119
95
92
82
2.5245
9
2.524590
2
6.37355
55
2.5245
9
38.444
38
Since our x2 statistic value (38.44438) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that IT infrastructures.
RESEARCH QUESTION 33: Bandwidth available for communication cannot be
guaranteed
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
column
total
18
20
11
61
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
2.3606
56
1.360655
7
1.85138
4
0.7842
67
1.3114
75
1.688524
59
2.85111
53
2.1739
75
1.4426
23
1.557377
05
2.42542
33
1.6812
59
120
2.8852
46
1.885245
9
5.3114
75
0.688524
59
0.47406
61
0.0892
53
2.9508
2
0.950819
7
0.90405
8
0.3063
75
3.2459
02
2.245901
6
5.04407
42
1.5539
82
6.4918
03
2.508196
72
6.29105
08
0.9690
76
5.9016
39
5.901639
3
34.8293
47
5.9016
39
3.2786
89
1.721311
48
2.96291
32
0.9036
89
3.6065
57
3.393442
62
11.5154
53
3.1929
21
7.2131
15
0.786885
25
0.61918
84
0.0858
42
3.2459
02
3.754098
36
14.0932
55
4.3418
61
1.8032
79
1.803278
7
3.25181
4
1.8032
79
1.9836
07
1.983606
6
3.93469
5
1.9836
07
3.9672
13
0.032786
89
0.00107
5
0.0002
71
1.1803
28
2.819672
13
7.95055
09
6.7358
83
0.6557
38
0.655737
7
0.42999
19
0.6557
38
3.55415
21
1.2318
37
121
0.7213
11
0.721311
5
1.4426
23
1.442623
0.52029
02
0.7213
11
2.08116
1
1.4426
23
36.558
69
Since our x2 statistic value (36.55869) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that bandwidth for
communication is guaranteed.
RESEARCH QUESTION 34: This Concurrent Engineering concept will be better for
more mechanical production system
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
22
14
14
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
6.4918
03
1.491803
3
2.22547
7
0.3428
13
3.6065
57
0.606557
4
0.36791
19
0.1020
12
122
3.9672
13
5.032786
89
25.3289
44
6.3845
68
7.9344
26
2.934426
2
8.61085
73
1.0852
53
4.1311
48
0.131147
5
0.01719
97
0.0041
63
2.2950
82
0.295082
0.08707
34
0.0379
39
2.5245
9
1.524590
2
2.32437
52
0.9206
94
5.0491
8
1.950819
67
3.80569
74
0.7537
26
4.1311
48
0.868852
46
0.75490
46
0.1827
35
2.2950
82
2.295082
5.26740
12
2.2950
82
2.5245
9
2.524590
2
6.37355
55
2.5245
9
5.0491
8
3.950819
67
15.6089
76
3.0913
88
2.0655
74
0.065573
8
0.00429
99
0.0020
82
1.1475
41
2.852459
02
8.13652
24
7.0903
98
1.2622
95
1.262295
1
1.59338
89
1.2622
95
2.5245
9
1.524590
2
2.32437
52
0.9206
94
1.1803
28
0.819672
13
0.67186
24
0.5692
17
123
0.6557
38
0.344262
3
0.11851
65
0.1807
38
0.7213
11
0.278688
52
0.07766
73
0.1076
75
1.4426
23
1.442623
2.08116
1
1.4426
23
29.300
69
Since our x2 statistic value (29.30069) exceed the critical value for 0.05
probability level, we can reject the null hypothesis.
RESEARCH QUESTION 35: The concurrent engineering concept is too advanced
for a developing country
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
18
client
10
mat
&
supplier
11
contractor
s
22
17
14
13
11
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
5.0163
93
4.016393
4
16.1314
16
3.2157
4
2.7868
2.213114
4.89787
1.7574
124
85
75
69
73
3.0655
74
2.934426
23
8.61085
73
2.8088
89
6.1311
48
1.131147
5
1.27949
48
0.2086
88
4.1311
48
2.131147
5
4.54178
98
1.0994
02
2.2950
82
0.295082
0.08707
34
0.0379
39
2.5245
9
0.475409
84
0.22601
45
0.0895
25
5.0491
8
1.950819
67
3.80569
74
0.7537
26
3.8360
66
0.836065
6
0.69900
56
0.1822
19
2.1311
48
2.131147
5
4.54178
98
2.1311
48
2.3442
62
1.344262
3
1.80704
11
0.7708
36
4.6885
25
4.311475
41
18.5888
2
3.9647
48
3.2459
02
2.754098
36
7.58505
78
2.3368
11
1.8032
79
1.196721
31
1.43214
19
0.7941
88
1.9836
07
0.983606
6
0.96748
19
0.4877
39
3.9672
13
2.967213
1
8.80435
37
2.2192
79
125
1.7704
92
4.229508
2
17.8887
4
10.103
83
0.9836
07
0.983606
6
0.96748
19
0.9836
07
1.0819
67
1.081967
2
1.17065
31
1.0819
67
2.1639
34
2.163934
4
4.68261
22
2.1639
34
37.191
68
Since our x2 statistic value (37.19168) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that the concept is too advance.
RESEARCH QUESTION 36: ICT skilled workers are available in the company
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
11
18
client
10
mat
&
supplier
11
contractor
s
10
22
column
total
18
24
61
fo
fe
fo-fe
(fo-fe)
(fo-fe)2
/fe
126
5.3114
75
0.311475
4
2.9508
2
0.049180
33
0.00241
87
0.0008
2
3.2459
02
3.245901
6
10.5358
77
3.2459
02
10
6.4918
03
3.508196
72
12.3074
44
1.8958
44
11
7.0819
67
3.918032
79
15.3509
81
2.1676
15
3.9344
26
1.934426
2
3.74200
48
0.9510
93
4.3278
69
2.327868
9
5.41897
34
1.2521
11
8.6557
38
0.344262
3
0.11851
65
0.0136
92
1.1803
28
1.180327
9
1.39317
39
1.1803
28
0.6557
38
0.344262
3
0.11851
65
0.1807
38
0.7213
11
1.278688
52
1.63504
43
2.2667
66
1.4426
23
0.442623
0.19591
51
0.1358
05
2.3606
56
0.360655
7
0.13007
26
0.0551
1.3114
75
0.311475
4
0.09701
69
0.0739
75
1.4426
23
1.557377
05
2.42542
33
1.6812
59
0.09701
69
0.0182
66
127
2.8852
46
0.885245
9
2.0655
74
2.065573
8
4.26659
5
2.0655
74
1.1475
41
1.852459
02
3.43160
44
2.9903
98
1.2622
95
2.737704
92
7.49502
82
5.9376
2
2.5245
9
2.524590
2
6.37355
55
2.5245
9
0.78366
03
0.2716
1
28.909
1
Since our x2 statistic value (28.9091) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that ICT skilled workers are not
available.
