Académique Documents
Professionnel Documents
Culture Documents
Inland Design
10 Malin Road
PROFESSIONAL ENGINEERING SERVICES: Geotech/SW
10 Malin Road, West Whiteland Township
September 8, 2014
Chuck Dobson, P.E.
via Email
Bo Erixxon, Project Manager
via Email
PURPOSE
The purpose of this report is to present the Findings, Conclusions and Recommendations relative
to the physical investigation performed at the above captioned project location.
INVESTIGATION
Jason Culp, P.E. and Nick Banta were present on site Friday September 5th, 2014 to conduct a
subsurface investigation at the above mentioned project location. The investigation included
eight (8) double ring infiltrometer tests to be conducted within proposed infiltration areas. The
exact design of the stormwater facilities was not currently known as site data was required to
provide preliminary design. The findings and conclusions generated are to provide the initial
broad range characteristics for design. A final more detailed investigation of the site may be
required as the design proceeds further. In additional to information for the Stormwater related
facilities IES was also requested to record pertinent construction costs aspects of the site such as
shallow groundwater, soil suitability, rock depth etc. Testing was conducted according to the
Pennsylvania Stormwater Best Management Guidelines Appendix C: Site Evaluation and Soil
Testing Procedures. All double ring tests were presoaked for a minimum of one hour or two 30
minute intervals prior to recording measured infiltration readings.
FINDINGS
The Findings below use abbreviated nomenclature germane to soil morphology and other BMP
terminology.
Root mat
Root mat
Channery
Root mat
Channery
Root mat
Previous fill
Saprilite, very Friable CFs
Friable CFs
l/s
Previous fill
Gravels
S
Saprolite of parent formation
Friable CFs
Infiltration Testing
TP No. 1 4 4 4 4 4 4 final stabilized reading with 10 minute intervals
24.0 inches/hour Final Stabilized Reading @ 65 inches BGS
TP No. 2 3 3 3 3 3 3 3 final stabilized reading with 10 minute
intervals
21.0 inches/hour Final Stabilized Reading @ 58 inches BGS
TP No. 3 final stabilized reading with 30 minute intervals
0.25 inches/hour Final Stabilized Reading @ 70 inches BGS
TP No. 4 3/8 3/8 3/8 final stabilized reading with 30 minute intervals
0.75inches/hour Final Stabilized Reading @ 74 inches BGS
TP No. 5 1 1 final stabilized reading with 30 minute intervals
CONCLUSIONS
1. The Design Engineer is recommended to use the above information for sizing the
Proposed Stormwater Management Facilities with a slight rate reduction for
subsurface infiltration facilities to ensure the longevity of the systems given the
presence of fine grain soils and cohesive soil content.
2. The saprolite to residium strata that all tests were conducted within is highly variable
both vertically and laterally. The majority of test areas with well draining tests was
due to the near vertical bedding planes of the decomposed parent material (schist).
The rapidly draining areas of test pits 1 and 2 is composed of decomposed parent
rock, in this case Micaceous Schist to Gneiss. The material is highly decomposed
however is in a platy, vertical orientation which promotes infiltration through the
macropores of the soil/rock medium. In this area a filter layer of concrete sand will
be necessary to ensure the proper filtering of pollutants to ensure water quality
requirements are met.
3. We strongly recommends that a qualified Soil Engineer or representative thereof be
present during infiltration facility installation to ensure the stone facility-sand-soil
interface is placed at an appropriate depth to maximize recharge. Facility bottom
elevation often varies as overlying soils are not uniform thus requiring over
excavation in localized areas of the facility to maximize infiltration potential.
4. The geotextile fabric is recommended to not be utilized at the bottom of any
infiltration facility as the liner is serving too often as a hydraulically restrictive
material and creating a bath tub effect, ergo only utilize the geotextile on the
sides and top of the trench.
5. Test Pit no. 1 is the only area which exhibited somewhat shallow rock refusal. All
other test pits were excavated down to the maximum reach of the excavator. Most of
the material is fractured and decomposed and therefore rippable, especially in a
larger excavation.
10
11
12