Vous êtes sur la page 1sur 16

XLRI Jamshedpur

Rajiv Misra

PRODUCTION PLANNING AND


CONTROL
Team No 8
Name of Group Members
Shirish Pathak B14050
Ashutosh Mathur B14015
Tarun Bagri B14055
Nikhil Arora B14159

Name of file to be mailed to rajiv @xlri.ac.in Format: BM_PPC_Team X_2013


X is the team no

where

PROCESS ANALYTICS HANDBOOK

Problem 1: Three Step Process Assignment Questions


Process 1
To begin, consider the three-step process model in the Process 1 tab. The process is staffed by
three workers: Alice is assigned to step A, Bob is assigned to step B, and Charlie is assigned
to step C. Please answer the questions below.
1. What is the bottleneck of this process?
Bob
2. What is the cycle time of this process?
5 Min
3. What is the capacity of this process?
12 per hr
4. What is the throughput time or a rush order (that is, an order arriving when the system is
empty that is moved through the process without delay)?
10 Min

5. What is the labor utilization of each worker?


Alice:60%, Bob:100%, Charlie:40%

6. What is the average labor utilization of the workers?


66.67%

Process 2

Now that you have finished Process 1, consider the same process, but assume we assign
Betty, an additional worker, to a step B. Betty and Bob are equally qualified, and they are
told to split the work of step B (working simultaneously complete the 5 minutes of work on a
unit in half that time).
1.

Before doing any calculations, which process metrics would you expect to change
relative to Process1

Cycle time, Throughput time


2.

What is the cycle time of this process?

3 Min
3.

What is the capacity of this process?

20 per hr.
4.

What is the throughput time for a rush order (that is, an order arriving when the
system is empty that is moved through the process without delay)?

10 min

5.

What is the labor utilization of each worker?

Alice: 100%, Bob: 83%, Betty: 83%, Charlie: 67%

6.

What is the average labor utilization of the workers?

83.33%

7.

What have you learned?

Elevating one bottleneck shifts the process bottleneck.

Process 3

Look at Process 3, a variant of Process 1 ( 3 workers, Alice does step A, Bob step B, and
Charlie step C). However, assume that steps A and B can be completed in parallel, as shown
in the process diagram. (In parallel means that Alice can work on her component at the
same time as Bob works on his component. For example, Alice could be finishing a table top
at the same time Bob is finishing the four legs, and Charlie could be assembling the table by
attaching the legs to the table top.)
1. Before doing any calculations, which process metrics would you Process I?
Cycle time, throughput time
2. What is the bottleneck of this process?
Workstation B
3. What is the cycle time of this process?
5 Min
4. What is the capacity of this process?
12 per hr
5. What is the throughput time for a rush order (that is an order arriving when the system
is empty that is moved through the process without delay)?
7 Min
6. What is the labor utilization of each worker?
Alice: 60%, Bob: 100%, Charlie: 40%
7. What is the average labor utilization of the workers?
66.67%
8. What have you learned?
Throughput time can be reduced by doing activities in parallel.

Problem 2: Four Step Process Assignment Questions

Process 1
To begin, consider the four step process model in the Process 1 tab.
1. Calculate the amount of the time it would take to get a rush order through the process.
14.5 Min
2. Calculate the capacity of the process.
12 per Hr
3. Calculate the labor content of the process.
A: 100%, B: 60%, C:50%, D: 80%
4. Calculate the average labor utilization.
72.5%

Process 2
For the process 2, assume that you have hired an additional worker (i.e., a fifth for the
process). This new worker is cross trained at every step in process (can perform any of the 4
steps or any portion of any of the four steps). Inventory is permitted between steps so that the
cross trained worker can move around freely. Assume no transportation time in moving from
one step to another.
1.

At which step (s) does the worker spend the majority of his or her time?

Workstation A
2.

What is the impact on performance?

Capacity increased to 20 per hr, Utilization increased to 96.67%

Process 3

For Process 3, you have the opportunity to send each of your four specialists to get additional
training in the other process steps. As a result of this training program, you will have five
workers available to you, each one cross-trained at each of the four process steps.
1.

What benefits do you expect as a result of this additional training?