RESEARCH QUESTION 37: Not enough competent professionals to managed
Concurrent engineering
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
11
18
client
10
mat
&
supplier
11
contractor
s
22
16
17
17
61
column
total
128
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
4.7213
11
2.721311
5
7.40553
61
1.5685
34
2.6229
51
3.377049
18
11.4044
61
4.3479
51
2.8852
46
2.114754
1
4.47218
49
1.5500
19
5.7704
92
2.770491
8
7.67562
48
1.3301
51
5.0163
93
1.016393
4
1.03305
56
0.2059
36
2.7868
85
0.786885
2
0.61918
84
0.2221
79
3.0655
74
2.934426
23
8.61085
73
2.8088
89
6.1311
48
1.131147
5
1.27949
48
0.2086
88
1.1803
28
1.180327
9
1.39317
39
1.1803
28
0.6557
38
0.344262
3
0.11851
65
0.1807
38
0.7213
11
0.721311
5
0.52029
02
0.7213
11
1.4426
23
1.557377
05
2.42542
33
1.6812
59
11
5.0163
93
5.983606
56
35.8035
47
7.1373
08
129
2.7868
85
1.786885
2
3.0655
74
3.065573
8
9.39774
25
3.0655
74
6.1311
48
1.131147
5
1.27949
48
0.2086
88
2.0655
74
1.065573
8
1.13544
75
0.5497
01
1.1475
41
1.147541
1.31685
03
1.1475
41
1.2622
95
1.262295
1
1.59338
89
1.2622
95
2.5245
9
3.475409
84
12.0784
74
4.7843
3
3.19295
89
1.1457
09
35.307
13
Since our x2 statistic value (35.30713) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that there is enough competent
professionals.
RESEARCH QUESTION 38: Size and characteristics of an industry will help
improve concurrent engineering implementation
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
12
18
client
10
130
mat
&
supplier
11
contractor
s
22
16
23
61
column
total
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
0.52029
02
0.1102
4.7213
11
0.721311
5
2.6229
51
1.377049
18
1.89626
44
0.7229
51
2.8852
46
2.885245
9
8.32464
39
2.8852
46
5.7704
92
2.229508
2
4.97070
68
0.8614
01
12
6.7868
85
5.213114
75
27.1765
65
4.0042
77
3.7704
92
0.770491
8
0.59365
76
0.1574
48
4.1475
41
3.147541
9.90701
42
2.3886
48
8.2950
82
1.295082
1.67723
73
0.2021
97
2.3606
56
0.360655
7
0.13007
26
0.0551
1.3114
75
0.311475
4
0.09701
69
0.0739
75
1.4426
23
0.442623
0.19591
51
0.1358
05
131
2.8852
46
1.114754
1
1.24267
67
0.4307
2.0655
74
2.065573
8
4.26659
5
2.0655
74
1.1475
41
0.147541
0.02176
83
0.0189
7
1.2622
95
1.737704
92
3.01961
84
2.3921
65
2.5245
9
0.475409
84
0.22601
45
0.0895
25
2.0655
74
2.065573
8
4.26659
5
2.0655
74
1.1475
41
0.147541
0.02176
83
0.0189
7
1.2622
95
4.737704
92
22.4458
48
17.781
78
2.5245
9
2.524590
2
6.37355
55
2.5245
9
20.985
09
Since our x2 statistic value (20.98509) did not exceed the critical value for 0.05
probability level, we can accept the null hypothesis.
RESEARCH QUESTION 39: Electricity supply is readily available for project
execution.
options
strongly
A
No
option
Agree
strongly
D
Disagr
ee
row
total
consultant
10
18
client
10
132
mat
&
supplier
11
11
contractor
s
12
22
column
total
38
19
61
fo
fe
(fo-fe)2
/fe
fo-fe
(fo-fe)
17.7503
36
1.5829
98
11.213
11
4.213114
8
6.2295
08
1.770491
8
3.13464
12
0.5031
92
11
6.8524
59
4.147540
98
17.2020
96
2.5103
54
12
13.704
92
1.704918
2.90674
55
0.2120
95
10
5.6065
57
4.393442
62
19.3023
38
3.4428
15
3.1147
54
2.114754
1
4.47218
49
1.4358
07
3.4262
3
3.426229
5
11.7390
49
3.4262
3
6.8524
59
1.147540
98
1.31685
03
0.1921
72
0.2950
82
0.295082
0.08707
34
0.2950
82
0.1639
34
0.836065
57
0.69900
56
4.2639
34
0.1803
28
0.180327
9
0.03251
81
0.1803
28
133
0.3606
56
0.360655
7
0.5901
64
0.409836
07
0.16796
56
0.2846
08
0.3278
69
0.327868
9
0.10749
8
0.3278
69
0.3606
56
0.360655
7
0.13007
26
0.3606
56
0.7213
11
0.278688
52
0.07766
73
0.1076
75
0.2950
82
0.295082
0.08707
34
0.2950
82
0.1639
34
0.163934
4
0.02687
45
0.1639
34
0.1803
28
0.180327
9
0.03251
81
0.1803
28
0.3606
56
0.639344
26
0.40876
11
1.1333
83
0.13007
26
0.3606
56
21.259
2
Since our x2 statistic value (21.2592) exceed the critical value for 0.05
probability level, we can reject the null hypothesis.
