Académique Documents
Professionnel Documents
Culture Documents
Abstract
World class ERD wells are being used in the Russian Far East
to develop an offshore reservoir from an onshore location.
These wells have reaches of 9-11 km. While drilling the initial
wells into the reservoir, high torque was experienced even
while using a nonaqueous drilling fluid (NAF). The torque
was sufficiently high that concerns arose about the feasibility
of being able to drill longer wells later in the development.
Consequently, finding techniques to reduce drilling torque
became a major focus for the drilling phase of the project.
A systematic R&D process was initiated to look for solutions
to the torque problem. The scope of the investigations
included consideration of different drilling fluid base oils,
solid/liquid lubricants, and mechanical means to reduce
torque. Small-scale screening lubricity testing was performed
in a controlled laboratory environment to identify potential
lubricant candidates. Full-size laboratory testing was then
performed on the leading products. Various mechanical means
to reduce torque were also evaluated. Finally, field trials were
performed using solid and liquid lubricants and different types
of mechanical torque-reduction tools.
Solid lubricants caused plugging problems with BHA
components and their use was discontinued. Liquid lubricants
achieved torque reductions of 5-15%, which was sufficient to
drill the longest throw wells. The mechanical tools when
added to the drill string showed the greatest reductions in
torque, but were very expensive.
Since the liquid lubricants represented a significant addition to
the cost of the wells, other means of reducing torque were
investigated. Eventually, it was discovered that the use of
4,500 m of range II drill pipe instead of range III caused a
reduction in the torque. This is believed to be related to the
Introduction
The Sakhalin-1 project will develop about 2.4 billion bbl of oil
and approximately 17 TCF of gas. For the initial phase, 15
ERD wells are planned from the land well site (Figure 1), and
an additional 18 ERD wells will be drilled from an offshore
location1, as shown in Figure 2. These wells will be used to
develop the Chayvo field reservoirs.
The well design for the land-based wells, shown in Figure 3,
has the following features:
Very shallow KOP at app. 200 m
18-5/8-in. surface casing at 800 m
13-5/8-in. intermediate casing at 3300 m
4,500-6,300 m long tangent section at a 76-81 deg
sail angle
9-5/8-in. production casing run to the top of the
pay at 7,800-9,600 m MD
A 1,300-3,200 m long horizontal section cased
with a 6 5/8 in. or 7-in. liner
The horizontal section crosses multiple hydrocarbon intervals
before reaching total depth (TD) from 9,100 - 11,134 m. The
wells are drilled with rotary steerable systems (RSS) from the
17-1/2-in. hole down to TD. These tools contribute
significantly to the success of the wells. They enable a smooth
borehole to be drilled along the planned directional path. On
the eight wells drilled to date, all of the 13-5/8-in. and 9-5/8in. casings and the 7-in. liners have reached their target depth
IADC/SPE 98969
IADC/SPE 98969
Lubricant Testing
There are two categories of drilling fluid additives (lubricants)
that may reduce the CoF: solids and chemicals. Solids act like
ball or roller bearings in the mud to keep the metal-to-metal or
metal-to-rock interface from occurring. The end result is a
metal-to-solid or rock-to-solid contact thus reducing the CoF.
Chemical lubricants are believed to adhere to or modify the
surface of the metal and/or borehole thus reducing the CoF.
Testing Procedures. In testing lubricants, one of the most
important factors is using consistent test procedures and
consistent drilling fluid. During the initial testing, it was
found that the results were significantly effected if the
procedures were not followed exactly (mixing time, order of
addition, letting the mud cool down before testing, etc.). This
led to the writing of detailed testing procedures (including
duplicate testing) and lab technician signoff to ensure accurate
and consistent data.
The drilling fluid was built in the same laboratory using the
same procedures to ensure a consistent lab-prepared drilling
fluid.
Testing Fluids. A 55-gallon drum of drilling fluid from a
recent Sakhalin well was shipped to Houston for lubricity
testing, as this is a more representative sample of fluid than a
lab-prepared sample. Due to the limited volume, only the
small scale testing was performed using the field drilling fluid.
Lab-prepared muds were used for the large scale testing
(described later).