Capacity increased to 20.69 per hr, Utilization increased to 100%

Process 4
Go to Process 4, a variant of Process 1. Your analysis was done with the assumption that no
inventory would be allowed to build up between steps. Answer these questions without that
assumption.
1. How would performance change if this restriction were relaxed? That is, what would
impact of allowing inventory to accumulate between steps?
Capacity changed to 12 per hr, utilazation to 72.5%

Problem 3: Sub Assembly Assignment Questions


Consider the following process in the Process 1 tab. All steps (A, B, C, D) are necessary to
create each finished unit. Each step employs a single worker who is not cross-trained for any
other processing times listed represent the amount of time each worker spends on a single
unit. There is not variability in processing times.
Process 1
1. What is the fastest that a rush order can go through the process?
35 Min

2. Working 8 hours a day, what is the daily capacity?


32

Process 2
For the next two questions, consider a fifth step added to the process along with a fifth
worker. The fifth step, Step E, is done after Step C, and before Ste D, as depicted Process 2.
All steps (A, B, C, D, and E) are necessary to create each finished unit. Processing times are
shown for each process step.
3. What is the fastest that a rush order can go through the process?
45 min

4. Working 8 hours a day, what is the daily capacity?


32

Problem 4: Batch Processing Assignment Questions


Consider the following three-step worker- paced line in the Process 1 tab. Each step employs
a single worker who is not cross- trained for any other step. The setup represents the amount
of time the worker spends setting u e machine hatch. No units can be processed during setup.
The run time represents the amount of time it takes the worker to process a single unit. When
a worker completes a batch, he or she hands it off to the next stage.
Process 1
1. If only 10-unit batches are produced, what is the average capacity of the process per 8hour
50
2. At what batch size does the bottleneck move? That is, at what batch size are there two
steps that are the bottleneck?
5

Problem 5: Random Variation Assignment Questions


Consider the six-step process in the Process 1 tab, where the processing time for each step is
uniformly distributed. Processing times can range from 12 to 18 minutes (any value in that
range is as likely to occur as any other in that range).
Process 1
1. If inventory were permitted to accumulate throughout this process, what impact would
you expect on capacity (as compared to the process without inventory)?
Capacity would increase in the case with inventory compared to case without inventory as it
would act as a buffer in case of uncertainty

2. If you could add one inventory buffer, where would you add it to maximize capacity?
Would add inventory buffer before lowest workstation utilization hence workstation C to
make sure that low utilization is not due to material unavailability
3. If you added a second unit of buffer to the same location as the first, what would be the
incremental impact on capacity of the second unit as compared with the first unit?
Incremental impact of the second inventory buffer would be less as compared to the first unit

Problem 6: Inventory Assignment Questions


consider the four-step worker paced line in the Process 1 tab. Each step employs a single
worker who is not cross-trained for any other step. The processing times listed represent the
amount of time each worker spends on a single unit. There is no variability in processing
times. Assume that all workers begin to work on the next unit as soon as they can.
Process 1
1. Assume that inventory is not permitted to accumulate - i.e., a unit cannot be passed to the
next stage until the worker receiving the unit is ready for it. What is the capacity of the
process?
3 per hr

2. If inventory were allowed to accumulate in this process, where would it accumulate?


1. Between A and B.
2. Between C and D
3. If inventory were allowed to accumulate, how would capacity be affected?
No impact as there is no variability in the process time

4. If inventory were allowed to accumulate, how would average throughput time be


affected?
Average throughput time will increase as more material will be in process due to inventory
buffer but processing time will remain same.

From this point forward, assume that inventory is not permitted to accumulate, and that work
cannot be passed to the next stage until the worker receiving the unit is ready.
5. If a fifth worker were added to the process, what would the maximum capacity be?
Assume that you can add the fifth worker to anyone of the four tasks, that the worker is
not cross trained to do any of the other tasks and that the fifth worker works at the same
rate as the original worker doing that task.
4 per hr

6. Instead, if a fifth worker who was cross trained for all tasks were added to the process,
what would the new capacity be? Assume that this fifth worker incurs no travel time in
moving between Compare the labor utilization of the worker at Step 1 in the original
situation (four workers, no inventory) and the situation with the addition of the crosstrained fifth worker from the Four Step Process problem. How does it change?
New capacity 5.14 per hr.
Utilization would increase from 62.5% to 85.71%