RESEARCH QUESTION 40: Members of your technical team often require
supervision to perform their work effectively
options
consultant
client
mat &
supplier
strongly
No
A
Agree
option
9
5
2
1
5
strongly Disagr
row
D
ee
total
0
4
0
18
1
2
4
10
0
11
134
contractor
s
column
total
fo
10
22
26
16
10
61
fe
7.6721
9
31
2
5
10
5
1
3
7
0
1
0
1
4
2
0
4
0
4
3
0
4.2622
95
4.6885
25
9.3770
49
4.7213
11
2.6229
51
2.8852
46
5.7704
92
0.5901
64
0.3278
69
0.3606
56
0.7213
11
2.9508
2
1.6393
44
1.8032
79
3.6065
57
2.0655
74
1.1475
41
1.2622
95
2.5245
9
(fo-fe)2
fo-fe
(fo-fe)
/fe
1.327868 1.76323 0.2298
85
57
23
2.262295 5.11797 1.2007
1
9
57
0.311475 0.09701 0.0206
41
69
92
0.622950 0.38806 0.0413
82
77
85
0.278688 0.07766 0.0164
52
73
5
1.622950 2.63396 1.0042
8
94
01
0.114754 0.01316 0.0045
1
85
64
1.229508 1.51169 0.2619
2
04
69
0.590163 0.34829 0.5901
9
35
64
0.672131 0.45176 1.3778
15
03
69
0.360655 0.13007 0.3606
7
26
56
0.278688 0.07766 0.1076
52
73
75
1.049180 1.10077 0.3730
33
94
42
0.360655 0.13007 0.0793
74
26
44
1.803278 3.25181 1.8032
7
4
79
0.393442 0.15479 0.0429
62
71
21
2.065573 4.26659 2.0655
8
5
74
2.852459 8.13652 7.0903
02
24
98
1.737704 3.01961 2.3921
92
84
65
- 6.37355 2.5245
2.524590
55
9
2
135
2
21.587
52
Since our x2 statistic value (21.58752) exceed the critical value for 0.05
probability level, we can reject the null hypothesis that the professionals involves are
confidence the technical team does not require any supervision to their effectively.
RESEARCH QUESTION 41: Your specialist are committed to any project at hand
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
6
1
3
1
strongly Disagr
row
D
ee
total
2
9
0
18
1
2
3
10
11
14
22
22
18
11
61
fo
fe
6
6.4918
03
3.6065
57
3.9672
13
7.9344
26
5.3114
75
2.9508
2
2
14
2
1
3.2459
02
6.4918
03
1.7704
92
0.9836
fo-fe
0.491803
3
0.606557
4
3.032786
89
1.934426
2
4.311475
4
1.950819
7
1.245901
6
7.508196
72
0.229508
2
0.016393
(fo-fe)
(fo-fe)2
/fe
0.24187
05
0.0372
58
0.36791
19
9.19779
63
0.1020
12
2.3184
53
3.74200
48
0.4716
16
18.5888
2
3.4997
47
3.80569
74
1.2897
09
1.55227
09
56.3730
18
0.05267
4
0.00026
0.4782
25
8.6837
22
0.0297
51
0.0002
136
07
1
1.0819
67
2.1639
34
3.2459
02
1.8032
79
1.9836
07
3.9672
13
2
9
0
3
1
0
1.1803
28
0.6557
38
0.7213
11
1.4426
23
44
0.081967
2
0.163934
4
5.754098
36
0.196721
31
1.983606
6
3.967213
1
1.180327
9
2.344262
3
0.278688
52
1.442623
87
73
0.00671
86
0.0062
1
0.02687
45
33.1096
48
0.03869
93
0.0124
19
10.200
45
0.0214
61
3.93469
5
1.9836
07
15.7387
8
3.9672
13
1.39317
39
5.49556
57
0.07766
73
2.08116
1
1.1803
28
8.3807
38
0.1076
75
1.4426
23
44.213
49
Since our x2 statistic value (44.21349) did not exceed the critical value for 0.05
probability level, we can reject the null hypothesis.
RESEARCH QUESTION 42: Material suppliers are very proficient
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
7
2
0
1
fo
strongly Disagr
row
D
ee
total
1
5
3
18
2
3
4
10
11
11
22
19
16
11
61
(fo-fe)2
fe
fo-fe
(fo-fe)
/fe
5.6065 1.393442 1.94168 0.3463
7
57
62
23
23
2
137
3.1147
54
3.4262
3
6.8524
59
4.7213
11
2.6229
51
0
6
2
11
1
2
2.8852
46
5.7704
92
2.0655
74
1.1475
41
1.2622
95
2.5245
9
3.2459
02
1.8032
79
1.9836
07
1
3
5
3.9672
13
2.3606
56
1.3114
75
1.4426
23
2.8852
46
2
3
4
3.114754
1
2.573770
49
0.852459
2.721311
5
1.622950
8
0.885245
9
5.229508
2
1.065573
8
0.852459
02
0.262295
1
0.475409
84
1.754098
36
1.196721
31
0.983606
6
1.967213
1
0.639344
26
2.688524
59
0.442623
2.885245
9
9.70169
31
6.62429
45
0.72668
64
3.1147
54
1.9334
07
0.1060
48
7.40553
61
1.5685
34
2.63396
94
1.0042
01
0.78366
03
27.3477
56
0.2716
1
4.7392
42
1.13544
75
0.72668
64
0.5497
01
0.6332
55
0.06879
87
0.22601
45
3.07686
11
1.43214
19
0.0545
03
0.0895
25
0.9479
22
0.7941
88
0.96748
19
0.4877
39
3.86992
74
0.40876
11
7.22816
45
0.19591
51
0.9754
78
0.1731
56
5.5114
75
0.1358
05
8.32464
39
2.8852
46
26.322
11
Since our x2 statistic value (26.32211) exceed the critical value for 0.05
138
probability level, we can accept the null hypothesis that material suppliers are
proficient.