Screening Process. There are several laboratory lubricity
measuring devices on the market; most of them measure
metal-to-metal interfaces. The performed testing focused on
metal-to-metal testing as more than 75% of the hole is cased
while drilling the 8--in. hole section where the highest
torque values are seen. After evaluating six lubricity devices,
three were chosen for the planned work. These were a Baroid
lubricity meter (Figure 4), a special lubricity tester built by
MI/Westport (Figure 5), and a Falex lubricity meter located at
Southwest Research Institute (SWRI) (Figure 6).
IADC/SPE 98969
reduce the CoF in the field. The testing showed that each of
the devices had its own range of CoFs and % improvement.
In general, the laboratory lubricant testing indicated that,
under ideal conditions, certain lubricants added to the NAF
could reduce the CoF by up to 50%.
1.
2.
3.
4.
5.
6.
Based on this testing (plus logistical and other considerations), it was decided to stay with the current NAF
system. However, the best performing lubricants were taken to
the next step: full-scale testing.
Full-Scale Testing. Final testing was performed on a fullscale test device (Figure 9). Modifications to an existing
device that had been used to measure riser wear due to tool
joint rotation were made. These modifications included
enabling the interface between a fullsize 5-7/8- in. tool joint
(7-in. OD) and a piece of Chayvo 9-5/8-in. casing to be
submerged in a circulating NAF at an elevated temperature.
This device rotates a tool joint at ~150 RPM, applies a side
load up to 3,200 lb/ft to the 9-5/8-in. casing as it is pressed
against the tool joint, and measures the torque imparted to the
casing using a load cell (Figure 10).
The device is configured with mud mixers and a circulation
pump so that after a baseline torque is measured, a lubricant
can be added to the drilling fluid on-the-fly so that the effect
of the lubricant can be measured without any other changes to
the test setup. Testing was done using a NAF designed to be
similar to that being used at Chayvo including incorporation of
appropriately-sized sand particles. All testing was done at the
Chayvo downhole circulating temperature of ~150 F. The
large-scale testing was used as a final verification of the
lubricants to be used in the field. Figure 11 shows typical test
results from the modified large-scale apparatus.
Lubricant Testing Results. Recognizing the differences in the
design of the test equipment, the goal of the lubricity testing
was to obtain similar trends in the results of all the lubricity
testing devices to help ensure that a selected lubricant would
Limited testing of drill beads was also conducted on the largescale testing device. The results indicate that beads can reduce
the coefficient of friction. However, due to operational
constraints, drill beads have not been used in Chayvo field
operations.
Mechanical Tool Evaluation
Drill String Subs. Mechanical torque reduction subs have
been successfully used in other ERD projects4-8. The limited
use of mechanical torque reduction devices in the Z-4 well had
also proven the concept, but the test showed that the tool used
was not robust enough to withstand the requirements of the
Chayvo downhole conditions. A quick survey of the current
market indicated several additional designs were available for
5-7/8-in. drill pipe. These tools have an inner mandrel and
outer sleeve and are designed as an integral part of the drill
string.
The tools were evaluated for their robustness and the inherent
risk of loosing parts in the hole. Out of this pre-screening, one
tool was eventually selected for further studies. A study was
conducted with the scope to estimate the margin of safety of
the sub under static design loading conditions using finite
element analysis (FEA). Not included in the study were cyclic
(fatigue) or dynamic loading conditions and effects of wear.
During the study, FEA models were developed for the
mandrel and the sleeve, and a mechanical analysis was
performed for the locking collar and pins to estimate shear,
crush and breakthrough limits. The general conclusion was
that the structural performance of all parts exceeded the
capacity required for expected levels of tension, torque,
bending, side- and drag loads. Consequently, a
recommendation to build 200 tools for a pilot test at Chayvo
was made.