Problem 7: Krunchy Kreme Assignment Questions


Krunchy Kreme, marking its famous doughnuts, begins with the three-step process shown in
Process 1. One dedicated worker mixes the dough and creates the doughnut shape from it.
Batches of doughnuts from the Shaping stage are processed in one of two identical machines
in the third step, staffed by one worker each. (Ignore the remaining steps in the process, such
as frying and packing, because they have ample capacity.) Assume that all setups are done by
the workers. A setup must be performed in each step of the process before every batch. Also,
assume that each worker is busy during the run time of his or her operation.
Process 1
1. Suppose that the batch size is 50 doughnuts. What is the capacity in an eight hour day?
500

2. What is the average utilization of these four workers?


84.21%

3. If Krunchy Kreme decides to change batch sizes, for what range of batch sizes is mixing
the bottleneck?
Workstation A & Workstation B: Batch size 28.57
Workstation A & Workstation C: Batch size 81.81
Workstation C & Workstation B: Batch size 175

Problem 8: Random Variation with Long Chains Assignment


Process 1
For the processes in this assignment, we will explicitly account for variability in process time
with those process times distributed according to a uniform distribution. Thus, a process time
of 5 1 minutes/unit indicates that there is equal probability that the process (machine or
person) will have a process time of anywhere from four to six minutes/unit. There are no
setups.
1. Consider an eight-workstation in-series line, with all workstation processing time at 5 1
minutes per unit. Allocate 22 units of buffer capacity to this line so as to maximize average
output. What is the best such allocation?
To maximize the average output allocate equal units before each workstation. Hence from
workstation 2 allocate 3 units each and remaining one extra units before workstation 8 as
more variability will be there.
For the rest of this part, consider four different production ,lines consisting of in-series
workstations with no buffers between stations. The numbers under e workstation represent
the process time per unit, in minutes.
2. Assuming that Line A has been operating for a while, the expected capacity of Line A is a.
a. Less than 6 units per hour
b. Greater than 6 units per hour
c. 6 units per hour
d. Cannot be determined
3. Comparing the utilization of Machine A2 of Line A to that of Machine B3 of Line B,
e. A2 has the same utilization as B3
f. A2 has a lower utilization than B3
g. A2 has a higher utilization than B3
h. Cannot be determined
4. Comparing the capacity of Line B to that of Line C,
i. Line C has a higher output than Line Bs
j. Line C has a lower output than Line Bs
k. Line C has an output equal to that of Line B
l. Cannot be determined
5. Comparing the capacity of Line C to that of Line D,
m. The output of Line D is lower than line C,
n. The output of Line D

o. The output of Line D is higher than Line Cs


p. Cannot be determined

Problem 9: Rework and Scrap Assignment Questions


Imagine a three-workstation worker-paced line with task times 7, 6, and 8 minutes,
respectively. In the previous problems, a 100% yield was assumed - i.e., no defects. The
present problem will explicitly consider the impact of nonzero defect rates. In particular,
assume that the first workstation has an 8% defect rate and that the second workstation has a
12% defect rate. The third workstation, in contrast, generates no defects. For problems 1 to 4,
assume that all defective units are scraped.
Part A
1. What is the capacity of this process?
6.44 per hr
2. Where is the bottleneck?
Workstation A
3. Is the utilization of the bottleneck step 100%? If so, why? If not, why not?
No. Because of the scrap the process utilization decreases
4. What is the yield of the process (the ratio of good process)?
80.96

Part B
Now assume that the second workstation feeds its defects to a rework station that performs a
delicate and lengthy task of disassembling the product and repairing it. Thus, it requires a
relatively long time (here, 40 minutes on average) to fix defects. There is an inventory buffer
in front of this rework step to accommodate for the unlikely case that there are several defects
in a row. While time- consuming, it still is successful only 90% of the time. When rework is
successful, the rework station passes the now- good unit to the third workstation in the line. If
it is not successful, the product is scrapped.

The third workstation, receiving reworked units, now has an average task time of 9 minutes.
1. What is the capacity of this process?
6.22
2. Where is the bottleneck?
Workstation C
3. Is the utilization of the bottleneck step 100%? If so, why? If not, why not?
No. Because of the rework of the scrap material generated

4. What is the yield of the process (the ratio of good finished product to items started in
the process)?
90.896

Name of Group Members

GENERAL QUESTIONS

Refer to the discussion on the CARD GAME.


Each member to prepare 3 cards each for the game

Vous aimerez peut-être aussi