RESEARCH QUESTION 43: A higher number of labours will be required in
concurrent engineering
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
8
6
6
4
fo
strongly Disagr
row
D
ee
total
2
2
0
18
0
0
0
10
10
11
22
30
18
61
fe
fo-fe
(fo-fe)
8.8524
- 0.72668
8
59 0.852459
64
4.9180 1.081967 1.17065
6
33
21
31
5.4098 4.590163 21.0696
10
36
93
05
10.819 4.819672 23.2292
6
67
1
39
5.3114 0.688524 0.47406
6
75
59
61
2.9508 1.049180 1.10077
4
2
33
94
3.2459 2.245901 5.04407
1
02
6
42
6.4918 0.508196 0.25826
7
03
72
39
1.7704 0.229508 0.05267
2
92
2
4
0.9836 0.983606 0.96748
0
07
6
19
1.0819 1.081967 1.17065
0
67
2
31
2.1639 1.836065 3.37113
4
34
57
68
2 1.1803 0.819672 0.67186
(fo-fe)2
/fe
0.0820
89
0.2380
33
3.8946
85
2.1469
45
0.0892
53
0.3730
42
1.5539
82
0.0397
83
0.0297
51
0.9836
07
1.0819
67
1.5578
74
0.5692
139
28
0
0.6557
38
0.7213
11
1.4426
23
0.8852
46
0.4918
03
0
3
0.5409
84
1.0819
67
13
0.655737
7
0.721311
5
0.557377
05
0.885245
9
0.491803
3
0.540983
6
1.918032
79
24
17
0.42999
19
0.6557
38
0.52029
02
0.31066
92
0.7213
11
0.2153
5
0.78366
03
0.8852
46
0.24187
05
0.4918
03
0.29266
33
3.67884
98
0.5409
84
3.4001
49
19.550
81
Since our x2 statistic value (19.55081) did not exceed the critical value for 0.05
probability level, we can accept the null hypothesis that a higher labour will required
for this system.
RESEARCH QUESTION 44: Government as regulators will create a constrain
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
0
11
4
4
strongly Disagr
row
D
ee
total
0
7
0
18
1
0
1
10
11
22
11
28
13
61
fo
fe
0
4
3.2459
02
1.8032
79
fo-fe
(fo-fe)
3.245901
6
2.196721
31
10.5358
77
4.82558
45
(fo-fe)2
/fe
3.2459
02
2.6760
06
140
1.9836
07
11
3.9672
13
8.2622
95
4.5901
64
5.0491
8
10.098
36
2.3606
56
1.3114
75
1.4426
23
2.8852
46
3.8360
66
2.1311
48
1
0
7
2.3442
62
4.6885
25
0.2950
82
0.1639
34
0.1803
28
0.3606
56
0
6
0
5.016393
44
3.967213
1
2.737704
92
0.590163
9
1.049180
3
1.098360
7
2.360655
7
0.311475
4
1.442623
4.114754
1
3.163934
43
2.131147
5
2.344262
3
1.311475
41
0.295082
0.836065
57
0.180327
9
0.360655
7
25.1642
03
12.686
09
15.7387
8
7.49502
82
3.9672
13
0.9071
36
0.34829
35
0.0758
78
1.10077
94
0.2180
11
1.20639
61
0.1194
65
5.57269
55
2.3606
56
0.09701
69
2.08116
1
16.9312
01
10.0104
81
0.0739
75
1.4426
23
4.54178
98
2.1311
48
5.49556
57
1.71996
78
0.08707
34
0.69900
56
2.3442
62
0.3668
46
0.2950
82
4.2639
34
0.03251
81
0.1803
28
0.13007
26
0.3606
56
46.192
98
5.8682
2.6095
7
Since our x2 statistic value (46.19298) exceed the critical value for 0.05
141
probability level, we can reject the null hypothesis that Government regulation will
not be a constrain.
RESEARCH QUESTION 45: Institutional support is required for concurrent
engineering application.
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
10
8
5
4
fo
strongly Disagr
row
D
ee
total
0
0
0
18
0
0
1
10
11
14
22
20
31
61
fe
fo-fe
(fo-fe)2
5.9016 4.098360 16.7965
10
39
66
6
3.2786 1.721311 2.96291
5
89
48
32
3.6065 0.606557 0.36791
3
57
4
19
7.2131 5.213114 27.1765
2
15
8
65
9.1475
- 1.31685
8
41 1.147541
03
5.0819 1.081967 1.17065
4
67
2
31
5.5901 0.590163 0.34829
5
64
9
35
11.180 2.819672 7.95055
14
33
13
09
1.1803 1.180327 1.39317
0
28
9
39
0.6557 0.655737 0.42999
0
38
7
19
0.7213 1.278688 1.63504
2
11
52
43
1.4426 0.557377 0.31066
2
23
05
92
(fo-fe)2
/fe
2.8460
84
0.9036
89
0.1020
12
3.7676
6
0.1439
57
0.2303
54
0.0623
05
0.7111
2
1.1803
28
0.6557
38
2.2667
66
0.2153
5
142
0.5901
64
0.3278
69
0
2
0
1
1
2
0.3606
56
0.7213
11
1.1803
28
0.6557
38
0.7213
11
1.4426
23
0.590163
9
0.327868
9
0.360655
7
1.278688
52
1.180327
9
0.344262
3
0.278688
52
0.557377
05
0.34829
35
0.5901
64
0.10749
8
0.3278
69
0.13007
26
1.63504
43
0.3606
56
2.2667
66
1.39317
39
0.11851
65
0.07766
73
0.31066
92
1.1803
28
0.1807
38
0.1076
75
0.2153
5
18.314
91
Since our x2 statistic value (18.31491) did not exceed the critical value for 0.05
probability level, we can accept the null hypothesis that institutional support will be
instrumental.