Field Testing of Lubricants and Tools
While drilling the two longest wells of the Chayvo drilling
campaign:
- Chayvo Z-1 with a TD of 10,995 m, and
- Chayvo Z-2 with a TD of 11,134 m,
IADC/SPE 98969
IADC/SPE 98969
Conclusions
At the time of this writing, eight Chayvo ERD wells have been
successfully drilled into the reservoir. After the initial pilot
wells, six 8-1/2-in. hole sections were drilled using liquid
lubricants or integral torque-reduction subs. All products used
were the result of a focused research effort to reduce the CoF
in a NAF. The following findings and conclusions can be
drawn from the laboratory results and the field testing:
2.
3.
4.
5.
6.
7.
8.
Next Steps
The remaining wells to be drilled from the Chayvo land pad
are similar in measured depth and horizontal displacement to
the wells already drilled. The authors believe that the existing
lubricants and available tools will enable all of the currently
planned wells to be drilled to TD. Better protection of the drill
pipe will be necessary to reduce both costly hardbanding
requirements and drill pipe replacement. This will hopefully
come with the added benefit of a CoF reduction.
Future ERD wells with up to 11-15 km reach are currently
under consideration. To accomplish this world-record reach,
the following drilling technologies may need to be applied:
x 3.048*
x 2.54*
x 4.448 222
x 6.894 757
E-01=m
E+00=cm
E+00=N
E+00=kPa
IADC/SPE 98969
OPF
Chayvo Top View
Chayvo
Bay
Co
ast
lin
e
Onshore
Yastreb
Drillpad
Offshore
Orlan Platform
Location
-2000
30 @ 90m
18 5/8 @ 800m
2000
TVD (m)
1000
13 5/8 @ 3300m
9 5/8 @ 7800-9,600mm
3000
7 @ 9375-10,900m
1000
2000
3000
4000
5000
6000
7000
8000
9000
IADC/SPE 98969
Bellows
Seal
0.160
0.140
Field Mud
Ester
Diesel
Ester
Internal Olefin
Reciprocate
Casing
Coefficient of Friction
0.120
0.100
Tool
Joint
0.080
158 RPM
0.060
0.040
200
400
600
150F
NAF
Measure
Torque
Casing
800
Impart
Side Load
0.130
0.120
Lubricity Test
3500
0.100
175
150
3000
Machine Settings:
- Escaid 110 (20 gal)
- 9-5/8" Mill Casing
- 7" Bare Tool Joint
- Axial Reciprocation
- 158 RPM
- 0-12% Lubricant K
- 2% Sand
2500
0.080
0.070
0.060
0.050
2000
1500
0.040
0
200
400
600
800
1000
0% Lubricant
Baseline
1000
1200
125
Temperature (F)
Side Load (lb/ft)
Torque (ft-lb)
100
75
3% Lubricant
-18% Torque
6% Lubricant
-51% Torque
9% Lubricant
-51% Torque
12% Lubricant
-51% Torque
50
0.090
500
25
0
0
60
120
180
0
300
240
60,000
n
Z-2
Added into NAF :
6% lubricant K
55,000
8
Z-3
Added into NAF :
16% Lubricant H
50,000
1
Z-6
Torque (ft-lbs)
Coefficient of Friction
0.110
Glycerol
Gilsonite
Miscellaneous
Glycerol
Micro Emulsion 2
Sulfurized fatty acid
Micro Emulsion 1
Organic Polymer
Ester
Vegetable Oil / surfactant
45,000
3
40,000
Tool Joint
Casing
35,000
30,000
7,500
8,000
8,500
ZG-2
Z-4
7
Z-5
Z-1
9,000
ZG-1
66
9,500
10,000
10,500
Depth (m MD)
11,000
11,500
IADC/SPE 98969
Cumulative Dogleg
0
40
ZD-1
Z-4
1,000
Z-6
Z-1
35
Z-2
2,000
30
ZG-1
ZG-2
ZD-1
Torque (ft-lb)
Z-5
Z-7
3,000
Z-23
Z-3
4,000
25
20
15
Bare TJ, No Sand
Mid-Joint Upset, No Sand
5,000
Depth [m, MD]
10
6,000
0
7,000
10
20
30
40
50
Minutes
8,000
9,000
Z-5
Z-6
10,000
Z-3
Z-4
ZG-2
11,000
ZG-1
Z-1
Z-2
12,000
0
50
100
150
200
250
300
60