RESEARCH QUESTION 46: Will you support concurrent engineering for your
company
options
consultant
client
mat &
supplier
contractor
s
column
total
strongly
No
A
Agree
option
12
6
7
2
fo
strongly Disagr
row
D
ee
total
0
0
0
18
0
0
1
10
11
13
22
40
13
61
fe
fo-fe
(fo-fe)
11.803 0.196721 0.03869
12
28
31
93
6.5573 0.442622 0.19591
7
77
95
51
(fo-fe)2
/fe
0.0032
79
0.0298
77
143
7.2131
15
14.426
23
3.8360
66
2.1311
48
2.3442
62
4.6885
25
1.4754
1
13
0.8196
72
0.9016
39
1.8032
79
0.2950
82
0.1639
34
0
1
4
0
1
0
1
0
1
0.1803
28
0.3606
56
0.5901
64
0.3278
69
0.3606
56
0.7213
11
0.786885
25
1.426229
5
2.163934
43
0.131147
5
0.344262
3
1.688524
6
1.475409
8
0.819672
1
0.098360
66
2.196721
31
0.295082
0.163934
4
0.180327
9
0.639344
26
0.590163
9
0.672131
15
0.360655
7
0.278688
52
0.61918
84
0.0858
42
2.03413
06
4.68261
22
0.1410
02
1.2206
81
0.01719
97
0.0080
71
0.11851
65
0.0505
56
2.85111
53
0.6081
05
2.17683
42
1.4754
1
0.67186
24
0.00967
48
4.82558
45
0.08707
34
0.8196
72
0.0107
3
2.6760
06
0.2950
82
0.02687
45
0.1639
34
0.03251
81
0.40876
11
0.1803
28
1.1333
83
0.34829
35
0.45176
03
0.5901
64
1.3778
69
0.13007
26
0.07766
73
0.3606
56
0.1076
75
11.338
32
Since our x2 statistic value (11.33832) did not exceed the critical value for 0.05
144
probability level, we can accept the null hypothesis that CE is concept that has come
to stay.
4.3 SUMMARY OF RESULTS
COOMPARISON OF RESULT SAMPLES.
Agree/disagr
Agree/disagree
ee
S/NO
Questions
General sample
From
State
and
Warri.
1.
Disagree
Disagree
2.
Disagree
Disagree
3.
Agree
Disagree
Disagree
Disagree
be
Disagree
Disagree
Disagree
Disagree
execution
4.
5.
Plant/equipment
support
would
Agree
Disagree
8.
Disagree
Disagree
control
9.
Disagree
Disagree
10.
Disagree
Disagree
Disagree
Disagree
Disagree
Disagree
12.
145
Disagree
Disagree
14.
Disagree
Disagree
15.
Disagree
Disagree
16.
Disagree
Disagree
Disagree
Disagree
undeveloped
17.
18.
Disagree
Disagree
19.
Disagree
Disagree
Disagree
Disagree
Agree
Disagree
Disagree
Disagree
expensive
20.
21.
22.
needed
requirements
of
Concurrent
engineering
23.
Disagree
Disagree
Disagree
responsibility
25.
Agree
Disagree
26.
Agree
Disagree
Disagree
Disagree
Disagree
Agree
is easy
27.
28.
Dependence
on
imported
material
and
146
Facilities
for
professional
teaming
is
Agree
Disagree
Disagree
Disagree
Disagree
Disagree
Disagree
Disagree
communication
Disagree
Disagree
Disagree
Disagree
Disagree
inadequate
30.
The
local
penetration
of
information
32.
33.
Bandwidth
available
for
cannot be guaranteed
34.
Disagree
Disagree
Disagree
Disagree
Agree
Disagree
Disagree
Disagree
Disagree
Disagree
Agree
Disagree
Disagree
Disagree
company
37.
Not
enough
competent
professionals
to
improve
concurrent
engineering
implementation
39.
40.
41.
42.
147
43.
Agree
Disagree
Disagree
Disagree
Agree
Agree
concurrent engineering
44.
45.
46.
Disagree
your company
4.4 DISCUSSION
After analysing the results using Chi square, results assessment obtained from
Edo State and Warri in Delta State shows that there is actually a low level of
awareness. Comparing this result with the general samples from the six different
States, the awareness is generally low.
These result further shows that, there are constraints that will hinder it
implementation if not closely examined. Such constrains includes;
1.
2.
3.
4.
5.
6.
7.
8.
Government policies
Plant and Equipment support
Import and Export policies
Corruption in the system
Facilities for professional training
Bank and Credits facilities
Insurance policies
Availability of power
The most of the respondents agreed that it will help in improve construction
148
CHAPTER FIVE
5.0 CONCLUSION
The assessment of this research has so far shown the level of awareness and
use of concurrent engineering of the respondents on the feasibility of the system,
benefits and constraints that will be experience in the Nigeria system.
It is expected that these will guide organisation and firms in Nigeria and other
developing countries identify where to focus their efforts to promote increase in
productivity in applying concurrent engineering in the construction industry in
Nigeria.
5.1 RECOMMENDATION
149
This should be review in the next few years to measure any quantitative and
qualitative advancement in application of concurrent engineering and it sustainability
in the Nigeria construction industry.
REFERENCES
1. Aniekwu N. (1995). The business environment of the construction industry in
Nigeria, Construction Management and Economics 13, 445-455.
2. Arif A. A and Karam A.H. (2001). Architectural practices and their use of IT
in the Western Cape
Province, South Africa, Journal of Information Technology in Construction,
6, 17-34, at http://www.itcon.org/2001/2
3. Adachi, T., Enkawa, T. and Shih, L. C. (1995), A concurrent engineering
methodology using analogies to just-in-time concepts, International Journal
of Production Research, Vol. 33, No. 3, pp. 587609.
4. Adebayo A. Oladapo, 2006. An investigation into the use of ICT in the
Nigerian construction industry
5. Adler, P., Mandelbaum, A., Nguyen, V. and Schwerer, E. (1994), From
project
to
process
management
in
engineering:
managerial
and
150
151
152
35. Rockart, John F. & Short, James E. 1989. IT in the 1990s: Managing
Organizational Interdependence. Sloan Management Review, Winter 1989. P.
7 - 17.
36. Plenert, Gerhard. 1990. Three differing concepts of JIT. Production and
Inventory Management Journal, Second Quarter, pp. 1 - 2.
37. Pall, Gabriel A. 1987. Quality Process Management. Prentice-Hall,
Englewood Cliffs, NJ.
38. Schonberger, Richard J. 1982. Japanese manufacturing techniques. The Free
Press, New York. 260 p.
39. Schonberger, Richard J. 1986. World class manufacturing. The Free Press,
New York. 253 p
APPENDIX 1
FEASIBILITY OF CONCURRENT ENGINEERING IN THE
NIGERIAN CONSTRUTION INDUSTRY
153
Note:
disagree = 1
A BRIEF INTRODUCTION OF CONCURRENT ENGINEERING (CE)
In the context of the construction industry, Evbuomwan & Anumba (1998)
defined Concurrent Engineering as an attempt to optimise the design of the
project and its construction process to achieve reduced lead times, and improved
quality and cost by the integration of design, fabrication, construction and erection
activities and by maximising concurrency and collaboration in working practices.
This is in sharp contrast with the traditional approach to construction project
delivery.
There is growing awareness and interest in the adoption of Concurrent
Engineering (CE) in the Construction Industry because CE has the potential to make
construction projects less fragmented, improve project quality, reduce project
duration and reduce total project cost. The urgent need to improve the performance
of construction can also be achieved during the design process by concurrently
considering key aspects of the construction projects downstream phases. It is evident
that by adopting Concurrent Engineering, the construction industries have
significantly improved their business processes.
154
155
SECTION A
Please specify your role on site;
1. Client
2. Consultant
3. Contractors
4.
contractors
Sub-
5.
Material
suppliers/manufacturers
Please circle the letters of your appropriate view on the following statements.
1.
b. 30-50 years
c. 10-30 years d.
5-10
years
e. Less than 5 years
2.
b. 75-50%
c. 50-25%
d.25-10%
e. Less
than 10%
3.
How much collateral are you normally required to furnish when taking a loan
from a bank?
a. 100-75%
b. 75-50%
c. 50-25%
d.25-10%
e. Less
than 10%
4.
b. 75-50%
c. 50-25%
d.25-10%
e. Less
d. Rarely
e. Never
than 10%
5.
a. Always
c. Sometimes
156
6.
b. 75-50%
c. 50-25%
d.25-10%
e.
Less
than 10%
7.
How many of your technical staff are co-located in the same environment?
a. 100-75%
b. 75-50%
c. 50-25%
d.25-10%
e. Less
than 10%
How often are meetings held with the clients for briefing on work progress?
8.
a. Always
c. Sometimes
d. Rarely
e.
Never
9.
c. Sometimes
d. Rarely
e.
Never
10.
Projects
Projects
Buildings
Airports
Dams
Bridges
Highways
works
Ports/harbour
Tower constructions
157
12.
Projects
% Projects
Government ministries
Private companies
Government parastatals
International/foreign
organisation
Private individuals
14.
Please
tick
which
of
these
is
readily
available
for
Telephone
Internet
Fax
Post office
Courier service
SECTION B
Note: strongly agree = 5, Agree = 4, no option = 3, disagree =2,
strongly disagree = 1
Please tick your appropriate view in the following statements.
S/N
O
158
1.
2.
3.
4.
5.
6.
This
concept
of
Concurrent
Engineering is for smaller firms and
younger person
7.
8.
S/N
O
9.
10.
11.
12.
13.
Insurance
policies
implemented
14.
15.
are
well
159
16.
17.
18.
19.
20.
21.
22.
23.
24.
involves
S/N
O
25.
Compliance
with
contract is low
conditions
26.
Sabotage
of
the
concurrent
engineering system is easy
27.
Compliance/cooperation
of
team
members is not guaranteed without
sanction
28.
29.
of
160
inadequate
30.
31.
Dependence
of
Concurrent
Engineering on communication will
create problems for the effectiveness
of the concept
32.
33.
Bandwidth
available
for
communication cannot be guaranteed
34.
35.
36.
37.
S/N
O
38.
39.
40.
41.
161
42.
43.
44.
45.
46.
Will
you
support
concurrent
engineering for your company
Thank you very much for taking the time to complete the
questionnaire. If you wish to comment further please use the space
below.
162
APPENDIX 2
Chi-square distribution table
P
DF
1
0.995
0.975
0.0000393 0.000982
0.20
0.10
0.05
0.025
0.02
0.01
0.005
0.002
0.001
1.642
2.706
3.841
5.024
5.412
6.635
7.879
9.550
10.828
0.0100
0.0506
3.219
4.605
5.991
7.378
7.824
9.210
10.597
12.429
13.816
0.0717
0.216
4.642
6.251
7.815
9.348
9.837
11.345
12.838
14.796
16.266
0.207
0.484
5.989
7.779
9.488
11.143
11.668
13.277
14.860
16.924
18.467
0.412
0.831
7.289
9.236
11.070
12.833
13.388
15.086
16.750
18.907
20.515
163
0.676
1.237
8.558
10.645
12.592
14.449
15.033
16.812
18.548
20.791
22.458
0.989
1.690
9.803
12.017
14.067
16.013
16.622
18.475
20.278
22.601
24.322
1.344
2.180
11.030
13.362
15.507
17.535
18.168
20.090
21.955
24.352
26.124
1.735
2.700
12.242
14.684
16.919
19.023
19.679
21.666
23.589
26.056
27.877
10
2.156
3.247
13.442
15.987
18.307
20.483
21.161
23.209
25.188
27.722
29.588
11
2.603
3.816
14.631
17.275
19.675
21.920
22.618
24.725
26.757
29.354
31.264
12
3.074
4.404
15.812
18.549
21.026
23.337
24.054
26.217
28.300
30.957
32.909
13
3.565
5.009
16.985
19.812
22.362
24.736
25.472
27.688
29.819
32.535
34.528
14
4.075
5.629
18.151
21.064
23.685
26.119
26.873
29.141
31.319
34.091
36.123
15
4.601
6.262
19.311
22.307
24.996
27.488
28.259
30.578
32.801
35.628
37.697
16
5.142
6.908
20.465
23.542
26.296
28.845
29.633
32.000
34.267
37.146
39.252
17
5.697
7.564
21.615
24.769
27.587
30.191
30.995
33.409
35.718
38.648
40.790
18
6.265
8.231
22.760
25.989
28.869
31.526
32.346
34.805
37.156
40.136
42.312
19
6.844
8.907
23.900
27.204
30.144
32.852
33.687
36.191
38.582
41.610
43.820
20
7.434
9.591
25.038
28.412
31.410
34.170
35.020
37.566
39.997
43.072
45.315
21
8.034
10.283
26.171
29.615
32.671
35.479
36.343
38.932
41.401
44.522
46.797
22
8.643
10.982
27.301
30.813
33.924
36.781
37.659
40.289
42.796
45.962
48.268
23
9.260
11.689
28.429
32.007
35.172
38.076
38.968
41.638
44.181
47.391
49.728
24
9.886
12.401
29.553
33.196
36.415
39.364
40.270
42.980
45.559
48.812
51.179
25
10.520
13.120
30.675
34.382
37.652
40.646
41.566
44.314
46.928
50.223
52.620
26
11.160
13.844
31.795
35.563
38.885
41.923
42.856
45.642
48.290
51.627
54.052
27
11.808
14.573
32.912
36.741
40.113
43.195
44.140
46.963
49.645
53.023
55.476
28
12.461
15.308
34.027
37.916
41.337
44.461
45.419
48.278
50.993
54.411
56.892
29
13.121
16.047
35.139
39.087
42.557
45.722
46.693
49.588
52.336
55.792
58.301
30
13.787
16.791
36.250
40.256
43.773
46.979
47.962
50.892
53.672
57.167
59.703
164
31
14.458
17.539
37.359
41.422
44.985
48.232
49.226
52.191
55.003
58.536
61.098
32
15.134
18.291
38.466
42.585
46.194
49.480
50.487
53.486
56.328
59.899
62.487
33
15.815
19.047
39.572
43.745
47.400
50.725
51.743
54.776
57.648
61.256
63.870
34
16.501
19.806
40.676
44.903
48.602
51.966
52.995
56.061
58.964
62.608
65.247
35
17.192
20.569
41.778
46.059
49.802
53.203
54.244
57.342
60.275
63.955
66.619
36
17.887
21.336
42.879
47.212
50.998
54.437
55.489
58.619
61.581
65.296
67.985
37
18.586
22.106
43.978
48.363
52.192
55.668
56.730
59.893
62.883
66.633
69.346
38
19.289
22.878
45.076
49.513
53.384
56.896
57.969
61.162
64.181
67.966
70.703
39
19.996
23.654
46.173
50.660
54.572
58.120
59.204
62.428
65.476
69.294
72.055
40
20.707
24.433
47.269
51.805
55.758
59.342
60.436
63.691
66.766
70.618
73.402
41
21.421
25.215
48.363
52.949
56.942
60.561
61.665
64.950
68.053
71.938
74.745
42
22.138
25.999
49.456
54.090
58.124
61.777
62.892
66.206
69.336
73.254
76.084
43
22.859
26.785
50.548
55.230
59.304
62.990
64.116
67.459
70.616
74.566
77.419
44
23.584
27.575
51.639
56.369
60.481
64.201
65.337
68.710
71.893
75.874
78.750
45
24.311
28.366
52.729
57.505
61.656
65.410
66.555
69.957
73.166
77.179
80.077
46
25.041
29.160
53.818
58.641
62.830
66.617
67.771
71.201
74.437
78.481
81.400
47
25.775
29.956
54.906
59.774
64.001
67.821
68.985
72.443
75.704
79.780
82.720
48
26.511
30.755
55.993
60.907
65.171
69.023
70.197
73.683
76.969
81.075
84.037
49
27.249
31.555
57.079
62.038
66.339
70.222
71.406
74.919
78.231
82.367
85.351
50
27.991
32.357
58.164
63.167
67.505
71.420
72.613
76.154
79.490
83.657
86.661
51
28.735
33.162
59.248
64.295
68.669
72.616
73.818
77.386
80.747
84.943
87.968
52
29.481
33.968
60.332
65.422
69.832
73.810
75.021
78.616
82.001
86.227
89.272
53
30.230
34.776
61.414
66.548
70.993
75.002
76.223
79.843
83.253
87.507
90.573
54
30.981
35.586
62.496
67.673
72.153
76.192
77.422
81.069
84.502
88.786
91.872
55
31.735
36.398
63.577
68.796
73.311
77.380
78.619
82.292
85.749
90.061
93.168
165
56
32.490
37.212
64.658
69.919
74.468
78.567
79.815
83.513
86.994
91.335
94.461
57
33.248
38.027
65.737
71.040
75.624
79.752
81.009
84.733
88.236
92.605
95.751
58
34.008
38.844
66.816
72.160
76.778
80.936
82.201
85.950
89.477
93.874
97.039
59
34.770
39.662
67.894
73.279
77.931
82.117
83.391
87.166
90.715
95.140
98.324
60
35.534
40.482
68.972
74.397
79.082
83.298
84.580
88.379
91.952
96.404
99.607
61
36.301
41.303
70.049
75.514
80.232
84.476
85.767
89.591
93.186
97.665
100.888
62
37.068
42.126
71.125
76.630
81.381
85.654
86.953
90.802
94.419
98.925
102.166
63
37.838
42.950
72.201
77.745
82.529
86.830
88.137
92.010
95.649
100.182
103.442
64
38.610
43.776
73.276
78.860
83.675
88.004
89.320
93.217
96.878
101.437
104.716
65
39.383
44.603
74.351
79.973
84.821
89.177
90.501
94.422
98.105
102.691
105.988
66
40.158
45.431
75.424
81.085
85.965
90.349
91.681
95.626
99.330
103.942
107.258
67
40.935
46.261
76.498
82.197
87.108
91.519
92.860
96.828
100.554 105.192
108.526
68
41.713
47.092
77.571
83.308
88.250
92.689
94.037
98.028
101.776 106.440
109.791
69
42.494
47.924
78.643
84.418
89.391
93.856
95.213
99.228
102.996 107.685
111.055
70
43.275
48.758
79.715
85.527
90.531
95.023
96.388
112.317
71
44.058
49.592
80.786
86.635
91.670
96.189
97.561
113.577
72
44.843
50.428
81.857
87.743
92.808
97.353
98.733
102.816 106.648
111.412
114.835
73
45.629
51.265
82.927
88.850
93.945
98.516
99.904
116.092
74
46.417
52.103
83.997
89.956
95.081
99.678
117.346
75
47.206
52.942
85.066
91.061
96.217
118.599
76
47.997
53.782
86.135
92.166
97.351
116.359
119.850
77
48.788
54.623
87.203
93.270
98.484
121.100
78
49.582
55.466
88.271
94.374
99.617
122.348
79
50.376
56.309
89.338
95.476
111.144
115.117 120.052
123.594
80
51.172
57.153
90.405
96.578
116.321 121.280
124.839
166
81
51.969
57.998
91.472
97.680
117.524 122.507
126.083
82
52.767
58.845
92.538
98.780
118.726 123.733
127.324
83
53.567
59.692
93.604
99.880
105.267 110.090
119.927 124.957
128.565
84
54.368
60.540
94.669
100.980 106.395
111.242
129.804
85
55.170
61.389
95.734
131.041
86
55.973
62.239
96.799
132.277
87
56.777
63.089
97.863
133.512
88
57.582
63.941
98.927
134.745
89
58.389
64.793
99.991
135.978
90
59.196
65.647
137.208
91
60.005
66.501
138.438
92
60.815
67.356
139.666
93
61.625
68.211
104.241 110.850
140.893
94
62.437
69.068
105.303
111.944
142.119
95
63.250
69.925
106.364 113.038
143.344
96
64.063
70.783
107.425 114.131
144.567
97
64.878
71.642
145.789
98
65.694
72.501
147.010
99
66.510
73.361
148.230
100
67.328
74.222
111.667
149.449
101
68.146
75.083
150.667
102
68.965
75.946
151.884
103
69.785
76.809
153.099
104
70.606
77.672
154.314
105
71.428
78.536
155.528
111.553
115.876
167
106
72.251
79.401
156.740
107
73.075
80.267
157.952
108
73.899
81.133
159.162
109
74.724
82.000
160.372
110
75.550
82.867
161.581
111
76.377
83.735
162.788
112
77.204
84.604
163.995
113
78.033
85.473
165.201
114
78.862
86.342
166.406
115
79.692
87.213
167.610
116
80.522
88.084
168.813
117
81.353
88.955
170.016
118
82.185
89.827
171.217
119
83.018
90.700
172.418
120
83.852
91.573
173.617
121
84.686
92.446
174.816
122
85.520
93.320
176.014
123
86.356
94.195
177.212
124
87.192
95.070
178.408
125
88.029
95.946
179.604
126
88.866
96.822
180.799
127
89.704
97.698
181.993
128
90.543
98.576
183.186
129
91.382
99.453
184.379
130
92.222
185.571
168
131
93.063
186.762
132
93.904
187.953
133
94.746
189.142
134
95.588
190.331
135
96.431
191.520
136
97.275
192.707
137
98.119
193.894
138
98.964
195.080
139
99.809
196.266
140
100.655
197.451
141
101.501
198.635
142
102.348
199.819
143
103.196
201.002
144
104.044
202.184
145
104.892
203.366
146
105.741
204.547
147
106.591
205.727
148
107.441
206.907
149
108.291
208.086
150
109.142
209.265
151
109.994
210.443
152
110.846
211.620
153
111.698
212.797
154
112.551
213.973
155
113.405
215.149
169
156
114.259
216.324
157
115.113
217.499
158
115.968
218.673
159
116.823
219.846
160
117.679
221.019
161
118.536
222.191
162
119.392
223.363
163
120.249
224.535
164
121.107
225.705
165
121.965
226.876
166
122.823
228.045
167
123.682
229.215
168
124.541
230.383
169
125.401
231.552
170
126.261
232.719
171
127.122
233.887
172
127.983
235.053
173
128.844
236.220
174
129.706
237.385
175
130.568
238.551
176
131.430
239.716
177
132.293
240.880
178
133.157
242.044
179
134.020
243.207
180
134.884
244.370
170
181
135.749
245.533
182
136.614
246.695
183
137.479
247.857
184
138.344
249.018
185
139.210
250.179
186
140.077
251.339
187
140.943
252.499
188
141.810
253.659
189
142.678
254.818
190
143.545
255.976
191
144.413
257.135
192
145.282
258.292
193
146.150
259.450
194
147.020
260.607
195
147.889
261.763
196
148.759
262.920
197
149.629
264.075
198
150.499
265.231
199
151.370
266.386
200
152.241
267.541
201
153.112
268.695
202
153.984
269.849
203
154.856
271.002
204
155.728
272.155
205
156.601
273.308
171
206
157.474
274.460
207
158.347
275.612
208
159.221
276.764
209
160.095
277.915
210
160.969
279.066
211
161.843
280.217
212
162.718
281.367
213
163.593
282.517
214
164.469
283.666
215
165.344
284.815
216
166.220
285.964
217
167.096
287.112
218
167.973
288.261
219
168.850
289.408
220
169.727
290.556
221
170.604
291.703
222
171.482
292.850
223
172.360
293.996
224
173.238
295.142
225
174.116
296.288
226
174.995
297.433
227
175.874
298.579
228
176.753
299.723
229
177.633
300.868
230
178.512
302.012
172
231
179.392
303.156
232
180.273
304.299
233
181.153
305.443
234
182.034
306.586
235
182.915
307.728
236
183.796
308.871
237
184.678
310.013
238
185.560
311.154
239
186.442
312.296
240
187.324
313.437
241
188.207
314.578
242
189.090
315.718
243
189.973
316.859
244
190.856
317.999
245
191.739
319.138
246
192.623
320.278
247
193.507
321.417
248
194.391
322.556
249
195.276
323.694
250
196.161
324.832
300
240.663
381.425
350
285.608
437.488
400
330.903
493.132
450
376.483
548.432
500
422.303
603.446
173
550
468.328
658.215
600
514.529
712.771
650
560.885
767.141
700
607.380
821.347
750
653.997
875.404
800
700.725
929.329
850
747.554
983.133
900
794.475
818.756 935.499 954.782 970.904 985.032 989.263 1001.630 1013.036 1026.974 1036.826
950
841.480
866.477 986.478 1006.272 1022.816 1037.311 1041.651 1054.334 1066.031 1080.320 1090.418
100
0
888.564
914.257 1037.431 1057.724 1074.679 1089.531 1093.977 1106.969 1118.948 1133.579 1143.917
174
175